    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    1 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

    INSTALLATION GUIDELINES

    1. Space around DG SetThere shall be at least one meter free spare around BLISS DG Set to facilitate DG set door opening and

    maintenance.

    2. Installation SurfaceThe installation surface must be flat, even, firm and without undulations.

    3. Requirement of PlatformConcrete platforms should be foreseen to prevent water entry in situations of flooding.

    4. Cross ventilationIf installed in an enclosed space, the room should have cross ventilation allowing fresh air to enter from

    alternator side of the canopy and hot air to move out of the room on the opposite side.

    5. DG Set orientationIf installed in an enclosed space, the Radiator of the BLISS DG Set should face an opening in the wall for

    hot air to escape.

    6. Hot Air evacuationSilencer and associated pipes radiates heat. Hence the room must have provision to evacuate hot air

    accumulated at the top by ventilator or exhaust fan.

    7. Multiple Set OrientationsMultiple DG sets should be installed one beside the other and not one facing the other or one behind

    the other.

    8. EarthingRegulations vary from place to place. Hence advice should be sought from the local supply utility about

    requirements. The frame of the alternator, engine and control panel are all connected. Hence earthing

    the frame of the BLISS DG set ensures earthing the body of all the components. The neutral of thealternator has to be earthed separately. The provision for the same is also made in BLISS DG set.

    Grounding should be done in accordance with applicable National, Local code/Regulation.

    Regulations normally require 4 earth pits, one pair for alternator neutral and the other pair for DG set

    body. The earth pits should be separated by not less than 1 meter.

    9. Roof top installationsExperts in the respective field like Structural Engineers must be consulted for roof top installations.

    10. Exhaust Connections

    The exhaust system is used to direct exhaust gases to non-confined areas and reduce the noise totolerable levels. When designing a system, the main objective is to minimise back pressure. Excessive

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    2/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    2 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

    back pressure in an exhaust system will create horsepower loss and increase the engine operating

    temperature and emissions. When bends are required in exhaust system, always make the radius at least

    150% of the inside diameter of the pipe. As most exhaust system designs are governed by the physical

    characteristics of the building or room in which they are located, it is of utmost importance that the

    exhaust pipe be routed in a path offering the least amount of turns or bends so as not to increase back

    pressure more than 50mm of Hg. Bevel the end of the pipe at a 30-45 degree angle. Should the pipe end

    be horizontal, bevel the pipe from the top back to the bottom. This will not only reduce the noise levels

    at the outlet but will also minimise entrance of precipitation on horizontal pipes.

    By locating the silencer as close to the engine as possible you will be able to minimise the noise level in

    the exhaust piping.

    Each DG Set installation should have its own exhaust system and should not be connected to a system

    accommodating more than one DG Set as the possibility of exhaust gas and condensation backflow may

    cause permanent damage to an idle engine.

    11. Balancing the loadsWhile connecting the loads on BLISS DG set, care should be taken to distribute the single phase loads

    equally on all the three phases.

    12. Power FactorAs per standard, BLISS DG set is capable of providing power at 0.8 power factor (lag).Hence the

    maximum kW BLISS DG Set can supply is obtained by multiplying kVA by pf (Which is 0.8).Power factor

    lower than 0.8 (lag) will stress the alternator, while pf more than 0.8(lag) will stress the engine. Hence it

    is advisable to check KW and kVA loading separately. Leading power factor loads, as presented by power

    factor improvement capacitors will cause voltage instability and hence should be avoided on BLISS DG

    Set.

    UP KEEP1. As a daily routine, clean the BLISS DG Set with dry cloth.

    2. Keep the door of the DG Set closed.

    3. Dont fill the fuel without strainer.

    4. Maintain log book for BLISS DG set.

    WATCH KEEP1. Verify battery charge, lube oil level, coolant level & fuel level in the daily

    routine checks.

    2. Regularly check all the connections of air, oil, coolant, fuel and exhaust for

    leaks. Report if

    abnormal.

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    3/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    3 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

    3. Observe loosening of parts, nuts & bolts. Report if abnormal.

    4. Observe for unusual sound of set. Report if abnormal.

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    4/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    4 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    5/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    5 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    6/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    6 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    7/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    7 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

    DOS & DONTSDos.....

    1. Ensure that keys for the locks are in proper custody.

    2. Use proper & appropriate place for storage of BLISS DG set, Spares and

    associated items.

    3. Understand information provided in DG operation & maintenance literature

    and as conveyed during training & follow them.

    4. Ensure minimum 1 meter clear distance between BLISS DG set & all

    surrounding structures. Remove obstacles if any for easy access to DG set.

    5. Ensure free flow of fresh air to inlet provided on DG set and hot air fromradiator to move out to atmosphere without restriction / reflection.

    6. As a daily routine, clean the DG set with dry cloth.

    7. Include verification of battery charge, lube oil level, fuel level & water level

    in the daily routine checks.

    8. Regularly check all connections of Air, Oil, Water, Exhaust & Diesel for leaks.

    9. Release start push bottom when speed picks up to prevent damage to self-

    starter.

