4771 mark scheme june 2005 mark scheme 4771 …mei.org.uk/files/papers/all packs/ms_mei_d1.pdf4771...
TRANSCRIPT
4771 Mark Scheme June 2005
Mark Scheme 4771June 2005
4771 Mark Scheme June 2005
1. (i) Any connected tree. 12 connections (ii) 14 connections (iii) e.g. He might be able to save cable by using it. e.g. To avoid overloading. (iv) Yes. A minimum connector is a tree. This gives the min number of arcs (n–1). This gives the minimum no of connections (2(n–1)).
M1 A1 B1 B1 B1 B1 B1 B1
2.
(i) Janet John (ii) Yes Janet’s route traces west and south walls plus
"attachments". John’s route traces north and east walls plus
"attachments". − or equivalent (Any “islands” are irrelevant.) (iii) Yes (iv) Yes All avenues covered by forward and backward pass (i.e.
by John's original route + Janet's route).
M1 A1 A1 M1 A1 B1 B1 B1
4771 Mark Scheme June 2005
3. (i) (ii) Critical − A, D and C (iii) Total float for B = 2 Independent float for B = 1 Total float for E = 1 Independent float for E = 0
M1
A1 B1 B1 B1 B1 both total floats A1 B's independent A1 E's independent
5
D A 3
0 3 5 0 5
3
4
C 1 2
23 E B
4771 Mark Scheme June 2005
4. (i) P Q R S T U V 45 14 12 15 25 31 49 P T S C V U S C (ii) PV ST CR RT UV Length = 80 TU QR (iii) CP reduced to 26 CV reduced to 34 (iv) UV replaced by PQ New length = 74 (v) Q Semi-Eulerian. (Order of P changed from 3 to 4, but
order of Q changed from 2 to 3 − so still 2 odd vertices.) or Cross the bridge and proceed as before or A valid route
B1 starting at C M1 Dijkstra A1 labels A1 order of labelling A1 working values B1 B1 B1 M1 A1 first 5 A1 last 2 B1 length B1 (both and no more) B1 M1 A1
P
U
S R
C
Q
14
V
20
22 818
8
16
16
10 T
14
10 12
15
15 0 1
14 3
26 12 2
12
14
31
45 7 45
25 5 25
31
15 4
49 49 6 8
4771 Mark Scheme June 2005
5. (i) eg. 00–19 → 0 20–49 → 1 50–69 → 2 70–84 → 3 85–99 → 4 (ii) 1, 0, 2, 3, 1, 3, 4, 3, 0, 0 (iii) eg. 00–15 → 0 16–39 → 1 40–63 → 2 64–95 → 3 96–99 → ignore (iv) 1, 0, 1, 0, 1, 1, 3, 3, 2, 2 (v) Day 0 1 2 3 4 5 6 7 8 9 10 Stock 3 3 3 2 0 0 0 0 0 2 4 Disptd 0 0 0 0 1 0 2 1 0 0 0 (vi) Day 0 1 2 3 4 5 6 7 8 9 10 Stock 3 3 3 2 0 1 0 0 1 3 5 Disptd 0 0 0 0 0 0 0 1 0 0 0 Only 1 disappointed under new policy against 4 under
old policy. Not definitely, but pretty convincingly.
M1 sca at proportions A1 M1 A1 M1 missing some A1 times B1 one ignored B1 rest M1 A1 A1 M1 using both ret dists A1 A1 B1 B1
4771 Mark Scheme June 2005
6. (i) Let f be the number of litres of Flowerbase produced B1
M1 A1
Let g be the number of litres of Growmuch produced Max 9f + 20g s.t. 0.75f + 0.5g ≤ 12000 M1 A1
A1
f + 2g ≤ 25000 (ii) B1 labels + scales
B1 B1 lines B1 shading
M1 A1
Max profit = £2500 by producing 12500 litres of
Growmuch (iii) No effect
B1 M1 A1
(iv) No effect The profit on Flowerbase will be reduced by more than
that suffered by Growmuch, since it uses more fibre. The objective gradient will thus increase from −9/20, making it even less attractive to produce any Flowerbase.
(v) £3000
B1
f
2500
24000
12500
16000 1440
25000
g
(11500, 6750)2385
Mark Scheme 4771January 2006
1.
2. (ii) Merges ordered lists to give an ordered list (iii) 7 (iv) Max = x + y – 1 Min = min (x, y)
M1 sca A1 to first step 3 inc. A1 to second step 3 A1 rest B1 B1 B1 B1
(i) & (ii) Critical: A, E (iii) A, E and D 6 days
B1 C OK B1 D OK B1 E OK M1 early and late A1 times B1 critical B1 B1
0 0
5 5
5 5
5 5
10 10B 3
A 5
C 3
D 4
E 5
(i)
Step number
List 1 List 2 A B List 3
1 3 4 4 3 4 3 3
2, 34, 35, 56 34, 35, 56 35, 56 35, 56 35, 56 56 56
13, 22, 34, 81, 90, 92 22, 34, 81, 90, 92 22, 34, 81, 90, 92 34, 81, 90, 92 81, 90, 92 81, 90, 92 90, 92 90, 92 90, 92
2 34 34 34 35 35 56 56
13 13 22 34 34 81 81 81
2 2, 13 2, 13, 22 2, 13, 22, 34 2, 13, 22, 34, 34 2, 13, 22, 34, 34, 35 2, 13, 22, 34, 34, 35, 56, 81, 90, 92
3. (i) Ins and outs One more out than in at D. Vice-versa at A. Start at D and end at A (ii) Existence – A B D C A Uniqueness – Only alternative is A B C …!!! Extra arc – New possibility A D C B … !!! (iii) B D C A B
M1 A1 B1 B1 M1 A1 A1 B1
4. (i) 12.5 kg 250 g (of butter) 10 kg 3 kg (of sugar) (ii) Identification of variables e.g. Let x = kg of toffee made Let y = kg of fudge made Max x + y st 100x + 150y ≤ 1500 800x + 700y ≤ 10000 Make 9 kg toffee and 4 kg fudge (iii) 12.5 kg of toffee and no fudge – either by comparing
68.75 with 67.50 with 45, or by a gradient argument Toffee price must decrease by £0.36, or to £5.14.
B1 B1 B1 B1 B1 B1 B1 B1 axes labelled and
scaled B1 butter line B1 sugar line B1 shading B1 max x+y + solution M1 A1 B1 B1
x
y
10
2714
12.5 15
(9,4)
5. (i) Total length = 57 miles Might be used to determine where to lay pipes or cables to
connect the towns. (ii) Shortest route: AGE Length: 24 (iii) Shortens mst to 53 miles (√ by 4) New shortest route ABGE – 23 miles (√ by 1)
M1 A1 selections A1 order of selecting A1 deletions B1 B1 B1 M1 sca Dijkstra A1 labels A1 order of labelling A1 working values B1 B1 B1 B1 B1
1 2 5 6 4 7 3 A B C D E F G
A – 10 – – – 12 15 B 10 – 15 20 – – 8 C – 15 – 7 – – 11 D – 20 7 – 20 – 13 E – – – 20 – 17 9 F 12 – – – 17 – 13 G 15 8 11 13 9 13 –
A
B C
D
E F
G
A
B C
D
E F
G
10
15
7
20
17
12
15
8 11
20
9 13 13
5 24
29 24
3 12
12
1 0
30 28
25
2 10
10
4 15
15
6. (i) e.g. 0 – 6 petrol 7 – 9 other (ii) e.g. 0 – 2 1 min 3 – 6 1.5 mins 7 – 8 2 mins 9 2.5 mins (iii) e.g. 00 – 13 1 min 14 – 41 1.5 mins 42 – 69 2 mins 70 – 83 2.5 mins 84 – 97 3 mins 98, 99 reject Two digits – fewer rejects (v) 24.5/10 = 2.45 mins
B1 M1 A1 M1 some rejected A1 2 rejected A1 B1 B1 arrival times M1 types M1 service start M1 service duration M1 service end M1 time in shop A1 M1 A1
(iv) Customer number
Inter-arrival time
Arrival time
Type of customer
Arrival at till
Time at till
Departure time
Queuing + paying
1 1 1 F 1 1 2 1 2 0.5 1.5 N 2 2 4 2.5 3 3.5 5 N 5 1.5 6.5 1.5 4 3 8 F 8 1.5 9.5 1.5 5 1 9 F 9.5 1 10.5 1.5 6 0.5 9.5 F 10.5 1 11.5 2 7 1.5 11 F 11.5 2.5 14 3 8 2 13 N 14 2.5 16.5 3.5 9 2 15 F 16.5 2 18.5 3.5
10 0 5 15 5 F 18 5 1 5 20 4 5
Mark Scheme 4771June 2006
4771 Mark Scheme June 2006
(i) Least weight route: A F B G E D Weight = 10 (ii) 11 From working value. Can't be bettered since new least
weight must be bigger than 10.
M1 sca Dijkstra A1 labels A1 order of labelling A1 working values B1 B1 B1 B1
2.
(i) e.g. a tree (ii) 13 (iii) 14 (iv) e.g.
M1 A1 B1 B1 B1 M1 A1 A1
G F
E D
C
B A
2
5
3
6 12
1
6
1
8 3
2
7
1 0
3 35 3
2 22
4 55
6 912 10
7 10
11 10
5 67 6
×
× × × × ×
×
×
× ×
× × ×
×⊗ ⊗
4771 Mark Scheme June 2006
3. (i) M = 1 f(M) = –1 L = 1 M = 1.5 f(M) = 0.25 R = 1.5 (ii) Solves equations (Allow "Finds root 2".) (iii) A termination condition
B1 B1 B1 B1 B1 B1 B1 B1
4.
(i) & (ii) Critical activities: A, C, E (iii) (iv) 2 hours (resource smoothing on A/B, but extra time needed for
D/E). (v) P – Q – R – S Q, R T Q, R U R V S, T, U W U
M1 sca activity-on-arc A1 A, B, C A1 D A1 E B1 forward pass (1.25 at end of B/dummy) B1 backward pass (1.25 at start of dummy/D) B1 M1 A1 M1 A1 B1 B1 B1 B1 B1
0 0
1.25 1.25
1 1
1.75 1.75
1.25 1.25
B 0.5
A 1
C 0.25
D 0.25
E 0.5
1
0.5 hours
people
A
B
C
D
E E A
4771 Mark Scheme June 2006
5. (i) Let x be the number of hours spent at badminton Let y be the number of hours spent at squash 3x + 4y ≤ 11 1.5x + 1.75y ≤ 5 (ii) (iii) x + 2y (iv) 22/4 > 5 > 10/3, so 5.5 at (0, 11/4) (v) Squash courts sold in whole hours 1 hour badminton and 2 hours squash per week (vi) 3 hours of badminton and no squash
B1 B1 B1 B1 axes labelled and
scaled B1 line B1 line B1 shading B1 intercepts B1 (1, 2) B1 M1 A1 B1 B1 B1 B1
x
y
11/3 10/3
11/4 20/7
(1, 2)
4771 Mark Scheme June 2006
6. (i) year 1: 00 – 09 failure, otherwise no failure year 2: 00 – 04 year 3: 00 – 01 year 4: 00 – 19 year 5: 00 – 19 year 6: 00 – 29 (ii)(A) (B) 0.6 (iii) (A) if no failure then continue after year 3 – but using rules
for yrs 1 to 3 (B) (C) 0.3 (iv) more repetitions
M1 A1 A1 M1 ticks and crosses A1 run 1 A1 runs 2–4 A1 runs 5–7 B1 runs 8–10 B1 B1 B1 M1 A1 runs 1–5 A1 runs 6–10 B1 B1
Run 1
Run 2
Run 3
Run 4
Run 5
Run 6
Run 7
Run 8
Run 9
Run 10
year 1
√ √ √ √ x √ √ x √ √
year 2
√ √ √ √ √ √ √ √
year 3
√ √ √ √ √ √ √ √
year 4
√ √ √ x √ √ x √
√ √ √ √ √
Run 1
Run 2
Run 3
Run 4
Run 5
Run 6
Run 7
Run 8
Run 9
Run 10
year 1
√ √ √ √ x √ √ x √ √
year 2
√ √ √ √ √ √ √ √
year 3
√ √ √ √ √ √ √ √
year 4
√ √ √ √ √ √ x √
√ √ √ √ √ √ √
D1 June ‘06 6(ii) (A) Run 1 Run 2 Run 3 Run 4 Run 5 Run 6 Run 7 Run 8 Run 9 Run 10 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 6(iii) (B) Run 1 Run 2 Run 3 Run 4 Run 5 Run 6 Run 7 Run 8 Run 9 Run 10 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6
83
Mark Scheme 4771January 2007
4771 Mark Scheme Jan 2007
84
1. (i) (ii) Any two of 1 or 2 or 3 or 5 or 7 (iii)
(iv)
(v) A tree
B1 B1 B1 M1 branching tree A1 M1 branching tree A1 B1
2. (i) 109; 32; 3; 523; 58 32; 3; 109; 58; 523 4 comparisons and 3 swaps 3; 32; 58; 109; 523 3 and 2 3; 32; 58; 109; 523 2 and 0 3; 32; 58; 109; 523 1 and 0 10 and 5 in total (ii) 523; 109; 58; 32; 3 10 swaps (iii) 1.5 × 1002 = 15000 seconds = 4 hrs 10 mins
M1 A1 only if all iterations
completed B1 B1 B1 B1 M1 A1 hours and minutes
3. (i) e.g. 0, 1 → A 2, 3 → B 4, 5 → C 6, 7 → D 8, 9 → E (ii) e.g: 3, 4, 4, 4, 1 (iii) In the above simulation mean = 3.2 (Correct expectation is 2.5 – geometric rand variable) (iv) More repetitions
M1 A1 proportions OK B1 efficient M1 A1 M1 A1 B1
4771 Mark Scheme Jan 2007
85
4. (i) (ii) See above Critical activities: A; B; D; F; G; I; K Duration = 46 (iii) E: total float = 1; independent float = 1 H: 1 and 0 J: 14 and 13 C: 2 and 2 (iv) Tiler (I) – 2 days – £500 Electrician (D) – 1 day – £300 Bricklayer (B) – 1 day – £350
M1 activity-on-arc A1 single start and
end A1 dummy 1 A1 dummy 2 A1 rest M1 A1 forward pass M1 A1 backward pass B1 critical activities B1 duration B1 total floats B1 independent floats B1 tiler B1 electrician B1 bricklayer
10 10 17 17
0 0
22 22
41 41
30 31
31 31
28 28 22 22 A 10
B 7
C 10
D 5 E 4
F 6
H 2
G 3
I 10
J 2 46 46
K 5
4771 Mark Scheme Jan 2007
86
5. (i) Let x be the number of m2 of lawn. Let y be the number of m2 of flower beds. x + y ≥ 1000 0.80x + 0.40y ≤ 500, i.e. 2x + y ≤ 1250 y ≥ 2x x ≥ 200 Minimise 0.15x + 0.25y (ii) & (iii) Lay 250 m2 of lawn and 750 m2 of flower beds. Annual maintenance = £225. (iv) Intersection of y ≥ 2x & area constraint is at
(333.33,666.67) so max useful capital is £533.33. So £33.33.
