2011-06-13 site plan report...summerhaven site plan report june, 2011 report no. 10-1151-0035 1 1.0...

12
June, 2011 NEXTERA ENERGY CANADA, ULC SUMMERHAVEN WIND ENERGY CENTRE APPLICATION FOR A RENEWABLE ENERGY APPROVAL Site Plan Report REPORT Report Number: 10-1151-0035 Distribution: Ministry of Environment - 3 copies NextEra Energy Canada, ULC - 3 copies Air Energy TCI Inc. - 2 copies Golder Associates Ltd. - 2 copies Submitted to: Director, Ministry of Environment 2 St. Clair West, Floor 12A Toronto, Ontario M4V 1L5

Upload: others

Post on 10-Mar-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

June, 2011

NEXTERA ENERGY CANADA, ULC SUMMERHAVEN WIND ENERGY CENTRE APPLICATION FOR A RENEWABLE ENERGY APPROVAL

Site Plan Report

REP

OR

T

Report Number: 10-1151-0035

Distribution:

Ministry of Environment - 3 copies

NextEra Energy Canada, ULC - 3 copies

Air Energy TCI Inc. - 2 copies

Golder Associates Ltd. - 2 copies

Submitted to: Director, Ministry of Environment 2 St. Clair West, Floor 12A Toronto, Ontario M4V 1L5

Page 2: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035 i

Table of Contents

1.0  INTRODUCTION ............................................................................................................................................................... 1 

2.0  PROJECT LOCATION...................................................................................................................................................... 2 

3.0  REFERENCES .................................................................................................................................................................. 6 

TABLES

Table 1: Design and Operations Report requirements under O. Reg. 359/09 ............................................................................ 1 

Table 2: Modifications to the Project Design Relative to the Draft REA Reports ........................................................................ 3 

FIGURES

Figure 1 Site Plan 

Page 3: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035 1

1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report) has been prepared to provide

information to the public, Aboriginal communities, municipalities and local authorities regarding the proposed

Summerhaven Wind Energy Centre (the Project). The Site Plan is a required component of an Application for a

Renewable Energy Approval (REA Application) under Ontario Regulation (O. Reg.) 359/091 made under the

Environmental Protection Act (EPA).

This Site Plan has been prepared to address the requirement for providing a Site Plan as identified in O. Reg.

359/09 and Technical Bulletin Two: Guidance for preparing the Design and Operations Report (MOE, 2010).

Table 1 summarizes information to be included in the Report based on Table 1 of O. Reg. 359/09 and directs

readers to the associated section(s) of this document.

Table 1: Design and Operations Report requirements under O. Reg. 359/09

Requirement as per O. Reg. 359/09 Report section where information can be found

The proposed Site Plan Figure 1

Additional information about the Project can be found in the Construction Plan Report (Golder, 2011a), Design

and Operations Report (Golder, 2011b), Decommissioning Plan Report (Golder, 2011c), and Project Description

Report (Golder, 2011d). A description of the Site Plan design is provided in the Design and Operations Report.

As it is broadly applicable to all of the REA Reports, and to avoid redundancy, the Site Plan diagram has been

provided as a stand-alone document (this Report).

Technical studies associated with the REA Application requirements were initiated in 2007 and extended into

2010. Additional information about the Project and results of technical studies and assessments of negative

environmental effects are available in the following reports:

Wind Turbine Specifications Report (Golder, 2011e);

Natural Heritage Assessment Report (Golder, 2011f);

Stage 1 Archaeological Assessment Report (Golder, 2010a);

Heritage Assessment Report (Golder, 2011j);

Noise Study Report (Golder, 2011g);

Water Assessment Report (Golder, 2011h);

Site Plan Report (this Report); and

Consultation Report (Golder, 2011i).

Stage 2, Stage 3 and Stage 4 Archaeological Assessment Reports are not required as part of the REA

Application for this Project (Ministry of Energy and Infrastructure, 2010) and are typically not publically available

documents due to the confidential nature of the content. Stage 2, Stage 3 and Stage 4 Archaeological

1 As amended by O. Reg. 521/10 which came into force on January 1, 2011.

Page 4: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035 2

Assessment Reports will however be made available to the Ministry of Tourism and Culture (MTC) for review

and their issuance of a Comment Letter in advance of construction and hard copies of this information will be

provided to Aboriginal communities with an interest in the Project, as identified by the Director, and as agreed to

by individual Aboriginal communities.

