Page 1: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

2019 Design and Construction ProjectsAssistant City Engineers:

Sue Ellen Doudrick, PE

Jacob Klosinski, PE

Roger Nawrot, PE, PLS

Kyle Silveus, PE

Page 2: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

South Well Field ImprovementsProject Manager: Sue Ellen Doudrick, PE

Project Description:

• Phase I: Rehabilitation and improvements to South Well Field

• Phase II: Water main connection from well field to south pressure district

• Easement acquisitions

Expected Bid Date: Spring 2019/Winter 2019

GAC Adsorption Tanks

Existing GAC Feed

Page 3: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Prairie Avenue Water Main Loop

Project Manager: Sue Ellen Doudrick, PE

Project Description

• Water main extension to Four Winds Casino and looping the existing system• Boring under US 31/US 20

• New customers along SR 23

• Easement acquisitions

Expected Bid Date: 2019/2020

Page 4: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Sewer & Manhole Lining

Project Manager: Sue Ellen Doudrick, PE

Project Description:

• Rehabilitation of Diamond Avenue sewers and structures to extend service life of infrastructure

• Other various locations

Expected Bid Date: December 2019/January 2020

Page 5: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Small Drainage ProjectsProject Manager: Sue Ellen Doudrick, PE

Project Description:

• Mitigate drainage issues in

residential areas

Expected Bid Date:

Summer 2019

Page 6: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

2019 Curb & Sidewalk Program

Project Manager:Alicia Czarnecki, EI

Project Description:

• Replace curb, sidewalk, and curb ramps in various locations around the City

• Removal and replacement of trees

Expected Bid Date: Spring 2019

Page 7: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

West Bank Trail Improvements

Project Manager: Sue Ellen Doudrick, PE

Project Description:

• ADA trail• Overlooks, pedestrian bridge

• West Gate Repair at West Race• Intake gate replacement

Expected Bid Date: BID OPENING 3/12/19

Dr.

Ma

rtin

Lu

ther

Kin

g B

lvd

Colfax Ave

LaSalle Ave

Page 8: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Seitz Park Reconstruction Phases I & II

Project Manager:

Sue Ellen Doudrick, PE

Project Description:

• Phase I: East Bank Trail Connection (East Race to Howard Park)

• Phase II: Seitz Park recon with bandshell, vending building, and trail connection to Colfax Avenue

Expected Bid Date: Summer 2019 & 2020

Page 9: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

East Bank and East Race Repairs

Project Manager:Scott Kreeger, EI

Project Description:

• Stabilize embankment at the East Race boat ramp

• Fill a sinkhole and repair surrounding sidewalk

Expected Bid Date: Spring 2019

Page 10: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

VPA Athletic Court Renovations

Project Manager:Alicia Czarnecki, EI

Project Description:

• Renovation of tennis and basketball courts in several parks throughout the City of South Bend

Expected Bid Date: Summer 2019

Page 11: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Muessel Grove Public Restroom

Project Manager:Alicia Czarnecki, EI

Project Description:

• Renovate or replace existing public restroom building

Expected Bid Date: Summer 2019

Page 12: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Assistant City Engineer: Jacob Klosinski, P.E.

Page 13: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Wastewater Treatment PlantDigester Gas Utilization & CNG Fuel Station Improvements

Project Manager:

Jacob M. Klosinski, P.E.

Project Description:

• CNG Fuel Station Dispensers

• CNG Fuel Station Compressor

• Underground Piping and Valves

• Instrumentation and Controls

• Gas Cleaning Skid Removable Partition / Enclosure

Expected Bid Date: 4Q 2019-2020

Page 14: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Wastewater Treatment PlantSt. Joseph Riverbank Stabilization Phase 3

Project Manager:

Jacob M. Klosinski, P.E.

Project Description:

• Tree Removal / Clearing

• Embankment Stabilization

• Vegetation / Tree Planting

Expected Bid Date: Spring 2019

Page 15: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

St. Joseph Riverbank StabilizationRiverside Drive and Joyce

Project Manager:

Jacob M. Klosinski, P.E.

Project Description:

• Tree Removal / Clearing

• Embankment Stabilization

• Vegetation / Tree Planting

Expected Bid Date: Spring 2019

Page 16: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Ameritech-Parkland Drive Lift Station Rehabilitation

Project Manager:

Jacob M. Klosinski, P.E.