B1 B1 B1 B1 B1 B1 B1 B1 axes labelled +
scaled B4 lines B1 shading M1 A1 B1 (allow £533.33)
x 1000 625
1250
1000
200
y
(200,800)
(200,850)
(250,750)
230
242.5
225
4771 Mark Scheme Jan 2007
87
6. (i) DtoE; BtoD; CtoE; DtoF; AtoB Total length = 20 (iii) e.g. Total length = 37 (iii) Lengths are 27 and 28. Shorter and more nearly equal.
M1 A1 no BC nor BE A1 B1 B1 B1 reduced table M1 delete/select/delete A1 first 2 rows A1 rest of table A1 order B1 B1 B1 B1 B1 B1
1 3 4 6 2 5 A B C D E F A – – – – 12 – B – – 5 – 6 6 C – 5 – 8 – 7 D – – 8 – – – E 12 6 – – – 7 F – 6 7 – 7 –
F
E D
C
B A
F
E D
C
B A
Mark Scheme 4771June 2007
94
4771 Mark Scheme June 2007 1. (i) (ii) No. Two arcs AC. (iii)
(iv) No. ABDC(train)A is a cycle.
M1 4 nodes and 5 arcs A1 M1 A1 M1 5 nodes and 5 arcs A1 M1 A1
D C
B A
D C(train)
B A
C(bus)
2. (i) Rucksack 1: 14; 6 Rucksack 2: 11; 9 final item will not fit. (ii) Order: 14, 11, 9, 6, 6 Rucksack 1: 14; 11 Rucksack 2: 9; 6; 6 (iii) Rucksack 1: 14; 9 Rucksack 2: 11; 6; 6 e.g. weights.
M1 6 must be in R1 A1 B1 B1 ordering M1 11 in R1 A1 B1 B1
3. Optimum of 15.4 at x = 6.8 and y = 0.6.
B1 axes scaled & used M1 lines A1 B1 shading M1 two intersection A1 points M1 solution A1 (or by using the objective gradient to identify the optimal point)
2.8 4
7 8 14
(4, 2)
(6.8, 0.6) 8.4
14
14
15.4
x
y
95
4771 Mark Scheme June 2007 4. (i)
Activity Duration (minutes)
Immediate predecessors
A Rig foresail 3 – B Lower sprayhood 2 – C Start engine 3 – D Pump out bilges 4 C E Rig mainsail 1 B F Cast off mooring ropes 1 A, C, E G Motor out of harbour 10 D, F H Raise foresail 3 A I Raise mainsail 4 E J Stop engine and start sailing 1 G, H, I
(ii)
Critical activities: C; D; G; J Project duration: 18 minutes
(iii) H and I (iv) 25 mins Must do A, B, E, C, F, D (in appropriate order) then H and I with G,
then J. (v) 18 mins
e.g. Colin does C, D Crew does A, B, E, F Thence G et al
B1 A, B, C, D, E, H & I B1 F B1 G and J M1 A1 forward pass M1 A1 backward pass
B1 B1 B1 B1 B1 B1 B1 B1 B1
B 2
A
F 1 3 6
2 5 0 0
3 6
3 3 7 7
17 173 6 C 3
G 10
D 4
H 3
18 18
J 1 I 4
E 1
96
4771 Mark Scheme June 2007 5. (i) & (ii) Route: G A F C D Weight: 17 (iii) Route: G B C F E D or G B A E D Weight: 6 Any capacitated route application. (iv) Compute min(label, arc) and update working value if result is
larger than current working value. Label unlabelled vertex with largest working value.
M1 A1 arcs A1 arc weights M1 Dijkstra A1 labels A1 order of labelling A2 working values
B1 B1 B1 B1 B1 B1 B1 B1
F
E D
C
B
A
G 11
10 3 8 5
2
7
6
6
5
14
2 55
1 0 4 1414
6 15 15
7 17 5 14 15 14
3 8 8
or 4
or 5
19 17 if E is fourth
20
97
4771 Mark Scheme June 2007 6. (i)(a) e.g. Dry: 00 – 39 Wet: 40 – 69 Snowy: 70 – 99 (b) e.g. Dry: 00 – 19 Wet: 20 – 69 Snowy: 70 – 99 (c) e.g. Dry: 00 – 27 Wet: 28 – 55 Snowy: 56 – 97 Reject: 98 & 99 (ii) D (today) → D → S → S → W → S → D → D (iii) 3/7 (or 4/8) (iv) a (much) longer simulation run, with a "settling in" period ignored.
M1 proportions A1 efficient M1 proportions A1 efficient M1 reject some A1 proportions A1 reject 2 M1 applying their rules
sometimes A1 dry rules A1 wet rules A1 snowy rules B1
(v) Defining days as dry, wet or snowy is problematical. Assuming that the transition probabilities remain constant. Weather depends on more than just previous day's weather
B1 B1 B1 B1
98
4771 Mark Scheme January 2008
58
4771 Decision Mathematics 1
1 (i) 6 routes M→A→I→T→Pi→C M→A→I→T→Pi→R→C M→A→I→T→Pi→H→R→C M→V→I→T→Pi→C M→V→I→T→Pi→R→C M→V→I→T→Pi→H→R→C (ii) 6 routes M→A→I→Pa→Pi→C M→A→I→Pa→Pi→R→C M→A→I→Pa→Pi→H→R→C M→V→I→Pa→Pi→C M→V→I→Pa→Pi→R→C M→V→I→Pa→Pi→H→R→C (iii) M→V→I→Pa→Pi→H→R→Pi→C A R→H (iv) e.g. P→T→I→V→M→A→I→Pa→P→H→R→C→P→R
B1 B1 B1 B1 B1 M1 ends at R A2 (–1 each
error/omission)
4771 Mark Scheme January 2008
59
2.
(i) lines shading (3.6, 0.6) 25.8 at (3.6, 0.6) versus 21 and 24 (or profit line) (ii) 25 at (3, 1)
B2 B1 B1 graph or sim. eqns M1 A1 B1 B1
y
x
4771 Mark Scheme January 2008
60
3.
y = 2008 c = 2008/100 = 20 n = 2008 – 19 x (2008/19) = 2008 – 19 x (105) = 13 k = 3/25 = 0 i = 20 – 5 – 20 / 3 + 19 × 13 + 15 = 271 i = 1 i = 1 – 0 = 1 j = 2008 + 502 + 1 + 2 – 20 + 5 = 2498 j = 6 p = – 5 m = 3 d = 23 So 23rd March
B1 B1 B1 B1 B1 B1 B1 B1
4771 Mark Scheme January 2008
61
4. (i) e.g. 0–3→brown 4–7→blue 8–9→green (ii) e.g. 0–1→brown 2–5→blue 6–7→green 8–9→reject (iii) e.g. Eye colours
Parent 1 brown
brown
brown blue
Parent 2 brown blue brow
n blue
Offspring brown
brown
brown
brown
brown
green blue gree
n brown
brown
brown blue brow
n green
brown green
brown blue brow
n green
brown blue
M1 A1 proportions OK A1 efficient M1 some rejected A2 proportions OK (–1 each error) A1 efficient B1 br/br→br (4 times) B1 br/gr→bl B1 gr/gr→gr M1 br/bl rule A1 application A1 application B1 bl/bl application M1 gr/bl rule A1 application
4771 Mark Scheme January 2008
62
5. (i)&(ii) e.g. time − 55 weeks critical − A; B; F; G; J (iii) 50 weeks (49 weeks if G crashed rather than H) (iv) E − 1 week F − 3 weeks J − 2 weeks (G − 1 week, if crashed) (v) £115000 (£121000)
M1 sca (activity on arc) A1 dummy activities + E
and F A1 A, B, C, D A1 G, H, I, J M1 forward pass A1 M1 backward pass A1 B1 cao B1 cao B1 M1 A3 A1
D
B 22
J 5
C 10
F 11
G 9 I 3
H 10 0
4
8 30
30
41
50 55
55 55
55 50
41
30
30 8
30
A 8
E 9
4771 Mark Scheme January 2008
63
6. (i) e.g. Total length = 2.2 km (ii) Prim: connect in nearest to connected set Kruskal: Shortest arc s.t. no cycles (iii) Arcs used: AD, DE, EF, FG, DI, IH, AB or DB, FC or BC Total length = 2.7 km (AB&FC) or 2.9 km (AB&BC) or 2.4 km
(DB&FC) or 2.6 km (DB&BC)
M1 connecting tree A1 DE A1 FC, FG A1 AD, DI, FH A1 2 of length 0.4 M1 A1 M1 name A1 description M1 Dijkstra A1 working values (see vertex G) A1 order of
labelling A1 labels M1 arcs counted A1 only once A1
0.2
0.2
0.2
0.2
0.1
0.1
0.1 0.1 0.3
A
B C
D E
F G
H I
0 1
0.7
0.3
2 0.3
0.6
0.4
3 0.4
0.9
4 0.6
1.0
1.5
5 0.7
1.1
6 0.9 1.1
7 1.0
8 1.1
9 1.1
0.2
0.2
0.2
0.2
0.1
0.1
0.1 0.1 0.3
A
B C
D E
F G
H I
4771 Mark Scheme June 2008
83
4771 Decision Mathematics 1 Solutions 1. Objective has maximum value of 24 at (20,4)
M1 A1 third line B1 shading B1 (0,20) and (22,0) B1 (9,14) B1 (20,4) M1 A1 solution or M1 A1 B1, B1 scale (implied OK), B1 profit line, B1 (20,4) M1 A1 (20,4) A1 (24)
x
y
(20,4)
(22,0)
(9,14)
(0,20) or by profit line
4771 Mark Scheme June 2008
84
2. (i)
X Y 5, 14, 153, 6, 24, 2, 14, 15 5, 14, 153 5, 2 5, 14, 6, 24,14, 15 5, 14, 24 5 14, 6, 14, 15, 14, 15 14, 6 14, 14
Answer = 14 Comparisons = 30 (ii)
X Y 5, 14, 153, 6, 24, 2, 14 5, 14, 153 5, 2 5, 14, 6, 24,14 5, 14, 24 5 14, 6, 14 14 14, 6 14
Answer = 14 Comparisons = 24 (iii) Median (iv) Time taken approximately proportional to square of length
of list (or twice length takes four times the time, or equivalent).
M1 A1 A1 M1 A1 A1 B1 B1
3. (i) T1→T2 T1→T3→T2
T1→T3 T1→T2→T3 T1→T2→T3→T4 T1→T3→T4 (ii) T4→T3→T2→T1 T4→T3→T1
T4→T3→T1→T2 T4→T3→T2 T4→T3 (iii) 22 (iv) 11
M1 A1 M1 A1 M1 allow for 23 A1 M1 halving (not 11.5) A1
4771 Mark Scheme June 2008
85
4. (i) e.g. 00–09→1 10–39→2 40–79→3 80–89→4 90–99→5 (ii) e.g. 00–15→1 16–47→2 48–55→3 56–79→4 80–87→5 88–95→6 96, 97, 98, 99 reject (iii) & (iv) Sim. no.
