31_well design workflow
TRANSCRIPT
Copyright 2009, NExT, All rights reserved
Well Design Workflow
Copyright 2009, NExT, All rights reserved
Objectives
At the end of this training session, you shouldbe able to:
List and Describe the 3 phases of the well design process– State the 7 Design Modules of the Well Design phase
• Describe the 7 Design Modules– Explain what we monitor in the Execution phase– Explain why we evaluate performance in the Evaluation phase
Copyright 2009, NExT, All rights reserved
Outline
3 Phases of the drilling engineering processPhase 1: Well Design– Design ModulesPhase 2: Well ExecutionPhase 3: Well EvaluationSummary
Copyright 2009, NExT, All rights reserved
Engineering Process
Phases
Evaluate Design
Execute
Copyright 2009, NExT, All rights reserved
Phase 1: Well Design
Copyright 2009, NExT, All rights reserved
Key Elements of Well Design
Standards, Policies and ProceduresDE responsibility to adherence for deliveryEngineering Standards (API)Policy manuals– casing design– well control– surveying including anti-collisionProcedure manual or guidelines– drilling operations– directional
Copyright 2009, NExT, All rights reserved
Well Design Process Flowchart
Well Design Flowchart
Obtain wellrequirements Data transfer procedure
Input & validate
Obtain specialdata for field Input & validate
data sets
Data transfer procedure
This phase of theprocess is dataacquisition andvalidation from
the client. Theremust be a recordmaintained of this
transfer toSchlumbergerObtain lithology,
fracture and porepressure data Input & validate
data sets
Data transfer procedure
There must be designstandards for :
ConductorSurface Casing
Intermediate CasingsProduction CasingProduction Liners
DesignCasing
Pressurecontainment?
Yes
No
Well lifeconsiderations
?
No
Yes
TrajectoryDesign
TrajectoryDesign
Select HoleSizes to
deliver CasingDesign
Determine profileconstraints:
surfacereservoir
wellbore stability
SurfaceCollision Risk ?
SurveyProgramme
Design
Well PlanWell Plots
Yes
NoCan
better SurveyProgramme remove
risk?
Yes
No
Areall well
positionalrequirements
met?
No
Well drilling plan
CementingDesign
Drilling Fluid
Confirmlegislation
requirements
Select MW frompore pressureand wellbore
stability
Drilling Fluidprogramme
T&D, Casing Wear andHydraulic study OK?
No
Completed WellDesign
Yes
MW andFrictionFactors
Drillingsystemdesign
Select bitand systemcombination
Design BHAdetails to giverequired DLS
Design Drillstring
Bit/BHA strategywith drillstring
Drillstringand BHA
Select TOCfor each holesection fromLOF basis
Determine TOTCfor isolationpurposes
Determinevolumes preflush,
spacer andcements then
produce pumpingschedule
Get specialistcontractor to
formulaterecipes
Cementingprogramme
Copyright 2009, NExT, All rights reserved
Well Design Process
Casing Design
Data Gathering&
Validation
Trajectory Design
Survey Programme Drilling Fluids
Drilling SystemDesign
CementingDesign
CompleteWell Design
Start Finish
1
7
2 Re-iterate if needed
6
3 4 5
Copyright 2009, NExT, All rights reserved
Design Module 1
Data Gathering– Requires checklists – Requires client confirmation – Requires SLB QA
Copyright 2009, NExT, All rights reserved
Key Elements of Data Gathering
Data gathering and validation– checklist with client to gather data consistently– review results with client to confirm– demonstration of data used is vital to QA/QC process
• DE Checklists• Planning checklists• Positional accuracy• Internal sign off
Copyright 2009, NExT, All rights reserved
Design Module 2
Casing Design– Safety critical– Process must be formally recorded in a ‘Basis of Design’– Engineering involvement through Kick simulations, casing
wear affect on pressure ratings, running (T&D) and casing flotation
Copyright 2009, NExT, All rights reserved
Key Elements of Casing Design
Casing Design (including couplers)– Size range available with delivery times– Structural to take wellhead and environmental loads– Surface aquifer isolation to prevent pollution– Pressure containment– Kick tolerance– Metallurgy– Bending loads– Wear allowance– Burst / Collapse / Tensile safety factors
Copyright 2009, NExT, All rights reserved
Design Module 3
Trajectory Design– Well Plans produced according to a design process– ‘Basis of Design’ document detailing why selections have been
made.– Record of learning incorporated into BoD
Copyright 2009, NExT, All rights reserved
Key Elements of Trajectory Design
Trajectory Design– Surface collision avoidance– Dogleg limitations– Formation responses– Reservoir orientation and placement– Availability of tools to deliver profile ???
