MEP rough-in above ceiling on the first floor is complete. Started insulating pipe above ceiling on the first floor. Continue to frame exterior walls on the south elevation of the HQ. Installation of Fan Power Boxes began this week. Framing partitions throughout the HQ. Hanging lintel angle on the south elevation is ongoing. Start hanging the steel for the eyebrow at the HQ. Began installing piping at the high roof in the VC. Framing of interior partitions to deck on the 3rd floor is complete. Installed tiebacks on the VC roof. Installed roof blocking at the parapet. Texas A&M University Agriculture Headquarters Weekly Report: 2/15/10-2/19/10 Electrical Panel 4th Floor Sprinkler Piping North View of HQ South Side View of HQ Eyebrow Steel Exterior Sheathing at Penthouse

Upload: texas-am-agrilife

Post on 10-Mar-2016

212 views

Category:

Documents


0 download

DESCRIPTION

W e e k l y R e p o r t : 2 / 1 5 / 1 0 - 2 / 1 9 / 1 0 Electrical Panel 4th Floor Sprinkler Piping North View of HQ South Side View of HQEyebrowSteel Exterior Sheathing at Penthouse

TRANSCRIPT

• MEP rough-in above ceiling on the first floor is complete.

• Started insulating pipe above ceiling on the first floor.

• Continue to frame exterior walls on the south elevation of the HQ.

• Installation of Fan Power Boxes began this week.

• Framing partitions throughout the HQ.

• Hanging lintel angle on the south elevation is ongoing.

• Start hanging the steel for the eyebrow at the HQ.

• Began installing piping at the high roof in the VC.

• Framing of interior partitions to deck on the 3rd floor is complete.

• Installed tiebacks on the VC roof.

• Installed roof blocking at the parapet.

Texas A&M University Agriculture Headquarters

Week ly Repo r t : 2 / 1 5 / 10 - 2 / 19 / 10

Electrical Panel 4th Floor Sprinkler Piping

North View of HQ South Side View of HQ Eyebrow Steel

Exterior Sheathing at Penthouse