2012 bond premium reserve allocation follow-up...
TRANSCRIPT
BOC Premium Reserve Follow-up
Category Staff Recommended
Prioritization*
Additional Need Evaluated
& Presented
Maintenance $8.3M $8.2M
Technology $7.0M $8.1M+
Capacity Expansion/
Renovation $18.1M $22.0M
Total $33.4M* $38.3M+
• During the November 21st BOC working session and December 3rd Public
Comment session we have collected various questions on the
recommendations that are aggregated here
Capacity Process Overview
- 2 -
Maintenance Technology
Facility Maintenance: Stage Curtains
- 3 -
Question: The current recommendations include replacements for stage curtains at three schools:
Bromwell, Brown and Newlon. There was a request for additional information on the cost for stage
curtain replacement
Response: Stage curtain replacement will require replacement of the rigging, equipment, and other
safety upgrades as well as replacement of the curtains, valances, etc. The estimate of $128,400
per replacement is based on actual quotes received from vendors for similar replacements
Capacity Process Overview Maintenance Technology
Facility Maintenance: Water Quality
- 4 -
Question: In the 2012 CPAC there was a significant amount of water quality need. Question as to why
there are no water projects current recommended
Response: The 2012 GOB included a number of galvanized piping projects: • Cole – 2014 (some additional work to complete in 2015)
• Fairview – 2014
• Moore – 2014
• Morey – 2014
• Smiley – 2014
• Edison – 2015
• Lake – 2015
• Schenck – 2015
• Steele – 2015
• Hill – 2015
• Garden Place – 2015
• Park Hill – 2015
• Pioneer – 2015
• Valverde – 2016
• Rishel – 2016
• Beach Court – 2016
• Fairmont – 2016
• University Park – 2016
• Skinner – 2016
• South – 2014 [CDE BEST Funded]
If we add the next schools in line, Mitchell and Whiteman, we will be at 22 schools, about ¼ of the
schools with this need. At these schools there is some water discoloration but there are no imminent
health issues. They ended up below the line in 2012 due to prioritization and remain there in our current
recommendations due to criticality. This bond addresses 20 schools and hopefully in future bonds all
schools with galvanized piping will be fitted with copper.
Capacity Process Overview Maintenance Technology
Facility Maintenance: Turf Fields
- 5 -
Question: What is the current state/approach in DPS to building turf fields?
Response:
DPS currently has 11 Artificial Turfs Fields:
• North
• South
• West
• East
• Jefferson
• Kennedy
• Abe Lincoln
• Washington
• Manuel
• Evie Dennis
• Montbello
Each are showing wear and tear normal to their operation.
Current fields are constructed utilizing crumb rubber, which typically comes from ground-up tires, but
there are other sources as well. Facility Management recommends that any new artificial turf fields
considered being built are constructed with an alternative composition of crumb rubber products until
more research is completed. The newer products available may increase the overall costs of the
fields. The EPA has not completed their evaluations on the rubber sub-surface crumb rubber particles
historically used in Artificial Turf Fields, so no reliable research data exists at this time. In the
meantime, it is recommended that DPS utilize the newer options of crumb rubber sources until more
information is know on current materials.
Capacity Process Overview Maintenance Technology
Tech: Classroom Technology
- 6 -
Question:
• What precisely are the funds for? Chromebook carts, teacher laptops, chromebooks, and Ipads are
mentioned?
• What is the school minimum configuration (and does it vary by Elementary, Middle, and High School?
• What is the current status of achieving the minimum configuration?
Response: Please reference following slides
Capacity Process Overview Maintenance Technology
Tech: Classroom Technology
Bond and Mill Levy Spend Scenarios
Schools have received Mill Levy (recurring) and Bond (non-recurring) technology funds since 1998.
Device replacement cycle should be every 4 years.
Estimating $600/device, if schools used all of their Bond and ML funds (2011-2015) to purchase only
student devices, they could have achieved at best a 2:1 student to device ratio.
– This does not account for replacement of teacher devices. We have over 6000 District teachers.
