23376587-003-itp-ug-piping
TRANSCRIPT
PMC
LARSEN & TOUBRO LIMITEDMSQ UPGRADATION (EPCC-1) PROJECT IOCL - PANIPAT
INSPECTION AND TEST PLAN
FOR UNDER GROUND PIPING
Doc. No: LT/MSQ/ITP/PIPE/UG/003
Date: 01.11.07
PROJECT : EPCC-1 –MSQ UPGRADATIONOWNER : INDIAN OIL CORPORATION LTD.PANIPAT.PMC : JACOBS ENGINEERING INDIA PRIVATE LIMITEDCONTRACTOR : LARSEN & TOUBRO LIMITED
LEGEND : NA : Not Applicable, HP : Hold Point, W : Witness Point, Rw : Review of SUBCONTRACTOR / L&T's documentation, S : Surveillance by OWNER / PMC, WC : 100% Examination, Spec. : Specification, Dwg. : Drawing, Std. : Standard
PT : Penetarnt Testing, MT: Magnetic Particle Testing, PWHT: Post Weld Heat Treatment, IRN: Inspection Release Note
SL. No. DESCRIPTION OF ACTIVITY FIELD INSPECTION REPORT FORMAT No.
INSPECTION WITNESSES/GRADE REMARKS
L&T JACOBS
UNDER GROUND PIPING
A PRIOR TO FABRICATION
1 Incoming Material LT/MSQ/IMIR/GEN/001 Rev.01 WC W
2Welding Filler Material Approval / Qualification
APPROVED VENDER FORMAT WC HP
3 WPS / PQRLT/MSQ/STR/WPS/002LT/MSQ/STR/PQR/003
WC HP
4 Welder Performance Qualification LT/MSQ/STR/WPQ/004 WC HP
5 a) NDT Procedure Qualification NDT Report WC HP
b) PWHT Procedure Qualification (If any) SR CHART WC HP
6 Preparation of Sketches ISOMETRICS WC S
7 Joint Numbering APPROVED SKETCHES WC S
8 Material traceability& transfer of heat nos. LT/MSQ/PIPE/TRA/011 WC S
B FABRICATION ( SHOP & FIELD )
1Material as per piping class ( Check w.r.t. approved colour coding procedure )
LT/MSQ/PIPE/TRA/011 WC S
a) Fit Up checkLT/MSQ/STR/DNF/005LT/MSQ/STR/FNW/006
WC S
b) Dimensional checksLT/MSQ/STR/DNF/005
WC S
2 Pre heat NA WC S
3 Check for purity of purging / shielding gas BTC OF MANUFACTURER WC Rw / S
4 Purging (If any ) BTC OF MANUFACTURER WC S
5 Shielding rate ( If any ) BTC OF MANUFACTURER WC S
6 Baking of ElectrodesELECTRODE BACKING
REGISTERWC S
7 Interpass cleaning & temperature check NA WC S
SL. No.DESCRIPTION OF ACTIVITY FIELD INSPECTION REPORT
FORMAT No.INSPECTION
WITNESSES/GRADEREMARKS
Signature : Name :
Date
Prepared by L&T
Checked by L&T
Approved by JACOBS
Page 1 of 3
PMC
LARSEN & TOUBRO LIMITEDMSQ UPGRADATION (EPCC-1) PROJECT IOCL - PANIPAT
INSPECTION AND TEST PLAN
FOR UNDER GROUND PIPING
Doc. No: LT/MSQ/ITP/PIPE/UG/003
Date: 01.11.07
PROJECT : EPCC-1 –MSQ UPGRADATIONOWNER : INDIAN OIL CORPORATION LTD.PANIPAT.PMC : JACOBS ENGINEERING INDIA PRIVATE LIMITEDCONTRACTOR : LARSEN & TOUBRO LIMITED
LEGEND : NA : Not Applicable, HP : Hold Point, W : Witness Point, Rw : Review of SUBCONTRACTOR / L&T's documentation, S : Surveillance by OWNER / PMC, WC : 100% Examination, Spec. : Specification, Dwg. : Drawing, Std. : Standard
PT : Penetarnt Testing, MT: Magnetic Particle Testing, PWHT: Post Weld Heat Treatment, IRN: Inspection Release Note
L&T JACOBS
8 Visual cleaning of purging / shielding gas NA WC S
9 Monitoring of PWHT Cycle SR CHART WC S
10 Hardness CheckB.T.C. OF
MANUFACTURER/TEST REPORT OF LAB.
