Page 1:  · 2021. 1. 12. · On-Site Representative Present: Tom Fargo, Reidman Construction Site Notes: -Apartment structure is up and work continues on the building. -Excavation for the
Page 2:  · 2021. 1. 12. · On-Site Representative Present: Tom Fargo, Reidman Construction Site Notes: -Apartment structure is up and work continues on the building. -Excavation for the