i
EXECUTIVE SUMMARY
1. From the 2015 Composite Annual Action Plan from the District Medium Term
Development Plan (2014-2017), the Ahafo-Ano South District Assembly
proposed to implement 122 programmes, projects and activities.
2. Out of total 122 programmes, projects and activities proposed for implementation
in the 2015 Composite Annual Action Plan, 117 representing 95.9 percent were
initiated out of which 88 (72.1%) were fully implemented. 29 programmes,
projects and activities are still on-going with average completion rate of 94.1
percent.
3. Six programmes, projects and activities representing 4.1 percent were not initiated
at all due to inadequate funding from District Assemblies Common Fund (DACF)
and District Development Facility (DDF).
4. Recommendations
Based on the challenged faced in the year, 2015, we recommend early release of
DACF and DDF to the MMDAs. This is because most of the budget allocations are
from these sources and as result their delays affect the implementation of
programmes, projects and activities in the District. In addition, provision of
adequate logistics (Vehicle) for effective monitoring and evaluation will help to
improve M&E in the District.
ii
TABLE OF CONTENTS
EXECUTIVE SUMMARY ..................................................................................................................................... i
TABLE OF CONTENTS ....................................................................................................................................... ii
LIST OF TABLES ................................................................................................................................................ iii
ACRONYMS ........................................................................................................................................................ iv
CHAPTER ONE: INTRODUCTION .................................................................................................................... 1
1.1 Introduction ............................................................................................................................... 1
1.2 Processes Involved and Difficulties Encountered ..................................................................... 1
CHAPTER TWO: MONITORING AND EVALUATION REPORT ................................................................... 2
2.1 Status of Implementation of the 2014 – 2017 DMTDP ............................................................ 2
2.2 Programmes/Projects/Activities Status of 2015 Composite Annual Action Plan ..................... 2
2.3 Update on Indicators and Targets ............................................................................................ 15
2.3.1 Thematic Area 1: Ensuring and Sustaining Macroeconomic Stability ......................... 15
2.3.2 Thematic Area 2: Enhancing Competitiveness of Ghana’s Private Sector .................. 16
2.3.3 Thematic Area 3: Accelerated Agricultural Modernization and Sustainable Natural
Resource Management ................................................................................................. 17
2.3.4 Thematic Area 4: Infrastructure and Human Settlements Development ...................... 18
2.3.5 Thematic Area 5: Human Development, Productivity and Employment ..................... 20
2.3.6 Thematic Area 6: Transparent and Accountable Governance ...................................... 24
CHAPTER THREE: INCOME AND EXPENDITURE REPORT ...................................................................... 27
3.1 Update on Funding by Sources for 2015 ................................................................................. 27
3.2 Update on Disbursements for the Year, 2015 ......................................................................... 29
CHAPTER FOUR: UPDATE ON CRITICAL DEVELOPMENT AND POVERTY ISSUES ........................... 31
4.1 National Youth Employment Agency ..................................................................................... 31
4.1.1 Challenges facing NYEA in the District ...................................................................... 31
4.1.2 Policy Recommendations ............................................................................................. 31
4.2 Ahafo-Ano South Mutual Health Insurance Scheme .............................................................. 31
4.2.1 Challenges facing Ahafo-Ano South Mutual Health Insurance Scheme ...................... 32
4.2.2 Policy Recommendations ............................................................................................. 32
4.3 Livelihood Empowerment against Poverty (LEAP) Programme ............................................ 32
4.3.1 Challenges facing LEAP Programme ........................................................................... 33
4.3.2 Policy Recommendations ............................................................................................. 33
4.4 School Feeding Programme .................................................................................................... 33
4.4.1 Challenges facing School Feeding Programme ............................................................ 34
4.4.2 Policy Recommendation ............................................................................................... 34
4.5 Sensitization Workshops on LGS Protocols (SoS, CoS, CoC, SDS, PMS, OM) .................... 34
iii
LIST OF TABLES
Table 2.1: Implementation Status of 2015 Composite Annual Action Plan ........................................... 3
Table 2.2: Summary of Indicators under Ensuring and Sustaining Macroeconomic Stability............. 16
Table 2.3: Summary of Indicators under Enhancing Competitiveness of Ghana’s Private Sector ...... 16
Table 2.4: Summary of Indicators under Accelerated Agricultural Modernization and Sustainable
Natural Resource Management ........................................................................................... 17
Table 2.5: Summary of Indicators under Infrastructure and Human Settlements Development .......... 18
Table 2.6: Summary of Indicators under Human Development, Employment and Productivity ......... 20
Table 2.7: Summary of Indicators under Transparent and Accountable Governance .......................... 24
Table 3.1: Revenue Performance for the Year, 2015 .......................................................................... 28
Table 3.2: Expenditure Pattern for Year, 2015 .................................................................................... 30
Table 4.1: Active Membership of Ahafo-Ano South Mutual Health Insurance Scheme, 2015 ........... 32
Table 4.2: Name of Communities and Beneficiaries under LEAP ....................................................... 33
Table 4.3: Number of Pupils and Schools under School Feeding Programme in the District .............. 34
iv
ACRONYMS
AAP : Annual Action Plan
AIDS : Acquired Immune Deficiency Syndrome
AASDA : Ahafo-Ano South District Assembly
AMMHIS : Ahafo-Ano South Mutual Health Insurance Scheme
BAC : Business Advisory Centre
CHPS : Community Health Planning Services
CIC : Community Information Centre
CLTS : Community Led Total Sanitation
D/A : District Assembly
DACF : District Assemblies Common Fund
DBA : District Budget Analyst
DDF : District Development Fund
DE : District Engineer
DMTDP : District Medium Term Development Plan
DPCU : District Planning Co-ordinating Unit
DPO : District Planning Officer
FBOs : Farm Based Organisations
GES : Ghana Education Service
GOG : Government of Ghana
GSGDA : Ghana Shared Growth and Development Agenda
GYEEDA : Ghana Youth Employment and Entrepreneurial Development Agency
HIV : Human Infections Virus
HR : Human Resource
ICT : Information Communication Technology
IGF : Internally Generated Funds
LEAP : Livelihood Empowerment Against Poverty
M&E : Monitoring and Evaluation
MLGRD : Ministry of Local Government and Rural Development
MOFA : Ministry Of Food and Agriculture
MSMEs : Middle Small Medium Enterprises
Na : Not Application
NHIS : National Health Insurance Scheme
PPPs : Public Private Partnership
REP : Rural Enterprise Programme
SMEs : Small Medium Enterprises
SSNIT : Social Security National Insurance Trust
STIs : Sexually Transmitted Infections
TB : Tuberculosis
TBAs : Traditional Birth Attendants
WATSAN : Water and Sanitation
1
CHAPTER ONE
INTRODUCTION
1.1 Introduction
The 2015 Annual Progress Report is the appraisal of all programmes, projects and activities
embarked upon during the year under review. It is the second year assessment of the Ghana’s
Shared Growth and Development Agenda II (2014-2017) of the Ahafo-Ano South District
Assembly.
The focus here is to find out if the targets set by the District were achieved during the period
under review. The progress report will enable the District to measure the actual performance
against the set targets. The report is also as a result of the assessment of a set of indicators
and targets adopted for monitoring and evaluating the achievements and impacts of key
policy and programme intervention executed in the year, 2015 from 1st January, 2015 to 31st
December, 2015.
1.2 Processes Involved and Difficulties Encountered
The District Planning Co-ordinating Unit (DPCU) facilitated the preparation of the 2015
Annual Progress Report with the involvement of the Decentralised Departments of the
Ahafo-Ano South District. Monitoring and Evaluation data were compiled from both primary
and secondary sources. Secondary data were compiled from the various quarterly and Annual
Reports of Departments and Agencies as well as from the District Assembly and its
substructures. The data was collated and analysed by the DPCU.
A number of difficulties were encountered in the course of aggregating the data. Among
these were:
• Inadequate logistical support and other resources for monitoring and evaluation
activities in the District and at the sub-structures levels.
• Difficulty of assessment of performance because some indicators were without
baseline to assist in setting realistic targets.
• Inconsistency in some data gathered.
• Lack of permanent vehicle for monitoring and evaluation of programmes, projects and
activities in the District.
2
CHAPTER TWO
MONITORING AND EVALUATION REPORT
2.1 Status of Implementation of the 2014 – 2017 DMTDP
In reviewing the implementation status of the 2014-2017 DMTDP within the context of the
2015 Composite Annual Action Plan, disaggregated primary and secondary data were
collected from stakeholders including Sub-District Councils, Decentralized Departments,
Agencies and Organizations and Communities in the District to assess the implementation of
the identified programmes, projects and activities outlined under the Six (6) Thematic Pillars
of the Ghana Shared Growth Development Agenda II (GSGDA II) as well as other
interventions implemented during the year. The review process took into consideration the:
• extent/levels of the implementation of proposed programmes and projects; whether
the projects were fully implemented, partially implemented or not implemented at all
and whether set objectives, targets and goals were achieved.
• reasons for any deviations in terms of implementation and set targets.
2.2 Programmes/Projects/Activities Status of 2015 Composite Annual Action Plan
Out of 122 programmes, projects and activities proposed for implementation in the 2015
Composite Annual Action Plan, 17 representing 13.9 percent were rolled over from 2014. Six
accounting for 4.1 percent were not initiated due to inadequate funding (DACF and DDF).
117 representing 95.9 percent were initiated out of which 88 forming 72.1 percent were fully
completed and 29 forming 23.8 percent were partially completed with an average completion
(overall performance) of 94.1 percent. Table 2.1 shows the level of implementation of the
2015 Composite Annual Action Plan outlined under the Six Thematic Areas of the DMTDP,
2014-2017.
