4.annexure-iii-scope of work (sow)

Upload: dipali

Post on 07-Aug-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    1/14

    121 | P a g e UP14C15018

     ANNEXURE-III

    SCOPE OF WORK

    Sub: Repair of Regeneration Columns C-1202 and C-1302 of GSU-12 and GSU-13 Plants at

    ONGC Uran Plant, Uran 

    The GSU units of plant removes the shore content like H2S & CO2 from hydrocarbon gas before

    extracting the LPG,C2C3,LAN and sweet lean gas.

    During the turnaround inspection of the columns C-1202 and C-1302, it is found that there is

    thickness loss at various location on columns from inside as well as outside also. The thickness

    loss has to be repaired for the service of the remaining life of the columns.

    The repairing of columns has to be done by lap band repair at some of the location, at other

    locations by weld build up. At some location SS cladding (inside the column C-1302) is

    damaged, hence an internal repair including the replacement at some portion and patch weld/

    weld build up repair at some location of clad/column is to be carried out.

    Details of columns(C-1202 & C-1302)

    SL no. Details Specification values

    1 Design pressure (Ks/cm2g) 5.7

    2 Operating pressure

    (Ks/cm2g)

    0.5/0.7

    3 Design temperature ( ̊C)  97.3(top)/125.7(bottom)

    4 Service Sulfinol-X solvent+H2S+CO2+hydrocarbon gas traces

    5 ID 2550mm(top)/3500mm(bottom)

    6 Capacity 129.2m3

     7 Thickness of shell (mm) 12(9+3) top 3 mm clad up to 5 m from top,15mm in

    middle,19 mm at bottom

    8 Max height of columns

    (meter)

    25.7+1.15

    9 MOC of shell/clad SA516Gr.60/ SA516Gr.60+A240-321

    10 Insulation thickness(mm) 105

    11 Joint efficiency 1.0/0.85

    12 Code ASME Sec.VII DIV.I 1986

    A .Repair locations of C-1202:

    Area of Corroded Zone

    (mXm) of external surface of Shell

    Fillet Weld patches area

    (mXm)

    Weld overlay area ( mXm)

    1.0X0.5 1.2X0.8 Nil

    0.5X0.5 Nil 2.0X2.0

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    2/14

    122 | P a g e UP14C15018

    B. Repair locations of C-1302:

    S.No LOCATION Nom

    inal

    thick

    ness(

    mm)

    Observ

    ed min.

    thickne

    ss(mm)

    Area of

    corrod

    ed

    zone(m

    xm)

    Type of repair

    Area

    to

    be

    repaired

    Internal

    3mm S

    cladding are

    to b

    replaced (m

    X m)

    1 A/1ST  shell from

    top

    12 6.4 1.0x0.3 Area of Lap bands

    (M X M) OD of shell-

    2.74m

    8.6x1.0 1.5 X1.0

    2 B/1ST  shell from

    top

    12 4.5 2.0x1.2

    5

    8.6x2.0 2.5x1.5

    3 B/1ST  shell from

    top

    12 7.0 1.0x1.0 8.6x1.5 1.5x1.0

    4 D/5th  shell fromtop

    15 9.4 1.5x1.0 Fillet weld patchesarea M2

    1.5x1.0 Nil

    5 E/5th  shell from

    top

    15 7.7 1.0x1.0 Fillet weld patches

    area M2 

    1.5x1.0 Nil

    6 F/5th  shell from

    top

    15 8.6 1.0x1.0 weld overlay area m2  2.0 Nil

    7 G/5th  shell from

    top

    15 8.9 0.2x0.2 weld 1.0overlay area

    m2 

    2.0 Nil

    8 H/5th  shell from

    top

    19 13.4 1.0x0.5 weld overlay area m2  1.5 Nil

    9 I/5th  shell from

    top

    19 12.0 0.2x0.2 weld overlay area m2  1.5 Nil

    Detail scope of work:

    1.  Erection/dismantling of scaffolding at periphery of columns prior to the shutdown as per

    the instructions of Engineer in charge is in the scope of contractor. Scaffolding material and

    all tools/tackles including consumables like paint removers, Rustolene, Brass Wire brushes,

    waste clothes is in the scope of contractor.

    2. 

    Erection/dismantling of scaffolding at inside of column, (if require,) shall be done as per the

    instructions of Engineer in charge and same is in the scope of contractor.

    3.  The removal/installation of insulation shall be in scope of ONGC. The scrap of insulation

    shall be removed by ONGC

    4.  The removal of composite coating shall be in scope of contractor (if required).

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    3/14

    123 | P a g e UP14C15018

    5.  After shut down blinding/DE blinding of columns shall be performed by contractor as per

    instruction of EIC.

    6.  The repair is to be done at identified locations inside as well as outside of columns which

    are at various height. The contractor may visit the site so as to get first hand details about

    the job to be carried out.7.  The supply of all the material required (including logistics, loading/unloading etc.) to

    execute the job as per SOW is in the scope of contractor.