– Purchases of projectors, smart boards, clickers, etc. would increase the student:device ratio
- 7 -
Source Project / Use Amount Notes
2012 Bond Classroom Technology 10,100,000$ Allocated to schools on a per pupil funding basis of $125
2008 Bond Classroom Technology 10,011,000$ Allocated to schools on a per pupil funding basis of $125
2008 Bond Teacher Laptops 2,625,000$ Oct '10-Nov '12, 4,892 teacher laptops distributed, schools
advised to budget for replacement cycles.
2008 Bond Classroom Technology -
Innovation Grants
1,000,000$ Grants awarded to 13 schools/3 special ed programs per
application process
2008 Bond Supplemental
Assessment Tech Grant
1,000,000$ Grants awarded to 86 schools per application process
2012 ML* recurring
Devices and/or staff 4,000,000$ Allocated to schools on a $45 per pupil basis, 40% spent on
FTEs and 60% on devices in 2013-2014 SY
1998 ML* recurring
Devices and/or staff 2,000,000$ Allocated to schools on a $22 per pupil basis, 40% spent on
FTEs and 60% on devices in 2013-2014 SY
# of Students '98 Mill Levy '12 Mill Levy '12 Bond 2012-2015 Device Totals Student:Device Ratio
Large School 700 9,240$ 18,900$ 87,500$ 333 2:1
Medium School 500 6,600$ 13,500$ 62,500$ 238 2:1
Small School 350 4,620$ 9,450$ 43,750$ 167 2:1
Capacity Process Overview Maintenance Technology
Requirements & Recommendations
The minimum device configuration necessary is that each school mush have enough devices to support
online testing of the school‟s largest grade at the same time.1 This is the same for Elementary, Middle,
and High Schools.
We recommend all schools outfit each classroom with a digital projector, document camera, and
speakers and/or interactive white board.
DPS has not yet set a target student:device ratio as an instructional standard.
Current Inventory Summary – Aging Desktop Computers and Laptops2
Based on available school inventory data, ~ ½ of District computers and laptops are over 3 years old,
with over ¼ over 5 years old.
While the majority of laptops are less than three years old, the majority of computers are over 5 years old
and are due for replacement with an appropriate device.
Tech: Classroom Technology
Instructional Technology
- 8 -
1 Exceptions apply for K-8 and 6-12 schools which will be
required to test two grade levels concurrently 2 Computers & Laptops comprise 66% of device inventory
included in this analysis
Capacity Process Overview Maintenance Technology
Tech: Classroom Technology
Instructional Technology
User : Device Ratios
Student and Teacher : Computer and Laptop ratios across schools show a small % with ratios of less
than 2:1. About half of the schools in our inventory show ratios between 2:1 and 4:1, and more than 1/3
with ratios greater than 4:1.
Inventory data shows that schools have used ML and Bond funds to purchase devices for teachers and
students.
While device ratios are low for some schools, there is room to address aging devices and user : device
ratios for many schools.
- 9 -
Capacity Process Overview Maintenance Technology
Tech: Mobile Device Management
- 10 -
Question:
• What is this specifically for?
• Is this for IPADs, chromebooks, or both?
Response: Please reference word document: DPS Mobile Device Management_Dec2014
Capacity Process Overview Maintenance Technology
Capacity: School Expansion Fund (1 of 2)
- 11 -
Question:
• Provide more description of what has been funded from this fund in the 2012 Bond
Response:
Capacity Process Overview Maintenance Technology
2013 Projects Subtotal Description
ASHLEY $50,000 Facility modifications to support turn-around school efforts.
Compassion Road $478,100 Renovation of previous school facility including paint, modification of open work space and offices into classrooms, upgrade wireless and wired infrastructure, directional signage, security features including access control system and cameras.
DSST Stapleton $82,017 Create new classroom to accommodate new Special Education center program
Excel move to Lalo Delgado Campus
$140,000 Facility modifications to increase separation and security on shared campus to introduce third school to campus.
Fairmont $29,072 Modify previous middle school classrooms into elementary school classrooms, remove lockers.
FFE for 27 schools $2,792,329 Furniture, Fixtures & Equipment for schools modifying grade structure or phasing in.
GALS at Del Pueblo $103,000 Closing of several open plan classrooms.
