221084-89 dmm

Upload: ramki073033

Post on 03-Jun-2018

240 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 221084-89 dmm

    1/30

    Decision Making Model

    Transshipment Problem

    Case Presentation

    Submitted to: Prof. Hitesh Arora

    Presented by :

    Pankaj Bansal221084Piyush Jain221089

  • 8/11/2019 221084-89 dmm

    2/30

    Case Description

    There are two Suppliers (S1, S2) three plants (P1, P2, P3)and two warehouses(W1, W2).

    Warehouse receive the raw material from the two suppliers

    and ship them to the three plants.

    Supply value of Suppliers S1- 1000 units S2 - 1500 units

    Demand of plants

    P1800 units P21200 units P31000

    units

    Objective : To calculate the optimal shipping plan from

    different sources(suppliers) to different destinations

    (plants) through the transient nodes(warehouses).

  • 8/11/2019 221084-89 dmm

    3/30

    Transportation cost per unit b/w different sources

    and destinations combination can be

    represented as :

    P1 P2 P3 W1 W2 TotalSupply

    S1 17 16 1000

    S2 11 13 1500

    W1 15 8 20 0 13

    W2 18 10 9 14 0

    Total

    Demand

    800 1200 1000

    Here, Total Supply = 2500 units and Total Demand = 3000 units

    Total supply is not equal to total demand, therefore its an

    Unbalanced Transportation Problem

  • 8/11/2019 221084-89 dmm

    4/30

    Balanced Transportation Problem

    P1 P2 P3 W1 W2Total

    Supply

    S1 17 16 1000

    S2 11 13 1500

    Sd 0 0 500

    W1 15 8 20 0 13 3000

    W2 18 10 9 14 0 3000

    Total

    Demand

    800 1200 1000 3000 3000

    Cost Table

    BACK 1

    BACK 2

    BACK 3

  • 8/11/2019 221084-89 dmm

    5/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1 17 16 1000 1

    S2 11 13 1500 2

    Sd 0 0 500 0

    W1 15 8 20 0 13 3000 8

    W2 18 10 9 14 0 3000 9

    Demand 800 1200 1000 3000 3000

    Penalty 3 2 11 0 0

    1000 2000

    1

    USING VAM METHOD

  • 8/11/2019 221084-89 dmm

    6/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1 17 16 1000 1

    S2 11 13 1500 2

    Sd 0 0 500 0

    W1 15 8 20 0 13 3000 8

    W2 18 10

    1000

    9

    14

    0 2000 10

    Demand 800 1200 1000 3000 3000

    Penalty 3 2 11 0 0

    2000

    1000

    2

  • 8/11/2019 221084-89 dmm

    7/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1 17 16 1000 1

    S2 11 13 1500 2

    Sd 0 0 500 0

    W1

    15

    8 20 0 13

    3000

    8

    W2 18 10

    1000

    9

    14 2000

    0 3000 10

    Demand 800 1200 1000 3000 1000

    Penalty 11 0 0

    800 2200

    3

  • 8/11/2019 221084-89 dmm

    8/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1 17 16 1000 1

    S2 11 13 1500 2

    Sd

    0 0 500

    0

    W1 800

    15 8 20 0 13 2200

    8

    W2 18 10

    1000

    9 14

    2000

    0 3000 10

    Demand 800 1200 1000 3000 1000

    Penalty 11 0 13

    1200 1000

    4

  • 8/11/2019 221084-89 dmm

    9/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1 17 16 1000 1

    S2 11 13 1500 2

    Sd

    0 0

    500

    0

    W1 800

    15

    1200

    8 20 0 13 1000 13

    W2 18 10

    1000

    9 14

    2000

    0 2000 10

    Demand 800 1200 1000 3000 1000

    Penalty 11 0 13

    500

    500

    5

  • 8/11/2019 221084-89 dmm

    10/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1 17 16 1000 1

    S2 11 13 1500 2

