4. energy efficiency - somaiya vidyavihar. energy efficiency.pdf · 2020. 10. 9. · energy...

39
1 © Confederation of Indian Industry Energy Efficiency © Confederation of Indian Industry Building Energy Consumption Break-up of energy consumption in a building 57% 5% 16% 22% Air Conditioning Area Lights Mis Equipment Ventilation fans

Upload: others

Post on 23-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

1

© Confederation of Indian Industry

Energy Efficiency

© Confederation of Indian Industry

Building Energy Consumption

Break-up of energy consumption in a building

57%

5%16%

22%

Air Conditioning Area Lights

Mis Equipment Ventilation fans

Page 2: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

2

© Confederation of Indian Industry

Cooling Load Components

A Break Up Of The Heat Gain Through Various Building Components

WALL CONDUCTION

ROOF CONDUCTION

GLAZING CONDUCTION

INTERNAL GAINS (LIGHT, PEOPLE,COMPUTERS)

3%

16%

26%

55%

© Confederation of Indian Industry

Who is responsible for energy efficiency in a building ?

� Landscape architect ?

� Owner ?

� Facilities group ?

� MEP consultant ?

� Architect ?

All can contribute !

Page 3: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

3

© Confederation of Indian Industry

Approach 1) Orientation

2) Envelope measures

� Wall, Glazing, Fenestration, Shading,

Skylighting, Roof

3) Equipment & systems

� Air conditioning, Lighting, Pumps, Motors, VFD

4) Controls

� BMS, Temperature, Humidity

5) Commissioning

� Additional commissioning, M & V

© Confederation of Indian Industry

1) Orientation

� What is the ideal orientation ?

� East-West ?

� North-South ?

� Does not matter ?

� Buffer South and West Exposures with garages, utility rooms etc.

Saving potential : 2-3 % for 90o rotation

Page 4: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

4

© Confederation of Indian Industry

2) Envelop Measures

� Glass & glazing

� How much glazing ?

� High glazing

� Tremendous daylighting

� Heat ingress

� Need to balance

� High performance glass &

glazing

� Low U-value

� Low Shading Coefficient

� High VLT (Visual Light

Transmittance)

© Confederation of Indian Industry

Heat Transfer

� The three modes of heat transfer

Page 5: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

5

© Confederation of Indian Industry

Heat Flows Through Windows

© Confederation of Indian Industry

U-value

� U value – (W/m2.deg K)

� Heat transfer due to temperature

difference (conduction)

� Typical U values

� Single glazed glass (6mm) : 5-6

� High Performance glass : 1.7 – 3.0

(6mm+airgap+6mm)

Page 6: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

6

© Confederation of Indian Industry

Shading coefficient

� Shading coefficientHeat gain thru’ a given glazing (SHGC)

---------------------------------------------

Heat gain thru’ 3 mm clear glass (0.87)

� Solar heat gain coefficient (SHGC)

� Also called as Solar factor by manufacturers

� Indicates direct heat gain

� Typical values

� Single glazed 6mm glass : 0.5 – 0.8

� High performance glass : 0.1 – 0.4

© Confederation of Indian Industry

Significance of Glazing Properties

� Which one is more important ?

� U-value ?

� Shading coefficient ?

� Both ?

Page 7: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

7

© Confederation of Indian Industry

Relative Heat Gain

� RHG=Direct heat gain+Conductive heat gain

=SC (630) + U (35-24)

� Direct heat gain : 90 %

� Conductive heat gain : 10 %

© Confederation of Indian Industry

Walls & Roofs

� RCC Walls

� U-value : 1.95 W/m2 deg K

� Heat Storage higher

� Due to high mass

� Concrete Roof

� U value 2.5 – 3.0 W/m2 deg K

Efficient roof in a flat building

Efficient wall in multi-storied building

Page 8: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

8

© Confederation of Indian Industry

Wall options

� Brick wall with insulation

� Extruded polystyrene, Expanded

polystyrene (thermocol), Glass wool

etc.,

� Brick wall with air cavity

� Hollow blocks

� Flyash bricks

� Autoclaved Aerated Concrete Blocks

Savings Potential : 3-8 %

© Confederation of Indian Industry

Insulation Materials-Relative U-values(75 mm thick)

� Glass wool stuffed

� U value : 0.53 W/m2 deg K

� Thermocol

� U-Value : 0.47 W/m2 deg K

� Extruded Polysterene

� U-Value : 0.37 W/m2 deg K

� Polyurethane

� U-Value : 0.35 W/m2 deg K

Page 9: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

9

© Confederation of Indian Industry

Roof Insulation

� Over-deck ?