Gilpin $122,856 Facility modifications to accommodate Montessori secondary program - included new paint in classrooms, directional signage, lockers, creation of an office space, and creation of open student work area.
JUSTICE HS $900,000 Renovation of private leased facility at 300 E. 9th to accommodate alternative high school.
Manual $42,000 Facility modifications to accommodate professional development center, displaced from Del Pueblo.
Merrill C3 PH 2 $63,612 Modifications to facility to accommodate growing shared campus.
Montbello $505,000 Facility modifications of Montbello Campus included the following: Relocation of PUSH Academy to CAE; Add additional classroom capacity for phase-In of NCAS and DCIS grades 8 and 11; Renovate office space; Branding & paint
Montbello $5,000 Traffic study.
MONTCLAIR $12,744 Removal of 1/2 walls to create additional classroom capacity.
Noel $268,000 Facility modifications of Middle School to meet the educational requirements of KIPP (5-8) and CPA (9-12) as they built out including adding additional classroom capacity, creation of MI and MIS rooms for CPA; New computer lab for KIPP; HVAC upgrades for Center Program "Cool Down" rooms; branding.
PLACE ANNEX $33,025 Facility modifications to accommodate additional students on shared campus.
Remington $543,103 Modification of elementary school facility to serve middle school students, and updating of facility for 21st century learning.
Samsonite $768,382 Modifications of open plan child care oriented space (~1/4 of facility) to become appropriate for K-12 education.
Smedley $101,000 FFE and building modifications to accommodate DDES.
West Phase II $204,051 Modifications of facility to accommodate growth of shared campus. Included updating of some older spaces.
TOTAL $7,243,290
Capacity: School Expansion Fund (2 of 2)
- 12 -
Question:
• Provide more description of what has been funded from this fund in the 2012 Bond
Response:
Capacity Process Overview Maintenance Technology
2014 Projects Subtotal Description
400 S ZUNI $30,000 Due diligence and design for potential new facility.
C3 at Merrill $240,500 Modifications to facility to accommodate growing shared campus
CAE PUSH PH II $960,000 Modifications to new purchased facility to create high school and CTE campus.
EXCEL ACADEMY DESIGN
$31,968 Due diligence and design for potential new facility.
FFE for 23 schools $1,532,970 Furniture, Fixtures & Equipment for schools modifying grade structure or phasing in.
JFK RENOVATION $185,438 Facility modifications to create a CTE program.
KEPNER MS PREP $22,000 Facility modifications to create space suitable for shared campus.
NOEL RENOVATION $89,946 Creation of additional classrooms to provide additional secondary capacity in FNE.
OAKLAND RENOVATION
$187,700 Modification of elementary school to accommodate turn-around school program.
PRAISE CHURCH ARCHITECT STUDY
$5,000 Due diligence and design for potential new facility.
RISHEL PLAYFIELD $50,000 Modifications to Rishel Campus field to create regulation soccer field.
SAMSONITE TENANT IMPROVMENTS
$87,052 Facility modifications to further serve the shared campus expansion.
SMILEY RENOVATION $150,000 Facility modifications to accommodate McAuliffe on campus.
SE ANNEX PH2 $106,351 Facility Modification of newly acquired sf on Annex Campus to serve elementary students.
STRIVE @ NORTH $170,815 Facility modifications to serve full high school in former CTE building. Scope included creation of a high school science lab, adding lockers, and art sink installation.
TOTAL $3,849,740
Capacity: Summit Academy
- 13 -
Year Enrollment FRLPct MinorityPct ELLPct SPEDPct SPF
PointsPct SPF Rating
2010-11 131 77.1% 93.1% 21.4% 17.6% 21.1% Accredited On Probation
2011-12 163 73.0% 89.6% 19.6% 14.1% 17.7% Accredited On Probation
2012-13 224 74.1% 92.9% 20.5% 11.2% 20.5% Accredited On Probation
2013-14 157 81.5% 91.1% 27.4% 8.3% 28.1% Accredited On Probation
2014-15 263 TBD TBD
Question: What are the academic and enrollment trends at Summit?