Cars arriving after Joe – time interval│number of passengers
Time to 15 passengers (minutes)
1 3│2 2│1 1│2 2│2 3│1 6 2 3│1 2│2 1│4 1│2 5│1 6 3 5│1 2│2 2│1 3│4 2│2 12 4 4│6 3│2 4│1 1│2 2│3 4 5 5│1 4│1 3│2 5│4 2│2 17 6 4│4 4│2 5│3 1│4 1│4 8 7 4│1 4│2 3│1 5│4 1│3 16 8 2│2 2│2 2│4 3│5 1│2 6 9 1│1 1│1 1│1 1│1 1│2 5
10 2│4 3│2 2│6 2│5 2│1 5 (v) 0.8 more runs
M1 A1 proportions OK A1 efficient M1 some rejected A2 proportions OK (–1 each error) A1 efficient M1 A2 (–1 each error) M1 simulation A1 time intervals A1 passengers A1 time to wait
B1 B1
4771 Mark Scheme June 2008
86
5. (a)(i) Activity D. Depends on A and B in project 1, but on A, B and C in
project 2. (ii) Project 1: Duration is 5 for x<3, thence x+2. Project 2: Duration is 5 for x<2, thence x+3 (b) (i) & (ii) Project duration – 7 Critical activities – T, X
M1 A1 A1 B1 "5" B1 B1 beyond 5 M1 activity-on-arc A1 single start and single end A2 precedences (–1 each error) M1 A1 forward pass M1 A1 backward pass B1 B1
R 2
Y 3
X 2
S 1
T 5
W 3
Z 1
0 0
2
2
5
5
7 7
6
5
3
3
4771 Mark Scheme June 2008
87
6. (i)
Order of inclusion
1 3 6 4 5 2
A B C D E F
A – 10 7 – 9 5
B 10 – – 1 – 4
C 7 – – – 3 –
D – 1 – – 2 –
E 9 – 3 2 – –
F 5 4 – – – –
Arcs: AF, FB, BD, DE, EC Length: 15 (ii) & (iii) Arcs: AF, FB, BD, AC, AE Length: 26 (iv) Cubic n applications of Dijkstra, which is quadratic
M1 A1 select A1 delete A1 order B1 B1 B1 arcs B1 lengths M1 Dijkstra A1 working values A1 order of labelling A1 labels M1 A1 B1 B1
F
E D
C
B A 10
7
9
5
1 4
3
2
1 0
10
7
9
5
2 5
9
3 7
4(5) 9
(11)10
5(4) 9 6 10
4771 Mark Scheme January 2009
62
4771 Decision Mathematics 1
1. (i) (ii) Can't both have someone shaking hands with everyone and
someone not shaking hands at all. (iii) n arcs leaving By (ii) only n–1 destinations
M1 bipartite A1 one arc from each
letter A1 David A1 rest B1 0 ⇒ ~3 B1 3 ⇒ ~0 B1 B1
2. (i)
n i j k 5 1 3 3 2 2 8 3 1 13 4 0 16
k = 16 (ii) f(5) = 125/6 – 35/6 + 1 = 90/6 + 1 = 16
(Need to see 125 or 20.83•
for A1) (iii) cubic complexity
B1 B1 B1 B1 B1 M1 substituting A1 B1
B
C
D
A
1
2
3
0
4771 Mark Scheme January 2009
63
3. (i)
Cheapest: £11 [start (£2 starter)] → A (£3 main) → E (£3 main) → B (£1 main) → F (£2 sweet) → [end] (ii) repeated mains ! directed network
M1 Dijkstra A1 order A1 labels A1 working values B1 £11 B1 route B1 B1
start
1042
13 10 6
sweet £2
7 27
end
1 0
2 2 2
3 4 4
5 8 10 8
4 5 5
6 9
10 9 7 10 10
8 11 12 11
12
63
A B C
D E F
G
4771 Mark Scheme January 2009
64
4. (i) e.g. 00–47→90 48–79→80 80–95→40 96, 97,98, 99 ignore (ii) smaller proportion rejected (iii) e.g. 90, 90, 90, 80 350 (iv) e.g. 90, 80, 90, 80 340 80, 90, 80, 80 330 90, 40, 80, 90 300 40, 90, 90, 90 310 90, 90, 90, 90 360 80, 80, 40, 90 290 80, 80, 80, 90 330 90, 80, 90, 90 350 90, 40, 40, 80 250 prob (load>325) = 0.6 (v) e.g. family groups
M1 some rejected A3 correct proportions (–
1 each error) A1 efficient B1 M1 A1 A1√ M1 A3 (–1 each error) √ M1 A1 B1
5. (i)&(ii) e.g. time − 60 minutes critical − A; C; E; F; G; H (iii) A and B at £300 A; C; G; H B; E; F
M1 sca (activity on arc) A1 single start & end A1 dummy A1 rest M1 forward pass A1 M1 backward pass A1 B1 √ B1 cao B1 2 out of A, B, E B1 A B1 B B1 300 from A and B B1 B1
D 20
A 30
C 15
G 10
B 25
E 25
F 5
H 50 0
20
30 45
30
55
55
60 60
55
55
30
45 30
55
4771 Mark Scheme January 2009
65
6. (i) xi represents the number of tonnes produced in month i x2 ≤ x3
x1 + x2 ≤ 12 (ii) Substitute x3 = 20 – x1 – x2 x2 ≤ x3 → x1 + 2x2 ≤ 20 Min 2000x1 + 2200x2 + 2500x3 → Max 500x1 + 300x2 (iii) Production plan: 6 tonnes in month 1 6 tonnes in month 2 8 tonnes in month 3 Cost = £45200
M1 quantities A1 tonnes B1 B1 M1 A1 A1 M1 sca A3 lines A1 shading M1 >1 evaluated
point or profit line
A1 (6, 6) or 4800 M1 √ all 3 A1 cao
x1
x2
(4, 8) 4400
(0, 10) 3000
(6, 6) 4800
12
12
4771 Mark Scheme June 2009
84
4771 Decision Mathematics 1
Question 1 (i) 1 and 6, 2 and 5, 3 and 4 (ii) (iii)
B1 M1 10 to 14 edges A4 (–1 each edge error) B1 identification B1 sketch
Question 2. (i) A's c takes 2, leaving 3. You have to take 1. A's c takes one and you lose. (ii) A's c takes 3 leaving 3. Then as above. (iii) A's c takes 3 leaving 4. You can then take 1, leading to a win.
M1 A1 A1 M1 A1 M1 A1 A1
Vertex 1
Vertex 5
Vertex 4 Vertex 3
Vertex 2
Vertex 6
4771 Mark Scheme June 2009
85
Question 3. (i) 61 at (11, 7) (ii) Intersection of 2x+5y=60 and x+y=18 is at (10,8) 10 + 2×8 = 26
M1 optimisation A1 M1 A1
x
(5, 10) 55
(11, 7) 61
(18, 0) 54
(0, 12) 48
B3 lines B1 shading
4771 Mark Scheme June 2009
86
Question 4. (i) e.g. 0–4 exit 5–9 other vertex (ii) e.g. 0.5, 0.5, 1.9 (Theoretical answers: 2/3, 1/3, 2) (Gambler's ruin) (iii) e.g. 0–2 exit 3–5 next vertex in cycle 6–8 other vertex 9–ignore and re-draw (iv) e.g. 0.7, 0.1, 0.2 (Theoretical probs are 0.5, 0.25, 0.25) (Markov chain)
B1 B1 M1 process with exits A1 B1 probabilities M1 duration A1 M1 ignore DM1 conditionality A1 equal prob A1 efficient M1 A2 M1 A1
1 A ExA 2 A B A B A B ExB3 A ExA 4 A B A B A ExA 5 A B ExB 6 A B A B A B ExB7 A B A B ExB 8 A ExA 9 A B ExB 10 A ExA
1 A B A B A ExA 2 A C A ExA 3 A ExA 4 A B C B C ExC 5 A ExA 6 A C A B ExB 7 A ExA 8 A B C ExC 9 A ExA
10 A ExA
4771 Mark Scheme June 2009
87
Question 5.
(i) e.g. (ii) Order: AE; AD; DB; DC or AD; AE; DB; DC or AD; DB; AE; DC Length: 65 km OR Order: AD; DB; DE; DC Length: 66 km (iii) Length: 53 km Advice: Close BC, AE and BD (iv) facility (e.g. anglers) distances (e.g. B to C)
M1 A1 connectivity A1 lengths M1 connected tree A2 (–1 each error) A1 B1 M1 connected tree A2 (–1 each error)
B1 B3 B1
E
B
D C
A
B
E
D C
A E
B
D C
A
20
18
15
16
17
15
15 and/or 20
25
B
E
D C
A
X
4771 Mark Scheme June 2009
88
Question 6. (i)&(ii) time − 230 minutes critical − A; B; E; F; H (iii) e.g. Least time = 240 mins Minimum project completion times assumes no resource
constraints.
M1 sca (activity on arc) A1 single start & end A1 dummy A1 rest M1 forward pass A1 M1 backward pass A1 B1 B1 cao M1 cascade A2 B1 Joan/Keith B1 B1
E 16D 16
G 16F 16
B 16A 16
H 16
C 16
D 60
A 100
B 60
E 40
C 150
H 10
F 20 0
60
100 160 200
230
220 220
230
200
G 30
160 190
100
200
160
4771 Mark Scheme
59
4771 Decision Mathematics 1
1 (i) & (ii)
Critical activities: A and D
M1 activity-on-arc
A1 C and E OK A1 D OK M1 forward A1 pass M1 backward A1 pass B1
2 (i)
M1 subgraph A1 M1 Changing
colours A1 top right A1 bottom left A1 not singletons
B1
(ii) The rule does not specify a well-defined and terminating set of actions.
B1
A 3
B 2
C 3
D 5
E 1
0 0
3 3
3 3
6 7
8 8
Red
Blue
Red
Red
Red Blue
Blue
Red
Blue
Blue
Red
Red
Blue Blue
Red
Blue
Subgraph
Swap colours on connected vertices and complete
4771 Mark Scheme
60
3 (i) No repeated arcs. No loops B1 B1
(ii) Two disconnected sets, {A,B,D,F} and {C,E,G,H} M1 A1
(iii)
6 arcs added
M1 A1 B1
(iv)
4×4 = 16 or 8
12 28 12 162
− = − =
B1
A
B
C
D
E
F
H
G
4771 Mark Scheme
61
4
(i) e.g. Let x be the number of adult seats sold. Let y be the number of child seats sold. x + y ≤ 120 x + y ≥ 100 x ≥ y
M1 A1 B1 B1 B1
(ii)
B3 lines (scale must be
clear) B1 shading (axes must be
clear) B1 point +
amount M1 point A1 amount M1 point A1 amount
(vi) 6000+60c > 10000 => c ≥ 67
M1 A1
y
x 120
120
100
100
(iii) £12000
(iv) £9000
(v) £7500
4771 Mark Scheme
62
5 (i)
& (ii)
shortest route: A E C F distance: 26 miles
M1 network A1 arcs A1 lengths M1 Dijkstra A1 working
values B1 order of
labelling B1 labels B1 B1
(iii) CE CD AE CF AD BF AB EF total length of connector = 45
M1 5 arc connector
A1 AD not included
A1 all OK, inc order
B1
B1
(iv) A 3 miles (or length = 9)
B 2 miles (or length = 10)
B1 B1
A B
C
D E
F
22
13
12
6
11
5
10 26
1
12
22
10
10
0
2
15 36
12 3
15 4
26
5 22
6 26
A B
C
D E
F
13
6
11
5
10
4771 Mark Scheme
63
6 (i) e.g. 0, 1, 2 fall
3, 4, 5, 6, 7, 8 not fall 9 redraw
M1 ignore at least 1A1 proportions
correct A1 efficient
(ii) apple r n fall?
1 1 yes 2 3 no 3 8 no 4 0 yes 5 2 yes 6 7 no Three apples fall in this simulation.
M1 A2 –1 each error B1√
(iii) apple r n fall?
2 0 yes 3 1 yes 6 4 no apple r n fall? 6 4 no apple r n fall? 6 8 no apple r n fall? 6 0 yes 5 days before all have fallen
M1 A2 –1 each error A1√
(iv) apple r n fall? 1 picked 2 1 yes 3 3 no 4 8 no 5 0 yes 6 2 yes apple r n fall? 3 picked 4 7 no apple r n fall? 4 picked 3 days before none left
M1 A2 –1 each error B1√
(v) more simulations
B1
4771 Mark Scheme June 2010
1
1. (i)
AB 12 AB AC 13 AC AD 29 ABD AE 35 ABDE AF 22 ACF
(ii) 5
M1 Dijkstra A1 working values B1 order of labelling B1 labels B1 AB and AC B1 AD and AF B1 AE B1
2. (i) 3 8 6 4 12 2 24 1 24 (ii) 26 42 52 21 104 10 208 5 416 2 832 1 1092 (iii) multiplication
M1 doubling and halving M1 deleting and summing A1 cao M1 doubling and halving M1 deleting DM summing A1 cao B1
A B
C
D E
F
0 1
12
13
45
12 2
29
24
13 3
37
22
22 4
29 5
35
35 6
12
17
45
6
9
13 12
24
4771 Mark Scheme June 2010
2
3. (i) (ii) (iii) The graphs represent traffic flows within the junctions.
They do not take account of flows approaching or leaving the junctions.
(Graphs are not planar if these flows are added, so traffic flows have to cross.)
B1 B1 B1 B1 12 arcs B1 connectvity B1 3 out of each in vertex B1 3 into each out vertex B1
4771 Mark Scheme June 2010
3
4. (i) Each small tile has area 100 cm2 so 1000x Similarly 900y So 1000x + 900y ≥ 400×300 = 120000 (ii) y ≤ 100 10x ≤ 9y (iii) e.g. minimise 1.5x + 2y Integer solution required, so x=60, y=67, cost = 224 (iv) wastage or design
M1 areas A1 tile areas A1 B1 B1 B1 B1 B3 lines B1 shading M1 solving A1 x = 59-61 y = 66-68 A1 220-228 B2
(30, 100) 245
(60, 2366 )
223.33
(90, 100) y
x
100
4771 Mark Scheme June 2010
4
5. (i) e.g. 0 to 4 –> stagger left 5 to 9 –> stagger right + accumulation (ii) probably one of: (iii) repeat relative frequency (iv) e.g. 0 to 2 –> stagger left 3 to 8 –> stagger right 9 reject and redraw
M1 A1 B1 M1 A1 B1 B1 M1 reject some A1 proportions A1 efficient
(v) e.g. run 1 R L R L L Rrun 2 R L R R L Rrun 3 R R L L L Lrun 4 L L R L R Rrun 5 R R R * run 6 L R R R R *run 7 R R L R R *run 8 R R L R R *run 9 R R R *run 10 L R R L R R
Probability estimate = 0.5 (Theoretical = 0.73 + 5×0.74×0.3 = 0.70315)
M1 A2 (–1 each wrong row) B1 falling in M1 probability A1
4771 Mark Scheme June 2010
5
6. (i) & (ii) Duration = 24 months Critical : A; F; J; G (iii) Crash F by 1 month and G by 1 month at a cost of £6m. (iv) Crash G by 2 months at a cost of £8m.
M1 activity-on-arc A1 D, E, H and K A1 F A1 I and J A1 G M1 forward pass A1 M1 backward pass A1 B1 cao B1 cao B1 F by 1 month B1 G by 1 month B1 £6m M1 G only A1 £8m
A 4
C 7
B 2
K 12
G 6
0 0
4 4
4 4
18 18
24 24
7 8
11 11
H 3
F 7
I 12
D 12
E 5
J 7
4771 Mark Scheme January 2011 1. (i) (ii) 6 (iii) e.g. 4 arcs and (e.g.) {A}, {B, C, D, E} (iv) Reference to parts (i) and (ii), in reverse − or similar
M1 A1 M1 attempt at complete
connectivity A1 B1 B1 B1 B1
M1 any and only 3 of the 4 A1 all M1 5, 6 or 7 A1 6 4 ... set of 1 ... disjoint set of 4 SC M1 6 arcs A1 appropriate sets ... disjoint of size 2 and 3
A B
DE
C
1
4771 Mark Scheme January 2011
2. (i)
B1
B1
B1 (ii)
B1
B1 B1 B1 1,2 3 4
B1 5,6
7
8
cao cao ... allow extra second line of 5678 D, but with ‒1 cao cao
cao cao award the last two B1s only for contiguous blocks of 3 tests from line 3 allow extraneous lines but ‒1 once only, and only from the last two B1s
Test number
Sample drawn from flagons numbered
Result (D = dead, A = alive)
A 1 1, 2, 3, 4 2 5, 6 A 3 7 D 4 8 A
Test number
Sample drawn from flagons numbered
Result (D = dead, A = alive)
D 1 1, 2, 3, 4 2 5, 6, 7, 8 D 3 1, 2 A 4 3 D 5 4 A 6 5, 6 A 7 7 D 8 8 A
2
4771 Mark Scheme January 2011 3. (i) Shortest distance = 27 Shortest route … ABCEF (ii) Because F was the final vertex labelled. (iii) Because if there were to be a shorter route than BCEF
from B to F, then A to B followed by it would give a shorter route from A to F.
