25-1MAVEN IPSR October 30,31, 2012
Particles and Fields PackagePre-Ship Review
October 30,31, 201225: SMA
Jorg Fischer, MAM
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
25-2MAVEN IPSR October 30,31, 2012
PSR SMA - Summary
• EIDP (including GSFC, IRAP, LASP) flight travel books have been reviewed, all open items are identified by SSL and GSFC and are tracked – cont.
• Hardware and Software are in good shape• Configuration Control is in place and working• No parts or materials issues• No major issues during built-up – Exception: SWEA• No major non-compliance exists – Exception: SWEA• PFR’s: Jorg Fischer• Testing and Verification: David Curtis• Software code Status & GSE: Peter Harvey• SSL Safety: Jorg Fischer, Safety: LM
25-3MAVEN IPSR October 30,31, 2012
SMA SUMMARY
• Workmanship- SMA supported PMB, PWA fabrication, assembly modifications, tuning
efforts, repair/rework, box integration, and training (training at JPL, RMV, and informal in-house)
• Configuration Management- FHW – Checked FLT Binder documentation and PFR status to confirm
readiness, before start of testing- FSW – ongoing support of informal and formal reviews, walk-throughs, and monthly reports - Documentation Control – Performed FLT document reviews, and updates
• Work Order Management- Travelers – Reviews performed by SSL QA and GSFC QA- Procedures – Performed procedure reviews- Inspections – Ongoing - Performed by SSL QA and GSFC QA.
25-4MAVEN IPSR October 30,31, 2012
SMA SUMMARY
• Metrology & Calibration- Performed the monthly checks (Tools and Certifications) – no issues.
Scanned 100% of all certifications for EIDP delivery.
• Training- Performed certifications review – no issues- Cleanroom, PP, ESD, and Documentation training – no issues - Held SSL Safety Training Meetings - LM Training for SSL team members to meet LM in-house requirements
might be necessary. Contact with C. Love - in progress.- LL: Suspect counterfeit awareness training is planned for SMA and
purchasing personnel - NA-HQ-2012-00
• PFR-NCR SPR-SCR System- PFR-NCR database revised and updated, documentation - in progress - SPR-SCR list revised and updated, documentation - in progress
5
SMA SUMMARY
• Quality - Inspections of all FLT unit assemblies, PWA, boxes, and harnesses
– ongoing. All issues are documented in PFR System. - Testing - Provided support for offsite testing, such as, EMC,
Vibration testing setup and testing. Supported In-house testing, such as, TVAC set-up and testing of the instruments
- Supported of LASP EUV efforts at SSL- Continuous inspections of Flight assembly, cleanroom, and test
areas by SSL and GSFC QA- Supported PW board modifications/tuning and rework/repair- Supported integration and de-integration activities of the Instrument
Stacks (PFDPU, SWEA, SWIA, SEP, LPW, STATIC)
6
SMA SUMMARY
• ESD Control - Implementation, equipment, maintenance, measurement, and
training are addressed in the SSL ESD Control Plan (Rev. B)- Supported the annual independent ESD Control verification and
performed the monthly survey – no issues- SSL MAVEN team ESD training was performed, as required
• Material Processes and Parts Control- Updated EEE parts, Flight fastener, and Materials databases - As-built BOM documentation. ABPL for all instruments are complete- Alert response reports (GIDEP) – Provided disposition and updated
the alert response database – no issues (ref. GIDEP slide)- Polymerics – Updated mix record database. Performed polymeric
witness sample testing, filing, inspections, and documentation.
