STATUS REPORT OF MY HOME ABHRA “Block-”a” AS ON 23.02.13

1.Sub Cellar Slab(-2) Completed.2.Columns work in progress for cellar slab.

Page 2: 23 02-2013

STATUS REPORT OF MY HOME ABHRA “Block-”B” AS ON 23.02.13

1.Sub Cellar Slab(-2) Completed.2.Cellar slab (-1) flat number 1 & 2 Completed.

3.Remain flat Shuttering work in progress.

Page 3: 23 02-2013

STATUS REPORT OF MY HOME ABHRA “Block-”C” AS ON 23.02.13

1.Sub Cellar Slab(-2) Completed.2.Columns work in progress for cellar slab.

Page 4: 23 02-2013

STATUS REPORT OF MY HOME ABHRA “Block-”D” AS ON 23.02.13

1.Sub Cellar Slab(-2) Completed.2.Cellar slab (-1) flat number 1& 2 shuttering and-

-bar bending work in progress3.Remain flats columns work in progress

Page 5: 23 02-2013

STATUS REPORT OF MY HOME ABHRA “Block-”E” AS ON 23.02.13

1.Sub Cellar Slab(-2) 40%-Completed2.Remain 60% Shuttering and bar bending work in progress.

Page 6: 23 02-2013

STATUS REPORT OF MY HOME ABHRA “Total -site” AS ON 23.02.13

1.All Block Grade Slab Completed2.All Blocks Sub Cellar(-2) slab 88%-Completed3.All Blocks Cellar slab(-1) only 8%-Completed