Response:
Capacity Process Overview Maintenance Technology
Capacity: KIPP
- 14 -
Question:
• Who owns the land for KIPP Sunshine Peak expansion?
Response: Denver Public Schools owns the land for the KIPP Sunshine Peak expansion. KIPP
owns the current modular buildings.
Capacity Process Overview Maintenance Technology
Capacity: HS at Sandoval Campus
- 15 -
Question:
• List of HS features at Sandoval Campus and comparison with other HS
Response:
HS at Sandoval Campus:
Current Phase I + Recommendation
Evie Dennis Phase I (Multi-school campus, opened with 150 DSST
students, 150 SOAR students and 300
students from MLK)
Projected Students 900-1000 1200-1300
# of Classrooms 42 58
Art/Music/Tech
Rooms
Yes Yes
Square Feet 131,959 on 40 acres 101,097 on 35 acres
Cafeteria Warming Kitchen
Up to 360 for lunch
Full-Service Kitchen
572 for lunch
Performance Space Yes in cafeteria
332 seating for performance
Yes in cafeteria
286 seating for performance
CHSAA Gym Yes Yes
Bleacher Seats 800 650
CHSAA Fields MP Field, Track, Baseball, Softball, Tennis MP Field, Track, Baseball, Softball,
½ Soccer
Committed Budget $42.5M* Total budget of $48M for full build-out.
Phase I opened in fall 2010
Capacity Process Overview Maintenance Technology
Internal Draft *DPS also paid ~$3.9 million for the land where the Sandoval campus is located
Capacity: HS at Sandoval Campus
- 16 -
Question:
• It would appear that the compromise addition will alter the master plan for the site including the
commons building and parking. How does the compromise addition affect the Master Plan for the
site? Would any of the this compromise be undone in the future?
During the meeting, staff plans to present the recommendation in addition to alternatives and will
discuss how each relates to the master plan.
• On page 30 of the 11/21/14 BOC presentation, the “Sandoval Campus full building 3” is listed at $14
million. Is building 3 the commons building as conceived in the bond or something else? In earlier
discussions the shortfall for the commons building was reported as less than $10 million. Please
define what this building is and what the $14 million includes?
During the meeting, staff plans to present the recommendation in addition to alternatives and will
discuss how each relates to the master plan. The building shortfall figures previously note did not
provide a complete picture of the cost of the additional building at that time.
Capacity Process Overview Maintenance Technology
NNE Stapleton/Northfield Campus
Future Phases
# SLCs
4 additional
Tennis
Courts
Add Athletic Lockers,
Weight and Aerobic Rooms
CommonsArt, Music,
Cafeteria &
Kitchen
Repurpose Core
Admin & Support
Expand Bleachers
to 1600
Phasing Legend
Phase 1
Repurpose
Future Phases
Capacity Process Overview Maintenance Technology
- 17 -
Gym East Option A – Art/Music
$4.76M
Vocal
Instrumental Music
2D Art
3D Art
Associated Effects
Recovers temp Music and
temp Art spaces from
Academic Building
Capacity Process Overview Maintenance Technology
Note - this option utilizes the originally designed locker, weight, and aerobics rooms.
Expands East vs South and increases in total square foot.
- 18 -
Commons “Light” B – Café/Kitchen/Stage
$7.10M
Entry
Restrooms
Full Cafeteria – Seating
– Serving
– Full Kitchen
– Storage
Stage
Associated Effects
Frees temp
Cafeteria/Warming Kitchen
in the Gym for other uses
(i.e. Weight/Fitness area to
open up gym floor for
additional seating).
Capacity Process Overview Maintenance Technology
- 19 -
Commons “Light” C – Café/Kitchen/Stage/Drama
$9.20M
Entry
Restrooms
Full Cafeteria – Seating
– Serving
– Full Kitchen
– Storage
Stage
Drama
Associated Effects
Frees temp
Cafeteria/Warming Kitchen
in the Gym for other uses
(i.e. Weight/Fitness area to
open up gym floor for
additional seating).