� Under-deck ?

� Insulation

sandwiched

� Saving potential

� 3-8 % depending

on extent of roof 1: Reinforced concrete2: Separation layer3: Insulation4: Water proof membrane5: Screed6: Concrete roof deck

© Confederation of Indian Industry

Wall Insulation

� External or

Internal

� Internal if brick

exterior required

� Saving potential

� 3 – 8 %

1: Cement plaster / Gypsum wall board2: Insulation3: Brick or concrete wall4: Interior gypsum or plaster

Page 10: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

10

© Confederation of Indian Industry

Autoclaved Aerated Concrete Blocks

� AAC blocks

� Composed of fly ash, cement,

lime, Aluminum powder and

water

�Unique properties�Low U value: 0.67 W/m2 ok

�Reduction in temp possible : 4-5oC

� Economic Benefits� 15-20% savings in A/c Load

� Savings in Cement

© Confederation of Indian Industry

Envelope measures : Typical saving potential

� Orientation :0.5-1 %

� AAC wall : 3-8 %

� Brick wall with 75mm : 3-8 %

extruded polysterene insulation

� High Albedo roofing material : 2-3 %

� Roof garden : 1-2 %

� Low-U glass & glazing : 6-8 %

� Thermal break : 1-2 %

� Roof insulation (extr.polyst) : 5-6 %

Page 11: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

11

© Confederation of Indian Industry

3) Equipment & systems

� Air-conditioning

� COP: Higher than ASHRAE 90.1-2010

� VFD for supply & return fans and

pumps

� Heat recovery wheels, Economisers

� Controls & Building Management

Systems

© Confederation of Indian Industry

Life cycle cost for A/C systems

Operating Cost 89%

Maintenance/Consumables 1%

Initial Inv. 10%

Page 12: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

12

© Confederation of Indian Industry

Green Building – Air Conditioning

Design Stage

Conventional System

Wind Tower System

Geothermal Cooling

Earth Tunnel Cooling

© Confederation of Indian Industry

Conventional Vapour Compression Cycle

Condenser

Evaporator

CompressorThrottle valve

Discharge high pressure gas

High pressure liquid

Low pressure liquid and flash gas

Suction low pressure gas

T1

T2

CHW in or air in

CHW out or air out

Page 13: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

13

© Confederation of Indian Industry

Chiller Performance

COP : Amount of heat to be taken outAmount of work required

COP tested under ARI conditions:Condenser water inlet : 29.4 deg C, outlet : 35 deg CChilled water inlet : 12..2 deg C, outlet :6.7 deg C

© Confederation of Indian Industry

ASHRAE 90.1-2010 Efficiency Requirements

Path A: Buildings with consistent occupancy. Eg: Office buildings, etc.,; Applicable for all types of Chillers; Path B: Buildings with variable occupancy. Eg: Hotels, Malls, etc; Applicable for Screw Chiller & Centrifugal Chiller with VFD;

Page 14: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

14

© Confederation of Indian Industry

ASHRAE 90.1-2010 Efficiency Requirements

EER: Energy Efficiency RatioCOP: Coefficient of PerformanceIPLV: Integrated Part Load Value

Nad :The requirement is not applicable and cannot be used for complianceNre :There are no minimum requirements for this category.

© Confederation of Indian Industry

Typical AHU System

Condensor

Evaporator

Compressor

Throttle valve

Chilled water coil

Fresh Air

Return Air

Sensor

Supply Air

Enthalpy Control

Page 15: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

15

© Confederation of Indian Industry

Wind Towers

� Advantages

� Requires little / no energy

� Indoor air quality good

� Fresh air entry

� Disadvantage

� Performance dependent on wind

availability

© Confederation of Indian Industry

CII- Institute of Quality Building, Bangalore

Page 16: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

16

© Confederation of Indian Industry

Geo Thermal System

GroundBldg

Comp

Heat flow during cooling

Heat flow during heating

Refrigerant flow while heating

Refrigerant flow while cooling

� Refrigerant : Water / Environmentally safe Anti-fre eze liquid� HDPE pipes underground, Life 50 years� Length of pipes depends on area conditioned

