3d technical design td - rehau · 3d technical design - summary • uk based specialist heat...
TRANSCRIPT
3D TECHNICAL DESIGN LTD.
Always in Partnership
Heat Networks
De-risking the Civil Environment
&
Installation Cost Comparison
23rd March 2017
PRESENTATION CONTENTS
1. Introduction to 3D-Techncial Design.
2. Best Practice Route Proving/Development.
3. Buried Network Project Development/Planning.
4. Design and Installation Quality.
5. CAPEX considerations.
6. Installation Cost Comparison Study.
7. Any Questions.
3D TECHNICAL DESIGN - SUMMARY
• UK Based Specialist Heat Network – Buried Infrastructure Consultant.
• Practical Backgrounds of Designing, Delivering and Expanding City
Wide UK Schemes for over 15 years.
• Focused on the early de-risking of complex projects through:
• Technical and Commercial Feasibility
• Proving Routes and Major Infrastructure Crossings.
• Stakeholder Liaison.
• Detailed Network Design.
• GPR and 3D Modelling.
• Project Planning and Development
• Driving down CAPEX through early identification, mitigation and
management of risks, and establishing shallow and clear environments
within congested areas.
3D TECHNICAL DESIGN LTD.
COLLABORATIVE PARTNERSHIP STRUCTURE
Collaboration with a mature network of specialists across the Industry
District Energy
Project
Client
Contractor
Consultant
Reduce Network Costs
Improve Quality
Reduce Disruption
Risk Management
Detailed Planning
Accurate Tenders
Improved Safety
Technical Submissions
CURRENT UK MARKET/DESIGN PROCESS
Commercial and delivery process differs from Best Practice.
Contractor often prices and plans against a GA and available Service
drawings.
However, heat networks are almost always across areas of dense
services.
Significant volume of unknown/redundant buried services.
Aged utilities (cast iron water mains).
Non-Compliant with CDM regs 2015/ BIM II
Typically all-risk contracts (depth/welds/services).
Minimal due-diligence and planning prior to excavation.
Significant volume of mitred welds to overcome buried services.
Contractor undertakes their own QA of the installation.
As-built drawings are often incomplete.
CIBSE – BEST PRACTICE
HEAT NETWORK CODE OF PRACTICE
Best Practice includes obtaining and reviewing drawings of the existing
utilities and other record information in the area covered by the heat
network.
Determine additional barriers e.g. no space underneath certain roads due to
congestion of other utilities or opportunities e.g. the use of existing service tunnels,
basements etc.
This could be supplemented by undertaking ground penetrating radar
surveys to map existing services at critical points.
NETWORK DESIGN STAGE 1
FEASIBILITY SUPPORT
Heat Mapping & Energy Masterplan.
Identify Generation Source and Consumers
Route Option Appraisal.
OS Map,
Utility Drawings,
Desk Top Study
Identify Consents Required
Network Length
Risk Matrix Preferred Route Identified & Agreed with
Consultant and Client
GA with Utility Overlay
Early Cost Estimates
High Risk/Cost
Input from
Consultants
Output to
Stage 2
GA – ROUTE OPTIONS
• Starts from Energy
Masterplanning.
• Map Building Connections.
• Identify options and strategy
based on land rights
(highways/Public/Private Land).
• Assess Linear Route
Differences.
• Identify and measure alternative
routes.
C2 - UTILITY OVERLAY
• Overlay of all C2 (Utility Drawings)
• Inc. Gas, Elec, Water, Drainage, Data etc.
• Establishes Service Density to informs
route options
Highlights risks and observations such as:
• Age/likely condition on Asset.
• Nature of Asset (MDPE/Cast Iron)
• Size of Installation (11kv/ 33kv)
• Density of Chambers
• Significant density
ANNOTATED HISTORICAL
- OS MAP OVERLAYS.
Typically every 30 years, from
~1850 onwards
Identifies Legacy:
• Train/Tram
• Church/Burial
• Land use
• Structures
• Infilled Subways
• Industrial Contamination
• Historical Street Layout
• Canals
• Utility Infrastructure
ANNOTATED – CONCEPT DESIGNS FOR
MAJOR INFRASTRUCTURE CROSSINGS
• Rivers/Canal
• Bridges
• Rail/Tram
• Complex Junctions
• Roundabouts
• Motorways
• Interface close to protected
assets
NETWORK DESIGN STAGE 2
DESIGN DEVELOPMENT
Preferred Route
GA with Utility Overlay
GPR and Network Development.
