56 seiaa meeting (3.10.2012).pdf

91
Proceedings of the 56 th SEIAA meeting held on 3 rd October 2012 at Room No. 709, M.S Building, Bangalore. Members present: - 1. Dr. H.S. Ramesh - Chairman (SEIAA) 2. Dr. H.R. Raj Mohan - Member (SEIAA) 3. Sri Kanwerpal - Member Secretary (SEIAA) The Chairman welcomed the members and initiated the discussion. The following subjects were discussed and decisions were taken as there under. Deferred Projects: Construction Projects: 1. Construction of "Adarsh Capital", Star Hotel, No.56, Ward no.78, Palace Road, Bangalore by M/s Adarsh Developers (SEIAA 31 CON 2009) It is a proposal for construction of star Hotel of 429 Rooms and amenities like restaurants, business center, meeting rooms, office, retail shop, swimming pool, etc. with 3 Basement floor + Ground floor + 18 upper floors in an area of 8105.72 Sq.m and the total built up area is 59,205.51 Sq.m. The total water requirement is 420 KLD and the investment is of Rs.236 crores. The total parking provided is for 264 cars. The subject was placed in the 52 nd SEAC meeting held on 06.03.2010 and the proponent presented and explained the project. The proponent stated that initial CFE was obtained from KSPCB as the area of less than 20,000 Sq.mtr, the proponent has proposed to increase the built up area taking advantage of revised FAR. The proponent has also stated that construction activity has been stopped from one year for want of environmental clearance. The proponent was asked to submit the additional following information. 1. Realistic assessment of use of treated sewage water. 2. Specific social commitment plan. 3. Contour plan of site proposed for disposal of excess excavated soil 4. Assessment of the capacity of BWSSB sewer line if it is proposed to discharge surplus grey water into the sewer line. The Committee decided to recommend the proposal to SEIAA for environmental clearance after obtaining the above information. The subject was again placed in the 68 th SEAC meeting held on 30.04.2011 and the Committee noted that in spite of letter dated 11.03.2010, 21.04.2010 & 26.06.2010 followed by reminder dated 26.03.2011 requesting the proponent to submit the required information within 15 days failing which his file would be recommended for closure at his risk, the proponent has failed to submit the information. Hence, the Committee decided to recommend the proposal to SEIAA for closure as sufficient information was not available in the file. The subject was placed in the 41 st SEIAA meeting dated: 17.06.2011 and the Authority took note of the recommendation of the SEAC and decided to close the file and delist from the pendency with a direction to KSPCB to initiate action in accordance with the law if the project has been undertaken without prior Environmental Clearance. Accordingly the proponent was informed vide letter dated: 30.06.2011.

Upload: bhaskar-shanmugam

Post on 25-Oct-2015

132 views

Category:

Documents


2 download

DESCRIPTION

India

TRANSCRIPT

Page 1: 56 SEIAA Meeting (3.10.2012).pdf

Proceedings of the 56th SEIAA meeting held on 3rd October 2012 at Room No. 709, M.S Building, Bangalore.

Members present: -

1. Dr. H.S. Ramesh - Chairman (SEIAA) 2. Dr. H.R. Raj Mohan - Member (SEIAA) 3. Sri Kanwerpal - Member Secretary (SEIAA)

The Chairman welcomed the members and initiated the discussion. The following subjects were discussed and decisions were taken as there under.

Deferred Projects: Construction Projects:

1. Construction of "Adarsh Capital", Star Hotel, No.56, Ward no.78, Palace Road,

Bangalore by M/s Adarsh Developers (SEIAA 31 CON 2009)

It is a proposal for construction of star Hotel of 429 Rooms and amenities like restaurants, business center, meeting rooms, office, retail shop, swimming pool, etc. with 3 Basement floor + Ground floor + 18 upper floors in an area of 8105.72 Sq.m and the total built up area is 59,205.51 Sq.m. The total water requirement is 420 KLD and the investment is of Rs.236 crores. The total parking provided is for 264 cars.

The subject was placed in the 52nd SEAC meeting held on 06.03.2010 and the proponent presented and explained the project. The proponent stated that initial CFE was obtained from KSPCB as the area of less than 20,000 Sq.mtr, the proponent has proposed to increase the built up area taking advantage of revised FAR. The proponent has also stated that construction activity has been stopped from one year for want of environmental clearance.

The proponent was asked to submit the additional following information. 1. Realistic assessment of use of treated sewage water. 2. Specific social commitment plan. 3. Contour plan of site proposed for disposal of excess excavated soil 4. Assessment of the capacity of BWSSB sewer line if it is proposed to discharge surplus grey

water into the sewer line.

The Committee decided to recommend the proposal to SEIAA for environmental clearance after obtaining the above information.

The subject was again placed in the 68th SEAC meeting held on 30.04.2011 and the Committee noted that in spite of letter dated 11.03.2010, 21.04.2010 & 26.06.2010 followed by reminder dated 26.03.2011 requesting the proponent to submit the required information within 15 days failing which his file would be recommended for closure at his risk, the proponent has failed to submit the information. Hence, the Committee decided to recommend the proposal to SEIAA for closure as sufficient information was not available in the file.

The subject was placed in the 41st SEIAA meeting dated: 17.06.2011 and the Authority

took note of the recommendation of the SEAC and decided to close the file and delist from the pendency with a direction to KSPCB to initiate action in accordance with the law if the project has been undertaken without prior Environmental Clearance. Accordingly the proponent was informed vide letter dated: 30.06.2011.

Page 2: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

2

 

However, the proponent on 18.07.2011 submitted the information called vide letter dated: 21.04.2010 based on 52nd SEAC meeting wherein the proposal was recommended. The file is again taken up for appraisal as per the directions of the Member Secretary, SEIAA on file for reopening and making suitable recommendation.

It was informed that the proponent has expressed his inability to attend the SEAC meeting

vide letter dated: 15.09.2011. The Committee in the SEAC meeting held on 16.09.2011 observed that the proponent has submitted the information on 18.07.2011 with reference to this office letter dated: 21.04.2010 as per the 52nd SEAC meeting proceedings and was surprised how the proponent did not receive the various letters sent to him by SEAC asking for information. However, the Committee after studying the information provided by the proponent decided to reiterate the earlier decision taken in the 52nd SEAC meeting dated: 06.03.2010 and recommend to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC

during the meeting held on 05.11.2011. After discussion, the Authority decided to get the following information from the

proponent for further consideration of the proposal.

a) Present construction status of the project with latest dated photographs.

b) Status of UGD and plan for disposal of treated water with justification.

c) Quantum of debris and plan for its safe disposal with particulars of site proposed to be used for such disposal.

d) Copy of the CFE issued by the KSPCB and approved plan for undertaking construction.

e) Revised specific social commitment plan with time frame and budget

The Authority also decided to invite the proponent to the Authority meeting with all the relevant information.

The proponent has submitted the information vide letter dated 24.08.2012. The proponent was invited to the Authority meeting.

The Authority perused the information furnished by the proponent. Sri P. Krishnamurthy appeared before the Authority on behalf of the proponent with letter of authorization dated 28th September 2012.

The Authority noted that it is a proposal of 2009 and inordinately delayed by the proponent in furnishing the information sought by the Authority.

While replying to the query raised by the Authority, that whether the proponent is serious in pursuing the proposal, the representative for the company informed that due to certain financial problem and the market scenario they had stopped the work. Since there is an improvement in the market scenario and the client have showed interest they are now seriously pursuing the matter.

Page 3: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

3

 

The proponent in response to the query with regard to the availability of UGD facility and plan for disposal of excess treated water replied that the project site is amidst a developed area and the existing sewer lines are sufficient to accommodate the excess treated water. The proponent further informed that since it is a commercial development they proposed to use maximum treated water for the HVAC apart from other non-potable uses such as flushing, gardening, washing, etc. Therefore practically the proposed unit will be a zero discharge unit.

The Authority noted that the construction has been undertaken with the approval of BBMP as per the plan approved on 06.05.2006 that is prior to the inception of EIA Notification, 2006 for a total FAR area of 11,856.92 Sqm. and the present construction has three basements. The proponent while replying about the disposal of the excavated earth informed that it has been fully utilized within the project site for formation of roads and other landfilling.

The Authority further noted that the proponent have obtained consent for establishment from the Karnataka State Pollution Control Board on 02.08.2007 for a total built up area of 30,728.72 Sqm and now the proposal is for a total built up area of 59,205.51 Sqm.

The Authority opined that the project has been taken up piecewise.

In response to the proposed activity, the proponent clarified that the proposed structure having three basements and 17 upper floors. The basement will be used for parking, the first three floors will have public area such as board room, restaurant, conference room etc. Forth floor will be service area and the upper floors will be used for the hotel purpose.

The Authority noted that the road abutting the project site has a width of 15.40 meters. While the minimum requirement of RoW for the proposed building of 51 meters height is 24 m. Therefore the Authority sought to know whether the proposed construction meets the RoW criteria specified in the O.M. No. 21-270/2008- IA.III dated 7th February 2012.

The Authority further sought to know whether the existing building structurally support the proposed high rise building. The proponent in response submitted that initially the structural design was made taking into account future expansions in accordance with the BBMP by laws.

The Authority while perusing the report of traffic study observed that both on Palace Road and Cunningham road the modified LOS is shown as D. The proponent submitted that the Palace Road is relatively having lesser traffic density. The Authority opined that since the study reveals that it is par with Cunningham Road which is a busy road, the reports requires revisit.

The Authority after discussion, decided to get the following information for further consideration:

(a) Clarification as to whether the proposed construction is in compliance with the O.M. No. 21-270/2008- IA.III dated 7th February 2012 issued by the Ministry of Environment and Forests, Government of India with regard to requirement of RoW in relation to the height of the building.

(b) Structural design details of old proposal building and also new proposal building

(c) Report on Safe bearing capacity (SBC) of soil with all other engineering properties of soil.

Page 4: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

4

 

(d) Revised traffic survey and analysis report.

(e) Revision of parking facility calculated as per the MoEF / BBMP norms and keeping in view the NBC Code.

(f) Traffic study on the Palace Road keeping the incremental density due to the proposed activity.

(g) Landscape details duly marking on the layout plan.

(h) Modified layout plan with drive way of minimum 8 meters instead of 6 meters as proposed.

The Authority also decided to invite the proponent to the meeting after the submission of above information.

2. Residential Apartment Project at Sy.no.13, Khatha no.1307/1143/6/1/398/13, Talacauvery Layout, Amruthahalli village, Bangalore North Taluk, Bangalore by M/s. SVS Infrastructures (SEIAA 111 CON 2012)

It is a proposal for construction of Residential Apartment of 312 flats with Basement + Ground floor + 06 upper floors on an area of 16,205.42 Sq.m, and with the total built up area of 53,717.70 Sq.m. The total water requirement is 287 KLD and the investment is of Rs. 47.18 crores. The total parking provided is for 388 cars.

M/s. SVS Infrastructures have applied for Environmental Clearance (EC) from SEIAA for their new proposed Residential Apartment project at Survey Nos. 13, Khatha no.1307/1143/6/1/398/13, Talacauvery Layout, Amruthahalli village, Bangalore North Taluk, Bangalore, under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 47.18 Crores. Project comes under –BBMP limits;

Project Details: Land: Total plot area: 16,205.42 Sqm; Total built up area: 53,717.70 Sqm.

The Project comprises of 2 Blocks (A Block & B Block) with Basement Floor + Ground Floor & 6 Upper Floors. Landscape area: 7315 Sqm (45.13% of plot area). Water Requirement: Total water requirement is 219.12 KLD; Fresh water requirement: 151.58 KLD, sourced from BWSSB. Excavated Earth: Total Quantity of excavated earth: 45,589 Cum; backfilling quantity: 10,363 cum will be used for backfilling between foundations; 19,336 cum will be for back filling on backside of retaining walls, UG sumps, tanks etc, 7,090 cum for leveling the low lying areas; landscaping quantity: 5800 Cum; Sewage: Total quantity generated: 176 KLD, treated in proposed STP of design capacity 200 KLD; Sludge generated: - 8 kg/day used as manure. Municipal Solid Waste: Total generated: 390 kg/day; Organic waste: 255 kg/day treated in organic convertor and product used as manure. Inorganic waste: 140kg/day will be sent for recycling. Power: Total Requirement: 1.70 MVA from BESCOM; Backup Power: DG sets of 2X200 KVA; Parking: 388 Numbers.

Project surrounding details: Bannerughatta National Park – 35 km, Rachenahalli Kere – 2.25km, Nagawara Kere – 2.50km, Jakkur Kere – 2.10 km, Hebbal Kere – 2.50 km.Other details: Rain Water Harvesting is proposed.

Page 5: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

5

 

The subject was discussed in the SEAC meeting held on 21st July 2012. The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 20.85 m and the nearest fire station is 4.2 km away from the project site.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent.

1. NOC from BWS&SB for water supply. 2. Peak hour traffic photographs with date and time. 3. Details of public road adjacent to the project site with sketch. 4. Social commitment plan on letterhead for Rs. 5 Lakhs, as committed by the

proponent during the meeting. The proponent has submitted information vide letter dated 10.07.2012.

The Authority perused the information submitted by the proponent and took note of the recommendation of the SEAC during the meeting held on 03.09.2012.

The Authority noted that a complaint dated 17.09.2011 was received in the Authority from Sri Bharat Kumar with regard to starting of construction without obtaining the Environmental Clearance. Pursuant to this complaint a D.O. letter dated 30.09.2011 has been addressed to the Member Secretary, Karnataka State Pollution Control Board to get the spot inspection and initiate action against the proponent in accordance with the Environment (Protection) Act, 1986 if the activity has been undertaken without the required clearance. The proposal was forwarded to the SEAC for appraisal taking into account the allegation made with regard to starting of construction without prior Environmental Clearance. The Authority noted that confirmation or ruling out the allegation made is not forthcoming from the proceedings of the SEAC. The Authority after discussion, decided to get the following information for further consideration:

(a) Present status of construction along with the latest dated photographs. (b) Reasons for starting of construction activity if taken up without prior Environmental

Clearance. (c) Resolution of the Board of Directors as required under the Official Memorandum No.J-

11013/41/2006-IA.II(I) dated 16th November 2010 issued by Ministry of Environment and Forests, Government of India in case construction activity is taken up.

(d) Plan for development of greenery. The Authority also decided to invite the proponent to the meeting.

The proponent has submitted the information vide letter dated 24.08.2012. The proponent was invited to the Authority meeting.

The Authority perused the information furnished by the proponent. The proponent appeared before the Authority and briefly explained about the proposed project.

The Authority while going through the photographs submitted noted that the proponent have started construction activity. The proponent informed that this is the first project with total

Page 6: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

6

 

built up area of more than 20,000 Sqm and therefore were not aware about the statutory provision and the consultant also did not properly advised them. The proponent further submitted that application was submitted for the required Environmental Clearance as per their letter dated 21st April 2012 and the construction activity was started as monsoon was approaching. The Authority noted that even though the application bears the date as 21.04.2012 it has been received in the Authority on 04.06.2012. The Authority noted that the proponent have confirmed the commencement of construction activity without the prior Environmental Clearance and have resolved in the Board of Directors meeting held on 27th August 2012 that in future they will not undertake any construction activity without Environmental Clearance wherever required.