or “B is en route”
M1 Dijkstra A1 working values B1 order of labelling B1 labels B1 B1 B1 B1
cao
A
F
E D
C
B 5
7
10
5
9 6
22
25
37
28
19
05
19
28
2 5
27 21
37
1
42 3 12
22
1227 6
225
27
214
3
4771 Mark Scheme January 2011 4. (i) (ii)&(iii) (iv) critical activities: E; F; J duration: 7 minutes task: A B C D E F G H I J float: 4.5 4.5 4 4 0 0 3.5 4 4 0
B1 A, C, E and G B1 B, D and F B1 H, I and J M1 activity-on-arc A1 A, G, C ,E, B, D, F A1 H, I, J
M1 A1 forward pass M1 A1 backward pass B1 B1 B1
no follow through no multiple starts no multiple ends but no follow of activity-on-node ditto
cao cao cao blank=0
Task Description Duration Immediate predecessor(s) (mins) – A Fill kettle and switch on 0.5
B Boil kettle 1.5 A – C Cut bread and put in toaster 0.5
D Toast bread 2 C – E Put eggs in pan of water and
light gas 1
F Boil eggs 5 E – G Put tablecloth, cutlery and
crockery on table 2.5
H Make tea and put on table 0.5 B; G I Collect toast and put on table 0.5 D; G J Put eggs in cups and put on
table 1 F; G
B 0.5 5 6.5 2.5 1.5
A 0.5 H 0.5
G 0 6 7 2.5 7 0 2.5 I C
0.5 0.5 D 0.5 4.5 2.5 6.5 E 2 J 1 1
F 1 6 1 6 5
4
4771 Mark Scheme January 2011 (v) e.g.
M1 cascade or
condensed cascade A1 activities other than
B, D and F non-overlapping
A1 correctly finish in 7
need to have 9 or 10 activities E C A G H I J cao
J E F D C
G H I A B
5
4771 Mark Scheme January 2011 5. (i) e.g. 00–04 6 05–29 7 30–79 8 80–99 9 (ii) e.g. 00–09 goal 10–99 no goal (iii) e.g. 8 0 1 0 0 0 0 0 0 so 1 goal (iv) e.g. 00–31 5 32–63 6 64–79 7 80–95 8 96–99 reject and redraw (v) e.g. 6 0 0 1 0 0 0 so 1 goal (vi) Each scored 10 goals. Nothing to choose between
them. (vii) More repetitions
M1 rule using 2-digit nos
A1 correct proportions A1 efficient B1 B1 B1 B1 M1 2 or more rejected A1 correct proportions A1 efficient B1 M1 A1 M1 A1 B1
complete rule required rule (i) need to see which are converted ... their 8 and rule (ii) their 8 and rule (ii) ... ignore previous line allow part (iv) if seen elsewhere 3 or 4 rejected in part (v) below expect either 00‒11 or 88‒99 for goal any other rule must be declared to score marks rule (iv) their 6 ... need to see which are converted goals scored one, the other or indifferent, depending on goals scored “greater number of random numbers” 0 “more accurate data” 0 Also no “or”s! 3-digit RNs 0
6
4771 Mark Scheme January 2011
7
6. (i) Thousands of litres of A in stock = 2 b −4 (ii) 5(a+2) + 6(b+4) ≥ 61 (a+2) + (b+4) ≤ 12 giving a + b ≤ 6 (iii) (iv) Increase stock levels of A by 9000 litres. Reduce stock levels of B by 3000. (v) New stock levels are 11000 of A and 1000 of B. 511000 + 61000 = 61000 11000 + 1000 = 12000
B1 B1 M1 A1 M1 A1 B4 lines B1 shading B1 B1 B1 B1 B1
cao watch for fluke their negative gradient stock line shape = or
Give the marks for 9000, ‒3000, or equivalent 200 litres on both (iv) SC correct answer from nowhere OK Allow comment only for the “fully stocked” B1.
a
(9, −3)
6 5.4
b
6
4.5
4771 Mark Scheme June 2011
4771, June 2011, Markscheme 1.
(i) (ii) 14 (iii) 47 (iv) (0, 0) and (1, 0) (v) Explanation should recognise that a line is a set of
points − not appropriate in this context.
B1 3 to 4 deleted B1 1 to 4 deleted B1 4 to 4 added B1 M1 A1 cao B1 B1
-1 for each arc in error Award method mark if answer correct, or if wrong but with a sum of products shown. Award only if correct points are specified in some way. e.g. “Intermediate points have no meaning.” e.g. “Can’t have one and a half pairs of shoes.” (sic)
number of people
num
ber o
f pai
rs o
f sho
es
0
1
2
3
4
5
0
1
2
3
4
5
5
4771 Mark Scheme June 2011
2. (i) X = min(25, 8.5) = 8.5 or equivalent Y = min(5, 42.5) = 5 oe X* = (85–10)/10 = 7.5 oe Y* = (25–8.5)/5 = 3.3 oe (ii) Avoids tiny feasible regions.
B1 cao B1 cao B1 cao B1 cao B1 allow ft B1 cao B1 cao B1
OK if only seen once or more on graph OK if only seen once or more on graph OK if only seen on graph OK if only seen on graph sensibly scaled for their X and Y e.g. disallow if either of the lines in the question could intersect both axes. lines - can extend to beyond segment condone minor errors in plotting (e.g. 8.5 plotted at 9) need comment on size of region
(8.5, 3.3)
(0, 5)
(8.5, 0)
(7.5, 5)
6
4771 Mark Scheme June 2011
3. (i) e.g. 1, 2, 3 1 4 2 5, 6 3 (ii) e.g. 1, 2 1 3 2 4 3 (5, 6 reject and throw again) (iii) non uniform allows 100
M1 A1 A1 M1 reject some A1 reject two A1 rest
B1 B1
function with domain {1,2,3,4,5,6} and range {1,2,3} (special cases are possible – if correct!) proportions 3:2:1 all OK (Special cases are possible – if correct! e.g. allow throwing die twice and allocating correct proportions of 36.)
“101 values” OK no credit for, e.g. “3 is not a two-digit number”
7
4771 Mark Scheme June 2011
4. (i) e.g. x = number of large houses y = number of standard houses
land: 200x + 120y <= 120000 oe cash: 60x + 50y <= 42400 oe market: x <= 0.5y oe (ii) (iii) intersection of y=2x and 6x+5y=4240, (265, 530) 2650
(iv) their 60x + 50y <= 45000 or line from their (0, 900) to (750, 0)
Best point is at the intersection of the land constraint and the new cash constraint, and not on y=2x
(214, 643) 2785
M1 A1
B1 B1 B1 B1 line 1, allow ft B1 line 2, allow ft B1 line 3, allow ft B1 feasible region M1 correct point, cao A1
B1 ft
M1 comparison of two (or more) points
A1
M1 correct point, cao A1
M1 for variables for large and for standard A1 for “number”
use “isw” for incorrect simplifications -1 once only for any “ < ” for instance, if x <= 2y in part (i), then allow correct graph of x <= 0.5y or ft graph of x <= 2y plotting tolerance on axis intersection points – within correct small square must consider 3 lines ft if region includes y-axis interval from origin upwards allow any clear indication of feasible region ignore any indication(s) of boundary lines included or excluded identification only - coordinates not required here their 4x+3y from (260-280, 520-540)
can be implied from final M1 working
not just ringing points their identified best point is not on y=2x or an axis
identification, coordinates not required here bedrooms - their 4x+3y from (200-220, 620-660)
706.67 x
y 1000
(265, 530) 2650
600
848
8
4771 Mark Scheme June 2011
9
5. (i) (ii) (iii) critical activities: A; Pl; Fo; W; R; E; Deco project duration = 41 days act A Pl Dm Fo W Pb R Fl E WD Dc
M1 Fl correct A1 rest
M1 at least one correct nontrivial join
A1 forward pass M1 at least one correct
nontrivial burst A1 backward pass
B1 cao B1 cao B1 A, Pl, Dm, Fo, W B1 rest B1 B1 one of R/WD
excluding start node
cao cao – most see zeros, dashes or empty spaces won’t do SC1 for a convincing but not specific answer, e.g. “A dummy is needed to cater for both joint and separate precedences”.
float 0 0 21 0 0 2 0 1 0 4 0 (iv) Fl has both W and Pb as immediate predecessors. R and WD have only W as immediate predecessor.
10 24 31
32 36
41 41
36
31 24 10
Pl 14
Demo3
A10 W3
Pb2 Fl 2
R3 Fo4
WD1
E2 Deco5
0 28
34 34 31
28 0
Activity Immediate predecessors A – Pl A Demo – Fo Pl; Demo W Fo Pb Fo R W Fl Pb; W E R; Fl WD W Deco WD; E
4771 Mark Scheme June 2011
(v) (vi) new duration = 42 days critical activities: A; Pl; Fo; W; C; R; E; Deco
M1 C between W and R A1 Fl + dummy OK A1 WD OK B1 cao
both needed
WD Pl
Demo
A W
Pb Fl
R Fo C E Deco
10
4771 me June 2011
11
Mark Sche
6. (i)
1 7 9 8 2 10 3 6 11 5 4 P S F Ln Br Nr Bm Ld Nc Lv M
P − 150 − 240 125 − − − − − − S 150 − 150 80 105 − 135 − − − − F − 150 − 80 − − − − − − −
Ln 240 80 80 − 120 115 120 − − − − Br 125 105 − 120 − 230 90 − − − − Nr − − − 115 230 − 160 175 255 − − Bm − 135 − 120 90 160 − 120 − − 90 Ld − − − − − 175 120 − 210 100 90 Nc − − − − − 255 − 210 − 175 − Lv − − − − − − − 100 175 − 35 M − − − − − − 90 90 − 35 −
Length = 985 miles
M1 tabular
Prim A2 choosings A1 crossings B1 cao B1 cao
125 in P column and 90 in Br column ringed, with both rows crossed all circles in correct place; -1 each error (watch for one error making two changes to a row) all rows crossed out except, possibly, Nc row. accept convincing transpose
Nr
F
Nc
Ln
Ld
S
Bm
Br
Lv
M
P
4771 Mark Scheme June 2011
(ii) Advantage: shortest length of track Disadvantage: tree, no redundancy fragility (breakdown et al) Disadvantage: some journeys are not shortest paths (iii) Route: P S Ln Nr Distance: 345 miles
(iv) Distance by min connector = 425 miles
B1 cao B1 B1 M1 Dijkstra A1 working
values B1 labels B1 order of
labelling B1 cao B1 cao
B1 ft their mc
allow cost minimisation could say “no cycles” disallow comments relating to direct connectivity, or relating to more stops “longer journeys” or “takes longer” allowed allow “min connector arcs may be more expensive” oe don’t allow two marks for the same point described differently. e.g. longer journeys/more time/more upkeep correct working values (no extras) at Ln and Nr, and working values only superseded at Ln and Nr (ignore Nc for this M) (need to check Nc here)
Nc
Br
P S
Bm
F
Ln
Nr
Ld M
Lv
150
175
35 100
90
90
210
255
175120
160
90
230
120
135 115
120
240 125
150
80 80105
9 340 340 545 515
8 335 7 305
335 305
10 345 355 345
4 215 215
2 125 230 5 125 240 230
0 1
150 3 6 300 150 300
12
4771 Mark Scheme June 2012
Question Answer Marks Guidance 1 (i) & (ii) B1 connectivity B1 lengths B1 Dijkstra Award if wv’s OK at C. B1 working values allow legitimate later and other than at C larger wv’s which are listed, but not used. Disregard F. B1 order of labelling SC ... If possible follow for B1 labels these two marks. following
errors in network
B1 B1
Route: AECG Distance: 8
[8]
3 3 3
C
G
0 1
A
F
E D
B
3
5
1
2
6
4
1
5
4
8 3
8 4
5
2 3 9 6 8
8
1
6 6
7
3
9
5 7 5 7
5
4771 Mark Scheme June 2012
Question Answer Marks Guidance 2 (i) A L R B f(L) f(R)
3 3.382 3.618 4 2.146 1.910
B1 B1
R and L -1 once only for incorrect f(R) and f(L) accuracy, but condone 1.91. Surds OK, but lose the accuracy mark. (Q says 3dp.)
3.382 3.618 3.764 4 1.910 1.875
B1 B1 B1
A L and R f(L) and F(R)
3.618 B1 A [6] 2 (ii) Saves a function evaluation B1 Has to be a comment about
function values.
[1] 2 (iii) eg
Setting the control on a gas fire to achieve a room temperature of 20C. Function could be (temp–20)2. (This example shows that optimising can be used to “achieve”.) Note that the domain cannot be time based ... i.e finding when something occurred. One cannot go back in time to take a reading!
B1
Optimisation with need to “Deepest point in seabed” sample at discrete intervals. example seen. This is
acceptable, assuming that depth soundings are taken at points, and ignoring the fact that the domain is two dimensional rather than one dimensional.
[1]
6
4771 Mark Scheme June 2012
3 (i) M1 directed graph on 3 vertices A1 all correct M1 undirected on 3 vertices Arcs must either have an
arrow at each end. or no arrows.
A1 all correct
“shares at least one element with” “is a subset of”
[4] 3 (ii) M1 R subset of Q Allow area split in two, with A1 no other subsets third area. eg B1
B1 PQ PQ’
If P and R shown intersecting
then can score M1 A1 B0 B0.
eg
[4]
X Y
Z
X Y
Z
Q R P Q R P
7
4771 Mark Scheme June 2012
Question Answer Marks Guidance 4 (i) Let x be the number of type X motors produced. M1 adequate definition Strict inequalities are Let y be the number of type Y motors produced. A1 “number of” equally OK 10x + 12y 200 B1 x 5 and y 5 B1 0.5x + 0.3y 7 B1 [5] 4 (ii) B1 inclined line B1 inclined line B1 x=5 and y=5 B1 shading follow line errors if shape is
The guidance level of
accuracy throughout this question is 0.25 on the x coordinate and 0.25 on the y coordinate.
(Look at (8,10) first.)
Inaccurate sketch with axis intercepts given is OK.
[4]
y
23.3
x
(16, 8)
16.7
14 5
5
(8,10) 1500
(5,12.5) 1375
(11,5) 1450
15
(iv) (10,6.7)
18
8
4771 Mark Scheme June 2012
Question Answer Marks Guidance 4 (iii) Profit = 100X + 70Y
(5,12.5) or (5,12) 1375 or 1340 (8,10) 1500 (11,5) 1450 £1500 profit.
