3.1 work measurement_time study_w4
TRANSCRIPT
-
8/10/2019 3.1 Work Measurement_Time Study_W4
1/28
-
8/10/2019 3.1 Work Measurement_Time Study_W4
2/28
7-2 Design of Work Systems
Work MeasurementWork Measurement
TIME STUDY
Standard time
Stopwatch time study
Historical times
Predetermined data
Work Sampling
-
8/10/2019 3.1 Work Measurement_Time Study_W4
3/28
7-3 Design of Work Systems
Historical ExperienceHistorical Experience
Relatively easy, convenient, and inexpensive
Not objective, unknown accuracy
Not recommended
-
8/10/2019 3.1 Work Measurement_Time Study_W4
4/28
7-4 Design of Work Systems
Labor processing standards are based onobserving worker doing task
Observe only a sample of work
Time StudiesTime Studies
Use average time & pace to set standard
Disadvantages
Requires a trained & experienced analyst Standard cannot be set before task is
performed
-
8/10/2019 3.1 Work Measurement_Time Study_W4
5/28
7-5 Design of Work Systems
The Eight Steps to Conducting aThe Eight Steps to Conducting aTime StudyTime Study
1. Define the task to be studied (after a methods
analysis)
2. Break down the task into precise elements
.
must be measured
4. Record the times and ratings of performance for
the task elements[Rating = (Observed rating / standard rating)]
(*Rating = assessment of a worker relative work rate based on observers
observation compared with standard pace.)
-
8/10/2019 3.1 Work Measurement_Time Study_W4
6/28
7-6 Design of Work SystemsThe Eight Steps to Conducting aThe Eight Steps to Conducting aTime StudyTime Study -- continuedcontinued
5. Compute the average observed cycle time (elementtimes adjusted for unusual influences)
6. Compute the normal time for each task element
Normal time = (Average actual cycle time) x (Rating factor)
-
8/10/2019 3.1 Work Measurement_Time Study_W4
7/28
7-7 Design of Work Systems
7. Sum the normal times for each element to
develop a total normal time for the task
The Eight Steps to Conducting a TimeThe Eight Steps to Conducting a Time
StudyStudy -- continuedcontinued
.
Standard time =Total normal time
(1- Allowance factor)
-
8/10/2019 3.1 Work Measurement_Time Study_W4
8/28
-
8/10/2019 3.1 Work Measurement_Time Study_W4
9/28
-
8/10/2019 3.1 Work Measurement_Time Study_W4
10/28
7-10 Design of Work Systems
Direct Time Study (Example)Direct Time Study (Example)
Element Cycle 1 Cycle 2 Cycle 3 Cycle 4 Cycle 5 Average Normal
time
Std
time
1 8 9 8 10 8 8.6 9.46 11.129
2 10 12 10 11 12 11 12.1 14.235
3 25 25 25 25 25 25 25 25
4 8 8 6 8 6 7.2 7.92 9.318
Element 1:
Average time = (8+9+8+10+8)/5 = 8.6 sec
Normal time = Average time x Rating = 8.6 x 1.1 = 9.46 sec
Standard time = Normal time /(1-allowance) = 9.46 / (1-0.15) = 11.129 sec
Total Standard Time = 11.129+14.235+25+9.318 = 59.682 sec/product
-
8/10/2019 3.1 Work Measurement_Time Study_W4
11/28
-
8/10/2019 3.1 Work Measurement_Time Study_W4
12/28
7-12 Design of Work Systems
-- Example 2Example 2 --
Work Elements Cycle 1 Cycle 2 Cycle 3 Cycle 4
1 0.22 0.26 0.25 0.23
2 0.15 0.18 0.15 0.16
3 0.90 1.10 1.04 1.00
4 0.72 0.80 0.76 0.68
study. The worker is rated at 108%. The allowances are 5% for fatigue, 6% for delay,and 6% for personal relief. The workers salary is RM1000 per month.
a) Compute the total assembly standard time for the assembly process.
b) If the demand is 100,000 unit per month, estimate the number of operators
required for the assembly process. The company is operating 24 days per monthand a single 8 hour shift per day.
c) If the company can only manage to employ 18 workers, compute the over time
cost per day for each workerfor the production of 100,000 units per month.