GPR Drawing/Survey
GPR Modelling
Dimensioned route
Refined Expansion Strategy
Weld Positions
Approval to Commence 3D Design Modelling
GA of Detailed Network Route
Revised Cost Estimates and schedule of rates.
Risks can be minimized further
Input from
Stage 1
Output to
Stage 3
UTILITY DETECTION – GPR/EML
RED LINE DRAWING
• PAS 128
• Grid Size
reflective of
environment
• Topographical
Survey Area
DETAILED GA –
GPR AND TOPOGRAPHICAL SURVEY
• Weld Positions
• Chambers
• Alignment with
highways, trees,
structures.
• Accurate Trial
Hole Identification
• Coordinated and
informed decision
making
NETWORK DESIGN STAGE 3
3D MODEL AND CONSTRUCTION DRAWINGS
Detailed Route
GA of Detailed Route
GPR Model
Technical Consents Identified
3D Design and Modelling
Model Network Through Services
Finalise Expansion Strategy
Construction Drawings
Technical Submissions for Consents
Project Ready for Tender, Phasing and Programming
Tender pack with all construction drawings.
Accurate phasing.
Consents secured.
Programme Agreed.
Risks Managed and reflected in Contractor Pricing
Input from
Stage 2
Output to
Construction
CONSTRUCTION HAZID
• Evolves from Feasibility
Phase HAZID.
• Design Led.
• Project Specific.
• Developed throughout
the Design Process.
• Compliance with CDM
2015.
KEY BENEFITS OF DETAILED
UPFRONT 3D NETWORK DESIGN
Engineering and Contracting Best-Practice
Client (Often Local Authority): Reduced Network Costs and Programme.
Therefore - Scheme and connection viability improves.
Improved Operational Life - Reduced stresses and mitres.
QA measures in place for Contractor Performance.
Consultants: Complements existing skills in Heat Mapping, Energy Masterplanning
and Feasibility.
Improved assurance to clients.
Contractors. Quality-led approach thrives.
Reduced risk.
Improved Temporary Works and Safe Material Handling.
Improved planning, programming and phasing.
Policy/Society HNDU delivers against its core objectives.
INSTALLATION COST COMPARISON STUDY
POLYMER VS STEEL - SCOPE
Review/ Budget analysis - Between the installation costs/factors of
equivalent Polymer and Steel system designs.
It is highlighted that this is was a high level initial study, where further investigations and
limitations have been advised.
• Purpose - Stimulate
understanding/dialogue within
an area with little existing
evidence.
• 3D-TD produced an equivalent
Steel design to Polymer.
• Based on a recent Project
connecting 120 dwellings.
• Assess costs of:
• Excavation
• Jointing
• Prelims
• Installation
• Commissioning
INSTALLATION COST COMPARISON STUDY
POLYMER VS STEEL
• Steel Design Criteria:
• Accommodated Expansion.
• Used Curves/Straight Pipes on Spine and
Localised Spine.
• Offered Building Connections in both rigid and
flexible steel.
• Jointing Criteria
• Compression fittings for Polymer
• Class 1 weld/Fusion Sleeves for Steel main
• Trench Criteria
• Calculated by reference to pipe manufacturer’s
typical trench detail.
• Provision for Jointing Pits.
INSTALLATION COST COMPARISON STUDY
KEY FINANCIAL FINDINGS:
Cost Type Polymer Cost Steel/Aluminium Cost Variance
Jointing / welding costs 30,870.00£ 226,311.00£ 195,441.00£
Civils (Fencing, Excavation and re-instatement) 204,009.47£ 238,022.25£ 34,012.78£
Prelims (Compound, Welfare, Site Management) 60,000.00£ 77,000.00£ 17,000.00£
Pipe laying costs 10,808.00£ 15,655.63£ 4,847.63£
Testing and commissioning costs 11,814.90£ 11,892.92£ 78.02£
Key Variance Analysis
• Jointing
• Significant difference between Polymer and Rigid Steel
• Strong conclusion of the study
• Civils
• Marginal increased costs for Steel Design
• Jointing Pits
• Prelims
• Increased project length due to welding/sleeving
• Larger Compound required for pipe storage.
THANK YOU FOR LISTENING
ANY QUESTIONS
Always in Partnership
Contact Details
Craig Grobety
Phone: (UK) 07825 108940
e-mail: [email protected]