Copyright 2009, NExT, All rights reserved
Well Surveying and AC Policy
Applies globally to all aspects of Survey Management– Includes survey data and database management– Geometric well trajectory planning– Survey Quality assuranceIt will be strictly followed except in the case where:– An established client policy with a higher safety threshold
exists and is implemented– Where a written exemption is granted by the appropriate
authority
Copyright 2009, NExT, All rights reserved
Policy Responsibilities
Local Engineering manager – Responsibility for all well design activity, including SM– Responsible for technical integrity of any well design– Primary sign off authority Line Management– Ultimate accountability– Final signature on the well planMandatory for final well design delivered to client, sign off by:– Originator, DEC sign-off authority, D&M line mgt, client
Copyright 2009, NExT, All rights reserved
Classification of Well Types
Trajectory Planning Design– All wells classified as either “single” or “nearby wells”After global scan of definitive database if no other well within30,000 meters of its surface location– Treat as a single wellAll other wells classified as nearby wells
Copyright 2009, NExT, All rights reserved
Design Module 4
Survey Programme– The planned series of instruments to be used, surveying
requirements to be met during the execution of the well designProgramme designed to provide in the most cost effective and safe manner:– Achieve target sizing– Well position uncertainty for:
• Relief well purposes • Anti-Collision
Copyright 2009, NExT, All rights reserved
Design Module 4
Survey Programme– Drilling Target Size
• Geological target reduced by an amount representing the survey errors
– Close approach• Approved anti-collision policy and process, referencing the
correct ‘part’ of the programme at all depths– Redundant principle of survey program design– Survey Contingency Planning– Approved Error models
Copyright 2009, NExT, All rights reserved
Key Elements of Survey Design
Policy– redundant principle or exemption from clientClient– review their policies– confirm our software can manage client policyInstrument Error– rank preference (ISCWSA, Topographic, WdW, Simple)– understand 3d, 2d, 1d– understand sigma value
Copyright 2009, NExT, All rights reserved
Key Elements of Survey Design
Design– parts; correct part used for anti-collision at the right depths– what constitutes the definitive surveyOperation– instruments performing to specification– instruments run to programmed depths– contingency if hole deteriorates
Copyright 2009, NExT, All rights reserved
Key Elements of Survey Design
Quality– every survey is QA/QC’d– MWD is surveying– evidence is kept that tools have met performance criteria– failures are fully investigated– root causes of failures are identified– aim to GUARANTEE the definitive survey
Copyright 2009, NExT, All rights reserved
Design Module 5
Fluids Programme– Not internal to Oil Co normally– Major impact on T&D, hydraulics– Wellbore stability
• Not just hydrostatic pressure– Impact on downhole drilling systems
Copyright 2009, NExT, All rights reserved
Key Elements of Fluid Design
Drilling Fluid Design– Environment– Density > pore pressure and < fracture pressure– Rheology (hole cleaning and ECD)– Inhibition– Formation damage– Lubricity– Cost
Copyright 2009, NExT, All rights reserved
Design Module 6
Drillstring design and considerations– Integrity– T&D, hydraulics– Tapered strings– Rig capacity and sizing– ECD
Copyright 2009, NExT, All rights reserved
Key Elements of Drilling System Design
Drilling System Design– Maximise efficiency– Select right bit for each system– Process will identify critical components– Process will identify critical measurements– Accuracy of measurements will be specified– Drillstring design
Copyright 2009, NExT, All rights reserved
Design Module 7
Cementing Design– ‘Basis of Design’ document detailing why selections have been
made.– Record of learning incorporated into BoD– Practical involvement through drillouts (bit/BHA) sidetracking,
loss control, drillstring contamination
Copyright 2009, NExT, All rights reserved
Key Elements of Optimisation
Design Optimisation– Torque– Drag– Hydraulics– Casing WearIterative approach– if a problem arises we must have sufficient knowledge to
understand the problem before attempting to resolve it
Copyright 2009, NExT, All rights reserved
Well Execution Flowchart
Identifyprocess to
monitor
Data StoredData
recorded Data QA/QC'd
Reports
Is plan beingachieved?
Yes Is Datarecorded ?
No
Yes
No
Is allowabledeviationfrom plan
quantified?
Yes
No
Can plan bemodified within
limits?
Modify andinform ALL
partiesYes
No
Re-engineerfrom currentposition tonext target
Haltoperations
Normal QA/QCprocess to record
changes andlessons learned
Release newplan to ALL
parties
Non-ConformanceReport issued
Copyright 2009, NExT, All rights reserved
Well Execution
What do we monitor ?– Well integrity
• Casings on depth and sufficient kick tolerance to finish section– Deviation
• No collision issues• Can still get to target within Inc, Azi and DLS limits and driller’s
target still valid– Survey Programme
• All instruments perform to specification• All instruments are run to programmed depths
Copyright 2009, NExT, All rights reserved
Well Execution
What do we monitor ?Real time? – BHA performance
• Delivers expected DLS• Drills in time and cost effective manner
– Bit performance• ROP is as expected or better
– Mud• properties are within specification
– Logistics• All equipment for the well is available within delivery schedule
Copyright 2009, NExT, All rights reserved
Well Evaluation Flowchart
ProcessEvaluation
Review metricsfor each processDo performance
metrics exist ? Yes
No
Is theperformance of thisprocess assessed?
