2016 team conferencemar 10, 2016 · cory imhoff, p.e. – design manager . simon sun, p.e. –...
TRANSCRIPT
![Page 1: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/1.jpg)
© 2015 HDR, all rights reserved.
Waverly Road Progressive Design Build Project Owner: City of Edgerton, KS
2016 TEAM Conference
March 10, 2016
![Page 2: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/2.jpg)
Project Location
![Page 3: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/3.jpg)
Project Location
BNSF LPKC
BNSF Transcon
Tracks
BNSF Intermodal
Lead Trucks
Gardner, KS
Waverly Road
Edgerton, KS
![Page 4: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/4.jpg)
Project Team
![Page 5: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/5.jpg)
Clarkson Construction Company Tom Kellerman, P.E. – Chief Engineer – Project Sponsor Pat Weaver, P.E. – Project Manager Randy Smith, P.E. – Structures Manager
Design Build Team
HDR Cory Imhoff, P.E. – Design Manager Simon Sun, P.E. – Roadway Design Lead Chad Hall, P.E. – Structures Design Lead Shannon McCauley, P.E. – Railroad Liaison Subconsultants Renaissance Infrastructure Consultants Braun Intertec Terra Technologies
Design Team
Owners Beth Linn, City Administrator Kenny Cook, Community Development Director David Hamby, City Engineer (BG Consultants, Inc.)
![Page 6: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/6.jpg)
Progressive Design Build Process
![Page 7: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/7.jpg)
Delivery Phases
1. Qualifications Phase
• Statement of Qualifications
• Shortlist • Interview • Selection
2. Guaranteed Maximum Price (GMP) Development Phase
• Collaborative Design and Estimating
• Setting Scope and Schedule of Project
• Advance Permitting, Utility Relocation and Right of Way Acquisition
• Setting Guaranteed Maximum Price for Project Scope (30% plans)
3. Final Design & Construction
• Project segmentation • Developing 100% plans
for owner review and approval
• Finalize Right of Way Acquisition
• Finalize Utility Relocation
• Finalize Permitting • Release for
Construction Documents
• Construction
![Page 8: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/8.jpg)
November 2014 RFQ December 2014 Shortlist/Interview January 2015 Pre-GMP Design
to March 2015 & Estimating
Project Schedule April to July 2015 Final Design April 2015 to May 2016 Construction
![Page 9: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/9.jpg)
1. Qualifications Phase
![Page 10: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/10.jpg)
RFP/RID Alignment Over Existing & Future BNSF IMF Tracks Impacts KCP&L Wetlands Parcel Position Relative to BNSF Lead Track Monitoring Equipment Complicates Intersection at 183rd Street Required Steel Plate Girders
![Page 11: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/11.jpg)
Wetland & Conservation Corridor Impacts DWR, COE, KDWP, KDHE, USFWS FAA 7460 for Lights on Bridge & Cranes Schedule Risk
Permitting
![Page 12: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/12.jpg)
Utilities
KCP&L, Gardner Water, Gardner Electric, Water District 7, Century Link, Kansas Gas, BNSF Minimize Impacts City & Utility Staff Integral Part of Process Schedule Risk
![Page 13: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/13.jpg)
Quick Decisions City Leadership o Beth Linn
Cooperation with North Point and BNSF KCP&L Wetland City of Gardner Boundary Mixed Results with Private
Properties o Biggest challenge to
project delivery Schedule Risk
Right of Way
Private Property
Private Property
![Page 14: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/14.jpg)
Bridge Over Existing & Future BNSF IMF Tracks Avoid Impacts to KCP&L Wetlands Parcel to Maintain Schedule Stay on or Near Existing Alignment Use Precast Girders to Maintain Schedule Straddle Bent Required Over Future Lead Track (Square or Skewed?) Evaluate Longer Bridge to Avoid Culvert Replacement(s) & Additional Impacts
KCP&L Overhead
Gardner Water
![Page 15: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/15.jpg)
Waverly Road Profile Over BNSF RFP/RID 183rd Street Intersection Was A Concern Relocating 183rd Street Intersection Allows Tie In and Access to BNSF Water Storage Tank