Saving Potential : 30 – 50 %

© Confederation of Indian Industry

Earth Tunnel Air Conditioning

� Concrete hume pipes laid below 4m

� Length of Pipe α Building area

� Room conditions

� Temperature

� Summer - 21-23oC

� Winter – 20 - 22oC

� RH - 50%

� Running equipment (2 HP blower)

Page 17: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

17

© Confederation of Indian Industry

Earth Tunnel Air Conditioning

� Wonder Utilisation of

Nature

� Earth below 4 m

� Cooler - During Summer

� Warmer - During Winter

© Confederation of Indian Industry

Lighting

� ASHRAE requirement

� Overall lighting density:< 1.0 w/sq.ft

� Trade-off allowed

� Maximum daylighting

� Daylight-cum- dimmer controls

� Occupancy sensors (toilets)

� CFL, T-5 lamps, LED

� Equipment density: 1.5 – 2.0 w/sq.ft

Page 18: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

18

© Confederation of Indian Industry

4) Controls and BMS

� Why BMS ?

� Variations inevitable

� Load

� Occupancy schedule

� Climatic conditions

� Human interface minimized

� On-line corrections

BMS – An effective tool

© Confederation of Indian Industry

Capability of BMS

� Centralized Control

� Monitor

� On-line interaction� Chillers

� Pumps

� Fans

� Lighting

� Measurement & Verification� IPMVP protocols

� Data generation & updating

Page 19: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

19

© Confederation of Indian Industry

BMS – HVAC system

© Confederation of Indian Industry

5) Commissioning

� Best of equipment, systems, controls may

be in place

� No savings if not commissioned

� Can result in 5-10 % savings

� Especially if carried out by a III party

Page 20: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

20

© Confederation of Indian Industry

IGBC Green New Building Rating System - Perspectives

© Confederation of Indian Industry

Energy EfficiencyCredit Title Points

Mandatory Requirement 1

Ozone Depleting Substances Required

Mandatory Requirement 2

Minimum Energy Efficiency Required

Mandatory Requirement 3

Commissioning Plan for Building Equipment & Systems

Required

Credit 1 Eco-friendly Refrigerants 1

Credit 2 Enhanced Energy Efficiency 15

Credit 3 On-site Renewable Energy 6

Credit 4 Off-site Renewable Energy 2

Credit 5Commissioning, Post-installation of Equipment & Systems

2

Credit 6 Energy Metering and Management 2

Total 28

Page 21: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

21

© Confederation of Indian Industry

EE Mandatory Requirement 1

Ozone Depleting Substances

�Intent

� Encourage use of eco-friendly

refrigerants and halons free refrigerants

� To minimise negative impact on the

ozone layer

© Confederation of Indian Industry

EE Mandatory Requirement 1

Ozone Depleting Substances

� Compliance Options

� Refrigerants

� CFC (Chloro Fluoro

Carbon) – free

(And)

� Halon-free Fire

Suppression Systems

Chimes , GurgaonGold Rated

Page 22: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

22

© Confederation of Indian Industry

EE Credit 1

Eco-friendly Refrigerants

� Compliance Options

�Refrigerants used in HVAC equipment

� Low or no Ozone Depletion Potential (ODP)

and Global Warming Potential (GWP)

LCGWP + LCODP x 105 ≤ 13

© Confederation of Indian Industry

EE Mandatory Requirement 2

Minimum Energy Efficiency

�Intent

� Optimise energy consumption to

reduce negative environmental

impacts from excessive energy use

Page 23: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

23

© Confederation of Indian Industry

EE Mandatory Requirement 2

Minimum Energy Efficiency

� Compliance Options

� Case 1 - Air conditioned Buildings

� Option 1 - Whole Building Simulation

� Option 2 - Prescriptive Approach

(Or)

� Case 2 - Non-air conditioned Buildings

(Applicable only for Owner-occupied buildings)

� Prescriptive Approach

© Confederation of Indian Industry

Case 1 - Air conditioned Buildings

Page 24: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

24

© Confederation of Indian Industry

Option 1 - Whole Building Simulation

� Demonstrate building performance

compliance through simulation

� ECBC

(Or)

