2020-03-15 application of earned value management …
TRANSCRIPT
DSpace Institution
DSpace Repository http://dspace.org
Construction Technology and Management Thesis
2020-03-15
APPLICATION OF EARNED VALUE
MANAGEMENT (EVM) ON
PERFORMANCE EVALUATION OF
INFRASTRUCTURE PROJECTS: A
CASE STUDY OF AMHARA ROAD
WORKS ENTERPRISE (ARWE)
CONSTRUCTION PROJECTS
Yitayih, Wollelaw
http://hdl.handle.net/123456789/10331
Downloaded from DSpace Repository, DSpace Institution's institutional repository
BAHIR DAR UNIVERSITY
BAHIR DAR INSTITUTE OF TECHNOLOGY
SCHOOL OF RESEARCH AND POSTGRADUATE STUDIES
FACULTY OF CIVIL AND WATER RESOURCE ENGINEERING
APPLICATION OF EARNED VALUE MANAGEMENT (EVM) ON
PERFORMANCE EVALUATION OF INFRASTRUCTURE PROJECTS:
A CASE STUDY OF AMHARA ROAD WORKS ENTERPRISE (ARWE)
CONSTRUCTION PROJECTS
By
Wollelaw Yitayih Tegegne
Bahir Dar, Ethiopia
July 30, 2019
APPLICATION OF EARNED VALUE MANAGEMENT (EVM) ON PERFORMANCE
EVALUATION OF INFRASTRUCTURE PROJECTS: A CASE STUDY OF AMHARA
ROAD WORKS ENTERPRISE (ARWE) CONSTRUCTION PROJECTS
By
Wollelaw Yitayih Tegegne
A Thesis submitted to the school of Research and Graduate Studies of Bahir Dar Institute
of Technology, BDU in partial fulfillment of the requirements for the degree of Master of
Science in Construction Technology and Management in the Faculty of Civil and Water
Resource Engineering.
Advisor Name: Asregedew Kassa Woldesenbet, Ph.D., P.E.
Co-Advisor Name: Habtamu Lulseged (MSc.)
Bahir Dar, Ethiopia
July 30, 2019
i
ii
© 2019
Wollelaw Yitayih Tegegne
ALL RIGHTS RESERVED
iii
iv
ACKNOWLEDGEMENTS
Above all, I would like to say Glory to God for what he has done for me and giving me all
the strength to accomplish this task and throughout my life.
Next, I would like to express my gratitude and deep appreciation to my advisor, Asregedew
Kassa Woldesenbet, Ph.D., P.E. for his valuable comment, constructive suggestions and
insightful guidance during prepared this thesis paper.
I would like also to thank all Amhara Road Works Enterprise staffs and in particular Ato
Asmamaw and Ato Gebeyaw, for their keen interest and contributions for facilitating and
cooperation by providing the necessary information and data required for this thesis. It is
also my pleasure to thank all of the professionals in Consulting firms, Contractors and Client
representatives who made this thesis possible by responding to questionnaires.
I want to also acknowledge Bahir Dar University, Institute of Technology, School of Civil
and Water Resource Engineering for the financial assistance and Madda Walabu University
for sponsoring me to enroll in the MSc program.
Finally, I thank my parents and siblings as they have been involved in many ways in my
learning process, inspiration of the thesis result and their kindness and generosity.
v
ABSTRACT
The construction industry in Ethiopia is one of the major sectors that considering the rapid
growth, where public and private sectors are investing substantial amount of resource.
However, the performance of construction projects is non optimum. The causes for this
low performance may be attributed to improper planning, execution and monitoring
according to the required guidelines and best-practices in modern construction
management. So to achieving better performance, this study examines the applicability of
Earned Value Management (EVM) technique in measuring the performance and
forecasting of infrastructure projects as alternative means. EVM is a project monitoring
and controlling technique which integrates technical performance, cost, and schedule.
This paper investigates the usage and level of awareness of EVM through expert analysis
using questionnaire survey. The study revealed that key players in Bahir Dar construction
industry have very low usage and low level of awareness. A relatively low number of
stakeholders have applied some parts of EVM concepts in construction projects. The study
identified as potential barriers in using Earned Value. Few of this barriers are lack of EVM
expertise and experience, minimal awareness of EVM including training, low familiarity
with the EVM techniques and poor understanding of EVM. In addition, the application of
the technique is illustrated using two case studies on ongoing infrastructure projects.
Finally, the paper recommends a set of practices to overcome barriers and facilitate the use
of EVM. Thus, EVM can be a useful tool to monitor project status and forecast by
integrating cost and time.
Keywords: Project management, EVM, Earned value, Performance Evaluation, control
system
vi
TABLE OF CONTENTS
DECLARATION.............................................................. Error! Bookmark not defined.
ACKNOWLEDGEMENTS ............................................................................................ iv
ABSTRACT ........................................................................................................................v
TABLE OF CONTENTS ................................................................................................ vi
LIST OF ABBREVATIONS .............................................................................................x
LIST OF FIGURES ........................................................................................................ xii
LIST OF TABLES ......................................................................................................... xiii
CHAPTER ONE ................................................................................................................1
INTRODUCTION..............................................................................................................1
1.1. General ..................................................................................................................1
1.2. Statement of the Problems.....................................................................................2
1.3. Research Questions ...............................................................................................4
1.4. Objectives of the Study .........................................................................................4
1.4.1. General Objective ......................................................................................... 4
1.4.2. Specific Objectives ....................................................................................... 4
1.5. Theoretical Framework .........................................................................................5
1.6. Scope of the Study.................................................................................................5
1.6.1. Content Scope ............................................................................................... 5
1.6.2. Geographical Scope ...................................................................................... 6
1.7. Significance of the Study ......................................................................................6
1.8. Expected Result .....................................................................................................6
1.9. Structure of the Thesis...........................................................................................6
CHAPTER TWO ...............................................................................................................8
LITERATURE REVIEW .................................................................................................8
2.1. Introduction ...........................................................................................................8
2.2. Earned Value Management (EVM).......................................................................8
2.3. Origins and Evolution of EVM ...........................................................................10
2.3.1. History of EVM development ..................................................................... 10
vii
2.3.1.1. Industrial Engineering Origins ................................................................ 10
2.3.1.2. Program Evaluation and Review Technique ........................................... 11
2.3.1.3. Cost/Schedule Control Systems Criteria (C/SCSC) ................................ 11
2.3.1.4. EVMS Standard....................................................................................... 11
2.4. EVM Terminology ..............................................................................................13
2.4.1. Key Parameters of EVM ............................................................................. 14
2.4.2. Performance Measure ................................................................................. 15
2.4.3. Predicting the Future with EVM ................................................................. 17
2.5. Earned Value Method..........................................................................................22
2.6. Project Management ............................................................................................23
2.7. Construction Project Management ......................................................................24
2.7.1. Project Time management .......................................................................... 25
2.7.2. Project Cost Management ........................................................................... 26
2.8. Traditional Cost Management vs. Earned Value ................................................27
2.8.1. Simple Deviation Analysis ......................................................................... 27
2.9. EVM and the Project Management Process ........................................................28
2.9.1. Project Planning Process ............................................................................. 30
2.9.2. Project Execution Process ........................................................................... 30
2.9.3. Project Monitoring and Controlling ............................................................ 30
2.10. Construction Performance Measure Using Earned Value Technique .................32
2.11. Current Status of Earned Value Management (EVM) ........................................34
2.12. Early Warning Tool .............................................................................................35
2.13. Problems Associated with Earned Value ............................................................36
2.14. Implementation Requirements and Benefit of the EVM .....................................38
2.15. Research Gap.......................................................................................................41
2.16. Summary of Literature Review ...........................................................................42
CHAPTER THREE .........................................................................................................43
METHODOLOGY ..........................................................................................................43
viii
3.1. Introduction .........................................................................................................43
3.2. Research Design ..................................................................................................43
3.2.1. Survey Research Design ............................................................................. 44
3.2.2. Case Study .................................................................................................. 44
3.3. Sampling Technique ............................................................................................45
3.4. Methods of Data Collection and Source of Data.................................................45
3.4.1. Literature Review........................................................................................ 46
3.4.2. Questionnaire Survey Method .................................................................... 46
3.4.3. Interview Method ........................................................................................ 46
3.5. Data Analysis ......................................................................................................46
3.5.1. Analysis of Quantitative Data ..................................................................... 46
3.5.2. Analysis of Qualitative Data ....................................................................... 47
3.6. Measurement of Variables ..................................................................................47
3.7. Reliability Test ....................................................................................................48
CHAPTER FOUR ............................................................................................................49
DATA ANALYSIS AND DISCUSSION ........................................................................49
4.1. Introduction .........................................................................................................49
4.2. Interview Result and Discussion .........................................................................49
4.3. Survey Result and Discussion .............................................................................52
4.3.1. Section A: Background Information ........................................................... 52
4.3.2. Section B: Earned Value Survey ................................................................. 57
4.3.3. Section C: Respondents Level of Agreement ............................................. 61
4.4. Practical Application of Earned Value Management ..........................................67
4.4.1. Methodology ............................................................................................... 68
4.4.2. Case Study One ........................................................................................... 68
4.4.3. Case Study Two .......................................................................................... 81
CHAPTER FIVE .............................................................................................................87
CONCLUSIONS AND RECOMMENDATIONS .........................................................87
ix
5.1. Findings ...............................................................................................................87
5.2. Recommendations ...............................................................................................90
5.3. Suggestions for Future Research .........................................................................90
Bibliography .....................................................................................................................91
APPENDIX .......................................................................................................................97
Appendix A: Survey .......................................................................................................98
Appendix B: The results of reliability test (Cronbach's Alpha) of questionnaire ........104
Appendix C: Interview Guide ......................................................................................107
Appendix D: Results of Practical Application .............................................................108
Appendix E: EVM Acronyms ......................................................................................112
Appendix F: ANSI/EIA-748 EVMS Criteria ...............................................................113
Appendix G: ANSI/EIA-748 EVMS Criteria in Five categories .................................115
x
LIST OF ABBREVATIONS AC Actual Cost
ACP Accomplishment/ Cost Procedure
ACWP Actual Cost of Work Performed
ANSI/EIA American National Standards Institute/Electronic
Industries Alliance
ARBDSWE Amhara Road and Building Design and Supervision
Works Enterprise
ARRTO Amhara Rural Road Transport office
ARWE Amhara Road Works Enterprise
APM Association of project management
ATC Actual time expended for the work to date
BAC Budget at completion
BCWP Budgeted Cost of Work Performed
BCWS Budgeted Cost of Work Schedule
CBC Cumulative Budgeted Cost
CPI Cost Performance Index
CPM Critical Path Method
CSF Critical Success Factors
CSPC Cost and Schedule Planning and Control
C/SCSC Cost & Schedule Control Systems Criteria
CV Cost Variance
DOD Department of Defense
EAC Estimate at completion
EACt Estimate at Completion time
ED Earned duration
ERA Ethiopian Roads Authority
ES Earned Schedule
xi
ETC Estimate to Complete
EV Earned Value
EVA Earned Value Analysis
EVM Earned Value Management
EVMS Earned Value Management System
GDP Gross Domestic Product
LSE London School of Economics
MoWUD Ministry of Works and Urban Development
MS Mean Score
NDIA National Defense Industry Association
PCWR Planned Cost of Work Remaining
PERT Program Evaluation and Review Technique
PMB Performance Measurement Baseline
PMBOK Project Management Body of Knowledge
PMI Project Management Institute
PMP Project Management Program
PMs Project Managers
PV Planned Value
RM Risk Management
SPI Schedule Performance Index
SPSS Statistical Package for Social science
SV Schedule Variance
SWOT Strengths, Weaknesses, Opportunities, Threats
TCPI To Complete Performance Index
TV Time Variance
WBS Work Breakdown Structure
VAC Variance at Completion
xii
LIST OF FIGURES
Figure 1. 1 Framework showing relationship between EVA and project performance...... 5
Figure 2. 1 EVM progress timeline....................................................................................13
Figure 2. 2 EVM and the basic project management process ........................................... 32
Figure 2. 3 EVM performance measure ............................................................................ 16
Figure 2. 4 EVM graph including trend analysis .............................................................. 20
Figure 3. 1 Research Methodology Flow chart ..................................................................44
Figure 4. 1 Firms Years since Establishment.....................................................................53
Figure 4. 2 Firms Classification ........................................................................................ 54
Figure 4. 3 Respondents’ Age ........................................................................................... 54
Figure 4. 4 Respondents’ Gender...................................................................................... 55
Figure 4. 5 Techniques used to Track Project Costs and progress ................................... 57
Figure 4. 6 Respondents’ Recommendation to Measure Performance on Construction
Projects .............................................................................................................................. 58
Figure 4. 7 Participant Opinion on the Value of EVM ..................................................... 58
Figure 4. 8 Participant Reasons for Using EVM .............................................................. 59
Figure 4. 9 Participant Reasons not using EVM ............................................................... 59
Figure 4. 10 Project Cost Monitoring Method of Participants ......................................... 60
Figure 4. 11 Earned Value as a new Estimate Value on Top of Plan Value and Actual
Cost ................................................................................................................................... 61
Figure 4. 12 Project Location Map ................................................................................... 69
Figure 4. 13 S-Curve for the Cumulative Cash Flow ....................................................... 71
Figure 4. 14 Graphical Analysis of Cumulative Planned Value, Earned Value and Actual
cost (As of July 30, 2018) ................................................................................................. 72
Figure 4. 15 Cumulative Cost Variance at Various Status Months .................................. 74
Figure 4. 16 Cumulative Cost Performance Index at Various Status Months .................. 74
Figure 4. 17 Cumulative Schedule Variance at Various Status Months ........................... 77
Figure 4. 18 Cumulative Schedule Performance Index at Various Status Months ........... 78
Figure 4. 19 Graphical Analysis of Cumulative Planned Value, Earned Value and Actual
Cost (As of August 30, 2018) ........................................................................................... 82
Figure 4. 20 Graphical Representation of Cumulative Cost &Schedule Performance Index
........................................................................................................................................... 83
Figure 5. 1 SWOT analysis of EVM ..................................................................................89
xiii
LIST OF TABLES
Table 2. 1 Interpretation of basic EVM performance measures ....................................... 17
Table 2. 2 Forecasting indicators by EVM Technique ..................................................... 19
Table 2. 3 Overview EVM metrics ................................................................................... 21
Table 2. 4 EVM and basic project management questions ............................................... 22
Table 2. 5 EVM and project management process ........................................................... 29
Table 2. 6 Problems Related to EVM Implementation .................................................... 38
Table 2. 7 Differences with EVA and without EVA ........................................................ 41
Table 3. 1 Interpretation of Alpha..................................................................................... 48
Table 4. 1 Respondents Interview Result in Percentage ................................................... 51
Table 4. 2 Questionnaire Response Rate .......................................................................... 53
Table 4. 3 Respondents’ Position in the Company ........................................................... 55
Table 4. 4 Respondents’ level of education ...................................................................... 56
Table 4. 5 Experience of the Respondents’ ...................................................................... 56
Table 4. 6 Participants Level of Agreement on their Knowledge about EVM ................. 62
Table 4. 7 The Level of Organization able to provide up-to Date Information ................ 63
Table 4. 8 Contribution of using EVM for Project Control Purpose ................................ 63
Table 4. 9 Barriers of Company to Practice EVM ............................................................ 64
Table 4. 10 Success Factors for EVM Implementation .................................................... 65
Table 4. 11 Cronbach's Alpha for each section of the questionnaire ................................ 67
Table 4. 12 Cumulative Earned Value (EV) Cost Analysis .............................................. 73
Table 4. 13 Cumulative Earned Value Schedule Analysis ............................................... 76
Table 4. 14 Problems encounter on the project ................................................................. 79
Table 4. 15 Project Comparative Findings ....................................................................... 80
Table 4. 16 Cumulative Earned Value Analysis ............................................................... 81
Table 4. 17 Cumulative EVM Performance Indexes ........................................................ 83
Table 4. 18 Cumulative Cost and Schedule Analysis ....................................................... 84
Table 4. 19 Project Comparative Findings ....................................................................... 85
Table B- 1: SPSS result of reliability test for contribution of using EVM for project
control purpose.................................................................................................................104
Table B- 2: SPSS result of reliability test (Cronbach's Alpha) for Barriers of Company to
Practice EVM .................................................................................................................. 105
Table B- 3: SPSS result of reliability test (Cronbach's Alpha) for Success Factors for
EVM Implementation ..................................................................................................... 106
1
CHAPTER ONE
INTRODUCTION
1.1. General
The construction industry in Ethiopia is one of the major sectors that considering the rapid
growth, where public and private sectors are investing substantial amount of resource.
According to Zewdu and Aregaw (2015), the GDP contribution of the industry has raised
to 5.6% and approaches to sub-Saharan average of 6%. However, the performance of the
industry is non optimum when it comes to construction project management practices. It is
said to harbor many inefficiencies and ineffectiveness in its delivery system and processes
(MoWUD, 2001). These inefficiencies result in a significant impact on the country’s socio-
economic growth.
Solomon (2015) argues that one of the causes for the inefficiencies is the lack of proper
planning, execution and monitoring of projects according to well-accepted guidelines of
construction management. This attributes to the lack of trained personnel, non-appreciation
of the importance of proper planning and monitoring schemes to improve performance and
the lack of appropriate guidelines in the managing various processes.
Solomon (2015) describes that the most commonly used way of evaluation of projects with
respect to time and cost are direct deviation analysis and Earned Value Analysis (EVA)
technique. This study assesses the applicability of EVM technique in measuring the
performance and forecasting of infrastructure projects. Naderpour and Mofid (2011) state
that Earned Value Analysis (EVA) is a technique that can effectively monitor and control
construction projects by integrating cost, time and technical performance and act as project
control method. EVA allows the calculation of cost and schedule variances and
performance indices and forecast project cost and schedule duration. Khamidi et al. (2011)
also argue that EVA is a worldwide technique adopted by many developed countries
including United States, United Kingdom, Australia and South Korea.
2
According to PMI (2005), Earned Value Management (EVM) is one of the most effective
performance measurement and feedback tools for managing projects. It enables managers
to close the loop in the plan-do-check-act management cycle. EVM has been called
‘‘management with the lights on’’, because it can help clearly and objectively illuminate
where a project is and where it is going as compared to where it was supposed to be and
where it was supposed to be going. It focuses on project evaluation and control system,
measuring project progress performance against a project plan to ensure that the project is
completed on time, within budget and meet users need. A good project evaluation and
control system should also provide project managers with advance warning of potential
problems and indications of project performance, before it is too late to correct them (PMI,
2005). Thus, EVM is a powerful quantitative technique for objectively monitoring project
progress.
1.2. Statement of the Problems
Project managers are always looking forward to see projects perform well with success.
This involves finishing projects on time, within budget, meeting end product specifications,
customer needs & requirements and management objectives (Cooke-Davies, 2003).
However, this is not the case as complains of exclusion are still reported. According to
Muhwezi and Otim (2014), the delays and cost overrun are attributed to poor project
management, inaccurate estimation, inappropriate construction method and delayed
payments.
The main reason that initiated this research is the finding of a recent study at the London
School of Economics (LSE) in UK that reported the management practice in Africa is poor
as compared to Europe and North America. According to the report, Ethiopia is the second
from last followed by Mozambique (Matters, 2014), which indicates that the management
practice in Ethiopia is even far behind from those poor performing developing countries in
Africa. Typically, Tadesse A. (2016) states the level of construction project management
practice in terms of adapting general project management procedures, project management
functions, tools & techniques to be unsatisfactory. Particularly the level of practice in terms
3
of time, cost and risk management are the most challenging issues for construction industry
professionals in managing their day to day’s activities in Ethiopia.
In the same way Pär Karlsson (2011) Ethiopian construction companies often have no well-
developed methods to control their projects. Project control is not prioritized and problems
are solved as when it is occurring rather than by controlling the project to avoid problems.
This causes several problems in the Ethiopian projects that could have been avoided if an
efficient project control were conducted.
In this regard clients, consultants and contractors in the Ethiopian construction industry
have continuously focused their attention in adapting EVM. However, its application for
project evaluation and control technique has not well-developed in Ethiopia, specifically
in Bahir Dar. Thus, this study examines the practical application of Earned Value
Management (EVM) technique in measuring the performance and control system of
ongoing road infrastructure construction projects constructed by Amhara Road Work
Enterprise. Based on a review of certain documents and preliminary interview with few
project managers in Bahir Dar, implementing and maintaining accurate monitoring and
control system is one of the challenges faced by management in road infrastructure
projects. Currently, the industry uses both simple deviation analysis and partially
implement Earned Value Analysis for monitoring and controlling project costs.
