www.energy.gov/EM 1
Environmental Management Cleanup Program Performance Measures
FY 2015 Actuals, FY 2016 Targets Rich Olsen
Planning Analyst DOE-Savannah River
Citizens Advisory Board
March 29, 2016
![Page 2: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/2.jpg)
www.energy.gov/EM 2
Purpose
• Fulfill a Strategic & Legacy Management (S&LM) Committee Work Plan requirement to periodically provide Environmental Management (EM) performance updates.
- Review Fiscal Year 2015 actual performance results
- Provide targets for Fiscal Year 2016 & actuals through January
![Page 3: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/3.jpg)
www.energy.gov/EM 3
SRS Cleanup Program - Background
Sept. 23, 1949
June 12, 1950
April 1, 1989
August 1, 2008
June 1, 2009
• The EM Cleanup Program for the SRS started in the 1990’s.
• Performance Measures have been developed to track
progress towards end state targets.
![Page 4: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/4.jpg)
www.energy.gov/EM 4
SRS Cleanup Program – Major Areas
Radioactive Liquid Waste
Nuclear Materials
Soil, Water
& Facilities
Solid Waste
Process Low
Level Component (Saltstone)
Vitrify Highly Radioactive Component
Tank Closures
Mixed & Low Level Waste
Transuranic (TRU) Waste
Spent Nuclear Fuel Receipt, Storage
& Disposition
Nuclear Materials
Disposition
Waste Site Remediation
Facilities Deactivation &
Decommission
![Page 5: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/5.jpg)
www.energy.gov/EM 5
SRS Cleanup Program
Located on the Savannah River, in Aiken and Barnwell counties
in South Carolina
Chosen for its location, chemistry, land quality,
soil characterization, and construction costs
“ How did we do in FY 2015 ? ”
Answer: Continued Progress but with Challenges
![Page 6: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/6.jpg)
www.energy.gov/EM 6
FY15 Challenges
Located on the Savannah River, in Aiken and Barnwell counties
in South Carolina
Chosen for its location, chemistry, land quality,
soil characterization, and construction costs
• Temporary Closing of Waste Isolation Pilot Plant (WIPP) - Delay of Transuranic Waste (TRU) shipments • Higher than expected level of Mercury in Liquid Waste - Impacted operations of Saltstone Facility and Defense Waste Processing Facility (DWPF) • Antifoam issue in Defense Waste Processing Facility (DWPF) - Impacted Canister production and ARP/MCU operations • HB Line Agitator Event and Operational Pause - Impacted operations of Nuclear Materials
![Page 7: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/7.jpg)
www.energy.gov/EM 7
Highlights of FY 2015 SRS Cleanup Program
Located on the Savannah River, in Aiken and Barnwell counties
in South Carolina
Chosen for its location, chemistry, land quality,
soil characterization, and construction costs
• Vitrified 93 Canisters of Radioactive Liquid Waste
• Completed operational closure of Liquid Waste Tank (Tank 16)
• Spent Nuclear Fuel: Continued Dissolution of Foreign & Domestic Research Reactor fuel for uranium recovery & completed L-Basin modifications for acceptance of Canadian fuel receipts
• Prepared Plutonium for Disposition
• Continued receipt, safe storage and shipment of Nuclear Materials, including Spent Nuclear Fuel
• Significant progress towards closure of the D Area Ash Basin
• Upgrades to Site Infrastructure (Roof Replacements, Telephone System, Laboratory Facilities)
• Met 100% of FY 2015 FAA & RCRA Regulatory Milestones
![Page 8: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/8.jpg)
www.energy.gov/EM 8
Liquid Waste: Vitrification Process
Canister Production
*Based on System Plan Rev 19
Performance
Measure
Unit of
Measure
Target FY15
Actual FY15
Target FY16
Jan YTD Actuals
FY16
Cum To
Date
End
State*
%
Compl.
Vitrify Insoluble Waste (Sludge)
Canisters Produced 156 93 150 41 4,011 8,582 46.7%
![Page 9: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/9.jpg)
www.energy.gov/EM 9
Liquid Waste: Saltstone Processing
Located on the Savannah River, in Aiken and Barnwell counties
in South Carolina
Performance
Measure
Unit of
Measure
Target FY15
Actual FY15
Target FY16
Jan YTD Actuals
FY16
Cum To
Date
End
State*
%
Compl.
Process Salt Solution
K Gallons Processed 1,200 828 1,500 167 10,788 152,743 7.1%
Saltstone Disposal Unit (SDU-6) Saltstone Production Facility
* Based on System Plan Rev 19
![Page 10: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/10.jpg)
www.energy.gov/EM 10
Liquid Waste: Tank Closure
Tank 12 Grouting
* Based on System Plan Rev 19
Performance
Measure
Unit of
Measure
Target FY15
Actual FY15
Target FY16
Jan YTD Actuals
FY16
Cum To
Date
End
State*
%
Compl.