3
Table 2.1: Implementation Status of 2015 Composite Annual Action Plan Objectives Programmes/ Projects/
Activities
Status of Implementation
Comments/Remarks
Fully
Implem.
On-Going Not
Implem.
%
Comp.
THEMATIC AREA 1: ENSURING AND SUSTAINING MACRO-ECONOMIC STABILITY
1. Improve
fiscal revenue
mobilisation
and
management
and improve
public
expenditure
management
Finance Department
1. Prepare and implement 1
Revenue Improvement Action
Plan, 2015(RIAP)
√ 100% Target achieved
(The RIAP, 2015 was successfully
prepared and its implementation is
on-going)
2. Organise 2 tax educational
campaigns in the District
√ 100% Target achieved
(2 tax educational campaigns were
organised to sensitise communities
to pay taxes in the District. The
attendees included 215 MSMEs
(100-Males and 115-Females). All
the 10 Area Councils were
covered)
3. Organise one Stakeholder’s
forum on 2016 Fee Fixing
Resolution
√ 100% Target achieved
(1 Stakeholder’s forum on 2016
Fee Fixing Resolution was
organised. This forum was used to
discuss extensively on the Fee
Fixing and how the payments could
be made with ease. The forum was
attended by 23 males and 18
females totaling 41 stakeholders)
4. Provide logistics
(Raincoats, Willington boats,
Torchlights and other
incentives) for revenue
collectors
√ 100% Target achieved
(Stationery and other relevant
materials were provided to 24
revenue collectors to aid in
effective revenue collection. This
benefited 9 males and 15 females)
5. Procure Value Book for
revenue mobilization
√ 100% Target achieved
(All the Value Books for the
Revenue Unit were procured for
2015. This was to aid the collection
of revenue in the District. In all 200
Value Books were procured)
6. Organise 2 training
workshops for Revenue
Collectors
√ 100% Target achieved
(The two training programmes
were organised in First and Third
Quarter of 2015 which benefitted
24 Revenue Collectors and
Commissioners (15 females and 9
males))
7. Compile and update
District Revenue Database
√ 100% Target achieved
(Data has been collected on all
activities of the informal sector in
the District in May, 2015. 1,320
small businesses in the District was
captured in 257 communities. This
was made up of 731 female’s
owners and 589 male’s owners)
8. Pay Compensation to
Established Post and Non-
Established Post
√ 100% Target achieved
(The compensation for established
and non-established employees has
all been paid for 2015. This
benefited 97 females and 54 males’
staff)
4
THEMATIC AREA 2: ENHANCING COMPETITIVENESS OF GHANA’S PRIVATE SECTOR
2. Improve
efficiency and
competitivenes
s of MSMEs
Trade, Industry and Tourism Department (Office of Departmental Head)
9. Organise 4 training
programme for women in
Local Economic Development
(Palm oil Processing, Palm
Kernel Oil Processing, Soap
Making and Gari Processing)
√ 100% Target achieved
(Four training programmes were
organised for women in Palm oil
Processing, Palm Kernel Oil
Processing, Soap Making and Gari
Processing at Kunsu and
Adugyama. This benefited about
60 females in the District)
10. Support 4 Training
Programmes for MSMEs
organised by BAC in Local
Economic Development
(Mushroom Production,
Grasscutter rearing, Gari
Processing, Palm oil
Processing, Palm Kernel Oil
Processing, Fish Farming and
Soap Making)
√ 150% Target exceeded
(Four trainings were conducted at
Kunsu and Mankranso on
Entrepreneurship, Welding &
Fabrication and Carpentry &
Joinery, Mushroom Production,
Grasscutter rearing, Gari
Processing, Palm oil Processing,
Palm Kernel Oil Processing, Fish
Farming and Soap Making. In all,
88 people participated involving 51
males and 27 females)
11. Support to District
Cooperative Office to train
Producer Groups engaged in
Local Economic Development
activities
√ 100% Target achieved
(The District Cooperative Office
was supported quarterly to train
various Producer Groups in the
District. This programme benefited
four Producer Groups totaling 52
individuals (33 males and 19
females))
3. Promote
sustainable
tourism to
preserve
historical,
cultural and
natural heritage
12. Prepare a Tourism Profile
for the District
√ 0% Target not achieved
(Lack of Funds)
THEMATIC AREA 3: ACCELERATED AGRICULTURE MODERNISATION AND SUSTAINABLE NATURAL RESOURCE MANAGEMENT
4. Develop an
effective
domestic
market
Works Department
13. Complete 1 No. Market
Shed at Mpasaaso No.2
√ 100% Target achieved
(Work is completed and
commissioned. This has benefited
the Mpasaaso No. 2 and the
surrounding communities totaling
about 2,500 – 1,500 females and
1,000 males)
Health Department (Environmental Health Unit)
14. Organise 1 market forum
for market users in the District
√ 100% Target achieved
(The market forum was at Kunsu
Market to sensitise market users on
the need to adhere to best sanitation
practices. This forum covered
about 300 people made of 130
males and 170 females)
15. Facilitate the provision of
5 litre bins at market centres
√ 400% Target exceeded
(200 litre bins have been
distributed at various locations in
the District including market
centres)
5
5. Improve
Agriculture
Financing
Agriculture Department 16. Conduct Annual Farmers'
Day in the District
√ 100% Target achieved
(The Annual Farmers’ Day was
organised at Nsuta. This was
attended all the stakeholders in the
District. About 30 awards were
presented to 30 individual farmers
made up of 10 females and 20
males)
17. Organise 4 Public
Education on consumption of
Locally Produced Foods
under Local Economic
Development
√ 100% Target achieved
(Four public education have been
organised on consumption of
Locally prepared foods. About 80
farmers 55 males and 25 females)
were involved)
18. Provide quarterly training
support in Climate Change
and Green Economy for the
District Agriculture
Department
√ 100% Target achieved
(20 Farmer Groups made up of 197
males and 134 females were
trained in Climate Change and
Green Economy in the District)
19. Support Agriculture
Extension Officers to
undertake farm visits to train
farmers in Climate Change
and Green Economy
√ 100% Target achieved
(20 Farmer Groups made up of 197
males and 134 females were visited
to ensure compliance to Climate
Change and Green Economy
activities in the District)
20. Train 200 farmers in
modern technology of farming
in Green Economy and soil
management practices
√ 161.5% Target exceeded
(323 farmers made up of 173 males
and 153 females were trained in
modern technology of farming. 24
farmers out of the whole (18 males
and 6 females) were taken on a
field trip to Amansie, a no till site
as part of the training in Green
Economy)
21. Promote and vaccinate
1,000 small ruminants (dogs,
cats, sheep and cattle) against
PPR
√ 100% Target achieved
(About 1,000 small ruminants
(dogs, cats, sheep and cattle) were
vaccinated in the District. This
benefited about 350 people – 230
males and 120 females)
6. Promote the
development of
selected cash
crops
22. Organise 4 training
programmes to educate
farmers on proper use and
handling of Agro-chemical
Inputs
√ 100% Target achieved
(20 farmer groups made up of 170
males and 153 females were
trained on proper use and handling
of Agro-chemical inputs in the
District)
7. Promote
efficient land
use and
management
systems
Disaster Prevention Department (NADMO)
23. Facilitate the planting of
100 trees along river banks
√ 40% Target not achieved
(20 Coconut Trees were planted
along River Mankran)
THEMATIC AREA 4: INFRASTRUCTURE AND HUMAN SETTLEMENTS DEVELOPMENT
8. Create and
sustain an
efficient and
effective
transport
system that
meets user
needs
Works Department
24. Reshape/Rehabilitate
30km feeder roads in the
District to promote Local
Economic Development
√ 66.7% Target achieved
(20km feeder roads were
rehabilitated on Kunsu-Saakrom,
Asudei-Bonsukrom, Amoakokrom-
Apenimade and roads)
25. Provide support to Feeder
Roads operation and
maintenance activities
√ 100% Target achieved
(The Feeder Road Unit was
supported quarterly to provide
maintenance services in the
District)
6
9. Provide
adequate, reliable
and affordable
energy to meet
the national needs and for
export
26. Procure 60 No. Electricity
Poles for Rural Electrification
Project under Electricity
Expansion Project
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
2012 District Development
Facility)
27. Facilitate the supply of
200 solar lamps for the poor
and vulnerable in the District
√ 950% Target exceeded
(Solar lamps were acquired and
distributed to 20 poor communities
benefitting about 800 people (600
males and 200 females in the
District)
10. Accelerate
the provision
of adequate,
safe and
affordable
water
28. Construct, mechanise and
rehabilitate 10 No. boreholes
in the District
√ 50% Target not achieved
(Five boreholes have been
rehabilitated with the remaining
five yet to be awarded due to the
delay in the release of 2012 District
Development Facility)
11. Accelerate
the provision
of improved
environmental
sanitation
facilities
29. Rehabilitate/Construct 10
No. Aqua Privy Public Toilets
in selected communities in the
District
√ 110% Target exceeded
(11 No. Aqua Privy Public Toilets
have been rehabilitated at Kunsu,
Fawoman, Mpasaaso No. 2,
Biemso No.1, Domeabra Soroase
and Mankranso)
30. Complete 1 No. 12-seater
APPT at Sabronum
√ 100% Target achieved
(Works completed and
commissioned)
31. Complete 1 No. 12-seater
APPT at Bonkwaso
√ 100% Target achieved
(Works completed and
commissioned)
Health Department (Environmental Health Unit)
32. Prepare 2016-2020
DESSAP for the District
√ 100% Target achieved
(2016-2020 DESSAP has prepared.