    8.  The welder/welders deputed for the job shall be a qualified welder and requisite associated

    manpower shall be made available at the site so as to complete the job within stipulated

    time.

    9.  The procedure given for carrying out the repair shall be followed and as per the guidelines

    of ASME Sec IX and ASME Sec II Part C.

    10.  The type of repair like lap banding, fillet weld of patch, weld overlay and clad (inside the

    column) replacement have been provided above in the table but same is indicative only. If

    needed repair work in more area shall be performed in addition to above. And the

    contractor has to adopt the appropriate procedure to do all said repairing work accordingly.

    11.  Suitable NDT to be done after every root and final weld run. After completion of the

    repair, radiography shall be done by the contractor as per the instructions of Engineer-in-

    charge.

    12.  On completion of repair, two coats of high temperature & corrosion resistance

    paint shall be applied over the repaired surface as well as on whole surface of columns after

    properly cleaning and corrosion removing as per the standard procedure with minimum DFT

    after each coat 20 microns.

    13.  The scrap generated during the execution of the repair job will become the property of

    the contractor and shall be taken out of ONGC premises. Accordingly the bidder has to

    quote the price for the safe disposal and comply all statutory requirement.

    14.  All the jobs to be carried out shall be executed as per the instructions of Engineer-in-

    charge and within the given time period.

    15.  The columns shall be flushed and washed the whole column from inside properly by

    contractor followed by oxygen test before taking repair job either from inside or from

    outside of columns.

    16.  If needed the contractor has to remove nearly 7 trays, do the repair/replacement work

    inside the column and then refit same trays properly.

    17.  Bidder has to do hydro test of column at test pressure for leak test at 1.5 times of design

    pressure.

    18.  The contractor has to paint the railing, grating, ladder platform of the column with

    suitable paint as per procedure.

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    4/14

    124 | P a g e UP14C15018

    19.  Contractor has to arrange PPE (Personal Protective Equipments) like safety shoes, safety

    belts, helmets etc. for all his personals to be engaged during execution of job at site.

    20.  The contractor has to get gate pass for men and equipment himself. ONGC shall assist

    him. Providing all required documents and police verification shall be responsibility of

    contractor.21.  On accident if any for employees of contractor, ONGC shall not any responsibility for

    same and ONGC shall transport the victim up to ONGC plant occupational health center.

    Transportation of patient from ONGC premises to required hospital and treatment shall be

    responsibility of contractor.

    22.  Following procedures of repairing of damaged at different portion of columns can be

    adapted by bidder.  Replacing the section or component containing the defect for clad

    pad portion.

    1.  Damaged or eroded shell plates (reduced thickness) area may be repaired by

    removing a section and replacing the plate as per required thickness and

    material specification.

    2.  Full penetration groove weld to be provided.

    3.  The welds are radio graphically tested with applicable construction code.

    Ultrasonic examination by an industry qualified UT shear wave examiner. May

    be substituted by radiography if NOE procedure is approved.

    4.  All patch plates corners that do not extend to existing longitudinal or

    horizontal weld shall be rounded having a 1 in. (2Smm) minimum radius. Weld

    proximity to existing weld shall be reviewed by the engineer.

    Fillet weld patches:Following procedure should be used for fillet weld patches or weld build up:

    Fillet weld patches may be used to make temporary repairs to damaged,

    corroded or eroded areas of pressure vessel components. Temporary repairs

    using fillet welded patches shall be approved by an inspector and engineer.

    The use of fillet welded patches may be subject to the acceptance of the

    governing jurisdiction.

    Fillet welded patches require special design consideration specially related to

    weld joint efficiency, filler welded patches may be applied to internal or

    external surface of shell, heads and header provided that in the judgment of

    the engineer, either of the following is true:- The fillet welded patches provide design safetyequivalent to reinforced

    openings designed according to the applicable construction code.

    a.  The fillet welded patched are designed to absorb the membrane strains of

    the parts so that in accordance with the rules of the applicable

    construction code, the following result:

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    5/14

    125 | P a g e UP14C15018

    b.  The allowable membrane stress is not exceeded in the vessel part or

    patches.

    c.  The strain in the patches does not result in fillet weld stresses that

    exceed allowable stress for such welds.

    Lap band repairs:

    The band is designed to contain full vessel design pressure,

    All longitudinal seams in the repair band are full penetration butt weld with the

    design joint efficiency and inspection "consistent with the appropriate code,

    The circumferential fillet welds attaching the band to the vessel shall are

    designed to transfer the full longitudinal load in the vessel shell, using a joint

    efficiency of 0.45,

    Appropriate surface NDE shall be conducted on all attachment welds,

    The band material and weld material are suitable for contact with the

    contained fluid at the design conditions and an appropriate corrosion

    allowance is proved in the band.