In simple deviation analysis, graphic presentation of costs and benefits over time are
represented, while in EVA, existing performance measuring techniques used on
construction projects practice, is the difference between the amounts of work executed to
the amount of total expense in order to indicate profit and loss. This only considers cost
component. Typically, EVM adds schedule and a third parameter on the amount of work
accomplished or the value of work performed, referred as Earned Value. Comparing the
EV to the plan value and actual cost, a project manager can identify whether a project is
ahead or behind schedule and over budget or under budget at any time. Besides, current
practices do not relate any current performance trend to forecast future performances. Thus,
the usage of project performance monitoring and forecasting tool has been limited. Because
of this limitation, this study focuses on evaluating the concept of Earned Value Analysis
4
for monitoring and controlling of projects. It also examines factors that hinders its adoption
in Bahir Dar Road constructions.
1.3. Research Questions
In relation to the above highlighted focus area, the study tries to address the following
research questions:
1. What are the current management (monitoring and controlling) practices method
and their drawback?
2. What factors hinder the use and application of EVM in Bahir Dar Road
Construction Projects?
3. What are the critical success factors (CSF) for EVM implementation?
4. What is the relationship between Earned Value Management (EVM) technique and
performance of Amhara Road Work Enterprise infrastructure construction project?
1.4. Objectives of the Study
1.4.1. General Objective
The general objective of this study is to examine the applicability of EVM
technique in measuring the performance and forecasting of infrastructure projects
both time and cost.
1.4.2. Specific Objectives
The study also achieves the following specific objectives:
Determine current monitoring and controlling practices of construction project
management method and major drawbacks in the context of EVM techniques
Identify factors that hinder the usage and application of EVM.
Identify critical success factors for EVM implementation
Assess the relationship between EVM technique and performance of project in Amhara
Road Work Enterprise.
5
1.5. Theoretical Framework
According to Ng shi cia (2015) analyzed related to independent variable which is EVA and
dependent variable is cost performance in construction project. But in this research, it was
developed the independent variable is Earned Value Analysis, while the dependent
variables are key performance indicators of construction projects focus on two dimensions
namely cost and time performance. The relationship between EVA and project
performance in construction project is shown in Figure 1.1.
Independent variable Dependent variable
Figure 1. 1 Framework showing relationship between EVA and project performance
1.6. Scope of the Study
1.6.1. Content Scope
The scope of this research focuses on examining the relationship between EVM technique
and project performances. The variables and case study considers the relationship between
EVM techniques and performance of infrastructure construction projects constructed by
Amhara Road Works Enterprise (ARWE).
Earned Value Analysis Performance of Construction
Project
Implementation of EVA in Construction
Project
Early Warning Tools
Project Status Indicator
Earned Value Forecasting
Parameter
Performance of Construction Project
Cost & Schedule Variance
Cost & Schedule Performance
Index
Estimate at Completion &
Estimate to Completion
6
1.6.2. Geographical Scope
The study is carried out within Bahir Dar city and is focused mainly on road infrastructure
construction projects.
1.7. Significance of the Study
This study will give construction sector a guideline on how to measure cost and time
performance and project progress using Earned Value Analysis. Implementing of EVA in
a construction project serves as a guidance in improving cost performance by providing
feedback. Timely and targeted feedback can enable project managers to identify problems
early and make adjustments to keep projects on time and budget. Thus, EVM uses
fundamental principle to project managers that shows patterns and trends in the past and
can be good predictors of the future. In addition, the study helps construction parties, policy
makers, government and other stakeholders use the findings to make improvement within
the industry and make good decisions.
This study can also help researchers explore challenges, barriers and application of EVM
techniques and make further investigation on the subject matter.
1.8. Expected Result
The study is expected to reach the objectives thereby increasing the usability of EVA in
Bahir Dar road construction projects. It is expected to provide a better view on the
relationship between Earned Value Analysis and performance. This study can also supply
a guideline to construction managers in measuring project performance and forecast using
Earned Value Analysis.
1.9. Structure of the Thesis
This research paper is organized into five chapters that will move the reader from an
introduction of Earned Value Management and the processes involved with establishing
this analysis tool and how it can be utilized using Amhara Road Works Enterprise
7
infrastructure projects. Projects from two Amhara Road Works Enterprise construction will
be utilized to highlight the analysis possibilities that could be realized. Finally, the research
wraps up with conclusions and recommendations for future research.
Chapter 1: Introduction to the subject of Earned Value Management, research questions,
objectives of this paper and purpose are outlined.
Chapter 2: In this chapter, the supporting literature review on EVM and closely related
topics and details including the evolution of Earned Value Management; the basic elements
involved in analyzing data and project management questions; and how EVM can answer
this question are addressed. This chapter also presents and outlines the steps required in
implementing an Earned Value Management System and performance measurement tools
for calculating and analyzing project data.
Chapter 3: Is dedicated to the methods undertaken in using Earned Value analysis.
Chapter 4: In this chapter, analysis of survey results on project management practitioners
experience on project control practices, attitudes towards EVM, barriers that could impede
the full implementation of the Earned Value approach and success factors to implement
EVM for this barriers. This chapter also assess the practical application of the methodology
identified in this paper is presented and reviewed along the relationship implication of
performance of road infrastructure construction project and Earned Value Management
techniques in the context of Amhara Road Work Enterprise construction projects.
Chapter 5: Finally, concludes the paper and recommends areas for future research.
8
CHAPTER TWO
LITERATURE REVIEW
2.1. Introduction
This chapter reviews relevant existing literature on EVM concept and its applicability of
EVM technique on measuring the performance of construction projects and overall project
management. The chapter is divided into different section in a sequential manner:
definition and origins of EVM, performance analysis and forecasting, how EVM can
answer project management questions, an outline of knowledge gaps and finally synthesis
of the literature review addressed by this study.
2.2. Earned Value Management (EVM)
Earned Value Management (EVM) is a technique that project management practitioners
have developed to measure project performance and progress based on a combination of
schedule, costs, and work performed with a focus on early warning of trends in either of
these areas. Through EVM’s advancement, various definitions have been provided by
various institutions, organizations and researchers. Some of important definitions of
Earned Value management referred in the published literatures are:
1. Project Management Institute (PMI) - PMI defines Earned Value management
(EVM) as “a management methodology for integrating scope, schedule, and
resources, and for objectively measuring project performance and progress.
Performance is measured by determining the budgeted cost of the work performed
(i.e. Earned Value) and comparing it to the actual cost of the work performed (i.e.
actual cost). Progress is measured by comparing the Earned Value to the planned
value” (PMI, 2004). This definition is actually quite limited, for EVM comprises
not only those three comparisons, but also the use of those three measures to create
variances, indicators, and forecasts of project performance and progress. Note that
9
PMI uses the term performance to describe the resource (cost) efficiency, and
progress to identify the schedule (time) efficiency.
A project evaluation and control system measure project progress performance
against a project plan to ensure that the project is completed on time, within budget
and to meet of users need. A good project evaluation and control system should be
also providing project managers with advance warning of potential problems,
before it is too late to correct them. EVM is a powerful quantitative technique for
objectively monitoring the physical project progress. It enables measuring actual
work performance and associated cost and time versus an agreed plan. It also gives
early indications of project performance to highlight the need for eventual
corrective action (PMI, 2005).
2. NASA defines it as “an integrated management control system for assessing
understand and quantifying what a contractor or filed activity is achieving with
program dollars. EVM provide project management with objectives, accurate and
timely data for effective decision making” (Henderson & Zwikael, 2008).
3. Association for Project Management (APM) – APM defines EVM as “a project
control process based on a structured approach to planning, cost collection and
performance measurement. It facilitates the integration of project scope, time and
cost objectives and the establishment of a baseline plan for performance
measurement.” (APM, 2006).
4. MS Project - The user guide for Microsoft Project defines Earned Value as “a
method for measuring project performance (Uyttewaal, 2003). It indicates how
much of the budget should have been spent, in view of the amount of work done so
far and the baseline cost for the task, assignment or resources”. Earned Value
analysis is a method of performance measurement and program management
technique that uses work in progress to indicate what will happen to work in the
future. It is also system for planning and controlling the project cost performances.
EVM establish work packages Earned Value base line by integrating project scope,
time schedule
5. Researchers - Englert and associates define it as “A method for measuring project
performance. It compares the amount of work that was planned with what was
10
actually accomplished to determine if cost and schedule performance is as
planned” (Englert and associates, 2000). Earned Value project management is well
known management system that integrates cost, schedule and technical
performance. It allows the calculation of cost and schedule variances and
performance indices and forecasts the project cost and schedule duration
(Naderpour and Mofid, 2011).
Richard states that "Earned Value Management is the use of an integrated
management system that coordinates work scope, schedule, and cost goals and
objectively measures progress toward these goals. Earned Value Management
(EVM) emphasizes the planning and integration of a program's technical
performance, cost, and schedule, to support program manager's decisions." Beside
it uses progress against previously defined work plans to forecast such important
concerns as estimated completion costs, finish dates, and the effectiveness of
corrective action plans. Earned Value is the measurement of what was physically
received for what was actually spent, or the value of work accomplished (Richard,
2001).
The most adopting definitions of EVM is it is a management methodology that combines
scope, schedule, and resource measurements to assess project performance and progress,
by the integration of the three key elements of projects which are schedule, work scope,
and cost.
2.3. Origins and Evolution of EVM
2.3.1. History of EVM development
2.3.1.1. Industrial Engineering Origins
EVM was initially conceived by industrial engineers in the USA, such as Fredrick W.
Taylor, Henry L. Gantt, and others in late 19th century (Fleming & Koppelman, 2005).
They compared ‘planned standards’ with ‘earned standards’ and ‘actual expenses’ in their
early concepts, and identified ‘cost variance’ as the difference between the actual costs of
performing work, and value of the achievements according to their estimated or budgeted
11
costs (Moski, 1951). The Earned Value approach was found to be more valuable in a
project environment – rather than ongoing operations (Fox, 1996).
2.3.1.2. Program Evaluation and Review Technique
PERT was introduced by the US Navy in 1958. The technique simulated development
planning with a logic diagram, and could assess statistical probability of achieving the
project plan objectives. Unfortunately, computers were not widely available to implement
the complex PERT calculations. The PERT approach was not as successful as the Critical
Path Method (CPM) which was being used in construction at the time. PERT/Cost in 1962
included calculation of actual cost, and comparison of that with the value of work
performed (now EV) to indicate cost status. It also compared value of work performed with
the cost and work value budget (now PV) to show schedule status (Paige H., 1963).
PERT/Cost was ultimately not widely adopted, but its underlying concepts became the
basis for EVM.
2.3.1.3. Cost/Schedule Control Systems Criteria (C/SCSC)
Initiated by US Air Force in 1965, C/SCSC included Earned Value methodology
(Christensen, 1990) . It was later developed by US Dept. of Defense (DoD) in 1967 and
applied to new weapons systems development, such as the Minuteman Missile program.
C/SCSC established 35 criteria or standards for compliance by industry contractors, and
provided DoD with some assurance of the final cost of new systems on open-ended
contracts. At the same time, corporations in the USA were investigating planning and
control systems such as Cost and Schedule Planning and Control (CSPC) (Saitow, 1969)
and the Accomplishment/ Cost Procedure (ACP) (Block, 1971) for reporting cost and
schedule to executive levels in meaningful ways. Both of these approaches have marked
similarities to EVM techniques.
2.3.1.4. EVMS Standard
The Earned Value Management System (EVMS) was developed by US industry
associations in 1996, with the National Defense Industry Association (NDIA) as the lead.
12
In the process, the team rewrote and simplified the 35 criteria in C/SCSC into 32 criteria,
but retained the essential components. Some key terms were renamed (e.g. BCWS to
Planned Value) in order to increase acceptance in industry. At the same time, many
practitioners and academics were documenting the costs and benefits of EVM.
(Christensen, 1998). The EVMS standards were issued (NDIA, 1998) by ANSI/EIA
(American National Standard Institute / Electronic Industry Association) and were
subsequently adopted by the Project Management Institute as a Practice Standard (PMI,
2005).
DoD came up with criteria for how to do cost and schedule control systems. As this was
documented and refined, it became widely accepted in the commercial world. In its current
state, it is an ANSI standard (748) – referred to as the Earned Value Management Systems,
or EVMS. EVMS has 32 guidelines that was summarized into five major areas:
1. Organization (5 guidelines)
2. Planning, Scheduling and budgeting (10 guidelines)
3. Accounting Considerations (6 guidelines)
4. Analysis and Management Reports (6 guidelines)
5. Revisions and Data Maintenance (5 guidelines)
The Project Management Institute (PMI) recently updated their Project Management to
include more of the EVM basics but did not include all 32 guidelines. It is often debated
whether all 32 guidelines are even needed to do EVM (Deltek, 2008). In place of these 32
criteria, the PMI-EVM provides in its Chapter 4 Guidance for the use of EVM Practices a
simplified set of ten practices in two groups (PMI, 2005). It shows the interdependence of
the fundamental practices of EVM and project management. Those are summarized as:
A. Establish a performance measurement baseline (PMB)
1. Decompose work scope to a manageable level
2. Assign unambiguous management responsibility
3. Develop a time-phased budget for each work task
4. Select EV measurement techniques for all tasks
13
5. Maintain integrity of PMB throughout the project.
B. Measure and analyze performance against the baseline
6. Record usage during project execution
7. Objectively measure the physical work progress
8. Credit EV according to EV techniques
9. Analyze and forecast cost/schedule performance
10. Report performance problems and/or take action
The project manager can use EVMS as a guideline to manage the project and Earned Value
Analysis technique to measure the project performance. Generally, EVM progress timeline
can be show in the following Figure.
PERT/Cost in 1962
C / SCSC ………..1967-1996
EVMS; ANSI / EIA Standard in 1998
Simplified EVM Terminology, published by PMI in 2000
Practice Standard for EVM published by the PMI in 2005
Figure 2. 1 EVM progress timeline
2.4. EVM Terminology
PMI (2005) classifies EVM terminology into two categories: (1) key parameters of EVM,
including Planned Value (PV), Earned Value (EV) and Actual Cost (AC), and (2) EVM
14
measures (variances, indices and forecasts). Key parameters are straightforward in their
formulation.
2.4.1. Key Parameters of EVM
2.4.1.1. Planned Value (PV)
It is also known as the Budgeted Cost of Work Scheduled (BCWS), represents an initial
estimate for planned work. It is the typical information provided on Project Budgets and
produced by estimating departments. It is provided by quite well established procedures to
evaluate planned costs and has been incorporated by EVM to enhance the set of tools their
practitioners are able to offer in their consulting work. It is based on a Project Breakdown
Structure that does not necessarily follow the set of operations that would flow on site. Site
planning will inform the expected amount of budgeted work that should be accomplished
according to a progress elapsed duration.
2.4.1.2. Earned Value (EV)
It is also known as Budgeted Cost of Work Performed (BCWP), represents the amount of
work that has actually been accomplished to date, expressed as the initial budget for that
work. For the moment, it should be mentioned that such figures of Planned and Earned
amounts to be called value should be at least correct in terms of estimating procedures.
Moreover, if it is to represent value for the client, this can only be accepted with the indirect
help from microeconomics: if it has rationally been accepted as the amount of money to be
paid for the project, total estimated price and value might be equated according to client’s
views.
2.4.1.3. Actual Cost (AC)
It is also known as the Actual Cost of Work Performed (ACWP), represents true cost of
work performed to date. In order to provide feedback information on actual costs, planning
and control systems should be equipped with company accounts linkages or other
mechanism to estimate and take notice of real costs (PMI, 2005), (Fleming and Koppelman,
2010). The timely evaluation of actual costs might prove to be a major burden to apply
15
EVM. It can be said that during the course of a project only estimates of real costs are
available, with their inherent probability nature in terms of accuracy.
2.4.2. Performance Measure
EVM measures, the second category of terms to be defined, make use of a combination of
previous key parameters.
2.4.2.1. Schedule Variance (SV)
Schedule Variance (SV) is calculated as SV= EV – PV. It represents how much the project
is ahead (SV>0) or behind (SV<0) schedule. As both EV and PV use cost estimates taken
from the initial budget, SV takes care of time performance. Notwithstanding, it might
happen that the project is taken as behind schedule (EV<PV) due to errors in the initial
budget. Suppose that a great number of out of schedule activities was performed but their
cost was underestimated and that overestimated scheduled activities were left behind. SV
calculations will inform that a great amount of costs should be already allocated, due to the
overestimated scheduled activities, what will not be compensated by the underestimated
out of schedule activities that were actually performed.
2.4.2.2. Cost Variance (CV)
Cost Variance (CV) CV is calculated as CV= EV – AC. It represents how much the project
is under (CV > 0) or over budget (CV < 0) (PMI, 2005); (Fleming and Koppelman, 2010).
It essentially measures cost variations, but is also subjected to errors for initial estimates in
connection to EV. As AC should be evaluating with real costs during various stages of
construction, there is a burden on the cost control system to produce such figures, what
might end up in calculating AC through another set of estimates of actual costs.
2.4.2.3. Schedule Performance Index (SPI)
Schedule Performance Index (SPI = EV/PV) represents the rhythm of production, i.e., the
rate of converting planned cost into Earned Value. It provides the same information as SV,
but now in relative terms. It varies around 1: SPI greater than one indicates that time
16
performance is better than expected. Sources of inaccuracy for this index are the same as
discussed for SV.
2.4.2.4. Cost Performance Index (CPI)
Cost Performance Index (CPI=EV/AC) represents how efficiently resources are being
used. CPI represents the rate of converting AC in EV (PMI, 2005), (Fleming and
Koppelman, 2010). A CPI smaller than 1 indicates that the project is heading to a cost
overrun, since what has been achieved do not correspond to what has been estimated, for
the same set of activities. The only explanation is that costs are increasing in comparison
with what has been estimated, or as before for CV, activities whose costs are added up to
comprise EV were overestimated in the initial budget. The following figure shows the
relationships among the basic EVM performance measures. These variances, indices, and
forecasts can be used to answer the key project management questions raised Table 2.4.
Figure 2. 2 EVM performance measure (Source: PMI, 2005)
The following Table 2.3 shows what EVM performance measures indicate about a project
in regard to its planned work schedule and resource budget.
17
Table 2. 1 Interpretation of basic EVM performance measures
2.4.3. Predicting the Future with EVM
All of the performance measures help PMs to monitor the progress of the project both from
a cost and schedule point of view. Therefore, EVM acts as an early warning system that
helps PMs to solve problems and exploit opportunities during project execution. Besides,
these measures and indicators are also used to make predictions about the future
performance of the project. However, the construction cost estimation practice in Ethiopia
clearly indicates that the knowledge and experience of construction cost estimation of the
contractors and consultants is very poor. This poor construction cost estimation practice
has contributed its own negative impact on development of the construction industry. Due
to this most contractors are delivering poor quality and delayed projects as well as suffering
bankruptcy. There are also cases whereby projects are executed at excessively higher
construction costs from time to time (Tadesse Y. , 2006). The next section will describe
how cost and time forecasts are made using EVM.
2.4.3.1. Cost forecasting
First of all, the predictive power of the cost performance measures is considered. Here the
focus lies on predicting the final cost of the project. This final cost will be referred to as
the Estimate at Completion (EAC). The EAC consists of the Actual Cost (AC), the cost
that has been spent so far and an estimate of the cost of the remaining work (Estimate to
Performance measures Schedule
Cost
SV>0& SPI>1.0 SV=0&SPI=1.0 SV<0 &SPI<1.0
CV>0 & CPI>1 Ahead of schedule
Under budget
On schedule
Under budget
Behind schedule
Under budget
CV=0 &
CPI=1.0
Ahead of schedule
On budget
On schedule
On budget
Behind schedule
On budget
CV<0 &
CPI<1.0
Ahead of schedule
Over budget
On schedule
Over budget
Behind schedule
Over budget
18
Completion, ETC). In some literature, ETC is also referred to as Planned Cost of Work
Remaining (PCWR). It can be calculated as follows:
𝐸𝑇𝐶 = ((𝐵𝐴𝐶 − 𝐸𝑉))/( 𝑝𝑒𝑟𝑓𝑜𝑟𝑚𝑎𝑛𝑐𝑒 𝑓𝑎𝑐𝑡𝑜𝑟)
Several different formulas exist to calculate the EAC, depending on the performance factor
that is used to calculate the ETC.
2.4.3.2. Duration forecasting
EVM provides an organization with the capability of practicing ‘‘management by
exception’’ on its projects. This practice contributes greatly to the efficiency and
effectiveness of project management, by allowing managers and others to focus on project
execution and invoke control actions only when and where they are needed (PMI, 2005).
EVM has also been used to predict the final duration of projects. This is done analogue to
forecasting the EAC. It can be calculated as follows:
𝐸𝐴𝐶𝑡 = (BAC/SPI )/(BAC/months)
Generally, in the following table the forecasting methods can be summarized.
