3-1. estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose...

21
S preadsheet Problem Type ofC ontract M arkup C ontractP rice 1. Lum p sum M = (R +R 1 )E B = (1 + R + R 1 )E 2. Unitprice M = (R +R 2 )E B = (1 + R + R 2 )E 3. C ostplus fixed % M = RA = RE B = (1 + R )E 4. C ostplus fixed fee M = RE B = (1 + R )E 5. C ostplus variable % M = R (2E -A)= R E B = (1 + R )E 6. Targetestim ate M = R E + N(E -A)= R E B = (1 + R )E 7. G uaranteed m axim um price M = (R +R 3 )E B = (1 + R + R 3 )E Type ofC ontract M arkup C ontractP rice 1. Lum p sum =(0.1+0.02)*6000 =(1+0.1+0.02)*6000 2. Unitprice =(0.1+0.01)*6000 =(1+0.1+0.01)*6000 3. C ostplus fixed % =0.1*6000 =(1+0.1)*6000 4. C ostplus fixed fee =0.1*6000 =(1+0.1)*6000 5. C ostplus variable % =0.1*(2*6000-6000) =(1+0.1)*6000 6. Targetestimate =0.1*6000+0.5*(6000-6000) =(1+0.1)*6000 7. G uaranteed m axim um price =(0.1+0.05)*6000 =(1+0.1+0.05)*6000 Solved Hom ew ork due 27-Feb-02 Original E stimated C ontract P rices (in $ thousands) A nalyze the follow ing construction project,com paring the relative costs of each of the seven contracts types presented in class. The contractor's original estim ate is $6,000,000, and the m arkup percentages are: R = 10% , R 1 = 2% , R 2 = 1% , and R 3 = 5% . The shared savings factoris .5. D eterm ine the contractor's m arkup and the original contract price (B )foreach of the contract types. Original E stimated C ontract P rices U niversity ofD elaw are D epartm entofC iviland Environm entalEngineering C onstruction M ethods & M anagem ent C IEG 467/667-012

Upload: blanca-goodenow

Post on 15-Dec-2015

244 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

Spreadsheet Problem

Type of Contract Markup Contract Price

1. Lump sum M = (R+R1)E B = (1 + R + R1)E

2. Unit price M = (R+R2)E B = (1 + R + R2)E

3. Cost plus fixed % M = RA = RE B = (1 + R)E

4. Cost plus fixed fee M = RE B = (1 + R)E

5. Cost plus variable % M = R(2E - A) = RE B = (1 + R)E

6. Target estimate M = RE + N(E - A) = RE B = (1 + R)E

7. Guaranteed maximum price M = (R+R3)E B = (1 + R + R3)E

Type of Contract Markup Contract Price

1. Lump sum =(0.1+0.02)*6000 =(1+0.1+0.02)*6000

2. Unit price =(0.1+0.01)*6000 =(1+0.1+0.01)*6000

3. Cost plus fixed % =0.1*6000 =(1+0.1)*6000

4. Cost plus fixed fee =0.1*6000 =(1+0.1)*6000

5. Cost plus variable % =0.1*(2*6000-6000) =(1+0.1)*6000

6. Target estimate =0.1*6000+0.5*(6000-6000) =(1+0.1)*6000

7. Guaranteed maximum price =(0.1+0.05)*6000 =(1+0.1+0.05)*6000

Solved Homework due 27-Feb-02

Original Estimated Contract Prices (in $ thousands)

Analyze the following construction project, comparing the relative costs of each of the seven contracts types presented in class. The contractor's original estimate is $6,000,000, and the markup percentages are: R = 10%, R1 = 2%, R2 = 1%, and R3 = 5%. The shared savings factor is .5. Determine the contractor's markup and the original contract price (B) for each of the contract types.

Original Estimated Contract Prices

University of DelawareDepartment of Civil and Environmental Engineering

Construction Methods & ManagementCIEG 467/667-012

Page 2: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

Solved Homework due 27-Feb-02

Spreadsheet Problem

Analyze the following construction project, comparing the relative costs of each of the seven contracts types presented in class. The contractor's original estimate is $6,000,000, and the markup percentages are: R = 10%, R1 = 2%, R2 = 1%, and R3 = 5%. The shared savings factor is .5. Determine the contractor's markup and the original contract price (B) for each of the contract types.