The Authority after discussion, opined that ignorance of law is no excuse and therefore technically the activity constitutes violation of the provisions of the EIA Notification, 2006 and therefore the proponent deserves to be proceeded with in accordance with the law. The Authority therefore decided to recommend to the State Government for initiating required legal action for the violation through the Karnataka State Pollution Control Board under the relevant provisions of Environment (Protection) Act, 1986.

The Authority further decided to issue Environmental Clearance along with the condition that “This environmental clearance is issued without any prejudice to the legal cases if any, which may arise on account of violation” in pursuance of the direction of MoEF vide letter No.J-11013/8/2009-IA-II(I) dated 06.04.2009 and also subject to submission of the following information:

(a) Location of STP and facility for municipal solid waste management duly marking on the layout plan.

(b) Copy of the approved plan / conceptual plan.

(c) Letter of commitment admitting the fact that the construction has been undertaken along with reasons thereof.

3. Residential Complex consisting residential units, villas and Club house at Sy. Nos. 65(P), 66/4, 66/2(B), 66/2(C), 66/5, 67/4, 67/5, 67/6, 67/7 68/4, 68/5, 69/4, 69/7, 69/8, 70/5, 70/6, 70/1B, 70/7, 70/8(P) Kodigehalli Extension, Municipal Ward No.15, Byatarayanapura, Bangalore North Taluk, Bangalore by M/s Antevorta Developers Pvt. Ltd. (SEIAA 50 CON 2012)

It is a proposal for construction of Residential Apartment of 545 Units with 3 Basement floors + Stilt + 18 Upper Floors, 1 Club House and a Sports Court on an area of 40,470 Sq.m and the total built up area is 1,47,082.66 Sq.m. The total water requirement is 405 KLD and the investment is of Rs. 625.29 crores. The total parking provided is for 1441 cars.

M/s. Antevorta Developers Pvt. Ltd., have applied for Environmental Clearance (EC) from SEIAA for their new proposed “residential Complex” Project at Sy. No. 65(P), 66/4, 66/2(B), 66/2(C), 66/5, 67/4, 67/5, 67/6, 67/7, 68/4, 68/5, 69/4, 69/7, 69/8, 70/5, 70/6, 70/1B, 70/7, 70/8(P), Kodigehalli Extension Ward No. 15, Byatarayanapura, City Municipal Coun Bangalore North Taluk Bangalore under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total

Page 7: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

7

 

project cost is Rs. 625.69 Crores. Project comes under BBMP Limits; Land conversion obtained from DC. The site is a vacant land.

Project Details: Land: Total Land area: 40,470 Sqm; Total built up area: 1,32,623.93 Sqm. Project consists of 540 Units, with Stilt + 39 Upper Floors and 10 Villas & Club House Landscape area: 17066.78 Sqm (42.15 % of plot area). Water Requirement: Total water requirement is 260 KLD; sourced from BWSSB. Excavated Earth: Total Quantity of excavated earth: 2,15,058 Cum; backfilling quantity: 20,240.8 Cum; landscaping quantity: 1,25,496 Cum; Balance quantity will be disposed to an alternate site. Sewage: Total quantity generated: 312 KLD treated in proposed STP of design capacity 315 KLD based on SBR Technologies; Sludge generated: 16.0 kg/day used as manure. Municipal Solid Waste: Total generated: 1360 kg/day; Organic waste: 545 Kg/day treated in organic convertor and product used as manure. Inorganic waste 815 kg/day will be sent for recycling. Power: Total Requirement: 6045 KVA from BESCOM; Backup Power: DG sets of 4 X 750 KVA, 1 X 500 KVA, 1X 380 KVA & 1 X250 KVA.

Project surrounding details: Bannerghatta National Park – 40 km. Kodigehalli Lake – 500

m, Hebbal Lake – 1 km, Doddabommasandra Lake-1.5 km. Amruthahalli Lake – 3 kms. Nagavara Lake – 4 Kms. BIAL: 25.7 Kms. Other details: Rain Water Harvesting is proposed.

The subject was placed in the 82nd SEAC meeting held on 27/28.04.2011 and the subject

was deferred since the circulation material was not received by members and also the proponent vide letter dated: 19.04.2012 has informed his inability to attend the meeting due to personal reasons.

The subject was placed in the 83rd SEAC meeting held on 25/26.05.2012 and the proponent and the consultant present in the meeting explained the project. The proponent informed that the height of the proposed building is 87.9 m and the RoW of the existing road in front of the project site is 24 m; the nearest Fire Station is at a distance of 3.1 km.

The Committee noted that the project does not comply with the provisions of the O.M dated 07.02.2012 regarding high rise buildings and decided to give 30 days’ time to the project proponent to submit revised proposal (if he is willing, otherwise the proposal may be recommended to SEIAA for closure).

The proponent has submitted the revised proposal on 12.07.2012. The salient features of the revised proposal are as follows:

Project Details: Land: Total Land area: 40,470 Sqm; Total built up area: 1,47,082.66Sqm. Project consists of 545 Residential Units (with 3 Basements +Stilt + 18Upper Floors) Club House & Sports Court. Landscape area: 21,105.93 Sqm (52.15 % of plot area). Water Requirement: Total water requirement is 405 KLD (Fresh water: 276 & balance 129 KLD will be sourced from the Sewage Treatment Plant); sourced from BWSSB. Excavated Earth: Total Quantity of excavated earth: 2,15,058 Cum; backfilling quantity: 20,240.8 Cum; landscaping quantity: 1,25,496 Cum; Balance quantity will be disposed to an alternate site at Devanahalli. Sewage: Total quantity generated: 310 KLD treated in proposed STP of design capacity 310 KLD adopting Sequencing Batch Reactor Process; Sludge generated: 15.5kg/day used as manure. Municipal Solid Waste: Total generated: 1350 kg/day; Organic waste: 540 Kg/day treated in organic convertor and product used as manure. Inorganic waste 810 kg/day will be sent for

Page 8: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

8

 

recycling. Power: Total Requirement: 6170 KVA from BESCOM; Backup Power: DG sets of 2 X 750 KVA & 4X625 KVA. The total project cost is 625.69 Crores.

The subject was discussed in the SEAC meeting held on 20th & 21st July 2012. The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 59.9 m and the RoW of the existing road in front of the project site is 24 m. The nearest fire station is 4 km away from the project site. The proponent informed that the drainage is covered with concrete slab. NOC from BWS&SB obtained and submitted. The proponent informed that the RoW in front of the project site is 24 m whereas it is shown as 12 m in CDP.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent.

1. Document showing the RoW in front of the project site as 24 m from BBMP. 2. Disposal of excess treated water during rainy season (revised water balance) 3. Land details of disposal site of excess excavated earth. 4. Social commitment plan on letterhead for Rs. 62.5 Lakhs, as committed by the

proponent during the meeting.

The proponent has submitted information vide letter dated 09.08.2012. The Authority perused the information submitted by the proponent and took note of the

recommendation of the SEAC during the meeting held on 03.09.2012. The Authority noted that it is proposed to build three basements, wherein safety, proper

ventilation, disposal of excavated earth, etc are the aspects to be addressed. The Authority also noted that proper source of water supply is not established. It is proposed to be sourced water from BWS&SB and NOC in this regard has not been furnished.

The Authority after discussion, decided to get the following information for further consideration:

(a) Safety plan proposed for excavation work as the project activity involves excavation for three basements and ventilation plan during operation phase.

(b) Details of structures in the proximity of the proposed project site. (c) Details of excavated earth and plan for safe disposal of excess earth along with land records

and present land use of the site proposed to dispose the excess earth. (d) NOC from the BWS&SB. (e) Details of parking proposed along with the relevant norms such as MoEF/BBMP/BHK with

calculation. (f) Details of kharab land with present land use, duly marking it on the layout plan. (g) Details of area proposed for establishment of STP and facility for management of solid

waste duly marking it on the layout plan. (h) Plan to ensure that the nearest water bodies are not polluted due to project activities.

The Authority also decided to invite the proponent to the meeting. The proponent has submitted the information vide letter dated 28.09.2012. The proponent was invited to the meeting.

Page 9: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

9

 

The Authority perused the information furnished by the proponent. The proponent appeared before the Authority and briefly explained about the proposed project. The proponent while responding with regard to safety of structures with the vicinity while excavating for three basements submitted that the adjacent plots are also vacant and therefore there are no structures that get affected due to excavation. The proponent further submitted that all the safety measures will be put in place during the excavation to avoid any untoward incidents. The proponent while responding with regard to safe disposal of excess excavated earth submitted that a total quantity of 2,23,694.5 Cum of soil is expected of which 16,884.8 Cum of top soil will be retained for the backfilling and landscape area and the balance of 185756 Cum will be used for leveling of vacant land of their own at land bearing Khata. No.144 situated at Sanneamanikere Village, Kasaba Hobli, Devenahalli Taluk proposed to be developed for villas. While responding to the query on kharab land, the proponent submitted that 4 Gunta of kharab land is a seasonal nallah and it will be maintained without any disturbance in the hydrology. The proponent further submitted that 15 meters of buffer zone also will be maintained without any development along the nallah as per BDA norms. With regard to compliance to the O.M. dated 07.02.2012 issued by the Ministry of Environment and Forests, Government of India on RoW, the proponent submitted that the maximum height of the building will be 59.9 meters. It complies with the RoW criteria as the abutting road has a width of 24 meters. The Authority while going through the layout plan apprehended that the solid waste management facility is located in a corner and therefore would create inconvenience to the neighbourhood. The proponent clarified that required arrangement will be made for planting of 2 to 3 rows of tall trees of aromatic species in order to avoid any smell nuisance and dust problem to the neighbourhood. The proponent submitted a modified layout plan accordingly. The Authority after discussion decided to issue Environmental Clearance subject to submission of the following information:

(a) Authentic document on RoW. (b) Relocation of D G Sets clearly indicating on the conceptual plan. (c) Commitment with regard to planting of trees all through the boundary line of project site in

addition to development of greenery in the front and at the back of the proposed development.

(d) Commitment with regard to development of greenery around the solid waste management facility with 2 to 3 rows of tall aromatic tree species.

(e) Safety aspects proposed in the swimming pool and kids pool. (f) Revised social commitment plan with budget, activity and time frame.

Industry Projects:

1. Establishment of Coke Oven Project (2 X 1,20,000 MTPA) and coke oven off gases based Captive Power Plant (2 X 9 MW), Ginigera Village, Koppal Taluk and District of M/s. Kalyani Steels Limited (SEIAA 14 IND 2009)

Page 10: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

10

 

It is a project proposal for Establishment of coke oven plant of capacity 2,40,000 TPA and Waste heat power plant of 2 X 9 MW. The total plot area is 52 acres 11 guntas. The total water requirement is 3473 Cum per day. The investment is of Rs. 148.71 Crores

The subject was placed in the 37th SEAC meeting held on 20.06.2009 and the proponent has presented and explained about the project. The Committee has decided to categories this project as “B1” and to issue the following ToRs in addition to the standard ToRs:

1. Impact of transportation of Coal. 2. Details of green belt area with type and no. of tree species proposed. 3. Comprehensive health report of people in the surrounding villages. 4. Source and transportation of water.

ToRs issued on 17.06.2009 for the preparation of EIA report. The proponent has submitted the EIA report along with the public consultation on 2.12.2010 & 12.05.2011.

The subject was placed in the 70th SEAC meeting held on 17th & 18th June 2011 and the subject was deferred as the members informed that the appraisal material from the project proponent has not been received. The same was informed to the project proponent present.

The proponent and environmental consultant present explained EIA during the SEAC meeting held on 07.07.2011. The proponent informed the following points before the Committee. 52 acres additional land is required for the project and it is allotted by the KIADB. The proposed site is adjacent to the existing plant. T.B. reservoir is 6.0 Kms upstream of the project site. Nearest habitation is Ginigera which is around 1 Km away. Coal is imported from Australia having 25% ash content. Coal is stored in an open space with concrete flooring. Coal is transported through rail route.

The Committee advised the proponent to install continuous ambient air quality monitoring station and adopt the green technology for the project. The Committee advised the proponent to provide ambulance facility to the villagers and also to plant trees in the landscape area to mitigate pollution.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the details of number of tree species proposed to be planted from the proponent.

The proponent had submitted the information vide letter dated 31.07.2011.

The Authority perused the information submitted by the proponent and took note of the recommendation of the SEAC during the meeting held on 26.08.2011.

The Authority desired to know the cumulative impact of the existing industry and the proposed industry on the environment and the action taken for safe disposal of fly ash. After discussion, the Authority decided to get the following information:

(a) Details of industries within the radius of 10 Kms from the project site and the cumulative impact including the proposed activity on the environment in terms of air pollution, water pollution, impact on road infrastructure and socio economic aspects.

Page 11: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

11

 

(b) Compliance on the suggestions of the public hearing held for the existing industry and the proposed activity.

(c) Compliance on the EC/CFO of the existing industry. (d) Proposal for safe disposal of fly ash in accordance with Fly Ash Notification, S.O. 763

(E) dated 14.09.1999 and amendments thereon.

The Authority also decided to invite the proponent to the Authority meeting to provide further clarification, if any.

The proponent has submitted the information vide letter dated 27.06.2012. The proponent has been invited to the meeting.

The Authority perused the information furnished by the proponent during the meeting held on 6th August 2012. The proponent remained absent. The Authority noted that information sought vide Authority letter dated 05.09.2011 has been submitted on 26.06.2012, after lapse of almost 10 months. The information furnished does not reveal the detailed compliance on the EC / CFO issued for the existing unit. It is observed from the information that the development of greenbelt is very poor.

The Authority after discussion, decided to provide one more opportunity to the proponent to appear before the Authority and furnish information / clarification on the project. The Authority decided to defer the subject to the next meeting and to invite the proponent.

The proponent was invited to the Authority meeting held on 03.09.2012.

The proponent vide letter dated 30.08.2012 have informed that the senior management team of the company is travelling abroad on company business and therefore unable to attend the scheduled meeting.

The Authority in the meeting held on 03.09.2012, noted that the proponent have not shown interest either in submitting the information sought or in attending the Authority meeting to furnish the required information. It was further noted that the information sought vide letter dated 05.09.2011 was submitted vide letter dated 26th June 2012 after a lapse of almost 10 months. Subsequently, the proponent has failed to attend the Authority meeting held on 6th August 2012 also.

The Authority after discussion decided to provide a last opportunity and invite him for the next meeting of the Authority. The Authority also decided to get a report from the Karnataka State Pollution Control Board with regard to whether the activity has been undertaken without the required Environmental Clearance or otherwise.

The proponent was invited to the Authority meeting.

The Authority perused the information furnished by the proponent. The proponent appeared before the Authority and briefly explained about the proposed project.

The Authority observed that the proponent has not shown interest both in submitting the information sought and in attending the meeting for furnishing the additional information. The Authority further noted that the proponent have taken 10 months time for submitting the information sought and did not attend the last two meetings inspite of intimation. The Authority sought to know whether the proponent is keen at taking the project.

The proponent admitted that there has been delay from their side. The proponent further added that due to non-availability of ore only one of the three existing gas blast furnaces is

Page 12: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

12

 

working. Therefore the company is going slow on the expansion issue. Now that the mining activity is getting resumed in the district of Bellary, Chitradurga and Tumkur in lieu of the recent Supreme Court order, the situation of supply of ore will be improved. With this background now the company is keen to undertake the proposed activity.