19
Table 2. 2 Forecasting indicators by EVM Technique (Source: PMI, 2005)
Indicator Equation Interpretation
Budget at
Completion
(BAC)
-
BAC represents total budget at completion; at
completion
PV=BAC
Estimate to
complete
(ETC)
𝐸𝑇𝐶 = 𝐵𝐴𝐶 − 𝐸𝑉 Cost to complete the project if all packages
remain achieving the goals of time and cost,
irrespective of what happened to EV
𝐸𝑇𝐶 =𝐵𝐴𝐶 − 𝐸𝑉
𝐶𝑃𝐼
Cost to complete the project assuming that
current cost performance will remain the same (as
occurred up to EV) throughout the rest of the
project
𝐸𝑇𝐶 =𝐵𝐴𝐶 − 𝐸𝑉
𝐶𝑃𝐼 ∗ 𝑆𝑃𝐼
Cost to complete the project assuming that
current performance cost and schedule
performance will remain the same as occurred up
to EV throughout the rest of the project
Estimate at
completion
(EAC)
𝐸𝐴𝐶 = 𝐴𝐶 +(𝐵𝐴𝐶 − 𝐸𝑉)
CPI
= 𝐵𝐴𝐶/𝐶𝑃𝐼
Future cost performance will be the same as all
past cost performance
EAC=AC+(BAC−EV)∗(ACi+ACj+ACk)
(EVi+EVj+EVk)
Future cost performance will be the same as the
last three measurement periods (i,j,k)
𝐸𝐴𝐶 = 𝐴𝐶 +(BAC − EV)
(CPI ∗ SPI)
Future cost performance will be influenced
additionally by past schedule performance
𝐸𝐴𝐶 = 𝐴𝐶 +(BAC − EV)
0.8 ∗ CPI + 0.2SPI
Future cost performance will be influenced
jointly in some proportion by both indices
Estimate at
completion
(EACt)
𝐸𝐴𝐶𝑡 = BAC/SPI
BAC/months
The estimated completion time for the project if
the work continues at the current rhythm
Variation at
completion
(VAC)
𝑉𝐴𝐶 = 𝐵𝐴𝐶 − 𝐸𝐴𝐶
Cash balance at completion
20
According to Richard states analyzing the cause of a variance, the project manager can
identify significant differences between the planned and actual cost performance.
Generally, a negative variance can be viewed as bad and a positive variance as good,
although this may not always be the case. For example, a positive variance may be caused
from the contractor's front-loading of schedule of values, thereby robbing resources
intended for later tasks. Another indicator of problems during variance analysis is if no
variances are reported over several periods. This can indicate a lack of tracking on the
contractor's part since it is difficult to forecast work with such accuracy. During analysis,
if the cumulative CV and SV both reflect negative trends, the task being performed may
be very complex, the contractor may have underestimated the scope of the task, or the
method of calculating Earned Value may not fully take credit for work as it is performed.
Positive values for both variances may be due to good contractor performance, a simple
task, or an overly generous contractor estimate for the effort (Richard, 2001).
Figure 2. 3 EVM graph including trend analysis (taken from the Earned Value
management: APM Guidelines, 2008)
21
The above Figure demonstrates the performance of the project using the Earned Value data
elements. It provides a quick view of project status and predicting trends and may be used
as bases for forecasting the project end conditions. It can also include if required the EAC
and the forecast completion date for the previous reporting periods. This include EVM
main variables, variances and forecasting simulations.
An overview of all EVM key parameters, performance measures and forecasting indicators
can be summarized in Table 2.7, which was found in the book “Measuring Time”
(Vanhoucke, 2010).
Table 2. 3 Overview EVM metrics (Source: Vanhouke Mario, 2010)
Earned Value key parameters
Planned value (PV)
Actual cost(AC)
Earned Value (EV)
Earned schedule (ES)
Earned Value Performance Measure
Cost performance index (CPI)
Cost variance (CV)
Schedule performance index
(SPI)
Schedule Variance (SV)
Schedule performance
index (SPI(t))
Schedule Variance (SV(t))
Translation to time units
Time variance (TV)
Earned duration(ED)
Earned Value Forecasting Indicators
Cost
Estimate at completion(EAC)
Duration
Estimate at completion
(EAC(t))
Duration
Estimate at completion
(EAC(t))
22
2.5. Earned Value Method
Earned Value method (EVM) is a systematic approach to the integration and measurement
of cost, schedule, and technical (scope) accomplishments on a project or task. It provides
both the government and contractors the ability to examine detailed schedule information,
critical program and technical milestones, and cost data. It supplies organizations with the
methodology needed to integrate the management of project scope, schedule, and cost
(PMI, 2005).
EVM focus on forecasting final costs and project duration, what is deemed crucial to alert
managers and enforce their reaction to overcome delays and cost overruns. Management
tools that might bring project again on schedule are not provided by the EVM technique,
but it might be taken that they do not exceed what is normally available in the manager’s
tool box. This is to say that the analysis of variations and a clear display of project goals
are the key elements to trigger standard management efforts that would naturally induce
appropriate decisions leading to project success (PMI, 2005), (Acebes et al., 2013). EVM
can play a crucial role in answering management questions that are critical to the success
of every project. The following Table 2.2 shows the relationship between those project
management questions and the EVM performance measures.
Table 2. 4 EVM and basic project management questions (Source: PMI, 2005)
Project management question EVM performance measures
How are we doing cost wise? Cost analysis & forecasting
o Are we under or over our budget? o Cost variance (CV)
o How efficiently are we using our resource? o Cost performance index (CPI)
o How efficiently must we use our remaining
resource?
o To complete performance index (TCPI)
o What is the project likely to cost? o Estimate at completion (EAC)
o Will we be under or over budget? o Variance at completion (VAC)
23
o What will the remaining work cost? o Estimate to complete (ETC)
How are we doing time wise? Schedule analysis & forecasting
o Are we ahead or behind schedule? o Schedule variance (SV)
o How efficiently are we using time? o Schedule performance index(SPI)
o When are we likely to finish work? o Time estimate at completion (EACt)
According to PMI (2005), if the application of EVM to a project reveals that the project is
behind schedule or over budget, the project manager can use the EVM methodology to help
identify:
Where problems are occurring?
Whether the problems are critical or not
What it will take to get the project back on track?
2.6. Project Management
The PMBOK have defined a project as “a temporary endeavor undertaken to create a
unique produce, service or result” (PMI, 2004) and “unique, transient endeavors
undertaken to achieve a desired outcome” (APM, 2006). Project Management is the
planning, organizing, directing, and controlling of company resources for a relatively short-
term objective that has been established to complete specific goals and objectives
(Kerzener, 2001).
Kerzner has defined a project more specifically, as “any series of activities and tasks that
(1) have a specific objective to be completed within certain specifications, (2) have defined
start and end dates, (3) have funding limits (if applicable), (4) consume human and non-
human resources, and (5) are multi-functional (i.e. cut across several functional lines)”
(Kerzner, 2003). Those five characteristics respectively lead to: dedicating resources for
their completion, time schedules for their organization, relationships between their
components, responses to their uncertainty and the communication between their
24
stakeholders. The study will examine all of those items in this thesis, through the lens of
project performance management.
Project management institute addresses EVM in its Chapter 7 on Project Cost
Management. The section on Cost Control identifies five tools and techniques: Cost
Change Control System; Performance Measurement Analysis; Forecasting; Project
Performance Reviews; Project Management Software; and Variance Management (PMI,
2004). Since all of those techniques are directly or indirectly related to Earned Value
methods.
2.7. Construction Project Management
According to Gower (2007) the purpose of project management is to “foresee or predict as
many of the dangers and problems as possible and to plan, organize and control activities
so that projects are completed successfully in spite of all the risks”. This need plans early
before resources committed there is need of organization to have management technique,
and the process must continue until all work is finished. So Earned Value management
technique to an organization may be able to help the organization. However, the level of
construction project management practice in terms of adapting general project management
procedures, project management functions, tools & techniques to be unsatisfactory in
Ethiopian construction industry (Tadesse A. , 2016). Particularly the level of practice in
terms of safety, risk and time management was found to be very low. This result also
agreed with Hailemeskel, who states from the Ethiopian construction industry context of
management control practice of the researcher conducted to the following conclusions
(Hailemeskel, 2013).
There is lack of modern Scheduling techniques, planning and evaluation practice at
project level.
Project management and control capability in terms of time, manpower, material,
finance, and quality control are not up to standard.
There is lack of knowledge for project control and management tasks.
25
There are no well-developed procedures, guidelines and standards for project
management
Besides Kerzner, state that “the project manager must control company project resources
within time, cost, and performance and most companies have six resources those are
Money, Manpower, Equipment, Facilities, Materials and technology” (Kerzner, 2003).
Even if Heagney argue that the role of the project manager is to help the team get the work
completed (Heagney, 2012).
2.7.1. Project Time management
PMI defines project time management as the effective and efficient use of time to facilitate
the execution of project, which starts from planning, scheduling and controlling the project
to achieve the time objectives (PMI, 2004). It includes the processes required to ensure
timely completion of the project (Duncan et al., 1990).
Techniques that are usually used in managing project time are as follow:
Critical Path Methods (CPM); Calculated a single, deterministic early and late
start and finish date for each activity based on specified, sequential network logic
and a single duration estimate. The focus of CPM is on calculating float in order to
determine which activities have the least scheduling flexibility (Clough, 2000).
Program Evaluation and Review Technique (PERT); uses sequential network
logic and weighted average duration estimate to calculate project duration.
Although there are surface differences, PERT differs from CPM primarily in that
uses the distribution’s mean (expected value) instead of money likely estimate
originally used in CPM (PMI, 2004).
Bar Chart; it’s the simplest project management technique for scheduling,
planning and controlling. It shows graphically or in tabular form the daily costs and
accumulated costs over a designated period. In projects of normal delivery or stable
performance, the general contractor creates the bar chart once an award is made and
each bar represents the beginning, duration and completion of some designated
26
segment of total project. Together, the bars make up a time schedule for the entire
job (Ritz 1994 & Degoff et, 1999).
2.7.2. Project Cost Management
Project cost management includes the processes required to ensure that the project is
completed within the approved budget (Duncan et al., 1990). Although management
discretion may occasionally dictate otherwise, an effort is usually made to achieve gains in
time with the least possible increase in project cost. If project management has to make
schedule adjustments at an additional cost, it is necessary to understand how the costs of
construction operations vary with time (Clough, 2000).
Two techniques that are usually used in managing project cost are as follow (Clough,
2000):
Cash Flow; One of managing cash flow activities is to make sure that there is still
enough money to cover the cost of performing project-employees’ payment,
charges for material, subcontractor invoices and others suitable with the established
estimation. The key to manage cash flow is to ensure that cash comes in balance
with what goes out. Key effective in cash flow control is aggressively addressing
negative cost variance and cost inefficiencies as soon as they are identified, rather
than hoping that things will get better as the project goes on. Even when projects
have only positive cash flow and cost variances, it is important not to let that flow
and variance become worse. A concentrated effort should be made to keep it that
way because as stated above it becomes difficult to get back on track.
Cost Plan; (Spinner, 1997) mentioned that the cost planning starts with the
proposal for the project. The cost section of a proposal may consist of tabulations
of the contractor’s estimated costs for such elements as labors, materials,
subcontractors, equipment and others. In addition, the proposal might also include
an amount for contingencies, to cover unplanned expenses. It can conclude that cost
plan is the task of allocating sums to the various project activities scheme from
starting the first task to finishing the last one.
27
Once the project starts, it is necessary to keep track of actual cost and committed cost so
that they can be compared to cumulative budgeted cost (CBC). After this has been done,
the project cost performance can be analyzed by looking at the total budgeted cost, the
cumulative budgeted cost, the cumulative actual cost and the cumulative Earned Value.
They are used to determine whether the project is being performed within budget and
whether the value of the work performed is in line with the actual cost. So in order to meet
this requirement EVM techniques fundamentally applicable.
2.8. Traditional Cost Management vs. Earned Value
Under what Fleming & Koppelman (2005) describe as traditional cost management, a two-
dimensional approach is employed: the simple relation of planned costs to the actual costs.
Using this approach, it is difficult if not impossible to determine the true cost performance,
since a comparison between the budgeted plan and actual costs can be faulty and
misleading. Beside these are Variance or Deviation Analysis based on direct differences or
Earned Value analysis between planned and actual conditions (Harrison, 1997). This study
called these two project performance analysis approaches as Simple Deviation Analysis
and Earned Value Deviation Analysis. Harrison presented the various and commonly used
simple deviation analyses and claimed that these are inadequate, often misleading and
sometimes meaningless.
2.8.1. Simple Deviation Analysis
Time Performance: Scheduled start or finish time against Actual start or finish time;
Schedule date of a milestone against Actual date when the milestone was reached;
Cost Performance: Budgeted cost against Actual Cost; Measured value against Actual
cost; Budgeted man-hour against actual man-hour; Budgeted unit cost against Actual unit
cost; Budgeted percentage completion against Actual percentage completion.
Harrison indicated that simple deviation analysis does not use sufficient information to
determine performances. Harrison generally put forward the following limitations in using
simple deviation analysis.
28
It is historic than forward looking.
It does not indicate performances clearly.
It is not sensitive enough for early gauging.
It does not use all the data available.
It requires considerable subjectivity for interpretation.
It falls short of integrating cost and time performance criteria.
It falls short of indicating accountability and responsibility.
In contrast, Earned Value project management adds a third dimension: the amount of work
accomplished or the value of the work performed. With this third dimension, a project
manager has a better measure of "what they got for what they paid." By comparing the
Earned Value to the planned cost for a given period, the project manager can now identify
whether the project is ahead or behind schedule. Similarly, by comparing the Earned Value
to the actual costs expended during a given period, a determination of whether the project
is underrunning or overrunning its budget can be made (Fleming & Koppelman, 2005).
2.9. EVM and the Project Management Process
EVM is a comprehensive methodology used to manage projected efforts. The methodology
addresses many project management areas, including project organization, planning,
scheduling and budgeting, accounting, analysis, reporting, and change control (Flemming,
1998). EVM also incorporates specific mechanics to include the use of the work breakdown
structure (WBS), performance curves (S-curves), as well as a defined set of performance
metrics. EVM is among the first project management methodologies to be codified by
national standards setting organizations (ANSI/EIA, 1998).
In order to meet the requirement of the project, project management process is
accomplished through the following sequential and intergraded project phases (PMBOK,
2008); (Williams, 2008), (Bower, 2007) and (PMI, 2005). Initiating, Planning, Executing,
Controlling and close out. The effective use of EVM requires that it is used on projects
where the principles of good project management, as outlined in A Guide to the Project
Management Body of Knowledge (PMBOK_ Guide), are being applied. To establish a
29
basic foundation for understanding EVM’s role in effective project management, it is
important that examine the relationship between EVM and the PMBOK_ Guide’s Project
Management Process Groups and Knowledge Areas. Project management is primarily a
matter of planning, executing, and controlling work (PMI, 2005). The following table
indicates the areas of project management to which EVM is fundamentally most applicable.
Table 2. 5 EVM and project management process (Source: PMI, 2005)
Knowledge Areas Process Groups
Initiating Planning Executing Controlling Closing
Integration Ҳ Ҳ Ҳ
Scope Ҳ Ҳ
Time Ҳ Ҳ
Cost Ҳ Ҳ
Quality
Human Resources
Communication Ҳ Ҳ Ҳ
Risk Ҳ Ҳ
Procurement Ҳ Ҳ
Key
One or more project management process where EVM is fundamentally applicable
One or more project management process for which EVM is of little significance
No project management process is mapped here
Project management institute states that, these criteria are very important, they shall be
read, studied and applied as key procedures to achieve success in the application of EVA.
Ҳ
30
2.9.1. Project Planning Process
In the planning process, the means for assessing physical work progress and assigning
budgetary Earned Value also needs to be established. In addition to routine project
management planning, Earned Value measurement techniques are selected and applied for
each work task, based on scope, schedule, and cost considerations. According to PMI
(2005), project planning is mostly a matter of determining:
What work must be done (scope) and in what pieces (work breakdown structure)
Who is going to perform and manage the work (responsibility assignment matrix)
When the work is going to be done (schedule)
How much labor, materials, and related resources the work is going to require
(cost).
2.9.2. Project Execution Process
In the project execution process, EVM requires the recording of resource utilization (i.e.,
labor, materials, and the like) for the work performed within each of the work elements
included in the project management plan. In other words, actual costs need to be captured
in such a way that permits their comparison with the performance measurement baseline.
Project execution is primarily a matter of doing the planned work and keeping workers and
managers informed (PMI, 2005).
2.9.3. Project Monitoring and Controlling
Project control focuses mostly on monitoring and reporting the execution of project
management plans related to scope, schedule, and cost, along with quality and risk. In other
words, project control is a process for keeping work performance and results within a
tolerable range of the work plan. In the project control process, EVM requires that physical
work progress be assessed and budgetary Earned Value be credited (using the selected
Earned Value measurement techniques), as prescribed in the project management plan.
With this Earned Value data, the planned value data from the performance measurement
baseline, and the actual cost data from the project cost tracking system, the project team
31
can perform EVM analysis at the control account and other levels of the project work
breakdown structure, and report the EVM results as needed (PMI, 2005).
Controlling is a combination of two elements: monitoring and taking corrective action
(PMI, 2004). PMI defines control as “comparing actual performance with planned
performance, analyzing variances, assessing trends to effect process improvements,
evaluating possible alternatives, and recommending appropriate corrective action as
needed.” Therefore, monitoring, controlling and evaluation is contingent of the
appropriateness of the plan (base line) against which performance is compared with. In this
regard, ERA’s practices, both in terms of its baseline establishment and performance
evaluation and taking corrective actions has considerable drawbacks when compared to
this best practices (Solomon, 2015). The key performance indicators used the planned
values against which performance is compared are not established systematically. Solomon
states in ERA’s case as well, although the contractors produce the work programs (with
associated resource deployments schedule) and reporting may reveal that such programs
are not being implemented, timely corrective actions are not taken.
The selection of a project control system is an important element in the management of a
project or program (Shtub et, 2005) and the lack of such systems has been identified with
a major role as a cause of project failures (De Falco & Macchiaroli,, 1998) . However,
EVM was developed by the US Department of Defense (DoD) as a project control system
that specifically integrated the time and cost dimensions. Abba, states that a work
breakdown structure (WBS) is used to provide the integration necessary between these two
very different dimensions (Abba, 1997). A WBS requires the hierarchic structuring of the
project using its major components and subcomponents. The lowest level of the WBS is
the work package, which comprises a set of related tasks to be performed by a single
organizational unit (PMI., 2001).
Some attention has been paid to determining the optimum size of such work packages (Raz
& Globerson, 1998) in order to maximize benefits while minimizing the necessary
administrative effort. As a performance management methodology, EVM adds some
critical practices to the project management process. These practices occur primarily in the
32
areas of project planning and control, and are related to the goal of measuring, analyzing,
forecasting, and reporting cost and schedule performance data for evaluation and action by
workers, managers, and other key stakeholders. See the following Figure 2.2
Figure 2. 4 EVM and the basic project management process (Source: PMI, 2005)
Once the project comes to an end, the closure must be planned and scheduled, monitored
and controlled-as if it is a project in its own right. This administrative closure work is
carried out in addition to the activities already planned to complete the production of
project deliverables (Frigenti and Comninos, 2002). It is also emphasized that both of these
plans need to be monitored and controlled to ensure timely and effective completion of the
project.
2.10. Construction Performance Measure Using Earned Value
Technique
EVA is a valuable technique to determine real gains and losses on projects and provides a
means to balance gains/losses and maximize the gains. EVA is a powerful tool to control
simultaneously physical and cost performance. It provides integrated schedule (time),
progress and cost management information related to scope and procurement, quality and
risks (Carlos, 2004). On the other hand, Kerzner considers EVA a relevant maturity
differential in project management. Managing costs using EVA is referred to as “managing
with open eyes” because the manager can clearly see what was planned, what was
performed and the actual costs. This is a powerful tool in the decision making process. In
Plan
Scope
Schedule
cost
Control
Measure
Analyze
report
Execute
Work
Record
33
the day-to-day activities of the project manager, EVA provides “alarm” signals and
facilitates decisions that keep the project on time and on budget (Kerzner Harold, 1998).
Kerzner (2003) recognizes the value of EVM as a risk monitoring tool. Specifically, “it
provides a basis to determine if risk handling actions are achieving their forecasted results”.
EVM allows the performance and progress of a project to be assessed at a single point in
time, usually repeated on a regular basis such as weekly or monthly. Projects are composed
of many activities (sometimes hundreds or thousands) with differing durations and start
times. Therefore, at any point during the project some activities have been completed, some
are underway, and some have not been commenced. The only possible exception arises
when a project is divided into separate phases that do not overlap, and the point of EV
assessment happens to coincide with the period of inactivity between those phases. At that
instant, it would be possible for no activities or work to be in progress.