Original Estimated Contract Prices

Type of Contract Markup Contract Price

1. Lump sum M = (R+R1)E B = (1 + R + R1)E

2. Unit price M = (R+R2)E B = (1 + R + R2)E

3. Cost plus fixed % M = RA = RE B = (1 + R)E

4. Cost plus fixed fee M = RE B = (1 + R)E

5. Cost plus variable % M = R(2E - A) = RE B = (1 + R)E

6. Target estimate M = RE + N(E - A) = RE B = (1 + R)E

7. Guaranteed maximum price M = (R+R3)E B = (1 + R + R3)E

Original Estimated Contract Prices (in $ thousands)

Type of Contract Markup Contract Price

1. Lump sum 720 6720

2. Unit price 660 6660

3. Cost plus fixed % 600 6600

4. Cost plus fixed fee 600 6600

5. Cost plus variable % 600 6600

6. Target estimate 600 6600

7. Guaranteed maximum price 900 6900

University of DelawareDepartment of Civil and Environmental Engineering

Construction Methods & ManagementCIEG 467/667-012

Page 3: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine is excavating sand and gravel

Bucket Fill Factor (average) = 0.95 (Table 3-2)

Load Factor = 0.89 (Table 2-5)

Page 4: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine is excavating sand and gravel

Bucket Loadbank = heaped volume x bucket fill factor x load factor

= 2.10 x 0.95 x 0.89 = 1.78 BCY

= 1.6 x 0.95 x 0.89 = 1.35 BCM

Page 5: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

3-3. A 2-CY (1.53 CM) dragline is being used to excavate a canal in common earth. The average swing angle is 70º, the average depth of cut is 8.9 ft. (2.7 m), and the job efficiency is 50 min/hr. Estimate the dragline’s hourly production in loose measure.

Page 6: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

Job efficiency = 50/60 = 0.83

Swing-depth factor = 1.06 (Table 3-9) (70º swing, 90% optimum depth)

2.73.0

% optimum depth = x 100 = 90%

8.99.9

90%x 100 =% optimum depth =

Ideal output = 230 BCY/hr (176 BCM/hr) (Table 3-7)

Optimum depth = 9.9 ft. (3.0 m) (Table 3-8)

Page 7: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

Production = ideal output x swing-depth x job efficiency

= 230 x 1.06 x 0.83 = 202 BCY/hr

= 176 x 1.06 x 0.83 = 155 BCM/hr

Page 8: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

3-5. An hydraulic excavator-backhoe is excavating the basement for a building. Heaped bucket capacity is 1.5 CY (1.15 CM). The material is common earth with a bucket fill factor of 0.90. Job efficiency is estimated to be 50min/hr. The machine’s maximum depth is of cut 24 ft (7.3 m) and the average digging depth is 13 ft (4.0 m). Average swing angle is 90º. Estimate the hourly production in bank measure.

Standard cycles/hr = 160 (Table 3-3)

% maximum depth = 1324

x 100 = 54%

% maximum depth = 4.07.3

x 100 = 54%

Page 9: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

Swing-depth factor = 1.08 (Table 3-3) (90º swing, 54% maximum depth)

Heaper bucket volume = 1.5 LCY or 1.15 LCM

Bucket Fill Factor = 0.90 (Table 3-2)

Job efficiency = 50/60 = 0.83

Load factor = 0.80

Page 10: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

Production (loose) = C x S x V x B x E

= 160 x 1.08 x 1.5 x 0.90 x 0.83 = 194 LCY/hr

194 LCY x 0.80 = 155 BCY/hr

= 160 x 1.08 x 1.15 x 0.90 x 0.83 x 0.80 = 119 BCM/hr

Page 11: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

3-6. A small hydraulic excavator will be used to dig a trench in soft clay (bucket fill factor = 0.90). The minimum trench size is 24” (0.61 m) wide by 6’ (1.83 m) deep. The excavator bucket available is 30” (0.76) wide and has a heaped capacity of ¾ CY (0.57 CM). The maximum digging depth of the excavator is 17.5’ (5.3 m). The average swing angle is expected to be 90º. Estimate the hourly trench production in LF (m) if the job efficiency is 50 min/hr.