The Project, as depicted on the Site Plan, consists of the site preparation, construction, operation, and

decommissioning of a 59 turbine wind generating facility with a total installed nameplate capacity of 131.04 MW.

The Project will be owned and operated by NextEra Energy Canada, ULC (NextEra Energy Canada) and will be

located in the vicinity of Nanticoke, Haldimand County, Ontario. The Project lifespan from obtaining the REA

Approval to the end of Decommissioning is estimated to be 27 years.

2.0 PROJECT LOCATION This section provides details on the proposed Project Location and the collective Project design including a

summary of changes relative to October and December 2010 draft Project designs (Golder, 2010c, 2010d). A

summary of design modifications and rationale for these changes are provided in Table 2. Design modifications,

including the selection of the substation and transmission line option, were based on the consideration of many

factors including, but not limited to, discussions with Haldimand County, Hydro One, Haldimand Hydro,

landowners, outcomes of the consultation process, and reducing potential negative environmental effects

through constraints avoidance and mitigation by design.

As part of the draft REA Reports which were available in October 2010, there were two substation location

options (Option 1 and Option 2) and two transmission line options (Option A and Option B) which were being

considered by NextEra Energy Canada (Golder, 2010c). For the Project design provided in the December 2010

reports and this Report, Substation Option 1 and transmission line Option A were selected and substation Option

2 and Transmission line option B information were removed from the Site Plan and all REA Reports. As shown

on Figure 1, the substation will be located on the south side of Concession Road 5 in the vicinity of Turbine 17

and Turbine 24. From the substation, a 230 kV transmission line will follow Concession Road 5 traveling west for

approximately 1.9 km to a point north of Turbine 23. At this point the transmission line will turn and continue

southwest through private lands between Concession Roads 4 and 5 for approximately 3.6 km. Part of this

section of the transmission line, south of Turbine 22, was straightened out relative to the October 2010 Project

Location (Golder, 2010c). From Lot 11 Concession 5, Township of Walpole, the transmission line will travel

generally southwest for approximately 2 km crossing Concession Road 4 and ending at the switchyard area.

Relative to the December 2010 REA Reports, five additional modifications were made to the Project Location, as

outlined in Table 2 below.

Page 5: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035 3

Table 2: Modifications to the Project Design Relative to the Draft REA Reports

Modifications to the Project Design since Draft REA Reports NextEra Energy Canada rationale for Modification

Relative to the Draft Summerhaven Project Location made publicly available in October 2010

Turbine 2 and associated access road and 34.5 kV buried collection line removed

Feedback from Haldimand County regarding overlap with urban expansion.

Turbine 60 and associated access road and 34.5 kV buried collection line removed

Landowner no longer participating in Project.

Turbine 36 construction staging area and turnaround reorientation. Landowner request to reduce impacts to agricultural practices. Access road and 34.5 kV buried collection line to Turbine 36 straightened

to run at the same orientation of parcel boundaries.

Turbine 44 construction staging area and turnaround reorientation. Landowner request to reduce impacts to agricultural practices. Access road and 34.5 kV buried collection line between Turbine 44 and

Turbine 45 adjusted to travel directly north-south.

Access road from Turbine 42 to Regional Road 8 removed. Landowner request to reduce impacts to agricultural practices.

East/west portion of access road and 34.5 kV buried cable from Turbine 43 moved to follow southern parcel boundary.

Landowner request to reduce impacts to agricultural practices.

Additional access road included between Turbine 46 and Turbine 47 in eastern direction.

Improved turbine access during construction and facility operations.

Access road and 34.5 kV buried cable moved to the west of Turbine 55 and Turbine 56.

Reduce predicted negative effects to natural features by avoiding candidate significant woodland.

Addition of a 7.3 m wide emergency services road east of Turbine 7 traveling south to Concession Road 6

Request from Haldimand County Planning and Economic Development Department, specifically Emergency Medical Services.

Switchyard area relocated approximately 10 m in southerly direction. Consultation with Hydro One.

Four meteorological towers added to the Project design. Two meteorological towers in the south-east of the Project Area (SMT2 and SMT4) are connected to the SCADA system which connects the individual turbines, substation, and meteorological towers to the Operations Building.

Assessment of meteorological conditions and wind resources requires permanent meteorological stations to be established. Stations used for pre-development wind resourcing studies determined to be insufficient for long term monitoring during Operations.

Access road near Turbine 59 rerouted to the east and south to connect with Turbine 16 and cable and road crossing of watercourse removed.

Reduce predicted negative effects to natural features by avoiding a water crossing.