B1
M1
A1
optimisation either profit line or
evaluating and comparing at their 3 appropriate points
(OK if on graph) 1500 seen cao
SC B1 for 1500 without the preceding M mark
[3] 4 (iv)
Solution in range 41
32
41 6,10 =
691.6641.6,25,1075.9
Identification of one of (9,7), (10,6) and (11,5). Evaluation at all three of (9,7) (10,6) (11,5) 1390 1420 1450 So 11 of X and 5 of Y
B1
B1
M1
A1
cao looking for 326,10
cao cao
[4]
9
4771 Mark Scheme June 2012
Question Answer Marks Guidance 5 (i) eg 07 double M1 reject Rejection can be implied. 8 single A1 correct proportions 9 reject and re-draw [2] 5 (ii) eg 05 double M1 reject Rejection can be implied. 6,7 single A1 correct proportions Ignore rule for (4,0). 8,9 reject and re-draw [2] 5 (iii) e.g. day doubles singles random number
selection 1 5 0 2 4 1 5 double 3 3 2 9, 4 double 4 2 3 0 double 5 1 4 Probability of drawing a single bag on day 5 is now 4/6.
M1 A1
M1 A1
M1 A1
M1 A1
[8]
For the simulation M1’s you need to see a random number being used with their rules
allow 5 shown as used on RN list. selection must show RN(s) explicitly Follow a candidate who new scenario seen explicitly, manages correctly to go from not implied by day 4 rule (4,1) to (4,0). It will then gain
M1 if it correctly goes to (3,1) on day 4, with A1 if shows no simulation needed.
a correct day 4 rule rule must be seen selection and new scenario needs RN explicit. Allow new
scenario if seen in subsequent probability calculation.
denominator = 6 Can be implied by 2/3 or 1/3 if numerator correct for their simulation.
10
4771 Mark Scheme June 2012
Question Answer Marks Guidance 5 (iv) 4 simulations, each ending with 6 bags
all scenarios correct
M1
A1
[2]
Condone one slip. Condone simulating at (4,0) if correctly done. 6 bags can be implied by probs of thirds or sixths.
5 (v) Either averaging correct probabilities or sum of singles/30 M1 Correct computation, but allow 1 slip or omission. A1 Correct answer for their simulations.
[2]
11
4771 Mark Scheme June 2012
12
Question Answer Marks Guidance 6 (i)
&
M1 activity on arc
(ii) A1 at least 1 dummy for E and F A1 precedences for D A1 precedences for G A1 rest eg. penalise multiple starts M1 forward pass A1 M1
A1
B1
backward pass If OK at start of dummy. If there is no dummy then these two marks are not available.
B1
Minimum completion time = 14 mins Critical activities ... A, B, D, G, H
[11] 6 (iii) 2 people
B1
[1]
6 (iv) 1 person ... 15.5 mins B1
[1]
6 (v) B1 network B1 time with small oven
time = 35.5 minutes [2]
6 (vi) revised time = 26.5 minutes
B1
[1]
time with large oven
A 0.5
F 0 .5
14 14 H 104 4 G
0.53.5 3.5 D 2 E
0.5
B 1 C
0.5
0.5 0.5
0.5 3.5
1.5 1.5
O2
O3
O1
0 0
P2
P3
P1
Oxford Cambridge and RSA Examinations
GCE
Mathematics (MEI) Advanced Subsidiary GCE
Unit 4771: Decision Mathematics 1
Mark Scheme for January 2013
4771 Mark Scheme January 2013
5
Question Answer Marks Guidance 1 (i) M1 Dijkstra (if working values
correct at D) A1 working values B1 order of labelling B1 labels Route ... ABDCF Time ... 51 minutes B1 route and time [5] (ii) B1 methodology indicated B1 correct min connector
Time ... 52 minutes B1 cao [3]
B D
F
C
A
5
E
18
19
10
15
B D
F
C
A
41
5
17
2
17
32 31 30
10
4
56 51
51 6
3 15
1 0
E
18
21
19 32 21
10
15
15 10
33
5 33 30
4771 Mark Scheme January 2013
6
Question Answer Marks Guidance 2 (i) bipartite B1 cao [1] (ii) 100 M1
A1 [2]
allow for 200 cao
(iii) B1 Darcy correct B1 Elizabeth correct B1 Panto characters correct [3] (iv) 58 18 + (8 5) M1 allow for 98 A1 cao [2]
A
B
Charming
Darcy
E
F
G
H
I
J
V W Cinderella Ugly sister 1 Ugly sister 2 Ugly sister 3 Elizabeth X Y Z
4771 Mark Scheme January 2013
7
Question Answer Marks Guidance 3 (i) Step 1 x = 0.44
Step 2 oldr = 1 B1 cao
Step 345 i = 1, j = 0.5, k = 0.5 Step 6 change = 0.22
Step 7 newr = 1.22 Step 9 oldr = 1.22
B1 set-up (i.e. as far as 1.22)
Steps 10 11 12 i = 2, j = –0.5, k = –0.125 B1 3 steps correct Step 13 change = –0.0242 Step 14 newr = 1.1958 B1 new estimate (1.1958) Step 15 |change| = 0.0242 Step 9 oldr = 1.1958 Steps 10 11 12 i = 3, j = –1.5, k = 0.0625 Step 13 change = 0.005324 Step 14 newr = 1.201124 Step 15 |change| = 0.005324 Step 9 oldr = 1.201124 B1 iteration (to 1.201124) Steps 10 11 12 i = 4, j = –2.5, k = –0.03906 Step 13 change = –0.0014641 Step 14 newr = 1.1996599 Step 15 |change| = 0.0014641 Step 17 1.1996599 B1 iteration and end [6] (ii) 1 – 0.22 – 0.0242 – 0.005324 – 0.0014641 = 0.7490119 M1
A1 use of –0.44 as shown SC1 (cao) for algorithm repeated or answer only
[2]
4771 Mark Scheme January 2013
8
Question Answer Marks Guidance 4 (i) M1 activity on arc & A1 single start and end (ii) A1 A, B, C OK A1 J, K, L OK A1 rest OK [5] M1
A1 forward pass (must have at least one join correct
M1
A1 backward pass (must have at least one burst correct)
Minimum completion time = 155 minutes B1 cao Critical activities are C, D, E, F, G, J, K and M B1 cao [6] 4 (iii) eg
Kate C C C D D D E1 F1 F1 F1 F1 F1 F1 H1 H1 H1 H1 H1 H1Pete A B E2 F2 F2 F2 F2 F2 F2 H2 H2 H2 H2 H2 H2
B1 ABCD cont. G1 G1 G1 G1 G1 G1 I1 I1 I1 J1 J1 J1 J1 K1 K1 K1 K1 K1 K1
cont G2 G2 G2 G2 G2 G2 I2 I2 I2 J2 J2 J2 J2 K2 K2 K2 K2 K2 K2B1 rest ... watch for M’s after
K’s and L’s cont L1 L1 L1 M1 M1
cont L2 L2 L2 M2 M2
215 minutes (3 hours and 35 minutes) B1 cao [3] 4 (iv) Two more people would be needed, so that the H’s and I’s could be done at the same time as the F’s and
G’s, and so that the two L’s could be done at the same time as the two K’s B1 B1
cao reasoning
[2]
C 15
A 5
15 15 0 0
65 65
35 35 30 30 H 30
D 15
E 5
M 10
F 30
J 20
B 5
95 95
65 80
5 10
I 15
G 30
K 30
L 15
115 130
115 115
145 145 155 155
4771 Mark Scheme January 2013
9
Question Answer Marks Guidance 5 (i) e.g. 0 0 M1 either 0.2 for 1 or 0.3 for
2 1, 2 1 A1 all proportions correct 3, 4, 5 2 6, 7 3 8, 9 4 [2] 5 (ii) random number 5 3 0 2 4 7 9 1 1 8 M1 8 outcomes correct number of occupants 2 2 0 1 2 3 4 1 1 4 A1 all correct [2] 5 (iii) e.g. 0, 1 child B1 must use all 10 digits 2 – 9 adult cao [1] 5 (iv) chair 1 2 3 4 5 6 7 8 9 10
occ1 6 A 0 C 9 6 A 2 A 9 A 1 C 5 A 6 A 2 A occ2 2 A 6 A 5 2 1 C 1 C 4 A 8 1 9 A occ3 3 7 2 1 3 6 A 6 A 5 3 5 A occ4 3 1 1 2 8 0 6 A 0 5 1 C
M1 8 chairs OK
number of children = 5 A1 all OK number of adults = 15 [2] 5 (v) 40 children and 120 adults B1 FT... by 8 [1] 5 (vi) e.g. 00 – 06 0 M1 ignore some 07 – 13 1 A1 proportions correct 14 – 34 2 A1 efficient 35 – 55 3 56 – 90 4 91 – 99 ignore and “redraw” [3]
random number
child (C) or adult (A)
4771 Mark Scheme January 2013
10
Question Answer Marks Guidance 5 (vii) random number 23 65 07 99 37 45 M1 3 OK number of occupants 2 4 1 – 3 3 A1 all correct FT [2] 5 (viii) chair 1 2 3 4 5
occ1 1 C 9 A 6 A 8 A 1 C occ2 2 A 2 A 8 0 C 8 A occ3 6 3 A 2 2 A 1 C occ4 4 6 A 1 9 4
number of children = 4 number of adults = 9 B1 FT ... all correct 64 children and 144 adults B1 FT ... by 16 [2] 5 (ix) greater reliability or more representative B1 [1]
4771 Mark Scheme January 2013
11
Question Answer Marks Guidance 6 (i) e.g. Let x be the number of hats which Jean knits B1 must say “number of” Let y be the number of scarves which Jean knits B1 or vice-versa of course 1.5x + 3y ≤ 75, i.e. x + 2y ≤ 50 B1 simplification not 4x + 2.5y ≤ 100, i.e. 8x + 5y ≤ 200 B1 required x ≤ 20 and y ≤ 20 B1 both
B1 B1 B1 B1 lines (cao) B1 shading ... follow any set
of two horizontal, two vertical and two negatively inclined lines which give a hexagon in the bottom left corner.
[10]
50 25 hats - x
scarves - y
25
40
20
20
(20, 8) 220
(13.64, 18.18) 277.27
(10, 20) 270
4771 Mark Scheme January 2013
12
Question Answer Marks Guidance 6 (ii) Objective = 7x + 10y B1 objective Best non-integer point
Solution ... (12, 19) 274, (13, 18) 271 or (14, 17) 268
M1 A1
considering profits at their three points as indicated cao
So 12 hats and 19 scarves B1 cao [4] 6 (iii) 10 hats and 20 scarves B1 cao £34 B1 FT ... their answer – 240 [2]
4771 Mark Scheme June 2013
5
Question Answer Marks Guidance 1 (i)
M1
A1
simple and connected but not complete. (Ignore directions) cao
e.g.
B1
planar - cao
[3] 1 (ii) e.g.
M1 A1
exactly 3 vertices cao
[2] 1 (iii) B1 complete graph on 4
letters M1 4 regions A1 cao (planar OK) [3]
A B
C D
A B
C D
1
2 3
A B
C D
1 2
3 4
A B
C D
2 1
3 4
3
A B
C D
2 1
4771 Mark Scheme June 2013
6
Question Answer Marks Guidance
2 (i) comps swaps i=1 9 7 3 11 5 13 5 3 i=2 7 3 9 5 11 13 4 3 i=3 3 7 5 9 11 13 3 2 i=4 3 5 7 9 11 13 2 1 i=5 3 5 7 9 11 13 1 0
B1 B1 B1
B1 B1
i=2 row OK i=3 row OK FT i=4 and 5 rows OK cao comparisons swaps
[5] 2 (ii) comparisons 6 B1 cao (OK if in 2 parts) swaps 3 B1 cao (OK if in 2 parts) [2] 2 (iii) further swaps 6 B1 cao [1]
4771 Mark Scheme June 2013
7
Question Answer Marks Guidance
3 (i) B1 Dijkstra – C correct B1 other working values B1 order of labelling B1 labels Note that D and G could
be labelled in the reverse order.
AB 13 ABC 26 ABCD 39 ABE 44 ABCF 35 ABCG 39 ABCDH 52 ABCGI 46
B1 B1
first 4 pairs second 4 pairs
[6] 3 (ii) Turn distances to times throughout the network.
Add 10 mins to every arc incident upon C. (or do Dijkstra twice, once with C deleted, and compare with the adjusted time through C)
E1
E1
Explanations needed, not answers any correct logic
[2]
B
D G
C
A
E
F
I H 25
17
7
9 13
17 19
13
11 9
23 13
51 27 13 31
13 1 0
13
51 27
2 13
44 26
3 26
35 39
39
5 39
6 39 4 35
54 52 52 46
7 44
8 46 9 52
4771 Mark Scheme June 2013
8
Question Answer Marks Guidance
4 (i) & (ii)
M1 activity on arc A1 single start and end A1 A, B, C OK A1 D, F, I OK A1 rest OK [5] M1 forward pass (must have at
least one join correct A1 FT M1 backward pass (must have
at least one burst correct) A1 FT Minimum completion time = 100 minutes
Critical activities are A, C, D, I, J and L B1 B1
cao cao
[6] 4 (iii) e.g. Critical activities (100 mins) + others.
e.g. B has to be done whilst A is underway. B1 Needs a comparison of
times, possibly implied. [1] 4 (iv) (If L omitted in (i) ignore omission here.)
e.g.
M1
A1
A1 A1
diagram like this or attempted cascade ... no more than 1 omitted activity nowhere needing more than 2 people precedences correct fully correct, inc who does what
[4]
B 10
A 30
100 100 30 30
30 30
15 80
0 0 85 85 60 60 50 50
H 10
C 20
D 10
G 5
F 5
E 15
I 25
J 10
L 5
K 15
95 95
G C A D I J L Simon
Friend B E K H F 10 25
30
40 50 60
85 95
100
4771 Mark Scheme June 2013
9
Question Answer Marks Guidance
5 (i) e.g. Let x be the number of snowboards B1 Let y be the number of (pairs of) skis B1 or vice-versa of course x + y ≤ 600 B1 x ≤ 250 and y ≤ 500 B1 both 1.1x ≤ y B1
B1 FT horizontal line B1 FT vertical line B1 FT positive slope line B1 x+y = 600 Note ... error tolerance of
+/- half a small square within feasible region.
