2.810t.gutowski1 2.810 quality and variation part tolerance process variation taguchi “quality...
TRANSCRIPT
2.810 T.Gutowski 1
2.810 Quality and Variation
Part ToleranceProcess VariationTaguchi “Quality Loss Function” Random Variables and how variation grows with size and complexityQuality Control
2.810 T.Gutowski 2
References;
Kalpakjian pp 982-991 (Control Charts)
“Robust Quality” by Genichi Taguchi and Don Clausing
A Brief Intro to Designed Experiments
Taken from Quality Engineering using Robust Design by Madhav S. Phadke, Prentice Hall, 1989
5 homeworks due Nov 13
2.810 T.Gutowski 3
Interchangeable Parts;Go, No-Go; Part Tolerance
2.810 T.Gutowski 4
Product specifications are given as upper and lower limits, for example the dimensional tolerance +0.005 in.
Upper Specification Limit
Lower Specification Limit
Target
2.810 T.Gutowski 5
Process VariationProcess measurement reveals a distribution in output values.
0
5
10
15
20
25
30
35
1 2 3 4 5 6 7 8 9 10 11 12 13
Discrete probability distribution based upon measurements
Continuous “Normal” distribution
In general if the randomness is due to many different factors, the distribution will tend toward a “normal” distribution. (Central Limit Theorem)
2.810 T.Gutowski 6
Tolerance is the specification given on the part drawing, and variation is the variability in the manufacturing process. This figure confuses the two by showing the process capabilities in terms of tolerance. Never the less, we can see that the general variability (expressed as tolerance over part dimension) one gets from conventional manufacturing processes is on the order of
to210000,1
10
410100
01.
Homework problem; can you come up with examples of products that have requirements that exceed these capabilities? If so then what?
2.810 T.Gutowski 7
We can be much more specific about process capability by measuring the process variability and comparing it directly to the required tolerance. Common measures are called Process Capability Indices (PCI’s), such as,
6
LSLUSLC p
3
),min( LSLUSLC pk
2.810 T.Gutowski 8
Case 1 In this case the out of specification parts are 4.2% + 0.4% = 4.6% What are the PCI’s?
Upper Specification Limit
Lower Specification Limit
Target
2.810 T.Gutowski 9
Case 2 However, in general the mean and the target do not have to line up. What are the PCI’s? How many parts are out of spec?
Upper Specification Limit
Lower Specification Limit
Target
2.810 T.Gutowski 10
Comparison
Case 1Cp = = 2/3
Cpk =
Min()=2/3
Out of Spec = 4.6%
Case 2Cp = = 2/3
Cpk =
Min()=1/3
Out of Spec = 16.1%
Note; the out of Spec percentages are off slightly due to round off errors
2.810 T.Gutowski 11
Why the two different distributions at Sony?
20% Likelihood set will be returned
2.810 T.Gutowski 12
Qu
alit
y
Loss
Deviation,
2
!2
)0()0()0()( f
ffQL
Goal Post Quality
Taguchi Quality Loss Function
QL = k 2
2.810 T.Gutowski 13
Homework Problem
Estimate a reasonable factory tolerance if the Quality Loss ($) for a failure in the field is 100 times the cost of fixing a failure in the factory. Say the observed field tolerance level that leads to failure is field.
2.810 T.Gutowski 14
Random variables and how variation grows with size and complexity
Random variable basics
Tolerance stack up
Product complexity
Mfg System complexity
2.810 T.Gutowski 15
If the dimension “X” is a random variable, the mean is given by = E(X) (1)
and the variation is given by
Var(x) = E[(x - )2] (2)
both of these can be obtained from the probability density function p(x).