While responding to compliance on the latest CFO issued by the Karnataka State Pollution Control Board, the proponent submitted that the CFO has been issued in month of July 2012 for the existing unit and the compliance on the same will be submitted soon.

While going through the details of development of greenbelt the Authority opined that the pictures shown depicts very poor tree growth. A minimum of 1/3rd of the area has to be developed as greenbelt with thick foliage, indigenous and tall tree species.

While explaining the proposed activity, the proponent submitted that it is proposed to establish a coke oven plant of 2 X 1,20,000 TPA and coke oven off gas based captive power plant of 2 X 9 MW. The proponent further submitted that 1.35 Tons of coal will yield one ton of coke. Therefore a total quantity of about 3,24,000 Tons of coal will be handled every year.

While responding on the source of coal, the proponent informed that the coal will be imported from Australia. The Authority sought to know chemical composition of the raw material, chemical composition of the final product (coke), chemical composition of volatile organic matter expected to generate during charging of coal.

The proponent while explaining the process informed that the combustion takes place in the presence of air. The Authority observed that the documents reveal that it is through Pyrolysis. The proponent clarified that they have employed non-recovery type of coke oven plant wherein the volatile gases that are generated get burnt at high temperature with sufficient excess air. The Authority sought to know the composition of volatile gases that get generated while charging the coal. The Authority apprehended that the volatile gases include Benzene, Toluene, Phenols, Ammonia, etc. Therefore details of flue gas having NOx, SOx, NH3, VOC, particulate matter, etc. are required to assess the impact on the environment.

The Authority also apprehended that the solid waste will include the hazardous waste also, therefore requires plan for safe disposal.

The proponent informed that the technical details will be submitted as they do not have on hand.

The Authority after discussion decided to get the following information to be submitted within 30 days for further consideration:

(a) Process flow chart for coke making. (b) Technical options of process change for the reduction of pollutants. (c) Mitigation plan for each parameter in the form of matrices. (d) Chemical composition of the raw material (coal), chemical composition of the final

product (coke), chemical composition of volatile organic matter expected to generate during charging of coal.

(e) Details of material balance and quantum of emissions with composition. (f) Management plan for mitigating the impact of Volatile Organic Compound.

Page 13: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

13

 

(g) Details of habitation within 5 Kms radius with distance from each habitation with population duly marked on the map.

(h) Details of solid waste generated and plan for safe disposal including details of hazardous waste.

(i) Details of coal handling facility, storage facility and measures adopted to prevent pollution due to leachate from the coal stock.

(j) Expected environmental impact and the proposed mitigatory measures step wise in the raw material handling, process, storage and transportation of coke.

(k) Details of waste water generated, treatment and disposal of treated water.

The Authority also decided to invite the proponent after submission of the required information.

Mining Project:

1. "Grey Granite Quarry" (QL No. 414), Sy.No.401/1, Mudgal village, Lingasugur Taluk, Raichur District by Sri Rekhappa L. Rathod (SEIAA 8 MIN 2012)

It is a project proposal for Grey Granite Quarrying with the production of 2000 cubic mtrs / annum. Total land area 0.81 Ha in Private Patta land. The investment of Rs. 100 lakhs.

      

Sri. Rekhappa L. Rathod has applied for EC from SEIAA for their proposed Expansion of Quarrying with production of Grey Granite at 2000 cum/year at quarry lease No. 414 at Sy. No. 401/1 of Mudgal Village, Lingasugur Taluk, Raichur District over an area of 2.00 Acres of Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Man Power: 20; Proposed Method of Quarrying/: Open Cast Semi- Mechanized with optima wire saw for cutting of granite block (replacing the conventional method to avoid blasting). The drilling is by small dia. jack hammer dust proof drills. Mineable reserves: 55,000cum. The total project cost: Rs. 100 Lakhs. The proponent has submitted Quarry License No. 414/2000 granted with effect from 23.01.2001 for a period of 10 years by DMG and environmental management plan prepared by the accredited consultant.

Project Details: (a) Land: The Quarry Lease area is Patta Land. Land Use pattern: Quarry– 0.25 Ha; Waste Dumps- 0.063 Acres; Roads – 0.25 Acres; infrastructure – 0.021 Acres; mineral stockyard – 0.123 Acres; Green Belt 0.02 Acres; (b) Water: Total Requirement: 5 KLD is sourced from bore well for domestic, sprinkling for dust suppression and afforestation. (c) Over Burden: total Quantity: 10,000 cum in 5 years plan period. Project Surrounding Details: Jakkar-Madu Village: 1.10 km;

The subject was discussed in the SEAC meeting held on 07.07.2012. The proponent and environmental consultant present explained the project. The proponent informed that the lease area is situated in private land and no sensitive area like water bodies, wildlife sanctuaries, national parks, monuments and interstate boundaries exist within 10 km from the study area. The proponent informed that quarry lease renewal application is submitted to DMG on 28.09.2010 and NA from Revenue Department for grand of renewal of lease dated 13.01.2009. The proponent submitted the approved quarrying plan dated 07.07.2012 from DMG.

The proponent requested for B2 category for the following justification:

Page 14: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

14

 

1. The proposed quarrying is a small scale open cast quarrying without deep hole drilling and blasting with very less over burden. The granite production is only 2000 cum/year.

2. Mitigation measures such as dust proof drilling units and wire saw cutting to avoid blasting are proposed.

3. There is no crushing or screening and total handling of granite block and waste/defective blocks is very minimal.

The Committee discussed the above points in detail and decided to categorize the project under B2 category in view of the minimal environmental impact. After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC during the meeting held on 6th August 2012.

The Authority after discussion, decided to get the following information for further consideration.

(a) Details of yearwise production and removal of granite in the past. (b) Details of remaining resource and methodology adapted for estimation with details of

estimation. (c) Feasibility of quarrying in 0.8 Ha of land. (d) Type of machinery to be used / deployed for production of granite block. (e) Plan for safe disposal of waste. (f) Profile of labourers engaged, their medical health check up reports (g) Measures adapted for health and safety of workers.

The proponent has furnished information vide letter dated 24.08.2012. The Authority perused the information furnished by the proponent during the meeting held on 03.09.2012. The Authority noted that as per the IBM guidelines a minimum of 7.5 meters safety area has to be left from the boundary of the lease area. Mining/ quarrying has to be undertaken with benches of 3 meters with 45 degree slope. Following this criteria mining / quarrying can be undertaken only for 3 to 4 benches. A minimum of 30 meters at bottom of the mine pit has to be maintained. Therefore, mining / quarrying in smaller extent does not appear to be technically feasible. Added to this, the area is also to be reserved for storing mineral blocks, storage of waste material and area is also needed for development of greenbelt. Thereby taking all these parameters, no environmentally sustainable quarrying can be achieved in less than one hectare of area. The Authority after discussion, decided to direct the proponent to increase the lease area and to furnish the revised land use plan for taking environmentally sustainable quarrying.

Subsequently the proponent has submitted the details of additional land available vide letter dated 14.09.2012. The Authority perused the information furnished by the proponent and noted that additional two Acres of patta land of the proponent is available adjacent to the proposed leased land. The Authority further noted that the said land also has been converted for quarry purpose. This land

Page 15: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

15

 

can be utilized for auxiliary activities such as storing of minerals, waste dumping, green belt development, etc. The Authority noted that the total extent of the proposed quarrying activity will now stands revised to 4 Acres.

The Authority after discussion and taking note of the resources available have decided to issue Environmental Clearance for extraction of 1,600 Cum per Annum of grey granite subject to submission of the following information:

(a) Revised quarry plan for the entire area of 4 Acre, prepared by a qualified person recognized by the Indian Bureau of Mines.

(b) Order of the conversion of land from agriculture to non-agriculture purpose issued by the Deputy Commissioner.

(c) Commitment that 7.5 meters of safety zone is maintained / will be maintained from the lease boundary.

(d) Reclamation and Rehabilitation Plan including progressive and final mine closure plan. (e) List of workers engaged with their health checkup report.

2. Pink Granite Quarrying at Sy.no.12/7, Purtigeri village, Kustagi Taluk, Koppal District by Sri Mallikarjun V Shettar (SEIAA 77 MIN 2012)

It is a project proposal for Pink Granite Quarrying with the production of 4,000 cum/year. Total land area is 1.20 Acres in Private Patta land. The investment of Rs. 100 lakhs.

Sri. Mallikarjuna V. Shettar has applied for EC from SEIAA for their proposed New of Quarry of Pink Granite of 4,000 cum/year production at Quarry Lease No. Applied at Sy.No. 12/7, Purtigeri of Kustagi Village, Koppal Taluk and District over an area of 1.20 Acres of Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying: Open Cast Semi-mechanized with small scale drilling by jack hammer and cutting by optima wire saw. Man Power: 35; Total project cost: Rs. 100 Lakhs. The project lease area is connected to Purtigeri – Hulageri PWD road 1.5 km away. Geological Resources: 31,000 Cum; Mineable reserve: 41312 Cum.

The Project Proponent has submitted Quarrying Plan approved by Mines & Geology Dept

on 07.07.2012, Land documents (RTC), Notification for grant of lease dated 22.02.2012 issued by C&I Dept for a period of 10 years, Survey of India Topo-sheet, Pre-feasibility Report and EMP. Land NA conversion obtained from DC on 03.01.2012.

Land-use pattern: Mining –0.5 Acres; Infrastructure: 0.001 Ha; Waste Dumps- 0.2 Acres; Roads – 0.05 Ha; green belt 0.1 Ha; Mineral storage: 0.1 Ha; Undisturbed Area: 0.549 Ha. Water: Total Requirement: 5 KLD sourced from water tankers. Over Burden (OB): Total Quantity: 88500 TPA at the end of 5 years.

Project Surrounding Details: nearest village Purtigeri: 2 km; nearest Town (Ilkal) 12km, nearest densely populated/built up area- Bandarkal – 2.00 km.

The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent and environmental consultant present explained the project. The proponent informed that there are no national park, wildlife sanctuary, archaeological sites and interstate boundaries within 10 km radius of the project site. The proponent informed that he has obtained NOC from revenue Department for grant of quarry lease dated 28.06.2007. The proponent informed the Committee

Page 16: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

16

 

that they have constructed toilets for schools and established greenery as part of the Social commitment plan. After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC during the meeting held on 03.09.2012.

The Authority observed that the proposal is for extraction of pink granite in an area of 1.2 Acres (0.48 hectare) of Patta land.

The Authority noted that as per the IBM guidelines a minimum of 7.5 meters safety area has to be left from the boundary of the lease area. Mining/ quarrying has to be undertaken with benches of 3 meters with 45 degree slope. Following this criteria mining / quarrying can be undertaken only for 3 to 4 benches. A minimum of 30 meters at bottom of the mine pit has to be maintained. Therefore, mining / quarrying in smaller extent does not appear to be technically feasible. Added to this, the area is also to be reserved for storing mineral blocks, storage of waste material and area is also needed for development of greenbelt. Thereby taking all these parameters, no environmentally sustainable quarrying can be achieved in less than one hectare of area.

The Authority after discussion, decided to direct the proponent to increase the lease area and to furnish the revised land use plan for taking environmentally sustainable quarrying.

Subsequently the proponent has submitted the details of additional land available vide letter dated:15.09.2012.

The Authority perused the information furnished by the proponent and noted that the proposed One Acre 20 Guntas lease is out of the total 4 Acres patta land of the proponent. Therefore additional land is available adjacent to the proposed leased land. This land can be utilized for auxiliary activities such as storing of minerals, waste dumping, green belt development, etc. The Authority noted that the total extent of the proposed activity now stands revised to 4 Acres.

The Authority after discussion and taking note of the resources available have decided to issue Environmental Clearance for extraction of 1,500 Cum per Annum of pink granite subject to submission of the following information/ documents:

(a) Revised quarry plan for the entire area of 4 Acre, prepared by a qualified person recognized by the Indian Bureau of Mines.

(b) Order of conversion of land from agriculture to non-agriculture purpose issued by the Deputy Commissioner.

(c) Commitment that 7.5 meters of safety zone will be maintained from the lease boundary abutting to quarry pit.

(d) Reclamation and rehabilitation plan including progressive and final mine closure plan.

Page 17: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

17

 

3. Pink Granite Quarrying, QL.No.573 at Sy.no.184/2, Hulageri village, Kustagi Taluk, Koppal District by Sri Mallikarjun V Shettar (SEIAA 78 MIN 2012)

It is a project proposal for pink Granite Quarrying with the production of 5,000 cum/year. Total land area is 1 Acre in Private Patta land. The investment of Rs. 100 lakhs.

Sri. Mallikarjuna V. Shettar has applied for EC from SEIAA for their proposed Renewal of Quarry of Pink Granite of 5,000 cum/year production at Quarry Lease No. 573 at Sy.No. 184/2, Kustagi Village, Koppal Taluk and District over an area of 1-00 Acres of Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying: Open Cast Semi-mechanized with small scale drilling by jack hammer and cutting by optima wire saw. Man Power: 35; Total project cost: Rs. 100 Lakhs. The project lease area is connected to Purtigeri – Hulageri PWD road 1.5 km away. Geological Resources: 80,000 Cum; Mineable reserve: 40,000 Cum.

The Project Proponent has submitted quarry lease granted on 15.04.1997 and corrigendum dated 15.11.2002 valid for 5 years w.e.f. 28.01.2003; Quarrying Plan approved by Mines & Geology Dept on 07.07.2012, Land documents (RTC), Notification for grant of lease dated 26.03.2012 issued by C&I Dept for a period of 10 years, Survey of India Topo-sheet, Pre-feasibility Report and EMP. Land NA conversion obtained from DC on 03.01.2012.

Land-use pattern: Mining –0.5 Acres; Top soil storage: 0.05 Ha; Infrastructure: 0.001 Ha; Waste Dumps- 0.2 Acres; Roads – 0.05 Ha; green belt 0.1 Ha; Undisturbed Area: 0.099 Ha. Water: Total Requirement: 5 KLD sourced from water tankers. Over Burden (OB): Total Quantity: 81000 TPA at the end of 5 years.

Project Surrounding Details: nearest village Purtigeri: 2 km; nearest Town (Ilkal) 12km,

The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent and environmental consultant present explained the project. The proponent informed that there are no national park, wildlife sanctuary, archaeological sites and interstate boundaries within 10 km radius of the project site. The proponent informed the Committee that they have constructed toilets for schools and established greenery as part of the Social commitment plan. After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC during the meeting held on 03.09.2012.

The Authority observed that the proposal is for extraction of pink granite in an area of 1 Acres (0.40 hectare) of Patta land.

The Authority noted that as per the IBM guidelines a minimum of 7.5 meters safety area has to be left from the boundary of the lease area. Mining/ quarrying has to be undertaken with benches of 3 meters with 45 degree slope. Following this criteria mining / quarrying can be undertaken only for 3 to 4 benches. A minimum of 30 meters at bottom of the mine pit has to be maintained. Therefore, mining / quarrying in smaller extent does not appear to be technically feasible. Added to this, the area is also to be reserved for storing mineral blocks, storage of waste material and area is also needed for development of greenbelt. Thereby taking all these parameters, no environmentally sustainable quarrying can be achieved in less than one hectare of area.

Page 18: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

18

 

The Authority after discussion, decided to direct the proponent to increase the lease area and to furnish the revised land use plan for taking environmentally sustainable quarrying.