Raveesh L. & Sundip S., (2015) states Earned value is a project control technique which
provides cost and schedule performance measurements. It compares actual
accomplishment of scheduled work and associated cost against an integrated schedule and
budget plan. EVM provides project managers and the organization with triggers or early
warning signals that allow them to take timely actions in response to indicators of poor
performance and enhance the opportunities for project success. Once a project has
advanced to a stage of performance, the consistent and constant flow of information on the
true status of the project is essential. The fundamental principle of EVM is that the patterns
and trends of performance, when compared against a soundly developed baseline, can be
excellent predictors of the future project performance. Feedback is critical to the success
of any project. Getting the relevant feedback in time enables project managers to identify
problems early and make adjustments that keeps a project on time and on budget. So one
of the most effective performance analysis and feedback tools for controlling construction
projects is EVM.
34
2.11. Current Status of Earned Value Management (EVM)
Ng shi cia (2015) express that nowadays, the EVM is an effective performance monitoring
tool and valuable in any type of projects. The EVM becomes the great need for current
project management environment because of cross-industry collaboration. EV practice has
adopted widely in defense, energy, product, and software development projects.
According to Kim et al., (2003) stated that 82% of project managers that has used the EVM
is accepted or strongly accepted the methodology. There are many EVM users either fully
or partially implemented or computerized to help the EVM processes. The EVM was
strongly accepted by the project manager is a proof that the EVM can effectively manage
well the project performance. Bower (2007) indicated in 1995 International Performance
Management Council was created by the defense departments of Australia, Canada, and
the USA to facilitate mutual development in the EVM field. Today, Australia and Canada
have adopted this technique by establishing the US similar EV criteria and industry
standards in government and private sectors (Bower, 2007). Furthermore, Japan joined the
EVM community through its Ministry of Construction (Song, 2010). In European
countries, the EVM techniques were widely adopted in UK and Sweden (Ng shi cia, 2015).
However, De Marco & Narbaev (2013) stated that the construction industry is still facing
difficulties to adopt the EVM in the project that can help managers to effectively monitor
the project and predicting the result of the project. In order to enhance the adoption of EVM
in the construction industry, the choice of EVM form with an appropriate selection of its
criteria is very important in order to monitoring and controlling the project well. There are
many proper selections of EVM practice standards such as PMI,2011, ANSI/IEA-748 (the
US National Defense Industrial Association), DoD's C/SCSC (the US DoD), and similar
EVM guides for the UK, Australia, and Canada (Song, 2010).
As a project management its application is not common in practical for project evaluation
and control technique in Bahir Dar construction industry. The study identifies the reasons
for this limited adoption, their practice to improvements of EVM and increase its
acceptance for the application of Earned Value concept. When the researcher conducted
35
preliminary interview with few road construction project managers in Bahir Dar there is
lacks of construction monitoring &controlling techniques. If this problem is not well
addressed, it may lead project delays, cash flow problems and does not meet users need
due to the lack of provide serviceability of the road on the schedule time. In order to solve
these problems, a substantial effort on managing the construction process must be provided
and could not be done without an effective performance monitoring tool. Widespread,
using of EVM techniques the study measures the performance of the project in progress,
and provides forecasts of the final results for two key dimensions of the project – time and
cost – at its completion. On that basis, EVM is useful control and communication technique
that should assist management in achieving the successful completion of the selection
project.
2.12. Early Warning Tool
Time and cost overrun usually occur in the beginning of the project but the project manager
do not realize until they cannot achieve the objective of the project (Alvardo and David,
2004). However, PMI states in order to minimize the time and cost overrun, EVA as a
project monitoring tool to monitor the progress of the projects. By using EVA, the project
manager can examine the true performance of the project to know the latest progress of the
project and identify the problem of the project. Earned Value provides an "Early warning"
signal for do corrective action. Early warning signal is given a notice to the project
managers when the project is in a trouble situation. This can provide alerts to the company's
management to avoid some crisis in the project.
Project managers can manage the project by referring the objective cost and time estimated
which can enhance the probability of the project success. Since Feedback is critical to the
success of any project. Timely and targeted feedback can enable project managers to
identify problems early and make adjustments that can keep a project on time and on
budget. Earned Value Management (EVM) has proven itself to be one of the most effective
performance measurement and feedback tools for managing projects (PMI, 2005). EVM
uses the fundamental principle that patterns and trends in the past can be good predictors
36
of the future. The Earned Value metrics are set up as a warning signal to detect in an easy
and efficient way in the project.
Furthermore, early warning signal can help the project team to reduce the risk or
uncertainty in the project. The project manager can have a clear picture about the current
stage of the project and know the current risk may occur in the project. The warning signal
can alert the project manager to do the contingency plan in order to mitigate the risk that
happen in the project. This can support by Ng shi cia (2015) as EVA act as an early warning
project management tools to identify the problem before loss control.
2.13. Problems Associated with Earned Value
There are numerous factors or resistance that could have slowed the adoption of EVM.
This resistance is associated with a perception that the planning work and control rise in an
unjustifiable way, when using EV techniques. Antvik states that the resistance comes from
a cultural process of informality in the control of projects (Antvik, 1998). Brandon (1998)
identified several reasons for the lack of EVM adoption outside government agencies. (1)
Minimal awareness of EVM in commercial and corporate circles, including training
courses; (2) Data acquisition (for obtaining percent complete and actual cost numbers)
requires significant resources and time; (3) EVM reporting has not been handled in an
easily implemented manner; and (4) Significant employee resistance problems have
surfaced when EVM is put in place.
There have been many studies about the utility of EVM. Thamhain evaluated the popularity
of different project management practices. He surveyed 400 professionals who lead 180
projects (as managers, directors, etc.) in Fortune-1000 companies. They were asked about
the popularity and value of various performance evaluation techniques. A significant group
(41%) of the respondents stated that they had used EVM. However, when he asked about
value of the technique they placed EVM at a level below almost all of the techniques listed
(Thamhain, 1998). In attempting reconcile this apparent contradiction, Thamhain states
that the low utilization can be attributed to these barriers:
37
Lack of comprehension of how the technique works
Anxiety concerning the adequate use of the tool
Use of the tool requiring a lot of work and time consumption;
Tools trimming creativity in the use of other strategic
Inconsistency of the tool in managerial procedures/business processes
Method of control as a threat, concerning the freedom of the team
Vague and inaccurate purpose and its benefit
High cost of its implementation
Unsuccessful prior experience in the use of other techniques
Low familiarity with the technique
Fleming and Koppelman found that difficulty in applying EVM is about an adequate work
breakdown structure (WBS). If the work is subdivided in small packages of work, it will
represent a high cost of control and a lot of paperwork (Fleming and Koppelman, 2009).
On the other hand, a badly stratified subdivision may represent an inaccuracy of data,
concerning real costs and deadlines. This confirmation may be proved in the low
application of the Earned Value analysis in technology and marketing areas, where the
creative work is the variant in a scope previously defined, making its application limited
and directly related to the stability of a defined scope (Peterson & Oliver, 2001). They state
that, the more short-term projects grow, with reduced team and a generically defined scope,
the more the Earned Value Analysis, is not viable, due to inaccurate projections,
consequence of a badly defined scope and to high costs noticed by the entrepreneurs.
In the same way, Earned Value analysis is an adequate tool for the generation of reports of
work done, but not a managerial tool. They stated that an Earned Value analysis shows
only the performance obtained until that point – not the future forecast of the project
(McKay.J., & Marshall. P,, 2001). On the other hand, the empirical studies revealed that a
number of factors may impede the implementation of EVM, which is stated by the
following researcher: (Association National Security Industrial, 1980); (Little Inc., 1983 );
(Kim et al., 2003); (Brock, 1983); (Butler et al., 1993); and (Fleming and Koppelman,
2010).
38
Table 2. 6 Problems Related to EVM Implementation
2.14. Implementation Requirements and Benefit of the EVM
Flemming (1998) identified some of the essential requirements for proper implementation
of EV on all projects. The most important requirement is to have a clearly defined Work
Scope at the onset through establishment of a detailed and priced Work Breakdown
Structure (WBS); then establish an integrated bottom-up plan with scheduled Work
Packages that have estimated costs and resources, and estimated completion duration; and
Project Control through Measurements against Schedule: Project’s schedule performance,
project’s cost efficiency, and forecasting the final cost periodically. On the other hand, the
accuracy of estimated data and actual data and the time intervals for measuring are of
Problems related to EVM
Items taken /adapted from
Ass
oci
atio
n N
atio
nal
Sec
uri
ty I
ndu
stri
al,
19
80
Lit
tle
Inc.
, 1
98
3 &
198
4
Kim
et
al.,
20
03
Bro
ck,
198
3
Bu
tler
et
al.,
19
93
Fle
min
g a
nd
Ko
pp
elm
an,2
009
&
20
10
Difficulty in adequate work breakdown
structure (WBS) to apply EVM
High cost, complicated and burdensome
paper work
Poor understanding of EVM
Distrust and conflict between project
managers, project consulting and
government
Pressures to report only good news
Contract in fixed price that makes EVM
less attractive to client
Unavailability of cost and schedule
integrated data
39
paramount importance to its successful application (Smith,Winter, Morris & Cicmil, ,
2006).
Christensen points out that implementing EVM requires a cultural change, which requires
time and effort. Key policies and knowledge regarding Earned Value methodology must
be taught by the organization in order to facilitate adoption (Christensen, 1998). Also
Wideman states that the Earned Value technique is conceptually attractive; however, it
requires a great deal of effort to maintain it. EVM therefore needs a qualified team not only
to understand its requirements, but also to provide reliable information and many project
managers don't believe that the significant cost of implementing EVM is worth the limited
benefit. (Wideman, 1999).
From those varied perspectives, it is evident that EVM presents some effective features;
however, it presents great difficulty in data collection or in the low speed of information
generation. Terrel M. et al., assert that in order to effectively implement EVM, information
about project resource usage must be clearly defined. Failure to obtain that data creates an
inaccurate performance measurement baseline (PMB), with little relationship to the actual
situation (Terrel M. et al., 1998). According to Fleming & Koppelman, a key success factor
is preparing a suitable work breakdown structure (WBS). If the work is subdivided
excessively, control will be expensive and cumbersome. On the other hand, they point out
that a badly stratified subdivision may present inaccurate data on real costs and deadlines
(Fleming & Koppelman, 2005).
One survey of the Hong Kong construction industry Deng & Hung indicated that only a
small percentage of construction projects implemented an integrated cost/schedule control
system (Deng, M. & Hung, Y., 1998). In the construction industry, Earned Value concepts
could be readily applied. Almost all construction work is routinely divided into identifiable
packages, most deliverables are tangible, and typically costs are carefully tracked. But it is
quite evident that Earned Value has not been widely accepted as the preferred means of
monitoring, controlling and reporting cost status on construction projects (True, 2003).
40
Once the EVM System is designed and implemented on a project, there are significant
benefits to the contractor and to the customer. Contractor benefits include increased
visibility and control to quickly and proactively respond to issues which makes it easier to
meet project schedule, cost, and technical objectives. Customer benefits include confidence
in the contractor’s ability to manage the project, identify problems early, and provide
objective, rather than subjective, contract cost and schedule status. Project Managers
(PMs) may be required to use Earned Value management as one tool to monitor progress
and to develop cost and schedule forecasts for active projects. It is also used the provision
of more accurate management and financial reports. These assist in the better management
of cash flow and in the reporting of results to shareholders.
According to Sparrow Earned Value analysis provides a supplementary benefit to the
project because it offers a forecast of its final results. It demonstrates emerging cost and
schedule trends at an early point in the project – when there is still the possibility of
implementing corrective actions (Sparrow, 2000). Kerzner Harold considers EVA a
relevant maturity differential in project management. Managing costs using EVA is
referred to as “managing with open eyes” because the manager can clearly see what was
planned, what was performed and the actual costs. This is a powerful tool in the decision
making process. In the day-to-day activities of the project manager, EVA provides “alarm”
signals and facilitates decisions that keep the project on time and on budget (Kerzner
Harold, 1998). Moreover, Christensen listed main benefits of Earned Value are EV
provides a single management control system providing reliable data, and an integration of
work, schedule, and cost using a Work Breakdown Structure. The system also provides a
database useful for comparative analysis (Christensen, 1998). Most important of all, it is
an early warning signal for cost and time performances with projections of final cost and
time. It can help identify, address, and resolve problems timely (Schulte, 2001).
In addition, contractors are encouraged to implement EV because it improves their cash
flow when applied appropriately. A regular monitoring by the parties will make the
assessment of the Contractor’s claim for payment more efficient and judicious. Moreover,
the application of EV is useful not only at the project level, but also at the whole business
level. EVM leads to successful portfolio management: failing projects may stop and
41
resources may be shifted to a more successful project. Several authors have advocated the
use of EVM techniques to provide the justification for claims related to cost adjustments
and scope changes. They further advise that, if claims cannot be resolved and legal
remedies are pursued, EVM appear consistent with legal standards for substantiating cost
claims (Kauffmann et al., 2002).
Besides, EVM offers the choice to integrate the Risk Management (RM) within the Earned
Value Management, insights of one can be used to inform the other (Hillson, 2004a,
October 2004). Earned Value also helps us mange by providing data to enable objective
measurement of project status, providing basis for estimating the final cost, predicting
when the project will be complete, supporting the effective management of resource and
providing a means of managing and controlling change (APM, 2013) .
Alberto et al. compares project management with EVA and without EVA as shown in the
following table (Alberto et, 2004).
Table 2. 7 Differences with EVA and without EVA
Without EVA With EVA
Blind management Management with open eyes
Cost, time and progress separated Integrated cost, time and progress
Planned values compared with actual cost Earned Value Analysis
2.15. Research Gap
This chapter introduce the research evaluation of project performance and forecasting in
the context of Earned Value Management (EVM) techniques. This research wants to add
the relationship implication of performance of road infrastructure construction project and
Earned Value Management techniques in the context of Amhara Road Work Enterprise
construction project. Practically the study address activity cost based wise as well as month
wise plan value on Amhara Road Work Enterprise construction project. However, this
study is relatively new in Ethiopian context because there is limited studies.
42
Different research studies conducted on EVM techniques in various developing and
developed countries. They recognized that Earned Value Management (EVM) is one of the
few management techniques that are unique to construction project management. Actually
EVM is a standard section in every project management course and textbook, even though
no more organizations had actually applied it to manage projects practically. To increase
its adoption, the study also assesses project management professionals and others that are
expected to have knowledge on EVM technique at his/her place of work both from project
and office in the context of road construction sector for the contribution of EVM. Led it to
investigate EVM further, and to identify not only significant issues that might be hindering
its adoption – but also sound and practical improvements that could increase its utilization
in Bahir Dar city road constructions.
2.16. Summary of Literature Review
Earned Value is an important tool for monitoring and controlling project performance. It
is also included in any set of best practices in project management. It is a methodology for
evaluating project performance and progress by integrating project scope, schedule, and
cost (APM, 2006). EVM has been widely applied in various industrial sectors and many
studies have been conducted on EVM and its application in the industry. This paper
provides an analytic of EVM studies and its applications. EVM studies published in a
number of sources are reviewed. The key issues reviewed include effective implementation
of EVM requirement and benefit, behaviors of cost performance index, cost control
techniques, schedule performance index and time control techniques.
43
CHAPTER THREE
METHODOLOGY
3.1. Introduction
Research methodology is a way to systematically solve the research problem and research
methodology shall identify the research basis, research hypothesis or questions, research
design and research analysis (Abraham, 2008). This chapter presents the methodology that
is adopted in the study. It describes and discusses the research design, sampling technique,
data collection and data analysis used during the study and measurement of variables.
3.2. Research Design
According to Sekaran (2003) research design shows the detail of the study in relation to
purpose of the study, type of investigation, and the extent of researcher interference,
measurement and measures, unit of analysis, sampling design, data collection method and
data analysis are integral to research design. The study adopts a mixed method approach.
Both quantitative and qualitative research methods are used to explain the phenomenon.
In this study a questionnaire will be designed to collect primary data from client
representative, contractors and consultant. Interviews method also employed. Lastly
discussions and recommendations is drawn (Figure 3.1).
44
Figure 3. 1 Research Methodology Flow chart
3.2.1. Survey Research Design
Survey Research design is a valuable tool for assessing opinions and trend. Often, it is a
low cost and its ease of accessing information, where data can be collected more than one
cases at a single point in time for collective use of both qualitative and quantitative data of
two or more variables (Magigi, 2015). The use of this tool is used for addressing specific
objectives one, two and three of the study. The data is collected by sending a structured
open-ended and closed questions to respondents including senior project managers,
Engineers, Architects and Quantity Surveyors data on road construction projects in Bahir
Dar city.
3.2.2. Case Study
Case study is a method for testing whether models, formula can be applied to phenomena
(Magigi, 2015). Two ongoing road projects were taken as sample case studies. The
45
information was gathered from tender document, bill of quantities, contract documents,
progress report and abstract sheets to provide necessary data for project cost and scheduling
activities which used to make suggestion toward the application of EVMS. This design is
in line with specific objective four.
3.3. Sampling Technique
Sampling is the process of selecting a sufficient number of elements from the population,
so that a study of the sample and an understanding of its properties or characteristics would
make it possible for us to generalize such properties or characteristics to the population
elements (Sekaran, 2003). Purposive sampling was used on road construction firms and
projects. It is technique in which researcher relies on choosing members of population to
participate in the study. Select projects managers and professionals from road construction
firms who are expected to have technical and specialized knowledge on EVM technique
and performance of infrastructure projects in Bahir Dar City. These include Engineers,
Architects and Quantity Surveyors from their respective professional bodies.
The study of sample size be comprised 7 main parties that participate on road construction
projects in Bahir Dar and it was distribute all of them based on Purposive sampling.
3.4. Methods of Data Collection and Source of Data
For this research, two types of data were gathered and used. The first is primary data, the
data which are obtained through questionnaires and interviews. Secondary data was
collected thorough literature review. It means data that are already available i.e. they refer
to the data which have already been collected and/or analyzed by someone else. These
different methods of data collection have been used in order that the data or information
obtained from one can be supplemented by the other whereby the collected data gives
multiple evidences.
46
3.4.1. Literature Review
In achieving the objectives of this study, the information regarding application of EVM,
how EVM techniques used measuring the performance and forecasting of construction
projects and how EVM answer basic project management questions were obtained from
various sources from international journal, international conference, reports and
published books.
3.4.2. Questionnaire Survey Method
Questionnaire provides first-hand information for the subject matter of a research as it is
focused on issues which further serves as a survey to understand the main concerns and
attitudes of respondents towards the problems (Kasiem, 2008). In this study, questionnaire
method was used to collect data on current practice and also the opinions of practitioners
towards EVM. Questionnaire is designed following up of in-depth assessment of literature
review, and distributed using purposive sampling technique.
3.4.3. Interview Method
The study also employed interview method. Interviews in this study helped the researcher
obtain more information from the Project Managers, Architect, Engineers and Quantity
Surveyor on the topic under investigation. This method also offers the researcher an
opportunity to adapt and clarify questions by using appropriate language, and clear doubts
and establish rapport and probe for more information (Sekaran, 2003).
3.5. Data Analysis
3.5.1. Analysis of Quantitative Data
Quantitative data measures phenomenon under study by using numerical or ranking scales
to measure quantities that are then analyzed using statistical analysis techniques. Statistical
package SPSS method was used to analyze the data. Descriptive statistics namely
frequency counts, percentages are used to analyze the respondents’ mean, while standard
47
deviation is used to analyze respondents’ opinions on the application of EVM to measure
construction project success.
In the analysis, ‘mean score’ method was adopted for the structured part of the
questionnaire, to establish the relative importance of factors based on frequencies of
occurrence. A five point Likert scales is used to calculate the mean score for each
contribution and barriers for EVM adoption.
The mean score (MS) for each potential factors are computed using the following
expressions (Abd Majid & McCaffer, 1997)
𝑀𝑆 = ∑(𝑓×𝑆)
𝑁………………………………….…Eqn. 1
Where: MS = Mean score,
f = frequency of response for each score,
S= score given to each factor (1 to 5), and
N= Total number of responses for each factor
3.5.2. Analysis of Qualitative Data
Qualitative data are analyzed using descriptive analysis. Responses from key information
have been collected related to current issues. The current issues which emerge in relation
to each guiding questions have been presented in the results, with selected participants
offered as illustrations.
3.6. Measurement of Variables
Data on the respondent’s views and opinions about EVM is obtained using scaled variables.
The responses to the questionnaire was based on Likert’s scale of five ordinal measures
which was from one 1 to five 5 arranged in ascending order according to the degree of
contribution to each question. A five point –Likert scale of strongly disagree, disagree, not
sure, agree and strongly agree is used to tap respondent’s perception on the study variables.
48
3.7. Reliability Test
Reliability: refers to whether the data collection techniques and analytic procedures would
reproduce consistent findings if they were repeated by another researcher. Reliability
mainly deals with the consistency, dependability and explicability of the results obtained
from a piece of research (Zohrabi, 2013.). Cronbach’s Alpha is used to assess the internal
consistency of a questionnaire or survey that is made up of multiple Likert type scales and
items.