For a discrete pdf, the expectation operation is:
(3)
E(X) xii p(xi)
2.810 T.Gutowski 16
Properties of the Expectation
1. If Y = aX + b; a, b are constants,
E(Y) = aE(X) + b (4)
2. If X1,…Xn are random variables,
E(X1 + … + Xn) = E(X1) +…+ E(Xn) (5)
2.810 T.Gutowski 17
Properties of the Variance
1. For a and b constants
Var(aX + b) = a2Var(X) (6)
2. If X1,…..Xn are independent random variables
Var(X1+…+ Xn) = Var(X1)+ Var(X2)+ + Var(Xn) (7)
2.810 T.Gutowski 18
If X1 and X2 are random variables and not necessarily independent, then
Var(X1 + X2) = Var(X1) + Var(X2) + 2Cov(X1Y) (8)
this can be written using the standard deviation “”, and the correlation “” as
(9)
where L = X1 + X2
L2 1
2 22 21 2
2.810 T.Gutowski 19
If X1 and X2 are correlated ( = 1), then
(14)
for X1 = X2 = X0
(15)
for N (16)
or (17)
L2 1
2 22 21 2 (1 2 )2
L2 N 2 0
2
0 NL
20
2 4 L
2.810 T.Gutowski 20
Now, if X1 and X2 are uncorrelated ( = 0) we get the result as in eq’n (7) or,
(10)
and for N (11)
If X1=X =Xo (12)
Or (13)
L2 1
2 22
2
1
2i
N
iL
L2 N 0
2
L N 0
2.810 T.Gutowski 21
Complexity and Variation
As the number of variables grow so does the variation in the system;
This leads to; more complicated systems may be more likely to fail
L N 0
0 NL
2.810 T.Gutowski 22
Homework; Consider the final dimension and variation of a stack of n blocks.
1, 2 …… nIf USL – LSL = ’, and Cp = 1a) How many parts are out of compliance?
b) Now USL-LSL=’, what is Cp? How many parts are out of spec?
c) Repeat a) with ’
Assume that target.
2.810 T.Gutowski 23
Homework Problem: Experience shows that when composites are cured by autoclave processing on one sided tools the variation in thickness is about 7%. After careful measurements of the prepreg thickness it is determined that their variation is about 7%. What can you tell about the source of variation?
2.810 T.Gutowski 24
Complexity and Reliabilityref. Augustine’s Laws
2.810 T.Gutowski 25
Quality and System DesignData from D. Cochran
2.810 T.Gutowski 26
Quality Control
Inputs “I”; Mat’l, Energy, Info
Operator inputs,”u”; initial settings, feedback, action?
Disturbances, “d”; temperature, humidity, vibrations, dust, sunlight
Outputs, “X”
Machine “M”
2.810 T.Gutowski 27
Who controls what?
X = f (M, I, u, d)
Equipment Purchase
Q.C., Utilities, etc
Operator, Real Time Control
Physical Plant, etc
So who is in charge of quality?
2.810 T.Gutowski 28
How do you know there is a quality problem?
1. Detection2. Measurement3. Source Identification4. Action5. Goal should be prevention
2.810 T.Gutowski 29
Detection
Make problems obvious Poke yoke at the process level Clear flow paths and responsibility Andon board Simplify the system
Stop operations to attend to quality problems Stop line Direct attention to problem Involve Team
2.810 T.Gutowski 30
Measurement
Statistical Process Control
Avera
ge v
alu
e x
Sampling period
Upper Control Limit
Lower Control Limit
Centerline
2.810 T.Gutowski 31
Statistical Process Control Issues
Sampling Period
Establish Limits
Sensitivity to Change
2.810 T.Gutowski 32
Source Identification; Ishikawa Cause and Effect Diagram
Man Machine
Material Method
Effect
Finding the cause of a disturbance is the most difficult part of quality control. There are only aids to help you with this problem solving exercise like the Ishikawa Diagrams which helps you cover all categories, and the “5 Whys” which helps you go to the root cause.
2.810 T.Gutowski 33
Truck front suspension assembly
Problem; warranty rates excessive
2.810 T.Gutowski 34
Setting the best initial parameters
Tables and Handbooks E.g. Feeds and speeds
Models E.g. Moldflow for injection molding
Designed Experiments E.g. Orthogonal Arrays
2.810 T.Gutowski 35
Designed Experiments
1. Temp “T” (3 settings)2. Pressure “P” (3 settings)3. Time “t” (3 values)4. Cleaning Methods “K” (3 types)How Many Experiments?One at a time gives 34 = 81
2.810 T.Gutowski 36
But what if we varied all of the factors at once?
