2x1000 mw_central jawa ipp-rfp ars

40
   Annex C Project Functional Specifications

Upload: saturasatu

Post on 05-Oct-2015

28 views

Category:

Documents


0 download

DESCRIPTION

big power plant in java

TRANSCRIPT

  • Annex C

    Project Functional Specifications

  • Annex C page i

    TABLE OF CONTENTS

    1. INTRODUCTION ...............................................................................................................1

    2. PROJECT INFORMATION AND SCOPE.........................................................................1

    2.1 PROJECT DESCRIPTION ......................................................................................1

    2.2 CONTRACT STRATEGY ......................................................................................2

    2.3 PROJECT SCOPE ...................................................................................................9

    2.4 TERMINAL POINTS AND INTERFACES .........................................................12

    3. DESIGN PRINCIPLES .............................................................................................................15

    3.1 DESIGN REQUIREMENTS .................................................................................15

    3.2 PERFORMANCE REQUIREMENTS ..................................................................15

    3.3 GENERAL REQUIREMENTS .............................................................................18

    3.4 STANDARDS AND STATUTORY REQUIREMENTS .....................................19

    4. PARTICULAR TECHNICAL REQUIREMENTS ...................................................................21

    4.1 INTRODUCTION .................................................................................................21

    4.2 MECHANICAL PLANT AND SYSTEMS REQUIREMENTS ..........................21

    4.2 ELECTRICAL PLANT AND SYSTEMS REQUIREMENTS .............................23

    4.4 CIVIL REQUIREMENTS .....................................................................................29

    4.5 ENVIRONMENTAL REQUIREMENTS .............................................................31

    5. QUALITY ASSURANCE, INSPECTION, COMMISSIONING AND TESTING ..................33

    5.1 GENERAL .............................................................................................................33

    6. SITE DESCRIPTION ...............................................................................................................33

    6.1 SITE LOCATION AND REQUIREMENTS ........................................................33

    7. PROJECT ADMINISTRATION ...............................................................................................34

    7.1 GENERAL .............................................................................................................34

  • Annex C page ii

    FIGURE

    NO. DESCRIPTION

    Figure 4-3 Configuration of GITET Mandirancan with the Introduction of PLTU Central

    Java

    Figure 6-1 GRID DEVELOPMENT OF CENTRAL JAVA AND YOGJAKARTA

    REGION 2010-2015

    Other: PLN design standards for 500kV transmission systems (in Data Room)

    PLN design standards for substations (in Data Room)

  • Annex C page 1

    1. INTRODUCTION

    These functional specifications (Functional Specifications) describe the minimum technical

    requirements for the development of the Project. The Plant will be located on a site in the

    Pemalang area.

    A jetty and unloading facilities shall be constructed by the SELLER to accommodate the vessels

    that will deliver coal for use at the Plant.

    PLN will purchase all energy from the Plant and transmit the energy to the load centers through

    the existing 500 kV transmission system. The evacuation of electric power generated by the

    Plant will be at 500 kV through a new 500 kV switchyard adjacent to the Plant to be built, owned

    and operated by the SELLER (Interconnection Facilities). A transmission line spur consisting

    of double circuit 500 kV transmission lines and a new substation (the Special Facilities)

    connecting the new switchyard to the existing 500 kV transmission system and connecting the

    existing 500 kV transmission system to the new switchyard will be built by the SELLER and

    turned over to PLN upon its completion.

    The Plant will use domestic Indonesian coal furnished by the SELLER and which complies with

    the minimum technical specifications listed in Section 2.4.1 below. The SELLER will be

    responsible to source, procure, transport, unload and store the coal for the Plant.

    The SELLER will be responsible for developing all geological, geotechnical and environmental

    information needed, including an AMDAL and other necessary Site investigations. The Plant

    will be required to comply with environmental standards and safeguards of the Laws of

    Indonesia and other environmental standards as may be required by the project lenders. The costs

    of any environmental impact assessment, Site investigations and investigations to ensure that any

    Indonesian or lenders requirements are satisfied will be borne entirely by the SELLER.

    A description of the AMDAL process is provided in Annex K of the RFP.

    2. PROJECT INFORMATION AND SCOPE

    2.1 PROJECT DESCRIPTION These Functional Specifications describe the minimum functional requirements for a two-Unit

    coal-fired Plant using supercritical or ultra-supercritical technology with a nominal Plant

    capacity of 1,600 MW (net) to 2,000 MW (gross) that the SELLER shall develop, build and

    operate in accordance with the PPA.

    The exact configuration of the Plant shall be determined by the SELLER, subject to the

    limitations specified in this Annex C. The SELLER will be responsible for selecting the location

    and obtaining the land for the Site and the Special Facilities Site.

  • Annex C page 2

    The SELLER will be responsible for constructing the seawater cooling intake piping system and

    cooling water discharge structures. The SELLER will also be responsible for constructing a

    jetty extending from the site a sufficient distance into the Java Sea to accommodate coal

    shipment vessels and which includes coal unloading and conveyance facilities.

    During site development and construction of the Central Java units, the SELLER will install a

    cooling water intake structure and a discharge structure to the Java Sea that will accommodate

    the required flows to and from the power plant. The SELLER will also construct the required

    pumping structure for the Plant.

    The Plant equipment and systems shall include all the systems, facilities, equipment, materials,

    and works required to ensure safe, reliable, and economic operation of the Plant such as coal

    handling systems, water treatment and storage facilities, and all the other necessary auxiliary and

    ancillary equipment required for the safe, reliable and efficient operation of the Plant. The Plant

    shall be constructed of new equipment and materials only.

    2.1.1 Proven Design and Technology Requirements

    The Plant is required to be highly reliable and efficient. It is essential that the key components of

    the Plant be of proven design and technology, which means that power plants of similar design

    must have been engaged in reliable commercial operation for at least three (3) years at three (3)

    different projects situated on different sites1. A project will be considered to have been in

    reliable commercial operation for the purposes of this requirement if the equipment proposed

    has an average forced outage factor that has not been above five percent (5%) and its average

    availability factor has not been below eighty percent (80%) for the duration of the commercial

    operation period. Forced outage factor and average availability factor can be provided by the

    power plants of similar design or provided from manufacturer data based on warranty claims and

    service calls.

    2.2 CONTRACT STRATEGY The SELLER shall be fully responsible for the financing of the Project, and the design, supply,

    delivery, erection, commissioning, operation, and maintenance of the complete Plant for the term

    of the PPA. Particulars of the Project performance requirements are given elsewhere in these

    Functional Specifications. The SELLER shall coordinate plans and activities with PLN during

    the design, construction, commissioning, and operation of the Project.

    These responsibilities will be contractually embodied principally in the PPA between the

    SELLER and PLN as the power purchaser and will include not only the requirements regarding

    the Plants Net Dependable Capacity and availability, but also stipulations of how the Plant will

    interface with PLNs Grid System in terms of start up times, performance ramp rates, ability to

    generate with falling system frequency, etc. in accordance with the PPA where applicable.

    1 A plant consisting of two or more units, constructed under a single PPA or EPC contract does not qualify as two or

    more different projects. However, two or three units installed at the same site, under different PPAs or EPC

    contracts qualify as two or three projects, respectively.

  • Annex C page 3

    2.2.1 Site

    The SELLER shall be fully responsible for the Site selection and acquisition, obtaining of any

    permits for its use and the design, supply, delivery, erection, commissioning, operation, and

    maintenance of the complete Plant on the Site for the term of the PPA. Neither PLN nor the

    Government shall have any obligation to assist with Site selection or acquisition, or obtaining

    permits.

    2.2.2 Special Facilities Site

    The SELLER shall be fully responsible for selection and acquisition of the Special Facilities

    Site, obtaining the necessary land and any necessary permits for its use and the design, supply,

    delivery, erection, commissioning and turning over to PLN of the Special Facilities including a

    substation and tie-in interconnections to the existing 500 kV transmission system, in accordance

    with the Project Milestone Schedule. The Special Facilities shall be designed, procured,

    constructed, tested and commissioned on the Special Facilities Site in accordance with PLN

    design standards and specifications for high voltage transmission systems.

    Neither PLN nor the Government shall have any obligation to assist with Special Facilities Site

    selection or acquisition, or obtaining permits.

    2.2.3 Tie-in to PLNs Grid System

    PLN will provide locations for the SELLER to use as connection points for connecting the

    transmission lines from the substation included in the Special Facilities by shortspan to the

    existing 500kV transmission system. The exact location of the connection points will depend on

    the Special Facilities Site selected by the SELLER.