Cronbach’s Coefficient Alpha
Developed by Lee Cronbach in 1951, measures reliability, or internal consistency. Therefor
Cronbach’s alpha tests to see if multiple-question Likert scale surveys are reliable
(Stephenie., 2017) .The normal range of Cronbach’s coefficient alpha value between 0.0
and + 1.0. Based on this, alpha for Likert scale questions are interpreting as follows in
Table 3.1:
Table 3. 1 Interpretation of Alpha
Cronbach’s alpha Internal consistency
α ≥ 0.9 Excellent
0.9 > α ≥ 0.8 Good
0.8 > α ≥ 0.7 Acceptable
0.7 > α ≥ 0.6 Questionable
0.6 > α ≥ 0.5 Poor
0.5 > α Unacceptable
49
CHAPTER FOUR
DATA ANALYSIS AND DISCUSSION
4.1. Introduction
This chapter describes the results of interview, questionnaire survey and case study
concerning practices and opinion about EVM in Bahir Dar road construction projects and
key participants; contractors, consultants and clients.
4.2. Interview Result and Discussion
The researcher interviewed four professionals; 1 from client’s representatives Amhara
Rural Road Transport office (ARRTO), 2 from contractor’s representatives Amhara Road
Works Enterprise (ARWE) and Amhara Region Urban Development and Construction
(ARUDC), 1 from consultant’s representatives Amhara Road and Building Design and
Supervision Works Enterprise (ARBDSWE).
The study asked participants concerning what construction project management tools are
used in their projects and organization. It is found that all use WBS, which provides the
scope of project, detailing each task required to be performed. Most organizations require
a WBS to prior to commencing a work. The researcher identified that participants use
Critical Path Method and Gant chart.
Project managers need to monitor and control progress throughout the project. However,
project managers and organizations use simple deviation analysis and partially
implemented Earned Value analysis. EVA is a tool for managing the work during the
Execution phase of a project and used to allow the project manager to control the work that
takes place during that Execution phase, while simple deviation analysis represents graphic
presentation of the costs and benefits over the time preparing cash flow activities. The cost
management control practice considers comparing of actual to budgeted cost. In EVA, the
existing performance measuring techniques used on construction projects practice indicate
the profit and loss (cost variance) using the difference between the amount of work
50
executed to the amount of total expense. This is actually true and is the result of Earned
Value in its purest form, but practitioners only consider cost components since the two
major components of project performance are schedule (on time delivery) and cost (over
or under budget). In addition, other project performance and forecasting tools are not
practiced.
Most project managers indicate that the possible barriers of EVM technique in measuring
performance of a construction project in Bahir Dar include minimal awareness of EVM
and training; low familiarity with EVM techniques and lack of EVM expertise and
experience. Their recommendations with regard to these challenges is giving good project
management training for project managers and professionals. This training can include
guiding the actual implementation of an Earned Value System, procedures, more
specifically the details of the Earned Value system to fully understand its tool requirement
in their proper context as to when, why and how to use it. Respondents also indicated the
availability of a good project plan, good estimates of project costs, and even more
fundamentally, a good cost management system to track and report costs is crucial.
Respondents believe that the possible benefits of EVM technique in measuring
performance of a construction project is to indicate whether a project is over budget or
under budget. Professionals theoretically agree that EVM is a proper project management
practice as project management principles, but practically it is not used at a detailed level.
When asked about the reason for not implementing EV at a detail level on their projects,
the majority of responses reason out that they do not have detail knowledge about the tool
and it has never have been required by a Client. Moreover, it can be seen in the following
Table 4.1.
51
Table 4. 1 Respondents Interview Result in Percentage
Project management tools used ARWE ARRTO ARUDC ARBDSWE %
WBS 100
CPM 25
Gant chart 100
Monitor and control techniques used
Simple deviation analysis 100
Partially use of EVA tools 100
Fully use of EVA tools 0
Forecasting using EVA tools 0
Barriers of EVM technique implement in a
construction project
Minimal awareness of EVM and training 100
Low familiarity with EVM techniques 75
Lack of EVM expertise and experience 100
Respondents recommendations
Good project management training 100
Availability of a good project plan 100
Good estimates of project costs 100
Good cost management system 100
Benefits of EVM technique
To indicate whether a project is over budget or
under budget
100
Theoretically agree that EVM is a proper
project management practice
100
Reason for not implementing EV
practically at a detailed level
Do not have detail knowledge about the tools 100
It has never have been required by a Client 75
52
4.3. Survey Result and Discussion
After collecting the raw data of questionnaire, the data was entered into computer SPSS
software program to analyze the data. Section-A of the questionnaire identified the
background information (Company and Respondent Profile).
Section B indicates the opinions of respondents about Earned Value Management to
determine the level of awareness through project managers and other respondents in Bahir
Dar road construction. It was important to conduct a double phased study, including, a
preliminary interview before distributing the questionnaire to identify knowledge on EVM
techniques related to the subject (first stage) and distribute the survey based on the first
stage (second stage). The survey was restricted to information related to the subject of
EVM usage practically or theoretical learning through experience.
The researcher preliminary interviewed 55 respondents. From the total, 15 (27.27%) of the
respondents have never heard about the term Earned Value. One of the limitations
highlighted is related educational problem and the extent of not familiarity of non-users of
EV and its characteristics, which reflects a poor professional training to Bahir Dar road
practitioners.
Section C determines respondents’ level of agreement and knowledge related to EVM
techniques, organizations’ ability to provide up-to-date information, contribution of EVM,
barriers to practice EVM and success factors for the implementation of EVM.
4.3.1. Section A: Background Information
This section is designed to provide general information about the respondents and
organization in terms of type of organization, year of establishment, classification of
company, age, gender, position, educational qualification and experience of the
respondents.
53
4.3.1.1. Survey Response Rate
Out of the 40 questionnaires: 3 were distributed for clients (Employers), 12 for consultants
and 25 for contractors. From the distributed 40 questionnaires, 33 (82.5%) returned, which
is a valid response rate and high percentage from the total distributed questionnaire, while
5 (12.5%) is not returned on time and 2 (5%) did not appropriately complete the survey.
Table 4. 2 Questionnaire Response Rate
Respondents
Category
Number of questioners
Distributed
Number of questioners
Returned
Percentage of response
rate (%)
Client 3 3 100
Contractor 25 21 84
Consultant 12 9 75
Total 40 33 82.5
4.3.1.2. Respondents’ Organization Establishment
Out of the 33 respondents, 15.16% (5) of the respondents’ organization have 5 or less years
of establishment, 24.24% (8) are 5 to 10 years of establishment, and 36.36% (12) have
more than 10 years of experience. 24.24% (8) did not respond their year of establishment
(Figure 4.1).
Figure 4. 1 Firms Years since Establishment
36.36%
24.24% 24.24%
15.16%
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
Above 10 years 5-10 years Not respond Less than 5 years
54
4.3.1.3. Respondents’ Organization Classification
Figure 4.2 shows that 51.51 % (17) of the respondents’ firm are General contractor (GC)
at construction works, 24.24% (8) of the respondents Organizations are Road contractors
(RC), 6% (2) are other classification and 18.19% (6) did not respond their classification.
Figure 4. 2 Firms Classification
4.3.1.4. Respondents Age
Figure 4.3 shows that 4 (12.1%) were less than 25 years of age, 24 (72.7 %) were 26-35
years, 4 (12.1%) were 36-45 years and 1(3.1%) was between 46-55 year.
Figure 4. 3 Respondents’ Age
51.51%
24.24%
18.19%
6%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
GC RC Not respond Other
72.70%
12.10% 12.10%
3.10%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
26-35 years Less than 25 years 36-45 years 46-55 years
55
4.3.1.5. Respondents’ Gender
Figure 4.4 shows that 24 (72.7%) were male, while 8(24.2%) were female. 1(3.1%) missed
(not responding) on his/her gender.
Figure 4. 4 Respondents’ Gender
4.3.1.6. Respondents Position in the Organization/Company
Table 4.3 shows that 10 (30.3%) of the respondents are project managers, 17 (51.5%) are
engineers, 4 (12.1 %) are other, and 2 (6.1%) did not respond on their position. Architect
and Quantity surveyor respondents did not participate in the survey.
Table 4. 3 Respondents’ Position in the Company
Position Number Percent
Project manager 10 30.3
Engineer 17 51.5
Others 4 12.1
Not respond 2 6.1
Total 33 100
24.20%
72.70%
3.10%
Female Male Not respond
56
4.3.1.7. Educational Qualification of the Respondents
Table 4.4 shows that educational level of the respondents. 13 (39.4%) are Master’s degree
holders, and 19 (57.6%) have Bachelors, while 1 (3%) did not respond on his/her level of
education. Other levels of educations, PhD, diploma, certificate did not participate.
Table 4. 4 Respondents’ level of education
Level of education Number Percent
Masters 13 39.4
Bachelors 19 57.6
Not respond 1 3
Total 33 100
4.3.1.8. Respondents Experience
Professionals involved in this questionnaire survey had different level of experience. 27.3%
of professionals have less than 5 years of experience and 54.6% of professional have 5-10
years of experience. Therefore, the maximum number of respondents (54.6%) have in the
range of 5-10 years of experience. The other 12.1%, and 3% of the respondents have 11-
16yrs and above 17 years of experience respectively. While the remaining professional
participated in the questioner survey were not willing to give response on his experience.
Table 4. 5 Experience of the Respondents’
Experience (yrs.) Employer Contractor Consultant Total
No. % No. % No. % No. %
Less than 5 yrs. - - 7 33.3 2 22.2 9 27.3
5-10 years 1 33.3 12 57.1 5 55.6 18 54.6
11-16 years 1 33.3 1 4.8 2 22.2 4 12.1
Above 17 years 1 33.3 - - - - 1 3
Not respond - - 1 4.8 - - 1 3
Total 3 100 21 100 9 100 33 100
57
4.3.2. Section B: Earned Value Survey
The purpose of the survey is to elicit opinions from project management practitioners and
obtain a rough indication of the usage of EVM and attitudes towards it. In this section,
some observations are provided based on the survey response.
4.3.2.1. Techniques Used to Track Project Costs and Progress
Only 9.09% of participants reported using EVM to track project costs and progress. Even
these participants use it rarely. The most common techniques used to track project costs
are Gant chart (42.42%) and critical path method (36.36%). Gant charts are suitable for
representation of schedules, but as a planning technique it is not suitable for planning of
complex projects. It cannot identify and highlight the engineering critical tasks that need
special attention for preventing schedule slippages, time overrun, contractual dispute and
bottlenecks (Alvardo and David, 2004).
Figure 4. 5 Techniques used to Track Project Costs and progress
4.3.2.2. Recommendation to Measure Performance on Construction Projects
The study identified that almost half of the project respondents (48.48%) recommend EVM
is the best method to measure performance on construction projects.
42.42%
36.36%
9.09% 9.09%
3.03%
0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
Gant chart CPM EVM Others PERT method
58
Figure 4. 6 Respondents’ Recommendation to Measure Performance on Construction
Projects
4.3.2.3. Participant Opinion on the Value of EVM
Participants believed that EVM is a valuable technique. 36.36% believe that EVM is
extremely valuable, while 63.63% believes it is suitable for projects.
Figure 4. 7 Participant Opinion on the Value of EVM
4.3.2.4. Reasons for using EVM within the Organization
In this question, only three respondents participated. These respondents identified that it is
required by client, voluntary use of managers, and used on trial bases.
48.48%
39.39%
9.09%
3.03%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
EVM Critical path
method
PERT method Gant chart
54.54%
36.36%
9.09%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
Useful for most projects Extremely valuable Suitable for some projects
59
Figure 4. 8 Participant Reasons for Using EVM
4.3.2.5. Reasons for not using EVM within the Organization
81.81% of respondents identified that lack of proper training to project managers in the
application of EVM is the hindrance for its use, while 12.12 % argue that senior
management or clients do not require EVM reports or EVM use. Other reasons include
limited budget, schedule and partial costs where project managers have to deal, due to its
complexity.
Figure 4. 9 Participant Reasons not using EVM
3.03% 3.03% 3.03%
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
3.00%
3.50%
Required by client Used voluntarily by
managers
Used on a trial
basis/occasionally
81.81%
12.12%9.09%
6.06% 6.06% 6.06% 6.06%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
No training Not
requested
No schedule Too complexNo budget Partial costs Not sure:
60
4.3.2.6. Project Monitoring Method of Participants
72.72% confirmed that the cost monitoring methods they use is comparing planned costs
against actual costs of their projects, but it is difficult to determine the true performance of
the project using this method. Monitoring and evaluation is contingent of the
appropriateness of the plan (baseline) against which performance is compared with. In this
regard, current practice both in terms of its baseline establishment, performance evaluation
and taking corrective actions has considerable drawbacks when compared to best practices
suggested in the literature. For instance, computations using simple analysis could not
address whether a project is on or above or below cost or time performances, and indicate
/predict/ the likelihood of completion cost and time. Thus, it is found that only some part
of the concept of EV is being used in Bahir Dar road construction projects, which indicates
the use at infancy stage.
Figure 4. 10 Project Monitoring Method of Participants
4.3.2.7. Earned Value as a new Estimate Value on Top of Plan Value and Actual
Cost
The study carried out almost all practitioners strongly agree or agree 93.93%, that EV is
necessary in cost estimating as a new estimate value on top of Plan Value and Actual Cost.
72.72%
15.15%12.12%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
By comparing only planned costs
against actual costs
By comparing Earned Value to
planned & actual cost
Not sure
61
In this approach Earned Value Analysis, project management focused on two major
principles; the integrative account of cost and time performance criteria. The Earned Value
is then used as a measure of project performance in terms of cost-schedule control system.
A concept developed from the triple constraints of planned value, Earned Value and actual
cost. This has improved the objective measurement level of simple deviation analysis
using more information’s on activities performed. Hence, the comparisons are made
between planned and Earned Values.
Besides, Earned Value provides estimated completion of the project (EAC and ETC) can
be computed using the three information and the total Budget at Completion (BAC).
Accordingly, these expressions can be used for computations (Table 2.4).
Figure 4. 11 Earned Value as a new Estimate Value on Top of Plan Value and Actual Cost
4.3.3. Section C: Respondents Level of Agreement
The study carried out a descriptive statistics analysis on various EVM principles and
respondents were to indicate the extent of use on a scale of 1-5 level of their agreement.
Scale: 1 “Strongly Disagree”, 2 “disagree”, 3 “not sure”, 4 “agree”, 5 “strongly agree”.
51.51%
42.42%
6.06%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
Agree Strongly agree Neutral
62
4.3.3.1.Respondents Knowledge about EVM
Table 4.6 shows the descriptive statistics of the participants’ level of agreement on their
knowledge about EVM.
Table 4. 6 Participants Level of Agreement on their Knowledge about EVM
Participants level of agreement on their knowledge about EVM
Expert Knowledgeable Familiar Slightly
familiar
Not familiar
Frequ
ency
% Frequ
ency
% Frequ
ency
% Frequ
ency
% Frequ
ency
%
Strongly
Disagree
18 54.5 7 21.2 0 0 0 0 11 33.3
Disagree 13 39.4 15 45.5 3 9.1 2 6.1 22 66.7
Not sure 1 3.0 5 15.2 9 27.3 0 0 0 0
Agree 1 3.0 4 12.1 11 33.3 7 21.2 0 0
Strongly
Agree
0 0 2 6.1 10 30.3 24 72.7 0 0
Total 33 100.0 33 100.0 33 100.0 33 100.0 33 100.0
This results and findings show that most of the key players in construction industry have
slightly familiar on level of awareness of EVM. Cumulatively, 72.7% of the respondents
have strongly agree with slightly familiar on level of awareness of EVM. Whereas almost
all of those 54.5% of participants believed they were strongly disagree and 39.4% Disagree
on EVM expert. This indicates very low level of respondents’ awareness on EVM. This
finding opposes to the literature review where EVM is well-known worldwide technique
as project measurement method (Acebes et al., 2013).
4.3.3.2.Organization is able to provide up-to-date information
Table 4.7 shows the level of respondents’ organization ability to provide up-to-date
information on project cost and schedule in time. It can be seen that 57.6% are not sure to
provide up-to-date information, while 21.2% are agree and the rest 21.2% disagree and
strongly disagree on providing up-to-date information on project cost and schedule. For
63
schedule and cost estimates, a time-phased baseline schedule needs to be developed. For
any date within the project, it is necessary to know how much money should have been
spent by that time. Up-to-date information on costs will allow the project manager to know
how much money has been spent at any given time.
Table 4. 7 The Level of Organization able to provide up-to Date Information
Organization is able to provide up-to-
date information Frequency Percent
Not sure 19 57.6
Agree 7 21.2
Disagree 6 18.2
Strongly disagree 1 3
4.3.3.1. What Does Earned Value Analysis Provide? Contribution of using EVM for
Project Control Purpose
The study sought to establish what the benefits of using EVM in project control purpose.
The questions comprise of the application of EVM in construction project management.
The responses agreement shown in the Table 4.8.
Table 4. 8 Contribution of using EVM for Project Control Purpose
Contribution of EVM Mean Std. Deviation
EVM provides early warning of performance problems to take corrective
action 4.55 0.666
Increased project visibility 4.27 0.574
Increase confidence in contractors ability to manage project by identifying
problems early 4.03 0.467
EVM assists the project team to achieve cost objectives 4 0.559
Used provide the provision of more accurate management and financial
report 4 0.559
EVM improves project scope management 3.91 0.631
EVM improves communication among project team members 3.85 0.667
Improved estimating and planning 3.67 0.736
64
EVM assists the project team to achieve schedule objectives 3.52 0.566
To monitor progress and to develop cost and schedule forecast for active
project 3.52 0.619
Overall, EVM is cost effective tool for performance management 3.15 0.667
EVM offers choice to integrate risk management 3.12 0.6
Based on Table 4.8, the contributions of EVM in construction projects adopted by
respondents are EVM provides early warning of performance problems to take corrective
action (MS=4.55) and increased project visibility (MS=4.27). The EVM method, having
defined all the elements of project cost management into accurate data, that can understand
easily and get a correct visibility of what is happening on the project during different stage
of the project execution. This project visibility can provide a proper base for the
management to set their decisions based on the reliable findings which can lead them to
success. The third and fourth important benefit highlighted by the respondents is increase
confidence in contractors’ ability to manage project by identifying problems early
(MS=4.03), EVM assists the project team to achieve cost objectives (MS=4) and used
provide the provision of more accurate management and financial report (MS=4).
4.3.3.3.Why does no One Seem to Use Earned Value? What are the Barriers?
This questionnaire survey form was designed to achieve the second specific research
objective which is to identify the factors that hinders the usage and application of EVM
applied in Bahir Dar road construction projects. The respondent agreements are shown in
the Table 4.9.
Table 4. 9 Barriers of Company to Practice EVM
Barriers of company to practice EVM Mean Std. Deviation
Lack of EVM expertise and experience 4.82 .465
Minimal awareness of EVM including training 4.52 .508
Poor understanding of EVM 4.21 .740
Low familiarity with the EVM techniques 4.18 .635
65
Lack of management support 3.55 1.121
Earned Value requires more information 3.27 .801
It takes too long to manually produce reports 3.18 .917
Distrust and conflict between project managers, project consulting and
government 3.12 .820
Inability to find qualified resources 2.94 1.029
Pressures to report only good news 2.88 .857
Difficulty integrating cost, resource and schedule data concerning real cost
and deadlines 2.70 .951
Difficulty in adequate work breakdown structure (WBS) to apply EVM 2.70 .883
With such analysis the primary inputs into an Earned Value system are lack of EVM
expertise and experience (MS=4.82). This is the major barrier to using Earned Value.
Another obstacle is the Minimal awareness of EVM including training (MS= 4.52). The
low level of awareness of the key players on EVM may be due to the least training
application of the method in Bahir Dar road construction industry. They might have used
some parts of EVM concept indirectly by using other terms. Therefore, the key players do
not aware of the terms used in EVM.
4.3.3.4. What needs to be done? Success Factors for EVM Implementation
Table 4.10 shows the descriptive statistics of critical success factors to implement EVM.
This questionnaire survey form was designed to achieve the third specific research
objective which is to identify critical success factors for EVM implementation.