This plan captured all the water and
sanitation facilities in the District)
33. Procure Assorted Refuse
Management Equipment and
Chemical Detergents for the
Environmental Health Unit to
improve environmental
sanitation
√ 100% Target achieved
(The Assorted Refuse Management
Equipment and Chemical
Detergents for the Environmental
Health Unit was procured
throughout the year. This was used
for National Sanitation Day
exercise as well as cleansing of the
offices throughout the year)
34. Organise 2 educational
campaigns on safe handling of
food and screen 2,500
food/drinks vendors
√ 100% Target achieved
(All the 10 Areas Councils were
educated on safe handling of food. This benefitted about 2,500 food handlers
(2,000 females and 500 males)
35. Organise 2 sensitization
programmes on cholera
prevention in the District
√ 100% Target achieved
(All the 10 Areas Councils were
sensitse on cholera prevention.
This benefitted 30 communities
that is three per Area Council)
36. Organise monthly
National Sanitation Day in the
District
√ 100% Target achieved
(All the monthly National
Sanitation Day in 2015 were
successfully organised at Abesewa,
Mankranso, Wioso, Kunsu,
Asuodai)
37. Implement Community
Led Total Sanitation activities
in the District –(Sanitation
Improvement Package)
√ 100% Target achieved
(The Community Led Total
Sanitation activities were organised
in various communities to
commensurate the National
Sanitation Day)
7
38. Evacuate/Push 2 refuse
dump sites in the District
√ 100% Target achieved
(2 Refuse Dump Sites were
evacuated at Wioso and
Adugyama)
39. Fumigate the District
against diseases
√ 100% Target achieved
(All Refuse Dump Sites and Toilet
Facilities at Wioso and Mankranso
have been fumigated)
12. Improve
and accelerate
housing
delivery in the
rural areas
Physical Planning Department (Town and Country Planning Division)
40. Organise 1 Stakeholder’s
meeting on proper usage of
land in the District
√ 300% Target exceeded
(Stakeholders such as chiefs and
elders as well as community
members at Biemso, Kunsu and
Mpasaaso II were educated on
proper usage of land in their
communities)
41. Provide street names and
property addressing at
Mankranso and Kunsu
√ 60% Target not achieved
(16 Street Name Posts have been
erected with others yet to be
erected at Mankranso. However,
Kunsu street naming exercise is yet
to be implemented)
42. Prepare settlement layout
for 1 community in the
District
√ 90% Target not achieved
(Layout for Mpasaaso has
commenced with the drawings of
the Base Map completed and that
of Beposo has begun)
43. Provide support for the
T&CP Department and Works
Department to promote
housing standards, design and
construction
√ 100% Target achieved
(The Assembly supported the TCP
Department to carry out routine
inspection to educate communities
to conform to planning and
building standards in the District.
Kunsu, Biemso and Adugyama
were among the beneficiaries
communities)
THEMATIC AREA 5: HUMAN DEVELOPMENT, PRODUCTIVITY AND EMPLOYMENT
13. Increase
inclusive and
equitable access
to, and
participation in
education at all
levels
Education, Youth and Sports Department (Education Division)
44. Complete the
construction of 1 No. 3-Unit
classroom block with office,
store and 1 No. 4-seater
KVIP and urinal at
Barnorkrom (School Under
Tree)
√ 70% Target not achieved
(Lack of Funds-DACF. Project is
on-going)
45. Complete the
construction of 1 No. 3-Unit
classroom block with office,
store and 1 No. 4-seater
KVIP and urinal at Asikantia
(School Under Tree)
√ 70% Target not achieved
(Lack of Funds-DACF. Project is
on-going)
46. Complete the
construction of 1 No. 3-Unit
classroom block with office,
store and 1 No. 4-seater
KVIP and Urinal at
Mpasaaso –Nyamebekyere
(School Under Tree)
√ 100% Target achieved
(Work completed and
commissioned)
8
47. Complete 1 No. 3-Unit
classroom block with office,
store and 1 No. 4-seater aqua
privy toilet and urinal at
Nsuta-Nyamebekyere
(School Under Tree)
√ 100% Target achieved
(Work completed and
commissioned)
48. Complete the
construction of 1 No. 3-Unit
classroom block with office,
store and 1 No. 4-seater
KVIP and Urinal at
Amoakokrom (School
Under Tree)
√ 100% Target achieved
(Work completed and
commissioned)
49. Construct 1 No. 6-Unit
classroom block with office,
store and 1 No. 4-seater
KVIP and Urinal at
Sabronum
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
Social Investment Fund)
50. Construct 1 No. 3-Unit
classroom block with office,
store and 1 no. 4-seater Aqua
Privy Toilet and urinal at
Ango (School Under Tree)
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
2012 District Development
Facility)
51. Construct 1 No. 3-Unit
classroom block with office,
store and 1 no. 4-seater Aqua
Privy Toilet and urinal at
Adugyama (School Under
Tree)
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
2012 District Development
Facility)
52. Construct 1 No. 3-Unit
classroom block with office,
store and 1 No. 4-seater aqua
privy toilet and urinal at
Odoyefe (School Under
Tree)
√ 0% Target not achieved
(Lack of Funds-DACF)
53. Construct 1 No. 3-Unit
classroom block with office,
store and 1 no. 4-seater aqua
privy toilet and urinal at
Akwatiakrom (School Under Tree)
√ 0% Target not achieved
(Lack of Funds-DACF)
54. Rehabilitate 1 No. 6-unit
classroom block at Nsuta
√ 0% Target not achieved
(Lack of Funds-DACF)
55. Rehabilitate 1 No. 3-unit
classroom block at
Potrikrom
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
2012 District Development
Facility)
56. Rehabilitate 6 No. 3-unit
classroom blocks in selected
communities
√ 0% Target not achieved
(Lack of Funds-IGF)
57. Construct 1 No. 6-unit
teachers quarters with
auxiliary facilities at
Asukese
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
Social Investment Fund)
58. Complete the
construction of 1 No. 4-unit
teachers’ quarters at
Sabronum-Camp
√ 70% Target not achieved
(Lack of Funds-DACF. Project is
on-going)
9
59. Complete the
construction of 1 No. 4-unit
teachers’ quarters at Pokuase
√ 70% Target not achieved
(Lack of Funds-DACF. Project is
on-going)
60. Complete the
construction of 4 No. 4-unit
teachers quarters at Abasua,
Kunsu-Dotiem,
Aponaponoso and
Bonsukrom (Started under
Fast Track Catalytic
Initiative)
√ 70% Target not achieved
(Lack of Funds-DACF. Project is
on-going)
61. Complete the
construction of 2 No. 4-unit
teachers quarters at Adanse
Yawboadi and Barniekrom
(Started under CBRDP)
√ 70% Target not achieved
(Lack of Funds-DACF. Project is
on-going)
14. Improve
quality of
teaching and
learning
62. Supply and delivery of
550 dual desks and 150
teachers tables and chairs to
promote Girl Child
Education
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
2012 District Development
Facility)
63. Support the
implementation of School
Feeding Programme to
promote Girl Child
Education
√ 100% Target achieved
(A total of 18 schools are
benefiting from the programme. In
total 4,537 pupils made up of 2,241
boys and 2,296 girls benefitted
from it. A total of GHȼ127,487.00
was been received in 2015)
64. Provide quarterly support
to District Education Fund /
District Education Oversight
Committee (DEOC)/
SPAM/STMIE Clinic (2%)
to celebrate girl child
education week and other
girl child related activities
√ 100% Target achieved
(2% of the DACF was released to
support sensitisation drive to
promote girl child enrolment in
schools in 2015. This has so far
benefited about 1,000 females
students)
65. Provide support for
teachers at remote areas and
poor and vulnerable students
under GPEG annually (solar
lamps, uniforms, textbooks,
sanitary pads, pens &
pencils, maths set etc)
√ 100% Target achieved
(The Assembly supported the
District Education Unit under
GPEG programme to supply 3,081
school uniforms to needy girls and
boys in deprived communities in
the District. Moreover, a number of
furniture, chalks, sanitary pads and
other educational materials have
been distributed to all schools in
the District benefiting over 4,000
male students and 3,500 female
students)
66. Organise My First Day at
School for boys and girls in
the District
√ 100% Target achieved
(The activity was carried out on 8th
September, 2015 which benefited
all the schools in the 10 Circuits.
About 1,000 pupils (510 females
and 490 males) aged between 3 and
5 years benefited from programme)
67. Identify and provide
bursaries to 50 Needy
Students and to promote
especially Girl Child
Education in the District
√ 100% Target achieved
(50 students have benefited from
the programme. This benefitted 37
females and 13 males)
10
68. Organise 2 No.
literacy/quiz competitions to
promote gender competition
√ 150% Target exceeded
(Three quiz competitions have been
organised in the District in 2015.