Subsequently the proponent has submitted the details of additional land available vide letter dated 15.09.2012.

The Authority perused the information furnished by the proponent and noted that the proposed One Acre lease is out of the total land of 3 Acres 30 Guntas of patta land of the proponent. Therefore additional land is available adjacent to the proposed leased land. This land can be utilized for auxiliary activities such as storing of minerals, waste dumping, green belt development, etc. The Authority noted that the total extent of the proposed activity will now stands revised to 3 Acres and 30 guntas.

The Authority after discussion and taking note of the resources available have decided to issue Environmental Clearance for extraction of 1,600 Cum per Annum of pink granite subject to submission of the following information/ documents:

a) Revised quarry plan for the entire area of 3 Acres and 30 guntas, prepared by a qualified person recognized by the Indian Bureau of Mines.

b) Order of conversion of land from agriculture to non-agriculture purpose issued by the Deputy Commissioner.

c) Commitment that 7.5 meters of safety zone will be maintained from the lease boundary abutting to quarry pit.

d) Reclamation and rehabilitation plan including progressive and final mine closure plan.

Fresh Projects:

Construction Projects:

1. Establishment / construction of International Standard Golf Course with 18 holes, Academy, Hotel with Sports Complex, Conference Facilities and Residential Layout of 900 plots at various Sy. Nos. of Varkodi and Vajamangla village, Mysore Taluk, Mysore District and Bothaganhalli village of Srirangapattana Taluk, Mandya District by M/s Eagleburg India Pvt. Ltd. (SEIAA 113 CON 2011)

It is a proposal for establishment of International Standard Golf Course with 18 holes, Academy, Hotel with Sports Complex, Conference Facilities and Residential Layout of 900 plots of various dimensions with Ground + 3 Upper Floors on an area of 16,88,156.22 Sq.m (417 Acres) and with the total built up area of 27,640 Sq.m. The total water requirement is 877 KLD and the investment is of Rs. 98 crores. Total parking provided is for 240 cars, 50 Scooters, 90 Bicycles and 50 Golf Cart (Total : 430 Nos).

M/s. Eagleburg India Pvt. Ltd., have applied for EC from SEIAA for their new proposed Construction of International Standard Golf Course with 18 holes, Academy, Hotel (with 139 Rooms of B+G+4 Floors) with Sports Complex (G+1), Conference Facilities & Residential Layout (with 900 Sites) at Varkodi & Vajamangla Village, Mysore Taluk, Mysore District & Bothaganhalli Village, Srirangapattana Taluk, Mandya District under Schedule No 8(b) of EIA

Page 19: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

19

 

Notification, 2006. Total Project cost: Rs. 98 Crores. Project comes under MUDA under commercial Zone. The details of land converted by DC, Mysore and details of land acquired by KIADB are submitted.

Project Details: (a) Land: Total plot area: 16,88,156.22 Sqm; Total built up area: 27,640 Sqm; (b) Greenery: Landscape area: 8,48,198.62 Sqm (50.24%) (c) Water Requirement: Total water requirement is 877 KLD sourced from Mysore Municipal Corporation. (d) Excavated Earth Management: Total excavated soil generated: 4, 50,000 Cum; back filling: 2, 00,000 and Landscaping quantity 50,000 Cum within the project Site and about 2, 00,000 Cum will be used for Golf Course (e) Sewage: Total quantity generated: 390 Cum treated in proposed STP design capacity of 750 KLD with SBR 694 KLD;. Sludge- 694 used as manure. (f) Solid waste: Total generated: 2166Kg/day; organic waste of 1300 Kg/day, treated in compost pits & Converted to manure. Inorganic waste of 866 Kg/day will be sent for recycling. (g) Power Requirement: Total Requirement: 1250+5400 KVA from CESCOM; Power Backup 4X360 KVA DG sets (h) parking 430 Numbers.

Project Surrounding Details : Varuna Canal Water is near the project site. The project site is located on Bannur - Mysore Road, Mysore -28 Kms, Srirangapattana -25 Kms, Ranganathittu Bird Sanctuary -45 Kms; Other details: Rain Water Harvesting proposed. Soil investigation report submitted; UGD proposed.

The subject was placed in the 77th SEAC meeting held on 2/3.12.2012 and the proponent present explained the project. After deliberation, the Committee decided to issue the following ToRs along with model ToRs to the proponent for preparation of EIA by an accreditated consultant.

1. Protection of Varuna canal outside the project site. 2. Land records in the proponent’s name.

The proponent has submitted the EIA on 06.07.2012 in response to the ToRs issued on 01.02.2012. The proponent has submitted the various survey numbers of the project site as annexure in the application and also reflected in the EIA submitted.

The proponent and environmental consultant present explained the EIA before the SEAC meeting held on 20th July 2012.. The proponent informed that the height of the building is less than 15 m and hence the O.M on high rise building issued by MoEF does not apply. He also informed that Somanathapur temple monument is 25 km away from the project site. The project is connected to Mysore –Bunnur State High way No. 33. The existing, projected and modified LoS of this road is A-B-B.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining social commitment plan on letterhead for Rs. 10 Lakhs, as committed by the proponent during the meeting.

The proponent has submitted information vide letter dated 21.08.2012.

The Authority perused the information submitted by the proponent and took note of the recommendation of the SEAC.

The Authority observed that there is no firm commitment with regard to supply of water from the competent authorities. The Authority further noted that it is a mixed development having a golf course, hotel, sports complex apart from layout of 900 plots. The Authority opined that it is both an area development plan comprising of area of more than 50 Acres and as well as a

Page 20: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

20

 

construction project with a built up area of 27,640 Sqm. Therefore the appraisal need to take into account the cumulative impact of both the activities.

The Authority therefore decided to get the following information for further consideration of the proposal:

a) NOC from the competent authority for supply of water b) Details of proposed built up area including that of 900 plots. c) Details of Kharab land with its present land use duly marking on the layout plan. d) Alternate source of water and status of permission if any to extract ground water in case

the supply is inadequate.

The Authority also decided to invite the proponent to the meeting after submission of the information.

2. "E-City Residential Project- Godrej Universal" at Survey No. 51/16, 51/17, 51/18, 127/1,

127/2, 128/1,128/2, 128/3,128/4, 128/5, 128/6, 129/1A, 129/1B, 129/2, 129/3, 130/1,130/2,130/3,130/4,130/5A,130/5B,130/6, 130/7, 130/8, 143,Doddathogur Village, Begur Hobli, Bangalore South Taluk, Bangalore by M/s Universal Builders. (SEIAA 120 CON 2012)

It is a proposal for construction of Residential Apartment of 840 Units in 12 Block with Basement floor + Ground floor + 4 Upper floors on an area of 59,741.221 Sq.m and with the total built up area of 80,855.90 Sq.m. The total water requirement is 570 KLD and the investment is of Rs.135.06 crores. The total parking provided is for 800 cars.

M/s. Universal Builders have applied for Environmental Clearance (EC) from SEIAA for their new proposed E-City Residential project of Godrej Universal at Survey Nos: 51/16, 51/17, 51/18, 127/1, 127/2, 128/1, 128/2, 128/3, 128/4, 128/5, 128/6, 129/1A, 129/1B, 129/2, 129/3, 130/1, 130/2, 130/3, 130/4, 130/5A, 130/5B, 130/6, 130/7, 130/8, 143, Doddathogur Village, Begur Hobli, Bangalore South Taluk, Bangalore, under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 135.010 Crores; Land conversion obtained from DC.

Project Details: Land: Total plot area: 59,741.221 Sqm (14 acres 30.5 guntas); Total built up area: 80,855.90 Sqm. Project consists of 840 flats in 12 Blocks, with 31 units (B+G+4UF). Landscape area: 30,072.62 Sqm (50.33% of plot area). Water Requirement: Total water requirement is 345 KLD; sourced from BWS&SB. Sewage: Total quantity generated: 520 KLD, treated in proposed STP of design capacity 2 X 275 KLD with MBR technology; Sludge generated: 19.25 kg/day used as manure. Municipal Solid Waste: Total generated: 1260 kg/day; Organic waste will be treated in organic convertor and product used as manure. Inorganic waste will be sent for recycling. Power: Total Requirement: 4540 KVA from BESCOM; Backup Power: DG sets of 1X 62.5 KVA& 4 X 250 KVA; Parking: 800 Numbers. Project surrounding details: BIAL: 45 km; Other details: Rain Water Harvesting is proposed.

Note: 1. Consultant details submitted.

2. NOC from BWS&SB dated 11.04.2007 submitted.

The subject was discussed in the SEAC meeting held on 20th & 21st July 2012. The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 14.95 m and hence the O.M on high rise building issued by MoEF

Page 21: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

21

 

does not apply. The project site is connected to Electronic City- Jigani road. The existing, projected and modified LoS of this road remains at B.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent.

1. Rework on water balance. 2. Details of excess excavated earth and its disposal. 3. Social commitment plan on letterhead for Rs. 13.5 Lakhs, as committed by the

proponent during the meeting.

The proponent has submitted information vide letter dated 23.08.2012.

The Authority perused the information submitted by the proponent and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to

submission of the following information:

a) Layout plan duly marking the green belt. b) Parking facility duly calculating based on MOEF/BBMP norms and considering the

highest one. c) Details of Kharab land with its present land use. d) Revised specific social commitment plan with activity, budget and time frame.

3. Proposed Residential Apartment at Sy.No. 79, Katha No.572/438, Siddapura Village, Varthur Hobli, Bangalore East Taluk, Bangalore. by M/s Spectra Construction Private Limited (SEIAA 59 CON 2012)

It is a proposal for construction of Residential Apartments of 195 units in 2 Blocks with Basement + Ground floor + 14 Upper floors on an area of 12,064.76 Sq.m and with the total built up area of 27,145 Sq.m. The total water requirement is 160 KLD and the investment is of Rs. 45 crores. The total parking provided is for 263 cars.

M/s. Spectra Constructions Private Limited has applied for EC from SEIAA for their new proposed residential apartment project at Sy. No. 79, Katha No. 572/438, Siddapura, Varthur Hobli, Bangalore East Taluk, Karnataka under 8(a) of schedule of EIA Notification, 2006 under category-B requiring EC from SEIAA. Total project cost: Rs.45 Crores. Project comes under BBMP limits.

Project Details: (a) Land: Total plot area: 12,064.76 Sqm; Total built up area: 27,145 .00 Sqm. The project consists of 195 units in 2 Blocks with Basement + Ground Floor + 4 Upper Floors. (b) Greenery: Landscape area: 3908.98 Sqm (32.41% of plot area). (c) Water Requirement: Total water requirement is 160 KLD; Source of water: BWSSB. (d) Soil: Total excavated soil: 19365 Cum; Backfilling Quantity: 1390 Cum, landscaping quantity: 5205 Cum within the project site, 6133 Cum for road /ramps formation, 1116 Cum for leveling of the site using cut and fill method, 2504 Cum for mounds creation in garden area and 3017 Cum soil will be transported to adjacent layout development & brick kiln. (e) Sewage: Total quantity generated: 128 KLD, treated in proposed STP of design capacity 150 KLD; Sludge generated: - 22Kg/day used as manure. (f) Solid Waste: Total generated: 533Kg/day; Organic waste: 320Kg/day will be

Page 22: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

22

 

composted at the project site and product used as manure. Inorganic waste: 213 Kg/day will be sent for recycling. (g) Power Requirement: Total Requirement: 1750 KVA from BESCOM; Power Backup: 3X500KVA & 250 KVA DG sets (h) Parking: 263 Numbers. Other Details: Rain Water Harvesting is proposed.

The subject was placed in the 82nd SEAC meeting held on 27/28.04.2012 and the proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 14.95 m and the RoW in front of the project site is 18 m. The nearest fire station is 4 km away from the project site. The proponent informed that the UGD line is existing and they have applied for NOC from BWS&SB for water supply. The Committee advised the proponent to adopt better technology for STP. The proponent informed that the project is located near to Varthur Main Road –Nallurahalli Road. The existing, projected and modified LoS of this road remains at D.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the project proponent:

1. NOC from BWS&SB for water supply. 2. Dated site photographs. 3. Number of trees proposed for landscape species- wise. 4. Social commitment plan for Rs. 5 Lakhs, as committed by the proponent during the

meeting (letter not given).

The subject was again placed in the 86th SEAC meeting held on 20/21.07.2012 for closure and the Committee noted that the proponent has submitted the information on 19.07.2012 and hence decided to take action as per the proceedings of 82nd SEAC dated 27-28/04/2012.

Meanwhile, the proponent has submitted the revised proposal on 16.08.2012 in view of the prevailing market conditions. The comparative statement of the salient features of the earlier proposal and revised proposal is given in the table below:

Features Unit Earlier Proposal Revised Proposal Type of Development Residential No change Project Cost Rs. Crores. 45 No change Plot Area Sqm 12064.76 No change Gross Built Up Area Sqm 27145 No change Landscape area Sqm 3908.98 (32.41%) 4102.01 (34%) Building Floors B+G+4UF B+G+14UF Dwelling units # 195 195 Height of the Building m 14.95 44.56 Road Width(RoW) m 18 18.3 Distance to the nearest Fire Station

km 5 5

Water requirement KLD 160 160 Source of water BWSSB No change Wastewater generation KLD 128 No change STP capacity KLD 150 No change Sludge generated Kg/day 22 No change Solid Waste Kg/day 533 No change Power requirement KVA 1750 No change

Page 23: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

23

 

Power Source BESCOM No change Backup power(DG sets) KVA 3 X 500 KVA & 1

X 250 KVA 2 X 380

Parking facilities PCU 263 No change

The proponent and environmental consultant present explained the project before the SEAC during the meeting held on 25.08.2012. The proponent informed that the height of the building is increased from 14.95 to 44.56 m and the RoW of the existing road in front of the project site is 18.3 m (as per the BBMP letter dated 18.01.2012. The nearest fire station is 5 km away from the project site. The landscape has been enhanced due to vertical expansion.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Clarification with regard to change in the layout plan due to change in the number of upper floors from 4 to 14.

b) Authentic document with regard to ROW. c) Status of UGD and plan for disposal of excess treated water in the absence of UGD d) Revised specific social commitment plan with activity, budget and time frame.

4. Residential villas at Sy.No. 120,21,22,23, Chikkabanahalli village, Bangalore East

Taluk, Bangalore by M/s Sycon Constructions Pvt. Ltd. (SEIAA 73 CON 2012)

It is a proposal for construction of 70 Residential villas on an area of 45,395.553 Sq.m and with the total built up area of 27,125.166 Sq.m. The total water requirement is 56.7 KLD and the investment is of Rs. 40 crores. The total parking provided is for 154 cars.

M/s. Sycon Construction Pvt. Ltd., have applied for Environmental Clearance (EC) from SEIAA for their new proposed residential villas project at Survey Nos: 20, 21, 22, 23, Chikkabanahalli Village, Bangalore East Taluk, Bangalore, under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 40 Crores. Project comes under BBMP; Land conversion obtained from DC vide letter dated 21.10.2011 & 23.10.2011. Height of the building is 10 m.

