39 th updea general assembly tangier, morocco: october 30 th, 2007 presented by engr. amadou diallo...
TRANSCRIPT
39th UPDEA General Assembly Tangier, Morocco: October 30th, 2007
Presented by Engr. Amadou DIALLO
Secretary General, WAPP
WAPP Emergency Power Supply Security Plan
- 2 -
Presentation Outline
Background
Status of Power Supply in ECOWAS
Conclusions of Study
Recommendations of Study
Next Steps
- 3 -
Background
Scope of Study: Analyse electricity demand & supply balance in each state Review & comment on emergency plans and infrastructure Recommend Emergency Power Supply Plan for Member States
(Emphasis on regional solutions) Identify the required additional generating capacities and sites Propose the following:
Strategy, Implementation framework, Financing, and Roles of participants
- 4 -
Status of Power Supply in ECOWAS1:Supply Sources1
Half of the member states depend on Thermal sources for the majority of their supply.
Three (3) states depend on Hydro sources for majority of their supply.
Four (4) states depend on importsfor majority of their supply.
Actual Hydro
Actual Thermal
Import + Others
- 5 -
Status of Power Supply in ECOWAS2:Supply Sources2
Import + Others
5% Hydro31%Thermal
64%
- 6 -
661 688 3,004 1707,773
860 16 16 841
38,370
1,800 56 674-
10,000
20,000
30,000
40,000
50,000
GWh
Benin
Burkin
a Fas
o
Cote
d'Ivo
ire
Gambia
Ghana
Guinea
Guinea
Biss
au
Liber
iaM
ali
Nigeria
Seneg
al
Sierra
Leo
neTog
o
MetUnmet
Status of Power Supply in ECOWAS3:Demand-Supply Balance
Unmet46%
Met54%
- 7 -
Technical Causes Obsolete & unreliable equipment; Inadequate maintenance;
Operations inefficiencies; Insufficient Capacity; and, Non-availability of primary energy sources.
Financial Factors Low user tariffs; Low collection rates; and,
Inadequate financial standing of utilities.
Institutional Issues Planning & implementation responsibility; Bureaucracy in
decision-making; Sensitivity of tariffs to low income/wage levels; and, volatile petroleum prices limiting fuel purchases.
Status of Power Supply in ECOWAS4:Causes of Shortages
- 8 -
Initiatives based on Indigenous Resources
Hydro Guinea (Kaleta, Souapiti & Amaria) Liberia (Mano & St Paul River) Mali (Felou & Gouina) Kainji & Jebba Rehab. Nigeria (Mambilla)
Coal Nigeria
Petroleum Natural Gas
(Nigeria, Cote d’Ivoire & OMVS) Liquids
(Nigeria, Cote d’Ivoire)
Hydro Bumbuna Mount Coffee Bui Buyo
Coal Nigeria
Petroleum Natural Gas
(Nigeria, Ghana, Togo & Benin)
Liquids (All Member States)
Key National Initiatives Initiatives of Regional Significance
- 9 -
Criteria for Viable Regional Options
Economic Consideration: A viable sub-regional supply option must be economically cost
competitive (lower cost) when compared with local alternatives
Plant size: Capacity must exceed 100MW to have relevant export potential
Lead time: Implementation must preferably be less than 24 months
Compatibility with medium & long-term strategy Proposal must be consistent with the future needs of the sub-
region and use stable sources of fuel.
- 10 -
Criteria for Optimum Location of Facilities
Fuel Source Proximity to indigenous fuel sources, or Availability of adequate and stable fuel supply
Site Access and Facilities Road access for transportation of heavy plant and equipment Access to industrial infrastructure needed for plant operation
Interconnection opportunities for evacuation Proximity to load centers to reduce power transmission losses Availability of interconnection for export to neighboring states
Cooling water requirements Easy access to bodies of water suitable for plant cooling needs
- 11 -
Conclusions1
Generation needs of the sub-region are: Plants to produce Least Cost Power when operated at base load
to address power shortage situation of member states Plants to serve as Reserve under normal conditions to ensure
network reliability & security of supply. Plants to allow adequate Frequency Control/Regulation for the
successful synchronization of the networks in WAPP
Sub-regional generation projects that complement ongoing national initiatives are the best option for member states with significant interconnections.
- 12 -
Conclusions2
The order of merit for least-cost generation are: Coal-fired Steam Turbine Plants; where coal is available Natural gas-fired Combined Cycle plants; if gas is
available. Steam or Diesel plant fired with Heavy Fuel Oil
Possible locations for sub-regional plants are: Alagbado in Lagos, Nigeria Maria Gleta in Benin. Lome in Togo Tema in Ghana Aboadze in Ghana Abidjan (Vridi) in Cote d’Ivoire OMVS System
- 13 -
Conclusions3
Until power links are built to connect the 5 isolated member states, regional approach cannot be adopted. Only national initiatives can mitigate power shortages.
The rehabilitation of existing hydro plants for which large portions of capital costs are already sunk, such as Kainji and Jebba in Nigeria, and Mount Coffee in Liberia which has been vandalized, could bring into service the production capacity that has otherwise been unavailable at relatively low incremental cost.
The completion of the ongoing Bumbuna HEP would also bring into use a source of production that had hitherto not been available.
- 14 -
Recommendations
Build 3 plants at locations with access to natural gas. 400MW combined cycle plant at Maria Gleta in Benin. 400 MW combined cycle plant at Aboadze in Ghana. 150 MW combined cycle plant within OMVS.
Expedite implementation of the WAPP Priority Projects to upscale interconnectivity.
In interim, deploy steam or diesel capacity running on heavy fuel oil for non-interconnected states.
Accelerate completion of the rehabilitation of Kainji, Jebba and Mt. Coffee dams, and completion of the Bumbuna dam.
- 15 -
Rationale and Benefits
Economy-wide Benefits :- Poverty Reduction, Economic growth& Development
Direct Cost Savings :- Reduced cost of production for un-connected States
from the recommended local alternatives. Regional options provide least cost of supply.
Vital Ancillary Service to WAPP System :- Plants to provide Secondary Reserve Margin. Plants support network frequency control
Consistency with Objectives of Stakeholders :- Governments, Utilities, Development Partners and
Regional Bodies.
- 16 -
Next Steps of Plan -1-
Submit Plan to WAPP and ECOWAS authorities for adoptionImplement Near-term Mitigation Actions
Support where possible, initiatives already being pursued by individual Member States
Deploy in the interim, whilst the other more optimal actions are being pursued, mobile generating capacity running on suitable fuels for the non-interconnected states and for other member states with acute shortages.
Implement Optimum Strategic Actions Implement regional power plants. Could be through the creation of SPCs
under the framework of Public Private Partnerships. Implement pre-investment studies for remaining WAPP Priority
Interconnection Projects
Thank You for your Attention
WAPP Emergency Power Supply Security Plan