This benefitted about 25 females
and 34 males in selected schools in
the District)
69. Organise 2 Mock
Examinations for BECE
candidates in the District
√ 100% Target achieved
(Two Mock Examinations were
conducted for the 2015 BECE
candidates. About 3,000 students
benefited (1,600 males and 1,400))
15. Provide
adequate and
disability
friendly
infrastructure
for sports in
communities
and schools
70. Facilitate the
organisation of sports
activities in the District
√ 100% Target achieved
(From 11th to 13th March 2015 and
25th& 26th June, the Assembly
supported the District Directorate
to organise sporting activities in the
District. Friendly matches among
schools, under 13 boys’ soccer
competition, under 15 girls’ soccer
competition, hand ball and netball
competition were organised for 20
Basic Schools in the District. This
benefitted 250 males and 150
females)
16. Bridge the
equity gaps in
access to health
care
Health Department (Hospital Services Unit and Birth and Death Registry Unit) 71. Facilitate the
construction of 1 No.
pediatric ward at Mankranso
Government Hospital to curb
infant mortality
√ 65% Target not achieved
(Work is on-going)
72. Complete the
construction of 1 No. CHPS
Compound at Ahwerewam
to curb maternal and infant
mortality, STIs (HIV/AIDS)
and others
√ 100% Target achieved
(Works completed and
commissioned)
73. Construct 1 No. CHPS
Compound at Bokruwa to
curb maternal and infant
mortality, STIs (HIV/AIDS)
and others
√ 60% Target not achieved
(Work is still on-going and has
reached lentil stage)
74. Construct 1 No. CHPS
Compound at Kunsu to curb
maternal and infant
mortality, STIs (HIV/AIDS)
and others
√ 70% Target not achieved
(Work is still on-going and has
reached roofing stage)
75. Construct 1 No. CHPS
Compound at Barniekrom to
curb maternal and infant
mortality, STIs (HIV/AIDS)
and others
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
2012 District Development
Facility)
76. Construct 1 No. CHPS
Compound at Pokuase to
curb maternal and infant
mortality, STIs (HIV/AIDS)
and others
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
2012 District Development
Facility)
77. Construct 1 No.
Community Clinic at Kunsu
Camp to curb maternal and
infant mortality, STIs
(HIV/AIDS) and others
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
Social Investment Fund)
11
78. Construct 1 No.
Maternity Clinic at
Fawoman to curb maternal
and infant mortality, STIs
(HIV/AIDS) and others
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
Social Investment Fund)
79. Construct 1 No. Nurses
Quarters at Sabronum to
curb maternal and infant
mortality, STIs (HIV/AIDS)
and others
√ 5% Target not achieved
(The project is yet to be awarded
due to the delay in the release of
Social Investment Fund)
80. Rehabilitate 1 No. CHPS
Compound at Adukrom to
curb maternal and infant
mortality, STIs (HIV/AIDS)
and others
√ 100% Target achieved
(Works completed and
commissioned)
17. Enhance
national
capacity for the
attainment of
lagging health
MDGs, as well
as non-
communicable
diseases (NCDs)
and Neglected
Tropical
Diseases (NTDs
81. Provide support for roll
back malaria and
immunisation(NID) in the
District
√ 100% Target achieved
(DHS was supported to undertake
facility based malaria tests and
immunisation programmes. 2,256
children (1,106 males and 1,150
females) were immunized at
Mankranso, Pokukrom, Mpasaaso,
Wioso, Sabronum and Biemso.
Mosquito Net Facilities have
distributed throughout the 267
communities in the District)
82. Train and motivate 100
Traditional Birth Attendants
(TBAs) and Community
Volunteers to improve
maternal and infant health,
STIs (HIV/AIDS) and others
√ 100% Target achieved
(100 TBAs and Community
Volunteers (1000 females) were
trained and provided with the
necessary logistics for their
assistance in improving maternal
and infant health)
18. Ensure the
reduction of
new HIV and
AIDS/STIs
infections,
especially
among the
vulnerable
groups
83. Provide monthly support
for the co-ordination and
management of HIV/AIDS
programmes in the District
√ 100% Target achieved
(The monthly support for the co-
ordination and management of
HIV/AIDS programmes was
provided. This helped to improve
HIV/AIDS activities in the District)
84. Organise quarterly
monitoring and evaluation of
HIV/AIDS programmes in
the District
√ 100% Target achieved
(The quarterly monitoring and
evaluation of HIV/AIDS
programmes were successfully
organised throughout the year. In
all 10 health facilities were visited)
85. Organise 2 Educational
Campaigns on HIV Testing
and Counseling (HTC)
√ 100% Target achieved
(Two educational campaigns on
HIV Testing and Counseling were
organised at Mankranso and
Adugyama. The record shows that
about 100 males and 85 females
went to the various health facilities
to test for their status)
86. Organise 2 Educational
Campaigns on causes and
impacts of HIV/AIDS and
other STIs under Behaviour
Change Communication in
the District
√ 100% Target achieved
(Two educational campaigns on
causes and impacts of HIV/AIDS
were organised at Sabronum and
Kunsu. About 100 males and 120
females benefitted from the
programme in the two
communities)
12
87. Provide all year round
support for PLWHIV/OVC
√ 100% Target achieved
(All year round support was
provided to PLWHIV/OVC in the
District. About 118 HIV/AIDS
victims in the District made up of
87 females and 31 males were
supported throughout the year)
88. Organise annual
stakeholder’s workshop on
HIV/AIDS and other STIs
√ 100% Target achieved
(The Annual Stakeholder’s
Workshop on HIV/AIDS was
organised at Mankranso on the 11th
December, 2015. The workshop
was attended by 10 male and 4
female’s participants)
19. Protect
children against
violence, abuse
and exploitation
Social Welfare and Community Development Department
Social Welfare Division
89. Sensitise 5 communities
on the dangers and effects of
Child Labour especially in
cocoa growing areas
√ 100% Target achieved
(5 Communities (Pokuase,
Mmehame, Afresene Camp,
Bonkrom and Yawboadi) were
sensitized on the dangers and
effects of Child Labour. About 300
males and 250 females
participated)
20. Develop
targeted
economic and
social
interventions for
vulnerable and
marginalized
groups
90. Facilitate the
employment of 100 youths
under NYA
√ 0% Target not achieved
(National Youth Agency yet to be
commenced in the District)
91. Provide all year round
support to the vulnerable and
marginalized people under
LEAP
√ 100% Target achieved
(Four payments have been made to
LEAP beneficiaries (873
households; 1,327 females and 845
males)
92. Facilitate the registration
of 100 poor and
marginalised on NHIS under
LEAP
√ 100% Target not achieved
(100 poor and marginalized LEAP
beneficiaries (28 males and 72
females were registered with
NHIS)
93. Train and Sponsor 8
PWDs in Income Generating
Activities to promote Local
Economic Development
√ 100% Target achieved
(This was done under the 2%
Disability Fund where 5 males and
3 females PWDs benefited from
the package)
94. Provide all year round
support for People with
Disabilities in the District
(2%)
√ 100% Target achieved
(This was done under the 2%
Disability Fund for 40 males and
60 females)
Community Development Division
95. Train 100 Females in
Income Generating
Activities to promote Local
Economic Development
(Gender Mainstreaming)
√ 100% Target achieved
(100 females were trained in
various activities including pastries
and soap making in the District)
96. Organise review
meetings especially on issues
affecting women
√ 100% Target achieved
(Four review meetings were
organised throughout the year. This
benefitted about 320 women)
13
21. Reduce
spatial
development
disparities
among different
ecological zones
across the
country
97. Organise stakeholders
meeting for 20 communities
to discuss community
participation in development
project for them to undertake
Community Initiated
Projects and Programmes
√ 100% Target achieved
(Under this programme, 20
communities were sensitised to
initiate self-help projects and
programmes through community
harvest and other interventions. In
support of this, every quarter the
District procured building materials
to support communities that have
initiated projects)
THEMATIC AREA 6: TRANSPARENT AND ACCOUNTABLE GOVERNANCE
22. Ensure
effective
implementation
of the
decentralisation
policy and
programmes and
promote and
improve the
efficiency and
effectiveness of
performance in
the public and
civil services
Central Administration Department (Administration–Assembly Office)
98. Provide support to the 10
Area Councils
√ 80% Target not achieved
(Eight out of 10 Area Councils
were supported with logistics and
ceded revenue. The logistics were
in a form training and stationery)
99. Organise 2 training
workshops for
Assembly/Unit Committee
and Area Council Members
√ 100% Target not achieved
(One training workshop has been
organised for the Assembly
members and Unit Committee in
Kumasi at the TUC conference
room. The training benefited 71
Assembly members (six females
and 65 males)
100. Organise 4 No.
Workshops for women on
participatory decision
making process
√ 100% Target achieved
(Four workshops have been
organised for 80 women. The
workshops were used to discuss
how women could actively involve
in the decision making process at
family, governance, employment
and other gender related issues)
101. Organise 4 Training
Workshops and procure
office equipment for offices
of the District Assembly
under DDF 2012
√ 100% Target achieved
(Four training programmes were
organised for staff and departments
in the Assembly. This benefited all
the 10 Departments totaling 20
female and 38 male’s workers.