B1 shading ... follow any
pentagon bounded by the y-axis, a horizontal line, a vertical line, a negatively inclined line and a positively inclined line
[10]
600 250 boards - x
skis - y
500
600
(100,500) 29000
(250,350) 27500
(285.7, 314.3)
4771 Mark Scheme June 2013
10
Question Answer Marks Guidance 5 (ii) Objective = 40x + 50y B1 objective
M1 considering profits at the
two indicated points of their pentagon (or using a profit line)
29000 at (100,500) 27500 at (250,350) Solution ... 100 snowboards and 500 pairs of skis
A1 cao www
[3] 5 (iii) €10 or more B1 cao (allow €51 etc) [1] 5 (iv) 35 snowboards M1 moving to appropriate
new feasible point on their negatively inclined line
A1 cao... integer! (allowing 30 to 40 for graphical inaccuracy)
[2]
4771 Mark Scheme June 2013
11
Question Answer Marks Guidance 6 (i) e.g. 0, 1, 2 1
3, 4, 5, 6, 7 2 M1 either 3 numbers for 1 or
5 numbers for 2 8 3 A1 all proportions correct 9 4 [2] 6 (ii) random number 5 3 2 4 7 9 1 1 8
time interval (mins) 2 2 1 2 2 4 1 1 3 arrival times 0 2 4 5 7 9 13 14 15 18
M1 all outcomes achieved with first 2 correct for their rule
A1 all correct FT B1 accumulation [3] 6 (iii) e.g. 00 ‒ 13 0.1 M1 ignore some 14 ‒ 41 0.25 A1 proportions correct 42 ‒ 83 1 A1 efficient (fewer than 7
rejected) 84 ‒ 97 2 98, 99 ignore and “redraw” [3] 6 (iv) random number 23 15 01 32 45 47 86 71 17 83
processing time 0.25 0.25 0.1 0.25 1 1 2 1 0.25 1 M1 first 4 customers correct
for their rule A1 all correct FT [2] 6 (v) e.g. 0 ‒ 5 1 B1 6 ‒ 9 0.25 [1] 6 (vi) random number 8 3 0 1 4 0 2 5 7 6 B1 FT payment time 0.25 1 1 1 1 1 1 1 0.25 0.25 [1] 6 (vii) arrival 0 2 4 5 7 9 13 14 15 18 M1 deals with a wait correctly departure 0.5 3.25 5.1 6.35 9 11 16 18 18.5 19.75 A1 all correct FT [2] 6 (viii) arrival 0 2 4 5 7 9 13 14 15 18 M1 deals with last 3 correctly departure 0.5 3.25 5.1 6.35 9 11 16 18 15.5 19.25 A1 all correct FT [2]
4773 Mark Scheme June 2014
1
1. Annotations and abbreviations Annotation in scoris Meaning
Blank Page – this annotation must be used on all blank pages within an answer booklet (structured or unstructured) and on each page of an additional object where there is no candidate response.
and BOD Benefit of doubt FT Follow through ISW Ignore subsequent working M0, M1 Method mark awarded 0, 1 A0, A1 Accuracy mark awarded 0, 1 B0, B1 Independent mark awarded 0, 1 SC Special case ^ Omission sign MR Misread Highlighting Other abbreviations in mark scheme
Meaning
E1 Mark for explaining U1 Mark for correct units G1 Mark for a correct feature on a graph M1 dep* Method mark dependent on a previous mark, indicated by * cao Correct answer only oe Or equivalent rot Rounded or truncated soi Seen or implied www Without wrong working
4773 Mark Scheme June 2014
2
2. Subject-specific Marking Instructions for GCE Mathematics (MEI) Decision strand a Annotations should be used whenever appropriate during your marking.
The A, M and B annotations must be used on your standardisation scripts for responses that are not awarded either 0 or full marks. It is vital that you annotate standardisation scripts fully to show how the marks have been awarded. For subsequent marking you must make it clear how you have arrived at the mark you have awarded.
b An element of professional judgement is required in the marking of any written paper. Remember that the mark scheme is designed to assist in marking incorrect solutions. Correct solutions leading to correct answers are awarded full marks but work must not be judged on the answer alone, and answers that are given in the question, especially, must be validly obtained; key steps in the working must always be looked at and anything unfamiliar must be investigated thoroughly. Correct but unfamiliar or unexpected methods are often signalled by a correct result following an apparently incorrect method. Such work must be carefully assessed. When a candidate adopts a method which does not correspond to the mark scheme, award marks according to the spirit of the basic scheme; if you are in any doubt whatsoever (especially if several marks or candidates are involved) you should contact your Team Leader.
c The following types of marks are available. M A suitable method has been selected and applied in a manner which shows that the method is essentially understood. Method marks are not usually lost for numerical errors, algebraic slips or errors in units. However, it is not usually sufficient for a candidate just to indicate an intention of using some method or just to quote a formula; the formula or idea must be applied to the specific problem in hand, eg by substituting the relevant quantities into the formula. In some cases the nature of the errors allowed for the award of an M mark may be specified. A Accuracy mark, awarded for a correct answer or intermediate step correctly obtained. Accuracy marks cannot be given unless the associated Method mark is earned (or implied). Therefore M0 A1 cannot ever be awarded. B Mark for a correct result or statement independent of Method marks.
4773 Mark Scheme June 2014
3
E A given result is to be established or a result has to be explained. This usually requires more working or explanation than the establishment of an unknown result. Unless otherwise indicated, marks once gained cannot subsequently be lost, eg wrong working following a correct form of answer is ignored. Sometimes this is reinforced in the mark scheme by the abbreviation isw. However, this would not apply to a case where a candidate passes through the correct answer as part of a wrong argument.
d When a part of a question has two or more ‘method’ steps, the M marks are in principle independent unless the scheme specifically says otherwise; and similarly where there are several B marks allocated. (The notation ‘dep *’ is used to indicate that a particular mark is dependent on an earlier, asterisked, mark in the scheme.) Of course, in practice it may happen that when a candidate has once gone wrong in a part of a question, the work from there on is worthless so that no more marks can sensibly be given. On the other hand, when two or more steps are successfully run together by the candidate, the earlier marks are implied and full credit must be given.
e The abbreviation ft implies that the A or B mark indicated is allowed for work correctly following on from previously incorrect results. Otherwise, A and B marks are given for correct work only — differences in notation are of course permitted. A (accuracy) marks are not given for answers obtained from incorrect working. When A or B marks are awarded for work at an intermediate stage of a solution, there may be various alternatives that are equally acceptable. In such cases, exactly what is acceptable will be detailed in the mark scheme rationale. If this is not the case please consult your Team Leader. Sometimes the answer to one part of a question is used in a later part of the same question. In this case, A marks will often be ‘follow through’. In such cases you must ensure that you refer back to the answer of the previous part question even if this is not shown within the image zone. You may find it easier to mark follow through questions candidate-by-candidate rather than question-by-question.
f Wrong or missing units in an answer should not lead to the loss of a mark unless the scheme specifically indicates otherwise. Candidates are expected to give numerical answers to an appropriate degree of accuracy, with 3 significant figures often being the norm. Small variations in the degree of accuracy to which an answer is given (e.g. 2 or 4 significant figures where 3 is expected) should not normally be penalised, while answers which are grossly over- or under-specified should normally result in the loss of a mark. The situation regarding any particular cases where the accuracy of the answer may be a marking issue should be detailed in the mark scheme rationale. If in doubt, contact your Team Leader.
g Rules for replaced work If a candidate attempts a question more than once, and indicates which attempt he/she wishes to be marked, then examiners should do as the candidate requests.
4773 Mark Scheme June 2014
4
If there are two or more attempts at a question which have not been crossed out, examiners should mark what appears to be the last (complete) attempt and ignore the others. NB Follow these maths-specific instructions rather than those in the assessor handbook.
h For a genuine misreading (of numbers or symbols) which is such that the object and the difficulty of the question remain unaltered, mark according to the scheme but following through from the candidate’s data. A penalty is then applied; 1 mark is generally appropriate, though this may differ for some units. This is achieved by withholding one A mark in the question. Note that a miscopy of the candidate’s own working is not a misread but an accuracy error.
4771 Mark Scheme June 2014
1
Question Answer Marks Guidance
1 (i)
M1 12 vertices
A1 connectivity
(all 18 arcs and no extras)
[2]
1 (ii) 4 ( or “>2” or “multiple” ... not “some”) odd nodes ... top steps, pool, front steps, olive ...
so neither Eulerian nor semi-Eulerian., but not just “not Eulerian”. (This terminology not required.)
B1
[1]
1 (iii) start/end at pool/top steps, or vice versa M1
e.g. po–pd-fd-po-pa-pd-bd-fd-fs-gat-ol-fs-ol-gar-bd-pa-ts-fi-or-ts (20 nodes, 19 arcs) A1
path from front steps to the olive tree B1 must be stated
[3]
fig
top steps
back door
patio
pool door pool
front door
front steps
gate olive
garage
orange
4771 Mark Scheme June 2014
2
Question Answer Marks Guidance
1 (iv) Possible answer:
No repetition of any arc needed
M1
Start/stop are front steps/olive A1
Alternative answer:
By repeating fs/ol or ol/fs ...
(M1)
can start and stop at same point, e.g. front door. (A1)
[2]
2 (i) e.g.
0,1,2 coffee
3,4,5,6,7,8 tea
(9 reject and redraw)
M1
reject
A1
proportions + efficient,
ie using 9 digits (so allow
00, 01, ..., 09)
[2]
2 (ii) Ten simulated coffees or teas, corresponding to their rule and the given random digits.
e.g. T C C T C T T C T C
e.g. C T T T T C T T C T
B1
[1]
2 (iii) e.g.
Coffee at breakfast
00-54 coffee
55-99 tea
B1
Breakfast drink must be
specified.
Tea at breakfast
00-14 tea
15-99 coffee
B1
Breakfast drink must be
specified.
[2]
4771 Mark Scheme June 2014
3
Question Answer Marks Guidance
2 (iv) Ten simulated coffees or teas, using answers to part (ii) to define which rule to use.
e.g. C C T C C C C C T C
e.g. C C T C C T C C C C
e.g. C C C C T T C C C T
M1
A1
first 4, ref part (ii)
ft errors in (ii)
[2]
2 (v) Accumulating and computing the proportion.
e.g.
C - 65%
B1 ft
[1]
4771 Mark Scheme June 2014
4
Question Answer Marks Guidance
3 (i) ACD is 7+ 2 = 9 (< 12)
or AFD is 3+ 8 =11 (< 12)
B1
needs numerical
justification
AD could by via some point of interest, or over difficult terrain, or ... The triangle inequality applies to
triangles!
B1
[2]
3 (ii)
A 1 B 3 C 4 D5 E (6) F 2
A 6 7 12 3
B 6 10 8
C 7 10 2
D 12 2 9 8
E 8 9
F 3 8
26 (miles)
M1
M1
M1
A1
B1
B1
[6]
starting at and crossing
row A (i.e. no selection in
row)
selecting FA and BA
(or first two arcs following
wrong start)
numbering columns A, F
and B (similarly)
all correct
(dependent on 3 Ms)
(can cross all rows)
cao (weights not needed)
cao
A
B
C
D
E
F
6
7
3
8
2
or transpose
4771 Mark Scheme June 2014
5
Question Answer Marks Guidance
4 (i)
&
(ii)
e.g.
minimum completion time = 7.5 hours
critical activities – A, B, E, F, G
(or ABEG + ABEF)
M1 Activity on arc
A1 Single start and end
A1 A, B, C, D (precedences)
A1 E (precedences)
A1 F and G (all correct)
M1 A1
forward pass
M1 A1
backward pass
B1 time (cao)
B1 critical activities (cao)
[11]
4 (iii) e.g.
B1
not ft
B1
must be labelled or to
scale (e.g. on the squares
provided)
Can be written out instead.
[2]
4 (iv) 8.0 hours or delay 0.5 hours B1 cao ISW if needed
A, C, D B1 cao
8.5 hours or delay of 1 hour B1 cao ISW if needed
[3]
B
5
A
0.5 0.5 0.5
2.5 5.5
5.5 5.5
0 0
7.5 7.5
7.5 7.5 6.5 6.5
C
2 D
1.5
G
1
F
1 E
1
A B
F C D
0.5 2.5 4.0
5.5
7.5
7.5
6.5
G E
Needs to be clear what is done by whom.
This doesn’t necessarily require people
being labelled ... but might.
4771 Mark Scheme June 2014
6
Question Answer Marks Guidance
5 (a)
(i) 6 3 10 5 16 8 4 2 1 4 2 1 ... (can stop at second “4”)
M1 6 3 10
A1
[2]
5 (a) (ii) 256 128 64 32 16 8 4 2 1 4 2 1 ...
(as above, or can note repetition from “16”)
M1 256 128 64
A1
[2]
5 (a) (iii) e.g. Step 25 If n is 1 then stop. (Any step number between 21 and 29, or indicated in some other way.)
B1 ISW, but “Step 35” is
wrong.
[1]
5 (a) (iv) Need to know that all chosen numbers lead to 1. B1
[1]
5 (b) (i) Box 1: 2 1 6 A B C
Box 2: 3 3 D E
Box 3: 5 F
B1
3 boxes B1
[2]
5 (b) (ii) 1 2 3 3 5 6 B A D E F C B A E D F C
Box 1: 1 2 3 3 B A D E
Box 2: 5 F
Box 3: 6 C
B1
sorted increasing
B1
[2]
5 (b) (iii) (6 5 3 3 2 1) (C F D E A B) (C F E D A B)
Box 1: 6 3 1 C D B
Box 2: 5 3 2 F E A
M1
placing a “3” or D or E
into box 1
A1
[2]
4771 Mark Scheme June 2014
7
Question Answer Marks Guidance
5 (b) (iv) e.g. (for fitting into boxes of size 10)
6 3 3 2 2 2 2
Reducing order/first fit:
Box 1: 6 3
Box 2: 3 2 2 2
Box 3: 2
Optimal:
Box 1: 6 2 2
Box 2: 3 3 2 2
M1
valid example
A1
correctly doing it
[2]
5 (b) (v) 30 (60/6)2 = 3000 secs ... 50 minutes M1
multiplying 30 by a
squared value
A1
[2]
4771 Mark Scheme June 2014
8
Question Answer Marks Guidance
6 (i) Let x be the number of (10s of) litres of stew and y the number of (10s of) litres of soup that Ian makes.
B1
“number of”, referring to
soup & stew
B1 identification of soup and
stew variables
Carrots: 0.15x + 0.1y < 100, i.e. 3x + 2y < 2000 B1 -1 each scaling or
Beans: 0.1x + 0.075y < 70, i.e, 4x + 3y < 2800 B1 systematic error, e.g.
Tomatoes: 0.15x + 0.15y < 110, i.e. 3x + 3y < 2200 B1 equalities
[5]
6 (ii) Intercepts are (666.7,0) and (0,1000)
(700,0) and (0,933.3)
(733.3,0) and (0,733.3)
B1
axes consistently labelled
and scaled
B1 line 1
B1 line 2
B1
line 3 all subject to
negative gradients
B1 shading giving feasible
quadrilateral bounded by
axes ... or identified by
vertices
[5]
1000
733.3
y
x
933.3
733.3
700 666.7
bod shading here
Ignore “soup” and “stew” labelling on axes unless no variable
labelling.