    2.2.4 EPC Contract

    The SELLER shall enter into an EPC Contract for the design, engineering, procurement,

    construction, testing and commissioning of the Plant with an EPC Contractor meeting the

    experience requirements of Section 2.2.5. The Bidder must provide with its Proposal a

    memorandum of agreement attaching a detailed term sheet initialed by the EPC Contractor and

    Bidder indicating that if the Bidder is selected as the Winning Bidder, the EPC Contractor

    intends to enter into an EPC Contract with the SELLER to provide EPC services on the terms set

    out in the term sheet and which terms include the following:

    Commitment to meet the technical requirements detailed in this RFP

    Scope that includes the totality of the design, engineering, procurement, erection, construction, testing, commissioning and warranty obligations required to deliver

    a fully operational power plant

    Performance of the EPC Contract on a firm, fixed price, turnkey basis with completion of the EPC Contract on a date certain consistent with the Project

    Milestone Schedule

    In the case of a consortium EPC Contractor, joint and several liability among the members in respect of the totality of the obligations and liabilities of the

    EPC Contractor pursuant to the EPC Contract, or the inclusion of an EPC Lead

    Member that provides a wrap-around guarantee for the totality of the obligations

  • Annex C page 4

    and liabilities of the EPC Contractor pursuant to the EPC Contract

    Equipment and Plant warranties/guarantees

    Setting in place by the EPC Contractor, or its Affiliate, of a performance bond or other acceptable performance guarantee, payable when called by the SELLER

    Reasonable and customary liquidated damages for delays in performance and for failure to meet required capacity and heat rate

    Each Bidder shall provide with its proposal copies of the most recent Annual Report of the

    proposed EPC Contractor, or its parent organization.

    2.2.5 EPC Contractor Qualifications and Major Equipment Requirements

    Each Bidder shall nominate a proposed EPC contractor to design, engineer, procure equipment

    and materials, and construct the Project. The Bidders proposed EPC Contractor shall have

    appropriate experience in engineering, procuring for and constructing large coal-fired power

    plants so as to satisfy the EPC experience criteria in Section 2.2.5.1 below.

    The proposed EPC Contractor shall also have international experience which includes

    engineering, procurement for and construction of thermal power projects in the international

    market so as to satisfy the requirements of Section 2.2.5.2 below.

    The proposed EPC Contractor shall propose equipment suppliers that meet the criteria set forth

    in Sections 2.2.5.3 and 2.2.5.4.

    2.2.5.1 EPC Contractor large coal-fired power plant experience

    The proposed EPC Contractor (directly or through an Affiliate) shall have successfully provided

    engineering, procurement and construction services to have built at least two (2) coal-fired power

    generation projects, with all of the following characteristics:

    Each project shall have a unit (or units) with a capacity of at least 6002 MW (gross)

    Each project shall use pulverized coal technology

    Each of the projects shall use supercritical technology or if a Bidder proposes ultra-supercritical technology, then at least one of the projects shall use ultra-supercritical

    technology3

    Each project shall be connected to the national power grid(s) in the country(ies) in which such projects are located

    2 If Bidder offers a configuration of 2 x 800 MW (net) or higher but less than 2 x 900 MW (net), 600 MW shall be replaced

    with 500 MW.

    3 For the purposes of this Section 2.2.5, reheat steam temperatures above 580oC shall be considered as ultra-supercritical

  • Annex C page 5

    2.2.5.2 EPC Contractor international experience

    The proposed EPC Contractor must have successfully constructed at least two (2) thermal

    power projects in a country or countries other than the country where the proposed EPC

    Contractor is domiciled. The requirements of this section are independent of the

    technology / fuel or size of a project.

    If the projects cited to satisfy the requirements of Section 2.2.5.1 also meet the

    requirements of Section 2.2.5.2, Bidder need not submit additional projects that meet the

    requirements of Section 2.2.5.2.

    2.2.5.3 Other requirements

    No power generation project completed by a proposed EPC Contractor may be submitted to

    satisfy the criteria in Sections 2.2.5.1 and 2.2.5.2 unless (1) it has received all relevant permits,

    including environmental clearances to achieve commercial operation and (2) it has been

    completed and in commercial operation for at least three (3) years as of the Bid Submission

    Date.

    If the cited projects were constructed on Turnkey EPC Basis, the proposed EPC Contractor, or

    the EPC Lead Member of a proposed EPC Contractor consortium if a consortium is proposed to

    be utilized, shall have been the sole EPC contract member, or shall have been the EPC Lead

    Member of an EPC consortium, which performed the work on the completed power projects

    which are submitted to meet the experience requirements of Sections 2.2.5.1 and 2.2.5.2.

    If the cited projects were not constructed on Turnkey EPC Basis and a sole EPC Contractor is

    proposed, such sole EPC Contractor must have performed turbine erection, boiler erection,

    associated balance of plant (BOP) works and civil works for completed power projects that meet

    the experience requirements of Sections 2.2.5.1 and 2.2.5.2, save in the case of projects cited to

    meet the civil works experience, the cited projects need not have utilized supercritical or ultra

    supercritical technology.

    If the cited projects were not constructed on Turnkey EPC Basis and a consortium is proposed to

    be utilized as the proposed EPC Contractor, such consortium shall include an EPC Lead Member

    and possess experience, via members or sub-contractors, in turbine erection, boiler erection,

    associated BOP works and civil works that each (member or sub-contractor) individually

    performed the relevant work on completed power projects that meet the experience requirements

    of Sections 2.2.5.1, save in the case of the civil works member or sub-contractor, the cited

    projects need not have utilized supercritical or ultra-supercritical technology. For the avoidance

    of doubt, the EPC Lead Member may be any one of the consortium members that satisfies the

    experience in turbine erection, boiler erection or associated BOP works.

    Further, the proposed sole EPC Contractor or the proposed EPC Lead Member (as applicable)

    shall meet the experience requirements of Sections 2.2.5.1 and 2.2.5.2 and each project cited by

    such proposed sole EPC Contractor or the proposed EPC Lead Member (as applicable) to meet

  • Annex C page 6

    the experience requirements of Sections 2.2.5.1 and 2.2.5.2 shall meet the following criteria:

    built within 10% of the original cost estimate,

    built within two months of the original schedule

    built without environmental violations during construction and operation

    performance test results for capacity and heat rate met guaranteed levels.

    Each Bidder shall provide the information detailed in Annex D- Exhibit 6 as evidence of the

    proposed EPC Contractors required experience and conformance with these requirements.

    Bidders should note that if none of the qualifying projects cited by a Bidder to satisfy the

    requirements of Sections 2.2.5.1 and 2.2.5.2 were constructed on Turnkey EPC Basis, the PPA

    shall require that the amount of Bank Guarantees (Stage II only) shall be increased to USD 105

    million if such Bidder is selected as Winning Bidder.

    2.2.5.4 Boiler and Steam Turbine supplier requirements

    Supplier Experience

    The proposed EPC Contractor shall propose using boiler and turbine suppliers each of whom

    have designed and manufactured similar equipment which has been in use in at least two (2)

    supercritical units, of at least 900 MW (gross) size each, that have each been in successful

    operation for at least two (2) years as of the Bid Submission Date. If the Bidder proposes to use

    ultra-supercritical technology, then the proposed EPC Contractor shall propose using boiler and

    turbine suppliers each of whom have designed and manufactured similar equipment which has

    been in use in at least two (2) ultra-supercritical units, of at least 900 MW (gross) size each, that

    have each been in successful operation for at least two (2) years as of the Bid Submission Date.

    For the purposes of Annex C and Annex D Exhibit 6, the term similar equipment refers to

    equipment based on similar, but not necessarily identical, design and technology to that being

    proposed for the Project which may vary according to site conditions.

    Each Bidder shall provide the information detailed in Form 3B of Annex D: Exhibit 6 as

    evidence of the proven experience of the boiler and steam turbine supplier.

    Equipment Design and Technology

    Boiler and turbine supplier designs shall be based on designs which meet the Proven Technology

    requirements as set out in Section 2.1.1. Section 2.1.1 applies to industry-wide experience and

    not necessarily to a particular suppliers experience. Suppliers can meet the Proven Technology

    requirement based on other supplier(s)s technology/design if they have a valid license or

    agreement for such technology/design for use in the Facility. For the avoidance of doubt,

    suppliers must meet the Supplier Experience criteria above and may not use the experience of a

    licensor to meet the Supplier Experience requirements of this Section 2.2.5.3.

    Each Bidder shall provide the information detailed in Form 3A of Annex D: Exhibit 6 as

    evidence of the proven experience of the boiler and steam turbine.

  • Annex C page 7

    2.2.5.5 Major component equipment experience requirements

    The major equipment components (other than the boiler and steam turbine) which are critical to

    the operation of the Plant are identified in Section 4.2 of Annex D-Exhibit 6, namely:

    Generators

    Feedwater pumps and drivers

    Flue gas desulphurization (FGD)

    Control system

    Coal handling equipment

    The proposed equipment for the Project shall meet the Proven Technology requirements of

    Section 2.1.1 which is demonstrated in this case by considering their prior use in utility scale

    power generating units of at least 500MW. Section 2.1.1 applies to industry-wide experience and

    not necessarily to a particular suppliers experience. Suppliers can meet the Proven Technology

    requirement based on other supplier(s)s technology/design if they have a valid license or

    agreement for such technology/design for use in the Facility.