Swivel Chairs, printers and other
equipment were purchased for
DPCU secretariat)
102. Provide all year round
support for capacity building
programmes under DACF
√ 100% Target achieved
(Staff have been supported to
participate in various capacity
building programmes throughout
the year. This benefited about 50
staff (20 females and 30 males))
103. Provide support for the
Aged on Senior Citizenship
Day (Annual Get-together)
√ 100% Target achieved
(The Senior Citizenship Day was
organised on 1st July, 2015. The
invited retirees were screen
medically and shared experiences
with all participants. In all, about
70 males and 30 females benefited
from the programme)
104. Organise Monitoring
and Evaluation of all
programmes and projects
quarterly
√ 100% Target achieved (All completed and on-going projects and programmes were monitored and
evaluated by the District Monitoring
Team and DPCU. In all 122
programmes, projects and activities
were inspected for the year)
14
105. Provide support to
social and economic
development activities under
Social Investment Fund
(IRDP)
√ 100% Target achieved
(The Assembly has paid 100% of
the counterpart funding to SIF
totaling GH128,000.00)
106. Pay all allowances (fuel,
travelling, presiding member,
traditional authorities, donations,
overtime for drivers,
refreshment, commission
collectors, accommodation for
guest, assembly members/heads
of department and all other
meetings)
√ 100% Target achieved
(All allowances and transportation
for various activities in 2015 were
paid. This benefited about 200
people (130 males and 70 females))
107. Pay transfer and
haulage grants to newly
posted female and male staff
in the District
√ 50% Target not achieved
(Haulage grants have been paid to
three males and one female)
108. Pay utility bills
(Electricity, water, postal)
and Bank Charges
√ 100% Target achieved
(All utility bills and bank charges
in 2015 have been paid)
109. Maintain all Assembly
Vehicles, Grader, Tipper
Truck and general equipment
regularly including running
cost of office vehicles
√ 100% Target achieved
(All Assembly Vehicles, Grader,
Tipper Truck and general
equipment were maintained for the
Assembly’s day-to-day
administration)
110. Provide Funds for
Social Interventions and
Unanticipated Projects and
Programmes
√ 100% Target achieved
(Funds for Social Interventions and
Unanticipated Projects and
Programmes were paid in the year)
111. Provide support to other
administrative expenses
√ 100% Target achieved
(All other administrative expenses
were provided for during the year)
112. Provide support to
Other Departments in the
preparation of work plans
and quarterly progress report
√ 100% Target achieved
(All Departments and Units in the
Assembly were supported
throughout the year in the
preparation of work plans and
quarterly progress report)
113. Provide support to the
Security Service to perform
efficiently in maintaining
law and order
√ 100% Target achieved
(Support was given in the form of
fuel and other allowances for
Security Service operations in
maintaining law and order in the
District)
114. Implement constituency
projects and programmes for
Scholarships and Bursaries,
Building Materials, Local
Economic Development
empowerment, Relief Items
and other interventions in the
District
√ 100% Target achieved
(MPs projects and programmes
were successfully implemented
within the year. The benefits
include Scholarships and Bursaries,
Building Materials, Local
Economic Development
empowerment, Relief Items and
other interventions)
115. Procure Building
Materials for Community
Initiated (Self-Help)
Projects, Local Economic
Development, Relief Items
and other interventions (5%)
√ 100% Target achieved
(500 bags of cement and 50 packets
of roofing sheets were purchased
for some Community Initiated
Projects in 2015)
15
Works Department
116. Maintain residential
and office buildings in the
District
√ 100% Target achieved
(All maintenance works on
residential and office buildings
were carried out throughout the
year)
117. Rehabilitate 5 No. Staff
quarters in the District
√ 100% Target achieved
(5 No. staff quarters were
rehabilitated in the District)
118. Complete 1 No. 3-
bedroom residential
accommodation for staff of
the Assembly
√ 100% Target achieved
(Works completed and
commissioned)
23. Improve
internal security
for protection of
life and property
Disaster Prevention Department (NADMO)
119. Collate data on all the
disaster prone communities
in the District
√ 100% Target achieved
(In all, 20 communities were
identified to be disaster prone areas
in the District)
120. Procure Relief Items for
Disaster Victims in the
District
√ 100% Target achieved
(The activity was carried out
benefiting 10 communities under
self-help projects)
121. Organise 4 Public
Education on Disaster
Prevention and Management
√ 100% Target achieved
(Four public education campaigns
were organised on Disaster
Prevention and Management. This
benefited 4 communities including
Mankranso, Kunsu, Adugyama and
Wioso)
122. Facilitate with the
District Fire Service and
National Ambulance Service
to response to disasters in the
District
√ 100% Target achieved
(Support was given in the form of
fuel and other allowances for the
operations of District Fire Service
and National Ambulance Service in
the District)
Source: DPCU-AASDA, January, 2016
2.3 Update on Indicators and Targets
The DPCU with the aid of collaboration by other stakeholders has strategically devised a
number of core indicators to be used in tracking the performance of the development
interventions during the plan implementation period for 2015. The criteria used in the choice
of these indicators were cost effectiveness, timely collection of data, easiness to measure
indicator, relevance to project objectives and reliability of variables. The identified indicators
were grouped under the various Thematic Areas of the GSGDA II, 2014-2017.
2.3.1 Thematic Area 1: Ensuring and Sustaining Macroeconomic Stability
In order to achieve and sustain the macroeconomic stability of the District, the objectives set
for this thematic area is to improve fiscal revenue mobilisation and management and improve
public expenditure management by 2017. The performance indicators under this Thematic
Area are shown in the Table 2.2.
16
Table 2.2: Summary of Indicators under Ensuring and Sustaining Macroeconomic Stability No. Objectives Indicators
Target
2015
Baseline Indicator
2013
Indicator Status
2015
Progress
1
Improve fiscal
revenue mobilisation
and management and
improve public
expenditure
management
1. No. of Revenue Improvement Action
Plans prepared and
implemented
1
1
1 Target
achieved
2. No. of tax
educational
campaigns
organised
2 4 2 Target
achieved
3. No. of
stakeholder’s
forum on fee-
fixing resolutions
organised
1 1 1 Target
achieved
4. Proportion of
logistics provided
for the Revenue
Unit
1 1 1 Target
achieved
5. Proportion of
value book
procured
1 1 1 Target
achieved
6. No. of training
workshops
organised for
Revenue
Collectors and
Commissioners
2 2 2 Target
achieved
7. Proportion of
District Revenue
Database
compiled and
updated
1 1 1 Target
achieved
8. Proportion of
compensation to
Established Post
and Non-
Established paid
1 1 1 Target
achieved
Source: DPCU-AASDA, January, 2016
2.3.2 Thematic Area 2: Enhancing Competitiveness of Ghana’s Private Sector
In order to enhance the competitiveness of the District private sector, the objectives adopted
are to improve efficiency and competitiveness of MSMEs and promote sustainable tourism to
preserve historical, cultural and natural heritage by 2017. In achieving this objective, the
indicators to be measured are displayed in Table 2.3.
Table 2.3: Summary of Indicators under Enhancing Competitiveness of Ghana’s Private Sector No. Objectives Indicators
Target
2015
Baseline Indicator
2013
Indicator Status
2015
Progress
2
Improve efficiency
and competitiveness
of MSMEs
9. No. of training
programmes for
women in LED
organised
4 2 4 Target
achieved
10. No. of training
programmes for
MSMEs
organised by BAC
in LED
4 Na 4 Target
achieved
17
11. Proportion of
support provided
to District
Cooperative
Office
1 Na 1 Target
achieved
3 Promote sustainable
tourism to preserve
historical, cultural and
natural heritage
12. No. of District
brochure on
tourism prepared
1 0 0 Target not
achieved
Source: DPCU-AASDA, January, 2016
2.3.3 Thematic Area 3: Accelerated Agricultural Modernization and Sustainable
Natural Resource Management
The policy objective outline under this thematic area is: to develop an effective domestic
market, to improve Agriculture Financing, to promote the development of selected cash crops
and to promote efficient land use and management systems by 2017. These will be achieved
through a number of objectives and indicators as shown in Table 2.4.
Table 2.4: Summary of Indicators under Accelerated Agricultural Modernization
and Sustainable Natural Resource Management No. Objectives Indicators
Target
2015
Baseline Indicator
2013
Indicator Status
2015
Progress
4
Develop an effective
domestic market
13. No. of market
shed constructed
1 Na 1 Target
achieved
14. No. of market
forum organised
1 Na 1 Target
achieved
15. No. of litre
bins provided
5 Na 200 Target
exceeded
5
Improve Agriculture
Financing
16. No. of
Farmers' Day
organised
1 1 1 Target
achieved
17. No. of public
education on
consumption of
locally produced
foods under Local
Economic
Development
conducted
4 2 4 Target
achieved
18. No. of training
conducted for the
Agriculture Dept.
in climate change
and green
economy
1 1 1 Target
achieved
19. No. of farm
visits made by
Agriculture
Extension
Officers to ensure
climate change
compliance and
green economy
134 Na 134 Target
achieved
20. No. of
Farmers trained
in modern
technology
200 Na 323 Target
exceeded
18
21. No. of
vaccination for
small ruminants
promoted
1,000 Na 1,000 Target
achieved
6 Promote the
development of
selected crops
22. No. of training
programmes
organised for
farmers in proper
use and handling
of agro-chemical
inputs
4 Na 4 Target
achieved
7 Promote efficient land
use and management
systems
23. No. of trees
planted along
river banks
100 Na 20 Target not
achieved
Source: DPCU-AASDA, January, 2016
2.3.4 Thematic Area 4: Infrastructure and Human Settlements Development
The policy objectives are: to create and sustain an efficient and effective transport system that
meets user needs, to provide adequate, reliable and affordable energy to meet the national
needs and for export, to accelerate the provision of adequate, safe and affordable water, to
accelerate the provision of improved environmental sanitation facilities and to improve and
accelerate housing delivery in the rural areas in the District by 2017 to support infrastructural
and human settlements growth and development. These are to be achieved through a number
of projects and programmes indicators in Table 2.5.
