20100514 pipe arch presentation to iem may 2010

64
MMC-Gamuda Joint Venture Electrified Double Track Project Ipoh to Padang Besar PIPE ARCH TUNNEL by Mr. Don R. Hall Head of Tunneling Division, Gamuda Engineering Sdn Bhd May 2010 Presentation to Institution of Engineers, Malaysia

Upload: forcepraxeum

Post on 15-Nov-2014

3.036 views

Category:

Education


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Electrified Double Track Project Ipoh to Padang Besar

PIPE ARCH TUNNELby

Mr. Don R. Hall

Head of Tunneling Division, Gamuda Engineering Sdn Bhd

May 2010

Presentation to Institution of Engineers, Malaysia

Page 2: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Outline of Presentation:

1) General Project Information – Berapit Tunnel

2) Pipe Arch Tunnel – Geological Profile & Concept

3) Pipe Arch Tunnel – Chronology of Construction

4) Construction of Triple Cell 3m Ф Drainage Culvert

5) Demolition of Existing 3m x 3m Twin Box Drainage Culvert

6) Pipe Arch Tunnel Construction

7) Catastrophe

8) Summary and Q&A

Page 3: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

General Project Information – Berapit Tunnel

Page 4: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

General Project Information – Berapit Tunnel

CHARACTERISTICS Twin bore tunnels

LENGTH OF TUNNEL 2900m

GRADIENT IN TUNNEL 0.39%

OVERBURDEN Ave. 110m, Max. 220m

EXCAVATION SECTION AREA 50-60 m2

CROSS PASSAGE 9 nos.

GEOLOGY Granites of different weathering & fracturing degrees

TRAIN SPEED POTENTIALDesign speed for passenger train : 180 km/hOperating speed for passenger train : 140 km/hOperating speed for freight train : 90 km/h

CONSTRUCTION METHODS Mainly 80% drill & blast, 20% as cut & cover tunnel

Page 5: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

• Tunnel Length = Approximately 2900m• Twin Tunnels, Single track each• Track Structure : Slab Track

North-South Expressway (NSE)

Existing Railway Track

To IpohTo Taiping

YTLCEMENTPLANT

Pipe Arch Tunnel Crossing NSE

General Project Information – Berapit Tunnel

Page 6: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

PA

DA

NG

RE

NG

AS

EN

D P

OR

TA

L

- E

ND

CH

11

00

60

TA

IPIN

G E

ND

PO

RT

AL

- S

TA

RT

CH

10

71

70

EXISTING NORTHSOUTH HIGHWAY TO

BE MAINTAINED

EXISTINGRAILWAY TRACK

EXISTING FEDERAL ROUTE 1 / NORTH SOUTH HIGHWAY

TO BE MAINTAINED

22

0m

Gradient 0.39%

Federal Route 1 temporarily diverted for tunnel construction

Pipe Arch Tunnel Crossing

North-South Expressway (approx. 4m overburden only)

General Project Information – Berapit Tunnel

Drill & BlastSection

Pipe ArchSection

Cut & Cover Section

Page 7: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Typical Berapit Tunnel Cross Section:

General Project Information – Berapit Tunnel

Page 8: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture8

General Project Information – Berapit Tunnel

Page 9: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

CROSS PASSAGES EVERY 350m

General Project Information – Berapit Tunnel

Page 10: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel – Chronology of Construction

Page 11: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Northbound

Southbound

Northbound railway tunnel

Southbound railway tunnel

Pipe Arch Tunnel – Chronology of Construction

3. Twin pipe arch tunnel crossing underneath PLUS North-South Highway

KM 232.7

1. Triple 3m Ф cell drainage culvert at KM 232.6 of PLUS North-South

Highway to replace existing 3m x3m twin box culvert

2. Existing 3m x 3m twin box drainage

culvert to be demolished & replaced

Plan Layout of Twin Pipe Arch Tunnel

Page 12: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture12

3-D View of Twin Pipe Arch Tunnel

Northbound

Southbound

2. Existing 3m x 3m twin box drainage

culvert to be demolished & replaced

1. Triple 3m Ф cell drainage culvert at KM 232.6 of PLUS North-South

Highway to replace existing 3m x3m twin box culvert

3. Twin pipe arch tunnel crossing underneath PLUS North-South Highway

KM 232.7

Pipe Arch Tunnel – Chronology of Construction

Page 13: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Construction Of Triple Cell

Page 14: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

LONG-SECTION OF DRAINAGE CULVERT

IL 76.025

39

96

IL 75.812

RL 83.421 RL 82.808

3000m

m EXISTING GROUND LEVEL

NORTH SOUTH EXPRESSWAY

PROPOSED DRAINAGE CULVERT(LENGTH = 45.50m)

IL 76.130 IL 75.676

Jacking Length = 45.5m

4000

3000

IL IL

PLUS HIGHWAYSHOULDER LEVELEDGE OF

PROPOSED TRIPLE 3000mm Ø

1500 1500

RCP DRAINAGE CULVERT

PROPOSED TRIPLE 3.0m RCP DRAINAGE CULVERT

13800

10200

LONGITUDINAL SECTION

CROSS SECTION

Construction of Triple Cell 3m Ф Drainage Culvert

Page 15: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Construction of Triple 3m Ф Cell with Soft Ground Cutterhead Microtunneling Machine

First drive of jacking works of 3m Ф concrete pipes ongoing. Second & third drives awaiting for jacking with prepared entrance rings

Construction of Triple Cell 3m Ф Drainage Culvert

Page 16: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Jacking works ongoing

Construction of Triple Cell 3m Ф Drainage Culvert

Construction of Triple 3m Ф Cell with Soft Ground Cutterhead Microtunneling Machine

