3-dimensional views

11
3-Dimensional Views Existing spillway construction

Upload: diallo

Post on 25-Feb-2016

47 views

Category:

Documents


2 download

DESCRIPTION

3-Dimensional Views. Existing spillway construction. 3-Dimensional Views. First concrete pour inside spillway (summer 2013). 3-Dimensional Views. New concrete pier extensions (summer 2014). This work takes place “in the dry” behind a sheet pile cofferdam. 3-Dimensional Views. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: 3-Dimensional Views

3-Dimensional ViewsExisting spillway construction

Page 2: 3-Dimensional Views

3-Dimensional ViewsFirst concrete pour inside spillway (summer 2013)

Page 3: 3-Dimensional Views

3-Dimensional ViewsNew concrete pier extensions (summer 2014)

This work takes place “in the dry” behind a sheet pile cofferdam

Page 4: 3-Dimensional Views

3-Dimensional ViewsStoplogs are placed between piers & rest on new concrete sills

Once stoplogs are in place water levels can be returned to normal

Page 5: 3-Dimensional Views

3-Dimensional ViewsConstruction work taking place between 2015 and 2016

More concrete is poured in the

base of the spillway

Existing gate and bridge are removed

Page 6: 3-Dimensional Views

3-Dimensional ViewsConstruction work taking place between 2015 and 2016

Concrete rollaway slabs and most of upstream barrel arches are removed

Page 7: 3-Dimensional Views

3-Dimensional ViewsConstruction work taking place between 2015 and 2016

New concrete crest is poured

Page 8: 3-Dimensional Views

3-Dimensional ViewsConstruction work taking place between 2015 and 2016

Concrete overlay is placed over entire pier structure

Page 9: 3-Dimensional Views

3-Dimensional ViewsConstruction work taking place between 2015 and 2016

New bridge is constructed

Page 10: 3-Dimensional Views

3-Dimensional ViewsTobacco Spillway to be completed in 2016

New gate is installed and stoplogs are removed

Page 11: 3-Dimensional Views

3-Dimensional Comparison

Existing spillway Modified spillway