2019 design and construction projects - south bend, indiana · project manager: roger nawrot...
TRANSCRIPT
2019 Design and Construction ProjectsAssistant City Engineers:
Sue Ellen Doudrick, PE
Jacob Klosinski, PE
Roger Nawrot, PE, PLS
Kyle Silveus, PE
Annual Consultants and Contractors Meeting
South Well Field ImprovementsProject Manager: Sue Ellen Doudrick, PE
Project Description:
• Phase I: Rehabilitation and improvements to South Well Field
• Phase II: Water main connection from well field to south pressure district
• Easement acquisitions
Expected Bid Date: Spring 2019/Winter 2019
GAC Adsorption Tanks
Existing GAC Feed
Annual Consultants and Contractors Meeting
Prairie Avenue Water Main Loop
Project Manager: Sue Ellen Doudrick, PE
Project Description
• Water main extension to Four Winds Casino and looping the existing system• Boring under US 31/US 20
• New customers along SR 23
• Easement acquisitions
Expected Bid Date: 2019/2020
Annual Consultants and Contractors Meeting
Sewer & Manhole Lining
Project Manager: Sue Ellen Doudrick, PE
Project Description:
• Rehabilitation of Diamond Avenue sewers and structures to extend service life of infrastructure
• Other various locations
Expected Bid Date: December 2019/January 2020
Annual Consultants and Contractors Meeting
Small Drainage ProjectsProject Manager: Sue Ellen Doudrick, PE
Project Description:
• Mitigate drainage issues in
residential areas
Expected Bid Date:
Summer 2019
Annual Consultants and Contractors Meeting
2019 Curb & Sidewalk Program
Project Manager:Alicia Czarnecki, EI
Project Description:
• Replace curb, sidewalk, and curb ramps in various locations around the City
• Removal and replacement of trees
Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
West Bank Trail Improvements
Project Manager: Sue Ellen Doudrick, PE
Project Description:
• ADA trail• Overlooks, pedestrian bridge
• West Gate Repair at West Race• Intake gate replacement
Expected Bid Date: BID OPENING 3/12/19
Dr.
Ma
rtin
Lu
ther
Kin
g B
lvd
Colfax Ave
LaSalle Ave
Annual Consultants and Contractors Meeting
Seitz Park Reconstruction Phases I & II
Project Manager:
Sue Ellen Doudrick, PE
Project Description:
• Phase I: East Bank Trail Connection (East Race to Howard Park)
• Phase II: Seitz Park recon with bandshell, vending building, and trail connection to Colfax Avenue
Expected Bid Date: Summer 2019 & 2020
Annual Consultants and Contractors Meeting
East Bank and East Race Repairs
Project Manager:Scott Kreeger, EI
Project Description:
• Stabilize embankment at the East Race boat ramp
• Fill a sinkhole and repair surrounding sidewalk
Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
VPA Athletic Court Renovations
Project Manager:Alicia Czarnecki, EI
Project Description:
• Renovation of tennis and basketball courts in several parks throughout the City of South Bend
Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Muessel Grove Public Restroom
Project Manager:Alicia Czarnecki, EI
Project Description:
• Renovate or replace existing public restroom building
Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Assistant City Engineer: Jacob Klosinski, P.E.
Annual Consultants and Contractors Meeting
Wastewater Treatment PlantDigester Gas Utilization & CNG Fuel Station Improvements
Project Manager:
Jacob M. Klosinski, P.E.
Project Description:
• CNG Fuel Station Dispensers
• CNG Fuel Station Compressor
• Underground Piping and Valves
• Instrumentation and Controls
• Gas Cleaning Skid Removable Partition / Enclosure
Expected Bid Date: 4Q 2019-2020
Annual Consultants and Contractors Meeting
Wastewater Treatment PlantSt. Joseph Riverbank Stabilization Phase 3
Project Manager:
Jacob M. Klosinski, P.E.
Project Description:
• Tree Removal / Clearing
• Embankment Stabilization
• Vegetation / Tree Planting
Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
St. Joseph Riverbank StabilizationRiverside Drive and Joyce
Project Manager:
Jacob M. Klosinski, P.E.
Project Description:
• Tree Removal / Clearing
• Embankment Stabilization
• Vegetation / Tree Planting
Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
Ameritech-Parkland Drive Lift Station Rehabilitation
Project Manager:
Jacob M. Klosinski, P.E.