Our strategy would be to measure one of the factors, say temperature, while “randomizing” the other factors. For example measure T2 with all combinations of the other factors e.g. (P,t,K) = (123), (231), (312).
Notice that all levels are obtained for each factor.
2.810 T.Gutowski 37
“Orthogonal Array” for 4 factors at 3 levels. Only 9 experiments are needed
Exp temp pressure
time clean
1 1 1 1 1
2 1 2 2 2
3 1 3 3 3
4 2 1 2 3
5 2 2 3 1
6 2 3 1 2
7 3 1 3 2
8 3 2 1 3
9 3 3 2 1
2.810 T.Gutowski 38
Homework
Can you design an orthogonal array for 3 factors at 2 levels?
2.810 T.Gutowski 39
Summary – the best ways to reduce variation
Simplify design
Simplify the manufacturing system
Plan on variation and put in place a
system to address it
2.810 T.Gutowski 40
Aircraft engine case study
LPC
HPC
Fan case
HPT
LPT
exhaustcase
diffuser
gearbox
2.810 T.Gutowski 41
Engine Data
engine A1
engine A2
engine B1
engine B2
engine C1
engine C2
number ofpart numbers
~2,000 ~2,000 ~1,400
~1,300
4,465 3,485
total numberof parts
~15,000
~19,000
~7,000
~7,000
26,073 23,580
weight [lb] 2.3k-3.5k
9k-10k 1.5k-1.6k
1.5k-1.6k
2.3k-3.5k
1.5k-1.6k
thrust [lb] unlessotherwise noted
14k-21k
40k-50k
4k-5k hp
7k-9k 14k-21k
7k-9k
by-pass ratio 0.36:1 4.9:1 - 5.15:1 0.34:1 6.2:1
engine A1
engine A2
engine B1
engine B2
engine C1
engine C2
annualproduction
150 150 110 150 150 286
planned through-put time [days]
15 20 8 10 23 21
approx. takt time [shifts/engine]
7.30 7.30 6.64 4.87 4.87 2.55
Engine “complexity”
2.810 T.Gutowski 42
Scheduled build times Vs part count
y = 0.001x + 3.995
R2 = 0.968
0
5
10
15
20
25
0 5,000 10,000 15,000 20,000 25,000 30,000
total number of parts
days
A1
A2
B1
B2
C2
C1
Sch
ed
ule
d b
uild
ti
mes
2.810 T.Gutowski 43
Engine Delivery Late Times
A1 A2 B1 B2 C1 C20
10
20
30
40
50
60
avera
ge d
ays
late
A1 A2 B1 B2 C1 C2
engines
2.810 T.Gutowski 44
Late times compared to scheduled times
0
20
40
60
80
100
120
140
0 5,000 10,000 15,000 20,000 25,000 30,000
total number of parts
days
planned throughput time
avg. actual throughput time
shortest actual throughput time
longest actual throughput time
Linear (planned throughput time)
A1A2
B1
B2 C1C2
2.810 T.Gutowski 45
Reasons for delay at site A
2%
13%
38%
47%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
People shortage Quality Issues Part Shortages unknown
perc
enta
ge o
f occ
urr
ence
2.810 T.Gutowski 46
Reasons for delay at site B (Guesses)
part lost at site3%
people shortage9%
build awaiting inspection
7%
Quality problem9%
part shortages67%
station not available1%
tools not available4%
2.810 T.Gutowski 47
Reasons for delay at site A (data)
unknown rework paperwork Quality0%
10%
20%
30%
40%
50%
60%
70%
80%perc
enta
ge o
f occ
urr
ence
unknown rework paperwork Quality
Q
2.810 T.Gutowski 48
Engines shipped over a 3 month period at aircraft engine factory “B”
0
2
4
6
8
10
12
7-Jun 15-Jun 23-Jun 30-Jun 7-Jul 15-Jul 24-Jul 31-Jul 7-Aug 15-Aug 24-Aug 31-Aug
Weeks
en
gin
es s
hip
ped
per
week
month 1 month 2 month 3
2.810 T.Gutowski 49
Engines shipped over a 3 month period at aircraft engine factory “C”
0
1
2
3
4
5
6
7
may june july august
weeks
en
gin
es
ship
ped