30 112 27

x 6 x Actual volume/LF of trench =

= 0.55 BCY

= 1.39 BCM

or

Page 12: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

(Table 2-5)

Standard cycles/hr = 200 (Table 3-3)

Load factor = 0.77

% maximum depth = 6.017.5

x 100 = 34%

% maximum depth = 1.835.3

x 100 = 34%

Page 13: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

Swing-depth factor = 1.14 (Table 3-3) (90º swing, 34% maximum depth)

Heaped bucket volume = 0.75 LCY (0.57 LCM)

Job efficiency factor = 0.83

Trench adjustment factor = 0.92 (Table 3-5)

Bucket fill factor = 0.90

Page 14: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

= 200 x 1.14 x 0.75 x 0.90 x 0.83 = 128 LCY/hr

128 LCY x 0.77 = 99 BCY/hr

= 200 x 1.14 x 0.57 x 0.90 x 0.83 x 0.77 = 75 BCM/hr

Production (loose) = C x S x V x B x E

99

0.55Trench production = = 180 LF/hr

75

1.39Trench production = = 54 m/hr

Page 15: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

4-2. The tractor-scraper whose travel-time curves are shown in Figures 4-4 and 4-5 hauls its rated payload 4,000’ (1220 m) up a 5% grade from the cut to the fill and returns empty over the same route. The rolling resistance factor for the haul road is 120 lb/ton (60kg/t). Estimate the scraper travel time.

Effective grade:

120

20

60

10Haul = 5 + = 11%

11%=5 +Haul =

Page 16: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

Effective grade:

120

20

60

10

1%

Return = -5 + = 1%

Return = -5 + =

Haul time = 6.4 min (Figure 4-4)

Return time = 1.6 min (Figure 4-5)

Travel time = 8.0 min

Page 17: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

4-6. How many hours should it take an articulated wheel loader equipped with a 4 CY (3.06 CM) bucket to load 3,000 CY (2294 CM) of gravel from a stockpile into rail cars if the average haul distance is 300’ (91.5 m) one way? The area is level with a rolling resistance factor of 120 lb/ton (60 kg/t). Job efficiency is estimated at 50 min/hr.

Bucket fill factor = 0.95 (Table 3-2)

Bucket volume = 4.0 x 0.95 = 3.8 LCY

Bucket volume = 3.06 x 0.95 = 2.91 LCM

Basic cycle time = 0.35 min (Table 4-6)

Page 18: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

120

20 Effective grade = = 6%

60

10 Effective grade = = 6%

Travel time = 0.5 min (Figure 4-14)

Cycle time = 0.35 + 0.50 = 0.85 min

50

0.85224 LCY/hr Production = 3.8 x =

50

0.85 Production = 2.91 x = 171 LCM/hr

Page 19: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

5-1. The data in the accompanying table resulted from performing Modified Proctor Tests on a soil. Plot the data and determine the soil’s laboratory optimum moisture content. What minimum field density must be achieved to meet job specifications which require compaction to 90% of Modified AASHTO Density?

Page 20: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine
Page 21: 3-1. Estimate the actual bucket load in bank measure for a hydraulic excavator – backhoe whose heaped bucket capacity is 2.10 CY (1.6 CM). The machine

5-5. Estimate the production in compacted CY (CM) per hour of a self-propelled tamping foot roller under the following conditions: average speed = 5 mph (8.0 km/hr), compacted lift thickness = 6” (15.2 cm), effective roller width = 10’ (3.05 m), job efficiency = 0.75, and number of passes = 8.

16.3 x W x S x L x E

P

10 x W x S x L x E

P

CCY/hr

CCM/hr

Production = =

Production = =

16.3 x 10 x 5 x 6 x 0.75

8

10 x 3.05 x 8.0 x 15.2 x 0.75

P

Production = =

Production = =

458 CCY/hr

348 CCM/hr