Page 17: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Breaktrough of the first drive

Construction of Triple Cell 3m Ф Drainage Culvert

Construction of Triple 3m Ф Cell with Soft Ground Cutterhead Microtunneling Machine

Page 18: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Lifting of microtunneling machine after breakthough of first drive

Construction of Triple Cell 3m Ф Drainage Culvert

Construction of Triple 3m Ф Cell with Soft Ground Cutterhead Microtunneling Machine

Page 19: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Close up of RASA microtunneling machine

Construction of Triple Cell 3m Ф Drainage Culvert

Construction of Triple 3m Ф Cell with Soft Ground Cutterhead Microtunneling Machine

Page 20: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Completed construction of triple cell drainage culverts

Construction of Triple Cell 3m Ф Drainage Culvert

Construction of Triple 3m Ф Cell with Soft Ground Cutterhead Microtunneling Machine

Page 21: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Demolition of Existing 3m x 3m Twin Box Drainage Culvert

Page 22: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Demolition of Existing 3m x 3m Twin Box Drainage Culvert

PLAN VIEW

CROSS SECTION VIEW

Page 23: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Existing twin box culvert at KM 232.7 PLUS North-South Expressway before demolition

Demolition of Existing 3m x 3m Twin Box Drainage Culvert

Demolition of Existing 3m x 3m Twin Box Culvert for Pipe Arch Tunnel Construction

Page 24: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Demolition by coring & hacking to rid of reinforcement within existing twin box culvert for pipe arch tunnel construction

Demolition of Existing 3m x 3m Twin Box Drainage Culvert

Demolition of Existing 3m x 3m Twin Box Culvert for Pipe Arch Tunnel Construction

Page 25: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Demolition by coring & hacking to rid of reinforcement within existing twin box culvert for pipe arch tunnel construction

Demolition of Existing 3m x 3m Twin Box Drainage Culvert

Demolition of Existing 3m x 3m Twin Box Culvert for Pipe Arch Tunnel Construction

Page 26: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Sealing of existing twin box culvert for pipe arch tunnel construction

Demolition of Existing 3m x 3m Twin Box Drainage Culvert

2. Demolition of Existing 3m x 3m Twin Box Culvert for Pipe Arch Tunnel Construction

Page 27: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Page 28: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel– Concept

Page 29: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel – Concept

Mined excavation

Page 30: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Construction Sequence 1. Execution of sheet piles 2. Execution of the pipe arch microtunneling 3. Mined excavation of tunnel with steel ribs with bullflex, reinforced shotcrete & fibre glass elements 4. Casting of permanent concrete lining

Pipe Arch Tunnel – Concept

Site picture of project by Metropolitan Atlanta Rapid Transit Authority in USA

Page 31: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

LONGITUDINAL SECTION

CROSS SECTION

Page 32: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Limits of PLUS North-South Expressway (NSE)

Cut &Cover

Section

JackingPit Top of Soil Support Pipes

Southbound NSE

Residual Soil

Northbound NSE

ReceivingPit

Fill

Weathered Rock

Scale in Meters

0 5 10

RockBottomof Structure

Fill

Cut &CoverSection

0

5

10

15

20

Direction ofMicrotunneling

Pipe Arch Tunnel Construction

Jacking Length up to Toe of Highway Embankment= 90 m

Page 33: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Limits of PLUS North-South Expressway (NSE)

Cut &Cover

Section

JackingPit Top of Soil Support Pipes

Southbound NSENorthbound NSE

ReceivingPit

Fill

Weathered Rock

Scale in Meters

0 5 10

RockBottom

of Structure

Fill

Cut &CoverSection

0

5

10

15

20

Direction of MicrotunnelingResidual Soil

Pipe Arch Tunnel Construction (Right Bore)

Jacking Length up to Toe of Highway Embankment= 92 m

Page 34: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Cardox System – Non-explosive blasting

Page 35: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Cardox Blasting

Cardox Drilling & Connection

Cardox Gas Filling

Pipe Arch Tunnel Construction

Page 36: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Mini Pipe Arch

Page 37: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

AVN500

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Microtunneling machine with retraction mechanism in case of rock face encountered

Page 38: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

780m

m O

D

Jacking

Direction

Pre-welded Line-up Band

10mm Pipe Wall Thickness

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Pipe joint detail

Page 39: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Construction & staged excavation of bored pile jacking pit

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 40: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Coring of reinforcement of shotcreted bored pile wall to prepare soft eye for microtunneling machine advance

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 41: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Construction of thrust wall for jacking of microtunneling machine

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 42: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Microtunneling machine preparing to jack

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 43: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 44: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Jacking of microtunneling machine ongoing

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 45: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Welding Of Pipe

Pipe Arch Tunnel Construction

Page 46: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 47: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 48: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Pipe Arch Tunnel Construction

Page 49: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Catastrophe

Page 50: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Page 51: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Page 52: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Page 53: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Catastrophe

Pipe Arch Tunnel Construction

Set up to pull back pipe

Page 54: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Catastrophe

Locking device

Pipe Arch Tunnel Construction

Page 55: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

First pipe retreated

Page 56: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Damaged section

Page 57: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Damaged section exposed

Page 58: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Page 59: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Existing drive pressurized

Page 60: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Damaged pipe on surface

Page 61: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Damaged pipe on surface

Page 62: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Pipe Arch Tunnel Construction

Catastrophe

Rebar excavated under Plus Highway

Page 63: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

THANK YOU

Page 64: 20100514 pipe arch presentation to iem   may 2010

MMC-Gamuda Joint Venture

Q & A Session