Access road west of Turbine 14 that connected to the access road leading to Turbine 13 (and south to Turbine 20) was removed.

Reduce predicted negative effects to significant natural features by removing section of proposed road and constructing portion of the underground cable in or adjacent to natural features using horizontal directional drilling.

A section of the 34.5 kV buried collection line between Turbine 13 and Turbine 14 shifted to the north.

Page 6: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035 4

Modifications to the Project Design since Draft REA Reports NextEra Energy Canada rationale for Modification

Relative to the Draft Summerhaven Project Location made publicly available in October 2010

A section of the 34.5 kV underground collection line heading north from Turbine 20 that intersects with the underground line between Turbines 13 and 14 was shifted slightly to the west.

Reduce predicted negative effects to natural features by shifting portions of the cable outside of a valleyland and Regulation Limit.

Section of the 34.5 kV buried collection line heading west and north from Turbine 5 was rerouted.

Reduce predicted negative effects to natural features and avoid being in a wetland treated as significant.

Section of the Turbine 43 access road and 34.5 kV buried collection line route (connecting with Kohler Road) moved south.

Reduce predicted negative effects to natural features by avoiding a woodland that was not previously assessed (note that the December 2010 Project Location moved this infrastructure north, and the current Project Location moved the infrastructure back south to the previous, October 2010 Project Location).

A section of the access road and the 34.5 kV underground collection line between Turbines 25 and 26 was rerouted to the north.

Reduce predicted negative effects to a natural feature by moving the access road and cable and avoiding the northern edge of a woodlot.

A section of the 34.5 kV underground collection line transitioning to an overhead collection line south of Turbines 25 and 26 was rerouted to the north.

Reduce predicted negative effects to a natural feature by reducing the crossing length/number of crossings of a significant valleyland and a watercourse. Where the overhead cable coming from the east meets the edge of the valleyland, it will go under the valleyland via horizontal directional drilling, and then will continue as an underground cable to the north.

A section of the 34.5 kV overhead collection line east of Turbines 58 and 26 west of Regional Road 53 was moved underground.

Reduce predicted negative effects to a natural feature by changing an overhead water crossing to underground using horizontal directional drilling.

A section of the 34.5 kV overhead collection line between Turbines 10 and 11 was moved underground.

Reduce predicted negative effects to a natural feature by changing an overhead water crossing to underground using horizontal directional drilling.

A section of the 34.5 kV overhead collection line north of Turbine 27 was moved underground.

Reduce predicted negative effects to a natural feature by changing an overhead water crossing to underground using horizontal directional drilling.

A section of the access road and the 34.5 kV underground collection line north of Turbine 30 was rerouted.

Reduce predicted negative effects to a natural feature by avoiding woodland, and realigning the access road and collection line to follow lot boundaries.

A section of the 34.5 kV overhead collection line heading north from Turbines 48-51 along Fisherville Road was shifted to the east side of the road, and a portion of the shifted cable was moved underground.

Modify design to address space constraints and engineering limitations that may be associated with overhead cable. Reduce predicted negative effects associated with alternate design by moving

Page 7: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035 5

Modifications to the Project Design since Draft REA Reports NextEra Energy Canada rationale for Modification

Relative to the Draft Summerhaven Project Location made publicly available in October 2010

cable underground beneath edge of woodland boundary using horizontal directional drilling.

A section of the 34.5 kV underground collection line to Turbine 51 was shifted to the other side of the access road.

Minimize negative effects to a non-significant natural feature by minimizing the length of a cultural thicket that is crossed by the cable and access.

A section of the 34.5 kV underground collection line along Concession Road 5 was moved underground.

Reduce predicted negative effects to a natural feature by changing an overhead water crossing to underground using horizontal directional drilling.

Two sections of the 34.5 kV underground collection line south of Turbine 5 and along Concession Road 6 was moved underground.

Reduce predicted negative effects to a natural feature by changing an overhead water crossing to underground using horizontal directional drilling.

Alteration of transmission line route and pole placement at crossing of Concession Road 4.

Adjust transmission line alignment to avoid vegetation removal within a wetland feature and reduce interference to agricultural practices by shifting alignment to west side of field.

Sections of the 34.5 kV overhead collection line along Concession Road 4 east of Turbine 16 was moved to the north side of the road.

Avoid natural features that were located on the south side of the road.

Sections of the 34.5 kV overhead collection line along Concession Road 4 east of Turbine 16 was moved underground.

Reduce predicted negative effects to a natural feature by changing an overhead water crossing to underground using horizontal directional drilling.