    Sd

    0

    500

    0

    500

    0

    W1 800

    15

    1200

    8 20 0 13 1000 13

    W2 18 10

    1000

    9 14

    2000

    0 3000 10

    Demand 800 1200 1000 3000 500

    Penalty 11 11 0

    1000

    2000

  • 8/11/2019 221084-89 dmm

    11/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1 17 16 1000 1

    S2

    11 13 1500 2

    Sd

    0

    500

    0 500 0

    W1 80015 12008 20 0 13 3000 13

    W2 18 10

    1000

    9 14

    2000

    0 3000 10

    Demand 800 1200 1000 2000 1000

    500

    Penalty 11 6 3

    1500

    500

  • 8/11/2019 221084-89 dmm

    12/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1

    17 16

    1000

    1S2

    1500

    11 13 1500 2

    Sd

    0

    500

    0 500 0

    W1 80015

    12008 20 0 13 3000 13

    W2 18 10

    1000

    9 14

    2000

    0 3000 10

    Demand 800 1200 1000 500 1000

    500

    Penalty 11 17 16

    500

    500

  • 8/11/2019 221084-89 dmm

    13/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1

    500

    17 16

    1000

    500 16

    S2

    1500

    11 13 1500 2

    Sd

    0

    500

    0 500 0

    W1 800

    15

    1200

    8 20 0 13 3000 13

    W2 18 10

    1000

    9 14

    2000

    0 3000 10

    Demand 800 1200 1000 3000 1000

    500

    Penalty 11 17 16

    500

  • 8/11/2019 221084-89 dmm

    14/30

    P1 P2 P3 W1 W2 Supply Penalty

    S1

    500

    17

    500

    16

    1000

    16

    S2

    1500

    11 13 1500 2

    Sd

    0

    500

    0 500 0

    W1 800

    15

    1200

    8 20 0 13 3000 13

    W2 18 10

    1000

    9 14

    2000

    0 3000 10

    Demand 800 1200 1000 3000 3000

    Penalty 11 17 16

  • 8/11/2019 221084-89 dmm

    15/30

    Initial Basic Feasible Solution

    (IBFS)

    P1 P2 P3 W1 W2

    S1 - - - 500 500

    S2 - - - 1500 -

    Sd - - - - 500

    W1 800 1200 - 1000 -

    W2 - - 1000 - 2000

    Here, Number of Basic Variables = 9

    Also M+N-1 = 9

    Hence, Its a Non-Degenerate Solution .

    BACK

  • 8/11/2019 221084-89 dmm

    16/30

    MODI Method

    Ui

    - - - 17 16 16

    - - - 11 - 10

    - - - - 0 0

    15 8 - 0 - -1

    - - 9 - 0 0

    Vj 16 9 9 1 0

    Cost for Occupied

    CellsUi

    - - 16

    - 13 10

    0 - 0

    - - 20 - 13 -1

    18 10 - 14 - 0

    Vj 16 9 9 1 0

    Cost for Unoccupied Cells

    Ui + Vj= Cij IBFS COST TABLE

  • 8/11/2019 221084-89 dmm

    17/30

    p1 p2 p3 w1 W2

    S1 - -

    S2 - 3

    Sd -1 -

    W1 - - 12 - 14

    W2 2 1 - 13 -

    MODI Method

    Net Evaluation

    Cij = Cij(Ui + Vj )

    As there is a negative element ( i.e. all Cij > 0condition is not satisfied) innet evaluation table, thus it is NOT AN OPTIMAL SOLUTION.

    Need to introduce at the negative element position.

  • 8/11/2019 221084-89 dmm

    18/30

    P1 P2 P3 W1 W2

    S1 - - - 500- 500+

    S2 - - - 1500 -

    Sd - - - 500-

    W1 800 1200 - 1000 -

    W2 - - 1000 - 2000

    Minimal possible value of = 500

    Two basic cells will become zero.

    Introduction of Theta ()

  • 8/11/2019 221084-89 dmm

    19/30

    Basic Feasible Solution (NBFS) -

    1

    P1 P2 P3 W1 W2

    S1 - - - - 1000

    S2 - - - 1500 -

    Sd - - - 500 -

    W1 800 1200 - 1000 -

    W2 - - 1000 - 2000

    Here, Number of Basic Variables = 8

    Also M+N-1 = 9

    Hence, Its a Degenerate Solution .