7
SMA SUMMARY
•Facilities / Equipment-Continuous inspections of Flight assembly, vendor and in-house test areas by SSL and GSFC QA-Provided cleanroom support - cleaning of parts, continuous supplies, and maintenance, for all MAVEN cleanrooms-Industrial Safety: Provided support of chemical, hazardous waste inventory and UCB EH&S interaction
•Delivery Readiness -End Item Data Acceptance Package – ongoing-Reviewed LM AIRR list – ongoing-Support of shipping effort
25-8MAVEN IPSR October 30,31, 2012
PFR, ECN, Waiver, MUA Overview
• Anomalies/PFR/NCR 37 NCRs and 82 PFRs issued – STATUS next slides
• ECN/ECO 18 ECN/ECO issued, All closed
• WAIVERS, CCR 42 Waivers issued. Closure of all to be confirmed
• MUA 5 MUAs issued, Closure of all to be confirmed
9
SMA - MRB
• MRB System- PFR status report list sent to GSFC – weekly- PFR-NCR System will serve as a Lessons Learned System- Provided assistance to SSL engineers with PFR documentation and
related item close-out
PFR MRB Status (10/25/12):
SSL Problem count 124
MRB problems: 82 NCR problems: 37VOID : 5
Open problems in Review at SSL: 6 Problems in Review at GSFC: 8
SSL Total Closed count : 110Void: 5, Monitor: 3
GSFC Total CLOSED count: 101Open: 7, VOID: 5, Monitor: 3
Monitor: 3 (SWEA PFR 059 and 122; PFR 115: SWIA Vibration Frequency Shift – expected to close after vibe test
25-10MAVEN IPSR October 30,31, 2012
SMA - MRB
Anomalies/PFR/NCR – STATUS of six (6) open PFRs•PFR 105, EUV Temp Sensor Noise is open – LASP EUV - Waiting for thermal test•PFR 108, Operational and Actuator CE03 exceedances - PFDPU - Waiting for Waiver to close•PFR 109, MAG Heater CE03 exceedance - PFDPU - Waiting for test data with the filters •PFR 111, MAG Sensor CS101 MAG susceptibility - PFDPU MAG Sensor FM1,2 - Waiting for test data with the filters •PFR 119, STATIC TOF Field Emission Noise - SSL is working to close• PFR 124, LASP LPW Cold Anomaly – LASP EUV - Ready to close - FRB
25-11MAVEN IPSR October 30,31, 2012
PFR ECN Tracking
• PFRs, ECNs
25-12MAVEN IPSR October 30,31, 2012
Configuration Control
Instrument and Box Level1.Master sheet•Assembly•Subsystem Components•Cognizant Engineers•Serial Numbers and Designators: F1, F2, Spare.•Rev Level AS-BUILT•Schematics, AS-BUILT•BOMs, AS-BUILT•Assembly Instructions
2.Master Binder for•ECN, PFR, Waiver, MUA (all available electronically)
25-13MAVEN IPSR October 30,31, 2012
SMA – SPR-SCR System
25-14MAVEN IPSR October 30,31, 2012
Data Bases – Parts, Materials
• Approved no issues
25-15MAVEN IPSR October 30,31, 2012
Data Bases – Alerts and GIDEP
• Approved no issues
25-16MAVEN IPSR October 30,31, 2012
GIDEP Alerts & Problem Advisories
• As of 10/28/12, SSL SMA checked a quantity of 463 alerts• As of 10/28/12, SSL SMA closed a quantity of 463 alerts• Four (4) impact alerts were mitigated and closed1. Alert “051910 email from Oscar” Added a note to board drawings
that “The use of brominated polyimide is unacceptable.” SMA produced PWA specification for MAVEN – SOW2. KE1-P-11-02, SOTA, solderable thin film MIL-PRF-55342 resistors
were produced with defective end terminations. A) Date Codes not used. B) Additional inspections were implemented
3. RS2-P-11-0, Microsemi, diode re-classified as ESD Class 0 – installed ESD class 0 workbench, device installed at JPL.
4. NA-HQ-2012-001, Checked approx. 400 vendors, - no impact, used MFG authorized vendors only and received certs.
25-17MAVEN IPSR October 30,31, 2012
FLT Travel Books
• FLT Travel Books
25-18MAVEN IPSR October 30,31, 2012
SMA – Concerns & Observations
• Concerns – All concerns are well understood and are closely monitored by the SSL and GSFC QA teams.
• Pending – Expect two red flag PFRs (SWEA PFR 059 and PFR 122) – LM monitoring for both.
Communications and working relationship of the experienced MAVEN PFP teams are excellent.