Table 2.5: Summary of Indicators under Infrastructure and Human Settlements Development No. Objectives Indicators
Target
2015
Baseline Indicator
2013
Indicator Status
2015
Progress
8
Create and sustain an
efficient and effective
transport system that
meets user needs
24. Length of
feeders road
reshaped/rehabilit
ated
30km 100km
20km Target not
achieved
25. Proportion of
all year round
support to Feeder
Roads Unit
provided
1 1 1 Target
achieved
9 Provide adequate,
reliable and
affordable energy to
meet the national
needs and for export
26. No. of tension
electric poles
procured
60 Na 0 Target not
achieved
27. No. of solar
lamps supplied
200 Na 800 Target
exceeded
10 Accelerate the
provision of adequate,
safe and affordable
water
28. No. of
boreholes
rehabilitated/const
ructed
10 Na 5 Target not
achieved
11
Accelerate the
provision of improved
environmental
sanitation facilities
29. No. of APPT
constructed/rehabi
litated
10 0 11 Target
exceeded
30. No. of APPT
constructed at
Sabronum
1 0 1 Target
achieved
31. No. of APPT
constructed at
Bonkwaso
1 0 1 Target
achieved
19
32. No. of 2016-
2020 DESSAP
prepared
1 1 1 Target
achieved
33. Proportion of
Assorted Refuse
Management
Equipment and
Tools for
Environmental
Health Unit
procured
1 1 1 Target
achieved
34. No. of food
sellers screened
and educated on
safe handling of
food
2,500 Na 2,500 Target
achieved
35. No. of
sensitization
programmes
organised on
cholera
prevention
2 Na 2 Target
achieved
36. No. of
National
Sanitation Day
organized
12 Na 12 Target
achieved
37. Proportion of
all year round
Sanitation
Improvement
Package
implemented
1 Na 1 Target
achieved
38. No. of refuse
dumps evacuated
2 1 2 Target
exceeded
39. Proportion of
fumigation
against diseases
conducted
1 5 1 Target
achieved
12
Improve and
accelerate housing
delivery in the rural
areas
40. No. of
Stakeholder’s
meeting on proper
usage of land
organized
1 Na 1 Target
achieved
41. No. of streets
provided with
names and
property
addressing at
Mankranso and
Kunsu
32 Na 16 Target not
achieved
42. No. of
settlement layout
prepared
1 Na 0.9 Target
achieved
43. Proportion of
Annual support
provided for
Physical Planning
Department and
Works
Department
1 1 1 Target
achieved
Source: DPCU-AASDA, January, 2016
20
2.3.5 Thematic Area 5: Human Development, Productivity and Employment
The objectives to pursue under the human development, employment and productivity pillar
are: Increase inclusive and equitable access to, and participation in education at all levels,
Improve quality of teaching and learning, to increase equitable access to and participation in
education at all levels, to provide adequate and disability friendly infrastructure for sports in
communities and schools, enhance national capacity for the attainment of lagging health
MDGs, as well as non-communicable diseases (NCDs) and Neglected Tropical Diseases
(NTDs, Ensure the reduction of new HIV and AIDS/STIs infections, especially among the
vulnerable groups, protect children against violence, abuse and exploitation, Develop targeted
economic and social interventions for vulnerable and marginalized groups, to improve
efficiency and competitiveness of MSMEs and reduce spatial development disparities among
different ecological zones across the country. Table 2.6 provides the indicators of the
implemented projects and programmes for 2015.
Table 2.6: Summary of Indicators under Human Development, Employment and Productivity No. Objectives Indicators
Target
2015
Baseline Indicator
2013
Indicator Status
2015
Progress
13
Increase inclusive and
equitable access to,
and participation in
education at all levels
44. No. of 3-Unit
classroom block
constructed at
Barnorkrom
1 0 0.7
Target not
achieved
45. No. of 3-Unit
classroom block
constructed at
Asikantia
1 0 0.7 Target not
achieved
46. No. of 3-Unit
classroom block
constructed at
Mpasaaso –
Nyamebekyere
1 0 1 Target
achieved
47. No. of 3-Unit
classroom block
constructed at
Nsuta
Nyamebekyere
1 0 1 Target
achieved
48. No. of 3-Unit
classroom block
constructed at
Amoakokrom
1 0 1 Target
achieved
49. No. of 6-Unit
classroom block
constructed at
Sabronum
1 0 0.05 Target not
achieved
50. No. of 3-Unit
classroom block constructed at Ango
1 0 0.05 Target not
achieved
51. No. of 3-Unit
classroom block
constructed at
Adugyama
1 0 0.05 Target not
achieved
52. No. of 3-Unit
classroom block
constructed at
Odeyefe
1 0 0 Target not
achieved
21
53. No. of 3-Unit
classroom block
constructed at
Akwatiakrom
1 0 0 Target not
achieved
54. No. of 6-unit
classroom block
rehabilitated at
Nsuta
1 0 0 Target not
achieved
55. No. of 3-unit
classroom block
rehabilitated at
Potrikrom
1 0 0.05 Target not
achieved
56. No. of
classroom blocks
in selected
communities
rehabilitated/main
tained
1 0 0 Target not
achieved
57. No. of 6-unit
teachers’ quarters
completed at
Asukese
1 0 0.05 Target not
achieved
58. No. of 4-unit
teachers’ quarters
completed at
Sabronum Camp
1 0 0.7 Target not
achieved
59. No. of 4-unit
teachers’ quarters
completed at
Pokuase
1 0 0.7 Target not
achieved
60. No. of 4-unit
teachers quarters
completed
4 0 2 Target not
achieved
61. No. of 4-unit
teachers quarters
completed
(CBRDP)
2 0 1 Target not
achieved
14
Improve quality of
teaching and learning
62. No. of dual
desks and teachers
tables and chairs
supplied to
promote girl child
education
550/150 1,150/150 0.05 Target not
achieved
63. No. of schools
provided with
school feeding
18 16
18 Target
achieved
64. Proportion of
support provided
to District
Education Fund /
District Education
Oversight
Committee
(DEOC)/
SPAM/STMIE
Clinic
1 1 1 Target
achieved
65. No. of poor
and vulnerable
students
supported
annually under
GPEG
4,000 Na 4,000 Target
achieved
66. No. of My
First Day at
school organised
1 1 1 Target achieved
22
67. No. of needy
students provided
with bursaries and
scholarships
50 50 50 Target
achieved
68. No. of quiz
competition
organised
2 1 3 Target
exceeded
69. No. of Mock
Examinations for
BECE candidates
conducted
2 Na 2 Target
achieved
15 Provide adequate
and disability
friendly
infrastructure for
sports in
communities and
schools
70. Proportion of
sports activities
supported
annually
1 1 1 Target
achieved
16 Bridge the equity gaps
in access to health
care
71. No. of
pediatric ward
constructed at
Mankranso
1 0 0.65 Target not
achieved
72. No. of CHPS
compounds
constructed at
Ahwerewam
1 0 1 Target not
achieved
73. No. of CHPS
compounds
constructed at
Bokruwa
1 0 0.6 Target not achieved
74. No. of Health
Centre
constructed at
Kunsu
1 0 0.7 Target not
achieved
75. No. of CHPS
compounds
constructed at
Barniekrom
1 0 0.05 Target not
achieved
76. No. of CHPS
compounds
constructed at
Pokuase
1 0 0.05 Target not
achieved
77. No. of
Community
Clinic
constructed at
Kunsu Camp
1 0 0.05 Target not
achieved
78. No. of
Maternity Clinic
constructed at
Fawoman
1 0 0.05 Target not
achieved
79. No. of Nurses
Quarters
constructed at
Sabronum
1 0 0.05 Target not
achieved
80. No. of CHPS
Compound
rehabilitated at
Adukrom
1 0 1 Target
achieved
23
17 Enhance national
capacity for the
attainment of lagging
health MDGs, as well
as non-communicable
diseases (NCDs) and
Neglected Tropical
Diseases (NTDs
81. Proportion of
support for
rollback malaria
and immunisation
provided
1 Na 1 Target
achieved
82. No. of
Traditional Births
Attendants(TBAs)
trained and
motivated
100 100 100 Target
achieved
18 Ensure the
reduction of new
HIV and
AIDS/STIs
infections,
especially among
the vulnerable
groups
83. No. of
monthly support
provided for the
co-ordination and
management of
HIV/AIDS
programmes
12 12 12 Target achieved
84. No. of
quarterly
monitoring and
evaluation of
HIV/AIDS
programmes
organised
4 4 4 Target
achieved
85. No. of
Educational
Campaigns on
HIV Testing and
Counseling
(HTC) organised
2 2 2 Target
achieved
86. No. of
educational campaigns
organised on causes
and impacts of
HIV/AIDS and other
STIs
2 2 2 Target
achieved
87. Proportion of
all year round
support provided
1 1 1 Target
achieved
88. No. of
Annual
Stakeholder’s
workshop on
HIV/AIDS and
other STIs
organised
1 1 1 Target
achieved
19 Protect children
against violence,
abuse and
exploitation
89. No. of
communities
sensitised on the
dangers and
effects of Child
Labour
5 20 5 Target achieved
20
Develop targeted
economic and
social interventions
for vulnerable and
marginalized group
90. No. of youths
employed under
NYA
100 0 0 Target not
achieved
91. No. of
vulnerable and
marginalized
people supported
under LEAP
873 Na 873 Target
achieved
92. No. of poor
and marginalized
registered on
NHIS under
LEAP
100 0 100 Target
achieved
24
93. No. of PWDs
trained and
sponsored in
income generating
activities
8 Na 8 Target
achieved
94. No. of PWDs
provided with
financial support
quarterly
100 Na 100 Target
achieved
95. No. of
Females trained in
Income
Generating
Activities
100 Na 100 Target
achieved
96. No. of review
meetings on
issues affecting
women held
4 4 4 Target
achieved
21 Reduce spatial
development
disparities among
different ecological
zones across the
country
97. No. of
communities
sensitized to
undertake
community
initiated projects
20 Na 20 Target
achieved
Source: DPCU-AASDA, January, 2016
2.3.6 Thematic Area 6: Transparent and Accountable Governance
The objectives of the District for this Thematic Area are: Ensure effective implementation of
the decentralisation policy and programmes and promote and improve the efficiency and
effectiveness of performance in the public and civil services, and improving security facilities
and safety assurance. This is to be achieved through the implementation of the strategies and
interventions under thematic area indicated in the Table 2.7.