    10. Allow sufficient gap between successive starts to prevent draining of

    battery.

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    8/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    8 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

    11. While operation in manual mode, run for a while on No-load before

    loading. Disconnect the load first & run for a while on No-load before stopping

    the DG Set.

    12. Be alert for any unusual sound of DG Set and report without delay.

    13. Maintain DG Run log book, Fuel log book & Visit Register.

    14. Ensure maintenance checks are carried out in specified time as suggested in

    BLISS user Manual.

    Don'ts.....

    1. Don't allow DG set to run in inclined position.

    2. Don't allow unauthorized person/s to meddle with DG sets.

    3. Don't commission the DG set in the absence of authorised Kirloskar Electric

    service person/s.

    4. Don't fill the fuel without strainer.

    5. Don't allow operation of the DG set without proper Earthing.

    6. Don't fill the fuel when set is running.

    7. Don't bring the naked flame near the battery when it is being charged.

    8. Don't press start button when the set is running.

    9. Don't disconnect the battery when the set is running.

    10. Don't operate the DG with Engine Oil below min mark on the Oil dip stick.

    11. Don't start the DG set when there is any fault indication.

    12. Don't run the DG set without Maintenance checks as in user manual.

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    9/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    9 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

    13. Don't stop the set on LOAD.

    14. Don't open the Radiator cap when the set is running / hot condition.

    15. Do not over load the set.

    INSTALLATION CHECK LIST1. LOCATION RELEATED

    1.1 Is the set at sufficient height to prevent water entry in rainy season? Yes / No

    1.2 Is space surrounding the DG set sufficient to allow maintenance work? Yes / No

    1.3 Is the space around is levelled without pits, slopes and other physical

    Obstruction (as otherwise it is a safety hazard to persons attending) Yes / No

    1.4 Whether the DG room has adequate cross ventilation Yes / No

    1.5 Whether hot air from radiator moves out without obstruction. Yes / No

    1.6 Is care taken that the rain water falling from the adjoining building do not fall

    on the DG set? Yes / No1.7 Is exhaust directed away from likely human injury or damage to other

    equipment or air inlet for acoustic? Yes / No

    2. FOUNDATION AND PLATFORM RELATED

    2.1 Is the foundation levelled properly so that there are no gaps between

    base frame and platform surface of the foundation? Yes / No

    2.2 Is the area of the platform adequate to provide seating for the entire set? Yes / No

    3. PRODUCT INTACTNESS RELATED

    3.1 Is the base frame intact without damage and waviness at the bottom? Yes / No

    3.2 Is the enclosure dented or damaged during handing leading to rusting? Yes / No

    3.3 Is the door alignment OK? Yes / No

    3.4 Is the lock for enclosure functioning properly? Yes / No

    3.5 Whether bolts holding engine, alternator, control panel, silencer exhaust fan,

    fuel tank and bolts of acoustic enclosure tight? Yes / No

    3.6 Whether control panel components mounting tight and not loose? Yes / No

  • 8/13/2019 273034installation Guidelines for Kirloskar Bliss Dg Sets

    10/10

    June 12, 2011 INSTALLATION GUIDELINES FOR KIRLOSKAR BLISS GENSETS[ ]

    10 www.kineticdiesel.com | KINETIC DIESEL ENGINEERING

    3.7 Whether battery has any physical damage? Yes / No

    3.8 Whether any wire hanging loose or connection loose? Yes / No

    3.9 Whether all fuel connections and drain plug are tight? Yes / No

    3.10 Whether AVMs are positioned & not displaced? Yes / No

    4. EARTHING & CABLING

    4.1 Whether enclosure earthed? Yes / No

    4.2 Whether neutral earthed? Yes / No

    4.3 Whether Alternator body earthed? Yes / No

    4.4 Is cable of mains and load exerting pressure on terminals? Yes / No

    4.5 Whether connection to mains, load and alternator are with proper phase

    sequence? Yes / No

    5. LEAKAGE RELATED

    5.1 Is the lube oil level at the acceptable level? Yes / No

    5.2 Is the coolant level in the Radiator at the acceptable level? Yes / No

    5.3 Whether diesel is available at the required level in the fuel tank? Yes / No

    5.4 Whether any leakage of fuel, lube oil and coolant observed at drain plug, banjo point

    crimping or in the pipes or at the neck of the tank or in tank joints? Yes / No

    Signature and Seal of End User Signature and Seal of Installation Agency

    KINETIC DIESEL ENGINEERING

    853/1671, Cuttack - Puri Road,Opposite to Reliance Fresh,

    Bhubaneswar - 751006,ORISSA

    Ph: 91 674-2572838,91 674-2572839Mob: 91-9437036929, 91-9437002318, 91-9938398899

    Fax: 0674 - 2572839

    [email protected]

    www. Kineticdiesel.com

    Authorized Sales & Service Dealers For:KIRLOSKAR ELECTRIC CO. LTD,

    NO. T-4(A), 1stMAIN, 2

    ndCROSS,

    1stSTAGE,

    PEENYA INDUSTRIAL AREA,

    BANGALORE-560058

    PH-080-40902637