Project Details: Land: Total plot area: 45395.55 Sqm; Total built up area: 27125.166 Sqm. Project consists of 70 villas with G+2UF. Landscape area: 4542.57 Sqm (10 % of plot area). Water Requirement: Total water requirement is 56.7 KLD; sourced from Grama Panchayat. Excavated Earth: Total Quantity of excavated earth: 7000 Cum will be used within the project site for landscaping and road making etc. Sewage: Total quantity generated: 45.36 KLD, treated in proposed STP of design capacity 50 KLD of MBR technology; Sludge generated: 3 kg/day used as manure. Municipal Solid Waste: Total generated: 126 kg/day; Organic waste: 75.6 kg/day treated in organic convertor and product used as manure. Inorganic waste: 50.4 kg/day will be sent for recycling. Power: Total Requirement: 500 KVA from BESCOM; Backup Power: DG sets of 2 X 250 KVA Parking: 154 Numbers. Other details: Rain Water Harvesting is proposed.

Page 24: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

24

 

The subject was placed in the 83rd SEAC meeting held on 25/26.05.2012 and the proponent and the consultant were present in the meeting explained the project. The proponent informed that the height of the proposed building is 10 m; the RoW of the existing road in front of the building is 12 m, The nearest Fire Station is at a distance of 7 km away. The level difference in the project site is 2m. There is no UGD line in the project site. The project site is located along Chikkabanahalli Road and is 1km away from Whitefield main road which connects Hoskote on one side and Varthur on the other side. The existing, projected and modified LoS of Chikkabanahalli Road is A-A-A and the same for Whitefield Main road is B-C-C (road towards Hoskote) and B-B-B (road towards Varthur).

After deliberation, the Committee decided to reconsider the proposal after obtaining the following information from the proponent:

1. Scientific assessment of Panchayat borewell water along with quantity and quality and impact on the competitive users.

2. Grama Panchayat clearance for water supply. 3. Explore the possibility to enhance the energy savings. 4. Enhanced landscape plan with more number of local flower and fruit bearing

trees. 5. Revised water balance with plan for disposal of excess treated water. 6. Social commitment plan for Rs. 4 Lakhs, as committed by the proponent during

meeting (letter not given)

The proponent has submitted the above information on 22.08.2012 in response to this office letter dated 11.06.2012.

The Committee in the meeting held on 24th & 25th August 2012, perused the replies submitted by the proponent and decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Alternate source of water in case of shortage of supply from the panchayath. b) Clearance from the Central Ground Water Authority/competent Authority to abstract

ground water. c) Status of UGD and plan for disposal of excess treated water in the absence of UGD. d) Revised specific social commitment plan with activity, budget and time frame.

5. “Shriram Signiaa”, Residential Apartment at Sy. No.s 75/2 & 76/6, Doddathoguru Village, Begur Hobli, Bangalore South District by M/s. Shriram Properties Pvt. Ltd. (SEIAA 89 CON 2012)

It is a proposal for construction of Residential Apartment in 336 Units in Basement + Ground floor + 13 Upper floors and Club house in Ground floor + 2 Upper floors on an area of 19,424.91 Sq.m and with the total built up area of 54,319 Sq.m. The total water requirement is 231 KLD and the investment is of Rs. 86.86 crores. The total parking provided is for 376 cars.

M/s. Shriram Properties Private Limited., have applied for Environmental Clearance (EC) from SEIAA for their new proposed Residential Apartment of “Shriram signiaa” project at Survey Nos: 75/2 & 76/6, Doddathoguru Village, Begur Hobli, Bangalore South Taluk under 8(a) of

Page 25: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

25

 

Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 86.86 Crors. Project comes under BBMP Limits; Land conversion obtained from DC.

Project Details: Land: Total Plot area: 19,424.91 Sqm; Total built up area: 54,319 Sqm. Project consists of 336 flats with Basement + Ground+ 13 Upper Floors + Terrace. Landscape area: 7,571 Sqm (39 % of plot area). Water Requirement: Total water requirement is 249 KLD sourced from Doddathoguru Grama Panchyath: Excavated Earth: Total Quantity of excavated earth: 15,640 Cum; 6,795 Cum of the excavated earth will be used landscaping development & the remaining 8,845 Cum will be used for hardscape & formation activities the project site. Sewage: Total quantity generated: 200 KLD, treated in proposed STP of design capacity 200 KLD; Sludge generated: 72 kg/day used as manure. Municipal Solid Waste: Total generated: 739 kg/day; Organic waste: 443 kg/day treated in organic convertor and product used as manure. Inorganic waste: 296 kg/day will be sent for recycling. Power: Total Requirement: 1,500 KVA from BESCOM Backup Power: DG sets of 1 X 750 KVA & 1X 500 KVA Parking: 351 Numbers.

Project surrounding details: Veerasandra Kere – 2 km , East: Kammasandra Lake – 3.6 km, South East: Muthanallur Lake – 7.9 km South East Rayasandra Lake – 3.7 North East: Hosa Lake – 4.5 km North East: Begur Lake – 4.5 km North East: Begur Lake – 4.5 km North West; Madiwala Lake – 8.3 km North West; Jigani Lake – 5.8 km South West . Bannerughatta National Park – 10.4 km.

Other details: Rain Water Harvesting is proposed.

The subject was placed in the 84th SEAC meeting held on 22/23.06.2012 and the proponent and environmental consultant were present explained the project. The proponent informed that the height of the building is 43.835 m and the RoW of the existing road in front of the project site is 24 m. The fire station is 1.3 km away from the project site. The level difference in the project site is 3m. The project proponent informed that the project site is located near to Niladri road which connects Niladri on one side and Hosur other side. The existing, projected and modified LoS this road is B-D-C (Road towards Niladri) and B-C-B (Road towards Hosur).

After deliberation, the Committee decided to reconsider the proposal after obtaining the following information from the proponent.

1. Rework on landscape plan. 2. Scientific assessment of the panchayath borewell with quality and quality along with

impact on the competitive users. 3. Details of waste water disposal. 4. Rework on the land use pattern. 5. Social Commitment Plan for Rs. 9 Lakhs on letterhead as committed.

The proponent has submitted the above information on 30.07.2012 in response to this office letter dated 03.07.2012.

The Committee perused the replies submitted by the proponent and decided to recommend the proposal to SEIAA for issue of environmental clearance during the meeting held on 24th August 2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

Page 26: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

26

 

a) Yield of the bore wells estimated through actual measurement. b) Details on present average per capita supply of water from the panchayath. c) Alternate source of water in case of shortage of supply from the panchayath. d) Clearance from the Central Ground Water Authority/competent Authority, to abstract

ground water. e) Plan to increase green belt to at least 33%. f) Revised specific social commitment plan with activity, budget and time frame.

6. St Mark’s –Commercial Project, Municipal No.50, St. Marks Road, Bangalore District by M/s. Sobha Developers Ltd. (SEIAA 90 CON 2012)

It is a proposal for construction of Commercial Building (Commercial + Office + Food Court) of 5 Basement + Lower Ground + Ground + 5 Upper Floors on an area of 7269.54 Sq.m and with the total built up area of 34951.64 Sq.m. The total water requirement is 102 KLD and the investment is of Rs. 98 crores. The total parking provided is for 405 cars.

M/s. Sobha Developers Ltd., have applied for Environmental Clearance (EC) from SEIAA for their new proposed Commercial project “St Mark’s Property” at Municipal No. 50, St. Marks Road, Bangalore District under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 98 Crores. Land conversion obtained from DC. The project consists of Mall, office, and a Food Court.

Project Details: Land: Total plot area: 7269.54 Sqm; Total built up area: 29,295.41 Sqm. Project consists of 1 Blocked with 3B + LG + G+ 5 floors Landscape area: 1269.87 Sqm (20 % of plot area). Water Requirement: Total water requirement is 72 KLD out of which fresh water requirement is 40KLD sourced from BWSSB. Excavated Earth: Total Quantity of excavated earth: 49,173.72 Cum; backfilling & landscaping quantity: 40,145.07 Cum; and excess soil will be reused for road development and land filling within the project site. Sewage: Total quantity generated: 65 KLD, treated in proposed STP of design capacity 90 KLD; Sludge generated: 18.0 kg/day used as manure. Municipal Solid Waste: Total generated: 374 kg/day: Organic waste: 149.6 kg/day treated in organic convertor and product used as manure. Inorganic waste: 224.4 kg/day will be sent for recycling. Power: Total Requirement: 1923 KVA from BESCOM; Backup Power: DG sets of 2 X 1000 KVA + 1 X750 KVA Parking: 360 Numbers.

Project surrounding details: Halasuru Lake – 2 Km. Cariappa Park – 200m Cubbon Park – 400 m. Other details: Rain Water Harvesting is proposed.

The subject was placed in the 84th SEAC meeting held on 22/23.06.2012. The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 26.87 m and the RoW of the existing road in front of the project site is 20.7m. The level difference in the project site is 3.956 m. The proponent informed that the project site is surrounded by traffic roads on 3 sides namely St. Marks road, Church Street Road and Museum Road. The existing, projected and modified LoS of St. Marks Road, Church Street Road and Museum Road is D-F->F, A-A-A and A-B-B respectively.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent.

Page 27: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

27

 

1. Enhanced landscape plan. 2. Rework on effluent characteristics 3. Enhanced energy savings. 4. Social Commitment Plan for Rs. 10 Lakhs on letterhead, as committed.

The proponent has submitted the above information on 31.07.2012 in response to this office letter dated 03.07.2012 along with revised proposal on 31.07.2012. The comparative statement of the salient features of the earlier proposal and revised proposal is given in the table below:

Features Unit Earlier Proposal Revised Proposal Type of Development Commercial No change Project Cost Rs.

Crores. 98 No change

Plot Area Sqm 7269.54 No change Gross Built Up Area Sqm 29295.41 34951.64 Landscape area Sqm 1269.87 (20%) 2114.38 (33%). Building Floors 3B+LG+G+5UF 5B+LG+G+5UF

(addition of 2 Basements)

Dwelling units # - - Height of the Building m 26.87 No change Road Width(RoW) m 20.70 No change Distance to the nearest Fire Station

km 1.50 No change

Water requirement KLD 72 No change Source of water BWS&SB No change Wastewater generation KLD 65 No change STP capacity KLD 90 No change Sludge generated Kg/day 18 No change Solid Waste Kg/day 374 No change Power requirement KVA 1923 No change Power Source BESCOM No change Backup power(DG sets) KVA 2 X 1000 KVA &

1 X 750 KVA No change

Parking facilities PCU 360 No change

The proponent and environmental consultant present explained the project in the SEAC meeting held on 25th August 2012. The proponent informed that they have added 2 basements extra and consequently the built up area is increased in the revised proposal. This was necessitated for accommodating enhanced landscape area from 1269.87 (20%) to 2114.38 (33%) as instructed by the Committee earlier.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC.

Page 28: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

28

 

The Authority observed that it is a commercial development in the heart of the city and amidst a busy area. Provision has been made for 5 basements while revising the proposal. The Authority observed that it is an unusual proposition to increase the basements from 3 to 5 for increasing the green belt as recorded in the minutes of SEAC. The Authority further apprehended that excavating for five basements will pose several problems such as safety of adjacent structures, seepage during construction/operation, ensuring proper ventilation in the basements, safety of men and material during emergency, disposal of excess excavated earth, etc.

The Authority further observed that the proposed site has a level difference of 4 meters and

therefore calls for a well planned storm water management plan. It is noted that the traffic study on the St. Mak’s road shows D-F->F which need due attention for the environmental consideration.

The Authority therefore decided to get the following information for further consideration of

the proposal:

a) Justification for 5 Basements with safety measures as per NBC. b) Ground water table in the project site, possibility of seepage and management strategy

during construction and operation. c) Engineering and chemical characteristics of soil. d) NOC from BWSSB for supply of water. e) STP and Solid Waste Management Facility duly marking on layout plan. f) Proper storm water management plan taking the contour and level difference of the project

site in to consideration. g) Energy foot print. h) Traffic study near the project site.

The Authority also decided to invite the proponent to the meeting after submission of the information.

7. Residential Apartments at Plot no 3(B) & 3(F) in Doddenakkundi 1st Phase Industrial

Area Sy.No. 73 at Doddenakkundi Village, Bangalore East Taluk, Bangalore Urban District by Sri. Tony Vincent (SEIAA 125 CON 2012)

It is a proposal for construction of Residential Apartment project of 190 units with 2 Basement + Ground + 10 Upper Floors + Terrace on an area of 6537 Sq.m and with the total built up area of 34663.4 Sq.m. The total water requirement is 128.2 KLD and the investment is of Rs. 40 crores. The total parking provided is for 230 cars.

Sri. Tony Vincent has applied for Environmental Clearance (EC) from SEIAA for their new proposed Residential Apartment project at Plot No. 3(B) & 3(F) in Doddenakkundi 1st Phase Industrial Area (Sy. No. 73 of Doddenakkundi Village), Bangalore East Taluk, Bangalore under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 40 Crores. Project comes under BBMP limits; the site is vacant land flat terrain. Land conversion obtained from DC.

Project Details: Land: Total plot area: 6537 Sqm; Total built up area: 34663.40 Sqm. Project consists of 166 units with 2 Basement Floors + Ground Floor & 10 Upper Floors. Landscape area: 2157.21 Sqm (33% of plot area). Water Requirement: Total water requirement is 112 KLD; Fresh water requirement: 87,050 KLD, sourced from BWSSB. Excavated Earth: Total

Page 29: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

29

 

Quantity of excavated earth: 26000 Cum (Above 26000 cum will be used within the project site for landscaping of gardens and road making etc); Sewage: Total quantity generated: 89.6 KLD, treated in proposed STP of design capacity 100 KLD; Sludge generated: - 4 kg/day used as manure. Municipal Solid Waste: Total generated: 249 kg/day; Organic waste: 149.4 kg/day treated in organic convertor and product used as manure. Inorganic waste: 99.6 kg/day will be sent for recycling. Power: Total Requirement: 1000 KVA from BESCOM; Backup Power: DG sets of 2X500 KVA; Parking: 210 Numbers. Other details: Rain Water Harvesting is proposed.

The subject was placed in the 86th SEAC meeting held on 20/21.07.2012 and the proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 39.85 m and the RoW of the existing road in front of the project site is 30 m. The nearest fire station is 5 km away from the project site. The level difference in the project site is 2.221 m. The project site is located along ITPL Main road which connects ITPL on one side and Whitefield on the other side. The existing, projected and modified LoS this road is C-E-E (road towards ITPL) and D->F->F (road towards Whitefield).

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent.

1. Details of land for disposal of excess excavated earth. 2. Social commitment plan on letterhead for Rs. 4 Lakhs, as committed by the

proponent during the meeting.

The proponent has submitted the above information on 31.07.2012 in response to this office letter dated 01.08.2012. Meanwhile, the proponent has submitted the above information along with revised proposal on 31.07.2012. The comparative statement of the salient features of the earlier proposal and revised proposal is given in the table below:

Features Unit Earlier Proposal Revised Proposal Type of Development Residential No change Project Cost Rs. Crores. 40 No change Plot Area Sqm 6537.0 No change Gross Built Up Area Sqm 34663.40 No change Landscape area Sqm 2157.21 (33%) No change Building Floors 2B+G+10UF No change Dwelling units # 166 190 Height of the Building m 39.85 No change Road Width(RoW) m 30 No change Distance to the nearest Fire Station km 5 No change Water requirement KLD 112 128.25 Source of water BWSSB No change Wastewater generation KLD 89.6 102 STP capacity KLD 100 110 Sludge generated Kg/day 4 No change Solid Waste Kg/day 249 285 Power requirement KVA 1000 No change Power Source BESCOM No change Backup power(DG sets) KVA 2 X 500 No change Parking facilities PCU 210 230

Page 30: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

30

 

The subject was taken on 24.08.2012 in view of the oral submission made by the consultant about his inability to attend on 25.08.2012 for making presentation. The proponent and environmental consultant present explained the project. The proponent informed that only the number of flats is enhanced from 166 to 190 in the revised proposal and consequently the water requirement and the STP capacity have also been revised. The UGD works have already been started.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority noted that the proposed site is in the industrial area. The industrial site has been converted for residential use. Residential Developments amidst industries is not a welcome proposition. The proposal does not reveal the number and type of industries that are located at the vicinity of the project site. Whether the conversion is in accordance with KIADB norms is also not forthcoming.