    Each Bidder shall provide the information detailed in Form 3A of Annex D: Exhibit 6 as

    evidence of the proven experience of the above major components.

    2.2.6 O&M Operator Qualifications and Requirements

    Each bidder shall nominate an O&M Contractor to operate and maintain the Project (the O&M

    Contractor). The Bidders O&M Contractor shall have appropriate experience operating coal-

    fired projects so as to satisfy the O&M Experience Criteria below.

    Each Bidder must provide the name of their O&M Contractor and details of how such O&M

    Contractors experience meets the O&M Experience Criteria below. Each Bidder shall provide

    with its proposal copies of the most recent Annual Reports of the proposed O&M Contractor, or

    its parent organization In addition, the Bidder must provide a copy of a signed memorandum of

    agreement attaching a detailed term sheet initialed by each of the O&M Contractor and the

    Bidder, indicating that if the Bidder is selected as the Winning Bidder, the O&M Contractor

    intends to enter into an O&M Contract with the Project Company to be set up by such Bidder to

    be the counterparty to the PPA, to provide O&M services on the terms set out in the term sheet.

    Use of an Owner-Operator model is acceptable, provided that a Sponsor, or Affiliate of a

    Sponsor meets the experience and expertise above to provide these services. The requirement is

    that the operations be undertaken through an Agreement with a Sponsor or its Affiliate and the

    SELLER to provide services which will allow the SELLER to meet the performance objectives

    of the PPA. Bidder shall provide an executed Memorandum of Understanding (MOU) which

    describes the conditions to be included in a long-term agreement between the Owner-Operator

    and the SELLER. The agreement shall, as a minimum:

  • Annex C page 8

    Commit to provide experienced personnel and support services (expertise, systems and equipment) to the SELLER and include a scope of those services and personnel to be

    provided

    Include standards of performance reflecting the obligations of the SELLER under the PPA (eg, Plant Availability, Scheduled Outage coordination with PLN)

    Include commercial terms which are compatible with commercial terms included in the PPA

    Include lines of communication between SELLER and Sponsor or Sponsor Affiliates providing the O&M personnel and services

    The O&M Contractor (either directly or through an Affiliate) shall have successfully operated

    and maintained at least two (2) coal-fired power generation units, each unit having a capacity

    of at least 800 MW (gross) and each using pulverized coal technology with at least one of the

    units using supercritical technology. If a Bidder proposes to utilize ultra-supercritical

    technology, then at least one of the units cited to meet the experience criteria of this Section 2.2.6

    shall have utilized ultra-supercritical technology.

    Successfully operated and maintained means all the following:

    the units should have been completed and in commercial operation for at least three (3) years;

    the O&M contracts (if applicable) for each of the cited units have not been terminated or suspended as a result of a default by the O&M Contractor;

    no penalties or liquidated damages have been paid under any power purchase agreement for any of the cited units where such penalties or liquidated damages

    exceed fifteen percent (15%) of the total annual capacity payments payable in

    respect of the unit in question in any given year;

    the average forced outage factor shall not have been above five percent (5%) and the average availability factor shall not have been below eighty percent (80%) for

    the duration of unit operation under the power purchase agreement or O&M

    contracts (if applicable), whichever is longer, for each of the cited units; and

    there have been no material infringements of applicable environmental and/or occupational health and safety laws or regulations at any of the cited units.

    In respect of each power unit cited to meet the O&M Experience Criteria, each Bidder

    must provide details demonstrating how such criteria are met as well as details of the

    year commissioned, name of owner and representative (phone and facsimile number),

    data on availability, Gigawatt hours (GWh) produced for at least one year, and the

    Forced Outage Rate (as defined in appendix G of the PPA).

    Each Bidder shall provide the information detailed in Annex D-Exhibit 6 as evidence of the

    O&M Contractors required plant operating experience and conformance with these

    requirements.

  • Annex C page 9

    2.2.7 Local Content

    Local labor, materials, and manufacturing should be used to the maximum feasible extent and in

    compliance with applicable laws.

    2.2.8 Transfer of Plant

    The Plant will be overhauled, repaired and tested upon the expiry of the PPA and transferred to

    PLN, or its designee, in good order with the appropriate tools, parts, software and records as

    described in Section 3.3.2 below.

    2.2.9 Operational Performance

    The Plant will interface with PLNs Grid System in terms of start up times, performance ramp

    rates, ability to generate with fluctuating system frequency and voltage levels, providing

    protective relaying and metering in accordance with the PPA all in full compliance with the

    Java-Bali Grid Code

    2.3 PROJECT SCOPE The Plant shall comprise a complete coal-fired Plant with a capacity of between 1,600 MW (net)

    and 2,000 MW (gross) comprised of two equally sized units and all support facilities required for

    commercial operation. The maximum size of a unit is limited to 1000 MW gross rating for

    stability considerations.

    2.3.1 Scope of Work

    The scope of work to be provided by the SELLER for engineering, procurement, and

    construction of the Plant shall include, but not be limited to, the following:

    the overall management and control of the works

    control and supervision of the Contractors and sub-contractors

    provision of all labor, supervision, management, materials, equipment, on-Site storage and material handling and control of the complete works

    Site investigations and surveys, as required

    preparation and processing of an Environmental Impact Assessment

    obtaining all relevant Consents and Permits

    engineering and design

    detailed engineering

    procurement

    expediting

    inspection

    manufacture and fabrication

    painting

  • Annex C page 10

    packing, shipping, delivery to Site and insurance

    Site safety and security

    construction and erection

    protection and preservation

    testing and pre-commissioning

    commissioning and testing

    Performance Tests and Reliability Tests

    operation and maintenance of the Plant during the term of the PPA

    other services as specified or necessary to complete the Project

    temporary construction works and facilities, including camp facilities if required

    provision of documentation

    operators living quarters and facilities, if required

    Transfer of the Plant at end of Term of the PPA

    2.3.2 Scope of Supply

    The Plant will comprise, but not necessarily be limited to the following:

    Two pulverized coal fired boilers of equal size using supercritical or ultra-supercritical (USC) technology

    Two steam turbine generators, with a maximum size of 1000 MW gross rating

    Electrostatic precipitators or bag houses

    Flue gas desulfurization (FGD) systems (limestone based) - other than limestone based FGD systems are acceptable as long as Bidder

    meets environmental emissions requirements, both airborne and in

    seawater discharge and meets the requirements using the specified

    coals (Primary, Secondary and Qualifying Alternate Coal).

    Selective catalytic reduction (SCR), if required to meet NOx emission requirements

    Stack(s) tall enough to meet the ambient air quality requirements

    Continuous Air Emissions Monitoring Systems

    Surface condensers

    Condensate systems

  • Annex C page 11

    Feed water systems

    Steam systems

    Once through (or circulating) sea water condenser cooling system including

    Sea water intake piping and structures

    Sea water pump house

    Cooling water piping

    Discharge to the sea

    Fuel unloading jetty from the site to seawaters with sufficient depth to accommodate vessels delivering coal

    Coal stacker/reclaimer system

    Coal ship unloading system

    Coal conveyor transport systems, crushers and pulverizers

    Coal storage for at least 30 days (at minimum capacity factor of 80%)

    Start-up and supplemental fuel unloading, handling, and storage system

    Limestone storage and handling system

    FGD by-product handling and disposition

    Raw water system including necessary storage tanks and pumps

    Water Desalination Plant

    Water treatment systems including pre-treatment and de-mineralization

    Wastewater treatment systems

    Service water and auxiliary cooling water, and potable water systems

    Fire Detection and Protection System

    Ash handling system

    Service and instrument air systems

    HVAC systems

    Generator step-up transformers to connect to the 500 kV switchyard

    Auxiliary power and start-up transformers, as required

    500 kV switchyard ( Electrical Interconnection Facilities)

    Special Facilities including 500 kV transmission lines, substation and related equipment and components between the Electrical

  • Annex C page 12

    Interconnection Facilities and the existing 500 kV transmission

    system and including making the interconnections to the existing lines

    on a route to be determined by the SELLER.

    Distributed Control System and necessary instrumentation and control equipment

    Automatic Generation Control (AGC)

    Emergency Diesel generators to provide for safe plant shutdown

    Electrical switchgear of various voltages

    Direct current switchgear, batteries, chargers and inverters.

    Site fencing and security

    Earthing and lightning protection systems

    Control and Administration buildings

    Mosque

    Workshops and laboratories

    Spare parts inventory

    SCADA & communication systems

    The SELLER shall include any additional plant and equipment necessary to meet

    the Plant design, performance, operation, environmental criteria and Prudent

    Operating Practices but which are not specifically identified above, and to form a

    complete power project which is fit in all respects for its intended purpose and

    use.

    The SELLER will be required to meet the Laws of Indonesia.