Table 4. 10 Success Factors for EVM Implementation
Success factors for EVM implementation Mean Std. Deviation
Provide reliable data on real costs and deadlines 4.73 0.452
Preparing suitable work break down structure (WBS) 4.67 0.479
Convincing project managers of the value and necessity of using Earned Value
in achieve project success 4.64 0.489
Adequate EVM training 4.48 0.712
Understanding its requirement 4.3 0.467
Top management support 4.06 0.704
66
EVM needs qualified team 3.85 0.508
Culture of the organization and top management leadership style 3.7 0.637
Maturity of the organization’s project management system 3.67 0.595
Convince management of the need to require project managers to be responsible
for costs on a project. 3.24 0.792
Buy in of EVM by the project management staff 3.12 0.781
The most important barrier to be overcome EVM Implementation is providing reliable data
on real costs and deadlines (MS=4.73) and preparing suitable work break down structure
(WBS) (MS=4.67) on a project are the major success factors to implement the usability of
EVM. More importantly, at a higher level, it allows for better management and use of
resources to meet key company goals and objectives. The absence of good cost
management stops us from achieving these important goals. As a result, it is suggesting
that to invest in the infrastructure company goals and objectives there should be make the
right data available to the right people at the right time. This is good management planning,
and is required for project management. A detailed plan must be required for all projects.
That detailed plan will include the WBS listing all tasks. For every task, someone must be
listed as the responsible individual. In other words, a detailed project schedule must be
provided.
Another high level barrier to overcome is convincing project managers of the value and
necessity of using Earned Value in helping them achieve project success (MS=4.64). If this
goal is not achieved, then the other barriers will not ever be addressed.
The other level of barrier to overcome is good project management training (MS=4.48) and
Understanding its requirement (MS=4.3). This training may include guiding the actual
implementation of Earned Value System, procedures, more specifically the details of the
Earned Value system and fully understand its tool requirement in their proper context as to
when to use them, why to use them and how to use them.
67
4.3.3.5.Reliability Test Results of Questioner using Cronbach’s Alpha (α)
Table 4.11 shows the results of Cronbach’s Alpha are in the range from 0.714 and 0.831.
In this Table the output of reliability statistics Cronbach’s alpha coefficient scores are
over 0.7, which shows high internal consistency and it indicates the questionnaire is
reliable. Generally, the range is considered as high; which ensures the reliability of each
section of the questionnaire.
Table 4. 11 Cronbach's Alpha for each section of the questionnaire
Section of questioner Cronbach's Alpha (α)
Section-C:- 3: Contribution of EVM 0.831
Section-C:- 4: Barriers of company to practice EVM 0.76
Section-C:- 5: Success factors for EVM implementation 0.714
4.4. Practical Application of Earned Value Management
This section examines and presents the results of a practical application of Earned Value
Management to Amhara Road Work Enterprise (ARWE) construction Projects. In
reviewing this application, projects were selected from two ongoing road construction
projects. This is to ensure or indicate the project performance and forecasting when a
project will be complete and the amount of budget required, to tell the project team in the
EVA criteria, benefit and procedures to implement EVA in the project management and
assess the practical relationship between EVM technique and project performance. Earned
Value provides an objective measurement of how much work has been accomplished on a
project. Using Earned Value process, management methods can readily compare how much
work has actually been completed against the amount of work planned to be accomplished.
All work is planned, budgeted, and scheduled in time-phased "planned value" increments
constituting a Performance Measurement Baseline (PMB).
68
4.4.1. Methodology
The intention of the section is to give a clear understanding of the approach in carrying out
Earned Value Analysis in projects. Critical data analysis was made and discussed in this
section. Data including project details and understanding of EVM tools were used. Earned
Value differs from the usual budget verses actual costs incurred, in that it requires the cost
of work in progress to be quantified. This allows the project manager to compare how much
work has been completed against how much expected to be completed at a given point. In
applying the metrics identified with Earned Value analysis, the following were calculated
for projects.
Methods for Cost Analysis and forecasting
Cost Variance (CV)
Cost Variance Percent (CV %)
Cost Performance Index (CPI)
Estimate To Complete (ETC)
Estimates at Completion (EAC)
Percentage completion of financial performance
Methods for Schedule Analysis and forecasting
Schedule Variance (SV)
Schedule Variance Percent (SV %)
Schedule Performance Index (SPI)
Estimates at Completion (EACt)
Percentage of schedule performance
4.4.2. Case Study One
4.4.2.1. Description of Project
Government of Federal Democratic Republic of Ethiopia represented by Ministry of
Industry and Ministry of Agriculture is working in partnership to establish an integrated
69
Agro industry park with an aim of transforming the agricultural sector. In this
establishment, Bure Integrated Agro-Industrial Park Road Construction is one of the
projects. The detailed engineering design, tender document preparation have been under
taken by Mahindra Consulting Engineers, whereas supervision work have been under taken
by Amhara Road and Building Design & Construction Supervision Works Enterprise and
the construction have been taken by Amhara Road Works Enterprise.
This project case study describes the Earned Value Management method on the
construction of Bure Agro Industry Park Road Construction Project. The project is located
in Amhara Regional State Bure City which is 400Km from North West of Addis Ababa
(Figure 4.12).
Figure 4. 12 Project Location Map
The project includes construction of infrastructure works such as, road, storm water, drain
and sewerage system for the contract price equivalent of 704,446,300.63 (ETB: Seven
Hundred four million Four Hundred forty-six thousand three hundred and 63/100)
including as corrected and modified in accordance with the instructions to bidders. The
total area of the project is 260.56 ha. The project works comprise the construction of
infrastructure such as:
70
Site grading for finished road level, construction of Road, footpaths & cycle tracks
Earthwork (excavation and embankment)
Sub base and base course
Asphalt concrete surfacing
Ancillary works
Construction of storm water drains & culverts
Providing sewer network systems
Internal power and street lighting
Taking care of the work until the issue of taking over certificate and rectification of
the defect during the defects of liability period.
4.4.2.2. Project Details
Project name: Burie Agro Industry Park Road Construction Project
Location: Burie
Client: Amhara Industry Park Corporation
Contractor: Amhara Road Works Enterprise (ARWE)
Consultant: Amhara Road and Building Design and Construction Supervision Works
Enterprise (ARBDCSWE)
Contract amount: 704,446,300.63 ETB
Contract Signing data: 18-07-2017 G.C
Site hand over date: 17-08-2017 G.C
Original completion date: 335 days
4.4.2.3. Current Problem on Case Study
After defining the case study and given the project details, it was discovered that EVA is
relatively a less common user for project performance measurement technique in Bahir Dar
road construction projects. At the time this project was awarded, it had limited usage of
project monitoring tool. Due to the lack of project management tool, Earned Value
71
Management system is tested in order to get an effective EVA on the construction project.
Using this tool will help distinguish and track the projects progress to perceive the amount
of work gotten from the amount spent.
4.4.2.4. Budget Allocation
In order to establish a time-phased budget for the project, the project cash flow report starts
from the duration period of October 2018. The contractor did not start the work based on
the contract time. Figure 4.13 indicates the trend of budgeted expenditure allocated for the
project over a period using the S curve.
Figure 4. 13 S-Curve for the Cumulative Cash Flow
4.4.2.5. EVM Applied to Case Study
According to Khamidi, et al. (2011), the use of Earned Value metrics can be used to observe
the performance management of an on-going project and see how well the project is being
managed.
-
100,000,000.00
200,000,000.00
300,000,000.00
400,000,000.00
500,000,000.00
600,000,000.00
700,000,000.00
800,000,000.00
900,000,000.00
O c t o N o v e D e c e m J a n u F e b r u M a r A p r i M a y J u n e J u l y
Res
ou
rce
in E
TB
Time in Month
PV
PV
72
Figure 4. 14 Graphical Analysis of Cumulative Planned Value, Earned Value and Actual
cost (As of July 30, 2018)
Figure 4.14 shows the Earned Value graphical representation i.e. planned value (PV),
Earned Value (EV) and the actual cost (AC) of the project from October to July. It can be
seen from the above graph that the cumulative actual cost was less than the cumulative
planned value (PV) that indicates less money is being spent than budgeted and the Earned
Value (EV) remained less than the planned value (PV). Hence, the overall performance of
the project cost is favorable, but in schedule it remained unsatisfactory. This observation
derived from the graph because of the implementation of EVM could have resulted from
cost and schedule analysis.
4.4.2.6. Cost Analysis
The use of cost analysis empowers the project manager to gauge and monitor the project
progress in terms of cost. The EV cost analysis was being carried out as shown in the table
Octo Nove Decem Janu Febru Mar Apri May June July
PV 23,140,871. 43,746,188. 51,051,736. 136,072,118 339,324,130 486,698,533 715,812,316 762,684,389 797,707,611 810,512,068
EV 298,354.00 2,251,361.5 26,796,309. 32,920,230. 49,336,392. 77,215,718. 120,684,662 170,339,117 197,185,896 200,936,526
AC 987,880.15 3,855,498.3 19,564,551. 28,134,351. 45,872,204. 66,758,043. 91,285,492. 123,618,137 145,196,296 146,675,600
-
100,000,000.00
200,000,000.00
300,000,000.00
400,000,000.00
500,000,000.00
600,000,000.00
700,000,000.00
800,000,000.00
900,000,000.00
Res
ou
rce
in E
TB
Time in MonthPV EV AC
73
below, which shows the cost variance, percentage cost variance, cost performance index
and the progress made on the project.
Table 4. 12 Cumulative Earned Value (EV) Cost Analysis
S.No. Month EV cost analysis
CV CV% CPI % of Financial
performance
1 October -689,526.15 -231.1100739 0.30 0.04
2 November -1,604,136.76 -71.25185024 0.58 0.28
3 December 7,231,757.59 26.9878866 1.37 3.31
4 January 4,785,878.81 14.53780489 1.17 4.06
5 February 3,464,187.79 7.021566924 1.08 6.09
6 March 10,457,674.46 13.54345298 1.16 9.53
7 April 29,399,169.84 24.36031988 1.32 14.89
8 May 46,720,979.82 27.42821521 1.38 21.02
9 June 51,989,599.36 26.36577991 1.36 24.33
10 July 54,260,926.74 27.00401343 1.37 24.79
According to Alvardo and David (2004), time and cost overrun usually occur in the
beginning of the project, but the project manager does not realize until they cannot achieve
the objective of the project. This idea is supported by this case study. The project manager
shall examine the true performance of the project by using EVA, to know the latest progress
and identify the problem of the project and shall take corrective action.
The cost variance (CV) of the project is calculated by subtracting the EV from the AC. As
shown above, the CV consistently shows a negative value in October and November that
indicates unfavorable situation but in other months CV shows a positive value, which
portrays a favorable situation. This shows that the project is under budget in the sense that
the amount of money budget on the project is more than what was spent on the project. In
addition, CV can also be expressed in percentage by dividing CV by EV and multiplying
by 100. Graphically the cumulative CV can be shown in Figure 4.15.
74
Figure 4. 15 Cumulative Cost Variance at Various Status Months
The cost performance index (CPI) is an indicator that shows the efficiency of resource used
during the project duration as shown in Figure 4.16. This can be calculated as the ratio of
Earned Value to the actual cost of the project. For an ideal situation, it must be equivalent
to one or higher than one. In this case study, the CPI qualities are in the middle of 0.3 and
1.38. This demonstrates the project has a minimal cost effectiveness in the month of
October and November, while the other months demonstrate the project has cost
effectiveness. The graph shows values of CPI on the respective status months. Percentage
of financial performance can be calculated using the physical amount of work performed
to cumulative amount of budget at completion and multiplying by 100.
Figure 4. 16 Cumulative Cost Performance Index at Various Status Months
(10,000,000.00)
-
10,000,000.00
20,000,000.00
30,000,000.00
40,000,000.00
50,000,000.00
60,000,000.00
0 2 4 6 8 10 12
Res
ou
rce
in E
TB
Time in Month
CV
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
0 2 4 6 8 10 12
Val
ue
Time in Months
CPI
75
Cost analysis for this project has demonstrated that until the end of ten months’ cumulative
amount of money spent on the project is less than budgeted. It means that the project was
able to operate under budget, but as PV is above EV, it means that progress was slow. As
a consequence, SPI achieved a low performance (on average 0.25). Thus, the project was
not completed on time and it is affected by schedule performance which may be the cause
for cost overrun for the remaining works.
4.4.2.7. Cost Forecasting
Cost analysis for this project has demonstrated that the cumulative amount of money spent
on the project is less than budgeted. But this does not mean that the completion of overall
project performance will be cost effectiveness. Forecasting with EVM measures should
take project performance patterns and trends in to account. One consideration is schedule
performance. This project will be under performing in this regard, there may be reasons to
include the SPI in the forecasting calculation on the assumption that additional cost will be
incurred in attempt to recover and get the project back on schedule.
EVM provides an organization with the capability of practicing ‘‘management-by
exception’’ on its projects. Moreover, see Table 2.2 Forecasting indicators by EVM
technique. The implementation of Earn Value Management on this case study can also
show how much cost it will take to complete the project. The project shows poor
performing schedule performance. So future cost performance will be influenced
additionally by past schedule performance. To calculate the cost forecast at the end of the
ten month, here is a sample of the most common alternative ways of calculating the EAC.
𝐸𝐴𝐶 = 𝐴𝐶 + ((BAC − EV)/(CPI ∗ SPI))
= 146,675,600.2 + ((810,512,068.43 𝐸𝑇𝐵 − 200,936,527.0) ÷ (1.37 ∗ 0.25))
= 1,926,458,202.92 𝐸𝑇𝐵
Where BAC is the budget at completion of the project
EV is the Earned Value of the project
CPI is the recent cost performance index of the project
76
SPI is the recent schedule performance index of the project
To calculate Estimate to Complete (What will the remaining work cost) the project
assuming that current performance cost and schedule performance will remain the same as
occurred up to EV throughout the rest of the project.
𝐸𝑇𝐶 = (𝐵𝐴𝐶 − 𝐸𝑉 )/(𝐶𝑃𝐼 ∗ 𝑆𝑃𝐼)
= (810,512,068.43 𝐸𝑇𝐵 − 200,936,527.0 𝐸𝑇𝐵) ÷ (1.37 ∗ 0.25)
= 1,794,845,662.82 𝐸𝑇𝐵
4.4.2.8. Schedule Analysis
Schedule analysis in Earned Value management empowers the project manager to gauge
and forecast the project progress in terms of time. The EV schedule analysis was been
carried out monthly as shown in Table 4.13, which indicates the schedule variance,
percentage schedule variance, schedule performance index and the progress made on the
project.
Table 4. 13 Cumulative Earned Value Schedule Analysis
S.No Month Earned Value schedule analysis
SV SV% SPI % of schedule performance
1 October -22,842,517.08 -98.71 0.01 2.86
2 November - 41,494,826.69 -94.85 0.05 5.40
3 December -24,255,426.63 -47.51 0.52 6.30
4 January -103,151,887.99 -75.81 0.24 16.79
5 February -289,987,738.18 -85.46 0.15 41.87
6 March -409,482,815.75 -84.13 0.16 60.05
7 April -595,127,654.13 -83.14 0.17 88.32
8 May -592,345,272.17 -77.67 0.22 94.10
9 June -600,521,715.08 -75.28 0.25 98.42
10 July -609,575,541.45 -75.21 0.25 100.00
77
The schedule variance of the project is the difference between the Earned Value and the
planned value of the project, which is indicated as a negative value throughout the duration
of the project. This shows that the project is lagging behind schedule as planned. In
addition, time is being spent in contrast with the measure of work from the project and this
would affect the project negatively due to the late completion of the project. The SV can
also be expressed in percentage by dividing schedule variance (SV) by Planned value (PV)
and multiplying by 100 which lies between the ranges of -98.71% to – 47.51% which
indicates that the work percentage has not been completed with contrast with the schedule
plan of the project. Graphically the SV is shown in Figure 4.17.
Figure 4. 17 Cumulative Schedule Variance at Various Status Months
The Schedule performance index (SPI) is an indicator that shows the efficiency of the
project team during the project duration as shown above (Table 4.13). This can be
calculated as the ratio of the Earned Value to the planned value of the project. For an ideal
situation, it must be equivalent to one or higher than one. In this case study, the SPI qualities
are in the middle of 0.01 and 0.52. This demonstrates the project is lagging behind schedule
and not completed on time. This can be shown in the following figure.
(700,000,000.00)
(600,000,000.00)
(500,000,000.00)
(400,000,000.00)
(300,000,000.00)
(200,000,000.00)
(100,000,000.00)
-
0 2 4 6 8 10 12
Res
ou
rce
in E
TB
Time in Months
SV
78
Figure 4. 18 Cumulative Schedule Performance Index at Various Status Months
The graph shows months vs. value which indicates behavior of Schedule Performance
Index of construction work throughout the entire project lifecycle. It shows values of SPI
on the respective status months. All the values are less than 1 which shows that project is
delayed. The amount of percentage schedule performance analysis can be calculated by the
amount of plan value to the budget at completion and multiplying by 100.
4.4.2.9. Schedule Forecasting
Schedule analysis for this project has demonstrated that the task is lagging behind schedule
and not performing at most extreme effectiveness. The implementation of Earned Value
management on this case study can also show how long it would take to complete the entire
project using the trend analysis derived throughout the duration of ten months. To calculate
the schedule forecast in terms of time at the end of ten months, which is the estimate at
completion in terms of time is as shown below.
𝐸𝐴𝐶𝑡 = (𝐵𝐴𝐶 ÷ 𝑆𝑃𝐼) ÷ (𝐵𝐴𝐶 ÷ 𝑀𝑜𝑛𝑡ℎ𝑠)
𝐸𝐴𝐶10 = (810,512,068.43 𝐸𝑇𝐵 ÷ 0.25) ÷ (810,512,068.43 𝐸𝑇𝐵 ÷ 10)
= 40 𝑚𝑜𝑛𝑡ℎ
Where BAC is the budget at completion of the project
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0 2 4 6 8 10 12
Val
ue
Time in Month
SPI
79
SPI is the schedule performance index at the end of July month
Time represents the total amount of months planned for the project
Due to the less efficient performance of the project team, it was predicted that project
would fall behind the schedule and additional time is needed to complete the project.
Therefore, EACt demonstrates that if the present advancement pattern proceeds the project
will prone to complete in 40 months when contrasted with the initial completion time of
10 months.
The project performance indicators show that the project is behind the original schedule as
per the SPI calculations. The main reasons why this happen can be shown in the following
Table for each month.
Table 4. 14 Problems encounter on the project
Problems encounter Months
Oct
ob
er
No
vem
ber
Dec
emb
er
Jan
uar
y
Feb
ruar
y
Mar
ch
Ap
ril
May
Jun
e
July
Lack of Machineries
Lack of Skilled Manpower; Office Team leader,
Office Engineer, Planning Engineer
Right of way problem (Electric Poles)
The client doesn’t give quarry site on Bure (sub-
base material) and Injibara (red ash)
Right of way problem (crusher site)
Consultant delay on sending design data for
structure
Lack of Skilled Manpower; (Electrician and
sanitary engineer)
Delay on supply mixers, vibrator, mold and
formwork
shortage of resource supply (Lime, aggregate for
structure) and laboratory equipment
80
shortage of resource supply (Material and mold
for structure)
Shortage of Grader and Shower Truck
Shortage of resource supply (Material and
Machineries) (Shortage of Mixer, Vibrator,
Labor, Nail, Wood, Timber, Cement, Sand,
Aggregate)
Shortage of resource supply (Material and
Machineries) (Shortage of Mixer, Vibrator,
Labor, Nail, Wood, Timber, Cement, Sand,
Aggregate) and excess Rain
4.4.2.10. Case Study One Analysis
Generally, the analysis status before and after applying EVA in terms of benefits and
project variables are listed in the Table 4.15. It shows the data resulting before applying
EVA and afterwards and was generated by the contrast of calculation. Before applying
EVA, there was no accessible information on SPI and CPI in light of the fact that the
immediate connection between time and cost execution was missed. At the end of ten
months, the project is under budget, but the forecasting completion of overall project cost
will be non-effective as it is behind schedule. As for the whole project, it will have a cost
overrun and delay in schedule.
Table 4. 15 Project Comparative Findings
Item Status before applying EVA Status after applying EVA
Project budget 810,512,068.43 ETB 810,512,068.43 ETB
Cost variance (CV) Planned values compared with
actual cost
Earned Value compared with
actual cost
Cost performance index (CPI) Not available 1.37
Schedule performance index (SPI) Not available 0.25
Estimate at Completion (EAC) Not available 1,926,458,202.92 ETB
Estimate to Complete (ETC) Not available 1,794,845,662.82 ETB
Estimate at Completion time (EACt) Not available 40 months
81
4.4.3. Case Study Two
4.4.3.1. Project Details
Location: Bahir Dar
Project: Getermenged –Airport Asphalt Widening Road Project
Client: Bahir Dar Industry Development & City Service Office
Contractor: Amhara Road Works Enterprise
Consultant: Amhara Road and Building Design and Construction Supervision Works
Enterprise
Contract amount: 216,051,863.11 ETB
Commencement Date: March 03, 2018
Project Completion: - June 07, 2019
4.4.3.2. EVM Applied to Case Study
This case study has been identified therefore, EVM was been applied to this project to
monitor the progress of the project. The EVM analysis of this project is as shown below:
4.4.3.3. Earned Value Analysis:
Table 4. 16 Cumulative Earned Value Analysis
S.No. Month Earned Value (EV) Analysis
PV AC EV
1 May 2,234,778.70
0.00 0.00
2 June 11,229,101.75
286,220.42 0.00
3 July 20,810,148.46
704,017.92 2,282,800.67
4 August 26,660,644.33
3,368,835.81 4,083,530.68
82
Figure 4. 19 Graphical Analysis of Cumulative Planned Value, Earned Value and Actual
Cost (As of August 30, 2018)
The Earned Value Analysis Table 4.16 and graphical Figure 4.19 above was used to
monitor the performance management of a construction project in order to observe how
well the project is being managed. This shows the Earned Value graphical representation
i.e. planned value (PV), Earned Value (EV) and the actual cost (AC) of the project from
May to August. It can be seen from the above graph that the actual cost was less than the
planned value (PV) that indicates less money is being spent than budgeted and the Earned
Value (EV) less than the planned value (PV) that indicates the actual amount of work
performed is less than the plan value. Hence, the overall performance of the project is under
budget but it is affected by schedule performance. This observation derived from the graph.