� ASHRAE Standard 90.1-2010, Appendix - G

� Indoor temperature

� 24 ± 2 deg C

© Confederation of Indian Industry

Whole Building Simulation

� Submission

� Building energy simulation report

Page 25: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

25

© Confederation of Indian Industry

Credit 2

Percentage of Energy Cost Savings over ASHRAE Standard 90.1-2010 Base case

PointsOwner-occupied

Buildings

Tenant-occupied

Buildings

Major Renovation

Buildings

6% 4% 4% 1

8% 6% 6% 2

10% 8% 8% 3

12% 10% 10% 4

14% 12% 12% 5

16% 14% 14% 6

18% 16% 16% 7

20% 18% 18% 8

22% 20% 20% 9

24% 22% 22% 10

© Confederation of Indian Industry

Credit 2

Percentage of Energy Cost Savings over ASHRAE Standard 90.1-2010 Base case

PointsOwner-occupied

Buildings

Tenant-occupied

Buildings

Major Renovation

Buildings

26% 24% 24% 11

28% 26% 26% 12

30% 28% 28% 13

32% 30% 30% 14

34% 32% 32% 15

Page 26: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

26

© Confederation of Indian Industry

Option 2 - Prescriptive Approach

� Meet the applicable criteria as

established in prescriptive measures

� ECBC

(or)

� ASHRAE Standard 90.1-2010

© Confederation of Indian Industry

Case 2 – Non-air conditioned Buildings

(Applicable only for Owner-occupied buildings)

Page 27: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

27

© Confederation of Indian Industry

Non Air-conditioned Buildings(Definition)

� Those which are not serviced and will not be serviced in the future

� Either through central air-conditioned systems or unitary air-conditioners

� Air-conditioning may be considered for critical areas

� Not more than 10% of the total regularly occupied area

© Confederation of Indian Industry

Prescriptive Approach

1) Building Envelope(Baselines as per

Annexure – I)

2) Lighting

3) Air-conditioning Systems

4) Heating Systems

5) Fans

6) Pumps & Motors

Page 28: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

28

© Confederation of Indian Industry

EE Mandatory Requirement 3

Commissioning Plan for Building Equipment & Systems

�Intent

� Verify and ensure that the building’s

equipment & systems are commissioned

� To achieve performance as envisaged

during the design stage

© Confederation of Indian Industry

Commissioning Plan for Building Equipment & Systems

�Compliance Options

� Agreement with third party

commissioning authority

� Who is not involved in the design

� At least 3 years prior experience in

equipment and systems

� Document owners brief

Basically a plan

Page 29: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

29

© Confederation of Indian Industry

Commissioning Plan

� Commission Plan shall include:

� HVAC systems & accessories

� Pumps & Motors

� Lighting systems

� Renewable energy systems

� CO2 monitoring system

� Energy & Water metering

� Building management system

� Sewage treatment plant

� Diesel generator sets

© Confederation of Indian Industry

Commissioning Plan

� Report specific observations & variations

� Identified by the Commissioning Authority

� Post occupancy survey to verify:

� Lighting levels, temperature, relative humidity,

noise levels etc.,

� Report on green building performance

Page 30: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

30

© Confederation of Indian Industry

EE Credit 3

On-site Renewable Energy

�Intent

� Encourage the use of on-site

renewable technologies

� To minimise the environmental impacts

associated with the use of fossil fuel energy

© Confederation of Indian Industry

EE Credit 3

On-site Renewable Energy

�Compliance Options

� Owner-occupied Buildings

� 1% of total annual energy consumption of

the building

� Tenant-occupied Buildings

� 2% of total annual lighting energy

consumption of the building

� Interior & exterior areas, including tenant-

occupied spaces

Page 31: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

31

© Confederation of Indian Industry

EE Credit 3

On-site Renewable Energy

* % of total energy consumption – Owner-occupied buildings

Use of On-site Renewable Energy *

(Percentage)

Points

≥ 1% 2

≥ 2% 3

≥ 3% 4

≥ 4% 5

≥ 5% 6

© Confederation of Indian Industry

EE Credit 3

On-site Renewable Energy

* % of lighting energy consumption – Tenant-occupied buildings

Use of On-site Renewable Energy *

(Percentage)