Project Description:
• Replace Control Panel
• Replace Submersible Pumps
• Construct Flow Meter Vault
• Fiber Optic Cable Relocation
Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
Douglas Road Lift Station Relocation(St. Joseph County Douglas Road Widening)
Project Manager:
Jacob M. Klosinski, P.E.
Project Description:
• New Submersible Pump Station
• New Instrumentation Panel
• Flow Meter / Bypass Pumping
• Pressure Pipe Relocation traverses Juday Creek
• Fiber Optic Cable Relocation
Expected Bid Date: TBD – Est. 2020
Annual Consultants and Contractors Meeting
Edison Filtration Plant Roof Repair
Project Manager:Scott Kreeger
Project Description:
• Remove and replace existing ceiling supports and roof.
• Improve ceiling trusses with corrosive resistant material.
Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Pinhook Water Treatment Plant Improvements
Project Manager: Alicia Czarnecki
Project Description:
• Potential project elements include:• Replacement of electronic actuator
valves • Replacement of filter underdrains• Control panel and motor upgrades• Air handling system upgrades• Well replacement/repairs• Building roof repairs
Expected Bid Date: Fall 2019
Annual Consultants and Contractors Meeting
Pinhook Park
Project Manager: Alicia Czarnecki
Project Description:
• Potential project elements include:
• Trail and Access Improvements
• Playground Improvements
• Boat and Kayak Launch Improvements
• Pinhook Pavilion Internal Improvements
Expected Bid Date: Spring 2020
Annual Consultants and Contractors Meeting
Assistant City Engineer: Roger Nawrot, PE, PLS
Annual Consultants and Contractors Meeting
Bendix Drive Reconstruction
Project Manager: Roger Nawrot
Project Description:
• New concrete pavement built to a 3 lane pavement section.
• To be constructed in two independent sections north and south of Boland Drive.
• Reconfigure the Nimtz Parkway intersection.
Expected Bid Date: Fall 2019 on INDOT Letting
Annual Consultants and Contractors Meeting
Olive Street Reconstruction
Project Manager: Roger Nawrot
Project Description:
• This heavy haul route will have the pavement reconstructed from SR 23 to just south of Tucker Drive.
• The new pavement will be concrete built to a 3 lane section.
• New storm sewer will be installed.
Expected Bid Date: Spring 2020 on INDOT Letting
Annual Consultants and Contractors Meeting
Sample Street & Sheridan Street Intersection ImprovementsProject Manager: Roger Nawrot
Project Description:
• New traffic signal system at the intersection of Sample and Sheridan Streets
• Turning radii improvements for large trucks on the south side of Sample Street.
Expected Bid Date: Fall 2019
Annual Consultants and Contractors Meeting
Corby-Rockne-Ironwood Intersection ImprovementProject Manager: Roger Nawrot
Project Description:
• The intersection will be built with HMA pavement.
• The storm water will be separated and a retention basin will be constructed.
• A new traffic signal system will be installed.
• Expected Bid Date: Spring 2020 on INDOT Letting
Annual Consultants and Contractors Meeting
Street and Sewer Department Materials
Project Manager: Scott Kreeger
Project Description:
• Provide materials to be used by the Street Department, Sewer Department and other City of South Bend agencies for 2019.
Expected Bid Date: March 2019
Annual Consultants and Contractors Meeting
Michigan Street Pavement Replacement
Project Manager: Roger Nawrot
Project Description:
• Replacing existing concrete driving lanes between Western Avenue and Colfax Avenue.
• Changing the perpendicular parking to 60 degree angular.
• New street lighting in the block from Western Avenue to Wayne Street.
Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
River Walkway Extension and Lower River Wall RepairProject Manager: Roger Nawrot
Project Description:
• Building a new walkway that is 10 feet wide from Howard Park to Beyer Street along Northside Boulevard.
• Installing new pedestrian lighting along the new walkway and the lower river walk.
• Replacing 330 feet of existing lower river wall.
Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Storm Sewer Backwater ValvesProject Manager: Roger Nawrot
Project Description:
• Installation of 3 duckbill backwater valves on existing storm sewer discharge headwalls. The discharge sewer diameters are 36 to 42 inches.
