24” FORCE MAIN BYHDD FOR DALLASWATER UTILITIES
Presented By:James Bryan, P.E.Trag Bailey
![Page 2: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/2.jpg)
Agenda
•Project Overview•Why HDD?•Traffic Control•Construction Footprint•HDD Layout•Construction Photos•Summary
![Page 3: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/3.jpg)
Project Overview
•Location•Scope
• 9 MGD Lift Station• 15,000 LF 24” HDPE
Force Main• 5,000 LF by HDD
•Total Project Cost• $5.5 Million
![Page 4: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/4.jpg)
Project Overview
![Page 5: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/5.jpg)
Why HDD?
•Belt Line Road Corridor•Adjacent Development•Railroad•Traffic•School•Existing Utilities•Visibility
![Page 6: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/6.jpg)
Traffic Control
•Belt Line Road Section• 4-lane Divided• 6-lane Divided
•Maintain minimum two lanes each direction•Rolling lane closures•Phased traffic control plans•Strung pipe out in sections to keep mediansopen
•CTB protection for drill rig overnight; cones forremaining traffic control
![Page 7: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/7.jpg)
Construction Footprint
•Water Tanker Truck•Mud Recycling Trailer•Job/Tool Trailer•Drilling Rig•Excavator•Flatbed Truck•Work Trucks
![Page 8: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/8.jpg)
Project Overview
BELT LINE ROADDART RAILROAD FA
IRW
AYD
R.
TRA CONNECTION
HDD #1
HDD #2
HDD #3
HDD #4
NORTH
BARBARA BUSHMIDDLE SCHOOL
![Page 9: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/9.jpg)
Project Overview
BELT LINE ROAD
DART RAILROAD
HDD #1
HDD #2
ENTRYEXIT
1140 FEET
NORTH
![Page 10: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/10.jpg)
Project Overview
NORTH
BELT LINE ROAD
DART RAILROAD
HDD #2
HDD #3
ENTRY EXIT
890 FEET
HDD #1
![Page 11: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/11.jpg)
Project Overview
NORTH
BELT LINE ROAD
DART RAILROAD
HDD #3ENTRY EXIT
1150 FEET
HDD #2 HDD #4
![Page 12: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/12.jpg)
Project Overview
NORTH
BELT LINE ROAD
DART RAILROAD
HDD #4
ENTRY
EXIT
1060 FEET
FAIR
WAY
DRI
VE
HDD #3
![Page 13: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/13.jpg)
Project Overview
![Page 14: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/14.jpg)
Construction Footprint
•Water Tanker Truck•Mud Recycling Trailer•Job/Tool Trailer•Drilling Rig•Excavator•Flatbed Truck
![Page 15: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/15.jpg)
Photos
![Page 16: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/16.jpg)
Photos
![Page 17: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/17.jpg)
Photos
![Page 18: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/18.jpg)
Photos
![Page 19: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/19.jpg)
Photos
![Page 20: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/20.jpg)
Photos
![Page 21: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/21.jpg)
Photos
![Page 22: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/22.jpg)
Photos
![Page 23: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/23.jpg)
Photos
![Page 24: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/24.jpg)
Summary
•Schedule• 1 month per drill• 4 months total in Belt Line Road corridor
•Coordination success•Minimal disruption and no complaints!•Lessons Learned
• Depth variation/ideal radius• Utility clearance• Drill rig anchoring
![Page 25: 24” FORCE MAIN BY HDD FOR DALLAS WATER UTILITIES•Mud Recycling Trailer •Job/Tool Trailer •Drilling Rig •Excavator •Flatbed Truck •Work Trucks Project Overview BELT LINE](https://reader036.vdocuments.net/reader036/viewer/2022071114/5feb6945d846c27e101a64c0/html5/thumbnails/25.jpg)
Thank You! Any Questions?
James Bryan, P.E.Kimley-Horn and Associates, [email protected](972) 776-1752
Trag BaileyChisholm [email protected](214) 244-2722