Entrance And Improved Intersection Geometry Profile Controlled by Straddle Bent & Future IMF Tracks High Fills Over Culverts vs. Increasing Bridge Length & Avoiding Culvert & Stream Impacts Fill Heights & Potential MSE Wall Strap Length Conflicts for Parallel Walls
![Page 16: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/16.jpg)
Inverted Tee Straddle Bent Staged Post-Tensioning Inverted Tee Cap TxDOT Detailing Approach Good Alternative to a Framed Cap Simple Construction Can be Constructed Without Girders
![Page 17: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/17.jpg)
Maintaining Access During Construction Waverly Road Closed to Through Traffic Temporary Surfacing to Maintain Access for BNSF, Developers, Contractors,
Private Residents & Emergency Responders Segmentation and Use of Local Roads to Maintain Access for Everyone
WD No. 7
Kubota Private
BNSF
North Point
![Page 18: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/18.jpg)
2. GMP Development Phase
![Page 19: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/19.jpg)
Weekly Task Force Meetings o Owner o Major Stakeholders o Designer o Contractor
Communication is Key Decisions Made and Maintained Allows Priorities and Expectations for
Project to be Aligned Develop 30% Plans o Contract Basis for Construction and Design
Pricing Third Party / Independent Review of Pricing
Setting Project Scope, Schedule and Price
![Page 20: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/20.jpg)
During GMP development phase o Advance Permitting o Advance Utility Relocation o Advance Right of Way Acquisition
Owner involvement and decision making Working with single consultant and
contractor Owner retention of GMP plans whether
GMP contract is signed or not The owner, the contractor, and the designer
are on the same page going into final design and construction
GMP Development Phase is “The Advantage” of Progressive Design Build
![Page 21: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/21.jpg)
3. Final Design And Construction
![Page 22: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/22.jpg)
Bridge Packages
S01A – Girders & Bearings Waverly Road Bridge
S01B – Pier 1 Straddle Waverly Road Bridge
S01C – Abutment 1 & 2 Waverly Road Bridge
S01D – Pier 2, 3, 4 & 5 Waverly Road Bridge
S01E – Deck, Barrier, Joints, Lights Waverly Road Bridge
![Page 23: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/23.jpg)
![Page 24: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/24.jpg)
Roadway Packages
R01 – G, D & P 187th Street
R02A – G & D South – Sta. 65 + 50 to Sta. 126 + 75
R02B – G, D & P South – Sta. 65 + 50 to Sta. 110 + 00
R02C – G, D & P South – Sta. 110 + 00 to Sta. 131 + 50
R04 – G, D & P North – 185th Street to 183rd Street
R05A – G & D North – Sta. 126 + 75 to 202 + 02.13
R05B – G & D & P North – Sta. 126 + 75 to 202 + 02.13
R02 A, B
R02 C R04
R05 A, B
R01
![Page 25: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/25.jpg)
![Page 26: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/26.jpg)
Project Photos
![Page 27: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/27.jpg)
![Page 28: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/28.jpg)
![Page 29: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/29.jpg)
![Page 30: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/30.jpg)
![Page 31: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/31.jpg)
![Page 32: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/32.jpg)
![Page 33: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/33.jpg)
![Page 34: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/34.jpg)
![Page 35: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/35.jpg)
![Page 36: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/36.jpg)
![Page 37: 2016 TEAM ConferenceMar 10, 2016 · Cory Imhoff, P.E. – Design Manager . Simon Sun, P.E. – Roadway Design Lead . ... Relocating 183rd Street Intersection Allows Tie In and Access](https://reader033.vdocuments.net/reader033/viewer/2022041805/5e5408f94f47d54e56118b04/html5/thumbnails/37.jpg)
Questions