• The discharge locations are along Northshore Drive between Angela Boulevard and Michigan Street.
• Expected Bid Date: Fall 2019
Annual Consultants and Contractors Meeting
2019 Community Crossing Project
Project Manager: Scott Kreeger
Project Description:
• HMA overlay of Corby from east of Ironwood Drive to Manchester Drive, Jefferson Boulevard from Ironwood Drive to Logan Street, Linden Avenue from Mayflower Road to Lombardy Drive and Riverside Drive from Angela Avenue to Academy Place.
• Pavement grooving and thermoplastic pavement will be installed.
• Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Ewing Avenue & Fellows Street Traffic Signal ReplacementProject Manager: Roger Nawrot
Project Description:
• Replacement of one of the oldest signal systems in the City. The existing mechanical controller is a museum piece and can’t be repaired.
• The signal supports including foundations will be replaced.
• A new digital controller with foundation along with the service point will be installed.
Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Fire Station 3 RenovationProject Manager: Alicia Czarnecki
Project Description:
• Potential project elements include:• Concrete drive replacement• Bathroom remodel and plumbing
replacement• New electric panel and service• HVAC upgrade• Strip and polish flooring• Kitchen gut and remodel• Additional parking spaces in back lot
Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Fire Station 6 Second Floor RemodelProject Manager: Alicia Czarnecki
Project Description:
• Potential project elements include:• Address structural failure on South Wall• Provide second egress from top floor• Renovate restrooms to private single with
shower, sink and toilet• Reconfigure entrance to bathroom/locker
area• Provide carpeting for bedroom area• Provide separate study area at top of stairs• Replace windows for energy efficiency
Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Morris Theater – Plaster Ceiling Work
Project Manager: Alicia Czarnecki
Project Description:
• Remedial repairs to the decorative plaster wrapping the base of each of 4 domes in the ceiling of the Morris Performing Arts Center theater
Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
Assistant City Engineer: Kyle Silveus, PE
Annual Consultants and Contractors Meeting
Leeper Park Improvements
Project Manager: Kyle Silveus
Project Description:
• Installation of Studebaker Fountain, paths, playground relocation, and river overlook
• Includes removal of Duck Pond
Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
Pulaski Park Improvements
Project Manager: Kyle Silveus
Project Description:
• Improvement Entrance for increased visibility
• New restrooms, soccer field, walking paths with basketball court and parking improvements
• Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
Lincolnway East Corridor Improvements Phase II
Project Manager: Kyle Silveus
Project Description:
• Trail Link from Sample to Twyckenham
• Boardwalk and Railing Installation
Expected Bid Date: Spring 2020
Mia
mi S
t.
Annual Consultants and Contractors Meeting
Western Avenue Corridor Improvements – Phase III
Project Manager: Kyle Silveus
Project Description:
• Extends West from previous phases - Falcon St. to Dundee St.
• Streetscape project including storm sewer separation, new water main, concrete overlay
Expected Bid Date: Spring 2019Harrison Primary
Western Ave.
Annual Consultants and Contractors Meeting
O’Brien Center Improvements
Project Manager: Charlie Brach
Project Description:
• Renovation of the O’Brien Recreation Center
• Modernization to better fit within the goals of the VPA and provide better value to the City Residents
Expected Bid Date: July 2019
Annual Consultants and Contractors Meeting
Tech Resource Center
Project Manager: Zach Hurst
Project Description:
• Collaborative Working Area for the City, Private Businesses, and Academics
• Finishing of Catalyst Two Building in Ignition Park
• TIF Funding
Expected Bid Date: Spring 2019
Annual Consultants and Contractors Meeting
320 at the Cascade
Project Manager: Zach Hurst
Project Description:
• Multi-Phase Mixed-Use and residential project
• TIF Contribution for Architectural elements
• Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Commerce Center
Project Manager: Zach Hurst
Project Description:
• Mixed-Use project including apartments and downtown grocery store
• TIF Contribution for Architectural elements
• Expected Bid Date: Summer 2019
Annual Consultants and Contractors Meeting
Main/Jefferson Earthwork
Project Manager: Kyle Silveus
Project Description:
• Five-Story office building including a drive-thru coffee shop
• TIF contribution for Earthwork Elements
Expected Bid Date: Spring 2019