    2.4 TERMINAL POINTS AND INTERFACES The SELLER shall be responsible for making the connections required at all terminal (interface)

    points as specified.

    2.4.1 Fuel Supply - Coal

    The fuel shall be domestic Indonesian coal, sourced and supplied by the SELLER. Coal specified

    by the SELLER shall require the coal to: (1) have a minimum calorific value of 4,000

    kcal/kg(HHV4) (2) have a maximum calorific value of 5,500 kCal/kg (HHV); (3) all other

    criteria, such as HGI, moisture, ash, S, etc, should be in accordance with Appendix S of the PPA.

    4 On GAR basis

  • Annex C page 13

    Reference coal content shall be 5,000 kCal/kg(HHV). As a minimum requirement, the coal

    unloading jetty shall be capable of accommodating barges with 7 m draft and 14,000dwt

    capacity. On site coal handling will also be the responsibility of the SELLER, and adequate

    space for unloading, transfer and stacking and reclaiming coal shall be provided.

    2.4.2 Fuel Oil

    Fuel Oil for start up, supplemental firing, and the emergency diesel generator will be provided by

    the SELLER, along with unloading, storage and distribution facilities.

    2.4.3 Limestone

    Limestone and all associated receiving, handling, storage and treatment facilities as required for

    FGD systems is to be provided by the SELLER.

    2.4.4 FGD by-product

    The SELLER shall be responsible for the disposition of any solid and liquid by-products from

    the FGD system. The FGD by-product disposal area shall be separate from the ash disposal area.

    2.4.5 Water

    The SELLER is responsible for entering into any contractual arrangements necessary to meet the

    requirements specified below.

    (a) Raw Water

    Raw water used by the SELLER shall be provided via desalination

    (b) Potable Water

    The SELLER will have to treat raw water, if required, to use as potable water. The

    SELLER may choose to use bottled water for drinking or other acceptable option.

    (b) Condenser and Plant Cooling Water

    The Plant will be cooled by a seawater system. The intake piping and structures will be

    provided by the SELLER. The pumping and cooling water discharge facilities will also

    be provided by the SELLER. The SELLER will be responsible for constructing the

    cooling water pumping station required for the Plant.

    (d) Construction Water

    During construction the SELLER shall develop and distribute a source of water for

    construction.

    (e) Boiler Make-up Water

    The SELLER shall use the raw water to provide boiler make-up water to meet the

    requirements of the Plant.

  • Annex C page 14

    (f) Sanitary and Sewer Facilities

    The SELLER shall provide for adequate sanitary facilities during Plant construction and

    Plant operations, and treat sanitary drains to comply with applicable discharge standards

    of the Government prior to discharging it to the cooling water discharge canal.

    (g) Drainage

    Oily water and chemical drains shall be treated to an approved quality before being

    discharged to the cooling water discharge canal. All drains and other liquids, if

    discharged from the Plant shall at all times comply with appropriate environmental

    regulations and meet the quality standards specified by the Government and the EHS

    Guidelines.

    2.4.6 Electrical

    500 kV Switchyard and Interconnection to PLNs Grid system

    The SELLER will construct a 500 kV switchyard for the Plant (Electrical Interconnection

    Facilities) which will interconnect with the Special Facilities. The interfaces of the Electrical

    Interconnection Facilities with the Special Facilities are the gantrys in the 500kV switchyard

    bays that connect to the Special Facilities transmission lines. The Special Facilities transmission

    line circuits shall remain intact under breaker failure conditions affecting any breaker in the

    Electrical Interconnection Facilities.

    The SELLER, in coordination with PLN, will design and install main and back up protection

    relays with zones that extend into the switchyard, Special Facilities (see 4.3.11) and the power

    plant, particularly the protection of the Generator Step-up Transformers and generators.

    The SELLER will provide communication links to the power grid SCADA system including

    adequate Remote Terminal Unit (RTU) points to accommodate PLNs Java Control Center

    requirements.

    2.4.7 Communications, Control, and Instrumentation

    The SELLER shall provide all line relay equipment and communication equipment and RTUs to

    interface required Plant information with the Java Control Center, as required by PLN. The

    specifications of such relays, RTUs and communication equipments shall be matched with the

    existing equipment being used by PLN and be in accordance with Appendix I of the PPA.

    2.4.8 Ash Disposal (fly ash)

    Ash disposal is to be dry utilizing an onsite land fill. A pneumatic ash collection system is to be

    provided along with ash storage silo(s) and an onsite land fill. The SELLER shall develop the

    design to optimize ash sales for other uses.

  • Annex C page 15

    3. DESIGN PRINCIPLES

    3.1 DESIGN REQUIREMENTS The Plant shall be of proven design, built to appropriate internationally recognized standards,

    and complying with all the applicable statutory codes and regulations. Equipment suppliers for

    the Plant can meet the proven design and technology requirements of Section 2.1.1 based on

    another supplier(s)s technology or design if they have a valid license or agreement for such

    technology/design, including allowance under the license to export the technology.

    Plant reliability, availability, and maintainability consistent with high efficiency, are of

    paramount importance.

    The Plant shall be designed and equipment should be sized to permit reliable base load operation

    over the complete range of anticipated ambient conditions without limiting the plant output.

    The Site is in an area impacted by factors that may affect construction of the Plant. Thus these

    agents must be taken account in design. The factors include:

    Erosion agent from salt air of coastal region for the outdoor construction;

    Erosion agent from sea water for reinforced concrete construction and structural steel that contact directly to the sea water;

    Seismic zone 25 (bedrock acceleration of 0.15g to 0.2g for 500-year return period)

    3.2 PERFORMANCE REQUIREMENTS

    3.2.1 Operating Regime

    The Plant shall be designed primarily for base load operation but it must also be capable of

    operating continuously at reduced loads, if required. The Plant will be required to operate at high

    net capacity factors (plant factors) and in accordance with PPA Appendix L. The Plant will be

    normally frequency controlled rather than load controlled. Governor and droop settings etc shall

    be in accordance with the Java-Bali Grid Code.

    There is no requirement for the Plant to operate continuously above the manufacturers declared

    base load maximum continuous rating (MCR) at given ambient conditions and the physical

    condition of the Plant. However, during emergency conditions (as determined by the Java-Bali

    grid control), the plant output shall be increased to VWO conditions for a limited period.

    The Plant should be capable of automatic operation and control at loads between 100% and 40%

    of Net Dependable Capacity without supplemental firing. When only one unit is in operation, the

    operating range of such unit shall be from 20% to 50% of the Plant Net Dependable Capacity,

    without supplemental firing.

    5 Indonesian National Standard SNI 03-1726-2002 as expected to be revised

  • Annex C page 16

    3.2.2 Plant Start Up and Loading

    The Plant can be started using electrical energy provided through the 500 kV switchyard. In

    order to meet the PLN dispatch requirements, the Plant shall be designed to meet or improve

    upon the minimum start up time and loading rates as proposed by the SELLER and which will be

    included in the PPA, Appendix B. The SELLER will be reimbursed for excess starts of each Unit

    in a Contract Year as supplemental charges for start up from cold, warm and hot conditions per

    Appendix G of the PPA.

    For each Unit, the following definitions shall apply:

    a. cold start: A resynchronization after more than 48 hours of

    continuous shutdown.

    b. warm start: A resynchronization after more than 18 hours but

    less than 48 hours of continuous shutdown.

    c. hot start: A resynchronization after less than 18 hours of

    continuous shutdown

    3.2.3 Start Up Times and Load-Ramping Rates

    The SELLER shall provide the start up times, from start initiation to synchronization, and the

    load-ramping rates, from zero to rated output, that the Plant will achieve under cold, warm, and

    hot start up conditions. The start up times and the load-ramping rates shall be comparable with

    other plants within this size range.

    3.2.4 Availability and Reliability

    The Plant shall be designed to achieve the levels of availability and reliability normally expected

    for similar modern coal fired power plants, and as required by the PPA. It is expected that the

    Plant will operate as a base load plant based on economic dispatch and will be designed to meet

    an average lifetime Equivalent Availability Factor of no less than 88%. The Plant will be

    required to achieve an annual Actual Availability Factor meeting or exceeding the Projected

    Availability Factors for each operating year which will be specified in Appendix G of the PPA.