Points

≥ 2% 2

≥ 3% 3

≥ 4% 4

≥ 5% 5

≥ 6% 6

≥ 7% 7

≥ 8% 8

Page 32: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

32

© Confederation of Indian Industry

EE Credit 4

Off-site Renewable Energy

�Intent

� Encourage the use of off-site

renewable technologies

� To minimise the environmental impacts

associated with fossil fuel energy use

© Confederation of Indian Industry

Option 1: Off-site Renewable Energy Investments

� Owner-occupied Buildings

� 50% of the total annual energy consumption

� Tenant-occupied Buildings

� 50% of the total annual lighting energy

consumption

� Interior & exterior areas, including tenant-

occupied spaces

Page 33: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

33

© Confederation of Indian Industry

Option 1: Off-site Renewable Energy Investments

Percentage of Off-site

Renewable Energy *Points

≥ 50 % 1

100 % 2

* % of total energy consumption – Owner-occupied buildings

* % of lighting energy consumption – Tenant-0ccupied buildings

© Confederation of Indian Industry

Option 2: Renewable Energy Certificates (RECs)

� Owner-occupied Buildings

� 25% of the total annual energy consumption

� Tenant-occupied Buildings

� 25% of the total annual lighting energy

consumption

� Interior & exterior areas, including tenant-

occupied spaces

Page 34: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

34

© Confederation of Indian Industry

Option 2: Renewable Energy Certificates (RECs)

Percentage of Renewable Energy

Certificates (RECs) Purchased Points

≥ 25 % 1

≥ 50 % 2

* % of total energy consumption – Owner-occupied buildings

* % of lighting energy consumption – Tenant-occupied buildings

© Confederation of Indian Industry

Renewable Energy Certificates

Bombay House, MumbaiGold Rated

Page 35: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

35

© Confederation of Indian Industry

EE Credit 5

Commissioning Post-installation of Equipment & Systems

�Intent

� Verify and ensure that the building

equipment & systems are commissioned

� To achieve performance as envisaged

at the design stage

© Confederation of Indian Industry

�Compliance Options

� Report specific observations & variations

� vis-à-vis the Commissioning Plan

� Agreement with third party commissioning

authority

� Post occupancy commissioning

� for a period of one year

Commissioning Post-installation of Equipment & Systems

Page 36: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

36

© Confederation of Indian Industry

EE Credit 6

Energy Metering and Management

�Intent

� Encourage sub-metering and

continuous monitoring

� To identify improvement opportunities

in building’s energy performance

Tenant Sub MeteringBearys Golden Research Triangle, Bangalore,Platinum Rated

© Confederation of Indian Industry

EE Credit 6

Energy Metering and Management

� Compliance Options

� Case 1: Energy Metering (1 Point)

(And)

� Case 2: Building Management System

(1 Point)

Page 37: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

37

© Confederation of Indian Industry

Case 1: Energy Sub-metering . . .

� Install sub-meters for at least five of the

following:

1) Interior & Common area lighting

2) Exterior area lighting

3) Municipal water pumping

4) Ground water pumping

5) Treated waste water pumping

© Confederation of Indian Industry

Case 1: Energy Sub-metering

6) Renewable energy generation

7) Power backup systems (Generators sets, etc.,)

8) Elevators, Escalators, Travelators, etc.,

9) BTU meter for chilled water consumption

(Applicable for tenant-occupied buildings only)

10)Any other energy consuming equipment and systems

Page 38: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

38

© Confederation of Indian Industry

Case 2: Building Management System

�BMS to control and monitor:

� Air-conditioning management system

� Lighting management system

� Renewable energy management system

� Elevator management system

� Fresh air monitoring system

� CO2 control and monitoring system

� Water management system Commit to provide annual building energy consumption data

© Confederation of Indian Industry

Building Management System

Cooling Towers Temperature & RH

Chiller AHUChimes, GurgaonGold Rated

Page 39: 4. Energy Efficiency - Somaiya Vidyavihar. Energy Efficiency.pdf · 2020. 10. 9. · Energy Efficiency Credit Title Points Mandatory Requirement 1 Ozone Depleting Substances Required

39

© Confederation of Indian Industry

Energy EfficiencyCredit Title Points

Mandatory Requirement 1

Ozone Depleting Substances Required

Mandatory Requirement 2

Minimum Energy Efficiency Required

Mandatory Requirement 3

Commissioning Plan for Building Equipment & Systems

Required

Credit 1 Eco-friendly Refrigerants 1

Credit 2 Enhanced Energy Efficiency 15

Credit 3 On-site Renewable Energy 6

Credit 4 Off-site Renewable Energy 2

Credit 5Commissioning, Post-installation of Equipment & Systems

2

Credit 6 Energy Metering and Management 2

Total 28