Diaphragm Walls - Design and Construction

Diaphragm Wall- Principles and Applications- Le Havre Port 2000- The Sail

AGS-ATS Perth Aug 2010

D-Wall : retaining, cut off, foundation

AGS-ATS Perth Aug 2010

Diaphragm Wall – construction principles

AGS-ATS Perth Aug 2010

Diaphragm Wall – construction principles

AGS-ATS Perth Aug 2010

Diaphragm Wall – construction principles

AGS-ATS Perth Aug 2010

Diaphragm Wall – construction principles

AGS-ATS Perth Aug 2010

Diaphragm Wall – Equipment

AGS-ATS Perth Aug 2010

Diaphragm Wall – Equipment

AGS-ATS Perth Aug 2010

Diaphragm Wall – Equipment

AGS-ATS Perth Aug 2010

Diaphragm Wall – Equipment

AGS-ATS Perth Aug 2010

Application: retaining structure

AGS-ATS Perth Aug 2010

Application : TBM shaft, metro station,..

AGS-ATS Perth Aug 2010

Application : cut & cover tunnel, ramp,..

AGS-ATS Perth Aug 2010

Application : cut off

AGS-ATS Perth Aug 2010

Application : UG tanks, water station,..

AGS-ATS Perth Aug 2010

Application : car park, basement,..

AGS-ATS Perth Aug 2010

Diaphragm wall – indicative figures

Geometry Widths : 0.5 to 1.5mDepths : 25 to 45 m are common (max 150 m)Verticality: 1% is common

Material Tremie mix concrete, 20 mm slump Steel: 70 to 200 kg/m3

PropertiesMoments: 1200 kN/m for 0,8 m wall; 4 000 kN.m for 1,5 m wallPermeability: 10 E-7 m/s to 10 E-9 m/s

AGS-ATS Perth Aug 2010

PORT AUTONOME DU HAVRE

TheThe site on site on 10/09/200110/09/2001

Le Havre : Design

AGS-ATS Perth Aug 2010

Plan View

Le Havre : Design

AGS-ATS Perth Aug 2010

A reinforced concrete

front wall.

Sheet piled as rear wall

Tie – rods between the

walls.

Capping beam with bollards and

fenders

Le Havre : Design

AGS-ATS Perth Aug 2010

Le Havre : Design

Quay : 1600 lm Diaphragm Wall

42 m deep, 1,2 m wide, 150 kg/m3

67 000 m2, 80 000 m3 concrete, 12 000 t steel

Dewatering 180 wells, 1900 m3/dyAnchors 5,600TSheet Piles 1,000TDredging 11,000,000 m3Earthworks 3,000,000 m3Civil Works 30,000 m3Bored piles 500 nr, 17ml, 520 mm

AGS-ATS Perth Aug 2010

PHASE 1Preparation of working platform

Construction of Guide WallsInstallation of Well Points

Le Havre: phase 1

AGS-ATS Perth Aug 2010

Le Havre: phase 1

AGS-ATS Perth Aug 2010

PHASE 2Construction of Diaphragm Walls

Le Havre: phase 2

AGS-ATS Perth Aug 2010

Le Havre: phase 1

AGS-ATS Perth Aug 2010

AGS-ATS Perth Aug 2010

Le Havre:

AGS-ATS Perth Aug 2010

PHASE 3Removal of the guide walls

Excavation in front of the wall during dewatering

Le Havre: phase 3

AGS-ATS Perth Aug 2010

Le Havre: phase 3

AGS-ATS Perth Aug 2010

PHASE 4Cast capping beam and dock buffers

Le Havre: phase 4

AGS-ATS Perth Aug 2010

Le Havre: phase 4

AGS-ATS Perth Aug 2010

PHASE 5Earthwork excavation behind wall during

dewatering

Le Havre: phase 5

AGS-ATS Perth Aug 2010

Le Havre: phase 5

AGS-ATS Perth Aug 2010

PHASE 6Installation of sheet pile curtain

Lay lower layer of anchors

Le Havre: phase 6

AGS-ATS Perth Aug 2010

Le Havre: phase 6

AGS-ATS Perth Aug 2010

Le Havre: phase 6

AGS-ATS Perth Aug 2010

PHASE 6Backfill to level upper anchor layer and

lay upper layer of anchors

Le Havre: phase 6

AGS-ATS Perth Aug 2010

Le Havre: phase 6

AGS-ATS Perth Aug 2010

Sheet pilesSheet piles

DWall 1,20 mDWall 1,20 m

FF -7.50 Tie backsTie backs

Sea side

Land side

Le Havre: phase 6

AGS-ATS Perth Aug 2010

PHASE 6Backfill to formation level, construct all civil

works, install bumpers, stop dewatering, dredging, crane rail foundations and rails.