    In this specification the Equivalent Availability Factor formula is defined as:

    Where:

    A = Equivalent Availability Factor

    DC = Average Dependable Capacity for the year

    Y = Number of years

    MOcap = capacity reduction during Maintenance Outages

    8760

    )(8760

    DC

    SOHSOFOHFOMOHMODCA

    capcapcap

  • Annex C page 17

    MOH = Maintenance Outage hours

    FOcap = capacity reduction during Forced Outages

    FOH = Forced Outage hours

    SOcap = capacity reduction during Scheduled Outages

    SOH = Scheduled Outages hours

    3.2.5 Operating and Control Requirements

    It is anticipated that during early operating years the Plant will operate as a base load power

    generating station, generating close to the Plants rated output for much of the time. In later

    years it is possible that the Plant may be required to operate on a cycling basis and that the Plant

    and its control system must be designed to maximize efficient operation, under both these

    operating regimes

    The control and supervision of the Plant shall be carried out in a Central Control Room, from

    where the generators will normally be started, auto-synchronized, and initially loaded. Provision

    shall be made to allow the Plant output to be controlled remotely by PLN through the AGC

    program installed at PLNs Java Control Center. The Plant shall be designed to ensure that

    automatic hot, warm and cold starts, as well as shut downs, are achieved on a reliable basis

    throughout its design life. The Plant shall also meet the following steady state and transient

    operating conditions:

    a. Operate under automatic control for sustained periods at all loads above

    minimum controllable, for the given ambient temperature range.

    b. Provide the necessary equipment to ensure safe shut down of the Plant

    under all foreseeable circumstances.

    c. Automatic controls shall account for boiler and turbine operating

    conditions (hot, warm or cold), in setting the ramp rates for start up and

    loading.

    d. Each turbine generator shall be provided with a flexible governing system

    whose characteristics can be readily adjusted to accommodate any changes

    in the operating regime that may arise during the life of the Plant. The

    governing system should be provided with a set of control algorithms that

    allow Plant operators to change governor control parameters, if required.

    3.2.6 Plant Maintenance

    Maintenance of the Plant which requires an outage of a Unit or the Plant shall be scheduled in

    accordance with Appendix L of the PPA. Maintenance of the Plant can also be scheduled during

    other alternative periods as PLN may agree.

  • Annex C page 18

    3.3 GENERAL REQUIREMENTS

    3.3.1 Design Life

    The Plant shall be designed for a life of forty (40) years, and the SELLER shall be responsible

    for owning, operating and maintaining the Plant for the term of the PPA.

    3.3.2 Transfer

    Following the expiry of the PPA, ownership of the Plant will be transferred in accordance with

    the terms of the PPA.

    3.3.3 Staffing Levels

    The Plant shall be designed to require the minimum number of operating and maintenance staff,

    consistent with high operational safety, reliability and economy. SELLER shall employ local

    staff to the extent possible.

    3.3.4 Sparing Philosophy

    Redundancy of design shall be such that the performance of primary and auxiliary equipment

    shall be sufficient to meet the availability requirements of the Plant. No single failure of an

    active component shall result in more than one Unit being affected.

    3.3.5 Protection against adverse ambient conditions

    The Plant shall be designed to withstand extreme ambient conditions as determined in

    accordance with Section 6.2 and listed in Table 9.3-1 of Annex D: Exhibit 6 to which it may be

    exposed and to continue to function normally, within appropriate range of de-rating factors to

    account for such ambient conditions.

    3.3.6 Finishing and Surface Preparation

    Steel structures of the Plant shall be painted and surface protected suitably for local conditions in

    accordance with the standards and practices of the Steel Structures Painting Council.

    3.3.7 Thermal Insulation

    Insulation shall be provided where necessary for personnel protection and to minimize heat

    losses.

    3.3.8 Hazardous Areas

    Where possible, hazards should be reasonably avoided. Where appropriate, areas shall be

    classified to the relevant sections of the Indonesian environmental regulations and the NFPA, or

    other recognized standards. Suitably certified equipment shall be used in the designated

    hazardous areas.

    3.3.9 Units of Measurement

    The units of measurement used throughout the Project shall be expressed in the SI system, except

    that pressure shall be expressed in kg/cm2 (or Bar) and temperature shall be expressed in degrees

  • Annex C page 19

    Celsius (C). Energy content of fuel shall be expressed in kCal/kg. Heat rates shall be expressed

    in kCal/kWh.

    3.4 STANDARDS AND STATUTORY REQUIREMENTS

    3.4.1 Standards

    All Plant components, systems, and equipment shall be designed, manufactured, assembled and

    tested at manufacturers works, installed and, after installation at the Site, shall be tested and

    commissioned, in accordance with applicable internationally recognized standards, and statutory

    regulations, including those specifically listed in these Functional Specifications.

    Each Bidder shall provide with its Proposal a schedule of all the key codes proposed to be used

    for the construction, testing, etc., of the Plant.

    Any of the standards published by the authorities listed here are acceptable:

    ACI American Concrete Institute

    AISC American Institute of Steel Construction

    AISI American Iron and Steel Institute

    ANSI American National Standards Institute

    API American Petroleum Institute

    ASHRAE American Society of Heating, Refrigeration & Air Conditioning

    Engineers

    ASME American Society of Mechanical Engineers

    ASTM American Society for Testing and Materials

    ASTI

    AWS American Welding Society

    AWWA American Water Works Association

    BS British Standards Institution

    CEN European Committee for Standardization

    CENELEC European Committee for Electrotechnical Standardization

    DIN German Standardization Institute

    HEI Heat Exchange Institute

    HIS Hydraulic Institute Standard

    IAPH International Association of Ports and harbors

    ICORELS International Commission for Reception of Large ships

    IEC International Electrotechnical Commission

    IEE Institute of Electrical Engineers

    IEEE Institute of Electrical and Electronics Engineers

    IP Institute of Petroleum

    ISO International Standards Organization

    JIS Japanese Industrial Standards

    MSS Manufacturers Standardization Society

    NEMA National Electrical Manufacturers Association

    NFPA National Fire Protection Association

    PIANC Permanent International Association of Navigation Congresses

    SSPC Steel Structures Painting Council.

  • Annex C page 20

    TEMA Tubular Exchanger Manufacturers Association

    TRD Technical Rules for Steam Generators

    VDI Association of German Engineers

    VGB Society of large utility owners

    UBC Uniform Building Codes

    EHS EHS Guidelines

    Indonesian Codes and Standards

    MEMR Regulation 3/2007 on Java-Bali Grid Code

    MEMR Regulation 46/2006 on Electricity Installation

    Government Regulation No. 41, 26 May 1999, Air Pollution Control.

    State Minister of Environment Decree No. Kep.13/Men LH/3/1995,

    Emissions Standards from Stationary Sources, Exhibit III-B.

    State Minister of Environment Decree No. 122/2004

    State Minister of Environment Decree No.48/MENLH/11/1996.

    Government Regulation No. 27 year 1999 regarding Environmental

    Impact Assessment (AMDAL)

    Minister of Energy and Mineral Resources No. 1457/K/28/MEM/2000

    on Technical Guidelines on Environmental Management in the Field of Mining

    and Energy.

    Indonesian Ministry of Manpower re inspection and testing of pressure vessels

    and lifting equipment.

    Indonesian Concrete Code

    SNI - Indonesian National Standards

    Approval will be required for use of other codes or standards. The Bidder proposing such other

    codes or standards shall provide rationale and evidence of equivalence to support their case for

    approval. The evidence which is provided must clearly demonstrate that the proposed codes or

    standards have previously been demonstrated and accepted as equivalent to the specified codes

    and standards.

    3.4.2 Electrical Interconnections

    All interfaces with the PLNs Grid System shall comply with the requirements of PLN, the Java

    Bali Grid Code and Appendix I of the PPA.

    3.4.3 Fire Protection

    The fire detection and protection systems shall provide coverage of all the Plant and shall

    comply with NFPA codes in addition to all statutory and local authority requirements.

    3.4.4 Health and Safety at Work

    The Plant shall be constructed, installed and commissioned and be operable and maintainable in

    full compliance with relevant health and safety at-work orders, all related acts, regulations, codes

    and statutory requirements. All warning and instruction notices shall be in Indonesian and

  • Annex C page 21

    English.

    3.4.5 Hazardous Substances

    The SELLER shall implement all special requirements concerning the nature, handling and

    storage of all classified substances including fuels, oils, gases and chemicals. Toxic, radioactive,

    inflammable and explosive materials shall be declared and approved before importation to the

    Site.

    3.4.6 Escape Routes

    Equipment location and arrangement shall ensure that not less than two escape routes are

    available for personnel in case of fire or other hazard during normal operation and maintenance

    procedures.

    3.4.7 Environmental Requirements

    All statutory environmental regulations shall be adhered to during the design, construction and

    operating phases of the Project. Lender requirements in this respect are also to be complied with.

    3.4.8 Nameplates and Plant Coding System

    All nameplates on equipment shall be written in Indonesian and English. A consistent Plant

    coding system shall be used throughout the duration of the Project from design through the end

    of the operating period. Those items of Plant electrical equipment specified in the Java-Bali Grid

    Code (Connection Code Section) shall include equipment numbering and identification codes in

    accordance with the Connection Code.

    O&M Manuals shall be written in Indonesian and English whenever possible.

    4. PARTICULAR TECHNICAL REQUIREMENTS

    4.1 INTRODUCTION This section of these Functional Specifications describes the particular technical requirements of

    the principal items of the Plant and the associated systems. The detailed particular technical

    requirements, including the construction details of the Plant, will be the subject of specifications

    to be prepared by the SELLER.

