2010-06-11
DESCRIPTION
W e e k l y R e p o r t : 6 / 7 1 0 - 6 / 11 / 1 0 Main Entrance at HQ Gates & Louvers for Service Yard North View of HQ Vanity SupportsMEPRough-IninExhibitArea Scaffold at VC Exterior ColumnsTRANSCRIPT
• Completed MEP above ceiling rough-in on the east side of the 5th floor.
• Tying in outside duct to the ERU’s.
• Installation of stone at the main entrance to the HQ is 95% complete.
• MEP rough-in in the exhibit areas of the VC is ongoing.
• Started the installation of the standing seam roof at the eyebrow.
• Caulking windows and installing trim caps on the southeast side of the HQ is 100% complete.
• Continue to fire caulk the expansion joints on 1st thru 5th floors at the HQ.
• Currently framing toilet room ceiling on the 1st floor.
• Framing and sheathing exterior walls at the VC is 100% complete.
• Continue to one side walls on the 3rd, 4th, and 5th floors of the HQ and frame interior partitions in the VC.
Texas A&M University Agriculture Headquarters
We e k l y R e p o r t : 6 / 7 1 0 - 6 / 11 / 1 0
Main Entrance at HQ Gates & Louvers for Service Yard
North View of HQ Vanity Supports MEP Rough-In in Exhibit Area
Scaffold at VC Exterior Columns