Le Havre: phase 6

AGS-ATS Perth Aug 2010

Le Havre: phase 6

AGS-ATS Perth Aug 2010

Le Havre: phase 6

AGS-ATS Perth Aug 2010

Le Havre: phase 6

AGS-ATS Perth Aug 2010

Le Havre: Now

AGS-ATS Perth Aug 2010

Now in Cotonou

AGS-ATS Perth Aug 2010

Now in Cotonou

AGS-ATS Perth Aug 2010

The Sail @ Marina bay

Owner: City Dvpt /American

International

Engineer: Meinhardt

Main Contractor: Dragages

AGS-ATS Perth Aug 2010

9,090.9 sqmSite Area

118,182 sqmPermissible GFA

No of floors: 70Typical Floor GFA: 1,026 sqmHeight: 242m

Tower 1

No of floors: 63Typical Floor GFA: 746 sqmHeight: 202m

Tower 2

No of floors: 7Typical Floor Plate: 3,726 sqm

Podium

The Sail@ Marina Bay

AGS-ATS Perth Aug 2010

Site Condition (1995)

The Sail@ Marina Bay

AGS-ATS Perth Aug 2010

BH-5BH-5BH-5

Tower 2

Tower 1Expected Fort Canning

Boulder Bed

Existing Buried Pier

8m Canal

CST

The Sail: IssuesSite specificities• Thick marine clay (up to 35m

of Kallang formation = very soft to soft)

• Fort Canning Boulder Bed• UG obstacle = old pier below

the tower• MTR running tunnel & CS

excavation along the siteProject issues• To control movement of

MRT tunnels & CS Tunnel is a REAL must

• Very tight program = 6 months for foundations + excavation

AGS-ATS Perth Aug 2010

The Sail : Design Philosophy

Alternative solution by SB : Circular structure design• naturally self stabilising and VERY rigid • excavation possible with no jet grouting and no struting+ staggered equipments working units

safe solution in term of deflection/displacement as well as program

AGS-ATS Perth Aug 2010

The Sail: Design

AGS-ATS Perth Aug 2010

The Sail : Design 3D Finite Elements Design

• Predicted wall deflection is about 15mm• Basal heave FoS ~2.21• Movement of barrettes due to basal heave ~ 7mm• Distribution of forces in the Y panel considered

• Dissymmetrical loading due to soil variation considered• Dissymmetrical loading due GWT variation considered• Maximum differential excavation of about 0.5m allowed

AGS-ATS Perth Aug 2010

The Sail : Foundation PlanTemporaryRetentionSystem

T1

3rd

MRT R

eser

ved

Line

TemporaryD-W all

Perimeter • 3 symmetrical 32.2m diam circular Dwalls, • 29 m deep, 220 ml long• 800 mm thick• with cross walls.

Barettes • 79 Nos. of 1,2 x 2,8• up to 67 m deep, incl 20 m in SPT>100• all toes grouted ;

AGS-ATS Perth Aug 2010

The Sail: Works

AGS-ATS Perth Aug 2010

The Sail: Works

AGS-ATS Perth Aug 2010

Ultimate Load test

• 1 ultimate load test with smaller barrette 600 x 2400 @ 2.5 WL carried out – 2700 TONS

• 2 working barrette tests on 1000 x 2800 barrette carried out with settlement <15mm @ 1.5 WL –max 3660 TONS

• All the tests were done using kentledge method

AGS-ATS Perth Aug 2010

The Sail: Today

AGS-ATS Perth Aug 2010

Isle of Grain

AGS-ATS Perth Aug 2010

Conclusion

Le Havre Port 2000Site opportunity : shallow waterIssue : optimisation (phasage/dewatering/quantities/..)

The SailProject constraint: tight program, neighb. structuresIssue : design, execution