Table 2.7: Summary of Indicators under Transparent and Accountable Governance No. Objectives Indicators
Target
2015
Baseline Indicator
2013
Indicator Status
2015
Progress
22
Ensure effective
implementation of the
decentralisation
policy and
programmes and
promote and improve
the efficiency and
effectiveness of
performance in the
public and civil
services
98. No. of Area
Councils
supported
10 10 8 Target not
achieved
99. No. of training
workshops for
Assembly/Unit
Committee and
Area Council
Members
organised
2 Na 2 Target
achieved
100. No. of
workshops for
women on
participatory
decision making
process organised
4 10 4 Target
achieved
101. No. of
training
workshops for
senior and junior
staff organised
under DDF
4 4 4 Target
achieved
25
102. Proportion of
staff supported to
undergo capacity
building
programmes
1 1 1 Target
achieved
103. No. of Senior
Citizenship day
organized
1 1 1 Target
achieved
104. No. of
DPCU
Monitoring
Meetings
organised
4 4 4 Target
achieved
105. Amount of
money provided
as matching fund
under SIF
128,000.00 Na 128,000.00 Target achieved
106. Proportion of
allowances paid
all year round
1 1 1 Target
achieved
107. No. of newly
posted staff paid
for transfer and
haulage grants
4 1 2 Target not
achieved
108. Proportion of
Utility Bills paid
all year round
1 1 1 Target
achieved
109. Proportion of
Assembly
Vehicles
maintained
1 1 1 Target
achieved
110. Proportion of
Funds for social
interventions and
Unanticipated
projects and
programmes
provided all year
round
1 1 1 Target
achieved
111. Proportion of
Funds provided
for administrative
expenses all year
round
1 1 1 Target
achieved
112. Proportion of
support provided
to Other
Departments
1 1 1 Target
achieved
113. Proportion of
support provided
for Security
Services
1 1 1 Target
achieved
114. Proportion of
constituency
projects and
programmes
implemented
1 1 1 Target
achieved
115. Proportion of
building materials
for community
initiated projects
procured all year
round
1 1 1 Target
achieved
26
116. Proportion of
residential and
office building
maintained
1 1 1 Target
achieved
117. No. of staff
quarters renovated
5 Na 5 Target
achieved
118. No. of 3-
bedroom
residential
accommodation
for staff of the
Assembly
completed
1 Na 1 Target
achieved
23 Improving security
facilities and safety
assurance
119. No. of
disaster prone
communities
collated
20 Na 20 Target
achieved
120. Proportion of
Relief Items
procured all year
round
1 1 1 Target
achieved
121. No. of public
education on
Disaster
prevention and
management
organised
4 4 4 Target
achieved
122. Proportion of
District Fire
Service and
National
Ambulance
Service
collaboration
facilitated
1 1 1 Target
achieved
Source: DPCU-AASDA, January, 2016
27
CHAPTER THREE
INCOME AND EXPENDITURE REPORT
3.1 Update on Funding by Sources for Third Quarter of 2015
The Ahafo-Ano South District Assembly received a total of GH¢1,744,968.39 for the Third
Quarter 2015 fiscal year from a multiplicity of sources including the Taxes on Property,
Other General Government Units, Lands, Rent and Other Income, Fees, Licences, Fines,
Penalties/Forfeits and Miscellaneous. Notwithstanding the deductions at source, receipts from
the Grants (DACF) remain the single largest source of investment fund inflow into the
District. Table 3.1 shows a summary of the trend of revenue performance of the District for
the Third Quarter of 2015.
From Table 3.1, out of a total GH¢6,369,972.03 estimated for Third Quarter, 2015, an
amount of GH¢1,744,968.39 was realized representing a percentage shortfall of 72.6 percent.
The untimely release of the some Other General Government Units (DACF) limited the
Assembly’s ability to implement and complete 35 representing 28.7 percent of its Third
Quarter 2015 programmes, projects and activities. In order to generate enough IGF, measures
have been put in place to educate the public on the need to pay taxes.
During the review of the Third Quarter, 2015, several actions were taken by the Assembly to
improve revenue collection and management. These included establishment of a Revenue
Task Force and compilation of revenue items register for major towns in the District.
However, the Assembly experienced 77.5 percent increase more than the estimated revenue
in its Internally Generated Funds (IGF) for the Third Quarter, 2015, as it received
GH¢429,370.25 compared with the budgeted GH¢281,600.88.
28
Tab
le 3
.1:
Reven
ue
Per
form
an
ce f
or
the
Th
ird
Qu
art
er,
2015
CO
DE
S
OU
RC
E
2015
AN
NU
AL
ES
TIM
AT
E
(G
H¢)
2015
TH
IRD
QU
AR
TE
R
ES
TIM
AT
E
(GH
¢)
2015
TH
IRD
QU
AR
TE
R
AC
TU
AL
(GH
¢)
2015
TH
IRD
QU
AR
TE
R
VA
RIA
NC
E
(AC
T-E
ST
) (
GH
¢)
D
AC
F/D
DF
/GO
G/O
TH
ER
S
1331000
Gra
nts
7,2
98,3
22.7
2
5
,473,7
42.0
4
1,2
30,5
43.8
4
(4,2
43,1
98.2
0)
1332000
Capit
al
Gra
nts
/Oth
er S
ourc
es
913,3
72.4
4
685,0
29.3
3
85,0
54.3
0
(599,9
75.0
3)
IG
F
1131000
Rate
s/In
com
e on P
roper
ty
97,8
23.1
6
73,3
67.3
7
17,9
67.1
0
(55,4
00.2
7)
1412000
Lan
ds
& R
oyal
ties
28,5
00.0
0
21,3
75.0
0
89,6
53.9
2
68,2
78.9
2
1415000
Rent
and O
ther
Incom
e 22,6
82.0
4
17,0
11.5
3
52,8
42.0
0
35,8
30.4
7
1422000
Lic
ense
s 55,9
63.2
0
41,9
72.4
0
43,7
96.5
0
1,8
24.1
0
1423000
Fee
s 68,5
36.3
2
51,4
02.2
4
207,3
62.4
0
155,9
60.1
6
1430000
Fin
es,
Pen
alt
y/F
orf
eit
s 6,4
46.1
6
4,8
34.6
2
10,9
48.0
0
6,1
13.3
8
1450000
Mis
cell
aneo
us
Incom
e 1,6
50.0
0
1,2
37.5
0
6,8
00.3
3
5,5
62.8
3
T
OT
AL
RE
VE
NU
E
8,4
93,2
96.0
4
6
,369,9
72.0
3
1,7
44,9
68.3
9
(4,6
25,0
03.6
4)
IG
F
281,6
00.8
8
211,2
00.6
6
429,3
70.2
5
(211,2
00.6
6)
Sourc
e:
DP
CU
-AA
SD
A,
Januar
y,
2016
29
Policy Recommendations for Improved Revenue Mobilization
The following recommendations can help improve the revenue mobilization drive and
financial management of the Assembly:
• Establishment of Comprehensive Revenue Register.
• Preparation and implementation of a Revenue Improvement Plan.
• Ensuring strict compliance with appropriate directives, regulations and enactments in
financial transactions at all times.
• Implementation of the directives on revenue sharing/contract with Area Councils.
• Improvement in Budget compliance/execution and reporting.
• Improvement in the supervision of Revenue Collection/Mobilization Mechanisms.
• Empowering the Budget Implementation Committee to advise management on
compliance.
3.2 Update on Disbursements for the Third Quarter, 2015
From Table 3.2, out of the total estimated expenditure of GH¢6,214,647.96, 29.3 percent
(GH¢1,823,718.84) was spent in the Third Quarter of 2015. Moreover, out of the total actual
receipts of GH¢1,744,968.29, the District spent above the receipts (GH¢1,823,718.84)
leaving a balance deficits of 4.5 percent (GH¢78,750.45) as at the end of September, 2015.
However, out of the 22 types of expenditure, General Cleaning, Rentals, Travel and
Transport, Repairs & Maintenance, Special Services, Other Charges, Emergency Services
and Infrastructural assets exceeded their estimated expenditures for the Third Quarter, 2015.
