1 PMTurkeyCOLPEm Resource From: Orthen, Richard [[email protected]] Sent: Friday, December 14, 2012 11:45 AM To: Williamson, Alicia; Matthews, David; Maher, William; Comar, Manny; Stewart, Scott; McCree, Victor; Megan Clouser Cc: 'Anthony M Sicari ([email protected])'; 'Bob Yamrus ([email protected])'; Bortone, Pilar; Brown, Alison; Burski, Raymond; CHILDRESS, ELWOOD; Davidson, Angela; Mothena, Don; 'Douglas Kalinousky ([email protected])'; Franzone, Steve; Hamrick, Steven; Jacobs, Paul; '[email protected]'; Fazio, Joseph; 'Julius Isaac ([email protected])'; Madden, George; Magalhaes, Jose; Dryden, Mark; Mccool, Terry; Jordan, Michael; Murphy, Stella; Nicholson, Larry; Orthen, Richard; Petro, James; Raffenberg, Matthew; Reynolds, Mike; 'Ronald Anstey ([email protected])'; Scroggs, Steven; Mihalakea, Stavroula; Tomonto, Bob; Turbak, Michael; Weis, Rick; Winfield, Nadine; Proctor jr., Kennard; Kyle Turner; 'Karl Bullock'; 'Frank Matthews'; 'Douglas J. Schlagel, P.E., CHMM'; 'Susan Smillie' Subject: FPL Letter L-2012-441 Dated 14DEC12: Schedule for Response to NRC RAI Letter 121114 (eRAI 6879) Alternative Site Selection Attachments: L-2012-441 Dated 14DEC12 RAI Ltr 121114 eRAI 6879 Rev 0 Response Schedule.pdf U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555-0001 Re: Florida Power & Light Company Proposed Turkey Point Units 6 and 7 Docket Nos. 52-040 and 52-041 Schedule for Response to NRC Request for Additional Information Letter 121114 (eRAI 6879) Related to ESRP Section 9.3.1 Alternative Site Selection Reference: NRC Letter to FPL dated November 14, 2012, Environmental Request for Additional Information Letter 121114 Related to Environmental Standard Review Plan Section 9.3.1, Alternative Site Selection, for the Combined License Application Review for Turkey Point Units 6 and 7 The Nuclear Regulatory Commission (NRC) requested Florida Power & Light Company (FPL) to respond to the Request for Additional Information (RAI) within 45 days of the date of the referenced letter. If FPL was unable to provide a response within 45 days, the NRC requested FPL provide a schedule for the response. Pending staff and Army Corps of Engineers’ confirmation of additional information needs, the response to RAI 6879 questions 1 through 4 are scheduled to be provided by February 15, 2013. Richard F. Orthen Principal Licensing Engineer New Nuclear Projects NNP/JB B3314 Florida Power & Light Company 700 Universe Boulevard Juno Beach, FL 33408-0420 [email protected] o(561) 691-7512

Upload: others

Post on 05-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2012/12/14 Turkey Point COL Hearing - FPL Letter L-2012-441 … · Attachments: L-2012-441 Dated 14DEC12 RAI Ltr 121114 eRAI 6879 Rev 0 Response Schedule.pdf U.S. Nuclear Regulatory

1

PMTurkeyCOLPEm Resource

From: Orthen, Richard [[email protected]]Sent: Friday, December 14, 2012 11:45 AMTo: Williamson, Alicia; Matthews, David; Maher, William; Comar, Manny; Stewart, Scott; McCree,

Victor; Megan ClouserCc: 'Anthony M Sicari ([email protected])'; 'Bob Yamrus ([email protected])';

Bortone, Pilar; Brown, Alison; Burski, Raymond; CHILDRESS, ELWOOD; Davidson, Angela; Mothena, Don; 'Douglas Kalinousky ([email protected])'; Franzone, Steve; Hamrick, Steven; Jacobs, Paul; '[email protected]'; Fazio, Joseph; 'Julius Isaac ([email protected])'; Madden, George; Magalhaes, Jose; Dryden, Mark; Mccool, Terry; Jordan, Michael; Murphy, Stella; Nicholson, Larry; Orthen, Richard; Petro, James; Raffenberg, Matthew; Reynolds, Mike; 'Ronald Anstey ([email protected])'; Scroggs, Steven; Mihalakea, Stavroula; Tomonto, Bob; Turbak, Michael; Weis, Rick; Winfield, Nadine; Proctor jr., Kennard; Kyle Turner; 'Karl Bullock'; 'Frank Matthews'; 'Douglas J. Schlagel, P.E., CHMM'; 'Susan Smillie'

Subject: FPL Letter L-2012-441 Dated 14DEC12: Schedule for Response to NRC RAI Letter 121114 (eRAI 6879) Alternative Site Selection

Attachments: L-2012-441 Dated 14DEC12 RAI Ltr 121114 eRAI 6879 Rev 0 Response Schedule.pdf

U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555-0001

Re: Florida Power & Light Company Proposed Turkey Point Units 6 and 7 Docket Nos. 52-040 and 52-041 Schedule for Response to NRC Request for Additional Information Letter 121114 (eRAI 6879) Related to ESRP Section 9.3.1 Alternative Site Selection

Reference:

NRC Letter to FPL dated November 14, 2012, Environmental Request for Additional Information Letter 121114 Related to Environmental Standard Review Plan Section 9.3.1, Alternative Site Selection, for the Combined License Application Review for Turkey Point Units 6 and 7