A section of the 34.5 kV overhead collection line along Fisherville Road between Concession Road 3 and 4 was moved underground.

Reduce predicted negative effects to a natural feature by changing an overhead water crossing to underground using horizontal directional drilling.

A section of the access road and the 34.5 kV underground collection line heading west of Turbine 55 connecting with Reicheld Road was rerouted such that it now extends north to Dover Dunnville Road.*

Landowner where the former road and cable west to Reicheld Road decided to no longer participate in the Project.

* Note that the access road and underground collection line through the following land parcel is currently being confirmed: PT W1/2 LT 16 CON 1 RAINHAM PT 1 18R3593; HALDIMAND COUNTY.

Page 8: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035 6

3.0 REFERENCES Golder Associates Ltd. 2010a. Stage 1 Archaeological Assessment Report. Prepared for: Ministry of Tourism

and Culture and Ministry of the Environment.

Golder Associates Ltd. 2010c. Site Plan Report, Version 1. Prepared for: Ministry of the Environment. October

5, 2010.

Golder Associates Ltd. 2010d. Site Plan Report, Version 2. Prepared for: Ministry of the Environment.

December 17, 2010.

Golder Associates Ltd. 2011a. Construction Plan Report. Prepared for: Ministry of the Environment.

Golder Associates Ltd. 2011b. Design and Operations Report. Prepared for: Ministry of the Environment.

Golder Associates Ltd. 2011c. Decommissioning Plan Report. Prepared for: Ministry of the Environment.

Golder Associates Ltd. 2011d. Project Description Report. Prepared for: Ministry of the Environment.

Golder Associates Ltd. 2011e. Wind Turbine Specifications Report. Prepared for: Ministry of the Environment.

Golder Associates Ltd. 2011f. Natural Heritage Assessment Report. Prepared for: Ministry of Natural

Resources and Ministry of the Environment.

Golder Associates Ltd. 2011g. Noise Study Report. Prepared for: Ministry of the Environment.

Golder Associates Ltd. 2011h. Water Assessment Report. Prepared for: Ministry of the Environment.

Golder Associates Ltd. 2011i. Consultation Report, Version 2. Prepared for: Ministry of the Environment.

Golder Associates Ltd. 2011j. Heritage Assessment Report. Prepared for: Ministry of Tourism and Culture and

Ministry of the Environment.

Ministry of Energy and Infrastructure. 2010. Letter to Justin W. Rangooni, Ontario Policy Manager & Legal

Counsel, CanWEA. Exemption from having completed the Stage 2 Archaeology Assessment prior to

submission of the REA Application. June 14, 2010.

Ministry of the Environment (MOE). 2010. Technical Bulletin Two: Guidance for preparing the Design and

Operations Report. Queen’s Printer for Ontario. PIBS 7437e.

Page 9: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035

Report Signature Page

GOLDER ASSOCIATES LTD.

Jeff Wright, R.P. Bio., A.Sc.T. Anthony Ciccone, Ph.D., P.Eng. Project Manager Project Director

RC AE JR/JW AC/

Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation.

\\mis1-s-filesrv1\data\active\2010\1151\10-1151-0035 nextera - wind farm rea - nanticoke\4 - working rea reports\0 - site plan report\version 3\2011-06-13 site plan report.docx