30
Tab
le 3
.2:
Exp
end
itu
re P
att
ern
for
Th
ird
Qu
art
er,
20
15
Cod
e E
XP
EN
DIT
UR
E
20
15
AN
NU
AL
ES
TIM
AT
E
(GH
¢)
20
15
TH
IRD
QU
AR
TE
R
ES
TIM
AT
E
(G
H¢
)
20
15
TH
IRD
QU
AR
TE
R
AC
TU
AL
(GH
¢)
20
15
TH
IRD
QU
AR
TE
R V
AR
IAN
CE
(ES
T-A
CT
)
(GH
¢)
21
1100
0
Est
abli
shed
Posi
tion
1
,654,8
76.0
8
1
,241
,15
7.0
6
23
,167
.20
1
,217
,989.8
6
21
2100
0
Nati
onal
Insu
rance
Contr
ibuti
on
21
5,1
34.0
8
161
,35
0.5
6
-
161
,350.5
6
22
1010
0
Mate
rials
– o
ffic
e S
up
pli
es
62
6,7
61.2
0
470
,07
0.9
0
13
1,2
86
.64
338
,784.2
6
22
1020
0
Uti
liti
es
42
2,0
00.1
6
316
,50
0.1
2
10
,058
.15
306
,441.9
7
22
1030
0
Gen
eral
Cle
anin
g
-
-
4
,51
0.0
0
(4,5
10.0
0)
22
1040
0
Ren
tals
-
-
6
,90
0.0
0
(6,9
00.0
0)
22
1050
0
Tra
vel
and T
ransp
ort
15
2,7
80.1
6
114
,58
5.1
2
15
5,3
34
.17
(40,7
49
.05)
22
1060
0
Rep
air
s-M
ain
tenance
18
6,7
34.4
0
140
,05
0.8
0
34
3,0
64
.85
(203,0
14.0
5)
22
1070
0
Tra
inin
g-S
em
inars
-Confe
rence
15
3,6
00.2
4
115
,20
0.1
8
12
,385
.00
102
,815.1
8
22
1080
0
Consu
ltin
g S
ervic
es
6
4,9
39.0
8
4
8,7
04.3
1
-
4
8,7
04.3
1
22
1090
0
Spec
ial
Ser
vic
es
5,5
00.0
8
4,1
25.0
6
31
,178
.12
(27,0
53
.06)
22
1110
0
Oth
er
Char
ges
-
-
2
,37
1.2
2
(2,3
71.2
2)
22
1120
0
Em
ergency S
ervic
es
-
-
6
1,0
08
.00
(61,0
08
.00)
26
3110
0
Gra
nts
1
,499,9
29.4
4
1
,124
,94
7.0
8
54
4,7
04
.62
580
,242.4
6
28
2100
0
Gen
eral
Exp
ense
s
46
9,6
90.2
0
352
,26
7.6
5
30
2,4
49
.73
4
9,8
17.9
2
31
1110
0
Dw
elli
ngs
89
4,9
86.0
4
671
,23
9.5
3
10
6,4
31
.00
564
,808.5
3
31
1120
0
Non-R
esid
enti
al
Buil
din
g
1
,524,2
66.0
4
1
,143
,19
9.5
3
71
,244
.94
1
,071
,954.5
9
31
1130
0
Oth
er
Str
uctu
res
41
5,0
00.0
8
311
,25
0.0
6
14
,004
.70
297
,245.3
6
31
1220
0
Oth
er
Mac
hin
ery-E
quip
men
t
-
-
-
-
31
1210
0
Tra
nsp
ort
-Eq
uip
men
t
-
-
-
-
31
1310
0
Infr
astr
uct
ura
l A
sset
s
-
-
3
,62
0.5
0
(3,6
20.5
0)
31
2210
0
Mate
rials
-Sup
pli
es
-
-
-
-
T
OT
AL
EX
PE
ND
ITU
RE
8
,286
,197.2
8
6
,214
,64
7.9
6
1,8
23
,718
.84
4
,390
,929.1
2
Sourc
e: D
PC
U-A
AS
DA
, Ja
nuary
, 2
01
6
31
CHAPTER FOUR
UPDATE ON CRITICAL DEVELOPMENT AND POVERTY ISSUES
4.1 National Youth Employment Agency
As at the close of the year 2015, only the sanitation (Zoomlion) module had 176 people
employed in the programme with 63 percent females and 37 males. All personnel in the
other modules have exited waiting for fresh registration to be done after the passage of
the new National Youth Agency bill.
4.1.1 Challenges facing NYEA in the District
• Delay in the release of allowances to the beneficiaries.
• Ineffective monitoring of activities.
4.1.2 Policy Recommendations
• Allowances should be paid at regular intervals.
• Supply of adequate logistics to ensure effective monitoring.
• The bill has to be passed for the programme to commence in order to curb youth
unemployment in the District and country as a whole.
4.2 Ahafo-Ano South Mutual Health Insurance Scheme
In the year 2015, the Scheme registered 10,519 new members comprising 56.0 percent
females and 44.0 percent males. For old members who had renewals of their cards in
2015, they were 26,320 in number. It is significant to note that for both new members and
those who renewed their cards, females constitute the majority accounting for 56.0
percent and 60.0 percent respectively. Table 4.1 depicts the breakdown of the members of
the NHIS in the District.
32
Table 4.1: Active Membership of Ahafo-Ano South Mutual Health Insurance Scheme, 2015 Status Category New Renewals
Female Male Not Specified Female Male Not Specified Total
Children under 5 788 838 0 988 1,079 0 3,693
Dependent 2,421 2,367 1 6,066 5,793 0 16,648
Dependent of Military 1 1 0 0 0 0 2
Dependent of Police 4 0 0 14 12 0 30
Ex-Service Personnel 0 0 0 0 1 0 1
Ghana Police 0 2 0 1 1 0 4
Indigent 243 270 0 406 237 0 1,156
Informal 1,538 1,017 0 6,255 2,515 0 11,325
LEAP 3 3 0 13 3 0 22
No Status Category 51 24 0 282 166 0 523
Persons aged 70 and above 101 59 0 656 335 0 1,151
Pregnant Women 736 - - 714 - - 1,450
SSNIT Contributor 17 31 0 279 456 0 783
SNNIT Pensioner 0 3 0 8 40 0 51
Grand Total 5,903 4,615 1 15,682 10,638 0 36,839
Source: NHIS-AASDA, January, 2016
4.2.1 Challenges facing Ahafo-Ano South Mutual Health Insurance Scheme
• Inadequate office and residential accommodation.
• Frequent breakdown of official vehicle.
• Difficult to reach areas due to poor road network.
4.2.2 Policy Recommendations
• Provision of office and residential accommodation.
• Procurement of new vehicle.
• Reshape poor road network.
4.3 Livelihood Empowerment against Poverty (LEAP) Programme
LEAP is a cash transfer programme for the poorest households in Ghana. The government
aims to assist the poorest families with basic needs, including food and also to improve
health and education status of children in poorest families with this programme. A total
873 households are benefiting from the programme in 20 communities. The beneficiaries
include 1,327 females representing 61.1 percent and 845 males representing 38.9 percent.
33
Table 4.2: Name of Communities and Beneficiaries under LEAP No. Name of Community Total No. of
Households
No. of Beneficiaries
Female Male Total
1 Abodease 22 25 24 49
2 Adukrom 31 51 37 88
3 Ahwerewam-Domeabra 34 33 17 50
4 Akwasi Aworokrom 2 3 1 4
5 Biemtetrete 69 83 35 118
6 Mpasaaso I 16 16 8 24
7 Mpasaaso II 55 95 28 123
8 Nyame Ahyiraso 1 3 1 4
9 Abaasua 38 72 37 109
10 Afreseni 48 80 43 123
11 Boatengkrom 69 83 95 178
12 Pokuase 66 104 87 191
13 Anitemfe 55 75 87 162
14 Banniekrom 63 113 73 186
15 Biemso I 58 129 46 175
16 Biemso II 49 59 57 116
17 Dwinyama 68 118 69 187
18 Kunsu 43 87 22 109
19 Aponaponso 30 31 25 56
20 Ahwerewam 56 67 53 120
Total 873 1,327 845 2,172
Source: DSW-AASDA, January, 2016
4.3.1 Challenges facing LEAP Programme
• Inadequate logistics such as vehicle to deliver monies to beneficiaries.
• Poor road network to some selected communities.
4.3.2 Policy Recommendations
• Provide adequate logistics for smooth implementation of the programme.
• Reshape feeder roads in the District.
4.4 School Feeding Programme
Table 2.3 shows the number of communities benefiting from the School Feeding
Programme. A total of 16 schools were enrolled in the programme in 2013. Two more
schools were added to the existing ones in 2015 summing up to 18 schools. In total 4,537
pupils benefit from the programme with boys accounting for 49.4 percent and girls being
50.6 percent. Apart from few challenges confronted the programme especially the
untimely release of the feeding grants to the cooks, the programme has been successful. It
has increased the number of enrolment in the schools in which the programme is being
run.
34
Table 4.3: Number of Pupils and Schools under School Feeding Programme in the District No. Name of School Pupils Total
Boys Girls
1 Nyameadom D/A Primary & K.G. 105 115 220
2 Attakrom D/A Primary & K.G. 69 71 140
3 Aponaponso D/A Primary & K.G. 115 162 277
4 Asempanaye Primary ‘A’ 153 128 281
5 Asempanaye Primary ‘B’ 142 144 286
6 Pokukrom Meth. Primary ‘A’ 174 184 358
7 Pokukrom Meth. Primary ‘B’ 93 103 196
8 Ohiapae D/A Primary 95 83 178
9 Adense-Yawboadi D/A Primary 87 81 168
10 Barniekrom D/A Primary & K.G. 247 205 452
11 Kokoteasua D/A Primary 95 80 175
12 Biemso R/C Primary ‘A’ 180 170 350
13 Biemso R/C Primary ‘B’ 160 187 347
14 Bonsukrom D/A Primary 130 143 273
15 Asukese St. Peter’s D/A Primary 80 98 178
16 Adeambra D/A Basic School 146 150 296
17 Biemtetrete D/A Primary School 126 150 276
18 Aburaso Nahathatul Islamic Basic School 44 42 86
Total 2,241 2,296 4,537
Source: School Feeding Co-ordinator-AASDA, January, 2016
4.4.1 Challenges facing School Feeding Programme
• Delay in the release of the funds.
4.4.2 Policy Recommendation
• There should be timely released of funds.
4.5 Sensitization Workshops on LGS Protocols (SoS, CoS, CoC, SDS, PMS, OM)
Within the year under review, four training workshops were organized for all staff of the
Assembly on LGS protocols (SoS, CoS, CoC, SDS, PMS, Staffing Norms, HR Policy & OM,
etc.). The first quarter workshop was on the Scheme of Service (SoS) which was
organized for all the 151 staff (97 females and 54 males) of the Assembly. The second
quarter workshop was on the CoS. This training benefited the 151 staff (97 females and
54 males) of the Assembly.
In addition, in the third quarter, two-day training was organized by the Assembly in
collaboration with the Human Resource Management Unit of the Regional Co-ordinating
Council (RCC) on the Operation and Maintenance (OM). Finally, the fourth quarter
training was organised for the Head of Departments and Units on the SDS to improve
upon the quality of service in the District. In all, 20 staff benefited made up of 15 males