The Authority therefore decided to get the following information for further consideration of the proposal:

a) Details of industries around the project site within one Km. b) Whether the conversion is in accordance with KIADB norms and permission/NOC

obtained from KIADB, if any. c) NOC from BWSSB for supply of water. d) Water supply and water balance chart e) Type of industry that was existing in the project site. f) Due diligence report of the project site.

The Authority also decided to invite the proponent to the meeting after submission of the information.

8. Residential Apartment, Sy.no.39/1 & 39/2 of Battarahalli village, Bidarahalli Hobli,

Bangalore East Taluk, Bangalore Urban District by M/s. Gina Developers Pvt. Ltd. (SEIAA 133 CON 2012)

It is a proposal for midification of of residential apartment of 170 flats consists Basement Floor + Ground Floor + 11 Floors on an area of 7167.791 Sq.m and with the total built up area of 28,943.69 Sq.m. The total water requirement is 114.75 KLD and the investment is of Rs. 24 crores. The total parking provided is for 187 cars.

M/s. Gina Developers Pvt. Ltd have applied for Environmental Clearance (EC) from SEIAA for their modified “Gina Shalom” Residential Building project at Survey Nos: 39/1 & 39/2, under 8(a) of Schedule of EIA Notification, 2006 under category-B. Project comes under BBMP; Land conversion obtained from DC.

The proponent had obtained EC from SEIAA vide file No. SEIAA 30 con 2010 on 18.01.2011.The comparative statement of the salient features of the earlier proposal and revised proposal is given in the table below:

Features Unit Earlier Proposal Revised Proposal

Type of Development Commercial +Residential Residential

Page 31: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

31

 

Project Cost Rs. Crores. - 24 Plot Area Sqm 7167.791 No change Gross Built Up Area Sqm 30419.17 28943.69 Landscape area Sqm 2010 2466.57 (33%) Building Floors 2B+G+8UF B+G+11UF Dwelling units # - 170 Height of the Building m 27 36.65 Road Width(RoW) m 43 60.07 Distance to the nearest Fire Station km 4.3 No change Water requirement KLD 100 114.75 Source of water BWSSB No change Wastewater generation KLD - 91.8 STP capacity KLD 100 No change Sludge generated Kg/day - 15 Solid Waste Kg/day 492 510 Power requirement KVA - 1190 Power Source BESCOM No change Backup power(DG sets) KVA 2X250 KVA 2X140 KVA Parking facilities PCU - 187

The subject was discussed in the SEAC meeting held on 24th & 25th August 2012. The proponent and environmental consultant present explained the project. The proponent informed that the UGD has already come up. The 4-lane (NH-4) road in front of the project site has been converted to 6-lane thereby increasing the RoW from 43 m to 60.07 m. the Committee observed that the project proposal complies the guidelines of the O.M dated 07.02.2012 issued by MoEF, GoI. The proponent committed to spend Rs. 5 Lakhs as a part of his Social commitment plan toward environmental cause. The proponent informed that the project site is located near to Bangalore (K.R.Puram– Hoskote road) and the existing, projected and modified LoS for this road remains at D.

The subject is placed before the Authority for discussion and further decision.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Authentic document with regard to ROW. b) Compliance on the E.C issued earlier in juxta position. c) Revised specific social commitment plan with activity, budget and time frame.

9. Residential Apartment at Sy.no.352/1 P, 352/3 P, 352/4 P, 352/8 P, 354/1, 354/2, 355, 356/1, 356/2, 356/3, 356/4 A, 356/4 B, 356/5, 356/6, 357/4 P, 357/5, 357/8, 358/1, 358/2, 358/3, 358/4 P, 359 P, 360/1 P, 360/2 P & 371/2 P, Begur village, Begur Hobli, Bangalore South Taluk, Bangalore District by M/s. Annabel Builders & Developers Pvt. Ltd. (SEIAA 134 CON 2012)

It is a proposal for modification and expansion proposal of residential apartment Project of Basement + Ground + 19 Upper Floors on an area of 1,08,535.78 Sq.m and with the total built up area of 3,36,729.39 Sq.m. The total water requirement is 1298 KLD and the investment is of Rs.44 crores. The total parking provided is for 2,125 cars.

Page 32: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

32

 

M/s. Annabel Builders & Developers Pvt. Ltd., have applied for Environmental Clearance (EC) from SEIAA for their modification & expansion of residential apartment project at Survey Nos: 352/1 P, 352/3 P, 352/4 P, 352/8 P, 354/1, 354/2, 355, 356/1, 356/2, 356/3, 356/4 A, 356/4 B, 356/5, 356/6, 357/4 P, 357/5, 357/8, 358/1, 358/2, 358/3, 358/4 P, 359 P, 360/1 P, 360/2 P & 371/2 P, Begur village, Begur Hobli, Bangalore South Taluk, Bangalore District., under 8(a) of Schedule of EIA Notification, 2006 under category-B. Project comes under BBMP.

The proponent had obtained EC from SEIAA vide letter No. SEIAA 203 CON 2008 dated: 21.11.2009.

The proponent has now submitted the modification and expansion proposal on 09.07.2012. The proponent has submitted a copy of the acknowledgement and compliance report submitted to Regional Office, MoEF on 26.08.2012 pursuant to OM dated 21.05.2012 of MoEF, GoI. The comparative statement of the salient features of the earlier proposal and revised proposal is given in the table below:

Features Unit EC obtained on

21.11.2009 Revised Proposal

Remarks

Type of Development Residential No change - Project Cost Rs.

Crores. 536 264 -

Plot Area Sqm 1,11,287.62 No change - Gross Built Up Area Sqm 3,05,069,19 3,36,729.39 Additional BUA of

31,660.2 Sqm Landscape area Sqm 36,725 (33%) 38,901.39

(35.83%) Additional 2176.39 Sqm. (2.83 %)

Building Floors 2 blocks with B+G+19UF & 5 Blocks with B+G+18UF.

All the 7 blocks with B+G+19UF.

Change of floors.

Dwelling units # 1975 1922 Reduced by 53 flats Height of the Building

m - 59.875 -

Road Width(RoW) m - 24 - Distance to the nearest Fire Station

km - 2 -

Water requirement KLD 1334 1298 Reduced by 36 KLD Source of water BWSSB No change NOC obtained on

10.03.2008. Wastewater generation

KLD 1067 1038 -

STP capacity KLD 1300 1300 No change Sludge generated Kg/day - 480 - Solid Waste Kg/day 3950 3844 Power requirement MVA 12 12 - Power Source BESCOM BESCOM - Backup power(DG sets)

KVA 6 X 1010 & 1 X 500

6X1010 & 4X 500

-

Page 33: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

33

 

Parking facilities PCU 2345 2125 -

The subject was discussed in the SEAC meeting held on 24th & 25th August 2012. The proponent and environmental consultant present explained the project. The Committee noted that the project complies with the O.M. dated 07.02.2012 regarding high rise building issued by MoEF, GoI. The proponent informed that the Begur Lake is 4-5 km away from the project site.

The proponent informed that the project site is located at Begur Village and the site can be approached from Hosur Road (2.7 km) and Bannerghatta road (2.8 km). The existing, projected and modified LoS of Begur Main road is A-B-C (road towards Hosur road). The same for Hulimavu Main road is A-B-D (road towards Bannerghatta road). The existing, projected and modified LoS of Bannerghatta road is C-D-F (road towards Dairy Circle) and C-C-E (road towards Bannerghatta). The existing, projected and modified LoS of Hosur road is C-C-F (road towards Silk Board Junction) and C-C-E (road towards Hosur). The proponent informed that in terms of civil structure 80 % of the work is completed in the portion for which environmental clearance has been issued earlier.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue

of environmental clearance. The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Authentic document with regard to ROW. b) Compliance on the E.C issued earlier in juxtaposition. c) Revised specific social commitment plan with activity, budget and time frame, if any in

addition to what has been committed earlier.

10. Residential Villas at Sy.no.118/1,118/2,119,121/24,121/25,121/26,121/36,122/1,122/2,

123/1, 123/2,123/3,124,125/1,125/2,125/3,125/4,125/5,126/1,126/2,127/1,127/2, 127/3, 127/4, 128/1, 128/2, Hebbagodi Village, Attibele Hobli, Electronic City Post, Anekal Taluk, Bangalore Rural District by M/s. India Build Realty Pvt. Ltd. (SEIAA 137 CON 2012)

It is a proposal for construction of Residential Villas project of total 272 Villas consist of 1) Villa:- 153 with Ground + 2 Floors, 2) Row House:- 47 with Ground + 2 Floors, 3) Town Houses:- 72 with Ground + 3 Floors, 4) Club house:- Ground + 2 Floors on an area of 1,03,432.14 Sq.m (After area left for road widening of 215 Sqm, the Net Plot Area is 1,03,217.14 Sqm),and with the total built up area of 74,304.24 Sq.m. The total water requirement is 244 KLD and the investment is of Rs. 102.54 crores. The total parking provided is for 661 cars.

M/s. India Build Realty Private Limited have applied for Environmental Clearance (EC) from SEIAA for their new proposed villa project at Survey Nos. 118/1,118/2,119,121/24,121/25,121/26,121/36,122/1,122/2,123/1,123/2,123/3,124,125/1,125/2,125/3,125/4,125/5,126/1,126/2,127/1,127/2,127/3,127/4,128/1,128/2 of Hebbagodi Village, Attibele Hobli, Electronic city post, Anekal Taluk, Bangalore Rural under 8(a) of Schedule of EIA

Page 34: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

34

 

Notification, 2006 under category-B. Total project cost is Rs. 102.54 Crores. Project comes under BBMP limits.

Project Details: Land: Total plot area: 1,03,432.14 Sqm; Total built up area: 74,304.24 Sqm. Project consists of 153 villas with Ground & 2 Upper Floors + 47 Row Houses with Ground & 2 Upper Floors + 72 Town Houses with Ground & 3 Upper Floors and Club House with Ground & 2 Upper Floors ; Landscape area: 47,299.43Sqm (45.71% of plot area). Water Requirement: Total water requirement is 244 KLD; Fresh water requirement: 190 KLD, sourced from Hebbagodi Grama Panchyath. Excavated Earth: Total Quantity of excavated earth: 29,500 Cum; backfilling quantity: 18,500 Cum; landscaping quantity: 11,000 Cum. Sewage: Total quantity generated: 196 KLD, treated in proposed STP of design capacity 225 KLD; Municipal Solid Waste: Total generated: 719 kg/day; Organic waste: 431 kg/day treated in organic convertor and product used as manure. Inorganic waste: 288 kg/day will be sent for recycling. Power: Total Requirement: 2825KVA from BESCOM; Backup Power: DG sets of 3X500 KVA & 3X625KVA; Parking: 661 Numbers.

Project surrounding details: Bannerughatta National Park - 20 km. Water bodies: Hebbagodi Lake adjacent to the Project Site, Veerasandrakere Lake- 0.7 Km, Kammasandra Lake -1.5 Km. Other details: Rain Water Harvesting is proposed.

The subject was discussed in the SEAC meeting held on 25th August 2012. The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 12 m & 14.95 m and the RoW of the existing road in front of the project site is 9 m & proposed to widen for 12 m. The fire station is 1.5 km away from the project site. The proponent informed that the Hebbakodi Lake which is fence is abutting on the downstream side of the project and they have left 30 m wide buffer. There is no UGD facility at present and he excess treated water will follow to the Lake during the rainy season. Solar panels are proposed for each villa. The proponent committed and submitted an undertaking to spend Rs. 10.3 Lakhs as a part of his Social commitment plan toward environmental cause. The project site is located on Veerasandra Gollahalli Main road which is approach road to the project site. The project site is well connected to Bangalore-Hosur road. The existing, projected and modified LoS of Veerasandra Gollahalli Main road is A-C-B. The same for Bangalore-Hosur road is B-D-B (road towards Hosure) and B-C-B (road towards Bangalore). The committee suggested to the proponent to explore the possibility of creating an artificial water pond within the project site premises.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority observed that it is proposed to get the water supply from Hebbagodi village panchayath. Therefore a critical review of availability of water is needed. The Authority also observed that the project site is abutting to Hebbagodi lake.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Details on present average per capita supply of water from the panchayath.

b) Alternate source of water in case of shortage of supply from the panchayath.

Page 35: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

35

 

c) Clearance from the Central Ground Water Authority/competent Authority to abstract ground water.

d) Plan to prevent possible pollution of the Hebbagodi lake including formation of artificial water pools in the project site.

e) Commitment to provide appropriate treatment facility for supply of potable water.

f) Revised specific social commitment plan with activity, budget and time frame.

11. Proposed Mixed Use (Office & Hotel) Development at Plot No. 82-82-35, Binnamangala

Village, K. R. Puram Hobli, Bangalore East Taluk, Bangalore. by M/s. Mantri Cornerstone Holdings Pvt. Ltd. (SEIAA 162 CON 2011)

M/s. Mantri Cornerstone Holdings Pvt. Ltd., have applied for EC from SEIAA for their new proposed mixed use (office & hotel) project at Plot No. 82-82-35, Binnamangala Village, K. R. Puram Hobli, Bangalore East Taluk, Bangalore under Schedule No 8(a) of EIA Notification, 2006. Total project cost: Rs. 123.84 Crores.

Project Details: Land: Total plot area: 31,034.54 Sqm; Total built up area: 1,74,426 Sqm; The project consists of 2 office blocks and hotel block. Office block (1) consists of 3B+G+14UF, office block (2) consists of 3B+G+15UF and hotel block consist of 244 Nos of rooms with 3B+G+17UF; Landscape area: 9412.65 Sqm (30.32%). Water Requirement: Total water requirement is 960 KLD. Source: BWSSB & tanker supply; Soil: Total excavated soil: 1,80,000 Cum; Backfilling Quantity: 10,000 cum; Balance: 1,70,000 will be disposed off in the vacant land (Municipal No. 5 7 5/1, 80 Ft Road, Koramangala, Bangalore which belongs to M/s. Mantri Developers (P) Ltd. the vacant land measures about 9,646.23 Sqm); Sewage: Total quantity generated: 530 KLD treated in proposed 3 STP of design capacity of 2 X 200 KLD and 1 X 130 KLD; Solid waste: Total generated: 1550 Kg/day; organic waste will be treated in organic converter and product used as manure. Inorganic waste will be sent for recycling. Power Requirement: Total Requirement: 7847 KVA from BESCOM; Power Backup: 2 X 1250 KVA, 3 X 1010 KVA and 5 X 1500 KVA DG sets; Parking: 2173 Numbers.