Page 10: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

SUMMERHAVEN SITE PLAN REPORT

June, 2011 Report No. 10-1151-0035

FIGURE 1 Site Plan

Page 11: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

Mud Creek

Dry Cr

eek

Pike Creek

Gates C

reek

Holmes Creek

Stoney Creek

Spring Creek

Rogers Creek

Catfish Creek

Sulphur Creek

Sandusk Creek

Hickory Creek

Hemlock Creek

Wardells Creek

Fauri

e's C

reek

Nanticoke Creek

Grand River

Lake Erie

US SteelNanticokeGenerating

Station

Imperial OilRefinery

HaldimandNorfolk

Haldimand

Mississaugas Of New Credit

803m

790m

788m

779m

776m

754m 747m

725m

723m

706m 704m

695m

684m

656m

641m

638m

617m

616m

615m

610m

609m

600m

598m

588m

584m

581m

578m

570m

559m

557m

556m

542m

541m

538m

531m

530m

529m

523m

518m506m

499m

492m

486m

485m

482m

479m

478m 475m

464m

454m

452m

449m

440m

406m

394m

391m

486m

616m

485m

SMT02

SMT04

FPMT03

FPMT01

185180

220

210

215

195

200

175

190

205

225

180

220

205

210

210

195

220

185

195

185

190

200

200

200

195

190

215

190

220

220

210

190

200

210

220

195

200

215

185

190

190195

220

195

175

215

205

215

190

175

185

200

200

180

205

190

220

210

185

215

190

190

185

205

180

195

195

190

210

190

195

195

195

195

185

210

195

210

195

225

190

185

210

215

200

185

220

195

215

215

215

220

210

200

185

205

205

220

195

205

210

190

200

210

200

180

205

215

220

215

190

185

210

185

195

205

205

195

190

185

200

220

200

215

210

220

205

185

185

205

200

195

190

215

210

200

205

200

190

205

190

210

180

220185

195

185

210

220

205

215

220

190

200

200

200

220

200

185

205

200

205210

195

180

215

185

210

215

190

180

225

205

190

200

200

200

190

200

190

205

190

200

195

195

215

185

190

215

190

200

175

220

185

205

195

205

180

210

210

190

180

185

185

210

180

195

225

195

190200

195

185

195

195 200

180

200

215

205

195

205

205

180

190

205

180

225

220

205

195

180

210

195

185

205

200

215

180

190

220

185

180

190

205

195

210

205

200

210

215

215

205

195

215

180

190

195

175

200

205

185

215

180

215

190

200

200

175

210

220

200

195

205

200

200205

190

190

180

195

200

205

225

205

185

185

210

200

190

200200

195

190

205

195

205

205

205

195

195

205

200

195

180

190

200

195

205

195

195

185

200

210

195

180

210

190

215

190

175

215

200

215

195

210

195

205

195

200

200

200

205

205

195

205

195

190

190

210

200

200

205

190

210

200

185

185

195

180

220

200

215

205

185

200

215

200

215

205

210

200

195

180

190

195

190

210

185

200

190

205

195

185

185

195

215

205

220

195

220

210

205

180

205

200

210

215

190190

195

190

190

190

205

185

210

195

215

210

190

195

210

195

205

215210

185

195

200

185

190

195

210

215

220

205

195

195

185

195

200

185

195

210

190

220

195

180

205

215

200

200

210

200 185

200

185

190

185

195

190

185

210

200

205

210

180

220

200

205

195

205

220

180

190

215

200

210

195

225

185

185

215

215

205

180

185

225

215

205

210

210

190

200

200

200

190

195

190

220

215210

210

215

195

200

215

195

200

200

190

200

195

190

180

205

210

220

200

210

185

210

200

205

200

195

200215

185

205

205

205

205

205

200

195

205

215

190

175

205

215

200

200

190

210

185

200

190

185

210

195

210

200

220

185

200

185

190

195

215

215

195

190

220

200

175

190

190

195

180

190

215

190

190

195

205

195

190

225

195

215

185

210

185

215

210

210

200

215

210

190

185

195

220

190

195

200

180

195

205

185

200

195

205

195

200

205

210

200

200

190

210

220

205

190

180

190

190

220

185

200

185

185

215195

200

215

215

190

185

185

210

215

195

195

190

220

210

200

215

195

175

180

190

205

9

78

56

3 4

1

52

33

19

39

57

5455

38

53

58

61

56

20

17

15 23

59

40

41

11

12

62

34

16

18

13 14