Project Description:

• Replace Control Panel

• Replace Submersible Pumps

• Construct Flow Meter Vault

• Fiber Optic Cable Relocation

Expected Bid Date: Spring 2019

Page 17: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Douglas Road Lift Station Relocation(St. Joseph County Douglas Road Widening)

Project Manager:

Jacob M. Klosinski, P.E.

Project Description:

• New Submersible Pump Station

• New Instrumentation Panel

• Flow Meter / Bypass Pumping

• Pressure Pipe Relocation traverses Juday Creek

• Fiber Optic Cable Relocation

Expected Bid Date: TBD – Est. 2020

Page 18: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Edison Filtration Plant Roof Repair

Project Manager:Scott Kreeger

Project Description:

• Remove and replace existing ceiling supports and roof.

• Improve ceiling trusses with corrosive resistant material.

Expected Bid Date: Summer 2019

Page 19: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Pinhook Water Treatment Plant Improvements

Project Manager: Alicia Czarnecki

Project Description:

• Potential project elements include:• Replacement of electronic actuator

valves • Replacement of filter underdrains• Control panel and motor upgrades• Air handling system upgrades• Well replacement/repairs• Building roof repairs

Expected Bid Date: Fall 2019

Page 20: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Pinhook Park

Project Manager: Alicia Czarnecki

Project Description:

• Potential project elements include:

• Trail and Access Improvements

• Playground Improvements

• Boat and Kayak Launch Improvements

• Pinhook Pavilion Internal Improvements

Expected Bid Date: Spring 2020

Page 21: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Assistant City Engineer: Roger Nawrot, PE, PLS

Page 22: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Bendix Drive Reconstruction

Project Manager: Roger Nawrot

Project Description:

• New concrete pavement built to a 3 lane pavement section.

• To be constructed in two independent sections north and south of Boland Drive.

• Reconfigure the Nimtz Parkway intersection.

Expected Bid Date: Fall 2019 on INDOT Letting

Page 23: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Olive Street Reconstruction

Project Manager: Roger Nawrot

Project Description:

• This heavy haul route will have the pavement reconstructed from SR 23 to just south of Tucker Drive.

• The new pavement will be concrete built to a 3 lane section.

• New storm sewer will be installed.

Expected Bid Date: Spring 2020 on INDOT Letting

Page 24: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Sample Street & Sheridan Street Intersection ImprovementsProject Manager: Roger Nawrot

Project Description:

• New traffic signal system at the intersection of Sample and Sheridan Streets

• Turning radii improvements for large trucks on the south side of Sample Street.

Expected Bid Date: Fall 2019

Page 25: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Corby-Rockne-Ironwood Intersection ImprovementProject Manager: Roger Nawrot

Project Description:

• The intersection will be built with HMA pavement.

• The storm water will be separated and a retention basin will be constructed.

• A new traffic signal system will be installed.

• Expected Bid Date: Spring 2020 on INDOT Letting

Page 26: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Street and Sewer Department Materials

Project Manager: Scott Kreeger

Project Description:

• Provide materials to be used by the Street Department, Sewer Department and other City of South Bend agencies for 2019.

Expected Bid Date: March 2019

Page 27: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Michigan Street Pavement Replacement

Project Manager: Roger Nawrot

Project Description:

• Replacing existing concrete driving lanes between Western Avenue and Colfax Avenue.

• Changing the perpendicular parking to 60 degree angular.

• New street lighting in the block from Western Avenue to Wayne Street.

Expected Bid Date: Summer 2019

Page 28: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

River Walkway Extension and Lower River Wall RepairProject Manager: Roger Nawrot

Project Description:

• Building a new walkway that is 10 feet wide from Howard Park to Beyer Street along Northside Boulevard.

• Installing new pedestrian lighting along the new walkway and the lower river walk.

• Replacing 330 feet of existing lower river wall.

Expected Bid Date: Summer 2019

Page 29: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Storm Sewer Backwater ValvesProject Manager: Roger Nawrot

Project Description:

• Installation of 3 duckbill backwater valves on existing storm sewer discharge headwalls. The discharge sewer diameters are 36 to 42 inches.

• The discharge locations are along Northshore Drive between Angela Boulevard and Michigan Street.