-1 if variables swapped in error.
-1 if systematic scaling error (following inequalities in 6(i).
broken axis scores 0 for 6(ii)
4771 Mark Scheme June 2014
9
Question Answer Marks Guidance
6 (iii)
Line 2 irrelevant. Comparing at (0, 733.3), (533.3 10, 200 10) and (666.7, 0)
(accuracy quoted is for graphical solutions).
Max profit at intersection of lines 1 and 3 (533.33,200) with profit £3466.67 (accuracy from 3375 to 3560)
(cf £3333.33 and £2933.33)
M1
comparing 3 vertices (not
origin) or profit line with
approximately correct
gradient (–5/4)
So make 533.33 litres of stew and 200 litres of soup, A1 stew and soup (cao)
giving a profit of £3466.67 (3375 – 3560). A1 profit (cao)
[3]
6 (iv)
Best solution now at (0, 933.3) ... profit £3733.33 (£373.33)
M1
So best new solution uses 30 kg extra tomatoes (140 kg total)
A1
30kg (allow 140 new total)
cao
Extra profit is £(3733.33 – 3466.67 – 30*2.5) = £191.67
A1
(allow £3658.33 new total)
cao
[3]
Oxford Cambridge and RSA Examinations
GCE
Mathematics (MEI)
Unit 4771: Decision Mathematics 1
Advanced Subsidiary GCE
Mark Scheme for June 2015
OCR (Oxford Cambridge and RSA) is a leading UK awarding body, providing a wide range of qualifications to meet the needs of candidates of all ages and abilities. OCR qualifications include AS/A Levels, Diplomas, GCSEs, Cambridge Nationals, Cambridge Technicals, Functional Skills, Key Skills, Entry Level qualifications, NVQs and vocational qualifications in areas such as IT, business, languages, teaching/training, administration and secretarial skills. It is also responsible for developing new specifications to meet national requirements and the needs of students and teachers. OCR is a not-for-profit organisation; any surplus made is invested back into the establishment to help towards the development of qualifications and support, which keep pace with the changing needs of today’s society. This mark scheme is published as an aid to teachers and students, to indicate the requirements of the examination. It shows the basis on which marks were awarded by examiners. It does not indicate the details of the discussions which took place at an examiners’ meeting before marking commenced. All examiners are instructed that alternative correct answers and unexpected approaches in candidates’ scripts must be given marks that fairly reflect the relevant knowledge and skills demonstrated. Mark schemes should be read in conjunction with the published question papers and the report on the examination. OCR will not enter into any discussion or correspondence in connection with this mark scheme. © OCR 2015
4771 Mark Scheme June 2015
3
Annotations and abbreviations
Annotation in scoris Meaning and BOD Benefit of doubt FT Follow through ISW Ignore subsequent working M0, M1 Method mark awarded 0, 1 A0, A1 Accuracy mark awarded 0, 1 B0, B1 Independent mark awarded 0, 1 SC Special case ^ Omission sign MR Misread Highlighting Other abbreviations in mark scheme
Meaning
E1 Mark for explaining U1 Mark for correct units G1 Mark for a correct feature on a graph M1 dep* Method mark dependent on a previous mark, indicated by * cao Correct answer only oe Or equivalent rot Rounded or truncated soi Seen or implied www Without wrong working
4771 Mark Scheme June 2015
4
Subject-specific Marking Instructions for GCE Mathematics (MEI) Decision strand a Annotations should be used whenever appropriate during your marking.
The A, M and B annotations must be used on your standardisation scripts for responses that are not awarded either 0 or full marks. It is vital that you annotate standardisation scripts fully to show how the marks have been awarded. For subsequent marking you must make it clear how you have arrived at the mark you have awarded.
b An element of professional judgement is required in the marking of any written paper. Remember that the mark scheme is designed to assist in marking incorrect solutions. Correct solutions leading to correct answers are awarded full marks but work must not be judged on the answer alone, and answers that are given in the question, especially, must be validly obtained; key steps in the working must always be looked at and anything unfamiliar must be investigated thoroughly. Correct but unfamiliar or unexpected methods are often signalled by a correct result following an apparently incorrect method. Such work must be carefully assessed. When a candidate adopts a method which does not correspond to the mark scheme, award marks according to the spirit of the basic scheme; if you are in any doubt whatsoever (especially if several marks or candidates are involved) you should contact your Team Leader.
c The following types of marks are available. M A suitable method has been selected and applied in a manner which shows that the method is essentially understood. Method marks are not usually lost for numerical errors, algebraic slips or errors in units. However, it is not usually sufficient for a candidate just to indicate an intention of using some method or just to quote a formula; the formula or idea must be applied to the specific problem in hand, eg by substituting the relevant quantities into the formula. In some cases the nature of the errors allowed for the award of an M mark may be specified. A Accuracy mark, awarded for a correct answer or intermediate step correctly obtained. Accuracy marks cannot be given unless the associated Method mark is earned (or implied). Therefore M0 A1 cannot ever be awarded. B Mark for a correct result or statement independent of Method marks.
4771 Mark Scheme June 2015
5
E A given result is to be established or a result has to be explained. This usually requires more working or explanation than the establishment of an unknown result. Unless otherwise indicated, marks once gained cannot subsequently be lost, eg wrong working following a correct form of answer is ignored. Sometimes this is reinforced in the mark scheme by the abbreviation isw. However, this would not apply to a case where a candidate passes through the correct answer as part of a wrong argument.
d When a part of a question has two or more ‘method’ steps, the M marks are in principle independent unless the scheme specifically says otherwise; and similarly where there are several B marks allocated. (The notation ‘dep *’ is used to indicate that a particular mark is dependent on an earlier, asterisked, mark in the scheme.) Of course, in practice it may happen that when a candidate has once gone wrong in a part of a question, the work from there on is worthless so that no more marks can sensibly be given. On the other hand, when two or more steps are successfully run together by the candidate, the earlier marks are implied and full credit must be given.
e The abbreviation ft implies that the A or B mark indicated is allowed for work correctly following on from previously incorrect results. Otherwise, A and B marks are given for correct work only — differences in notation are of course permitted. A (accuracy) marks are not given for answers obtained from incorrect working. When A or B marks are awarded for work at an intermediate stage of a solution, there may be various alternatives that are equally acceptable. In such cases, exactly what is acceptable will be detailed in the mark scheme rationale. If this is not the case please consult your Team Leader. Sometimes the answer to one part of a question is used in a later part of the same question. In this case, A marks will often be ‘follow through’. In such cases you must ensure that you refer back to the answer of the previous part question even if this is not shown within the image zone. You may find it easier to mark follow through questions candidate-by-candidate rather than question-by-question.
f Wrong or missing units in an answer should not lead to the loss of a mark unless the scheme specifically indicates otherwise. Candidates are expected to give numerical answers to an appropriate degree of accuracy, with 3 significant figures often being the norm. Small variations in the degree of accuracy to which an answer is given (e.g. 2 or 4 significant figures where 3 is expected) should not normally be penalised, while answers which are grossly over- or under-specified should normally result in the loss of a mark. The situation regarding any particular cases where the accuracy of the answer may be a marking issue should be detailed in the mark scheme rationale. If in doubt, contact your Team Leader.
g Rules for replaced work If a candidate attempts a question more than once, and indicates which attempt he/she wishes to be marked, then examiners should do as the candidate requests.
If there are two or more attempts at a question which have not been crossed out, examiners should mark what appears to be the last
4771 Mark Scheme June 2015
6
(complete) attempt and ignore the others. NB Follow these maths-specific instructions rather than those in the assessor handbook.
h For a genuine misreading (of numbers or symbols) which is such that the object and the difficulty of the question remain unaltered, mark according to the scheme but following through from the candidate’s data. A penalty is then applied; 1 mark is generally appropriate, though this may differ for some units. This is achieved by withholding one A mark in the question. Note that a miscopy of the candidate’s own working is not a misread but an accuracy error.
4771 Mark Scheme June 2015
7
Question Answer Marks Guidance
1 (i)
M1
At least two directed arcs,
each from the top of a lift
to the bottom
A1 all 4 correct
[2]
1 (ii) (Angus has to repeat all of the chairlifts.)
He has to repeat A either because two ski runs deliver skiers to it, or because it serves two ski runs. B1
He has to repeat B and C …
… either because two ski runs deliver skiers to them, or because they serve two ski runs or because of ski
run 4.
M1
A1
[3]
1 (iii) Angus has to repeat ski run 3 because he has to repeat chairlifts B and/or C (or runs 4 and 5). M1 run 3
A1 for explanation
[2]
1 (iv) This would have to be represented by an arc from chairlift C to chairlift D, but in a bipartite graph an arc
can only connect two elements which are not in the same set. In this case the sets are chairlifts and ski
runs.
B1 needs to be contextualised
[1]
C
1
3
4
5
B
A
4771 Mark Scheme June 2015
8
Question Answer Marks Guidance
2 (i) i 1 2 3
m1 2
c1 8
m2 2
c2 5
m3 4
c3 3
j 1 2 3
a 2 3 4 1
b 3 4 1 5 2
M1
A1
j 1
a 2
b 3
as and bs
(4’s and 5’s not essential)
d1 2
x1 1
y1 7 B1 for 1 and 7
d2 -2
x2 2.5
y2 13
B1 for 2.5 and 13
d3 0
x3
y3
B1 for 0
Print area M1 use of print area
(1, 7)
(2.5, 13)
parallel A1 3 copied, inc “parallel”
[7]
2
(ii)
Finds the line intersections
B1
[1]
4771 Mark Scheme June 2015
9
Question Answer Marks Guidance
3 (i) At least 50% coffee (allow more than)
(so number of coffee filters ≥ number of tea bags,
so number tea bags ≤ number of coffee filters.)
B1
referral to sales info to
get ≤ (allow <)
At most 75% coffee (allow less than)
so number of coffee filters ≤ 3 number of tea bags,
so number of tea bags ≥ 1/3 number of coffee filters.
B1 referral to sales info +
explanation of 1/3 to get
≥ (allow >)
[2]
3 (ii) Let x be the number of coffee filters.
Let y be the number of tea bags ... or vice versa.
B1
“number of” essential
B1
“500” line
B1
£50 line
B1
lines from (i)
B1cao
shading
[5]
3 (iii) Coffee – 75% of 500. Tea – 50% of 500. B1cao
[1]
x
y
1000
500
500
4771 Mark Scheme June 2015
10
Question Answer Marks Guidance
4 (a)
B1
Dijkstra
award only if correct at E
B1
other working values
B1
order of labelling
B1 labels
AB 3
AC 2
AD 7
AFE 5
AF 3
B1
routes
B1 lengths
[6]
A B
C F 8
3
2
1
3
0
2 3
2 2
3/4 3
3/4 3 7
6
5
3
E D
4
5
7
5 6 7
2
8 5
4771 Mark Scheme June 2015
11
Question Answer Marks Guidance
4 (b) (i)
M1
tree or attempt at Prim
A1
Length = 15 B1
[3]
4 (b) (ii) Removes AE, AD, CE then BC M1 AE, AD, CE (in order)
A1 BC only
[2]
4 (b) (iii) It will remain connected. B1
There will be no cycles left. B1
Removing a largest possible arc at each stage guarantees a minimum spanning tree. B1
[3]
4 (b) (iv) (n2-3n+2)/2 (or equivalent) arcs for Jill to remove. B1 algebraic simplification
not needed
More than Prim if n is 5 or more B1
[2]
A B
C F
3
2
5
3
E D
2
4771 Mark Scheme June 2015
12
Question Answer Marks Guidance
5 (i)&(ii)
M1
activity on arc
A1 F & I
A1 J
A1 K
A1 rest
[5]
M1A1 forward pass
M1A1 backward pass
minimum completion time = 55 minutes B1cao time
critical activities – A, E, F, G, H, J, K B1cao critical activities
[6]
5 (iii)
e.g. (each cell represents 5 minutes)
1st person A E E F G J K
2nd person B D I I I I I I I
other activities C C C C
H H H H
M1
A, E, F, G allocated OK
A1
B, D, I, J, K OK
B1 C and H correctly timed
[3]
5 (iv) e.g.
1st person A D I I I I I I J K
2nd person B E E F G I
B1
a correct schedule for two
people
50 minutes
B1
50 minutes seen
[2]
B
5
E
10 F
5
D
5
H
20
0 0
5 5
10 30
G
5
I
30
C
20
J
5
10 15
15 15 20 20 25 25
45 45
50 50
55 55
A
5
K
5
4771 Mark Scheme June 2015
13
Question Answer Marks Guidance
6 (i) e.g.
French 0, 1, 2, 3, 4, 5, 6 Greek
7, 8, 9 French
Greek 0, 1, 2, 3, 4, 5 French
6, 7, 8, 9 Greek
B1
French
M1
A1
proportions
efficient
[3]
6 (ii) Using Greek rule
Using French rule
e.g. F G G G F G F G G G
M1 Greek
M1 French
A1
Computing observed probabilities
e.g. P(F)=0.3 and P(G)=0.7
(Long run probabilities are 6/13 French and 7/13 Greek.)
B1
[4]
6 (iii) e.g.