35

10

4342 45

4447

46

49

4851

50

2221

28

27

262524

36 37

31

30

32

HALDIMANDCONSERVATION

AREA

SELKIRK PROVINCIAL PARK

TALBOT RD

NANTICOKE RD

SANDUSK RD

INDIAN LINE RD

CHEAPSIDE RD

RIVER RD

MUD ST

KOHLER RD

CONCESSION RD 6

CONCESSION RD 9

CONCESSION RD 5

CONCESSION RD 4

ARMY CAMP RD

REGIONAL RD 53

REGIONAL RD 3

CONCESSION RD 10

LAKE SHORE RD

FISHERVILLE RD

CONCESSION RD 3

CONCESSION RD 2

LINK RD

SUTOR RD

DOVER DUNNVILLE RD

HIGHW

AY 6

TOWNLINE RD W

IRISH LINE RD

CONCESSION RD 13

REGIONAL RD 9

CONCESSION RD 8

DRY LAKE RD

REGIONAL RD 17

MEADOWS RD

SPRINGVALE RD

TOWNLINE RD

CONCESSION 1 RD S

2 LINE

LYNN VALLEY RD

ST JOHNS RD

WALPOLE WOODHOUSE TLINE

WINDECKER RD

PLAN

K RD

SOUTH COAST DR

BLOOMSBURG RD

ROCKFORD RD

TOWNLINE RD E

MCKE

NZIE

RD

INDIANA RD W

HIGHWAY 54

EAST QUARTER LINE

YANKEE RD

BAINS RD

CHERRY VALLEY RD

DECOU RD

STONE QUARRY RD

DEER PARK RD

CONCESSION 14 TOWNSEND RD CONCESSION RD 5

CONCESSION RD 3

CONCESSION RD 4

CONCESSION RD 6

Erie

GillNober

Kohler

Garnet

Jarvis

Cayuga

Varency

Sandusk

Marburg

Selkirk

Townsend

RockfordBalmoral

Haldimand

Dogs Nest

Cheapside

Nanticoke

Springvale

Sandy Cove

Fisherville

Decewsville

Clanbrassil

Keadon Park

Hagersville

Crescent Bay

Featherstone

Lambs Corners

Peacock Point

Hickory Beach

Woodlawn Park

Sweets Corners

Rainham Centre

Nelles Corners

Vaughan Survey

White Oaks Village

568000

568000

572000

572000

576000

576000

580000

580000

584000

584000

588000

588000

592000

592000

596000

596000

4736

000

4736

000

4740

000

4740

000

4744

000

4744

000

4748

000

4748

000

4752

000

4752

000

4756

000

4756

000

G:\Pr

ojects

\2010

\10-11

51-00

35_N

extEr

aNan

ticok

eWind

\GIS\

MXDs

\Draf

t\Rep

ort\D

esign

AndC

onstr

uctio

n\Site

Plan.m

xd

LEGENDBase Data - MNR NRVIS, obtained 2004, CANMAP v2008.4, SOLRIS 2000Provincially Significant Wetland and Area of Natural and Scientific Interest data - MNR, obtained 2009Significant Woodlot designation - Haldimand County OP, 2009Heritage Property Data - Haldimand County Navigator, www.haldimandcounty.on.caProduced by Golder Associates Ltd under licence from Ontario Ministry of Natural Resources, © Queens Printer 2009Projection: Transverse Mercator Datum: NAD 83 Coordinate System: UTM Zone 17

REFERENCE

REV.

Mississauga, Ontario

DESIGN

SITE PLAN

FIGURE: 1PROJECT NO. 10-1151-0035 SCALE AS SHOWN

PROJECT

TITLE

GIS

REVIEW

PP 28 Jul. 2010

CHECK

Summerhaven Wind Energy Centre

PP 29 Sep. 2010JRJW

29 Sep. 201029 Sep. 2010

Project Location

Turbine and Number

Meteorological TowerOverhead CableUnderground Cable - Directional DrilledUnderground Cable - TrenchedTransmission LineAccess RoadSwitchyard AreaConstruction Field Offices and Temporary StorageSubstation

Noise Receptor (Exisitng or Vacant Lot)Nearest Receptor (from Turbine or Substation)CommunitySchoolContour (5m interval)HighwayMajor RoadLocal RoadRailwayHydro One Utility LineMunicipal BoundaryProject AreaO.Reg.359/09 Natural Heritage/WaterSetback From Project Location

Provincial ParkConservation AreaHaldimand TractProvincially Significant Natural FeatureRegionally Significant Natural FeatureHaldimand County Industrial Influence Area

Land Cover (SOLRIS / NRVIS)Natural AreaForestPit \ QuarryUrban \ IndustrialWetlandWaterAgricultureAirport

NOTES:1. All Project Location inludes disturbance area2. Turbines 2, 29 and 60 do not exist3. Turbine 62 is a Siemens SWT-2.221-93 Low Noise wind turbine. All other turbines are Siemens SWT-2.221-101 Low Noise wind turbines.4. Any receptors less than 550m from wind turbines or either substation option are participating.

0 500 1,000 1,500 2,000 2,500250METRES1:30,000SCALE

401403

3

6

24London

Hamilton

Kitchener

Brantford

Port Dover

Niagara Falls

Lake Erie

Lake Ontario

USAProject Area

INDEX MAP

Page 12: 2011-06-13 Site Plan Report...SUMMERHAVEN SITE PLAN REPORT June, 2011 Report No. 10-1151-0035 1 1.0 INTRODUCTION The attached Site Plan diagram (Site Plan) (Figure 1, end of the Report)

Golder Associates Ltd.

2390 Argentia Road

Mississauga, Ontario, L5N 5Z7

Canada

T: +1 (905) 567 4444