May June July August Septe Octo Nove Decem Janu Febru March April May2
PV 2,234,77 11,229,1 20,810,1 26,660,6 39,811,8 55,797,1 65,363,7 79,640,2 105,095, 145,060, 168,775, 181,351, 187,871,
EV - - 2,282,80 4,083,53
AC - 286,220. 704,017. 3,368,83
-
20,000,000.0
40,000,000.0
60,000,000.0
80,000,000.0
100,000,000.0
120,000,000.0
140,000,000.0
160,000,000.0
180,000,000.0
200,000,000.0R
eso
urc
e in
ET
B
Time in Month
PV
EV
AC
83
4.4.3.4. Performance Analysis Index
Table 4. 17 Cumulative EVM Performance Indexes
S.No. Month Performance analysis index
CPI SPI
1 May 0 0
2 June 0 0
3 July 3.24 0.11
4 August 1.21 0.16
The cost performance index (CPI) is an indicator that shows the efficiency of resource used
during the project duration as shown above. This can be calculated as the ratio of the Earned
Value to the actual cost of the project. For an ideal situation, it must be equivalent to one
or higher than one but in this case study, the CPI qualities are zero at May and June means
the contractor was not mobilizing any activity. While at July and August demonstrates the
project has cost effectiveness. This demonstrates that project performance is acceptable.
Figure 4. 20 Graphical Representation of Cumulative Cost &Schedule Performance Index
The Schedule performance index (SPI) is an indicator that shows the efficiency of the
project team during the project duration as shown above. This can be calculated as the ratio
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
M A Y J U N E J U LY A U G U S T
Val
ue
Time in Month
SPI CPI
84
of the Earned Value to the planned value of the project. For an ideal situation, it must be
equivalent to one or higher than one. In this case study, the SPI qualities are in the middle
of 0 and 0.11. This demonstrates the project is lagging behind schedule and will not
completed on time.
4.4.3.5. Cost and Schedule Analysis
The cost variance (CV) of the project is calculated by subtracting the EV from the AC. As
been shown above, the CV consistently shows a negative value in June that indicates
unfavorable situation but in month July and August CV shows a positive value, which
portrays a favorable situation. This shows that the project is under budget in the sense that
the amount of money budget on the project is more than what was spent on the project. In
addition, CV can also be expressed in percentage by dividing CV by EV and multiplying
by 100.
Table 4. 18 Cumulative Cost and Schedule Analysis
S.No. Month Cost and Schedule analysis
CV CV% SV SV%
1 May 0 0 -1,809,499.95 -100
2 June -286,220.42 - -10,779,227.58 -100
3 July 1,578,782.75 69.12 -18,052,878.2 -88.77
4 August 714,694.87 17.5 -22,078,048.64 -84.39
As shown in the above table, the schedule variance of the project is the difference between
the Earned Value and the planned value of the project, which is indicated above as a
negative value throughout the duration of the project. This shows that the project is lagging
behind schedule as planned. In addition, time is being spent in contrast with the measure
of work really gotten from the project and this would affect the project negatively due to
the late completion of the project. The SV can also be expressed in percentage by dividing
schedule variance (SV) by Planned value (PV) and multiplying by 100 which lies between
85
the ranges of -100 % to -84.39 % which indicates that the work percentage has not been
completed with contrast with the schedule plan of the project.
It has been shown that at month May and June the SPI and CPI is zero. In case of that when
we combined the cumulative amount of CPI and SPI, to forecast future and remaining work
cost there may be a problem to estimate reliable data, using the systems of EAC and ETC.
In case, this study has not been analysis for future predictions.
Main problems that was encounter in the project are lack of skilled manpower; office team
leader, office Engineer, planning Engineer, insufficient machineries and excess rain.
4.4.3.6. Case Study Two Analysis
Generally, the analysis status before and after applying EVA in terms of benefits and
project variables are listed in the Table below:
Table 4. 19 Project Comparative Findings
Item Status before applying EVA Status after applying EVA
Project budget 187,576,040.3 ETB 187,576,040.3 ETB
Cost variance (CV) Planned values compared with
actual cost
Earned Value compared with
actual cost
Cost performance index (CPI) Not available 1.21
Schedule performance index (SPI) Not available 0.16
The Table above shown the data resulting before applying EVA and afterwards and was
generated by the contrast of calculation. Before applying EVA, there was no accessible
information on SPI and CPI in light of the fact that the immediate connection between time
and cost execution was missed. The conclusion was that the project had under budget and
a good preformed but it is affected by schedule performance. As for the whole project, it
had a bad effect of schedule performed and may delay the project.
86
4.4.3.7. Result Analysis on Case Studies
Earned value management was being applied to the case studies and the results gotten can
be seen in the section above. Earned value analysis, cost analysis, schedule analysis, cost
forecasting and schedule forecasting have been used to analysis the values gotten from the
project to identify the projects current situation and also look into the projects future. So
Earned value management not only gives a detailed insight to how well the project is going
but it also helps the project team understand/asses the status of the project and predict the
future performance of the project.
The results of EVA of the two case studies where by in both case study 1 and 2, it was
observed that the actual cost was under Earned Value for most of the months which
represent that a good performance of CPI in an average of both above 1.00. This means
that both projects were able to operate under budget. But as PV is above EV though all
months it means that the progress was slow. As a result of this, SPI achieved a low
performance on both cases an average of below 1.00 which represent delay for total project
duration. In the same way future cost performance is additionally influenced by badly past
schedule performance due to late completion of the project which will be one of the cause
for cost overrun.
87
CHAPTER FIVE
CONCLUSIONS AND RECOMMENDATIONS
5.1. Findings
This study reveals that the most key players in construction industry have limited
awareness of EVM and is not practiced by most project managers. EVM is an important
tool for monitoring and controlling project performance, which is best practiced in the
construction industry. This paper has identified reasons why EVM is not practiced; barriers
for its use and success factors for EVM implementation to overcome the barriers.
A comprehensive literature review and detail analysis of Earned Value Management
(EVM) was conducted in order to test its use in construction projects. From the survey
result it was found that EVM provides five main benefits: EVM allows early warning of
performance problems to take corrective action, increase project visibility, increase
confidence in contractors’ ability to manage project by identifying problems early, assists
the project team to achieve cost objectives and provides more accurate management and
financial report. Current practice of planning, scheduling and monitoring projects is not
explicit enough from EVM point of view. These difficulties were addressed and the
concept was introduced based on the Earned Value survey.
The study identified possible constraints and difficulties in Bahir Dar road construction
projects, which hinders EVM’s implementation. These include lack of EVM expertise and
experience, minimal awareness of EVM including training, low familiarity with the EVM
techniques and poor understanding of EVM. To overcome the barriers for EVM
implementation, five critical success factors were determined: providing reliable data on
real costs and deadlines, preparing suitable WBS, convincing project managers of the value
and necessity of Earned Value in achieve project success, adequate EVM training and
understanding its requirement.
The results in this study also examined the practical application of Earned Value
Management in practice. Case studies confirm that the feasibility of introducing EVM into
88
two infrastructure construction projects for performance reporting and evaluation appears
is suitable as monitoring and control techniques of project cost. This technique can
facilitate the continuity of project and identify project’s up to date progress. However, it
was not able to provide exact value and forecast the projects future whether the project is
over or under budget and above or behind schedule.
From the analysis and results obtained, it can be concluded that monitoring and control is
of great importance in project management. Monitoring and control helps project managers
get better results from projects by ensuring the project is on track and identifying any
irregularities that could occur in the project. From the two case studies the data and
calculated results can be concluded that:
Currently both projects are lagging behind the schedule, but are under budget.
At the beginning stage of both projects, the critical activities were not closely
monitored, which seems to be one of the reason for delay of the project.
The delay in completing the activities, will likely lead to increase cost of the project.
So it is recommended that, the project needs immediate attention to get it back on
track.
The overall aim of this research which is to analysis the use of Earn Value Management as
a trend analysis tool in monitoring and control project has been satisfied from the case
study analysis. Implementing Earned Value Management into the project has given a
clearer insight to the project by showing the project status in terms of cost and time and
forecasting when the project would be finished and how much the project still requires.
89
Figure 5. 1 SWOT analysis of EVM
To summarize EVM and its features from the literature and analysis point of view, a SWOT
analysis (strengths, weaknesses, opportunities, threats) was carried out. Different factors
identified in this thesis that either contribute or hamper the implementation of EVM were
grouped in this analysis. The result can be seen in Figure 5.1. The purpose of this analysis
is to give the reader an overview of meaningful factors of EVM in the context of the
literature and help to evaluate whether the benefits can be considered to be greater than the
potential risks of the investment.
Strengths
• Integrate cost, time and scope
• Variety of indicator
• Early warning signs of poor performance
• Forecasting
• Ability to compare performance between projects
• Tool especially for project mangers
Weaknesses
• Requires accurate scheduling andresource planning (bottom up plannedWBS)
• Integration to level of effort work
• Estimating EV is difficult in various ofactivities
• Earned value may not provid exact upto date progress and forecast
Opportunities
• Improving scheduling and planning support other project actions
• One clear direction to develop current monitoring practices
• Utilization of all EVM indicators
• Progress data of complex activities
Threats
• Misinterpretation of indicators
• Overwhelming data acquisition
• If not implemented well, can be morenuisance than helpful tool
• Development of other models like Monte Carlo Simulation
EVM
90
5.2. Recommendations
Based on the study findings, the following points are suggested in order to enhance the
awareness and increase the level of application on EVM for Bahir Dar road construction
projects.
1. It is recommended that much efforts to be made in order to enhance the awareness
and increase the level of application on EVM among the key players in Bahir Dar
road construction industry.
2. The study recommends that the project management team assess the progress of the
implementation of the project and comparing the expected progress with the actual
progress.
3. In the same way it recommends that project managers deploy EVM tools in projects
so as to monitor and control the performance and progress of the project as well as
identify problems in advance.
4. One of the characteristics of EV is adequate tool for portfolio management. Thus,
it would be encouraged that government and clients in general do mandate for the
use of EV by the contractor.
5.3. Suggestions for Future Research
It is recommended that similar studies can be performed to increase EVM adoption and
evaluate the project performance of infrastructure projects, by providing wide scope for
project management software and increase sample size which could produce pictorial
representation of EVM parameters.
91
Bibliography Abba. (1997). Earned Value Management: Reconciling government and commercial
practices. Program Manager.
Abd Majid & McCaffer. (1997). Assessment of Work Performance of Maintenance
Contractors in Saudi Arabia, Journal of Management in Engineering.
Abraham. (2008). Kothari as cited in Abraham, (2008). Kothari, C.R. (2004). Research
methodology, Methods and Techniques. New Age International Limited
Publishers.
Acebes et al. (2013). Beyond Earned Value Management: A Graphical Framework for
Integrated Cost, Schedule and Risk Monitoring. Procedia - Social and Behavioral
Sciences, .
Alberto et, .. (2004). The use of earned value analysis (EVA) in the cost management of
construction projects.
Alvardo and David. (2004). “Assessing the performance of construction projects
:implementing earned value management at the general service administration
”journal of facilities management.
Amin M.E. (2005). Social Science Research: Conception, Methodology and Analysis.
ANSI/EIA. (1998). American National Standards Institute/Electronic Industries Alliance
(1998). ANSI-EIA-748-98,Earned Value Management Systems. Arlington, VA:
Electronic Industries Alliance; USA.
Antvik, L. C. (1998). Earned Value Management: A 200 Year Perspective. Paper presented
at the29th Annual Project Management Institute Seminars & Symposium, Long
Beach, CA.
APM. (2006). APM Body of Knowledge (5th ed.). High Wycombe, Buckinghamshire, UK:
Association for Project Management.
APM. (2013). Earned Value Management handbook, APM: princes risborough.
Association National Security Industrial. (1980). Cost Schedule Systems Conpendium.
Washington, DC.
Bhosekar and Gayatri. (2012). Cost Controlling Using Earned Value Analysis in
Construction Industries. International Journal of Engineering and Innovative
Technology (IJEIT).
Block. (1971). Accomplishment/Cost: Better project control. Harvard Business
Review(May-June).
Bower. (2007). New Directions in Project Performance and Progress Evaluation. School
of Construction, Property and Project Management. Melbourne: RMIT University.
92
Brandon, D. M. (1998). Implementing Earned Value Easily and Effectively. Project
Management Journal,.
Brock. (1983). “Earned value: burden or benefit?” The Measurable News, Sept, 12-13.
Butler et al. (1993). “Cost and schedule control at besselaar.” Proc., Proj. Manage.
Institute.
Carlos. (2004). The use of Earned Value Analysis (EVA) in the cost management of
construction projects.
Christensen. (1990). The Role of Analysis in CSCSC. Program Manager, 19(July-August).
Christensen. (1998). The Costs and Benefits of the Earned Value Management Process.
Acquisition Review Quarterly (Fall 1998).
Clough. (2000). Clough, R. H., Sears, G. A., and Sears, S. K. (2000). Construction Project
Management 4th edition. John Wiley & Sons, Inc., USA.
Cooke-Davies. (2003). The maturity of project management in different industries: An
investigation into variations between project management models. International
Journal of Project Management.
De Falco & Macchiaroli,. (1998). Timing of project control activities in project planning.
International Journal of Project Management.
De Marco & Narbaev. (2013). Earned value-based performance monitoring of facility
construction projects. Journal of Facilities Management.
Degoff. (1999). Degoff, R. A., and Friedman H. A. (1999). Construction Management,
Basic Principle for Architects, Engineers and Owners. A Wiley Series in
Construction Management and Engineering.
Deltek. (2008). What are the biggest perceived issues with EVM? And what is the solution
for each issue?
Deng, M. & Hung, Y. (1998). Integrated cost and schedule control: Hong Kong
perspective.Project Management Journal,.
Duncan et al. (1990). J.M (1990) in Xiao, H., and Proverbs, D. (2002b).The Performance
of Contractors in Japan, The UK ant The USA: An Evaluation of Construction
Quality. International Journal of Quality and Reliability Management.
Englert and associates. (2000). Earned value management. Case study using Microsoft
project.
Fleming & Koppelman. (2005). Earned Value Project Management, 3rd edition. Newton
Square, PA: Project Management Institute (PMI).
Fleming and Koppelman. (2009). The Two Most Useful Earned Value Metrics: the CPI
and the TCPI).
93
Fleming and Koppelman. (2010). Earned Value Project Management, 4th ed, Proj.
Manage. Institute.
Flemming. (1998). Cost / Schedule Control Systems Criteria. The Management Guide to
C/SCSC. England: Probus Publishing Company, 1988.
Fox. (1996). Roots of Earned Value System. The Measurable News.
Frigenti and Comninos. (2002). The Practice of Project Management: a guide to the
business-focused approach. Kogan Page, London.
Gower. (2007). Project Management, Project and Programme Management Resources for
Students (9 ed.).
Hailemeskel, T. (2013). Management Control of Projects in Construction Industry
Ethiopian Context.
Harrison, F. L. ( 1997). Advanced Project Management: A Structured Approach England:
Gower Publishing Limited Company.
Heagney. (2012). Fundamentals of Project Management (4th ed.). New York: American
Management Association.
Henderson & Zwikael. (2008). “Does project performance Exist ? Are-examination of CPI
and Evaluation of SPI(t) stability”. Crosstalk-the journal of Defense Software
Engineering .
Hillson. (2004a, October 2004). Earned Value Management and Risk Management: A
Practical Synergy. Paper presented at the PMI Global Congress North America,
Anaheim, CA, USA.
Kasiem, S. (2008). Study of the problems of construction conditions of contract for public
worksin Ethiopia. Master’s Thesis, Addis Ababa University.
Kauffmann et al., P. K. (2002). Using Earned Value Methods to SubstantiateChange-of-
Scope Claims. Engineering Management Journal,.
Kerzener. (2001). Project Management: A system approach to planning, scheduling and
controlling (7th edn), London, John Wiley and Sons, Inc.
Kerzner. (2003). Project Management: A Systems Approach to Planning, Scheduling and
Controlling (8th ed.). Hoboken, NJ, USA: John Wiley & Sons.
Kerzner Harold. (1998). Project Management, A Systems Approach to Planning,
Scheduling and Controlling, Harold Kerzner, 6ª Edição, Van Nostrand Reinhold,
1998.
Khamidi et al. (2011). Application of Earned Value System on an Infrastructure project: A
Malaysian Case Study. 2011 International Conference on Management and Service
Science.
94
Kim et al. (2003). A model for effective implementation of Earned Value Management
methodology. International Journal of Project Management.
Little Inc. (1983 ). Survey relating to the Implementation of Cost/Schedule Control System
Criteria within the Department of Defense and Industry, Phase I and II: A Report
for the Assistant Secretary of Defense.
Lynn, M. R. ( 1986). Determination and quantification of content validity. Nursing
Research.
Magigi. (2015). The case study approach.
Matters. (2014). “Manufacturing report 2014,”.
McKay.J., & Marshall. P,. (2001). The Dual Imperatives of Action Research. Information
Technology& People,.
Moski. (1951). Cost Control Fundamentals. In Plant Executives' Handbook. New York:
McGraw-Hill Publishing Co.
MoWUD. (2001). Study for Capacity Building of the Construction Industry Ethiopia,
Ministry of Works and Urban Development, Addis Ababa (Amharic).
Muhwezi Acai & Otim. (2014). An Assessment of the Factors Causing Delays on Building
Construction Projects in Uganda. International Journal of Construction Engineering
and Management.
Naderpour and Mofid. (2011). Improving construction management of an educational
center by applying earned value management technique prociedia.
NDIA. (1998). ANSI/EIA-748 Guide: Earned Value Management System (Standard):
American National Standard Institute/Electronic Industry Association.
Ng shi cia. (2015). The contribution of Earned Value Analysis for cost controlling of
construction projects.
Paige H. (1963). How PERT-Cost Helps the General Manager. Harvard Business
Review(Nov-Dec).
Pär Karlsson. (2011). Project Management in Sweden and Ethiopia, Potential
improvements in Project Management methods.
Peterson & Oliver. (2001). EV-Lite: Earned Value Control for Fast Paced Projects. Paper
presented at the 32th Annual Project Management Institute Seminars and
Symposium, Nashville, TN.
PMBOK. (2008). A guide to the Project Management Body of Knowledge, Newtown
Square: Project Management Institute, Inc.
PMI. (2004). A Guide to the Project Management Body of Knowledge (3rd ed.). Newtown
Square, PA: Project Management Institute.
95
PMI. (2005). Practice Standard for Earned Value Management. Newtown Square, PA:
Project Management Institute.
PMI. (2011). A Guide to the Project Management Body of Knowledge ( PMBBOK Guide
3rd Edition). Newtown Square, PA. USA: Project Management Institute. inc.
PMI. (2001). Practice Standard for Work Breakdown Structures. Newtown Square, PA,
USA: Project Management Institute.
Raveesh L. & Sundip S. (2015). Project Performance Evaluation by Earned Value
Analysis.
Raz & Globerson. (1998). Effective Sizing and Content Definition of Work Packages.
Project Management Journal.
Richard. (2001). Analysis and Application of Earned Value Management to the Naval
Construction Force.
Ritz 1994 & Degoff et, .. (1999). Ritz, G. J. (1994). Total Construction Project
Management. Mc Graww-Hill, Printed in Singapore. Degoff, R. A., and Friedman
H. A. (1999). Construction Management, Basic Principle for Architects, Engineers
and Owners. A Wiley Series in Construction Managem.
Saitow. (1969). CSPC: Reporting project progress to the top. Harvard Business
Review(Jan-Feb).
Schulte. (2001). What is the Health of my Project? The Use and Benefits of Earned Value.
White Paper Library, Welcom.
Sekaran. (2003). Research Methods For Business - A Skill-Building Approach (4nd ed.).
New York: John Wiley & Sons, Inc.