French 0, 1 French
2, 3, 4, 5, 6, 7 Greek
8, 9 Hungarian
B1
Greek 0, 1, 2, 3, 4 French
5, 6, 7 Greek
8, 9 Hungarian
B1
Hungarian 0, 1, 2 French
3, 4, 5 Greek
6, 7, 8 Hungarian
9 reject and redraw
M1 reject one (or more)
A1 proportions
A1 efficient
[5]
4771 Mark Scheme June 2015
14
6 (iv) Greek rule applied in correct circumstances and correctly B1
French rule applied in correct circumstances and correctly B1
Hungarian rule applied in correct circumstances and correctly
e.g. F F H F G H F G F F
B1
so P(F)=0.6, P(G)=0.2, P(H)=0.2
(Long run proportions are 56/169, 74/169 and 39/169.) B1
[4]
Oxford Cambridge and RSA Examinations is a Company Limited by Guarantee Registered in England Registered Office; 1 Hills Road, Cambridge, CB1 2EU Registered Company Number: 3484466 OCR is an exempt Charity OCR (Oxford Cambridge and RSA Examinations) Head office Telephone: 01223 552552 Facsimile: 01223 552553 © OCR 2015
OCR (Oxford Cambridge and RSA Examinations) 1 Hills Road Cambridge CB1 2EU OCR Customer Contact Centre Education and Learning Telephone: 01223 553998 Facsimile: 01223 552627 Email: [email protected] www.ocr.org.uk For staff training purposes and as part of our quality assurance programme your call may be recorded or monitored
Oxford Cambridge and RSA Examinations
GCE
Mathematics (MEI)
Unit 4771: Decision Mathematics 1 Advanced Subsidiary GCE
Mark Scheme for June 2016
OCR (Oxford Cambridge and RSA) is a leading UK awarding body, providing a wide range of qualifications to meet the needs of candidates of all ages and abilities. OCR qualifications include AS/A Levels, Diplomas, GCSEs, Cambridge Nationals, Cambridge Technicals, Functional Skills, Key Skills, Entry Level qualifications, NVQs and vocational qualifications in areas such as IT, business, languages, teaching/training, administration and secretarial skills. It is also responsible for developing new specifications to meet national requirements and the needs of students and teachers. OCR is a not-for-profit organisation; any surplus made is invested back into the establishment to help towards the development of qualifications and support, which keep pace with the changing needs of today’s society. This mark scheme is published as an aid to teachers and students, to indicate the requirements of the examination. It shows the basis on which marks were awarded by examiners. It does not indicate the details of the discussions which took place at an examiners’ meeting before marking commenced. All examiners are instructed that alternative correct answers and unexpected approaches in candidates’ scripts must be given marks that fairly reflect the relevant knowledge and skills demonstrated. Mark schemes should be read in conjunction with the published question papers and the report on the examination. OCR will not enter into any discussion or correspondence in connection with this mark scheme. © OCR 2016
4771 Mark Scheme June 2016
3
1. Annotations and abbreviations Annotation in scoris Meaning and BOD Benefit of doubt FT Follow through ISW Ignore subsequent working M0, M1 Method mark awarded 0, 1 A0, A1 Accuracy mark awarded 0, 1 B0, B1 Independent mark awarded 0, 1 SC Special case ^ Omission sign MR Misread Highlighting Other abbreviations in mark scheme
Meaning
E1 Mark for explaining U1 Mark for correct units G1 Mark for a correct feature on a graph M1 dep* Method mark dependent on a previous mark, indicated by * cao Correct answer only oe Or equivalent rot Rounded or truncated soi Seen or implied www Without wrong working
4771 Mark Scheme June 2016
4
2. Subject-specific Marking Instructions for GCE Mathematics (MEI) Decision strand
a Annotations should be used whenever appropriate during your marking. The A, M and B annotations must be used on your standardisation scripts for responses that are not awarded either 0 or full marks. It is vital that you annotate standardisation scripts fully to show how the marks have been awarded. For subsequent marking you must make it clear how you have arrived at the mark you have awarded.
b An element of professional judgement is required in the marking of any written paper. Remember that the mark scheme is designed to assist in marking incorrect solutions. Correct solutions leading to correct answers are awarded full marks but work must not be judged on the answer alone, and answers that are given in the question, especially, must be validly obtained; key steps in the working must always be looked at and anything unfamiliar must be investigated thoroughly. Correct but unfamiliar or unexpected methods are often signalled by a correct result following an apparently incorrect method. Such work must be carefully assessed. When a candidate adopts a method which does not correspond to the mark scheme, award marks according to the spirit of the basic scheme; if you are in any doubt whatsoever (especially if several marks or candidates are involved) you should contact your Team Leader.
c The following types of marks are available. M A suitable method has been selected and applied in a manner which shows that the method is essentially understood. Method marks are not usually lost for numerical errors, algebraic slips or errors in units. However, it is not usually sufficient for a candidate just to indicate an intention of using some method or just to quote a formula; the formula or idea must be applied to the specific problem in hand, eg by substituting the relevant quantities into the formula. In some cases the nature of the errors allowed for the award of an M mark may be specified. A Accuracy mark, awarded for a correct answer or intermediate step correctly obtained. Accuracy marks cannot be given unless the associated Method mark is earned (or implied). Therefore M0 A1 cannot ever be awarded. B Mark for a correct result or statement independent of Method marks. E A given result is to be established or a result has to be explained. This usually requires more working or explanation than the establishment of an unknown result.
4771 Mark Scheme June 2016
5
Unless otherwise indicated, marks once gained cannot subsequently be lost, eg wrong working following a correct form of answer is ignored. Sometimes this is reinforced in the mark scheme by the abbreviation isw. However, this would not apply to a case where a candidate passes through the correct answer as part of a wrong argument.
d When a part of a question has two or more ‘method’ steps, the M marks are in principle independent unless the scheme specifically says otherwise; and similarly where there are several B marks allocated. (The notation ‘dep *’ is used to indicate that a particular mark is dependent on an earlier, asterisked, mark in the scheme.) Of course, in practice it may happen that when a candidate has once gone wrong in a part of a question, the work from there on is worthless so that no more marks can sensibly be given. On the other hand, when two or more steps are successfully run together by the candidate, the earlier marks are implied and full credit must be given.
e The abbreviation ft implies that the A or B mark indicated is allowed for work correctly following on from previously incorrect results. Otherwise, A and B marks are given for correct work only — differences in notation are of course permitted. A (accuracy) marks are not given for answers obtained from incorrect working. When A or B marks are awarded for work at an intermediate stage of a solution, there may be various alternatives that are equally acceptable. In such cases, exactly what is acceptable will be detailed in the mark scheme rationale. If this is not the case please consult your Team Leader. Sometimes the answer to one part of a question is used in a later part of the same question. In this case, A marks will often be ‘follow through’. In such cases you must ensure that you refer back to the answer of the previous part question even if this is not shown within the image zone. You may find it easier to mark follow through questions candidate-by-candidate rather than question-by-question.
f Wrong or missing units in an answer should not lead to the loss of a mark unless the scheme specifically indicates otherwise. Candidates are expected to give numerical answers to an appropriate degree of accuracy, with 3 significant figures often being the norm. Small variations in the degree of accuracy to which an answer is given (e.g. 2 or 4 significant figures where 3 is expected) should not normally be penalised, while answers which are grossly over- or under-specified should normally result in the loss of a mark. The situation regarding any particular cases where the accuracy of the answer may be a marking issue should be detailed in the mark scheme rationale. If in doubt, contact your Team Leader.
g Rules for replaced work If a candidate attempts a question more than once, and indicates which attempt he/she wishes to be marked, then examiners should do as the candidate requests.
If there are two or more attempts at a question which have not been crossed out, examiners should mark what appears to be the last (complete) attempt and ignore the others. NB Follow these maths-specific instructions rather than those in the assessor handbook.
4771 Mark Scheme June 2016
6
h For a genuine misreading (of numbers or symbols) which is such that the object and the difficulty of the question remain
unaltered, mark according to the scheme but following through from the candidate’s data. A penalty is then applied; 1 mark is generally appropriate, though this may differ for some units. This is achieved by withholding one A mark in the question. Note that a miscopy of the candidate’s own working is not a misread but an accuracy error.
4771 Mark Scheme June 2016
7
Question Answer Marks Guidance
1 (i) e.g. 0, 1, 2, 3 win
4, 5, 6, 7, 8, 9 lose
or 0, 1, 2, 3, 4, 5 lose
6, 7, 8, 9 win
M1
A1
correct rule
efficient rule
disallow 1, 8, 3, 5 win
disallow 6, 7, 1, 3 win
(ii) In the worst case Pierre will suffer 3 consecutive losses, of £100, £200 and £400 respectively. He will then
be unable to fund the next bet of £800.
B1 100, 200, 400 may by
implied, eg by 700 lost or
300 left
(iii) e.g. or
1, 6, 4 win 1, 6, 4 win
8, 6, 4 lose 8, 6, 4 win
8, 7, 4 lose 8, 7, 4 win
3, 1, 1 win 3, 1, 1 lose
5, 3, 2 win 5, 3, 2 lose
M1
A1
or
M1
A1
correct identification of
first win and of first loss
rest
numbers L/W for 1 6 4
and 8 6 4
rest + interpretation
(iv) 100 x no of wins + 700 x no of losses
eg1 … -£1100 eg2 … £3900
eg1 … on average a loss of £220 per application of the strategy eg2 … on average £780 left
M1
A1
A1
weighted sum or 5
monetary outcomes –
implied OK
(Their “700” OK here)
correct sum following
their simulation but not
their 700.
their sum/5
4771 Mark Scheme June 2016
8
Question Answer Marks Guidance
2 (i) n 1 2 3 4 5 6 7
p 1 0.962 0.888 0.785 0.664 0.537 0.413
M1
M1
A1
A1
n=2 … awrt 0.96
n=3 … awrt 0.88 or 0.89
n=4 … awrt 0.79
stopping at n=7 with p<0.5
(ii) Need to select 7 cards for the probability of repetition on the list to exceed 0.5. B1
B1
their “7”
P(repetition) exceeds 0.5
(iii) Step 1 Set n = 1.
Step 2 Set p = 1.
Step 3 Set n = n + 1.
Step 4 Set p = p (366-n)/365.
Step 5 If p < 0.5 then stop.
Step 6 Go to Step 3.
B1
both changes (step 4) and
no others
(iv) Because they do not have the same frequency of occurrence (probability) as other birthdays. B1
4771 Mark Scheme June 2016
9
Question Answer Marks Guidance
3 (i)
B1
B1
B1
adjacency graph all correct
cao
complement graph correct
cao
three colours
(ii)
A
B Two disjoint, complementary and complete subgraphs can be identified (in several ways)
M1
A1
A1
M1
A1
top front adjacency OK
adjacency graph all correct
complement graph correct
cao
two subgraphs
complete
base
front back
left right
base
front back
left right
So 3 colours
are needed
top front top back
top left top right
base front base back
base left base right
top front top back
top left top right
base front base back
base left base right
4771 Mark Scheme June 2016
10
Question Answer Marks Guidance
4 (i)
M1
A1
3 widths + waste
4 (ii) 0.06x + 0.21y + 0.04z (m2)
M1
A1
3 areas
any units OK ... ignore
scaling
4 (iii) 2x + y > 20 B1
4 (iv) y + 3z > 24
B1
4 (v) Use of z = 20 – x – y
Minimise 0.02x + 0.17y (constant of 0.8 not needed but OK if there)
st 2x + y > 20
-3x – 2y > -36 or 3x + 2y < 36
M1
A1
A1
“minimise” not needed -
given
z m
4cm waste
32cm
32cm
32cm
4771 Mark Scheme June 2016
11
Question Answer Marks Guidance
4
(vi)
B1
B1
B1
M1
M1
A1
A1
line (cao)
line (cao)
shading – follow two neg
grad lines making a
triangle with base on x-
axis
objective valued at (10,0)
and at (4,12)
z =10
both
waste
Cut 10m according to plan x and
10m according to plan z.
Gives ...
20m of material with width 47cm
30m of material with width 32cm
1m2 of waste.
y
x 10 12
18
20
(4, 12)
20 or 100 or 0.2 or 1
212 or 292 or 2.12 or 2.92
Min waste at (10, 0)
4771 Mark Scheme June 2016
12
Question Answer Marks Guidance
5 (i)
Activity Duration (weeks) Immediate predecessors
A 1 ‒
B 1 ‒
C 1 ‒
D 8 A
E 6 B
F 6 C, I
G 6 ‒
H 1 D, E, F,G
I 2 ‒
J 4 A, B, C
K 2 H, J
B1
B3
A, B, C, G and I
-1 for 1 or 2 wrong rows
-2 for 3 or 4 wrong rows
-3 for 5 or 6 wrong rows
5 (ii)+
(iii)
Critical activities ... A, D, H, K
M1
A1
A1
A1
A1
M1
A1
M1
A1
B1cao
activity on arc
immediate predecessors
A, B, C, I, G
immediate predecessors
D (A), E(B), F(C,I,)
immediate predecessors
J(A,B,C), H(D,E,F,G)
immediate predecessors
K(J,H) + rest
forward pass
backward pass
1 6
0 0
1 1
1 3
2 3
1 3
6 9
9 9
12 12 10 10
A
1
C
1
B
1
I
2
G
6
F
6
D 8
E
6
H
1
J
4 K
2
4771 Mark Scheme June 2016
13
Question Answer Marks Guidance
5 (iv) eg
Week 1 2 3 4 5 6 7 8 9 10 11 12
CPA start time 0 1 2 3 4 5 6 7 8 9 10 11
Room 1 A D D D D D D D D H K K
Room 2 B E E E E E E F F
Room 3 C F F F F
G G G G G G
I I
J J J J
B1cao
B1cao
F (ES2, LF9)
rest
4771 Mark Scheme June 2016
14
Question Answer Marks Guidance
6 (a) (i) e.g.
Route – A D C Z U W X or A B D C Z U W X Distance ‒ 48 km
B1
B1
B1
B1
B1 B1
Dijkstra – E correct
other working values
order of labelling
labels
6 (a) (ii) No difference, but allow “one fewer”, as 15 (CZ) does not need to be added on to determine the route.
Part (i) is effectively using Dijkstra on the left network then Dijkstra on right network, but starting at 30
instead of 0 on the right network.
M1
A1
Need comment re just
one arc connecting the
two networks.
4
2 4
16 15
6 15
1 0
8
3 8
15 14
5 14
9
4 9
30
7 30
41
9 41
49
49 48
11 48
39
8 39
46 45
10 45 A
B
C
D
E F
12
13 10
5
9
8
6
5
7
4
Z
U V
W
X
Y
11
9
9
10
7
8
4 7
3
15
4771 Mark Scheme June 2016
15
Question Answer Marks Guidance
6 (b) (i) Order of choice ... AB, BD DE, DC, EF
M1
A1
B1
Kruskal (first 2 arcs
identified – OK if by
length)
min connector
6 (b) (ii) Order of inclusion ... U, W, X, V Y, Z M1
A1
Prim (first 2 vertices
identified - OK to say
UW, WX, etc, but in that
order. Not OK to identify
by lengths)
B1
min connector
6 (b) (iii) Total length = 72 km. B1cao
B1
27 + 30
+ 15 for the pass
A
B
C
D
E F
5
6
5
7
4
Z
U V
W
X
Y
9
7
4 7
3
Oxford Cambridge and RSA Examinations is a Company Limited by Guarantee Registered in England Registered Office; 1 Hills Road, Cambridge, CB1 2EU Registered Company Number: 3484466 OCR is an exempt Charity OCR (Oxford Cambridge and RSA Examinations) Head office Telephone: 01223 552552 Facsimile: 01223 552553 © OCR 2016
OCR (Oxford Cambridge and RSA Examinations) 1 Hills Road Cambridge CB1 2EU OCR Customer Contact Centre Education and Learning Telephone: 01223 553998 Facsimile: 01223 552627 Email: [email protected] www.ocr.org.uk For staff training purposes and as part of our quality assurance programme your call may be recorded or monitored