    4.2 MECHANICAL PLANT AND SYSTEMS REQUIREMENTS

    4.2.1 Boilers

    The boilers shall be pulverized coal type, and use supercritical or ultra-supercritical technology.

    The boilers shall be designed to be capable of burning coals which satisfy the coal specifications

    in Attachments A and B to Appendix S to the PPA and which have a higher heating value (HHV)

    within the range between 4,500 to 5,000 kCal/kg. The boiler(s) and auxiliaries shall be sized to

    operate over the full range of ambient temperatures specified without limiting the plant output.

    They shall include economizer, evaporator, superheater and reheater tube bank section(s) with

    tubing, as appropriate, to maximize heat transfer.

  • Annex C page 22

    Pressure parts shall be designed, manufactured and tested in accordance with "ASME Boiler and

    Pressure Vessel Code, Section 1, Power Boilers".

    Each boiler shall exhaust through a separate flue and chimney or to a common multi-flue stack

    with a concrete protective shell. Carbon carry-over into the fly ash shall under normal operating

    conditions be less than six percent (6%).The stack height and the flue gas exit temperature shall

    be sufficient to ensure adequate dispersion of the flue gases in accordance with environmental

    standards and requirements. Chimneys shall have hazard lighting and painting as required by

    local aviation laws and regulations.

    4.2.2 Steam Turbine(s)

    The steam turbines shall be of proven design directly coupled to a 50 Hz generator. Design

    criteria shall be applied to ensure a long creep life, cyclic duty and fast start-up. Last stage blade

    materials and exhaust steam moisture shall be selected to minimize blade erosion. The last low

    pressure stage blade design shall have been proven in service. The boiler outlet steam

    parameters shall be selected to satisfy the necessary design steam parameters at the steam turbine

    inlet

    The steam turbine generators shall be installed within a common enclosed turbine building with

    indoor access to the control room. Overhead cranes shall be installed as required.

    The steam turbine exhaust and condenser configuration shall be to the manufacturers standard

    design.

    4.2.3 Feedwater System

    A feedwater system shall be designed to provide sufficient and reliable feedwater supply to the

    boilers. It shall include but not be limited to necessary feedwater heaters, deaerators, feedwater

    pumps, control valves and auxiliaries.

    4.2.4 Steam Condensers

    To condense steam exhausted by the steam turbine, the Plant shall utilize a water cooled

    condenser in an open seawater system. The surface condenser(s) shall be designed and

    constructed to HEI Standards, or equivalent, with sufficient margin and spare surface area for the

    maximum heat rejection duty under both normal operation and turbine bypass operation

    conditions for the operating regime specified.

    The condenser tube and tube sheet materials shall be suitable for the cooling water quality. An

    on-line condenser tube cleaning system shall be provided.

    The condenser(s) shall be of the divided waterbox type arranged to allow waterside cleaning of

    one half of the condenser with the turbine capable of generating a minimum of fifty percent

    (50%) of its full load capacity.

    4.2.5 Cooling Water System

    Cooling water for the steam turbine condenser(s) shall be supplied using a once through (or

    circulating) sea water cooling system equipped with necessary intake screens, screen cleaning

  • Annex C page 23

    and debris removing devices, circulating water pumps, piping, valves, controls, and auxiliaries.

    A chlorination system is to be provided if required.

    An auxiliary (closed circuit) fresh water cooling water system shall be provided for cooling

    turbine auxiliaries and other plant auxiliaries as required.

    4.2.6 Water Treatment Plant

    A desalination plant with one hundred percent (100%) redundancy shall be provided to meet the

    Plant demand for raw water for steam cycle makeup, auxiliary cooling, service water, fire water,

    potable water (if desired) and all other Plant water requirements. A pre-treatment system and a

    demineralizer are anticipated. The SELLER shall provide a Raw Water Storage Tank with a

    total capacity equal to at least twenty-four (24) hours of maximum water consumption by the

    Plant plus firewater storage required to meet the National Fire Protection Association (NFPA)

    and the local fire code requirements. Firewater storage refill requirements shall meet NFPA

    requirements. Fire fighting for the coal unloading and storage facilities shall be provided by the

    SELLER.

    4.2.7 Water Treatment Plant

    The SELLER shall provide wastewater treatment for the Plant to ensure that any water

    discharged from the Plant meets the Laws of Indonesia.

    4.2.8 Ash Disposal

    For the ash storage area, the clearing and grading will follow existing ground level. Only a small

    portion (5 years) of the total ash storage area will be prepared initially. The SELLER will

    operate and maintain the ash disposal system and land fill compliant with all applicable

    environmental regulations.

    An impervious layer shall be installed to prevent ash storage area runoff from entering the

    ground water. Appropriate wells will be installed to monitor the ground water. Fugitive ash dust

    from the ash disposal area will be controlled in an environmentally benign manner.

    4.3 ELECTRICAL PLANT AND SYSTEMS REQUIREMENTS In order to meet PLN dispatch requirements, the Plant shall be designed to meet, as a minimum,

    the technical limits described below and the requirements of the Java-Bali Grid Code and PPA

    Appendix I: Interconnection Points and Electrical Interconnection Facilities and PPA Appendix

    B: Technical Limits.

    4.3.1 Frequency Limits

    The Plant shall be capable of operation at frequencies as defined in the Java-Bali Grid Code,

    reproduced in Table 4.1: Frequency Limits, below.

  • Annex C page 24

    Table 4.1: Frequency Limits

    Frequency Range (Hz) Operation Condition

    49.0 to 51.0 Hz Continuous Operations

    48.0 to 49.0 Hz Twenty (20) minutes

    47.5 to 48.0 Hz Ten (10) minutes

    51.0 to 52.0 Hz Ten (10) minutes

    At 47.5 Hz Immediate trip

    At 52.0 Hz Immediate trip

    For further information, see Java-Bali Grid Code

    4.3.2 Voltage Limits/Current Limits

    Power station and system voltages shall be selected from IEC 60038 and conform to the existing

    voltages currently used by PLN, and shall be capable of operating over the range 5 % of the

    nominal voltage at 500 kV, as per the Java-Bali Grid Code.

    4.3.3 Generators

    Each generator shall comply with IEC 60034, the Java-Bali Grid Code, and PLN requirements.

    Generator and exciter windings shall possess insulation that is non-hydroscopic and of Class F

    type complying with IEC 60085, but having a temperature rise not exceeding that of Class B

    under any operating condition within the specified output.

    Generators must be able to receive and respond to Automatic Generation Control (AGC) signals

    from the Java Load Dispatch Center.

    Quality of the generators and accessories shall be in accordance with the requirements of ISO

    9001, EN 29001 or BS 5750 Part 1 and other similar equivalent international quality standards.

    Anti-condensation heaters shall be provided for the air circuits, generator windings, and

    excitation system and control cubicles. Heaters shall be capable of maintaining the air

    temperature above the dew point to prevent condensation. These heaters shall automatically

    switch on when the generator is taken out of service.

    Temperature detectors shall be provided to monitor the maximum operating temperature of the

    generator.

    The generators shall be capable of supplying their rated power within 49.0 Hz and 51.0 Hz and

    5% of nominal rated voltage within the power factor range 0.85 lagging and 0.90 leading.

  • Annex C page 25

    4.3.4 Excitation System

    Each Generating Unit must be equipped, in accordance with the Grid Code, with:

    a. Fast-reacting governors that have effect on System frequency primary governors

    in the range of 48.5 Hz to 51.0 Hz. Each Generating Unit must be able to receive

    Automatic Generating Control (AGC) signals from dispatches in Load Dispatch Centers

    to enable System frequency secondary regulation.

    b. Fast-reacting automatic voltage regulators (AVR) for regulating generator

    terminal voltage in the range of operations of the generating units without resulting in

    instability; and MVAR Limiter (under/over excitation limiter).

    c. Power system stabilizer (PSS).

    Manual excitation control facilities shall be provided as a backup to the automatic

    control, and shall have an adequate range to allow for control of excitation for testing

    purposes. A true null balance shall be provided to allow for smooth excitation transfer

    between manual and automatic control.

    4.3.5 Power, Startup and Auxiliary Transformers

    The SELLER shall provide generator step-up, startup and auxiliary transformers for Plant

    service, including all protection, bus bars, and disconnect switches as required, and transformers

    for all auxiliaries. It is expected that a startup transformer or a generator circuit breaker will be

    provided to allow energizing of unit auxiliary equipment while the unit is out of service. The

    Generator Step up Transformer shall be equipped with an on-line tap changer, 5% over and 5%

    below limits, and shall be delta wound on low voltage side and solidly grounded wye wound on

    the high voltage side. See the Java-Bali Grid Code for further requirements.

    4.3.6 Control and Supervision

    Supervision/control, monitoring and information systems shall comply with PLNs system

    control concepts and procedures and will be subject to the approval of PLN.