    Degeneracy is resolved by introduction of Epsilon ()

    BACK

  • 8/11/2019 221084-89 dmm

    20/30

    Introduction of Epsilon()

    P1 P2 P3 W1 W2

    S1 - - - - 1000

    S2 - - - 1500 -

    Sd - - - 500 -

    W1 800 1200 - 1000

    W2 - - 1000 - 2000

    Here, Number of Basic Variables = 9

    Also M+N-1 = 9

    Hence, Its a Non-Degenerate Solution

  • 8/11/2019 221084-89 dmm

    21/30

    MODI Method

    Ui

    - - - - 16 16

    - - - 11 - 24

    - - - 0 - 13

    15 8 - 0 13 13

    - - 9 - 0 0

    Vj 2 -5 9 -13 0

    Ui

    17 - 16

    - 13 24

    - 0 13

    - - 20 - - 13

    18 10 - 14 - 0

    Vj 2 -5 9 -13 0

    Cost for occupied

    cells

    Cost for unoccupied cells

    Ui + Vj= Cij BFS COST TABLE

  • 8/11/2019 221084-89 dmm

    22/30

    MODI Method

    Net Evaluation

    Cij = Cij(Ui + Vj )

    p1 p2 p3 w1 W2

    S1 14 -

    S2 - -11

    Sd - -13

    W1 - - -2 - -

    W2 3 15 - 21 -

    As there are negative elements ( i.e. all Cij > 0condition is not satisfied) innet evaluation table, thus it is NOT AN OPTIMAL SOLUTION.

    Need to introduce at the most negative element position.

  • 8/11/2019 221084-89 dmm

    23/30

    P1 P2 P3 W1 W2

    S1 - - - - 1000

    S2 - - - 1500 -

    Sd - - - 500-

    W1 800 1200 - 1000 + -

    W2 - - 1000 - 2000

    Minimal possible value of =

    One basic cell will become zero.

    Introduction of Theta ()

    B i F ibl S l ti (BFS)

  • 8/11/2019 221084-89 dmm

    24/30

    Basic Feasible Solution (BFS)

    - 2P1 P2 P3 W1 W2

    S1 - - - - 1000

    S2 - - - 1500 -

    Sd - - - 500 -

    W1 800 1200 - 1000 + -

    W2 - - 1000 - 2000

    Here, Number of Basic Variables = 9

    Also M+N-1 = 9

    Hence, Its a Non-Degenerate Solution .

    BACK

  • 8/11/2019 221084-89 dmm

    25/30

    MODI Method

    Ui

    - - - - 16 16

    - - - 11 - 11

    - - - 0 0 0

    15 8 - 0 - 0

    - - 9 - 0 0

    Vj 15 8 9 0 0

    Ui

    17 - 16

    - 13 11

    - - 0

    - - 20 - 13 0

    18 10 - 14 - 0

    Vj 15 8 9 0 0

    Cost for occupied

    cells

    Cost for unoccupied cells

    Ui + Vj= Cij BFS COST TABLE

  • 8/11/2019 221084-89 dmm

    26/30

    MODI Method

    Net Evaluation

    Cij = Cij(Ui + Vj )

    p1 p2 p3 W1 W2

    S1 1 -

    S2 - 2

    Sd - -

    W1 - - 11 - 13

    W2 3 2 - 14 -

    As there is no negative costs ( i.e. all Cij > 0) in net evaluationtable,

    thus it is an OPTIMAL SOLUTION.

    T t l

  • 8/11/2019 221084-89 dmm

    27/30

    P1 P2 P3 W1 W2Total

    Supply

    S1 17 16 1000

    S2 11 13 1500

    Sd 0 0 500

    W1 15 8 20 0 13 3000

    W2 18 10 9 14 0 3000

    Total

    Demand

    800 1200 1000 3000 3000

    P1 P2 P3 W1 W2

    S1 - - - - 1000

    S2 - - - 1500 -

    Sd - - - 500 -

    W1 800 1200 -1000 +

    -

    W2 - - 1000 - 2000

    Cost Table

    Optimal Table

  • 8/11/2019 221084-89 dmm

    28/30

    Final Optimal Cost

    The optimal cost for transshipment fromsources to destinations through transient

    nodes is :

    Z* = 16*1000 + 11*1500 + 0*(500-) + 0* +

    15*800 + 8*1200 + 0*(1000 + ) +

    9*1000 + 0*2000

    = Rs. 63100 ( is considered as negligible)

  • 8/11/2019 221084-89 dmm

    29/30

    Diagrammatic Representation

    S1

    S2

    P1

    P2

    P3

    1500

    1000

    800

    1200

    1000

    W

    W 2

    Sd500

  • 8/11/2019 221084-89 dmm

    30/30

    THANK YOU