WC S
11 DPT / MPT LT/MSQ/DPT/016LT/MSQ/MPT/017
WC S
12Radiography marking ( For Random Radiography )
LT/MSQ/PIPE/RGM/013 WC W
13 Radiography interpretation LT/MSQ/PIPE/RGI/014 WC HP
C PROOF TESTING
1 Procedure APPROVED PROCEDURE WC HP
2 Corrections of Testing arrangements LT/MSQ/PIPE/HYD/015 WC S
3 Calibration of Pressure Gauge WC Rw
4 R.F. Pad testing, if any LT/MSQ/RFPT/018 WC W
5Positive material Identification as per Specification after completion
LT/MSQ/PMI/STORE/019LT/MSQ/PMI/SITE/019A
WC HP
6Scrutiny of test packs for mechanical & NDT Clearance ( As per Annexure – A )
LT/MSQ/UGMC/SP/023 WC HP
7 Air / Water Flushing ( Preliminary ) LT/MSQ/UGMC/SP/023 WC W
8 Pneumatic / Hydro testing LT/MSQ/PIPE/HYD/015 WC HP
9 Draining of Water & Air drying LT/MSQ/UGMC/SP/023 WC S
D LAYING
1 Trench excavation and levels LT/MSQ/UGPC/021 WC S
2 Cleaning of pipe surface LT/MSQ/TC/020 WC S
3Approval of wrapping / coating material manufactures
APPROVAL LETTER/BTC OF MATERIAL
WC HP
4 Approval of agency for wrapping & coatingAPPROVAL LETTER/BTC OF
MATERIALWC HP
5Sample test of coating materials in approved laboratory
TEST REPORT OF LAB WC Rw
6Procedure qualification for wrapping & coating
APPROVED VENDER FORMAT WC HP
SL. No.DESCRIPTION OF ACTIVITY FIELD INSPECTION REPORT
FORMAT No.INSPECTION
SWITNESSES/GRADEREMARKS
Signature : Name :
Date
Prepared by L&T
Checked by L&T
Approved by JACOBS
Page 2 of 3
PMC
LARSEN & TOUBRO LIMITEDMSQ UPGRADATION (EPCC-1) PROJECT IOCL - PANIPAT
INSPECTION AND TEST PLAN
FOR UNDER GROUND PIPING
Doc. No: LT/MSQ/ITP/PIPE/UG/003
Date: 01.11.07
PROJECT : EPCC-1 –MSQ UPGRADATIONOWNER : INDIAN OIL CORPORATION LTD.PANIPAT.PMC : JACOBS ENGINEERING INDIA PRIVATE LIMITEDCONTRACTOR : LARSEN & TOUBRO LIMITED
LEGEND : NA : Not Applicable, HP : Hold Point, W : Witness Point, Rw : Review of SUBCONTRACTOR / L&T's documentation, S : Surveillance by OWNER / PMC, WC : 100% Examination, Spec. : Specification, Dwg. : Drawing, Std. : Standard
PT : Penetarnt Testing, MT: Magnetic Particle Testing, PWHT: Post Weld Heat Treatment, IRN: Inspection Release Note
L&T JACOBS
7 Application of primer LT/MSQ/TC/020 WC S
8 Coal tar temperature NA WC S
9 Coating and wrapping LT/MSQ/TC/020 WC S
10 Calibration of Holiday tester TEST REPORT OF LAB WC HP
11 Holiday testing LT/MSQ/TC/020 WC HP
12 Thickness of coating LT/MSQ/TC/020 WC HP
13 Peel test LT/MSQ/TC/020 WC HP
14 Lifting arrangement NA WC S
15 Lowering ( Levels & orientation of branches ) LT/MSQ/UGPC/021 WC S
16Checking of wrapping and coating for damages during lowering, their repair, holiday testing, etc.
LT/MSQ/TC/020LT/MSQ/UGPC/021
WC HP
17 Back filling LT/MSQ/UGPC/021 WC S
18 Location, Brickwork Plaster of valve pit WC S
19 Top cover & finish for valve pit WC S
E SYSTEM COMPLETION
1 Tie in joints ( As Annexure – B ) ( As Annexure – B ) WC W
2Scrutiny of test packs for system testing ( As per Annexure – C )
LT/MSQ/UGMC/022 WC W
3 System testing LT/MSQ/PIPE/HYD/015 WC W
SL. No.DESCRIPTION OF ACTIVITY FIELD INSPECTION REPORT
FORMAT No.INSPECTION
WITNESSES/GRADEREMARKS
Signature : Name :
Date
Prepared by L&T
Checked by L&T
Approved by JACOBS
Page 3 of 3
PMC
LARSEN & TOUBRO LIMITEDMSQ UPGRADATION (EPCC-1) PROJECT IOCL - PANIPAT
INSPECTION AND TEST PLAN
FOR UNDER GROUND PIPING
Doc. No: LT/MSQ/ITP/PIPE/UG/003
Date: 01.11.07
PROJECT : EPCC-1 –MSQ UPGRADATIONOWNER : INDIAN OIL CORPORATION LTD.PANIPAT.PMC : JACOBS ENGINEERING INDIA PRIVATE LIMITEDCONTRACTOR : LARSEN & TOUBRO LIMITED
LEGEND : NA : Not Applicable, HP : Hold Point, W : Witness Point, Rw : Review of SUBCONTRACTOR / L&T's documentation, S : Surveillance by OWNER / PMC, WC : 100% Examination, Spec. : Specification, Dwg. : Drawing, Std. : Standard
PT : Penetarnt Testing, MT: Magnetic Particle Testing, PWHT: Post Weld Heat Treatment, IRN: Inspection Release Note
L&T L&T
Signature : Name :
Date
Prepared by L&T
Checked by L&T
Approved by JACOBS
Page 4 of 3