    Automatic and manual synchronizing facilities, with such check facilities as are required shall be

    provided as a minimum for all circuits associated with generators.

    The Plant shall be provided with a centralized on-site Central Control Room so that operators

    can supervise the generators, perform switching and load dispatch. Also, a Distributed Control

    System (DCS) shall be provided to coordinate the control and supervision of the turbine

    generator control systems and power plant auxiliary systems. The DCS will have to meet the

    requirements of the Java-Bali Grid Code and PLN requirements regarding any interfaces with the

    500 kV switchyard and the SCADA/EMS systems of the Java Control Center.

    Generators must be equipped with fast reacting governors that have an effect on system

    frequency primary governors in the range of 48.5 Hz to 51.0 Hz. The generators must be capable

    of receiving and responding to (future) Automatic Generating Control (AGC) signals from

    dispatches in the Java Control Center to enable system frequency secondary regulation.

  • Annex C page 26

    The necessary data and information to be exchanged between the Plant and Java Control Center

    via the 500kV switchyard and SCADA/EMS systems of the Java Control Center includes but is

    not limited to the following list:

    No. Type of signals

    From the Plant

    Java

    Control

    Center

    1 Status of 500kV line circuit breakers X

    2 Status of 500kV grounding switches X

    3 Status of operated relay protection system of

    500kV

    X

    4 Measured signals of voltage, current, power

    and reactive power of all 500 kV lines

    X

    5 Measured signals of voltage, current, power

    and reactive power and tap changer positions

    of transformers

    X

    6 Measured signals of voltage, current, power

    and reactive power from the units

    X

    7 Measured signals of voltage of the bus bars X

    8. Measured signal of frequency X

    No. Type of signals

    To the Plant

    Java

    Control

    Center

    1 Raise/lower signals for controlling the unit

    outputs by either set point or pulses

    X

    2 Operation orders (open/close/trip) circuit

    breakers, disconnects grounding switches

    X

    4.3.7 Electrical Protection, Communication and Instrument Systems

    The SELLER shall provide a complete and comprehensive protection system for the

    generators/generator transformers/service transformers, transmission lines and the station

    electrical distribution systems. The SELLER shall undertake the installation of the protection

    relay panels within the control room, wiring between panels and switchyard equipment, and

    commissioning tests of the protection schemes. Protection will be coordinated with PLN.

    Transfer of electrical interface and control data between the Plant and the 500 kV switchyard

    shall be via RTUs or Fiber Optic. Ports shall be used to communicate with the 500 kV

    switchyard control room. The RTUs and Fiber Optic equipment shall comply with PLN

    configuration, features and functions. Communication, control, monitoring and voice channels

    will be provided between the power station and Java Control Center by the SELLER in

  • Annex C page 27

    consultation with PLN. Communication and SCADA signals shall terminate at the RTU and be

    in digital form. Telemetering and relay protection signals shall terminate in a Fiber Optic Panel.

    The following signals will be supplied to the 500kV switchyard control center in line with the

    SCADA Standard (note: provided in the Data Room).

    Status data:

    1. Protection system data for step up transformer bays

    a. Generator synchronizing circuit breaker status signals

    b. Over current relay signals

    c. Breaker failure relay signals

    2. Protection system data for overhead lines, if any:

    a. 500 kV circuit breaker, if any, status signals

    b. Breaker failure relay signals

    c. Line protection relay signals

    3. Bus bar protection

    a. Differential relay signals

    b. Circuit breakers status of the 500 kV switchyard

    Analog Data:

    1. Net power flow in MW, at the Delivery Point

    2. Reactive power flow in MVAR, at the Delivery Point

    3. Voltage in kV at the Delivery Point

    4. Frequency in hertz at the Delivery Point

    SCADA, communication, telemetry, fiber optic terminal, and teleprotection equipment will be

    supplied and installed by the SELLER and shall be compatible with PLN equipment and

    systems. The wiring of all signaling and control circuits required for the system shall be cabled

    out to interface marshalling cubicles by the SELLER. The SELLER shall supply and install

    necessary cabling and cubicles.

    The SELLER shall provide telecontrol facilities and information to the Java Control Center as

    required by the Java-Bali Grid Code, the PLN SCADA Standard and the agreement with PLN.

  • Annex C page 28

    4.3.8 Power Tariff Metering

    Power tariff metering shall be provided at the 500 kV side of the generator transformers and

    startup transformer for export and import metering. The Primary Metering System and Backup

    Metering System shall be provided and tested by the SELLER in accordance with the PPA

    Appendix K.

    The Primary and Backup Metering Systems shall use separate CTs and PTs. The tariff meters

    shall have separate facilities for recording the net inflow to the Plant and net outflow of energy

    from the Plant, and the aggregate of these parameters. This information shall be available for

    transmission to remote locations via the communication circuit between the 500-kV switchyard

    and the Java Control Center.

    The following class of Metering Transformers shall be provided as a minimum for each circuit,

    which has to follow the requirements of the Java-Bali Grid Code:

    Class 0.2 current transformers (three phases)

    Class 0.2 voltage transformers

    A three phase energy meter of Class 0.2, multi-tariff, two directions, capable to integrate to remote measuring data acquisition system, having

    provisions for local monitoring and remote monitoring, and complete with

    impulse output Plant and maximum demand Plant to record watt-hours

    and watts,

    A three phase integrating energy meter of Class 0.2, complete with impulse output facilities connected to read var-hours

    The tariff metering scheme shall have an overall accuracy of 0.3% for watt-hour and watt

    metering and 1.0% for var-hour metering.

    Separate summators shall be provided, if required, for the total Plant export and import MWh

    and MVarh.

    4.3.9 500 kV switchyard

    The outdoor 500 kV switchyard will include two outgoing 500kV circuits and two incoming

    500kVcircuits and will be configured with two bus bars and three circuit breakers for each feeder

    bay in a breaker and one half configuration. Details of the required arrangement and

    requirements by PLN to be used by the SELLER in its design and configuration of this

    switchyard are shown on the 500kV switchyard electrical one-line diagram shown in the attached

    Figure 4.3: Configuration of GITET Mandirancan with the Introduction of PLTU Central Java.

    The configuration shall ensure a continuous power supply when any circuit breaker needs to be

    removed from service for maintenance or repair. The provisions shown in Figure 4.3 for a future

    third transmission line and its future interconnection in the 500 kV switchyard (Electrical

    Interconnection Facilities) and its interconnection in the new Special Facilities substation are not

    included in the Scope of Supply of the SELLER.

  • Annex C page 29

    4.3.10 Construction Power

    Construction power will be available local to the site from PLNs 20 kV system in accordance

    with the provisions of the PPA. The SELLER will provide and install its own transformers.

    4.3.11 Special Facilities

    The Special Facilities shall include one row of transmission towers strung with double circuit

    500kV transmission lines; foundations; protection and operational relays and components,

    insulators and fittings, static line and communications lines and all other components necessary

    to connect from the Plants Interconnection Facilities to the existing 500 kV transmission system

    in accordance with Appendix I. The Special Facilities shall include a substation, located by the

    SELLER on the Special Facilities Site near the existing 500 kV transmission system. SELLER

    shall perform the tie in between the substation and the existing 500kV lines, including provision

    of turning towers and reinforcement of existing towers, if necessary.

    Sellers Scope of Supply for the substation shall include provision of connections from

    interconnecting towers and four breaker and a half bays which are located within the substation

    so as to permit the future expansion of the substation as shown schematically in the document

    entitled BASIC DESIGN 500KV TRANSMISSION LINE AND 500KV SUBSTATION FOR

    SPECIAL FACILITIES AND INTERCONNECTION FACILITIES OF CENTRAL JAVA

    STEAM POWER PLANT 2X1000 MW". That document is included in the Data Room and

    includes a single line diagram and specifications for the substation, transmission lines, towers

    and protective relays to be followed by the SELLER in design and construction of the Special

    Facilities. The second row of transmission towers shown in the original attachment of that

    document is not required and is not in the Scope of Supply of SELLER. A new single line

    diagram replacing the original attachment is included in the Data Room. The title of the new

    diagram is KONFIGURASI SISTEM PLTU JATENG 2X1000 MW DAN TRANSMISI &

    SWITCHING STATION TERKAIT, revision version of REVISI 1: DIV EDT PLN PUSAT,

    TGL 03 JANUARI 2011.

    4.4 CIVIL REQUIREMENTS

    4.4.1 General

    The Civil Works shall be designed to have a minimum working life of forty (40) years before

    any significant repair or replacement of the main structural elements and secondary structural

    elements/cladding is required. Applied coatings shall have a design life to first maintenance of

    ten (10) years minimum. All construction will comply with all codes, standards, and licensing

    requirements for such facilities

    4.4.2 Site and Special Facilities Site Conditions

    The SELLER shall carry out its own detailed topographical, hydro-geological and soil

    investigations, and fund other investigations as it deems necessary.