• Expected Bid Date: Fall 2019

Page 30: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

2019 Community Crossing Project

Project Manager: Scott Kreeger

Project Description:

• HMA overlay of Corby from east of Ironwood Drive to Manchester Drive, Jefferson Boulevard from Ironwood Drive to Logan Street, Linden Avenue from Mayflower Road to Lombardy Drive and Riverside Drive from Angela Avenue to Academy Place.

• Pavement grooving and thermoplastic pavement will be installed.

• Expected Bid Date: Summer 2019

Page 31: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Ewing Avenue & Fellows Street Traffic Signal ReplacementProject Manager: Roger Nawrot

Project Description:

• Replacement of one of the oldest signal systems in the City. The existing mechanical controller is a museum piece and can’t be repaired.

• The signal supports including foundations will be replaced.

• A new digital controller with foundation along with the service point will be installed.

Expected Bid Date: Summer 2019

Page 32: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Fire Station 3 RenovationProject Manager: Alicia Czarnecki

Project Description:

• Potential project elements include:• Concrete drive replacement• Bathroom remodel and plumbing

replacement• New electric panel and service• HVAC upgrade• Strip and polish flooring• Kitchen gut and remodel• Additional parking spaces in back lot

Expected Bid Date: Summer 2019

Page 33: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Fire Station 6 Second Floor RemodelProject Manager: Alicia Czarnecki

Project Description:

• Potential project elements include:• Address structural failure on South Wall• Provide second egress from top floor• Renovate restrooms to private single with

shower, sink and toilet• Reconfigure entrance to bathroom/locker

area• Provide carpeting for bedroom area• Provide separate study area at top of stairs• Replace windows for energy efficiency

Expected Bid Date: Summer 2019

Page 34: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Morris Theater – Plaster Ceiling Work

Project Manager: Alicia Czarnecki

Project Description:

• Remedial repairs to the decorative plaster wrapping the base of each of 4 domes in the ceiling of the Morris Performing Arts Center theater

Expected Bid Date: Spring 2019

Page 35: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Assistant City Engineer: Kyle Silveus, PE

Page 36: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Leeper Park Improvements

Project Manager: Kyle Silveus

Project Description:

• Installation of Studebaker Fountain, paths, playground relocation, and river overlook

• Includes removal of Duck Pond

Expected Bid Date: Spring 2019

Page 37: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Pulaski Park Improvements

Project Manager: Kyle Silveus

Project Description:

• Improvement Entrance for increased visibility

• New restrooms, soccer field, walking paths with basketball court and parking improvements

• Expected Bid Date: Spring 2019

Page 38: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Lincolnway East Corridor Improvements Phase II

Project Manager: Kyle Silveus

Project Description:

• Trail Link from Sample to Twyckenham

• Boardwalk and Railing Installation

Expected Bid Date: Spring 2020

Mia

mi S

t.

Page 39: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Western Avenue Corridor Improvements – Phase III

Project Manager: Kyle Silveus

Project Description:

• Extends West from previous phases - Falcon St. to Dundee St.

• Streetscape project including storm sewer separation, new water main, concrete overlay

Expected Bid Date: Spring 2019Harrison Primary

Western Ave.

Page 40: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

O’Brien Center Improvements

Project Manager: Charlie Brach

Project Description:

• Renovation of the O’Brien Recreation Center

• Modernization to better fit within the goals of the VPA and provide better value to the City Residents

Expected Bid Date: July 2019

Page 41: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Tech Resource Center

Project Manager: Zach Hurst

Project Description:

• Collaborative Working Area for the City, Private Businesses, and Academics

• Finishing of Catalyst Two Building in Ignition Park

• TIF Funding

Expected Bid Date: Spring 2019

Page 42: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

320 at the Cascade

Project Manager: Zach Hurst

Project Description:

• Multi-Phase Mixed-Use and residential project

• TIF Contribution for Architectural elements

• Expected Bid Date: Summer 2019

Page 43: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Commerce Center

Project Manager: Zach Hurst

Project Description:

• Mixed-Use project including apartments and downtown grocery store

• TIF Contribution for Architectural elements

• Expected Bid Date: Summer 2019

Page 44: 2019 Design and Construction Projects - South Bend, Indiana · Project Manager: Roger Nawrot Project Description: •Replacement of one of the oldest signal systems in the City. The

Annual Consultants and Contractors Meeting

Main/Jefferson Earthwork

Project Manager: Kyle Silveus

Project Description:

• Five-Story office building including a drive-thru coffee shop

• TIF contribution for Earthwork Elements

Expected Bid Date: Spring 2019