Project surrounding: Bellandur Tank: 2 Km; Venkatapura Kere: 5 Km; Chinnagara Kere: 4 Km; Kaikondanahalli Kere: 5 Km; Other details: Rain Water Harvesting proposed. Storm Water Management prepared. Proposed ToRs submitted.

The subject was placed in the 76th SEAC meeting held on 11.11.2011 and the proponent and environmental consultant present explained the proposed ToRs. After deliberation, the Committee decided to issue the following additional ToRs along with model ToRs for preparation of EIA by the proponent:

1. Address management of nearby lakes and nallahs if any.

The proponent has submitted the EIA on 18.02.2012 with response to the ToRs issued on 30.11.2011.

The proponent and environmental consultant present explained the EIA. The proponent informed that height of the building is 64.75 m for Block-1, 68.95 m for Block -2 and 68 m for Hotel Block. The RoW of the existing road in front of the project site is 24 m. The committee observed that the project does not comply with the provisions of the O.M. dated 07.02.2012 on high rise buildings and decided to give 30 days’ time to the project proponent to submit revised

Page 36: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

36

 

proposal (if he is willing, otherwise the proposal can be recommended to SEIAA for closure) in Form 1 & 1A.

The proponent has submitted the revised proposal in Form-1 and 1A the on 11.05.2012 in response to this office letter dated: 18.04.2012. The salient feature of the old and proposed proposal is given in the table below:

Sl. No.

Particulars Details of Old proposal Details of revised proposal.

1 Plot area 31,034.54 Sqm; No change. 2 Project Cost 123.84 Crores. No change. 3

4 Total built up area

1,74,426 Sqm 1,03,280.09 Sqm

5 Green belt area 9412.65 Sqm (30.32 % of plot

area) No change

6

Maximum number of levels

Office block (1) consists of 3B+G+14UF, Office Block (2) consists of 3B+G+15UF and hotel block consist of 244 Nos. of rooms with 3B+G+17UF;

Office block -1: 3B+G+13UF Office block -2: 3B+G+13UF Hotel block: 3B+G+16UF

7 height of the building

Office block -1: 64.75m Office block -2: 68.95m Hotel block: 68 m

Office block -1: 60.00m Office block -2: 60.00m Hotel block: 60.00m

8 Road Width 18.0 m No change.

9 No. of dwelling units

244 247

10 Nearest fire station

11 Parking facilities

2173 Numbers.

12

Total Water requirement

Office block -1: 405 KLD Office block -2: 215 KLD Hotel block: 340 KLD

Office block -1: 85 KLD Office block -2: 135 KLD Hotel block: 225 KLD

13 Use of treated water

Office block -1: 180 KLD Office block -2: 120 KLD Hotel block: 190 KLD

13

Wastewater generation @ 80% of consumption

Total quantity generated: 530 KLD

Office block -1: 120 KLD Office block -2: 185 KLD Hotel block: 200 KLD

14 Sources of water

BWSSB and tankers BWSSB and tankers

15

Sewage treatment plant and technology adopted

3 STP of design capacity of 2 X 200 KLD and 1 X 130 KLD;

1x200KLD, 1x120 KLD and 1x 180 KLD capacity

Page 37: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

37

 

16 Sludge generated

57.60 Kg/day

17 Power requirement and source

Total Requirement: 7847 KVA from BESCOM;

7200 KW

18

Backup power Power Backup: 2 X 1250 KVA, 3 X 1010 KVA and 5 X 1500 KVA DG sets;

Office block -1: 3x1010 KVA DG sets; Office block -2: 2x1500 and 2x1010 KVA DG sets; Hotel block: 2x1250 and 1x1010 KVA DG sets;

19

Solid waste disposal

Total generated: 1550 Kg/day; organic waste will be treated in organic converter and product used as manure. Inorganic waste will be sent for recycling.

Total generated: 1450 Kg/day; organic waste of 360.50 kg/day will be treated in organic converter and product used as manure. Inorganic waste will be sent for recycling.

20

Excavated Earth Disposal

Total excavated soil: 1,80,000 Cum; Backfilling Quantity: 10,000 cum; Balance: 1,70,000 will be disposed off in the vacant land (Municipal No. 5 7 5/1, 80 Ft Road, Koramangala, Bangalore which belongs to M/s. Mantri Developers (P) Ltd. the vacant land measures about 9,646.23 Sqm);

No change

The subject was placed in the 84th SEAC meeting held on 22/23.06.2012 and the proponent and environmental consultant were present explained the project. The height of all the three buildings is 60 m each and the RoW is 24.8 m in front of the project site (80 ft. wide HAL 2nd stage road). The nearest fire station: 4.8 km away from the project site. The proponent informed that the earlier land use was agricultural and they have obtained land conversion. The proponent informed that the present proposal is for total built up area of 1,70,789.28 Sqm. The Committee observed that the built up area shown in the revised Form 1 & 1A is 1,03,280.09 Sqm and hence requested the proponent to submit correct Form 1 &1A showing built up area of 1,70,789.28 Sqm as presented before the Committee.

After deliberation, the Committee decided to issue the model ToRs for the preparation of EIA by the proponent after obtaining corrected Form 1 & 1A.

The proponent has submitted the EIA on 06.08.2012 with response to the ToRs issued on 11.07.2012.

Meanwhile the pp has approached High Court vide W.P. No. 22107/2012 for withdrawal of the O.M dated 07.02.2012 issued by MoEF, GoI and letter dated 18.04.2012 issued by SEAC.

The proponent and environmental consultant were present in the meeting. The Committee noted that the project proponent has filed W.P. No. 22107/2012 (GM-RES) before the Hon’ble

Page 38: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

38

 

High Court of Karnataka with SEIAA as Respondent -1 and MoEF, GoI as Respondent-2 and praying the quashing of O.M dated 07.02.2012 regarding guidelines for high rise building issued by MoEF, GoI and staying of the operation of the endorsement dated 18.04.2012 issued by the Secretary, SEAC to the proponent. In the endorsement dated 18.04.2012, the SEAC has requested the proponent to submit revised proposal in Form-1 & 1A in compliance to the said O.M failing which the proposal will be recommended to SEIAA for closure at the proponents risk since the proposal does not comply with the guidelines of the said O.M.

The Hon’ble High Court of Karnataka vide order dated 03.07.2012 has issued notice to SEIAA and the Head of Legal Cell, DFEE has vide order No. FEE 27 EAA 2012 dated 19.07.2012 has authorized the Government Advocate to verify the writ & the stay petition and appear before the Court. The Special Director, DFEE who is also the Secretary, SEAC has been made the Litigation Conducting Officer & Swearing Officer.

In view of the above the Committee decided to defer the subject as the subject is Sub Judice.

The file has been forwarded to the Authority for information and further direction.

The Authority perused the proposal and took note of the decision of the SEAC to defer the subject treating as sub-judice.

The Authority noted that the proponent have now revised the proposal to meet the ROW criteria laid down by the MOEF vide OM dated 7.2.2012. Even though a Writ Petition has been filed by the Proponent in the Hon’ble High Court of Karnataka, questioning the validity of the OM issued by the MOEF, GOI and the letter of the Secretary, SEAC, dated 18.4.2012 directing to revise the proposal so as to suit the ROW criteria, the Hon’ble Court have not issued any interim order.

After discussion, the Authority opined that as the proponent have revised the proposal so

as to suit the ROW criteria in force and there is no direction from the Hon’ble Court, the proposal can be appraised in accordance with EIA notification, 2006.

The Authority therefore decided to send the proposal back to SEAC for appraisal and

sending suitable recommendation deemed fit based on its merit.

12. Chaithanya Health Park at Sy.Nos. 28/1, 28/2, 29/1 and 29/2, Pattandur Village, K.R.Puram Hobli, Bangalore East Taluk by M/s Chaithanya Projects Pvt. Ltd. (SEIAA 66 CON 2012)

It is a proposal for construction of Cultural 772 bedded Hospital comprising Tower 1 & Tower 2 with Basement + Ground floor + 10 Upper floors, Tower C with Basement + Ground floor + 8 Upper floors, Spine with Basement + Ground floor + 10 Upper floors and MLCP with 2 Basement + Ground + 11 Upper floors on an area of 38,242.47 Sqm (Net plot area is 36,451.47 Sq.m, after left for road widening of 1791 Sqm)and with the total built up area of 1,41,953.10 Sq.m. The total water requirement is 480 KLD and the investment is of Rs. 460 crores. Total parking provided is for 1029 cars, 4 ambulance and 6 mini buses.

M/s. Chaithanya Projects Pvt. Ltd., have applied for Environmental Clearance (EC) from SEIAA for their new proposed health care center (hospital) project called "Chaithanya Health Park" at Survey Nos: 28/1, 28/2, 29/1, 29/2, Pattandur Village, K. R. Puram Hobli, Bangalore

Page 39: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

39

 

East Taluk, Bangalore, under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 460 Crores. Project comes under Bangalore Municipality limits;

Project Details: Land: Total plot area: 38,242.47 Sqm; Net plot area: 36,451.47 Sqm;

Total built up area: 1,41,953.10 Sqm. Project consists of 772 bedded health park with 2B+G+10UF. Landscape area: 14717.5 Sqm (10.36 % of plot area). Water Requirement: Total water requirement is 480 KLD; sourced from BWS&SB Excavated Earth: Total Quantity of excavated earth: 94,090 Cum; backfilling quantity: 28,227 Cum; landscaping quantity: 8320 Cum: Top soil used for terrace garden base: 45,322 Cum; Balance quantity 12221 Cum will be carted out to neighboring land belonging to the proponent. Sewage: Total quantity generated: KLD, treated in proposed STP of design capacity 400 KLD; Sludge generated: 20.8 kg/day used as manure. Municipal Solid Waste: Total generated: 1035 kg/day; Organic waste: 620 kg/day will be composted at the project site and product used as manure. Inorganic waste: 415 kg/day will be handed over to the BBMP door to door collection facility sent for recycling. Power: Total Requirement: 6.3 MVA from BESCOM; Backup Power: DG sets of 4 X 2000 KVA and 2 X 1000 KVA. Parking: 1029 cars, 4 ambulances and 6 mini buses.

Other details: Rain Water Harvesting is proposed. NOC from BWS&SB not submitted. The subject was discussed in the SEAC meeting held on 25th & 26th May 2012. The

proponent and the consultant present in the meeting explained the project. The proponent informed that the height of the proposed building is 44.5 m; the RoW of the existing road in front of the building is 28.5 m. The nearest Fire Station is at a distance of 4.8 km. the landscape plan works out to 38.48 % on natural earth. The nearby lake is Varthuru lake is 7 km away. The level difference in the project site is 6.26 m. There is no UGD at present in the project. They have applied for NOC from BWS&SB for water supply. The Committee requested the proponent to ensure biomedical waste rules are strictly followed in the project. The Committee also advised the proponent to explore the possibility of creating their own incineration plant.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of

environmental clearance after obtaining the following information from the proponent.

1. NOC from BWS&SB for water supply. 2. Traffic management studies for projected and modified LoS. 3. Detailed calculation for cooling water. 4. Enlist primary health centers proposed with total cost and infrastructures facilities

proposed for poor patients as a part of social commitment plan.

The proponent has submitted the information vide letter dated 16.08.2012. The subject is placed before the Authority for discussion and further decision.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) NOC from BWSSB for supply of water. b) Location of STP and facility for handling MSW duly marking on the lay out plan. c) Plan for safe disposal of liquid and solid Biomedical Waste in accordance with Bio

Medical Waste (Management & Handling) Rules, 1998. d) Details of trees to be removed and status of clearance thereof.

Page 40: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

40

 

13. "Elegant Altis," Proposed Residential Apartments at Sy.No. 115/2 (old Sy.No 115),

Byrathi Village, Bidarahalli Hobli, Bangalore East Taluk, Bangalore by M/s Elegant Properties (SEIAA 112 CON 2012)

It is a proposal for construction of Residential Apartment of 208 Units comprising two towers spread over 4 Blocks with Basement floor + Ground floor + 13 Upper floors on an area of 8,082.56 Sq.m and with the total built up area of 35,345.74 Sq.m. The total water requirement is 150 KLD and the investment is of Rs. 40 crores. The total parking provided is for 268cars.

M/s Elegant Properties have applied for Environmental Clearance (EC) from SEIAA for their new proposed Residential Apartment “Elegant Altis” project at Survey Nos: 115/2 (old Sy.No 115), Byrathi Village, Bidarahalli Hobli, Bangalore East Taluk, Bangalore, under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 40 Crores. Project comes under BBMP; Land is classified as residential as per CDP - 2015

Project Details: Land: Total plot area: 8082.56 Sqm (Vacant land); Total built up area: - 35,345.74 Sqm. The Project consists of 2 Towers spread over 4 Blocks with 208 Residential Units with Basement Floor + Ground Floor & 13 Upper Floors. Landscape area: 3123.17 Sqm (38.64% of plot area). Water Requirement: Total water requirement is 150 KLD, sourced from BWSSB. Excavated Earth: Total Quantity of excavated earth: 8,600 Cum; backfilling quantity: 2,000 Cum; landscaping quantity: 2100 Cum; Road leveling/formation quantity: 4500 Cum; Sewage: Total quantity generated: -120 KLD, treated in proposed STP of design capacity 135 KLD; Sludge generated: 8 kg/day used as manure. Municipal Solid Waste: Total generated: 416 kg/day; Organic waste: 249.6 kg/day treated in organic convertor and product used as manure. Inorganic waste: 166.4 kg/day will be sent for recycling. Power: Total Requirement: 1000KVA from BESCOM; Backup Power: DG sets of 2X500 KVA; Parking: 268 Numbers.

Project surrounding details: BIAL – 28km, Bannerghatta National Park – 40km,

Doddagubbi Lake – 2.0km, Chokkondahalli Lake – 1.0km, Nagawara Lake – 5.4km, Rachenahalli Lake – 4km. Other details: Rain Water Harvesting is proposed.

The subject was discussed in the SEAC meeting held on 21st July 2012. The proponent

and environmental consultant present explained the project. The proponent informed that the height of the building is 43.60 m and the RoW of the existing road in front of the project site is 22.50 m. The level difference in the project site is 2.38 m. The project is well connected to Hennur – Bagalur main road which connects ORR on one side and Bagalur on the other side. The existing, projected and modified LoS of Hennur – Bagalur main road is B-C-B. NOC from BWSSB obtained on 28.05.2012.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the Social commitment plan on letterhead for Rs. 5 Lakhs, as committed by the proponent during the meeting.

The proponent has submitted the information vide letter dated 07.09.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

Page 41: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

41

 

a) Authentic document with regard to ROW with latest photographs of the site. b) NOC from the BWSSB for supply of water. c) Details of Excavated earth and plan for safe disposal of excess earth with particulars of

land proposed to be disposed and its present land use. d) Location of STP and MSW facilities duly marking it on layout plan. e) Status of UGD and plan for disposal of excess treated water in the absence of UGD. f) Revised specific social commitment plan with activity, budget and time frame.

14. Proposed Residential Development at Sy. No 120/2, 121/2, 121/3, 120/1, 120/3, Doddanekundi village, K.R Puram Hobli, Bangalore South Taluk, Bangalore by M/s. Sobha Developers Ltd. (SEIAA 114 CON 2012)

It is a proposal for construction of residential development of 316 units with 2 Basement + Ground + 7 upper floors on an area of 22,763.56 Sq.m and with the total built up area of 73,417.57 Sq.m. The total water requirement is 284.4 KLD and the investment is of Rs. 188.56 crores. The total parking provided is for 506 cars.