Capacity Process Overview Maintenance Technology
- 20 -
Commons “Light” D – Café/Kitchen/Stage/Drama/Music
$10.74M
Entry
Restrooms
Full Cafeteria – Seating
– Serving
– Full Kitchen
– Storage
Stage
Drama
Music
Associated Effects
Frees temp
Cafeteria/Warming Kitchen
in the Gym for other uses
(i.e. Weight/Fitness area to
open up gym floor for
additional seating).
Recover Music space from
Academic Building
Capacity Process Overview Maintenance Technology
- 21 -
Commons “Light” E – Café/Kitchen/Stage/Drama/Inst/Vocal
$11.97M
Entry
Restrooms
Full Cafeteria – Seating
– Serving
– Full Kitchen
– Storage
Stage
Drama
Instrumental Music
Vocal Music
Associated Effects
Frees temp
Cafeteria/Warming Kitchen
in the Gym for other uses
(i.e. Weight/Fitness area to
open up gym floor for
additional seating).
Recover Music space from
Academic Building
Capacity Process Overview Maintenance Technology
- 22 -
Overview
Premium Reserve Recommendations by Region
- 23 -
SE
(District* 1)
SW
(District 2)
NNE
(District 3)
FNE
(District 4)
NW
(District 5)
Maintenance $ 128,400 $ 2,286,835 $ 105,071 $ 1,950,000 $ 3,830,336
Technology** $ 490,496 $ 835,467 $ 435,136 $ 1,222,699 $ 696,202
Capacity $ - $ 9,000,000 $ - $ 4,000,000 $ 3,100,000
Total $ 618,896 $ 12,122,302 $ 540,208 $ 7,172,699 $ 7,626,537
District-wide Investments
Capacity: School Expansion Fund $2,000,000
Technology: Mobile Device Management Solution – Phase 1 $1,320,000
Technology: Instructional Management System Replacement $862,000
Technology: Infor S3 Payroll System Upgrade to v10 $1,150,000
Total $5,332,000
*Note: Board Districts reflect revised districts as adopted by the Board at the Oct 23rd, 2014 Board Meeting
**Assumes classroom tech „boost funds‟, school support personnel and electrical work will be distributed evenly across enrolled
students. May not be the case
Per the Bond Oversight Committee’s direction, an even distribution of premium funds across geographic
regions was not considered as a prioritization criteria
Capacity Process Overview Maintenance Technology
Overview
2012 GOB Investments by Region
- 24 -
SE
(District* 1)
SW
(District 2)
NNE
(District 3)
FNE
(District 4)
NW
(District 5)
Maintenance $34,562,017 $45,710,380 $16,675,167 $43,816,662 $70,767,510
Technology $5,989,108 $6,132,484 $5,837,428 $15,057,134 $7,736,850
Capacity $31,656,558 $22,093,428 $47,866,359 $122,662,554 $14,774,983
Total $72,207,683 $73,936,292 $70,378,954 $181,536,350 $93,279,343
Unallocated Bond Premium Reserve
$46,349,995
*Note: Board Districts reflect revised districts as adopted by the Board at the Oct 23rd, 2014 Board Meeting
Capacity Process Overview Maintenance Technology
A Vision for Technology at DPS
DPS – Making Connections
http://vimeo.com/97279994
- 26 -
Bond Oversight Prioritization Criteria
as adopted Nov 7
Capacity Process Overview
Overall, the projects that the Bond Oversight Committee recommend should be described with sufficient specificity and detail that the district can readily be held accountable for the proper and timely use of the funds allocated. More specifically, the Committee recommendations are based on projects aligning with these following key criteria: (not in prioritized order) • The project is necessary for the safe operation of a facility or other capital asset to meet health and
safety code compliance.
• The project is critical to the implementation of the ongoing instructional practices of the district.
• The project supports, leverages or enables the opportunity to attract other financial resources to support a district priority.
• The project enables a reduction in operating costs or leverages resources, thereby improving the long-term financial health of the district.
• The project supports the district’s technological infrastructure.
• The project fulfills commitments made to communities and taxpayers of the 2012 bond initiative.
• The project meets critical needs identified since the passage of the 2012 bond or of increased urgency since the 2012 bond.
• The project supports DPS’s shared core value of equity, as embodied in the goals of the Denver Plan 2020.
- 28 -
Maintenance Technology