    The SELLER shall be responsible for arranging for the supply of all Site services such as power,

  • Annex C page 30

    potable water, temporary sewage treatment facilities, laydown areas, camp facilities, telephone

    or other communications equipment that may be required during the construction of the Plant.

    Should the SELLER wish to provide accommodation facilities for the Plant operating staff, it

    shall submit details of these facilities together with the space requirements, with its Proposal.

    The SELLER will note in the proposal any additional land required for Plant staff housing. The

    accommodation facilities shall comprise permanent buildings constructed to appropriate

    standards and shall be compatible in quality to other buildings in the Plant.

    4.4.3 Site Levels

    The Site shall be raised out of the flood plain by the SELLER if required.

    The catchment drainage system shall be designed to ensure the drainage of surface water from

    the area of Plant with a flood frequency of 1% (100 year storm).

    4.4.4 Foundation Philosophy

    The entire foundation system shall be designed such that it will ensure the proper and due

    performance of the Plant and afford adequate protection against the effects of any long term

    settlement, against seismic activity, and against periodic flooding of the area.

    4.4.5 Engineering Design

    The design of all facilities shall be to an approved internationally recognized set of standards and

    codes, including those identified in Article 3.4 of this Appendix and shall also satisfy all

    applicable Indonesian standards. The designs shall be to an acceptable standard of professional

    competence and shall represent a safe, efficient use of materials to produce the required facilities.

    4.4.6 Design Loadings

    The design for each Plant shall incorporate the worst load combination taking into account the

    following criteria where applicable:

    a) Dead Loads - all loads arising from the mass of materials making up the

    permanent works.

    b) Live Loads - all superimposed loads arising from station operations,

    testing, traffic, cranes, storage of liquids and the like. These shall be

    derived from approved standards and shall represent a minimum load to be

    taken.

    c) Wind loads shall be calculated in accordance with the Indonesian Building

    Codes or other approved internationally recognized standard. All

    buildings, structures and equipment exposed to wind are to be designed for

    a basic wind velocity of 100 km/h (62.1 mph) per ANSI A58.1, Exposure

    Type D or approved equivalent.

  • Annex C page 31

    d) Road Loading - the design of the roads shall be satisfactory for the

    maximum load anticipated during both the construction and operational

    period of the Project.

    e) Seismic Loading - the design seismic lateral forces shall be calculated

    either by the Equivalent Static Force method, or by the Dynamic Response

    Method, based on the requirements of the Indonesian Building Codes

    supplemented as required by Uniform Building Code (UBC) 1997 as a

    minimum, or other approved internationally recognized standard.

    4.4.7 Materials

    Materials shall be durable and fit for purpose. Materials for external surfaces shall be selected

    for aesthetic qualities and proven durability to withstand all climatic conditions likely to be

    experienced, ease of maintenance and economy of cost. Reasonable endeavors shall be made to

    create as pleasant a working environment as is practical for the staff working in the buildings of

    the Plant.

    4.4.8 Workmanship

    All workmanship shall be in accordance with accepted international practice to ensure the Plant

    is fit for the purpose and will be serviceable for the design life of the Plant.

    4.5 ENVIRONMENTAL REQUIREMENTS The Project shall comply with the environmental requirements of the Laws of Indonesia,

    including Law No. 32 of 2009, Concerning Environmental Management and any requirements of

    the Finance Parties.

    The Winning Bidder must prepare and submit an Environmental Impact Assessment (AMDAL),

    in accordance with the Environmental Assessment Regulation, Government Regulation No. 51,

    1993, and Government Regulation No. 27, 1999, or any successive applicable legislation or

    regulation, which demonstrates that the Plant will produce impacts that are minimal and within

    an acceptable range, as well as meeting all of the Laws of Indonesia. The EIA shall include, but

    not be limited to:

    (i) identification of the existing social and physical conditions that may be

    affected by the construction of the Plant;

    (ii) identification of the existing land, air, water and solid waste environmental

    conditions and parameters;

    (iii) definition of permissible environmental conditions and parameters

    applicable to the Plant, including legislation and regulation;

    (iv) identification of the areas (if any) where the initial proposed design for the

    Plant would not meet the required criteria;

    (v) analysis of the suitability of any design modifications (if needed) proposed

    by the Winning Bidder;

  • Annex C page 32

    (vi) identification of permits and licenses required to comply with the

    environmental requirements prior, during and after construction and

    commissioning of the Plant, and

    (vii) specification and design of the monitoring programs that shall ensure that

    the Plant shall comply, in the future, with the permissible environmental

    standards.

    Prior to commercial operations, the SELLER shall carry out the necessary tests to insure

    that the Plant shall comply with the applicable environmental standards (both Indonesian

    and lender requirements to be met). It is noted here that once the Special Facilities have

    been handed over to PLN, only the applicable Indonesian standards will apply under the

    PPA.

    4.5.1 Exhaust Gas Emissions and Air Quality

    Exhaust gas emissions shall not exceed the emission rates allowed by Indonesian Standards, or,

    if more stringent, the requirements of the Finance Parties. These requirements apply under all

    normal operating conditions.

    The required air quality should be maintained by controlling emission limits and selecting

    appropriate stack height, stack gas exit velocity, and exhaust gas temperature.

    The SELLER shall be required to provide continuous emission monitoring for each stack, as

    required by the regulatory authorities.

    4.5.2 Effluent Discharges

    Effluent discharges shall not exceed the discharge limits for industrial/power plant effluents

    specified by the Laws of Indonesia and any requirements of the Finance Parties.

    4.5.3 Noise Emissions

    The operational noise emissions from the Plant at the Site boundary should not exceed the

    ambient noise criteria or limits for industrial areas specified by the Laws of Indonesia and any

    requirements of the Finance Parties.

    These limits should be maintained as an absolute requirement under all ambient conditions

    during normal power plant operation.

    In order to ensure a safe and satisfactory working environment a sound pressure level of 85 dB

    (A) should not be exceeded at 1.0 m from the equipment. In addition, compliance should be

    made with all statutory and other mandatory noise limitation criteria applicable to the Project.

  • Annex C page 33

    5. QUALITY ASSURANCE, INSPECTION, COMMISSIONING AND TESTING

    5.1 GENERAL The SELLER shall implement a quality assurance program for the Project and ensure that all

    work undertaken on the Project throughout the design, construction, commissioning, operation

    and maintenance of the Plant comply with the terms of a National or International Assurance

    Standard equal to ISO9001, and provide evidence of meeting this requirement.

    The whole of the works shall be tested in accordance with the standards adopted for the Project

    and SELLERs quality plans and testing procedures as further described in Appendix J

    5.2 SCOPE OF TESTS

    SELLER shall be required to perform the tests required in Appendix J of the PPA in addition to

    those which the SELLER would normally perform to ensure equipment quality and Plant

    reliability. Testing requirements include:

    Tests during manufacture

    Tests during construction and erection

    Tests upon completion of construction (including, as a minimum, Functional tests, PPA Tests, Performance and Plant Reliability Tests)

    Tests required under any other project agreement

    Requirements for tests, inspections, PLN witness, reports and PLN approval are more fully

    detailed in Appendix J.

    6. SITE DESCRIPTION

    6.1 SITE LOCATION AND REQUIREMENTS Characteristics of fifteen potential sites that have been identified and evaluated by PLN are

    presented in the Site Reconnaissance Study (available in the Data Room). However, the

    SELLER may select a different site, if it so chooses, which meets site suitability requirements for

    this Project.

    The selected site is to be within 15 km of the PLN 500kV Grid. The Site is to be located on the

    north coast of Pemalang area, Central Java Province, between Tegal (to the west) and Kendal (to

    the east) and new 500 kV transmission lines from the Plant (part of the Special Facilities) which

    will interconnect with the existing PLN 500kV grid via a new substation (included by SELLER

    with the Special Facilities) as shown in Figure 6-1. Site area requirement for the Project is

    expected to be about 250 hectares. The selected site shall be sufficiently large to accommodate

    the expansion of the Plant to include a third generating unit.

    Within the Site area, the SELLER must develop the proposed Plant layout taking into

    consideration the area (m2) allotted for the Plant including, water storage facilities, coal, ash and

    limestone handling and storage, and the general layout of buildings, mosque, facilities and

  • Annex C page 34

    equipment. The Electrical Interconnection Facilities will be contiguous with the Site. The final

    Plant arrangement will be coordinated with PLN and subject to PLN approval. The layout and

    orientation of the Electrical Interconnection Facilities shall be able to accommodate associated

    outgoing 500 kV transmission line.

    The Special Facilities Site shall be determined by the SELLER and shall comply with PLN

    design, construction and electrical safety requirements. Interconnection points between the

    Electrical Interconnection Facilities and the Special Facilities and also between the Special

    Facilities and the existing 500 kV transmission system shall be clearly noted on drawings

    prepared by the SELLER and shall be subject to PLN approval. Schedule for testing and

    commissioning of the Special Facilities shall be approved by PLN prior to the start of

    construction