W e e k l y R e p o r t : 2 / 1 5 / 1 0 - 2 / 1 9 / 1 0 Electrical Panel 4th Floor Sprinkler Piping North View of HQ South Side View of HQEyebrowSteel Exterior Sheathing at PenthouseTRANSCRIPT
• MEP rough-in above ceiling on the first floor is complete.
• Started insulating pipe above ceiling on the first floor.
• Continue to frame exterior walls on the south elevation of the HQ.
• Installation of Fan Power Boxes began this week.
• Framing partitions throughout the HQ.
• Hanging lintel angle on the south elevation is ongoing.
• Start hanging the steel for the eyebrow at the HQ.
• Began installing piping at the high roof in the VC.
• Framing of interior partitions to deck on the 3rd floor is complete.
• Installed tiebacks on the VC roof.
• Installed roof blocking at the parapet.
Texas A&M University Agriculture Headquarters
Week ly Repo r t : 2 / 1 5 / 10 - 2 / 19 / 10
Electrical Panel 4th Floor Sprinkler Piping
North View of HQ South Side View of HQ Eyebrow Steel
Exterior Sheathing at Penthouse