The Nuclear Regulatory Commission (NRC) requested Florida Power & Light Company (FPL) to respond to the Request for Additional Information (RAI) within 45 days of the date of the referenced letter. If FPL was unable to provide a response within 45 days, the NRC requested FPL provide a schedule for the response. Pending staff and Army Corps of Engineers’ confirmation of additional information needs, the response to RAI 6879 questions 1 through 4 are scheduled to be provided by February 15, 2013. Richard F. Orthen Principal Licensing Engineer New Nuclear Projects NNP/JB B3314 Florida Power & Light Company 700 Universe Boulevard Juno Beach, FL 33408-0420 [email protected] o(561) 691-7512

Page 2: 2012/12/14 Turkey Point COL Hearing - FPL Letter L-2012-441 … · Attachments: L-2012-441 Dated 14DEC12 RAI Ltr 121114 eRAI 6879 Rev 0 Response Schedule.pdf U.S. Nuclear Regulatory

Hearing Identifier: TurkeyPoint_COL_Public Email Number: 740 Mail Envelope Properties (AC64FC620563494A9FBAD712DBEE5670013A86) Subject: FPL Letter L-2012-441 Dated 14DEC12: Schedule for Response to NRC RAI Letter 121114 (eRAI 6879) Alternative Site Selection Sent Date: 12/14/2012 11:45:04 AM Received Date: 12/14/2012 11:45:16 AM From: Orthen, Richard Created By: [email protected] Recipients: "'Anthony M Sicari ([email protected])'" <[email protected]> Tracking Status: None "'Bob Yamrus ([email protected])'" <[email protected]> Tracking Status: None "Bortone, Pilar" <[email protected]> Tracking Status: None "Brown, Alison" <[email protected]> Tracking Status: None "Burski, Raymond" <[email protected]> Tracking Status: None "CHILDRESS, ELWOOD" <[email protected]> Tracking Status: None "Davidson, Angela" <[email protected]> Tracking Status: None "Mothena, Don" <[email protected]> Tracking Status: None "'Douglas Kalinousky ([email protected])'" <[email protected]> Tracking Status: None "Franzone, Steve" <[email protected]> Tracking Status: None "Hamrick, Steven" <[email protected]> Tracking Status: None "Jacobs, Paul" <[email protected]> Tracking Status: None "'[email protected]'" <[email protected]> Tracking Status: None "Fazio, Joseph" <[email protected]> Tracking Status: None "'Julius Isaac ([email protected])'" <[email protected]> Tracking Status: None "Madden, George" <[email protected]> Tracking Status: None "Magalhaes, Jose" <[email protected]> Tracking Status: None "Dryden, Mark" <[email protected]> Tracking Status: None "Mccool, Terry" <[email protected]> Tracking Status: None "Jordan, Michael" <[email protected]> Tracking Status: None

Page 3: 2012/12/14 Turkey Point COL Hearing - FPL Letter L-2012-441 … · Attachments: L-2012-441 Dated 14DEC12 RAI Ltr 121114 eRAI 6879 Rev 0 Response Schedule.pdf U.S. Nuclear Regulatory

"Murphy, Stella" <[email protected]> Tracking Status: None "Nicholson, Larry" <[email protected]> Tracking Status: None "Orthen, Richard" <[email protected]> Tracking Status: None "Petro, James" <[email protected]> Tracking Status: None "Raffenberg, Matthew" <[email protected]> Tracking Status: None "Reynolds, Mike" <[email protected]> Tracking Status: None "'Ronald Anstey ([email protected])'" <[email protected]> Tracking Status: None "Scroggs, Steven" <[email protected]> Tracking Status: None "Mihalakea, Stavroula" <[email protected]> Tracking Status: None "Tomonto, Bob" <[email protected]> Tracking Status: None "Turbak, Michael" <[email protected]> Tracking Status: None "Weis, Rick" <[email protected]> Tracking Status: None "Winfield, Nadine" <[email protected]> Tracking Status: None "Proctor jr., Kennard" <[email protected]> Tracking Status: None "Kyle Turner" <[email protected]> Tracking Status: None "'Karl Bullock'" <[email protected]> Tracking Status: None "'Frank Matthews'" <[email protected]> Tracking Status: None "'Douglas J. Schlagel, P.E., CHMM'" <[email protected]> Tracking Status: None "'Susan Smillie'" <[email protected]> Tracking Status: None "Williamson, Alicia" <[email protected]> Tracking Status: None "Matthews, David" <[email protected]> Tracking Status: None "Maher, William" <[email protected]> Tracking Status: None "Comar, Manny" <[email protected]> Tracking Status: None "Stewart, Scott" <[email protected]> Tracking Status: None "McCree, Victor" <[email protected]> Tracking Status: None "Megan Clouser" <[email protected]> Tracking Status: None Post Office: GOXSA1707.fplu.fpl.com Files Size Date & Time

Page 4: 2012/12/14 Turkey Point COL Hearing - FPL Letter L-2012-441 … · Attachments: L-2012-441 Dated 14DEC12 RAI Ltr 121114 eRAI 6879 Rev 0 Response Schedule.pdf U.S. Nuclear Regulatory

MESSAGE 1403 12/14/2012 11:45:16 AM L-2012-441 Dated 14DEC12 RAI Ltr 121114 eRAI 6879 Rev 0 Response Schedule.pdf 235210 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: Recipients Received: