42486-016: madhya pradesh urban services improvement project€¦ · detailed estimate for...
TRANSCRIPT
Initial Environmental Examination
Document stage: Final
Project Number: 42486-016
October 2019
IND: Madhya Pradesh Urban Services Improvement Program – Water Supply Improvement in Boda, Kurawar and Kothri Towns (PART B)
Package No: MPUSIP-1A
Prepared by Madhya Pradesh Urban Development Company, Government of Madhya Pradesh for the Asian Development Bank.
This final initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, management, or staff, and may be preliminary in nature. Your attention is directed to the ‘terms of use’ section on ADB’s website.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
98
Appendix 6: Groung water recharge and conservation plan for Kothri town
Proposed groundwater Recharge and conservation Plan Kothari:
Cost of Recharge & water conservation Plan NO Cost Rs (INR- in Lacs)
Pond Development 3 57.59 Recharge trench 3 24.77 Recharge shaft 8 65.28 Subsurface dyke 1 0.95 Gabion structure 4 6.08
No of structures 19 Rs 154.67 /- Consultancy Charges (6%) (as per market rate) 9.28/-
Total Project cost 163.95/-
Percolation Pond with Recharge shaft
Structures NO Dimension Cost
Pond Near pipal tree (76°49'54.725"E 23°4'6.557"N)
1 100*100* 4
27.95
Pond opp market/school (76°49'49.52"E 23°4'20.54"N )
1 45*24*3.5 6.24
Pond Near Nakundi dugwell (76°49'40.40"E 23°4'13.73"N)
1 90*75*4.0 23.4
Total cost of Pond development 3
57.59
Recharge Trench Recharge Trench (230 04'16.7":760 49'54.3")
1 300*9.5*3.0 4.52 Upstream of Kaddi shutter Recharge Trench (230 04'4.1":760 49'57.4" )
1 500*14*3.0 11.52 upstream of stop dam Recharge Trench (230 03'56.1":760 49'55.55" ) 1 500*11*3.0 8.73 Upstream of Tipakheri stop dam
Total Cost of Recharge Trench 3
24.77
No of proposed Recharge shaft No Rate Total Rs lakh
8 8.16 65.28
Sub Surface Dyke (76°49'34.56"E 23° 4'28.66"N) 1 12*3.5*4.5 0.95 Gabian 1. (76°49'55.90"E 23° 4'16.90"N) 1 11m x 2.20m x 1.75 m Gabian 2. (76°50'1.00"E 23° 4'13.70"N) 1 10m x 2.20m x 1.75 m Gabian 3. (76°49'52.40"E 23° 4'18.90"N) 1 10m x 2.20m x 1.75 m Gabian 4. (76°49'40.57"E 23° 4'21.01"N) 1 9m x 2.20m x 1.75 m Total cost of Gabian 4 6.08
Detailed Estimate for Construction of Pond Near Pipal tree (76°49'54.725"E 23°4'6.557"N)
USOR E-in-CWRD w.e.f. 1-4-2016
S. No.
Particulars of Item No. L B H Qty. Rate Amount
1 Excavation in all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud including placing excavated soil neatly in specified dump area or disposing off the same as directed, including cost of site clearance, all materials, machinery, labour and dressing etc. Complete. with dressing. USOR Item 2.01(b) P-21
(A) 1 100.00 100.0 2.5 25000.00
m3 40.00 1000000.00
2 Excavation in In all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud in pond bed with mixed bulders including 50 m lead and 1.5 m lift with dressing, including separation of boulder of size 0.004 cum and more from the earthwork. and under- drainage-arrangement including dressing to the profile and disposal of excavated materials etc. Complete. USOR Item 4.01(1) P-42
1 100.00 100.0 1.5 15000.00
m3 48.00 720000.00
3 Labour only for Filling foundations with hard soil including watering and ramming. USOR Item 709(a) P-52
1 10.00 14.0 13 1820.00
m3 43.00 78260.00
4 Compaction of earthwork at optimum moisture content to achive maximum dry density by mechanical (excluding watering ) Sheep foot roller/vibratory compactors. USOR Item 2.09 P-22
1820.00
m3 18.00 32760.00
5 Watering earth work for compaction at optimum moisture content with lead up to 100 m. USOR Item 2.10 P-22
1820.00
m3 10.00 18200.00
6 22 cm thick dry stone pitching(without quarry spall) with individual stones of 22 cm depth and minimum size 0.014 cum. USOR Item 1006 P-71
1 130.00 13.0 0.22 371.80 m3 723.00 268811.40
7 Lead of materials, 30 km -
Pitching Stones 371.80 m3 537.93 200002.37
Water 1820.00
m3 6.30 11466.00
Total 2329499.77
Add 20% above as per current market rates 465899.95
Total 2795399.73
Say ` 27.95
LAKHS
Detailed Estimate for construction of Kadishutter Pond opp market/school (76°49'49.52"E 23°4'20.54"N)
USOR E-in-C WRD w.e.f. 1-4-2016
S. No. Particulars of Item No. L B H Qty. Rate Amount
1 Excavation in all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud including placing excavated soil neatly in specified dump area or disposing off the same as directed, including cost of site clearance, all materials, machinery, labour and dressing etc. Complete. with dressing. USOR Item 2.01(b) P-21
(A) 1 45.00 24.0 1.5 1620.00
m3
40.00 64800.00
2 Excavation in In all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud in pond bed with mixed bulders including 50 m lead and 1.5 m lift with dressing, including separation of boulder of size 0.004 cum and more from the earthwork. and under- drainage-arrangement including dressing to the profile and disposal of excavated materials etc. Complete. USOR Item 4.01(1) P-42
1 45.00 24.0 2 2160.00
m3
48.00 103680.00
3 Labour only for Filling foundations with hard soil including watering and ramming. USOR Item 709(a) P-52
1 10.00 14.0 13 1820.00
m3
43.00 78260.00
4 Compaction of earthwork at optimum moisture content to achive maximum dry density by mechanical (excluding watering) Sheep foot roller/vibratory compactors. USOR Item 2.09 P-22
1820.00
m3
18.00 32760.00
5 Watering earth work for compaction at optimum moisture content with lead up to 100 m. USOR Item 2.10 P-22
1820.00
m3
10.00 18200.00
6 22 cm thick dry stone pitching (without quarry spall) with individual stones of 22 cm depth and minimum size 0.014 cum. USOR Item 1006 P-71
1 58.50 13.0 0.22 167.31
m3
723.00 120965.13
7 Lead of materials, 30 km -
Pitching Stones 167.31
m3
537.93 90001.07
Water 1820.00
m3
6.30 11466.00
Total 520132.20
Add 20% above as per current market rates 104026.44
Total 624158.64
Say ` 6.24
LAKHS
Detailed Estimate for construction of Pond Near Nakundi dugwell (76°49'40.40"E 23°4'13.73"N)
USOR E-in-C WRD w.e.f. 1-4-2016
S. No. Particulars of Item No. L B H Qty. Rate Amount
1 Excavation in all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud including placing excavated soil neatly in specified dump area or disposing off the same as directed, including cost of site clearance, all materials, machinery, labour and dressing etc. Complete. with dressing. USOR Item 2.01(b) P-21
(A) 1 90.00
75.0 2.5 16875.00
m3 40.00 675000.00
2 Excavation in In all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud in pond bed with mixed bulders including 50 m lead and 1.5 m lift with dressing, including separation of boulder of size 0.004 cum and more from the earthwork. and under- drainage-arrangement including dressing to the profile and disposal of excavated materials etc. Complete. USOR Item 4.01(1) P-42
1 100.00
100.0
1.5 15000.00
m3 48.00 720000.00
3 Labour only for Filling foundations with hard soil including watering and ramming. USOR Item 709(a) P-52
1 10.00
14.0 13 1820.00
m3 43.00 78260.00
4 Compaction of earthwork at optimum moisture content to achive maximum dry density by mechanical (excluding watering) Sheep foot roller/vibratory compactors. USOR Item 2.09 P-22
1820.00
m3 18.00 32760.00
5 Watering earth work for compaction at optimum moisture content with lead up to 100 m. USOR Item 2.10 P-22
1820.00
m3 10.00 18200.00
6 22 cm thick dry stone pitching (without quarry spall) with individual stones of 22 cm depth and minimum size 0.014 cum. USOR Item 1006 P-71
1 115.00
13.0 0.22 328.90 m3 723.00 237794.70
7 Lead of materials, 30 km -
Pitching Stones 328.90 m3 537.93 176925.18
Water 1820.00
m3 6.30 11466.00
Total 1950405.88
Add 20% above as per current market rates 390081.18
Total 2340487.05
Say ` 23.40
LAKHS
Detailed Estimate for construction of Recharge Trench (230 04'16.7":760 49'54.3" )
Upstream Area Of Kadishuteer Pond To Small Pond In Downstream Of Old Road
USOR E-in-C WRD w.e.f. 1-4-2016 Sno. Item No. L B D Qty Unit Rate Amount
1
1 Ordinary shrub jungle (Area below 25% covered by shrubs) clearance involving removal of grass. Shrubs and twigs, including rooting out. USOR Item 9.01 P-109
1.0 300.0 9.5 0.0 2850.0 Sqm 0.40 1140.00
2 Excavation in all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud including placing excavated soil neatly in specified dump area or disposing off the same as directed, including cost of site
1.0 300.0 9.5 1.5 4275.0 cum 40.0 171000.00
clearance, all materials, machinery, labour and dressing etc. Complete. with dressing. USOR Item 2.01(b) P-21
3 Excavation in In all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud in pond bed with mixed bulders including 50 m lead and 1.5 m lift with dressing, including separation of boulder of size 0.004 cum and more from the earthwork. and under- drainage-arrangement including dressing to the profile and disposal of excavated materials etc. Complete. USOR Item 4.01(1) P-42
1.0 300.0 9.5 1.5 4275.0 cum 48.0 205200.00
Total 377340.00
Add 20% above as per current market rates 75468.00
Total 452808.00
Say ` 4,52,000
Detailed Estimate for construction of Recharge Trench (230 04'4.1":760 49'57.4" )
Upstream area of stop dam to Tipakhedi raod USOR E-in-C WRD w.e.f. 1-4-2016
Sno. Item No. L B H Qty Unit Rate Amount
1
1
Ordinary shrub jungle (Area below 25% covered by shrubs) clearance involving removal of grass. shrubs and twigs, including rooting out. USOR Item 9.01 P-109
1.0 500.0 14.0 0.0 7000.0 Sqm 0.40 2800.00
2 Excavation in all kind of soft/loose/hard/dense
1.0 500.0 14.0 1.5 10500.0 cum 40.0 420000.00
soils, moorum & moorum mixed with boulders and mud including placing excavated soil neatly in specified dump area or disposing off the same as directed, including cost of site clearance, all materials, machinery, labour and dressing etc. Complete. with dressing. USOR Item 2.01(b) P-21
3
Excavation in In all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud in pond bed with mixed bulders including 50 m lead and 1.5 m lift with dressing, including separation of boulder of size 0.004 cum and more from the earthwork. and under- drainage-arrangement including dressing to the profile and disposal of excavated materials etc. Complete. USOR Item 4.01(1) P-42
1.0 500.0 14.0 1.5 10500.0 cum 48.0 504000.00
Total
926800.00
Add 20% above as per current market rates 185360.00
Total 111216
0.00
Say `
111200
0.00
Detailed Estimate for construction of Recharge Trench (230 03'56.1":760 49'55.55" )
Upstream area of stop dam to Tipakhedi raod
USOR E-in-C WRD w.e.f. 1-4-2016
Sno. Item No. L B H Qty Unit Rate Amount
1
1
Ordinary shrub jungle (Area below 25% covered by shrubs) clearance involving removal of grass. shrubs and twigs, including rooting out. USOR Item 9.01 P-109
1.0 500.0 11.0 0.0 5500.0 Sqm 0.40 2200.00
2
Excavation in all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud including placing excavated soil neatly in specified dump area or disposing off the same as directed, including cost of site clearance, all materials, machinery, labour and dressing etc. Complete. with dressing. USOR Item 2.01(b) P-21
1.0 500.0 11.0 1.5 8250.0 cum 40.0 330000.00
3
Excavation in In all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud in pond bed with mixed bulders including 50 m lead and 1.5 m lift with dressing, including separation of boulder of size 0.004 cum and more from the earthwork. And under- drainage-arrangement including dressing to the profile and disposal of excavated materials etc. Complete. USOR Item 4.01(1) P-42
1.0 500.0 11.0 1.5 8250.0 cum 48.0 396000.00
Total
728200.00
Add 20% above as per current market rates 145640.00
Total 873840.
00
Say ` 8,73,000
Detailed Estimate for construction of Sub Surface Dyke (76°49'34.56"E 23° 4'28.66"N)
USOR E-in-C WRD w.e.f. 1-4-2016
(2.5.00 m width, 4.5.00 m depth)
S.
No.
Particulars of Item No. L B D Qty. Rate Amount
1 Excavation in all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud including placing excavated soil neatly in specified dump area or disposing off the same as directed, including cost of site clearance, all materials, machinery, labour and dressing etc. Complete. with dressing. USOR Item 2.01(b) P-21
1 12.00 2.5 2 60.00 m3 40.00 2400.00
Excavation in In all kind of soft/loose/hard/dense soils, moorum & moorum mixed with boulders and mud in pond bed with mixed bulders including 50 m lead and 1.5 m lift with dressing, including separation of boulder of size 0.004 cum and more from the earthwork. and under- drainage-arrangement including dressing to the profile and disposal of excavated materials etc. Complete. USOR Item 4.01(1) P-42
1 12.00 2.0 1.5 36.00 m3 48.00 1728.00
Excavation in all kind of soft//hard/integrat ed /weathered rock including placing excavated soil neatly in specified dump area or disposing off the same as directed, including cost of site clearance, all materials, machinery, labour and dressing etc. Complete. with dressing. USOR Item 4.01.2 P-42
1 12.00 1.5 1 18.00 m3 104.00 1872.00
4 Puddle filling of good clay i/c lead upto 50m i/c mixing watering and kneeding by temping ramming and laying etc. USOR Item 3.44 at page 36
1 12 3.3 3 117.00 m3 196.00 22932.00
5 Collection of puddle earth USOR Item as per market rate
117.00 m3 283.00 33111.00
6 Providing and fixing in position LDPE film of 150 micron (0.15 mm ISI Mark 2508 (grade 231.) i/c heat sealed joint at enob as per 189698 USOR Item 2520 P-241
1 12.00 0.0 7 84.00 m² 28.00 2352.00
5 Watering earth work for compaction at optimum moisture content with lead up to 2000 m. USOR Item at market rate for 2 km lead
100.00 m3 150.00 15000.00
Total 79395.00
Add 20% above as per current market rates 15879.00
95274.00
Say ` 0.95
LAKHS
Detailed Estimate for construction of Recharge shaft
USOR E-in-C WRD w.e.f. 1-4-2016
(3 m dia, 1.5 m depth)
S. No.
Particulars of Item No. No. L B H Qty. Rate Amount
1 Excavation in hard soil including 50 m lead and 1.5 m lift with dressing. USOR Item 2.01(b) P-21
0.784 9.00 1.5 10.58 m3 40.00 423.36
2 Providing , placing and position and M-25 mm RCC excluding cost of reinforcement but including form work, viberation, finishing, quiring etc. complete with graded metal of maximum size 20 mm USOR Item 3.19.2 P-31
10.05 0.2 0.2 0.40 m3
9.891 0.15 1.7 2.52 m6
Total A+B 2.92 m3 4746.00
13877.90
3 Supplying and fixing steel reinforcement bars tested for RCC work including cleaning, straightening, cutting, bending, binding all handling placing in position and binding
8 mm
50 0.9 17.55 Kg
10 mm
10 9.891 61.32 Kg
10 mm
50 1.7 52.70 Kg
12 mm
4 9.891 35.21 kg
with .9 mm annealed wire, cold worked steel high strength bars. USOR item 3.13 page no29
166.79 kg 46.51 7757.22
4 Lead of materials, 30 km -
Cement - 0.00 0.00 m3 315 0.00
Sand - 0.00 0.00 m3 225.18 0.00
Metal - 0.00 0.00 m3 250.20 0.00
Steel - 0.00 0.00 Ton 225.18 0.00
5 Provision of drilling of telescopic Bore well with gravel packed 300 to 150 mm dia upto 180 m depth including cost of casing. (Non SOR)
LS 650000.00
6 Filling of filter media in the recharge shaft as below (Non SOR)
Coarse sand 7.056 0.5 3.53 Cum 2000.00
7056.00
Gravel 7.056 0.5 3.53 Cum 105.00 370.44
Pabbles 7.056 0.5 3.53 Cum 150.00 529.20
Total 680014.12
Add 20% above as per current market rates 136002.82
816016.95
Say ` 8.16
LAKHS
Name of village – Kothari kala -Estimate for Gabion:
Sr. no. Particulars Unit No. Length Width Av. Depth/ Height
Quantity
1/(SOR-301 B) Excavation of foundation for spillway
Cumt. 1 15.00 1.20 0.45 8.10
2/(SOR-301 B) Excavation of foundation for Extension wall
Cumt. 2 1.50 2.20 1.50 9.90
3(SOR-301 B) Excavation of apron Cumt. 1 8.00 1.00 0.20 1.60 4(SOR- 1813-a & 1818 C)
Spillway foundation Stone filling
Cumt. 1 15.00 1.20 0.45 8.10
5(SOR- 1813-a & 1818 C)
Stone Construction of Spillway above GL
Cumt. 1 15.00 1.20 1.00 18.00
6(SOR- 1813-a & 1818 C)
Stone construction of Extension wall
Cumt. 2 1.50 2.20 2.00 13.20
7(SOR- 1813-a & 1818 C)
Apron Stone filling Cumt. 1 8.00 1.00 0.30 2.40
8 Steel wire mesh for spillway Sqmt 1 15.00 4.9 73.50 9 Steel wire mesh for spillway
for apron Sqmt 1 2.60 17.1 44.46
Abstract Sheet
Sr. No.
Line Item Quantity Unit Rate Amount Labour Material
1
Excavation for foundation in all strata including dewatering and disposing excated stuff elsewhere directed with a lead of 1.00 mt. and lift at 3.00 mt.(SOR-301 B)
19.60 Cu mt 70.80 1387.68 1387.68 0.00
2 Collection of Boulder max. size 0.014 cum. (SOR- 1813-a & 1818 C)
41.70 Cu mt 308.50 12864.45 12864.45 0.00
3 Transportation of boulders with av. leads of 15 kms. (Sor-1902j & 1904/3)
41.70 Cu mt 299.80 12501.66 0.00 12501.66
4 Boulder Sowling without compaction(SOR- 2311)
41.70 Cu mt 271.40 11317.38 11317.38 0.00
5 Labour work for Wire mesh winding 117.96 Sq mt. 60.00 7077.60 7077.60 0.00 6 Purchasing of wire mesh (32kg/10SMt) 377.47 Kg 75.00 28310.40 0.00 28310.40
Total Amount 73459 32647 40812
Gabion Structure Cost = 73459
Total No. of Gabion Structure = 4
Cost of Gabion Structure= 293837 130588 163248
Add 3.5% work contingency 10284 0 10284
Total Cost of the Work 304121 130588 173533
Total Cost of the Work (in Lakh) 3.04 1.31 1.74
99
Appendix 7: Kunwar Chain Sagar Dam Quality Results at Proposed floating Pontoon (this source is used for Boda & Kurawar towns)
100
Appendix 8: Drinking Water Standards
S. No.
Parameters, unit
WHO Drinking Water standards
IS-10500:2012
Requirement acceptable limit
Permissible limit in the absence of alternate source
1 Color, Hazen Units
None 5 15
2 Odour None Agreeable Agreeable
3 Turbidity None 1 5
4 pH None 6.5-8.5 6.5-8.5
5 Total hardness as CaCo3,mg/l
None 200 600
6 IRON as Fe, mg/l
- 0.30 0.30
7 Chloride as Cl, mg/l
250 250 1000
8 Total Dissolved Solids, mg/l
- 500 2000
9 Calcium as Ca, mg/l
- 75 200
10 Copper as Cu, mg/l
2 0.05 1.5
11 Manganese as Mn, mg/l
0.4 0.1 0.3
12 Sulphate as SO4, mg/l
- 200 400
13 Alkalinity mg/l - 200 600
14 Magnesium as Mg, mg/l
- 30 100
15 Mercury as Hg, mg/l
0.006 0.001 0.001
16 Cadmium as Cd, mg/l
0.003 0.003 0.003
17 Selenium as Se, mg/l
0.04 0.01 0.01
18 Arsenic as As, mg/l
0.01 0.01 0.05
19 Lead as Pb, mg/l
0.01 0.01 0.01
20 Zinc as Zn, mg/l - 5 15
21 Chromium as (Cr), mg/l
0.05 0.05 0.05
22 Boron as B, mg/l
2.4 0.5 1.0
23 Fluoride, mg/l 1.5 1.0 1.5
24 Nickel as Ni, mg/l
0.07 0.02 0.02
25 Sodium as Na, mg/l
- -
26 Potassium as K, mg/l
- - -
27 Cobalt as Co, mg/l
- - -
101
S. No.
Parameters, unit
WHO Drinking Water standards
IS-10500:2012
Requirement acceptable limit
Permissible limit in the absence of alternate source
28 Aluminium as Al , mg/l
- 0.03 0.2
29 Coli form bacteria/100ml
0 0 -
30 Barium (as Ba), mg/l, Max
0.7 0.7 0.7
31 Free residual chlorine, mg/l,
5.0 0.2 1
32 Molybdenum (as Mo), mg/l, Max
0.07 0.07 0.07
33 Nitrate (as NO3), mg/l, Max
50 45 45
102
Appendix 9: Site Environmental Management Plan (SEMP)
Site Environmental Management Plan (SEMP): Package 1A
Package No. MPUSIP – 1A PIU - Bhopal
Package title Water Supply Improvement in Boda, Kurawar and Kothri towns
Contractor M/s Rean Water Tech Private Limited, Kolkata
Date of Contract Award 24.06.2017
Date of works commencement 04.08.2017
Contract period Construction: 28 months; O&M: 120 months
Project Towns Boda, Kurawar and Kothri
Project Description 3 separate / individual water supply schemes for 3 towns
Project Components As per the project detailed design
Town 1: Kothri (Sehore)
Town 2: Kurawar (Rajgarh)
Town 3: Boda (Rajgarh)
New tube wells 7 nos. Floating Pontoon in existing dam
1 nos. Floating intake in existing dam
1 nos.
Chlorination plant
1 nos. WTP 4.7 MLD WTP 1.5 MLD
OHT 2 nos. OHT 2. nos. OHT N/A OHT- 1 400 KL OHT- 1 900 KL OHT- 2 60 KL OHT- 2 250 KL GLSR 2 nos. GLSR N/A GLSR N/A GLSR- 1 200 KL GLSR- 2 150 KL Raw water rising main
N/A Raw water rising main (300 mm dia.)
33840 m
Raw water rising main (200 mm dia.)
14128 m
Clear water feeder main
4054 m
Clear water feeder main
3577 m Clear water feeder main (150 mm dia.)
1486 m
75 mm 357 m 200 mm 2344 m 110 mm 2854 m 150 mm 506 m 160 mm 843 m 100 mm 727 m Distribution Network
41284 m Distribution Network
53618 m Distribution Network
25764 m
75 mm 25743 m 75 mm 26730 m 75 mm 10578 m 110 mm 12631 m 90 mm 5815 m 90 mm 2306 m 160 mm 1888 m 110 mm 6095 m 110 mm 5171 m 200 mm 839 m 125 mm 2081 m 125 mm 1248 m 250 mm 183 m 140 mm 7389 m 140 mm 4428 m 160 mm 757 m 160 mm 641 m 180 mm 969 m 180 mm 415 m 200 mm 727 m 225 mm 324 m 225 mm 268 m 250 mm 653 m 250 mm 1178 m 280 mm 1609 m Household Connections
2141 Nos. Household Connections
3265 Nos.
Household Connections
2147 Nos.
Details of contractors on-site-personnel and workers
Kothri Kurawar Boda Remarks
Project Manager 1 for all towns
Technical / supervisory staff Senior engineer – 1 for all towns
Senior engineer – 2 for all towns
Senior engineer – 1 for all towns
1 trainee engineers and 1 supervisor
2 trainee engineers
2 trainee engineers
EHS Supervisor 1 for all towns Mobilized Skilled / semi-skilled workers 03 06 04 Unskilled workers 06 08 02 Women workers 03 04 05 (Local labour) Workers – local / migrant 09 14 06 Details of facilities
Construction camps, (no’s and locations)
Two labour camp (Kothri)
1. Opposite to New Nagar Parishad, Kothri. 2. Near Govt. school, Bedakhedi, Kothri
Two labour camp (Kurawar)
1. Near Govt. Hospital, Kurawar 2.Mohammadpur road, Kurawar
One labour camp (Boda)
1. WTP Premises (Kurawar-Boda-Talen road, 1 Km from Boda town)
List of plant & machinery / equipment / vehicles to be used
• Weight Batcher machines- 02 no’s
• Backhoe loader Excavator- 01 no’s
• Trolley tractor- 02 no’s
• Needle Vibrator- 03 no’s
• Lift Machine- 01 no’s
• Diesel Generator- 01 no’s
• Dewatering Pump motorized- 02 no’s
• Grinder and other hand tools
• Weight Batcher machines- 02 no’s
• Needle Vibrator- 04 no’s
• Excavator- 01 no’s
• Trolley tractor- 02 no’s
• Diesel Generator- 1 no’s
• Dewatering Pump motorized
• Grinder and other hand tools
• Weight Batcher machines- 1 no’s
• Excavator- 1 no’s
• Trolley tractor- 1 no’s
• Diesel Generator- 1 no’s
• Needle Vibrator- 01 no’s
• Dewatering Pump motorized
• Grinder and other hand tools
Table 1: Pre construction Phase Environmental Management Plan
Anticipated Impact
Mitigation Measures Status of Compliance
Yes/No Preconstruction phase Unsatisfactory compliance to EMP
• Environmental, Health and Safety (EHS) Supervisor will be mobilized to carryout environmental safeguard tasks
Yes
• Updated IEE / site specific EMP will be submitted Yes
Utilities on sites (electric, telephone lines, water pipes etc.)
• Location of utilities and respective operators will be identified, and measures to avoid damage/disruption will be implemented
Yes
• Contingency plan will be prepared and implemented in case of service disruption Yes
Construction materials
• Construction materials will be obtained only from government approved quarries Yes
• All clearance/license copies of quarries / borrow areas will be provided to PIU for prior approval Yes
• A monthly report will be submitted to PIU on construction material quantity (sources-wise) Yes
• No new borrow areas / quarries will be created for the work No
Approvals, permission, insurances, licenses, etc., for construction work
• All necessary permissions will be obtained prior to start of works Yes
• Copies of all permission/approvals will be submitted to PIU prior to start of work Yes
Training to staff & workers
• Staff and key workers will be trained (in construction methods, safety, EMP, EHS policy) prior to start of work
Yes
Guidelines to be followed for establishing construction camps / labour camps
• Camp sites shall be away from residential areas (100 m), sensitive areas (schools, hospitals, etc. 250 m,), water bodies (500 m) and forests (more than 1 km)
Yes
• Use unused, vacant lands; no trees shall be cut Yes
• Provide a proper fencing/compound wall Yes
• Prepare a site layout plan & display at the site; uniformly label (name boards) all the places in the facility
Yes
• Entire site/facility area shall be provided with hard leveled surface as appropriate; no loose soil, slush, water logging etc.,
Yes
• Living quarters and construction camps shall be provided with standard materials; no shacks or huts Yes
• Adequate lighting and ventilation Yes
• Provide drinking water, water for other uses, and sanitation facilities; drinking water should be regularly tested
Yes
• Provide clear pathways for safe movement Yes
• Provide cooking fuel (cooking gas); and a separate safe place to cook; fire wood not allowed Yes
• Construct septic tanks and soak pit arrangement for wastewater disposal Yes
Anticipated Impact
Mitigation Measures Status of Compliance
Yes/No
• Solid waste shall be properly manager – provide separate bins, compost biodegradable waste; sell recyclable waste
Yes
• Camp sites shall be cleared and restored to original after completion of work, all debris, wreckage cleared
Yes
Work site management
• Provide a proper fencing/compound wall Yes
• Prepare a site layout plan & display at the site; uniformly label (name boards) all the places in the facility
Yes
• Entire site/facility area shall be provided with hard leveled surface as appropriate; no loose soil, slush, water logging etc.,
Yes
• Provide clear pathways (for workers/staff) and roads (for vehicles) for safe movement in the work site
Yes
Worker amenities at all work sites
• A temporary rest area for workers (for resting in break time, protection against rain/sun, eating etc.,) Yes
• Drinking water Yes
• Wash area, toilets (separate for women); mobile toilets for linear work Yes
• Septic tank and soak pits for waste disposal Yes
• First aid Yes
Table 2: Construction Phase Environmental Management Plan
Anticipated Impact Mitigation Measures
Intake works in dam • Metal floating barge type intake proposed – no construction work is proposed in dam; no impacts envisaged
Bore well drilling • Slurry generated from drilling will be stored in temporary ditch for some time to allow sedimentation of solids, and then disposed to drains
Dust Control • Dust screen will be provided around work sites (OHT, GLSR, WTP, intake etc.,)
• Loose soil on work sites, vehicle and worker movement areas will be properly rammed and stabilized to minimize dust generation; it will be ensured that no loose soil surface at working places
• Water will be sprinkled adequately (at least daily 3 times in dry weather) to maintain surface in stabilized and damp condition
• Prior to any leveling or earth moving activity, water will be sprinkled to avoid dust
• Material stocks will be covered with tarpaulins/covers at the sites
• Access to work area will be controlled; unnecessary movement of vehicles, workers and public in work areas will be controlled to minimize soil disturbance
• Loose material (soil, sand, aggregate etc.,) will be covered with tarpaulins to when transported by open trucks;
• Loose material from trucks will be unloaded in a barricaded area and with water sprinkling
• Wheels and undercarriage of haul trucks will be cleaned prior to leaving construction site Dust control from pipeline works
• Construction area will be barricaded on both sides using hard barricades of 2m height
• Site clearance and excavation work will be commenced only after barricading the site
• Works and all associated activities (material, soil, debris, equipment and machinery) will be confined to barricaded area.
• Excavated soil storage will be removed from the site immediately & stored/disposed at identified site
• Work will be undertaken section wise (100-500 m) at various places; these sections will be demarcated and barricaded and trench filled
• Work will be conducted work sequentially - excavation, pipe laying, backfilling; testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done
• Excavated soil will be removed section-wise, and used for filling the previous section, this is to avoid stocking of excavated soil
• Road restoration will be taken up immediately after backfilling by proper consolidation Noise control • Noisy works will be avoided in the night
• Proper noise control apparatus (silencers, mufflers etc.,) will be ensured for construction equipment
• Maximum sound level of 75 db at a distance of 10 m from source will be ensured
• Before undertaking work with heavy noise/vibration, surrounding area/buildings will be surveyed to identify any old / sensitive buildings at risk, and necessary precautions will be taken to avoid any risk
• Drivers will be trained to avoid usage of horns unnecessarily
• Noisy works will not be conducted near sensitive places (hospitals, schools, etc.,) and at sensitive times (festivals etc.,); works will be scheduled accordingly
Vehicle emissions • All the construction equipment, machinery will be fitted with pollution control devises
• Pollution under control (PUC) certificate will be obtained for all vehicles, equipment, and records maintained Water pollution / works in rainy season
• No earthwork will be conducted during rainy season
• Stockpiles of earth will be covered by tarpaulins or plastic sheets
• Excess soils, debris and materials will be reused in the construction works
Anticipated Impact Mitigation Measures
• Disposal sites will be selected prior to start of construction following the EMP guidelines
• Temporary silt traps or sedimentation basins will be provided to control water pollution
• Storage areas for fuels and lubricants will be located away drainage lines & water bodies
• Fuels, construction chemicals etc. will be stored on an impervious floor, and carefully handled to avoid spillage; spill collection arrangement will be provided
• Wastes generated by construction activities will be disposed only in designated sites
• Surface water quality monitoring will be conducted as per the EMP
• Temporary drains or bunds will be created around the periphery of work area to avoid flooding, and entry of runoff
• Accumulated water in work areas / excavated pits will be pumped to a temporary ponds/sedimentation basins; only clarified water will be disposed into drains
• Safety measures will be undertaken to avoid any risk of collapse due to water entry Traffic management / access during pipeline works
• Pipeline work implementation plan will be prepared for each road; works will not be conducted in all roads at once in a locality; alternative roads for traffic movement will be ensured
• A simple traffic management plan will be prepared in consultation with traffic police for each road, and displayed on site; one-week prior notice will be provided
• Temporary diversions will be provided as required, with prior public information
• Work area will be properly defined, barricaded; minimum strip of land will be used
• Material / waste / soil will not be stocked obstructing the traffic, pedestrian etc.,
• Trench width will be minimized as much as possible by adopting best construction methods with proper shoring/bracing
• Work site will be kept free from all unnecessary obstructions
• Public information boards, sing boards, caution boards will be provided along with contact numbers
• Prior to start of pipeline work, information will be provide to the public through media – newspapers and local cable television (TV) services
Access to houses/business during pipeline works
• Gaps/wooden or metal planks will be provided on excavated trenches for access
• Access to any house, business or property will not be blocked completely, at least safe pedestrian access will be maintained
• Local/affected people/business will be informed 1-week in advance about the work and access restrictions
Material transport using heavy trucks
• Material haulage vehicles will main/wide roads as far as possible
• Transportation / hauling activities will be conducted during non-peak hours (indicate time: from 10:30 PM to 12:30 AM hrs)
• Proper entry and exits to facilities will be provided facilities at low traffic places
• Drivers will be trained to drive vehicles in a considerate manner and following all traffic rules Local employment • Local labors will be employed as far as possible Safety at work sites • Environment, Health and Safety (EHS) Policy/ plan will be established
• Site will be prepared and maintained to create safe working conditions; workers will be provided with safe work areas, elevated platforms, steps, ladders, walkways /access to work areas and amenities
• Deep excavations (more than 1 m) will be properly protected to avoid collapse (safety measures such as / shoring / safe slopes)
• Hard barricading will be provided around deep trenches / pits of more than 1.5 m deep
• All necessary precautions will be taken to avoid collapse of trench/pit, and damage to surrounding structures
• Proper personnel protection equipment will be provided to all workers / staff; and its use will be ensured
Anticipated Impact Mitigation Measures
• Proper audible back-up alarms will be ensured for all moving equipment/machinery
• All installations will be properly secured; hazardous locations will be properly marked
• All work sites will be properly secured, barricaded to avoid unauthorized public/traffic entry
• Provide road signs and flagman to regulate traffic / pedestrians / road users, of on-going trenching activities
• Provide safety sign, caution, information boards on site for workers and staff awareness, follow up
• Health and safety orientation training will be provided to all workers
• First aid, and staff with training in first aid will be made available at all sites
• Site safety orientation will be provided to all visitors to the site
• Drinking water, sanitation, washing and resting facilities will be provided at all sites; separate sanitation facilities for women
• Emergency procedures and contact information will be provided on all sites
• Accidents will be promptly registered and reported; register will be maintained at every work site
• Public compliant box and compliant register will be provided at every work site Construction waste / debris disposal
• Construction waste management plan will be prepared
• Excess soil / debris will be utilized in construction / useful purposes to avoid disposal
• Excess soils/debris will be removed from site on regular basis to avoid stockpiling at site
• Disposal site will be identified prior to start of work following EMP guidelines
• Domestic waste generated at camp sites will be properly segregated; biodegradable waste composted in impervious pit at site; recyclable waste will be sold in market
• Residual and hazardous wastes such as oils, fuels, and lubricants will be disposed via licensed agencies by MPPCB
• Burning of waste will not be allowed
• Sites will be managed neatly; waste collection bins will be provided, awareness will be created among workers, staff in site cleanliness
• All camp/work sites will be restored to original condition after the completion of work Chance find protocol
• If any chance find is suspected during excavation/works, work will be immediately stopped, and report to PIU/PMU and PMC
• Necessary action as suggested by concerned authorities will be undertaken AC pipes • Location of existing/old AC pipes will be identified prior to excavation for new pipes
• Underground AC pipes will left as it is in the ground without disturbing / touching
• Awareness will be created among workers and supervisors on AC pipes Post construction clean up
• All spoils wreckage, rubbish, or temporary structures (such as latrines) will be removed
• All excavated roads will be reinstated to original condition
• All disrupted utilities will be restored
• Any spillage of substances like oils, paints etc., will be cleaned up
• All hardened surfaces in work/camp areas will be ripped, all materials removed, and top soiled
• Restoration to original will be documented and reported to PIU
Table 3: Construction Phase Environmental Monitoring Plan
Monitoring field Monitoring Location
Monitoring parameters Frequency
Ambient air quality Total six (6) locations in three (3) towns
Kurawar (3 nos.) 1. OHT No. 1 2. WTP/ OHT No. 2 3. pipeline work sites
Boda (1 nos.) 1. WTP/ pipeline work sites
Kothri (2 nos.) 1. OHT No. 1 2. OHT No. 2/ pipeline work sites
PM10, PM2.5 NO2, SO2, CO • Once prior to start of work
• Quarterly during
construction
Ambient Noise 6 locations in 3 towns – same as above Noise Level – 24 hours – hourly measurements – day and night time noise levels
• Once prior to start of work
• Quarterly during construction
Surface water quality
Kunwar Chain Sagar Dam pH, Cl, F, NO3, TC, FC, Hardness,
Turbidity COD, DO, Oil & grease, total
alkalinity, heavy metals
• Once prior to start of work
• Once after placing intake barge/ floating Pontoon
Site specific attachments to this EMP 1. Details of construction work sites (except pipeline work sites)
2. Details of construction camp sites (labour camps, material storage/fabrication etc., work camps)
3. List of clearances & statutory requirements
4. Contractor’s EHS Policy & Organization
5. Utility Shifting & Relocation
6. Details of Construction Materials
7. Details of construction waste / debris / surplus soil
8. Work site management for pipeline works
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
SEMP Attachment 1: Boda Town
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Attachment 1: Details of construction Work sites
I WTP- 1.5 MLD work site, Boda Town Location: Kurawar- Boda- Talen Road (1 km from Boda town)
1 Material storage • Aggregate
• Sand
• Steel • Cement
• Bricks
2 Plant & machinery
• Earth compactor- 1 no’s
• Concrete Weigh Batcher Mixer – 1 no’s • Backhoe Loader Excavator- 1 no’s
• Diesel generator- 1 no’s
• Trolley Tractor- 1 no’s
• Dewatering motorized pump- 1 no’s • Needle Vibrator- 1 no’s
• Steel Grinder
• Small hand tools
3 Site office
4 Laboratory
• Compressive strength testing apparatus • Slump cone
• Flakiness & Elongation index
• Vicat Apparatus
• Weight Balance • Concrete cube mould
• Sieves with sieve shaker
• Sieve shaker
• Oven
5 Labour welfare facilities
• Labour rest area
• Drinking water
• Washing place • Toilets ( Mobile toilets for men and women)
• First aid
• Fire safety
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
6 Site layout plan - Plan (rough / not to scale map) is shown below with site boundary, roads/pathways, facilities, offices. - Site location with site approach road from main road/highway is shown below.
7 Site photographs Original site photographs
Site Photographs before the start of construction
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Site photos with facilities / work area
Construction worksite
Storage of Material Project Sign Board
Safety Awareness signage First Aid Kit
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Site Layout Plan Fire Extinguisher
Worksite Signage Complaint Box
Caution Sign Board Drinking water
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Mobile Toilet Van
Laboratory Room
Site office cum Laboratory
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Attachment 2: Details of construction camp sites
I Labour camp- 1 for WTP Labours,
Location: WTP premises, 1 km from Boda town
1 Accommodation - for 06 no’s migrant workers; No women / families in the camp
Facilities provided at camp site
• Type of living accommodation– Semi Pucca House (Brick masonry walls with shed)
• Camp area (living area) – 18 sq. m.
• Cots
• Separate cooking area
• Cooking gas • Drinking water
• Bath rooms
• Mobile Toilet Van
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
2 Site layout plan: attach separately
- Plan (rough / not to scale map) is shown with camp boundary and facilities
- Site location with approach road
3 Site photographs
Original site photographs
Site Photographs Before the construction of Labour camp
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Photos of camp and facilities provided
Labour camp Kitchen
Drinking Water facility Portable toilet
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Attachment 3: List of clearances & statutory requirements
A Project related Status
1 WRD permission for water abstraction from Kunwar Chain Sagar Dam Obtained
2 Consent to establish for WTPs from MPPCB In process
B Construction/work related
1 Road cutting permission from MPPWD for RWRM laying In process
C Labour safety / welfare related (indicate all as per the labour officer)
1 Labour license Obtained
2 Permit under BOCW Rules Obtained
3 Annual return under BOCW rules Obtained
D Safety / liability safety related (indicate all as per the contract)
1 Group insurance Available
2 Contractor All Risk (CAR) insurance Available
3 Medical insurance Available
E Others
1 Fitness certificate for vehicles, equipment used in construction Available
2 Pollution under control (PUC) certificates for vehicles and equipment Available
3 Driving licenses for drivers Available
4 Insurance for vehicles / equipment, as required Available
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Attachment 4: Contractor’s EHS Policy & Organization
1 Contractor agency has a EHS policy Yes / No
1 If yes, provide policy details
1. Policy statement:
2. EHS organization& responsibilities:
No
2 List safety risks anticipated in the project -
Area works ( WTP etc.,)
• Trips and falls
• Head injury from falling objects
• Confined work space
• Slope failure / trench collapse
• Road accidents
Linear works (pipelines)
• Slip ,Trips and falls
• Falling of vehicle
• Fall of person
• Collapse of Trench
3 List personal protection equipment provided to workers
PPEs No’s
Safety shoes 20 no’s
Gloves 60 no’s
Helmet 20 no’s
Gloves for Steel bending 45 no’s
Gum Boots 30 no’s
Safety jacket 46 no’s
Total 221 no’s
Yes
2 Contractor emergency procedure Yes Detail what steps/procedure to be adopted in emergency situation (e.g., accidents)
• For minor injury first aid box (available at site) will be serve the purpose.
• For major injury victim should be taken to nearest hospital by ambulance or by
arranging local vehicle.
• In case of fire fighting, people present in the site will be transferred to safe place
and 1 or 2 responsible person will use the fire extinguisher to prevent fire.
Contact information, staff and responsibilities for emergency situations
Designation Staff name &
contact
Emergency responsibility
1. Safety Steward Mr. Rajmani Kumar
+91-7828398174
Take care of victim and give first aid if
required
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
2. Site Engineer Mr. Plash Biswas
+91- 6294129025
Inform the senior and assemble the
worker at safe place and call the
ambulance if required
3. EHS Supervisor Md Mahboob
Hussain
+91-9934634361
Give necessary instructions to safety
steward and Site Engineer to handle
the situation
4. Project manager Mr. Aakash Diggaj
+91-8225055999
Monitors the situation and report to
officials at PIU Level
3 Reporting procedure in case of work accidents
Safety Steward → Site Engineer → EHS Supervisor →Project Manager (Contractor)
→Project Manager (PIU Bhopal)
Yes
Package 1A (Boda Town): Site Specific EMP Attachments 1- 8
Attachment 5: Utility shifting/relocation
1 List work sites that require Utility shifting, relocation, temporary shut off
Remarks
1 Area work sites (WTP)
1. No utilities shifted / temporarily disturbed
2 Linear work sites (pipeline works)
1. No utilities shifted / temporarily disturbed
Attachment 6: Details of Construction Materials
S. No
Material Approximate quantity required (m3) for project
Source Indicate if source has all necessary government clearances
1 Aggregate 503 Cum Shrinath crusher
(Pachore)
Yes
2 Sand 250 Cum Nayak Trader
(Kurawar)
Yes
3 Steel 57 tonnes Real Ispat & Power
Urla industrial area Raipur (CG)
Yes
4 Cement 7040 Bags Maihar Cement Unit
Sarlanagar- Satna (M.P.)
Yes
Attachment 7: Details of construction waste / debris / surplus soil
S. No
Waste likely be generated
Type of debris / waste
Approximate quantity
Indicate whether it will be reused / disposed off
In case of disposal, indicate disposal site name & location
1 Construction waste / debris
Steel 60 Kg Sold out to scrap vendor
-
2 Surplus soil Soil/Moorum 30-40 Cum Reused in site development and backfilling
-
Attachment 8: Work site management for pipeline works
1. Detail of Pipeline work in project area- Diameter wise
Pipe Diameter (mm)
Length (m)
Width of trench (m)
Depth of Trench (m)
Width of roads (m)
Type of roads
(earthen / BT / CC )
Excavation method (manual / mechanical)
RWRM & CWRM- DI K-9 pipes (15,614 m)
150 1486 0.55- 0.8 1.150 7.50 – 9 m CC/BT Mechanical
200 14128 0.6- 0.9 1.225 7.50 – 9 m Earthen/BT/ CC
Mechanical
Distribution Network- HDPE PN 10 (25,764 m)
75 10578 0.55- 0.8 1.075 2.50 – 4.50 CC/BT Manual/Mech
90 2306 0.55- 0.8 1.090 2.50 – 4.50 CC/BT Manual/Mech
110 5171 0.55- 0.8 1.100 2.50 – 4.50 CC/BT Manual/Mech
125 1248 0.55- 0.8 1.125 2.50 – 4.50 CC/BT Manual/Mech
140 4428 0.55- 0.8 1.140 2.50 – 4.50 CC/BT Manual/Mech
160 641 0.55- 0.8 1.180 2.50 – 4.50 CC/BT Manual/Mech
180 415 0.6- 0.9 1.200 2.50 – 4.50 CC/BT Manual/Mech
225 324 0.6- 0.9 1.250 2.50 – 4.50 CC/BT/Earthen Manual/Mech
250 653 0.6- 0.9 1.280 2.50 – 4.50 CC/BT Manual/Mech
2. Details of Roads in project area – town wise
(A) RWRM:
Town name / Type of road
Total width of roads (building line to building line)
Width of carriage way
Type of surface (BT/CC /WBM / Earthen)
Length of roads
Where pipe will be laid on road*
Boda
National highways
N/A N/A N/A N/A N/A
State highways N/A N/A N/A N/A N/A
District / other roads (MDR)
7.5 m 4.75 m BT 4,000 m Road Shoulder
Internal main roads (MPRRDA)
7.5 m 4.75 m Earthen/ BT 10,128 m Road shoulder/ One side of road carriageway
Internal sub-roads (Village road)
N/A N/A N/A N/A N/A
Streets N/A N/A N/A N/A N/A
Total length 14,128 m
(B) CWRM:
Town name / Type of road
Total width of roads (building line to building line)
Width of carriage way
Type of surface (BT/CC /WBM / Earthen)
Length of roads
Where pipe will be laid on road*
Boda
National highways
N/A N/A N/A N/A N/A
State highways N/A N/A N/A N/A N/A
District / other roads (MDR- PWD Road)
9.0 m 4.75 m BT 1,486 m Road shoulder
Internal main roads
N/A N/A N/A N/A N/A
Internal sub-roads
N/A N/A N/A N/A N/A
Streets N/A N/A N/A N/A N/A
Total length 1,486 m
(C) Distribution Network:
Town name / Type of road
Total width of roads (building line to building line)
Width of carriage way
Type of surface (BT/CC /WBM / Earthen)
Length of roads
Where pipe will be laid on road*
Boda
National highways
N/A N/A N/A N/A No
State highways N/A N/A N/A N/A No
District / other roads
9 m 4.75 m CC and BT 3,264 m Road shoulder
Internal main roads
N/A N/A N/A N/A No
Internal sub-roads
N/A N/A N/A N/A N/A
Streets 3- 4 m 2.5- 3 m CC and Earthen
22,500 m One side of road carriage way
Total length 25,764 m
SEMP Attachment 2: Kurawar Town
Attachment 1: Details of construction Work sites
I 250 KL OHT work site, Kurawar WSS
Location: Ward no. 05, Near Govt. Hospital, Kurawar
1 Material storage
• Aggregate • Sand
• Steel
• Cement
• Bricks
2 Plant & machinery • Backhoe loader excavator - 1 no’s
• Trolley Tractor- 1 no’s
• Weigh Batcher Mixer- 1 no’s • Needle Vibrator- 1 no’s
• Lift Machine- 1 no’s
• Dewatering pump motorized- 1 no’s
• Grinding Machine- 2 no’s and other hand tools
3 Site office
4 Security Cabin
5 Laboratory
• Compressive strength testing apparatus • Compaction factor equipment
• Slump cone
• Auto Level • Flakiness & Elongation index
• Vicat Apparatus
• Weight Balance
• Oven • Sand replacement equipment
• Concrete cube mould
• Sieves with sieve shaker
6 Labour welfare facilities • Labour rest area
• Drinking water
• Toilet
• Washing place • Toilets (separate for women)
• First aid
• Fire safety
7 Site layout plan - Plan (rough / not to scale map) is shown below with site boundary, roads/pathways, facilities, offices. - Site location with site approach road from main road/highway
8 Site photographs Original site photographs
Site photograph before the start of construction
Site photos with facilities / work area
OHT worksite
Project Information Board Proper Pathway/Approach
Material Stacking
Site Layout Plan First Aid Kit
Laboratory Room
Safety Signage’s
Fire Safety Drinking Water Facilities
Toilet (Men & Women) Separate toilet for Women
Waste collection Bin Prohibited Zone
II WTP- 4.70 MLD & 900 KL OHT work site, Kurawar WSS
Location: Mohammadpur Road, Kurawar
1 Material storage
• Aggregate
• Sand • Steel
• Cement
• Bricks
2 Plant & machinery
• Excavator/ Loader- 1 no’s • Trolley Tractor- 1 no’s
• Weight Batcher Machine- 1 no’s
• Needle Vibrator- 3 no’s
• Diesel Generator- 1 no’s • Dewatering pump motorized- 1 no’s
• Grinding Machine- 2 no’s and other hand tools
3 Security Cabin
4 Labour welfare facilities
• Labour rest area
• Drinking water- Yes • Washing place
• Toilets (separate for women)
• First aid • Fire safety
• Cots 5 Site layout plan
- Plan (rough / not to scale map) is shown below with site boundary, roads/pathways, facilities, offices.
- Site location with site approach road from main road/highway is shown below.
6 Site photographs Original site photographs
Site photographs before the start of construction
Site photos with facilities / work area
WTP & OHT Work site
Site Layout Plan Project Sign Board
Safety Signage Board
Clear Pathways & walkways First Aid Kit
Site office Cement Storage Room
Tool Box Meeting at Work site Drinking water facilities
Toilet
Attachment 2: Details of construction camp sites
I Labour camp for workers of 250 KL OHT
Location: OHT- 250 KL Premises, Near Govt. Hospital, Kurawar
1 Accommodation - for 6 migrant workers; No women / families in the camp Facilities provided at camp site
• Type of living accommodation– Semi Pucca House (Brick masonry walls with shed)
• Camp area (living area) – 18 sq. m
• No. of Rooms- 02 • Cots
• Accommodation provided for 6 workers
• Separate cooking area
• Cooking (Gas Cylinder) • Drinking water
• Bath rooms
• Toilets • Septic tank and soak pit
• Drainage
2 Site layout plan - Plan (rough / not to scale map) is shown below with camp boundary and facilities - Site location with approach road
3 Site photographs
Original site photographs
Site photograph before the labour camp setup
Photos of camp and facilities provided
Labour room Drinking Water Facilities
First Aid Kit Waste collection Bin
Toilet (Men & Women) Separate toilet for Women
II Labour Camp for workers of 900 KL OHT Site & WTP- 4.70 MLD
Location: WTP/900 KL OHT Premise, Mohammadpur Road, Kurawar
1 Accommodation - for 7 no’s migrant workers; No women / families in the camp Facilities provided at camp site
• Type of living accommodation– Semi Pucca House (Brick masonry walls with shed) • Camp area (living area) – 28 sq. m
• No. of Rooms- 02
• Accommodation provided for 7 workers
• Separate cooking area • Cooking gas
• Drinking water
• Bath rooms • Toilets
• Septic tank and soak pit 2 Site layout plan
- Plan (rough / not to scale map) is shown below with camp boundary and facilities - Site location with approach road
3 Site photographs
Original site photographs
Site photographs before the labour camp setup
Photos of camp and facilities provided
Labour camp First aid available
Drinking water facilities Clear pathway
Toilets
Attachment 3: List of clearances & statutory requirements
A Project related Status
1 WRD permission for water abstraction from Kunwar Chain Sagar Dam Obtained
2 Consent to establish for WTPs from MPPCB In process
B Construction/work related
1 Road cutting permit – NHAI In process
2 Road cutting permit – MPRDC/PWD In process
C Labour safety / welfare related (indicate all as per the labour officer)
1 Labour license Obtained
2 Permit under BOCW Rules Obtained
3 Annual returns under BOCW Rules Obtained
D Safety / liability safety related (indicate all as per the contract)
1 Group insurance Available
2 Contractor All Risk (CAR) insurance Available
3 Medical insurance Available
E Others
1 Fitness certificate for vehicles, equipment used in construction Available
2 Pollution under control (PUC) certificates for vehicles and equipment Available
3 Driving licenses for drivers Available
4 Insurance for vehicles / equipment, as required Available
Attachment 4: Contractor’s EHS Policy & Organization
1 Contractor agency has a EHS policy Yes / No
1 If yes, provide policy details
3. Policy statement:
4. EHS organization& responsibilities:
No
2 List safety risks anticipated in the project -
Area works (OHT / WTP etc.,)
• Trips and falls
• Head injury from falling objects • Confined work space
• Slope failure / trench collapse
• Road accidents
Linear works (pipelines) • Slip ,Trips and falls
• Falling of vehicle
• Fall of person
• Collapse of Trench
3 List personal protection equipment provided to workers
PPEs Numbers Safety shoes 40 Nos. Gloves 100 Nos. Gloves for Bar Bending 80 Nos. Helmet 40 Nos. Gum Boots 60 Nos. Safety jacket 65 Nos. Safety belt 30 Nos. Nose Mask 45 Nos. Ear Plug 35 Nos. Eye Protection Goggle 40 Nos. Total 535 Nos.
Yes
2 Contractor emergency procedure Yes Detail what steps/procedure to be adopted in emergency situation (e.g., accidents)
• For minor injury first aid box (available at site) will be serve the purpose.
• For major injury victim should be taken to nearest hospital by ambulance or by arranging local vehicle.
• In case of fire fighting, people present in the site will be transferred to safer place and 1 or 2 responsible person will use the fire extinguisher to prevent fire.
Contact information, staff and responsibilities for emergency situations
Designation Staff name &
contact
Emergency responsibility
5. Safety Steward Mr. Ratul Sinha +91-8240654303
Take care of victim and give first aid if
required.
6. Site Engineer Mr. Bablu Kumar +91-7771013946
Inform the senior and assemble the
worker at safe place and call the
ambulance if required.
7. EHS Supervisor Md Mahboob
Hussain
+91-9934634361
Give necessary instructions to safety
steward and Site Engineer to handle
the situation.
8. Project manager Mr. Aakash Diggaj
+91-8225055999
Monitors the situation and report to
officials at PIU Level
3 Reporting procedure in case of work accidents Safety Steward → Site Engineer → EHS Supervisor → Project Manager (Contractor) → Project Manager (PIU Bhopal)
Attachment 5: Utility shifting/relocation
1 List work sites that require Utility shifting, relocation, temporary shut off
Remarks
1 Area work sites (OHT: 900 KL & WTP Site)
2. No utilities shifted / temporarily disturbed
2 Area work sites (OHT: 250 KL)
1. No utilities shifted / temporarily disturbed
3 Linear work sites (pipeline works)
2. No utilities shifted / temporarily disturbed
Attachment 6: Details of Construction Materials
S. No
Material Approximate quantity required (m3) for project
Source Indicate if source has all necessary government clearances
1 Aggregate 975 Cum Shrinath Crusher
(Pachore)
Yes
2 Sand 580 Cum Nayak Traders
(Kurawar)
Yes
3 Steel 170 tonnes Real Ispat & power urla industrial area, Raipur, Chhatisgarh
Yes
4 Cement 11000 Bags Maihar cement Unit, Sarlanagar, Satna, (M.P.)
Yes
Attachment 7: Details of construction waste / debris / surplus soil
S. No
Waste likely be generated
Type of debris / waste
Approximate quantity
Indicate whether it will be reused / disposed off
In case of disposal, indicate disposal site name & location
1 Construction waste / debris
Steel 110 Kg Sold out to scrap vendor
-
2 Surplus soil Soil/Moorum 50-60 Cum Reused in backfilling
-
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Attachment 8: Work site management for pipeline works
1. Detail of Pipeline work in project area- Diameter wise
Pipe Diameter (mm)
Length (m)
Width of trench (m)
Depth of Trench (m)
Width of roads
(xx – xx m)
Type of roads
(earthen / BT / CC )
Excavation method (manual / mechanical)
RWRM & CWRM- DI pipe (37,417 m)
100 727 0.55- 0.8 1.100 2.50 – 4.50 CC/BT Mechanical
150 506 0.55- 0.8 1.150 2.50 – 4.50 CC/BT Mechanical
200 2344 0.6- 0.9 1.200 2.50 – 4.50 CC/BT Mechanical
300 33840 0.6- 0.9 1.300 2.50 – 4.50 CC/BT Mechanical
Distribution Network- HDPE PN 10 (53618 m)
75 26730 0.55- 0.8 1.075 2.50 – 4.50 CC/BT Manual/Mech
90 5815 0.55- 0.8 1.090 2.50 – 4.50 CC/BT Manual/Mech
110 6095 0.55- 0.8 1.100 2.50 – 4.50 CC/BT Manual/Mech
125 2081 0.55- 0.8 1.125 2.50 – 4.50 CC/BT Manual/Mech
140 7389 0.55- 0.8 1.140 2.50 – 4.50 CC/BT Manual/Mech
160 757 0.55- 0.8 1.160 2.50 – 4.50 CC/BT Manual/Mech
180 969 0.55- 0.8 1.180 2.50 – 4.50 CC/BT Manual/Mech
200 727 0.6- 0.9 1.200 2.50 – 4.50 CC/BT Manual/Mech
225 268 0.6- 0.9 1.225 2.50 – 4.50 CC/BT Manual/Mech
250 1178 0.6- 0.9 1.250 2.50 – 4.50 CC/BT/Earthen Manual/Mech
280 1609 0.6- 0.9 1.280 2.50 – 4.50 CC/BT Manual/Mech
2. Details of Roads in project area – town wise
(A) RWRM:
Town name / Type of road
Total width of roads (building line to building line)
Width of carriage way
Type of surface (BT/CC /WBM / Earthen)
Length of roads
Where pipe will be laid on road*
Kurawar
National highways
N/A N/A N/A N/A N/A
State highways N/A N/A N/A N/A N/A
District / other roads (MDR)
9 m 4.75 m BT 10,000 m Road Shoulder
Internal main roads (MPRRDA)
7.5 m 4.75 m BT 20,000 m One side of road carriageway
Internal sub-roads (Village road)
7.5 4.0 m BT/Earthen 3,840 m One side of road carriageway
Streets N/A N/A N/A N/A N/A
Total length 33,840 m
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
(B) CWRM:
Town name / Type of road
Total width of roads (building line to building line)
Width of carriage way
Type of surface (BT/CC /WBM / Earthen)
Length of roads
Where pipe will be laid on road*
Kurawar
National highways
N/A N/A N/A N/A N/A
State highways N/A N/A N/A N/A N/A
District / other roads (MDR- PWD Road)
9 m 4.75 m CC/BT 1,800 m One side of road carriageway
Internal main roads
N/A N/A N/A N/A N/A
Internal sub-roads
N/A N/A N/A N/A N/A
Streets 3- 4 m 3 m CC/BT 1,777 m One side of road carriageway
Total length 3,577 m
(C) Distribution Network:
Town name / Type of road
Total width of roads (building line to building line)
Width of carriage way
Type of surface (BT/CC /WBM / Earthen)
Length of roads
Where pipe will be laid on road*
Kurawar
National highways
12 m 7 m BT 5,000 m Road Shoulder
State highways N/A N/A N/A N/A N/A
District / other roads
N/A N/A N/A N/A N/A
Internal main roads
7 m 4.75 m BT 4,500 m Road Shoulder
Internal sub-roads
N/A N/A N/A N/A N/A
Streets 3- 4 m 2.5- 3 m Earthen/ CC/ BT
44,118 m One side of road carriageway
Total length 53,618 m
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
SEMP Attachment 1: Kothri Town
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Attachment 1: Details of construction Work sites
I 400 KL OHT work site, Kothri WSS
Location: Near New Nagar Parishad, Kothri 1 Material storage
• Aggregate
• Sand
• Steel • Cement
• Bricks 2 Plant & machinery
• Concrete weigh batcher mixer- 1 no’s • Trolley tractor- 1 no’s
• Needle Vibrator- 2 no’s
• Lift machine- 01 no’s
• Backhoe Loader Excavator - 1 no’s • Dewatering motorized pump- 01 no’s
• Grinding and other hand tools 3 Site office
4 Security Cabin
5 Laboratory
• Auto Level
• Compressive strength testing apparatus • Slump cone
• Vicat Apparatus
• Weight Balance • Concrete cube mould
• Sieves with sieve shaker
• Sand Replacement Equipment
• Oven • Flakiness & Elongation index
6 Labour welfare facilities
• Labour rest area
• Drinking water • Washing place
• Toilets (separate for women
• First aid
• Fire safety 7 Site layout plan
- Plan (rough / not to scale map) is shown below with site boundary, roads/pathways, facilities, offices. - Site location with site approach road from main road/highway is shown below.
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
8 Site photographs Original site photographs
Site photographs before the start of construction
Site photos with facilities / work area
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Work site photo Project Sign Board
Material Stacking Safety Signage Board
Site Office Laboratory
Site Layout Plan Drinking water facilities
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
First Aid Kit Toilet (Men & Women)
Labour with PPEs & Tool Box Meeting
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
II 60 KL OHT work site, Kothri WSS
Location: Near School, Mainakhedi, Kothri
1 Material storage
• Aggregate
• Sand • Cement
• Steel 2 Plant & machinery
• Concrete weight batcher Mixer- 1 no’s
• Trolley tractor- 1 no’s • Needle Vibrator- 2 no’s
• Backhoe Loader Excavator - 1 no’s
• Dewatering motorized pump- 01 no’s
• Steel Grinding machine- 1 no’s • Small hand tools
3 Site office
4 Labour welfare facilities
• Labour rest area
• Drinking water
• Toilet cum Washing place • Toilets (separate for women)
• First aid
• Cots 5 Site layout plan
- Plan (rough / not to scale map) is shown below with site boundary, roads/pathways, facilities, offices. - Site location with site approach road from main road/highway is shown below.
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
6 Site photographs
Original site photographs
Site photographs before the start of construction
Site photos with facilities / work area
OHT Worksite Project Sign Board
Site Layout Plan Proper Walkway/ Approach
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Material Stacking
Toilet Labour with PPEs/ Tool Box talk
First Aid Kit Drinking water facilities
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Attachment 2: Details of construction camp sites
I Labour Camp for workers of 400 KL OHT Site
Location: Opposite to New Nagar Parishad, Kothri 1 Accommodation - for 7 no’s migrant workers;
No women / families in the camp Facilities provided at camp site
• Type of living accommodation– Rented House (Pucca House)
• Camp area (living area) – 28 sq. m
• Cots • Accommodation provided for 7 workers
• Separate cooking area
• Gas cylinder for cooking • Drinking water
• Bath rooms
• Toilets
• Septic tank and soak pit 2 Site layout plan
- Plan (rough / not to scale map) is shown below with camp boundary and facilities - Site location with approach road
3 Site photographs
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Original site photographs
Labour Camp (Rented House)
Photos of camp and facilities provided
First Aid Box Separate Kitchen with Gas Cylinder
Toilet Drinking Water facilities
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
II. Labour camp for workers of 60 KL OHT Site
Location: Near Primary School, Mainakhedi, Kothri
1 Accommodation - for 6 migrant workers; No women / families in the camp Facilities provided at camp site
• Type of living accommodation – Rented House (Pucca House)
• Camp area (living area) – 18 sq. m
• Cots
• Accommodation provided for 6 workers • Separate cooking area
• Cooking (Gas Cylinder)
• Drinking water • Bath rooms
• Toilets
• Septic tank and soak pit
• Drainage 2 Site layout plan
- Plan (rough / not to scale map) is shown below with camp boundary and facilities. - Site location with approach road
3 Site photographs
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Original site photographs
Labour camp (Rented House)
Photos of camp and facilities provided
First Aid Box Toilet cum Wash Room
Water Storage Drinking Water Facilities
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Attachment 3: List of clearances & statutory requirements
S. No Project related Status
A Construction/work related
1 Road cutting permit– MPRDC/PWD In process
B Labour safety / welfare related (indicate all as per the labour officer)
1 Labour license Obtained
2 Permit under BOCW Rules Obtained
3 Annual returns under BOCW Rules Obtained
C Safety / liability safety related (indicate all as per the contract)
1 Group insurance Available
2 Contractor All Risk (CAR) insurance Available
3 Medical insurance Available
D Others
1 Fitness certificate for vehicles, equipment used in construction Available
2 Pollution under control (PUC) certificates for vehicles and equipment Available
3 Driving licenses for drivers Available
4 Insurance for vehicles / equipment, as required Available
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Attachment 4: Contractor’s EHS Policy & Organization
1 Contractor agency has a EHS policy Yes / No
1 If yes, provide policy details
5. Policy statement:
6. EHS organization& responsibilities:
No
2 List safety risks anticipated in the project -
Area works (OHT / WTP etc.,)
• Trips and falls
• Head injury from falling objects • Confined work space
• Slope failure / trench collapse
• Road accidents
Linear works (pipelines)
• Slip, Trips and falls
• Falling of vehicle • Fall of person
• Collapse of Trench
3 List personal protection equipment provided to workers
PPEs Numbers Safety shoes 50 Nos. Gloves 40 Nos. Gloves for Bar Bending 80 Nos. Helmet 50 Nos. Gum Boots 40 Nos. Safety jacket 60 Nos. Safety belt 20 Nos. Nose Mask 30 Nos. Eye Protection Goggle 35 Nos. Total 405 Nos.
Yes
2 Contractor emergency procedure Yes Detail what steps/procedure to be adopted in emergency situation (e.g., accidents)
• For minor injury first aid box (available at site) will be serve the purpose.
• For major injury victim should be taken to nearest hospital by ambulance or by arranging local vehicle.
• In case of firefighting, people present in the site will be transferred to safer place and 1 or 2 responsible person will use the fire extinguisher to prevent fire.
Contact information, staff and responsibilities for emergency situations
Designation Staff name &
contact
Emergency responsibility
9. Safety Steward Mr. Ashish Agrawal +91-9928254311
Take care of victim and give first aid if
required.
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
10. Site Engineer Mr. Rajpal Sharma +91-7771003814
Inform the senior and assemble the
worker at safe place and call the
ambulance if required.
11. EHS Supervisor Md Mahboob
Hussain
+91-9934634361
Give necessary instructions to safety
steward and Site Engineer to handle
the situation.
12. Project manager Mr. Aakash Diggaj
+91-8225055999
Monitors the situation and report to
officials at PIU Level
3 Reporting procedure in case of work accidents
Safety Steward → Site Engineer → EHS Supervisor →Project Manager (Contractor) →Project Manager (PIU Bhopal)
Yes
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Attachment 5: Utility shifting/relocation
1 List work sites that require Utility shifting, relocation, temporary shut off
Remarks
1 Area work sites (OHT: 400 KL, 60 KL)
3. No utilities shifted / temporarily disturbed
2 Linear work sites (pipeline works)
3. No utilities shifted / temporarily disturbed
Attachment 6: Details of Construction Materials
S. No
Material Approximate quantity required (m3) for project
Source Indicate if source has all necessary government clearances
1 Aggregate 480 Cum Patel stone crusher (Pipakheri, Sehore)
Yes
2 Sand 310 Cum Patel stone crusher (Pipakheri, Sehore)
Yes
3 Steel 65 tonnes Real Ispat & Power Urla industrial area Raipur, Chhatisgarh
Yes
4 Cement 4500 Bags Maihar Cement Unit Sarlanagar, Satna-Madhya Pradesh
Yes
Attachment 7: Details of construction waste / debris / surplus soil
S. No
Waste likely be generated
Type of debris / waste
Approximate quantity
Indicate whether it will be reused / disposed off
In case of disposal, indicate disposal site name & location
1 Construction waste / debris
Steel 50 Kg Sold out to Scrap vendor
-
2 Surplus soil Soil/Moorum 25-30 Cum Reused in site development and backfilling
-
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
Attachment 8: Work site management for pipeline works
1. Detail of Pipeline work in project area- Diameter wise
Pipe Diameter (mm)
Length (m) Width of trench (m)
Depth of Trench (m)
Width of roads
(xx – xx m)
Type of roads
(earthen / BT / CC )
Excavation method (manual / mechanical)
CWRM- HDPE PN 8 (4,054 m)
75 357 0.55- 0.8 1.075 2.50 – 4.50 CC/BT/ Earthen
Mechanical
110 2854 0.55- 0.8 1.075 2.50 – 4.50 CC/BT/ Earthen
Mechanical
160 843 0.55- 0.8 1.160 2.50 – 4.50 CC/BT/ Earthen
Mechanical
Distribution Network- HDPE PN 10 (41,284 m)
75 25743 0.55- 0.8 1.075 2.50 – 4.50 CC/BT Manual/Mech
110 12631 0.55- 0.8 1.100 2.50 – 4.50 CC/BT Manual/Mech
160 1888 0.55- 0.8 1.160 2.50 – 4.50 CC/BT Manual/Mech
200 839 0.6- 0.9 1.200 2.50 – 4.50 CC/BT Manual/Mech
250 183 0.6- 0.9 1.250 2.50 – 4.50 CC/BT/Earthen Manual/Mech
2. Details of Roads in project area – town wise
(A) CWRM:
Town name / Type of road
Total width of roads (building line to building line)
Width of carriage way
Type of surface (BT/CC /WBM / Earthen)
Length of roads
Where pipe will be laid on road*
Kothri
National highways
N/A N/A N/A N/A N/A
State highways 7 m 4.75 m Earthen/ BT 1,000 m Road Shoulder
District / other roads (MDR)
N/A N/A N/A N/A N/A
Internal main roads (MPRRDA)
N/A N/A N/A N/A N/A
Internal sub-roads (Village road)
N/A N/A N/A N/A N/A
Streets 3- 4 m 2.5- 3 m Earthen/ CC/ BT
3,054 m Road shoulder/ One side of road carriageway
Total length 4,054 m
Package 1A (Kothri Town): Site Specific EMP Attachments 1-8
(B) Distribution Network:
Town name / Type of road
Total width of roads (building line to building line)
Width of carriage way
Type of surface (BT/CC /WBM / Earthen)
Length of roads
Where pipe will be laid on road*
Kothri
National highways
N/A N/A N/A N/A N/A
State highways 7 m 4.75 m BT 6,000 m Road Shoulder
District / other roads
N/A N/A N/A N/A N/A
Internal main roads
N/A N/A N/A N/A N/A
Internal sub-roads
N/A N/A N/A N/A N/A
Streets 3- 4 m 2.5- 3 m Earthen/ CC/ BT
35,284 m Road shoulder/ One side of road carriageway
Total length 41,284 m
103
Appendix 10: Monitoring Checklist Format (1 to 11) Being Used at Work Sites
104
105
106
107
108
109
110
111
112
113
114
115
116
117
Checklist 7: Accident Reporting Cum First Aid Form Sr. No.
Name of Town
Date of the Accident and Time
Nature and Extent of Injury
Number of Persons injured/Died
Action Taken
Date reporting to PIU/PMU/PMC and time
Remarks
Checklist 8: Grievances Reporting Format Stage - 1 Contractor Level Stage-2 PIU level Stage-3 PMU level Remarks
Sr. No.
Name of
Town
Date of Grievance reported
Name of Person/Address/Mob.
No.
Type of Grievance
Action Taken
(Yes/No)
Whether resolved
or not
If not resolved (Date of
Forwarding to PIU)
Date of Grievance received
Type of
Action taken
Result of Action
(Resolve or not
resolve)
If not resolved (Date of
Forwarding to PMU)
Date of Grievance received
Recommendation of Committee
Date of
Action Taken
Checklist 9: Change of Location of Subproject Components and its Impact Sr. No.
Name of Town
Particulars Details of Proposed component as per DPR
Details of sub-component as per DBO Contractor
Any change recommended by DBO Contractor (If yes detail of that sub component with approval)
Design Submit/Approved
Land Details with Khasra No. and Map (P-II form)
Photograph Whether any Negative Impact on community/person reported (Impact Assessment/Transect walk required)
Source
Weir/Anicut/Reservoir
Intake Well cum pump house
Raw water pipe line
Water Treatment Plant
Clear water sump well
Clear water pipe line
118
Checklist 9: Change of Location of Subproject Components and its Impact Sr. No.
Name of Town
Particulars Details of Proposed component as per DPR
Details of sub-component as per DBO Contractor
Any change recommended by DBO Contractor (If yes detail of that sub component with approval)
Design Submit/Approved
Land Details with Khasra No. and Map (P-II form)
Photograph Whether any Negative Impact on community/person reported (Impact Assessment/Transect walk required)
Storage Structure (OHT/GSR/Sump Well)
1-
2-
3-
Distribution Network
House Hold Connections
Checklist10: Details about Unanticipated Environment & Social Impact on Property, Livelihood, Environment etc. reported during Construction Sl. No. Name
of the Town
Subproject component Any Impact Reported: Yes/No
Type of Impact: Permanent or Temporary
In case of Temporary Impact: (i)on property or structure, (ii)on livelihood, (iii) any other, specify………
Whether such type of Social Impacts are reported to PIU/PMU/PMC (Yes/No)
What type of Assistance or Compensation given to affected assets
Details about affected assets or Affected Persons
Checklist 11: Capacity Building Sr. No. Orientation of subproject with regard to ADB Safeguard policy Status (Yes/No) Provide Details with evidence
(Date, Venue, Photographs and signature of participants)
Number of Participants (Male/ Female)
1 ULB staffs and elected body
2 Other Stakeholders (town level NGO/Govt. Department etc.)
3 Public Consultation During Execution by DBO Contractor
4 Community Consultation 1
Community Consultation 2
Community Consultation 3
Community Consultation 4
Community Consultation 5
119
Appendix 11: Summary of Consultation with Stakeholders at Subproject Towns Under Package 1A
S. No. Date Location No. of Participants
Participants Topics Discussed Issues raised / Remarks
1 21.12.2018 ULB
office,
Boda
10 M=09 F=01
Elected representatives, Chairperson of ULB, Chief Municipal Officer, Engineers
• CMO has informed that water supply is being manhandled and there will be more problems from March, by the end of March there can be a lot of trouble for drinking water, Demand of water to be fulfilled by the tankers.
• System for current water supply
• Information about the proposed project was given.
• Chairman, ULB- Boda has informed that the construction work of water supply scheme is going on very slow, which requires the need for speed.
• Elected representatives and officials of ULB demanded for providing the raw water from the Kunwar chain Sagar dam by the last week of March for other utilities of houses/peoples; and suggest the contractor’s team for laying of RWRM before the summer season.
• Chairman requested to provide soft copy of the document related to the water supply scheme, so that they can get complete information about the project.
2 05.03.2019 Mata
Mandir,
Ward No.
08, Boda
07 M=03 F=04
General Community • System for current water supply
• Information about the proposed project was given.
• Possible positive and negative impacts from the implementation of the project.
• It was also told that the meter will be used for the record of the consumption of every house water.
• Due to poor people belonging to scheduled caste community, demand for apology or reduction in monthly water tax was sought.
• Demand for public stand post.
3 24.04.2019 Narsingh
Mohalla,
22 M=22
General Community • System for current water supply
• Due to poor people belonging to scheduled caste community,
120
Ward No.
09, Boda
F=00 • Information about the proposed project was given.
• Possible positive and negative impacts from the implementation of the project.
• It was also told that the meter will be used for the record of the consumption of every house water.
demand for apology or reduction in monthly water tax was sought.
• Demand for public stand post.
4 21.12.2019 ULB
office,
Kurawar
11 M=10 F=01
Elected representatives, Chairperson of ULB, Chief Municipal Officer, Engineers
• CMO has informed that water supply is being manhandled and there will be more problems from March, by the end of March there can be a lot of trouble for drinking water, Demand of water to be fulfilled by the tankers.
• Chairman requested to provide soft copy of the document related to the water supply scheme, so that they can get complete information about the project.
• Discuss with Grievance related issue
• Chairman, ULB- Boda has informed that the construction work of water supply scheme is going on very slow, which requires the need for speed.
• Elected representatives and officials of ULB demanded for providing the raw water from the Kunwar chain Sagar dam by the last week of March for other utilities of houses/peoples; and suggest the contractor’s team for laying of RWRM before the summer season.
5 18.12.2019 Ward No.
06,
Kurawar
13 M=10 F=03
Local Community • To remove the water line for tap water scheme for the city
• Participants demand water management
• The team told the local people that the present project is for urban water system water project related to you is under consideration by the government under the rural water system
• Facing severe water crisis for drinking water
121
• Information about Grievance Redressal committee
6 11.05.2018 Ward No.
05,
Kurawar
10 M=00 F=10
Local Community • System for current water supply
• Information about the proposed project was given.
• Possible positive and negative impacts from the implementation of the project.
• It was also told that the meter will be used for the record of the consumption of every house water
• Information about Grievance Redressal committee
• Due to poor people belonging to scheduled caste community, demand for apology or reduction in monthly water tax was sought.
• Demand for public stand post.
7 10.02.2019 Ward No. 07, Kothri
15 M=11 F=04
Local Community • Information about the proposed project.
• Possible positive and negative impacts from the implementation of the project.
• System for current water supply
• Successful operation and maintenance of proposed project with community participation.
• Facing severe water crisis for drinking water
8 10.03.2019 Ward No.
08, Kothri
08 M=08 F=00
Local Community • To remove the water line for tap water scheme for the Kothari town
• Participants demand water management
• The team told the local people that the present project is for urban water system. The water project related to you is under consideration by the
• Facing severe water crisis for drinking water
122
government under the rural water system
9 10.04.2019 Ward No.
07, Kothri
11 M=07 F=04
SC Community • System for current water supply
• Information about the proposed project was given.
• Possible positive and negative impacts from the implementation of the project.
• Successful operation and maintenance of proposed project with community participation
• Facing severe water crisis for drinking water
123
Appendix 12: Stakeholder Consultation Photographs & List of Participants
1. Meeting at ULB office, Boda on 21.12.2018
124
2. Consultation at Mata Mandir, Ward no. 08 on 05.03.2019 (Boda)
125
3. Consultation at Narsingh Mohalla, Ward no. 09 on 24.04.2019 (Boda)
126
4. Meeting at ULB office, Kurawar on 21.12.2018
127
5. Consultation at ward no. 05 on 18.12.2018 (Kurawar)
128
6. Consultation at Ward no. 5 on 11.05.2018 (Kurawar)
129
7. Consultation at ward no. 07 on 10.02.2019 (Kothri)
130
8. Consultation at ward no. 08 on 10.03.2019 (Kothri)
131
9. Consultation at ward no. 07 on 10.04.2019 (Kothri)
132
133
134
Appendix 13: Office Order of EA to Establish GRC at subproject town level
135
136
Summary Translation in English - Office Order of EA to Establish GRC at subproject town level
(i) Translation of Office Order No 3934 dated 06.03.2017 signed by Commissioner, Urban Administration and
Development, Madhya Pradesh
a. The Grievance Redressal Committees to be formed in all the externally funded projects to resolve the public grievances during
operation, implementation and maintenance phase. In the above committee, following members will be nominated:
• Project Officer, Project Implementation Unit (PM, PIU), MPUDC will be chairman and Nodal Officer of the committee
• An elected member nominated by Mayor in Council/ President in Council of associated Urban Local Body (ULB).
• A Social Worker nominated by Mayor in Council/ President in Council of associated Urban Local Body
• Commissioner of associated Urban Local Body/Chief Municipal Officer or Community Development Officer/Community Organizer
of Urban Local Body.
• Community Development Officer (CDO), Project Implementation Unit (PM, PIU), MPUDC will be chairman and Nodal Officer of the
committee
Committee should have at least one-woman member.
b. The process of grievance redressal should be as follows:
1. Complain shall be registered by affected person at – office of urban local body/or PIU/or Contractor through personal visit /or
telephonically by disclosing his/her identity or address.
2. Damage/or loss of livelihood/property/quality of services affected during construction/or operations and maintenance period of the
project shall be resolved by the Grievance Redressal Committee. Only Corruption related issues will not fall under the preview of
Grievance Redressal Committee to be resolved.
3. Compliance shall be addressed to the Project Manager of Project Implementation Unit. Site Engineer and Public Relation Officer will
be responsible to ensure compliance as per instructions of the Project Manager.
4. Grievance shall be resolved within two days of registration of complain by affected person. Complainant should be informed if
Grievance Redressal is taking time due to any technical reason.
5. Complainant can appeal to Grievance Redressal Committee with relevant documents in case grievance is neither resolved within two
working days nor affected person is informed about the delay in process.
6. Nodal officer can organize grievance redressal meeting to solve one or more problems but they have to avoid unnecessary delay in
resolving the problem. Complain will be presented by the project manager to review by the committee members and their decision
shall be discussed against each complain. Proceedings of grievance redressal meeting shall be documented. Decision to the
complainant will be informed in writing. Execution of decision should be performed either directly by PIU or with the support of
contractors.
137
Appendix 14: Letter to PIU From MPUDC (IA) to Establish GRC at subproject town level
138
Summary Translation in English - Letter to PIU From MPUDC (IA) to Establish GRC at
subproject town level
Letter No 1881 dated 31.05.2018 signed by EnC, MPUDC to Project Managers, PIUs(all), MPDUC Regarding formation of Grievance
Redressal Committees
Ref.: Order No 3934 dated 06.03.2017 of Directorate of Urban Development
In compliance of the above office order, the Grievance Redressal Committees to be formed in all the externally funded projects to resolve the
public grievance during operation, implementation and maintenance phase.
In compliance of above, please ensure formation of Grievance Redressal Committees in the sub projects where contract have been awarded. This
should be followed for all the future sub projects awarded.
139
Appendix 15: Letter to ULB From MPUDC to Establish GRC at subproject town level
140
Summary Translation in English - Letter to ULB From MPUDC to Establish GRC at
subproject town level
Translation of Letter No 1108 dated 23.06.2017 signed by EnC, MPUDC To Commissioner/Chief Municipal Officer, All ULBs regarding
formation of Grievance Redressal Committees
Ref.: Order No 3934 dated 06.03.2017 of Directorate of Urban Development
In compliance of the above office order, the Grievance Redressal Committees to be formed in all the externally funded projects during
operation, implementation and maintenance phase in the chairmanship of Project Officer, Project Implementation Unit (PM, PIU), MPUDC. In the
above committee, following members from the ULBs will be nominated:
• An elected member nominated by Mayor in Council/ President in Council of associated Urban Local Body (ULB).
• A Social Worker nominated by Mayor in Council/ President in Council of associated Urban Local Body
• Commissioner of associated Urban Local Body/Chief Municipal Officer or Community Development Officer/Community Organizer
of Urban Local Body.
It is therefore requested to nominate above members with immediate effect for form GRC.
141
Appendix 16: Letter for GRC Established in Boda Nagar Parishad
142
Summary Translation in English - Letter for GRC Established in Boda Nagar Parishad
In Compliance of order no 3937, dated 06.03.2017 the Grievance Redressal Committee has been formed for externally funded project MPUSIP during operation, implementation and maintenance phase in Boda town. The members of the committee are as follows:
S. No. Name Designation Post in GRC
1 Mr. V.K. Tiwari Project Manager, PIU Bhopal
Chairman/ Nodal officer
2 Mr. Rakesh Shandilya CDO/ PRO, PIU Bhopal Secretary
3 Mrs. Seema Verma Elected Member nominated by President of Council
Member
4 Mr. Vishnu Prasad Gudniya
Social Worker Member
5 Mr. Md. Saleem Khan Chief municipal officer (CMO), ULB Boda
Member
143
Appendix 17: Letter for GRC Established in Kurawar Nagar Parishad
144
Summary Translation in English - Letter for GRC Established in Kurawar Nagar Parishad
In Compliance of order no 3937, dated 06.03.2017 the Grievance Redressal Committee has been formed for externally funded project MPUSIP during operation, implementation and maintenance phase in Kurawar town. The members of the committee are as follows:
S. No. Name Designation Post in GRC
1 Mr. V.K. Tiwari Project Manager, PIU Bhopal
Chairman/ Nodal officer
2 Mr. Rakesh Shandilya CDO/ PRO, PIU Bhopal Secretary
3 Mr. Dinesh Mandloi Elected Member nominated by President of Council, ULB Kurawar
Member
4 Mrs. Ramadevi Jagirdar Social Worker, ULB Kurawar
Member
5 Mr. Ashok Singh Thakur Chief municipal officer (CMO), ULB Kurawar
Member
145
Appendix 18: Letter for GRC Established in Kothri Nagar Parishad
146
Summary Translation in English - Letter for GRC Established in Kothri Nagar Parishad
In Compliance of order no 3937, dated 06.03.2017 the Grievance Redressal Committee has been formed for externally funded project MPUSIP during operation, implementation and maintenance phase in Kothri town. The members of the committee are as follows:
S. No. Name Designation Post in GRC
1 Mr. V.K. Tiwari Project Manager, PIU Bhopal
Chairman/ Nodal officer
2 Mr. Rakesh Shandilya CDO/ PRO, PIU Bhopal Secretary
3 Mr. Rupesh Patel Elected Member nominated by President of Council, ULB Kothri
Member
4 Mrs. Manisha Manakchand Jain
Vice Chairman, ULB Kothri
Member
5 Mr. Nandkishore Jharvariya
Chief municipal officer (CMO), ULB Kothri
Member
147
Appendix 19: Grievance Registration Form
For Complainant
Date of Complain Registration Place of Complain registration Name of the Project Town
Personal Details
Name Sex (M/F) Age (in completed years)
Home Address:
Contact Number:
E mail (if any):
Complain/Grievance details
How do you want us to update you on the grievance registered with us: Phone / SMS/ Letter/ E-
mail/Personal Interaction
For Office use Only
Registered by (Name of grievance registered officer)
Mode of Communication – Personal visit/ Phone/ SMS/Letter/Email
Reviewed by -Name and position of personnel reviewed grievance
Action taken:
If action not taken then forwarded to:
Whether action taken disclosed-Yes/No
Means of disclosure: Phone / SMS/ Letter/ Email /Personal interaction