2013 wind conference. transmission service study process steve purdy
TRANSCRIPT
2013 Wind Conference
Transmission Service Study Process
Steve Purdy
Transmission Service
• Transmission Service Reservation (TSR) reserves a specific amount of – capacity in megawatts (MW)
– across a specific transmission system path
– for a given timeframe
• A Transmission Service Agreement (TSA) is a – legal contract between the customer and SPP
– filed with the Federal Energy Regulatory Commission (FERC)
– publicly available from FERC or SPP website 3
Transmission Service Parameters
• Term– Short-term (hourly, daily, weekly, monthly)
– Long-term (yearly)
• Firmness (priority)– Firm
– Non-Firm
• Class– Network (“NITS”)
– Point-to-Point (“PTP”)
4
Network and Point-to-Point
• NITS service is charged a cost based on the customer’s “load-ratio share”, or the customer’s load as a percentage of SPP’s total network load– Network Load
– Network Resources
• PTP service is charged based on the amount of reserved capacity and the path
• Designated Resources serve any load within the SPP region– Network Resources serve specifically Network Load
5
• First-come, first-served
• Short-term– SPP Operations
– AFC (Available Flowgate Capacity) process
• Long-term – SPP Engineering
– Study Process
Evaluation of Transmission Service Requests
6
Study Processes for LT Transmission Service
7
Aggregate Study
Attachment Z1
Aggregate Study
Attachment Z1
Delivery Point Transfer Study
Attachment AR
Delivery Point Transfer Study
Attachment AR
Delivery Point Addition Study
Attachment AQ
Delivery Point Addition Study
Attachment AQ
Transfer of an existing delivery
point from one SPP Network Customer
to another SPP Network Customer
All new PTP requests and re-directs, all requests to designate new resources, any other requests that
don’t fit one of the other processes
New network delivery points, facility
modifications to existing delivery points, and new “block” load additions to existing delivery points
Feb - MayOct - Jan June - Sept
Aggregate Study Process Open Seasons
• All long-term transmission service requests submitted within a 4-month “open season” are aggregated for purposes of evaluation
• Three aggregate studies are started each year
8
Aggregate Study is an iterative process that continues until no customers withdraw
Open Season
(4 months)
Open Season
(4 months)
Facilities Study
(60 days)
Facilities Study
(60 days)
Letter of Intent Response Period
(15 days)
Letter of Intent Response Period
(15 days)
Restudy Needed
?
Restudy Needed
?
Write Service
Agreement
Write Service
Agreement
YESYES
NONO
Aggregate Study Process
9
10
Model Build
Contingency Scan
Constraint Analysis
Cost Allocation
28 Models•7 Seasons: Years 1, 2, 5 Summer/Winter peak; Year 10 Summer peak•2 Cases: Base and Transfer•2 Scenarios: Projected Dispatch; Contractual Dispatch
Contingencies and Monitored Elements•N-1 Facilities in SPP•Flowgates for First-Tier areas and beyond
Identify Upgrades•Least-cost Solution•Utilize expansion-plan upgrades where possible
Attachment J, Z1, and Z2•Allocate Upgrade Costs by Flow Impact, including Crediting•Re-dispatch Calculation
Aggregate Facilities Study Stages
NPPDNPPD
AEPAEP
NPPDNPPD
OPPDOPPD
KCPLKCPL
SUNCSUNC WRWR
WFECWFEC OKGEOKGE
11
AEPAEPDecrease Generation
Increase Generation
Aggregate Study ProcessMISO
AECI
100 MW
SPP
Aggregate Study Process
• Upgrade Costs– Transmission System upgrades are determined for the entire
aggregate group of requests
– Upgrade costs are allocated to each request, based on its positive MW impact on the upgrade
– The MW impact must meet at least a 3% Transfer Distribution Factor (TDF) to be allocated to a request
• Study Costs– Study costs are allocated to all requests in the first study iteration
– Subsequent re-study costs are allocated to the withdrawing customer that drives the need for the re-study
12
Upgrade Funding for Service Upgrades• Designated Resources
– Base Plan “Highway/Byway” Safe Harbor Cost Limit of $180,000/MW
Qualifications
– 5-year term– Designated Resources ≤ 125% Designated Loads– Wind Resources ≤ 20% Designated Loads
– Excess = Directly Assigned Upgrade Costs (“And” Charge)
– Waiver Process
• PTP service – PTP revenue
– Excess = Directly Assigned Upgrade Costs (“Or” Charge)
13
Documents Posted on SPP OASIS
14
Documents Posted on SPP OASIS
15
Informational Documents
SPP Aggregate Study Email Exploder
16
Frequently-Asked Questions
• What is a Letter of Credit and when do I have to provide it?– Financial Instrument provided to SPP to cover the cost
of upgrades in case of customer default
– Typically 1-2% of the amount of the LOC
– Required prior to confirmation of service
• Can I request to be a Designated Resource for a Network Service Customer?– Only the Network Customer can request to designate a
new resource
17
Frequently-Asked Questions
• What are the steps in finalizing service?– SPP sends email to customer with instructions
– Customer updates OASIS request as needed
– Customer provides documentation as needed Attestation for Designated Resources
Re-dispatch Agreements
Letter of Credit
– SPP accepts OASIS request
– Customer confirms OASIS request
– SPP tenders service agreement18
Current Study Queue
StudyCurrently
Active Iteration
Due DateRequests Currently in Study
MW Currently in
Study
Currently Posted Study
Date Posted
2011-AG2 AFS-10 LOI 6/8/2013 17 1,252 AFS-9 3/13/2013
2011-AG3 AFS-9 7/15/2013 26 2,069 AFS-8 5/1/2013
2012-AG1 AFS-4 10/17/2013* 44 2,870 AFS-3 4/5/2013
2012-AG2 AFS-5 9/15/2013* 40 4,756 AFS-4 3/4/2013
2012-AG3 AFS-4 7/8/2013 49 6,435 AFS-3 4/24/2013
2013-AG1 AFS-2 6/17/2013 57 4,584 AFS-1 4/3/2013
2013-AG2 Open Season ends 5/31/2013
Total 233 21,966
19
As of May 30, 2013
Retract requests outside the parameters
Retract requests outside the parameters
Open SeasonOpen
Season
Aggregate Facilities
Study
Aggregate Facilities
Study
Tender Service
Agreements
Tender Service
Agreements
105 Days
Day 1 105
Overview of the Proposed Process
Feb 1Example Dates
Remove requests outside
parameters from analysis
Remove requests outside
parameters from analysis
Aggregate Facilities
Study Agreement
Aggregate Facilities
Study Agreement
Accept/Confirm all requests
within parameters
Accept/Confirm all requests
within parameters
June 1
Process continues without customer intervention
until all remaining requests are within the specified parameters
Process continues without customer intervention
until all remaining requests are within the specified parameters
1. Customer defines maximum acceptable directly-assigned upgrade cost & 3rd party upgrade cost estimates
2. Customer defines acceptable deferred start date
3. Customer defines acceptable re-dispatch criteria
4. Execute study agmt. with obligation to take service.
5. Submit attestation for DR requests
1. Customer defines maximum acceptable directly-assigned upgrade cost & 3rd party upgrade cost estimates
2. Customer defines acceptable deferred start date
3. Customer defines acceptable re-dispatch criteria
4. Execute study agmt. with obligation to take service.
5. Submit attestation for DR requests
Prohibit “mutually-exclusive” requestsProhibit “mutually-exclusive” requests
Post study results with cost estimates
for all requests, including removed
Post study results with cost estimates
for all requests, including removed
Questions