Assume only 15 workers are available for over time and the over time pay rate is 1.5times of the normal wage.
-
8/10/2019 3.1 Work Measurement_Time Study_W4
13/28
7-13 Design of Work Systems
Solved ProblemSolved Problem
Element Cycle 1 Cycle 2 Cycle 3 Cycle 4 Average Normal
Time
Std
Time
1 0.22 0.26 0.25 0.23 0.24 0.259 0.312
2 0.15 0.18 0.15 0.16 0.16 0.173 0.2083 0.90 1.10 1.04 1.00 1.01 1.091 1.314
4 0.72 0.80 0.76 0.68 0.74 0.799 0.963
min/unit2.7970.9631.3140.2080.312TimeStandardAssemblyTotal
min312.017.01
1259.0
Allowance-1
1xTimeNormalTimeStandard
min0.2591.08x0.24RatingxTimeAverageTimeNormal
min24.04
0.230.250.260.22TimeAverage
=+++=
=
==
===
=+++
=
-
8/10/2019 3.1 Work Measurement_Time Study_W4
14/28
7-14 Design of Work Systems
Solved ProblemSolved Problem
min520,11
min602481operator1oftimeWorking
(b)
==mthhrmth
day
day
hr
b) If the demand is 100,000 unit per month, estimate the number of
operators required for the assembly process. The company is operating 24
days per month and a single 8 hour shift per day.
2524.28
mth
unit4118.70
mth
unit100,000
operatorperCapacity
DemandMonthlyrequiredoperatorsofNumber
mth
unit4,118.70
unit
min2.797
min520,11operator1byproducedquantityMonthly
===
== mth
-
8/10/2019 3.1 Work Measurement_Time Study_W4
15/28
7-15 Design of Work Systems
Solved ProblemSolved Problem
unit
137,7418mth
unit4,118.70operators18byproducedquantityMonthly
(c)
units==
c) If the company can only manage to employ 18 workers, compute the over time
cost per day for each workerfor the production of 100,000 units per month.
Assume only 15 workers are available for over time and the over time pay rate is 1.5
times of the normal wage.
234.50min
014,3
min797.26.1077
day
unit1077.6producedtorequiredTime
6.1077
24
mth
unit25,863
shortagequantityDaily
mth
,,-,s ortagequant tyont y
day
hr
day
unitday
unit
day
unit
mth
day
==
=
==
== (monthly shortage, need OT)
-
8/10/2019 3.1 Work Measurement_Time Study_W4
16/28
-
8/10/2019 3.1 Work Measurement_Time Study_W4
17/28
7-17 Design of Work Systems
Labor standard is set using output and % oftime worker spends on tasks
Involves observing worker at random timesover a long period
Work SamplingWork Sampling
van ages Less expensive than time studies
Observer requires little training
Disadvantages Ineffective with short cycles
-
8/10/2019 3.1 Work Measurement_Time Study_W4
18/28
7-18 Design of Work Systems
Used for
Ratio delay studies
Setting labor standards
Work SamplingWork Sampling
Measur ng wor er per ormance
-
8/10/2019 3.1 Work Measurement_Time Study_W4
19/28
7-19 Design of Work SystemsThe Five StepThe Five Step
Work Sampling ProcedureWork Sampling Procedure
1. Take a preliminary sample to obtain an
estimate of the parameter value
2. Compute the sample size required
.
worker at appropriate times
4. Observe and record worker activities; rate worker
performance
5. Determine how workers spend their time (usually
as a percent)
-
8/10/2019 3.1 Work Measurement_Time Study_W4
20/28
-
8/10/2019 3.1 Work Measurement_Time Study_W4
21/28
7-21 Design of Work Systems
Work Sampling (Example)Work Sampling (Example)
Status Tally Sum Percentage
Productive IIIII IIIII IIIII IIIII IIIII IIIII IIIII IIIII I 41 41/45 = 91%
Idle IIII 4 4/45 = 9%
Work sampling studies were conducted for 6 consecutive days at a factory.