Yes
NoReport factual data
Data GatheringReview times to obtain dataReview data accuracy
Casing DesignCasing seat selection satisfactoryCasing w ear satisfactory
Trajectory DesignProfile drillableTorque and Drag predictionvalidation
Survey ProgrammeInstruments performanceQA/QC reports w rittenService performance
Drilling System PerformanceDLS w ithin criteriaWellbore tortuosity / Dif f icultyBit Selection review
Drilling FluidProblemsEnvironmental lossCost
CementingProblemsEnvironmental lossCost
Operations ReviewNon Productive Time and Cost
FailuresEff iciency review
Ft/Day$/Ft
LogisticsEff iciency review
Prepare metrics torepresent relevant
performance
Copyright 2009, NExT, All rights reserved
Well Evaluation
Why do we evaluate ?– To understand what happened– To improve our performance next time– To keep our customers satisfiedWhat do we evaluate ?– Metrics– Deviations from applied limits– Difficulty
Copyright 2009, NExT, All rights reserved
Summary
The 3 phases of the drilling engineering process are:Design – Execute – Evaluate
There are 7 Design modules in the Design Phase:1. Data Gathering2. Casing Design3. Trajectory Design4. Survey Programme5. Drilling Fluids Design6. Drilling System Design7. Cementing Design
Copyright 2009, NExT, All rights reserved
Analysis of Offset Wells
The main objectives of the offset well analysis are:– Identify all problem areas – Identify all events – Identify all good practices– Provide the necessary information to conduct a risk analysis– Measure performance for benchmarking– Identify constraints and areas of opportunity– Validate assumptions
Copyright 2009, NExT, All rights reserved
Relevant Offset Well
Guidelines for the identification of relevant offset wells:– Pick wells all around the target location– Pick the closest wells available– Old wells contain valuable information (original pressures,
drilling hazards, etc)– Recent wells are better for time analysis, bit selection, existing
pore pressure, etc.– Wells in close proximity to the new well but in different
structures or separated by faults can still yield valuable information
– Ideally, we are looking for geological similarity combined with geometrical similarity
Copyright 2009, NExT, All rights reserved
What Data Should be Reviewed?
Daily operations reportsDrilling fluids, cementing, casing reports.Composite log (mud loggers log)Drilling data Log (MD Totco, 6 pen geolograph, etc.)Open hole logs (e.g. Caliper, Gamma Ray, Resistivity, Neutron
Density, Sonic, etc.Cased hole logs (CBL-VDL, USIT, multi-finger calipers, etc.)Structure map showing location of offset wells (surface and subsurface) and location of proposed wells
Copyright 2009, NExT, All rights reserved
What Data Should be Reviewed?
Field map showing location of existing roads and existing padsEnd of Well ReportsSeismic sectionsBit RecordsPore and Frac pressure profilesTemperature Profiles
Copyright 2009, NExT, All rights reserved
Benchmarking and KPI’s
Requirement to benchmark against offset dataTechnical Limit Drilling
• Actual Time = Technical Limit + Waste (20-40%) + NPT(10-15%)
The Technical Limit is what could be achieved in a flawless operation using the best possible people, planning and technology
Copyright 2009, NExT, All rights reserved
Key Performance Indicators - KPIs
What are KPI’s– An analytical (metric) but continuous assessment of
performance at multiple levels within the organisationExists from the share holder to the bit!
Examples – non oilfield– GNP (Gross National Products)– Capita per head (measure of wealth)
Copyright 2009, NExT, All rights reserved
Performance Measurement Examples of Key Performance Indicators (KPI’s)
Days/10,000’Days/completion$ / Ft, ft / $$/completionQuartile rankingNPT for drlg/completion% NPT improvement% Flat time / drilling time$/BoeWell complexity
Days to top reservoirFootage per BHAFootage per dayFootage per 1000 circ hrNPT (contractors equipment, WOW)NPT/1000 ftNPT per 1000 circ hrEfficiency evaluationSlide/rotate ratios
Copyright 2009, NExT, All rights reserved
Analysis T - Plots
Inclination T-plot
0
1000
2000
3000
4000
5000
6000
70000 20 40 60 80
Inclination (deg)
Mea
sure
d D
epth
(m)
Planned inc As drilled inc
Azimuth T-plot
0
1000
2000
3000
4000
5000
6000
70000 100 200 300
Azimuth (deg)
Mea
sure
d D
epth
(m)
Planned azi As drilled azi
Copyright 2009, NExT, All rights reserved
Analysis T - Plots
Dogleg T-plot
0
1000
2000
3000
4000
5000
6000
70000 2 4 6
Dogleg (deg/30m)
Mea
sure
d D
epth
(m)
Planned dls As drilled dls
Tortuosity T-plot
0
1000
2000
3000
4000
5000
6000
70000 50 100 150 200
Total Curvature(deg)
Mea
sure
d D
epth
(m)
Planned tort As drilled tort
Copyright 2009, NExT, All rights reserved
Conclusions
So, now you should be able to:
List and Describe the 3 phases of the drilling engineering process– State the 7 Design Modules of the Well Design phase
• Describe the 7 Design Modules– Explain what we monitor in the Execution phase– Explain why we evaluate performance in the Evaluation phase
Copyright 2009, NExT, All rights reserved
End of Module