Shtub et, a. B. (2005). Project Management: Processes, Methodologies, and Economics (2
ed.). New York, NY: Prentice Hall.
Smith,Winter, Morris & Cicmil, . (2006). Winter, M.; Smith, C.; Morris, P.; Cicmil, S.
(2006) Directions for futureresearch in project management: the main findings of
a UK governmentfunding.
Solomon, S. (2015). The Management of Construction Processes in Developing Countries:
A Case Study of the Ethiopian Roads Authority.
Song. (2010). Earned Value Management-A Global and Cross-Industry Perspective on
Current EVM Practice. ISBN 978-1-935589-8, Project Management Institute,
Newtown Square, PA.
Sparrow, H. (2000). EVM = Earned Value Management Results in Early Visibility and
ManagementOpportunities. Paper presented at the 31st Annual Project
Management Institute Seminars andSymposium, Houston, TX.
96
Spinner. (1997). Spinner, M. P. (1997). Project Management Principles and Practice.
Prentice- Hall, Ohio.
Stephenie. (2017). Available at: http://www.statisticshowto.com/cronbachs-alpha-spss/.
Tadesse, A. (2016). Assessment on Performance and Challenges of Ethiopian Construction
Industry.
Tadesse, Y. (2006). MSc thesis on construction cost estimation guideline for local
contractors in Ethiopia. AAU.
Terrel M. et al., B. A. (1998). Evaluating Project Performance Tools: A CaseStudy. Paper
presented at the 29th Annual Project Management Institute Seminars
andSymposium, Long Beach, CA.
Thamhain, H. J. (1998). Integrating Project Management Tools with the Project Team.
Paperpresented at the 29th Annual Project Management Institute Seminars and
Symposium, LongBeach, CA.
True, L. (2003). Do you really know your construction costs? Journal of Construction
Accounting &Taxation,.
Uyttewaal. (2003). Dynamic Scheduling with Microsoft Office Project.
Vanhoucke, M. (2010). Measuring Time, Improving Project Performance Using Earned
ValueManagement. Springer.
Wideman, R. M. (1999). Cost Control of Capital Projects and the Project Cost Management
SystemsRequirements (2nd ed.). Vancouver, BC: AEW Services and BiTech.
Williams. (2008). The Principles of Project Management. VIC Australia: Site Point Pty
Ltd.
Zewdu and Aregaw. (2015). “Causes of Contractor Cost Overrun in Construction Projects:
The Case of Ethiopian Construction Sector.
Zohrabi. (2013.). Mixed Method Research: Instruments, Validity, Reliability and
Reporting Findings.
97
APPENDIX
98
Appendix A: Survey
Research Title: Application of Earned Value Management (EVM) on Performance
Evaluation of Infrastructure Projects: A Case Study of Amhara Road Works Enterprise
(ARWE) Construction Projects.
Dear Respondent: -
I am a postgraduate student in Construction Technology & Management in Bahir Dar
Institute of Technology, Faculty of Civil & Water Resource Engineering. At present, the
construction industry in Ethiopia is the major sector and developing tremendously where
public and private sectors are investing huge amount of resources. However, during
construction, it has been observed that various factors may lead to time and cost overrun.
Thus, it has become a major problem to complete projects on time and within the estimated
budget.
Therefore, this questionnaire survey is designed to evaluate the utilization of Earned Value
Management (EVM) to monitor projects as part of my master’s thesis. This survey is
intended to help the researcher get information on the current practices and drawbacks to
adopt the standard practices of EVM technique in measuring performance and forecasting
of road projects by knowing factors that hinder the usage and application of EVM in Bahir
Dar.
The purpose of this study is purely academic and the information given will be treated with
the highest degree of confidence. You have been selected as a key respondent for this study.
Kindly, complete the questionnaire to enable the researcher complete the study.
Please tick the answer which represents your opinion on the subject. If you have questions
related to the study, please don’t hesitate to contact me at +251918618384 or through email
address [email protected].
I appreciate your participation in this effort.
Thank you for your collaboration.
99
SECTION A: Background Information
1. Name of company (Optional) _____________________________________
2. Type of Organization: Contractor ___ Consultant ___ Owner ____ Other ____
3. Year of establishment: _______________________
4. Classification: GC ____ BC ____ RC_____ Grade ____Other ____
Please tick or circle the appropriate number.
1 AGE
Less than 25 years 26-35 years 36-45 years 46-55 years 56 years & above
1 2 3 4 5
4 EDUCATION QUALIFICATION
PhD Masters Bachelors Diploma Certificate Others specify
1 2 3 4 5 6
SECTION B: Multiple Choice - circle the letter/s that best indicates your opinion.
1. How do you track Project Costs/Progress?
a. Gant chart
b. Critical path method
c. PERT method
d. EVM Earned Value Management
e. Other ______________________
___________________________
2. Which technique do you recommend to measure performance on construction projects?
a. Gant chart
b. Critical path method
c. PERT method
d. EVM
e. Other ___________________
2 SEX
Female Male
1 2
3 TITLE
Project manager Architect Engineer Quantity surveyor Others specify
1 2 3 4 5
5 DURATION OF SERVICE
Less than 5 years 5-10 years 11-16 years Above 17 years
1 2 3 4
100
3. What is your opinion of the value of EVM?
a. Extremely valuable
b. Useful for most projects
c. Suitable for some projects
d. Not worth the effort
4. If EVM is used in your organization, identify one or more of these reasons:
a. Required by client
b. Required by project sponsors
c. Used voluntarily by managers
d. Used on a trial basis/occasionally
e. Not sure why it is used
f. Other _____________________
5. If EVM is not used in your organization, identify one or more of these reasons:
a. Not requested: Senior management or clients do not require EVM reports
b. Not successful: Earned Value techniques were tried in the past, and rejected
c. No training: Project managers are untrained in the application of EVM
d. Too complex: Earned Value procedures seem too complicated
e. No budget: Project budgets are not required by management or clients
f. No schedule: Project schedules are not required by management or clients
g. Partial costs: Project budgets do not cover the cost of all project resources or costs
h. Not sure: Uncertain, or other reasons
6. How do you monitor and control progress throughout a project, your project status
whether it is over budget or under budget and ahead of schedule or behind schedule?
a. By comparing only planned costs against actual costs
b. By comparing Earned Value (value of work performed) to planned & actual cost
c. Not sure
d. Others: specify __________________________________________________
7. How much do you agree that EV, as a new estimate value on top of Plan Value and
Actual Cost, is necessary in cost estimating?
a. Strongly agree
b. Agree
c. Neutral
d. Strongly disagree
e. Disagree
101
SECTION C: Respondents Level of Agreement
Please indicate the extent of use and level of agreement on various EVM principles on a
scale of 1-5 for the following questions.
Scale: 1 “Strongly Disagree”, 2 “disagree”, 3 “not sure”, 4 “agree”, 5 “strongly agree”.
1. How knowledgeable are you about EVM?
S.N Participants knowledge about EVM
techniques
Weighted value
1 2 3 4 5
1. 1 Expert
2. 2 Knowledgeable
3. 3 Familiar
4. 4 Slightly familiar
5. 5 Not familiar
2. How much do you agree that your organization is able to provide up-to-date
information on project cost and schedule in time?
3. The following are examples of EVM contribution. Based on your experience,
indicate your level of agreement on the contribution of EVM for project control.
S.N Contribution of EVM Weighted value
1 2 3 4 5
1. Increased project visibility
2. Improved estimating and planning
3. EVM provides early warning of performance problems to
take corrective action
4. EVM assists the project team to achieve cost objectives
S.N Weighted value
1 2 3 4 5
1 Organization is able to provide up-to-
date information
102
5. EVM improves communication among project team
members
6. EVM assists the project team to achieve schedule objectives
7. EVM improves project scope management
8. Overall, EVM is cost effective tool for performance
management
9. Increase confidence in contractors ability to manage project
by identifying problems early
10. To monitor progress and to develop cost and schedule
forecast for active project
11. Used provide the provision of more accurate management
and financial report
12. EVM offers choice to integrate risk management
13.
4. Following are list of barriers of company to adopt the practice of EVM for
measuring performance and forecasting construction projects. Which elements do
you think are the major barriers for a company to adopt efficient and effective
management practice of Earned Value Management?
S.N Barriers of company to practice EVM Weighted value
1 2 3 4 5
1. Lack of management support
2. Inability to find qualified resources
3. Difficulty integrating cost, resource and schedule data
concerning real cost and deadlines
4. It takes too long to manually produce reports
5. Pressures to report only good news
6. Difficulty in adequate work breakdown structure (WBS) to
apply EVM
7. Poor understanding of EVM
8. Distrust and conflict between project managers, project
consulting and government
9. Minimal awareness of EVM including training
10. Low familiarity with the EVM techniques
103
11. Lack of EVM expertise and experience
12. Earned Value requires more information.
13.
14.
15.
5. Following are list of Success factors for EVM implementation. Which elements do
you think are the major Success factors to implement the usability of EVM?
S.N Success factors for EVM implementation Weighted value
1 2 3 4 5
1. Convincing project managers of the value and necessity of
using Earned Value in achieve project success
2. Top management support
3. Convince management of the need to require project
managers to be responsible for costs on a project.
4. Buy in of EVM by the project management staff
5. Adequate EVM training
6. Culture of the organization and top management leadership
style
7. Maturity of the organization’s project management system
8. EVM needs qualified team
9. Understanding its requirement
10. Provide reliable data on real costs and deadlines
11. Preparing suitable work break down structure (WBS)
12.
13.
14.
15.
Thank you for your participation!
104
Appendix B: The results of reliability test (Cronbach's Alpha) of questionnaire
Table B- 1: SPSS result of reliability test for contribution of using EVM for project control
purpose
Reliability Statistics
Cronbach's Alpha N of Items
.831 12
Item-Total Statistics
Scale
Mean if
Item
Deleted
Scale
Variance if
Item
Deleted
Corrected
Item-Total
Correlation
Squared
Multiple
Correlation
Cronbach's
Alpha if
Item
Deleted
Increased project visibility 41.30 15.905 .591 .654 .811
Improved estimating and planning 41.91 16.523 .313 .320 .836
EVM provides early warning of
performance problems to take
corrective action
41.03 14.843 .712 .665 .799
EVM assists the project team to
achieve cost objectives
41.58 16.377 .497 .465 .818
EVM improves communication
among project team members
41.73 15.267 .619 .668 .807
EVM assists the project team to
achieve schedule objectives
42.06 17.934 .143 .301 .843
EVM improves project scope
management
41.67 15.542 .603 .785 .809
Overall, EVM is cost effective tool
for performance management
42.42 16.314 .404 .387 .826
Increase confidence in contractors
ability to manage project by
identifying problems early
41.55 15.943 .745 .748 .804
To monitor progress and to develop
cost and schedule forecast for
active project
42.06 16.934 .319 .464 .832
Used provide the provision of more
accurate management and financial
report
41.58 15.189 .789 .860 .796
105
EVM offers choice to integrate risk
management
42.45 17.131 .292 .328 .834
Scale Statistics
Mean Variance Std. Deviation N of Items
45.58 18.939 4.352 12
Table B- 2: SPSS result of reliability test (Cronbach's Alpha) for Barriers of Company to
Practice EVM
Reliability Statistics
Cronbach's Alpha N of Items
.760 12
Item-Total Statistics
Scale Mean
if Item
Deleted
Scale
Variance
if Item
Deleted
Corrected
Item-Total
Correlation
Squared
Multiple
Correlation
Cronbach's
Alpha if
Item
Deleted
Lack of management
support
38.52 21.195 .477 .444 .734
Inability to find qualified
resources
39.12 21.360 .521 .516 .726
Difficulty integrating
cost, resource and
schedule data concerning
real cost and deadlines
39.36 20.551 .686 .666 .703
It takes too long to
manually produce
reports
38.88 22.547 .457 .540 .735
Pressures to report only
good news
39.18 22.466 .513 .514 .729
Difficulty in adequate
work breakdown
structure (WBS) to apply
EVM
39.36 22.051 .547 .591 .724
Poor understanding of
EVM
37.85 24.508 .316 .394 .751
Distrust and conflict
between project
managers, project
consulting and
government
38.94 23.996 .336 .456 .750
Minimal awareness of
EVM including training
37.55 25.943 .226 .641 .758
Low familiarity with the
EVM techniques
37.88 27.172 -.031 .521 .780
106
Lack of EVM expertise
and experience
37.24 26.627 .110 .589 .765
Earned Value requires
more information
38.79 23.610 .401 .461 .743
Scale Statistics
Mean Variance Std. Deviation N of Items
42.06 27.371 5.232 12
Table B- 3: SPSS result of reliability test (Cronbach's Alpha) for Success Factors for EVM
Implementation
Reliability Statistics
Cronbach's Alpha N of Items
.714 11
Item-Total Statistics
Scale
Mean if
Item
Deleted
Scale
Variance
if Item
Deleted
Corrected
Item-Total
Correlation
Squared
Multiple
Correlation
Cronbach's
Alpha if
Item
Deleted
Convincing project managers of
the value and necessity of using
Earned Value in achieve project
success
39.82 10.028 .501 .419 .678
Top management support 40.39 9.121 .517 .574 .666
Convince management of the
need to require project managers
to be responsible for costs on a
project.
41.21 8.735 .525 .564 .663
Buy in of EVM by the project
management staff
41.33 11.354 -.028 .301 .765
Adequate EVM training 39.97 9.530 .405 .535 .687
Culture of the organization and
top management leadership style
40.76 9.752 .418 .601 .685
Maturity of the organization’s
project management system
40.79 9.672 .484 .434 .675
EVM needs qualified team 40.61 10.809 .225 .601 .711
Understanding its requirement 40.15 10.133 .494 .513 .680
Provide reliable data on real
costs and deadlines
39.73 11.017 .199 .560 .713
Preparing suitable work break
down structure (WBS)
39.79 10.360 .399 .624 .691
Scale Statistics
Mean Variance Std. Deviation N of Items
44.45 11.818 3.438 11
107
Appendix C: Interview Guide
Application of Earned Value Management (EVM) on Performance Evaluation of
Infrastructure Projects: A Case Study of Amhara Road Works Enterprise (ARWE)
Construction Projects.
INTRODUCTION: The purpose of the interview is to gather key information from the
project managers, Architects, Engineers and Quantity Surveyors about the application of
Earned Value Management (EVM) Technique to Measuring the Performance of a
Construction Project in Amhara Road infrastructure projects in Bahir Dar city. Here is list
of questions expected to be answered by respondent.
1. What are the existing performance measuring techniques used on the construction
projects?
2. How effective and efficient are they in measuring performance of a construction
project
3. What are the possible barriers of EVM Technique in measuring performance of a
construction project in Bahir Dar?
4. What are the likely recommendations with regard to the above challenges?
5. What are the possible benefits of EVM Technique in measuring performance of a
construction project in Bahir Dar?
6. What perception do professionals have on the EVM Technique in measuring
performance of a construction project in Bahir Dar?
7. Any general comment with regard to the application of EVM Technique on
measuring the performance of construction projects in Bahir Dar city?
Thank you!!!
108
Appendix D: Results of Practical Application
Figure A:Burie Agro Industry Park Road Construction Project Graphical Analysis of Cumulative Planned Value, Earned Value and Actual Cost (As of July 30)
Octo Nove Decem Janu Febru Mar Apri May June July
PV 23,140,871 43,746,188 51,051,736 136,072,118 339,324,130 486,698,534 715,812,317 762,684,390 797,707,611 810,512,068
EV 298,354 2,251,362 26,796,309 32,920,230 49,336,392 77,215,718 120,684,663 170,339,118 197,185,896 200,936,527
AC 987,880 3,855,498 19,564,552 28,134,351 45,872,204 66,758,044 91,285,493 123,618,138 145,196,297 146,675,600
-
100,000,000
200,000,000
300,000,000
400,000,000
500,000,000
600,000,000
700,000,000
800,000,000
900,000,000
Res
ou
rce
in E
TB
time
PV
EV
AC
109
Figure B: Burie Agro Industry Park Road Construction Project Cumulative cost and Schedule Variance
at Various Status Months
Figure C: Burie Agro Industry Park Road Construction Project Cumulative Cost and Schedule
Performance Index at Various Status
(700,000,000.00)
(600,000,000.00)
(500,000,000.00)
(400,000,000.00)
(300,000,000.00)
(200,000,000.00)
(100,000,000.00)
-
100,000,000.00
0 2 4 6 8 10 12
Res
ou
rce
in E
TB
Time in Months
SV CV
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
0 2 4 6 8 10 12
Va
lue
Time in month
SPI CPI
110
Figure D:Getermenged-Airport Asphalt Widening Road Construction Project Graphical Analysis of Cumulative Planned Value, Earned Value and Actual Cost (As of August
30)
May June July August September October November December January February March April May2
PV 2,234,778.7 11,229,101. 20,810,148. 26,660,644. 39,811,899. 55,797,199. 65,363,752. 79,640,207. 105,095,847 145,060,672 168,775,395 181,351,248 187,871,185
EV - - 2,282,800.7 4,083,530.7
AC - 286,220.4 704,017.9 3,368,835.8
-
20,000,000.0
40,000,000.0
60,000,000.0
80,000,000.0
100,000,000.0
120,000,000.0
140,000,000.0
160,000,000.0
180,000,000.0
200,000,000.0
Res
ourc
e
Time in Month
PV
EV
AC
111
Figure E: Getermenged-Airport Asphalt Widening Road Construction Project Cumulative Cost and Schedule
Performance Index at Various Status Months
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
M A Y J U N E J U LY A U G U S T
VA
LU
E
TIME IN MONTH
SPI CPI
112
Appendix E: EVM Acronyms
Table A.: Comparison of Earned Value Management acronyms (ANSI/EIA, 1998)
ANSI/EIA-748Standard DoD C/SCSC Standard Local name
Planned Value, PV Budgeted Cost of Work Scheduled,
BCWS
Planned
Actual Cost, AC Actual Cost of Work Performed,
ACWP
Expense
Earned Value, EV Budgeted Cost of Work Performed,
BCWP
Executed
Cost Performance Index, CPI Cost Performance Index, CPI -
Schedule Performance Index, SPI Schedule Performance Index, SPI -
Cost Variance Cost Variance Profit (Loss)
Schedule Variance Schedule Variance -
113
Appendix F: ANSI/EIA-748 EVMS Criteria
The criteria are: (ANSI/EIA, 1998)
1. Define authorized work
2. Identify Program Organization Structure
3. Company integration of EVMS subsystems with Work Breakdown Structure
(WBS)
4. Identify organization/function for overhead
5. Integrate WBS and Organization Breakdown Structure (OBS), create control
accounts
6. Sequential scheduling of work
7. Identify interim measures of progress, i.e. milestones, products, etc.
8. Establish time-phased budget
9. Identify significant cost elements within authorized budgets
10. Identify discrete work packages
11. All work package budgets and planning packages sum to control acct
12. Identify and control LOE budgets
13. Establish overhead budgets by organization element
14. Identify management reserve and undistributed budget
15. Reconcile program target cost goal with sum of all internal budgets
16. Record direct costs from accounting system
17. Summarize direct costs into WBS without allocation
18. Summarize direct costs into OBS without allocation
19. Record indirect costs
20. Identify unit costs, equivalent units’ costs or lot costs
21. Accurate material cost accumulation by control accounts; EV measurement at
right time; full accountability of material
22. Control account monthly summary, identification of Cost Variance (CV) and
Schedule Variance (SV)
23. Explain significant variances
24. Identify and explain indirect cost variances
114
25. Summarize data elements and variances thru WBS/OBS for mgmt.
26. Implement management actions as result of EVM analysis
27. Revise EAC based on performance data; calculate VAC
28. Incorporate authorized changes in timely manner
29. Reconcile budgets with prior budgets
30. Control retroactive changes
31. Prevent all but authorized budget changes
32. Document changes to Performance Measurement Baseline (PMB)
ANSI/EIA-748 EVMS Intent Guide [ANSI/EIA] defines in detail the management value
and intent for each of the 32 criteria listed above.
115
Appendix G: ANSI/EIA-748 EVMS Criteria in Five categories
Table B: Earned value management 32 criteria structured in five categories (ANSI/EIA,
1998)
Category General Content and
Description
Criteria
Numbers
Organization Define the work breakdown structure (WBS), the program
organizational structure and show integration with the host
organization for schedule and cost control.
1-5
Planning, scheduling and
budgeting
Identify the products, schedule the work according to work
packages and apply a time-phased budget to them and project
itself. Identify and control direct costs, overhead and time,
and
material items.
6-15
Accounting
considerations
Record all direct and indirect costs according to the WBS and
CAPs. Provide data necessary to support earned value
reporting and management.
16-21
Analysis and
management reports
Provide analysis and reports appropriate to the project. 22-27
Revisions and
data maintenance
Identify and manage changes, updating current scope,
schedule and budgets after changes are approved.
28-32