  • 8/13/2019 20131113 Group Meeting (Shanshan)

    1/18

    Shanshan BU

    Oct 2013

    Comparison Study of

    Green Building Design

    &

    Green Retrofit Design

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    2/18

    Contents

    Introduction: Sustainable Design1

    2

    BIM & MACES3

    Discussion4

    Green Building Design (New Build)Green Retrofit Design (Existing)

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    3/18

    Sustainable Design

    Green Building Design(GBD)

    Sustainable DesignGreen Building Design VS

    Green Retrofit Design

    Green Retrofit Design(GRD)

    Purpose to eliminate negative

    environmental impact completely

    through skillful, sensitive design

    (McLennan, 2004)

    Green building(also known as green

    constructionor sustainable building)

    refers to a structure and using process

    that is environmentally responsible and

    resource-efficient throughout a buildingslife-cycle: from siting to design,

    construction, operation, maintenance,

    renovation, and demolition. This requires

    close cooperation of the design team,

    the architects, the engineers, and the

    client at all project stages (EPA, 2012).

    GR refer to incremental

    improvements

    to the building fabric and systems

    with the primary intentionof

    improving energy efficiency and

    reducing carbon emissions(Rhoads,

    2010).This definition excludes disruptive

    refurbishment that would require

    the building to be vacated for

    an extended time, behavioural

    training programmes and

    space rationalisation or utilisation.

    Green Building and Green Retrofit definitions

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    4/18

    Research Objectives

    Formulation of userrequirements and

    functionalspecifications

    Objective 1

    Proposemethodologies fordeterminingeffective solutionsin the design offunctions andscheme selections

    Objective 2 Implementation theproposed

    framework with theintelligent agentsand webtechnologies

    Objective 3

    Test and evaluationof the computerprototypes

    Objective 4

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    5/18

    Strategies towards green retrofitting

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    6/18

    Green Building Standards

    Green Building evaluation standard in China

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    7/18

    Green Retrofit Standards (GeneralComparison)

    Figure 3. Credit weighting for Green

    Retrofits existing building

    (Source: BEAM Plus Existing Building

    Version 1.2 2012/7, HKGBC)

    Figure 2. General comparison of green standards(Lee, 2008)

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    8/18

    GRD Process in generic level

    Define Corporate Retrofit Goals

    TDesignate Roles & Responsibilitiesx Prioritize Building Portfolio

    A Green Financing Arrangement

    Select Appropriate Technology

    GRD GenericProcess

    GRD Process before delivery

    Figure 4. Green Retrofit Process (Source: Low Carbon Retrofit Toolkit)

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    9/18

    GRD Process in project level

    Figure 5 Green Retrofit Design Process in project level (Source from FCM)

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    10/18

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    11/18

    GBD vs GRD

    TEXT TEXT TEXT TEXT

    Standpoint GBD model BIM facilitated GRD modelCommunicative intent

    (semiotics)

    To site study and document the information from pre-

    design, construction, post-design

    (to extend the project ideas for the realisation)

    To standardise data structure used for the exchange of

    building information

    (to specify data structures for the information exchange)

    Authors

    (sender)Owner, Architects, & Engineers & , Speciality Consultant

    (A&E&S Group) Contractors

    Owner, User Group, A&E&S Group Public bodies,

    Contractors

    Audience

    (receiver)Energy analyst to study potential financial and

    environmental values of energy efficiency

    The roles in the projects have different professional

    backgrounds. (Cerovsek, 2011) Vendors of software

    presenting the process maps, function and behaviour of

    buildings.

    Authoring environment

    (encoder)Capture software include ImageModeler, Project

    Photofly, Global Link, Pictometry Online and PKNail

    Silo energy analysis tools such as Ecotect, Project

    Vasari, VE-Pro, Energy Plus, DOE2, TRNSYS with design

    optimization from aspects Building Orientation and

    Shape, Rational Planning Space and Control Shape

    Coefficient, Daylighting design etc.

    BIM tools software packages with GBS (Green Building

    Studio), Ecotect, Project Vasari, VE-Pro, Energy Plus,

    DOE2, TRNSYS these well- developed energy analysis

    tools. Design-Design (DD) as-design Model, Design-

    Construction (DC) as-construction Model and Design-

    Operations (DO) as-built Model are created.

    Modelling constructs

    (code)Calibration process to optimize model and measure

    parameters to contribute the simulation for providing

    more accurate estimation of annual cost saving

    associated with DCV (Demand-controlled Ventilation)

    (Lawrence, 2007)

    High level ontological constructs parametric 3D elements

    and components of real-world counterparts. (Cerovsek,

    2011)

    Modelling result

    (message)Actual energy conservation results and systems energy

    performance and economics to individuals competence

    (ASHRAE, 2010) in model views, elements, materials

    Non-linguistic data structures for the information states

    type of building elements and the components based on

    the design platform. (Cerovsek, 2011)

    Message formatting

    (encoding)in the form of gbXML, for the integration of BIM and

    Building Performance Analysis Software, IFC, ifcXML ,ecoXML, IDMxml (Welle, Rogers, & Fischer, 2012)

    Native/open model formats: rvt, pln, ifc, cis, xml, pdf,

    for schema exp, owl, xsd (Cerovsek, 2011)

    Table 1 Comparison of the roles in Green Building Design and Green Retrofit Design in generic level

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    12/18

    BIM

    2005~now

    1993~1995

    1985~mid1990

    1970

    Parametric Object Modeling

    Assembling Modeling

    CAD Platform

    Parametric Solid modeling

    Milestones for technology development in BIM would consider to be taken places in between time of 1970, 1985,

    1993-1995, end of 1990s until now (Moum, 2010).

    As early as 1970, according to Howard and Bjork, as product modelling was once introduced.

    Then since 1985 to mid-1990s, came with ISO (Standard for the Exchange of Product Data) in the application of

    some European and German research projects.

    From 1993 to 1995, after gaining the projects experiences from the COMBI, the industry consortium IAI

    (International Alliance for Interoperability) took over the AEC industry for the product modelling standardization.

    Finnish research activities including VERA programme in 2006 were in good effort in developing IAI then the well-know IFC (Industry Foundation Classes).

    AIA introduced the Brand BuildingSMART in June 2005 for integrating technologies 3D object-based modelling and

    BIM in the AEC industry.

    Figure 7. Design modeling development (Source: Eastman, 2011)

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    13/18

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    14/18

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    15/18

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    16/18

    Case Study of Festival Walk

    Negotiation with the owner

    Energy Saving Analysis and Retrofitting

    increase with frequencyconverter blower

    a new draught

    fanon the top

    optimize

    the control

    strategy,

    change to

    cascade

    control

    set unify

    supply air

    temperature value

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    17/18

    Case Study of Festival Walk

    Festival Walk Air Conditioning Retrofit Project

  • 8/13/2019 20131113 Group Meeting (Shanshan)

    18/18