A total of 45 observations were made during the 8 hours working period for
each day. The number of units managed to be produced are 3000 units for 1
week. The factory is operating 6 days a week. The data above are included
with rating and allowance of 97% and 15%.
Compute the process standard time.
-
8/10/2019 3.1 Work Measurement_Time Study_W4
22/28
7-22 Design of Work Systems
Work Sampling (Example)Work Sampling (Example)
Status Tally Sum Percentage
Productive IIIII IIIII IIIII IIIII IIIII IIIII IIIII IIIII I 41 41/45 = 91%
Idle IIII 4 4/45 = 9%
min2880day6hr
min60
da
hr8n timeobservatioTotal ==
unit
min0.997
15.01197.091.0
unit3000min2880STTime,Standard
allowance1
1Rating]%Productive
outputTotal
n timeobservatioTotal[
STTime,Standard
=
=
=
-
8/10/2019 3.1 Work Measurement_Time Study_W4
23/28
7-23 Design of Work Systems
Tutorial 1Tutorial 1
Proses Description Average Time (min)
1 Manual 23
2 Manual 32
3 Automatic machine 9
4 Manual 8
Rating : 110%Allowance: 20%
(a) Compute the standard time for each process.
(b) If the company has no problem with the availability of manpower,recommend the maximum capacity for the factory for a 8 hour shift work.
-
8/10/2019 3.1 Work Measurement_Time Study_W4
24/28
7-24 Design of Work Systems
Tutorial 1Tutorial 1
Proses Description Average Time
(min)
Normal
time
Std Time
1 Manual
2 Manual
(a)
machine4 Manual
(b)
-
8/10/2019 3.1 Work Measurement_Time Study_W4
25/28
7-25 Design of Work Systems
Tutorial 2Tutorial 2
Emirates Consultant conducted a work sampling studies for 5 consecutive days at an
assembly factory. A total of 48 observations were made during the 8 hour working
period for each day. The data collected during the 5 day studies is illustrated in Table
1. The whole assembly process is operating on 5 working days per week, 95% rating
and the companys allowable allowances is 20%.
(i) Compute the standard time (min/unit) for the assembly process.
(ii) At peak demand period, the factory is normally required to produce 3,100 units per
. ,
overtime per day must be arranged in order to meet the peak demand.
Item Data
Total output over 5 days studies 2,500 unit
Assembly process at fast speed 35% of observationsAssembly process at moderate speed 45% of observations
Assembly process at slow speed 5% of observations
Production is stopped due to no operator 5% of observations
Production is stopped due to no material 10% of observations
-
8/10/2019 3.1 Work Measurement_Time Study_W4
26/28
7-26 Design of Work Systems
Tutorial 2Tutorial 2
TimeStd
n timeobservatioTotal
(i)
=
=
day
unit
wk
unit
hours8normalduringCapacity
DemandPeak
(ii)
=
=
-
8/10/2019 3.1 Work Measurement_Time Study_W4
27/28
7-27 Design of Work Systems
Tutorial 2Tutorial 2
day
min
hoursover timetheover time,dotoforcedareemployeesallIf
unit/dayshortageCapacity
=
=
day
hourovertimethen total
over time,foravailableareemployeesof60%onlygConsiderin
=
7 28 D f W k S
-
8/10/2019 3.1 Work Measurement_Time Study_W4
28/28
7-28 Design of Work Systems
END OF CLASSEND OF CLASS