    Welding procedure:

    Following process may be used to obtain the finish weld.

    Contractor shall establish suitable WPS & PQR as per mandatory

    requirement of ASME Sec. IX, Also applicability of suitable welding rod,

    electrode and filler metal as per ASME Sec, II part C.

    The process may be SMAW or GTAW.

    Consumables for GTAW as per ASME SFA 5.18- AWS ER 70S2, for SMAW

    as per ASME SFA 5,1 - AWS E7018.The lap band can be partially or fully pre-fabricated according to design given

    by designer in accordance with appropriate code.

    Safe installation procedure to adopt by contractor for welding of

    circumferential fillet weld between band and shell. Pre heating to 150 deg. Or

    higher to be maintained during welding.

    Weld overlay of corroded area (clad repair procedure)

    The SS clad has been removed by erosion. It needs weld overlay over CS plate to protect the

    same. Following procedure shall be used1.  Mark clearly the area that needed to be repaired,

    2.  Ensure proper qualified welder who is doing welding jobs

    3.  Welding electrode used for SS are ER309 electrode by GTAW OR SMAW process.

    4.  Proper size electrode to be used and continuous run to be made over CS surface as per

    required thickness of SS clad.

    5.  Current to be properly controlled as excess current may burn out the base metal.

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    6/14

    126 | P a g e UP14C15018

    6.  After complete welding of required thickness proper flushing (grinding) to be done

    smooth surface.

    7.  NDT as MPI or LPT to be done on ground surface for defects.

    Welding process:-Following process may be used to obtain the finish weld. Contractor shall

    establish suitable WPS & PQR as per mandatory requirements of ASME

    Sec. IX. Also contractor has to establish applicability of suitable welding rod.

    Electrode & filler wire as per ASME Sec. I! Part C.

    1. SMAW

    2. GTAWProcedure:-

    Surface cleaning: Care to be taken previously installed paint / insulation is

    properly cleaned. Method like chipping, grinding can be used to achieve surface

    preparation.

    Marking: Prior to cutting, all affected members (where surface thinning is

    observed) shall be properly marked with appropriate length. Cutting can be done

    by gas cutter or by any other suitable method. During cutting method should be

    such selected that during the process it should not lead to distortion of the

    structure or any increase in joints.

    Welding: Prior to welding edge preparation, bevelling shall be carried out using

    grinding machine for proper joint preparation. Only qualified welders shall be

    deployed for welding as per ASME Sec IX or equivalent. All weldings shall be in

    minimum 2 passes. Welding shall be followed by suitable NOT (RT, UT and MPI)

    etc. to ensure the quality of weld.Precaution for repair: All sharp, rough, broken edges and the edge of joints shall

    be cleared out so as to avoid defects and to install or fabricate equipment and

    defect free joints. Precaution for repair shall be taken into consideration that it

    does not alter the mechanical properties of the material.

    In the ONGC’s scope: 

    a.  Low tension power supply and connections shall only be provided by ONGC.

    b.  Water and air at 4-6 kg /cm2 pressure shall be provided by ONGC.

    c.  Any power supply up to the column bottom for grinders etc. however, long cable from

    bottom to top of column to be arranged by contractor.

    Special Terms & Conditions:

      Payment terms:

    No advance payment shall be made. 100%Payment shall be made on successfully

    completion of each column repair job as per Scope of Work and terms and conditions of the

    contract.

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    7/14

    127 | P a g e UP14C15018

    Bidder has to submit the bill/invoice in triplicate with all required documents in the name of

    DGM (F&A), ONGC, Uran and should get tracking number from our HR/ER Section. The bill

    after tracking no. shall be forwarded to concerned Engineer in charge by HR/ER for

    certification, verification, and final release. Payment shall be released within 21 days from

    the date of submission of bill to concerned Engineer-In-Charge.

      Completion Schedule: Contractor has to complete the job of repair of each column within

    20 days from the date of handing over the respective columns.

      Mobilization: Maximum 15 days shall be allowed for mobilization of men, equipment and

    machinery etc. from date of LOA.

      Contract period: Contract period for the jobs will be 18 Months from placement of LOI.

      Inspection: Inspection shall be carried out by ONGC representative/ TPI(arranged by ONGC)

    Guarantee/Warrantee: Contractor has to furnish a guarantee/warrantee for a period of one

    year from the date of completion of job. During the period if any defect is observed in the

    executed job, the same shall be rectified by the contractor at free of cost within a minimum

    possible time.

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    8/14

    128 | P a g e UP14C15018

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    9/14

    129 | P a g e UP14C15018

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    10/14

    130 | P a g e UP14C15018

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    11/14

    131 | P a g e UP14C15018

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    12/14

    132 | P a g e UP14C15018

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    13/14

    133 | P a g e UP14C15018

  • 8/19/2019 4.Annexure-III-scope of Work (Sow)

    14/14

    134 | P a g e UP14C15018