Close Tanks: Old Style Tanks Closed 1 1 1 0 7 24 29%
Close Tanks: New Style Tanks Closed 0 0 0 0 0 27 0%
Tank 12 to be operationally
Closed in FY16
![Page 11: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/11.jpg)
www.energy.gov/EM 11
Solid Waste Disposal: Transuranic Waste
Transuranic Waste (TRU) Shipment to WIPP
Note: WIPP Shipments Temporarily Halted
Performance
Measure
Unit of
Measure
Target FY15
Actual FY15
Target FY16
Jan YTD Actuals
FY16
Cum To
Date
End State
%
Compl.
TRU- Legacy Shipped (in storage prior 2009)
Cubic Meters 0 0 0 0 10,445 11,062 95%
TRU- Newly Generated Shipped
Cubic Meters 0 0 0 0 177 TBD Ongoing
![Page 12: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/12.jpg)
www.energy.gov/EM 12
Solid Waste Disposal: Mixed & Low Level Waste
Low Level Waste (LLW) New Trench - On Site Mixed Waste Shipment to Utah
* Accumulation of M&LL not to exceed 400 Cu Meters at anytime
Performance
Measure
Unit of
Measure
Target FY15
Actual FY15
Target FY16
Jan YTD Actuals
FY16
Cum To
Date
End State
%
Compl.
M&LL-Legacy (Prior to April 2008)
Cubic Meters - - - - 103,171 103,171 100%
M&LL-Newly Generated Cubic Meters < 400* Met < 400* Met < 400 < 400 Ongoing
![Page 13: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/13.jpg)
www.energy.gov/EM 13
Spent Nuclear Fuel Receipt & Storage
Spent Nuclear Fuel (SNF) Bundle stored in L- Basin
Performance Measure
Unit of Measure
EOY Actual FY15
EOY Target FY16
Jan YTD Actuals
FY16
End State
L- Basin Additions: New Receipts Bundles 4 NA* 21 -
L-Basin Removals : Packaged for Transfer to H Canyon Bundles 109 0 0 -
L-Basin Inventory Bundles
Cores
2,960
120
NA*
0
2981
120
0
0
SNF being sent to H Canyon via 70 Ton Cask
* For security reasons targeted new receipts are not provided to the public
![Page 14: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/14.jpg)
www.energy.gov/EM 14
Nuclear Materials Management
Plutonium 3013 Type Container Spent Nuclear Fuel (SNF) Bundle placed into H-Canyon Dissolver
(1) AROD approved amounts of Material Test Reactor Bundles and HFIR Cores
Performance
Measure
Unit of
Measure
Target FY15
Actual FY15
Target FY16
Jan YTD Actual FY16
Cum To
Date
End State
%
Compl.
HEU Dissolved (SNF from L-Basin)
Bundles Cores
69 0
69 0
40 0
0 0
80 0
1,000 (1)
200 (1) 8% 0%
Plutonium Prepared for Disposition (All Paths)
Containers 20 8 0 2 177 5,600 3%
![Page 15: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/15.jpg)
www.energy.gov/EM 15
Soil, Water & Facilities
D Area Ash Project 488-2D and 488-4D
*Deactivated & Decommissioned
Performance
Measure
Unit of
Measure
Target FY15
Actual FY15
Target FY16
Jan YTD Actual FY16
Cum To
Date
End State
%
Compl.
Remediation of Waste Sites
Waste Site 0 0 0 0 402 515 78%
Facilities D&D* Facilities 0 0 0 0 289 1,127 26%
![Page 16: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/16.jpg)
www.energy.gov/EM 16
SRS Workforce - Historical
0
10000
20000
3000019
91
1993
1995
1997
1999
2001
2003
2005
2007
2009
2011
2013
2015
2017
2019
2021
2023
2025
Pers
onne
l
Savannah River Site Workforce
Actuals11,419 Dec 2015
![Page 17: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/17.jpg)
www.energy.gov/EM 17
Summary
• DOE-SR will continue to track & monitor performance measures for the key operational areas of EM cleanup operations.
• Suggestions from the CAB for any additional improvements
are welcomed.
![Page 18: 2015-2016 Performance Metrics - SRS](https://reader033.vdocuments.net/reader033/viewer/2022041802/62541b15bb55a82c8a50f325/html5/thumbnails/18.jpg)
www.energy.gov/EM 18
Acronyms
AROD Amended Record of Decision (1000 bundles + 200 HFIR Cores) ARP Actinide Removal Process D&D Deactivation & Decommission DWPF Defense Waste Processing Facility FFA Federal Facility Agreement HEU Highly Enriched Uranium LLW Low Level Waste MCU Modular Caustic Side Solvent Extraction Unit MLLW Mixed Low level Waste Pu Plutonium RCRA Resource Conservation & Recovery Act SNF Spent Nuclear Fuel SRNS Savannah River Nuclear Solutions SRE Sodium Reactor Experiment SRR Savannah River Remediation SWPF Salt Waste Processing Facility TRU Transuranic Waste WIPP Waste Isolation Pilot Plant