M/s. Sobha Developers Ltd., have applied for Environmental Clearance (EC) from SEIAA for their new proposed residential development project at Survey Nos: 120/2, 121/2, 121/3, 120/1, 120/3, Doddanekundi Village, K.R. Puram Hobli, Bangalore South Taluk, Bangalore, under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 188.56 Crores. Project comes under BBMP.

Project Details: Land: Total plot area: 22,763.56 Sqm; Total built up area: 73,417.57 Sqm. Project consists of 316 flats with 2B+G+7UF. Landscape area: 7511.97 Sqm (33% of plot area). Water Requirement: Total water requirement is 284.4 KLD; sourced from BWS&SB. Sewage: Total quantity generated: 255.96 KLD, treated in proposed STP of design capacity 300 KLD; Sludge generated: 60 kg/day used as manure. Municipal Solid Waste: Total generated: 853.2 kg/day; Organic waste: 511.92 kg/day treated in organic convertor and product used as manure. Inorganic waste: 341.28 kg/day will be sent for recycling. Power: Total Requirement: 2978KVA from BESCOM; Backup Power: DG sets of 4 X 380 KVA and 2 X 250 KVA; Parking: 506 Numbers.

Project surrounding details: Dodanekundi Lake: 4.1 km; Varthur Lake: 5.6 km; KR Puram Lake: 8.1 km; Haralur Lake: 10.3 km; Bellandur Lake: 8.3 km.

Other details: Rain Water Harvesting is proposed. Land records and NOC from BWS&SB not submitted.

The subject was discussed in the SEAC meeting held on 21st July 2012. The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 26.87 m and the RoW of the existing road in front of the project site is 15.87 m (Yemalur Road) and 32.5 m (Marthalli road). The fire station is 5 km away from the project site. The project site is located on the Yemlur road which connects Yemlur on one side and Varthur Main road on the other side. Varthur Main road connects Domlur on one side and Marthalli on the other side. The existing, projected and modified LoS of Varthur Main road is E-F-F (road towards Varthur) and D-F-F (road towards Domlur). The existing, projected and modified LoS of Yemlur road is C-C-C (road towards Varthru Main road) and B-C-C (road towards Yemlur).

Page 42: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

42

 

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent.

1. Land records. 2. NOC from BWS&SB for water supply. 3. Details of excavated earth and its disposal. 4. Social commitment plan on letterhead for Rs. 18 Lakhs, as committed by the

proponent during the meeting.

The proponent has submitted information vide letter dated 27.08.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Authentic document with regard to ROW. b) NOC from BWSSB for supply of water. c) Details of Excavated earth and plan for safe disposal of excess earth with

particulars of land proposed to be disposed and its present land use. d) Status of UGD and plan for disposal of excess treated water in the absence of UGD e) Revised specific social commitment plan with activity, budget and time frame.

15. Qube, Commercial (Office) Building project at Sy.No.133/2, Boganahalli Village,

Varthur Hobli, Bangalore by M/s Sai Srushti Infrastructure Pvt. Ltd. (SEIAA 128 CON 2012)

It is a proposal for construction of Commercial Building with Lower Basement + Upper Basement floor + Ground floor + 8 Upper floors on an area of 8,127 Sq.m and with the total built up area of 40,177.31 Sq.m. The total water requirement is 142 KLD and the investment is of Rs. 83.43 crores. The total parking provided is for 482 cars.

M/s. Sai Srushti Infrastructure Private Limited have applied for Environmental Clearance (EC) from SEIAA for their new proposed “Qube” Commercial (Office) Building project at Survey No. 133/2, Boganahalli Village, Varthur Hobli, Bangalore under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 83.43 Crores. The project is coming up in the Commercial zone of CDP.

Project Details: Land: Total plot area: 8,127 Sqm; Total built up area: 40,177.31Sqm.

Project consists of Lower Basement + Upper Basement + Ground Floor & 8 Upper Floors. Landscape area: 1,698 Sqm (23.44% of plot area). Water Requirement: Total water requirement is 142 KLD; sourced from BWSSB. Excavated Earth: Total Quantity of excavated earth: 33,000 Cum; backfilling quantity: 9000 Cum; landscaping quantity: 2000 Cum; 3,000 cum will be hardscaping and formation activities within the project site and excess excavated earth of 19,000 Cum will be disposed to brick manufacturers. Sewage: Total quantity generated: 114 KLD, treated in proposed STP of design capacity 125 KLD; Sludge generated: 45kg/day used as manure. Municipal Solid Waste: Total generated: 631 kg/day; Organic waste: 379 kg/day treated in organic convertor and product used as manure. Inorganic waste: 252 kg/day will be sent for recycling. Power: Total Requirement: 6000 KVA from BESCOM; Backup Power: DG sets of 4x2000KVA; Parking: 482 Numbers.

Page 43: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

43

 

Project surrounding details: Bannerghatta National Park – 21 km, Water Bodies:

Devarabeesanahalli Lake – 1.20 km, Boganahalli Lake – 1.0 km, Narasimha Shashtri Lake –1.0 km, Bellandur Lake - 2.5 km, Varthur Lake – 4.5 km.

Other details: Rain Water Harvesting is proposed. The subject was discussed in the SEAC meeting held on 25th August 2012. The proponent

and environmental consultant present explained the project. The proponent informed that the height of the building is 35 m and the RoW of the existing road in front of the project site is 18 m. The fire station is 4.9 km away from the project site. The proponent committed and submitted an undertaking to spend Rs. 8 Lakhs as a part of his Social commitment plan toward environmental cause. The project site is connected to Boganahalli Main road, ORR and Sarjapur road. The existing, projected and modified LoS these three roads are A-C-B, C-E-C and C-E-C respectively. The committee suggested to the proponent to explore the possibility of enhancement of landscape area on natural earth.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining NOC from BWS&SB for water supply from the proponent.

The proponent has submitted information vide letter dated 27.08.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Location of STP and facility for handling MSW duly marking on the lay out plan. b) Plan to increase the green belt to at least to 33%. c) Revised specific social commitment plan with activity, budget and time frame.

16. "Soul Space Arista", Residential Apartment & Commercial Building at Outer Ring

Road, Sy.no.37, 38/2, 38/3, 38/4, Doddanekkundi village, Bangalore East Taluk, Bangalore Urban District by M/s Soul Space Projects Limited. (SEIAA 132 CON 2012)

It is a proposal for construction of mixed development consisting commercial space and Residential Apartment of 135 Units in with 2 Basement floors + Ground floor + 8 Upper floors (Residential Block) and IT Space with 2 Basement floors + Ground floor + 6 Upper floorson an area of 11,891.96 Sq.m and the total built up area is 50,929 (Residential Building 36,133 +

Commercial Building 14,796) Sq.m. The total water requirement is 139 KLD and the investment is of Rs. 57.50 crores. The total parking provided is for 356 cars.

M/s. Soul Space Project Ltd., have applied for Environmental Clearance (EC) from SEIAA for their new proposed Mixed Development consisting of IT Space & Residential “Soul Space Arista” project The project consists of 135 Units & 1 Club House at Survey Nos: 37,38/2, 38/3, 38/4, Doddanekkundi Village, K.R. Puram Hobli (now Varthur Hobli), Bangalore East Bangalore Urban Bangalore under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs.57.50 Crores. Project comes under BBMP; Land conversion obtained from DC.

Page 44: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

44

 

Project Details: Land: Total plot area: 11,891.96 Sqm; Total built up area: 50,929.69 Sqm.

Project consists of 135 flats with 2 B + G + 8 Upper Floors (Residential Block) 2 B + G+ 6 Upper Floors. (IT Space). Landscape area: 4,080.93 Sqm (33.8% of plot area). Water Requirement: Total water requirement is 140 KLD; Fresh water requirement: 95 KLD & Recycled water – 45 KLD sourced from BWSSB (NOC dated 24.10.2008 submitted). Excavated Earth: Total Quantity of excavated earth: 43000 Cum; backfilling quantity: 6000 Cum; landscaping quantity: 8000 Cum; Balance earth of 29,000 Cum will be taken by our contractor for backfilling in an alternate site. Sewage: Total quantity generated: 78 KLD, treated in proposed STP of design capacity 80 KLD; Sludge generated: 12 kg/day used as manure. Municipal Solid Waste: Total generated 556 kg/day; Organic waste: 223 kg/day treated in organic convertor and product used as manure. Inorganic waste: 333 kg/day will be sent for recycling. Power: Total Requirement: 1934 KVA (3149.2 KVA) from BESCOM; Backup Power: DG sets of: 1 X 1000 KVA & 1X 250 KVA (Commercial) 1 X 380 KVA & 1 X 160 KVA (Residential) Parking: 356 Numbers.

Project surrounding details: Bannerghatta National Park – 25 km Doddnakundi Lake – 2km.

Mahadevpura Lake-3km, Kakadasanapura Lake: 4 km; Other details: Rain Water Harvesting is proposed.

The subject was discussed in the SEAC meeting held on 24th & 25th August 2012. The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 26.95 m for commercial building and 26.90 m for residential building. The RoW of the existing road in front of the project site is 51 m (ORR). The fire station is 4 km away from the project site. The proponent committed and submitted an undertaking to spend Rs. 6 Lakhs as a part of his Social commitment plan toward environmental cause.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent:

1. Dated photographs of the project site. 2. Explore possibility to enhance the landscape on natural earth. 3. Dated peak hour traffic density photographs. 4. MoU for disposal of excess excavated earth

The proponent has submitted information vide letter dated 27.08.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Authentic document with regard to ROW. b) Details of Excavated earth and plan for safe disposal of excess earth with particulars of

land proposed to be disposed and its present land use. c) Status of UGD and plan for disposal of excess treated water in the absence of UGD d) Revised specific social commitment plan with activity, budget and time frame.

Page 45: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

45

 

17. Expansion of "Shriram Smrithi", Residential Apartment, Sy.No. 327/1, 327/2, 328/2, 342, 343/1, 344, 355, 346/1, 346/2, 346/3 & 346/4, Bidaraguppa Village, Sarjapur Hobli,Anekal Taluk, Bangalore by M/s. Shriram Properties Pvt. Ltd (SEIAA 122 CON 2011)

It is a proposal for expansion of Residential Apartment Building in 360 Units to 1,288 Units with 5 Blocks: Block-A1 with Stilt + Ground + 3 Upper floors; Block- A2, B & C with Stilt + Ground +7 Upper floors and a club house (Block D) with Stilt + Ground floor + 2 Upper floors on an area of 84,121.27 Sq.m and with the total built up area of 1,82,629.85 Sq.m. The total water requirement is 875 KLD and the investment is of Rs. 76.29 crores. The total parking provided is for 1,459 cars.

M/s. Shriram Properties Pvt. Ltd., have applied for EC from SEIAA for expansion of their residential apartment building “Shriram Smrithi” at Sy. No. 327/1, 327/2, 328/2, 342, 343/1, 344, 345, 346/1, 346/1, 346/2, 346/3 & 346/4 of Bidaraguppe Village, Sarjapur Hobli, Anekal Taluk, Bangalore under Sl. No 8(b) of schedule of EIA Notification, 2006. Total project cost: Rs. 76.29 Crores. Project comes under BBMP.

The project proponent has obtained EC from SEIAA vide letter No. SEIAA 68 CON 2009 dated: 04.06.2010. Salient features of the project (Existing and Proposed) are shown below:

Sy. No.

Particulars Earlier proposal

(EC obtained)

Expansion proposal (now

applied)

Total project (after expansion)

1 Plot Area 84,121.27 sq. m No Change 84,121.27sq. m Built up area 95,422.3 sq. m. 70,900.95 Sqm 1,66,323.25 sqm

2 Number of units 928 units 360 units 1288 units

3

Building configuration

Stilt + Ground + 3 UF and clubhouse with G+1 UF.

5 Blocks: Block-A1 with S+G+3 UF; Block- A2, B & C with S+G+7 UF and a club house (Block D) with S+G+ 2UF.

Same as expansion proposal.

4 Water requirement

630 KLD 245 KLD 875 KLD

5 STP capacity 525 KLD 725 KLD 725 KLD. 6 Parking provided 928 Cars 531 Cars 1459 Cars

The source of water is Bidaraguppe Grama Panchayath (NOC not submitted) and borewell (NOC obtained from CGWA on 03.06.2011); Landscape area: 31,335.74 Sqm (37.25%); Solid waste management: Total: 2,576 KG/day; organic waste of 1,546 Kg/day will be treated in organic converter and product used as manure. Inorganic waste of 1,030 Kg/day will be sent for recycling; Power Requirement: Total Requirement: 4,419 KW from BESCOM; Power Backup 1 X 225 KVA, 2 X 250 KVA and 2 X 350 KVA DG sets.

Project surrounding: Water Bodies: Bidaraguppe Lake (adjacent) and Mallenahalli Lake – 2 Km. Other details: the proponent has not submitted the compliance to the earlier EC.

The subject was placed in the 75th SEAC meeting held on 14/15.10.2011 and the

proponent present explained the ToRs proposed by him. The proponent informed that a shallow irrigation tank is abutting to the project site at the downstream. The proponent informed that the

Page 46: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

46

 

CGWA letter obtained is for water requirement for pre- expansion only. For the present expansion, the source of water is borewell and village panchayat supply. The Committee requested the proponent to seek CGWA approval if water is required from additional borewells.

After deliberation, the Committee decided to issue the following ToRs along with model

ToRs for preparation of EIA by the proponent.

1. Management plan for protection of the Lake (Pond) during construction and operation phase.

2. Scientific evaluation of the capability of village Panchayat to supply the required quantity of fresh water to the project with alternative sources of water and impact on other competitive users.

3. Plan for disposal excess treated water.

The subject was placed in the 77th SEAC meeting held on 2/3.12.2011 and the subject was deferred since the project proponent has informed orally about his absence to the meeting.

The proponent has submitted the EIA on 30.06.2012 in response to the ToRs issued on 02.11.2011.

The proponent and environmental consultant present explained the EIA before the SEAC meeting held on 20th July 2012. The proponent informed that the height of the building is 32.6 m and the RoW is 18 m in front of the project site. The nearest fire station is 9.1 km away from the project site. The proponent informed that the source of water for the project is borewells and Bidaraguppe Grama Panchayat. The NOC obtained from CGWA on 03.06.2011 is given partly. NOC from Grama Panchayat is obtained. Hydrogeological study of borewells is being prepared and will be submitted. The proponent informed that Harenur Lake is located at a distance of 60 m from the project site and measures have been taken for the protection of the lake. The project is connected to Sarjapur –Attibele road and the existing, projected and modified LoS of this road is B-D-C.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of

environmental clearance after obtaining the following information from the proponent:

1. Scientific assessment of borewell water and Village Panchayat water along with impact on the competitive user’s requirement.

2. Social commitment plan on letterhead for Rs. 7 Lakhs, as committed by the proponent during the meeting.

The proponent has submitted information vide letter dated 05.09.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC. The Authority noted that source water is proposed to be sourced from panchayath.

Assessment of yield of water from the panchayath bore wells is stated to be on assumption. The assessment should be made on actual scientific measurement.

The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

a) Authentic document with regard to ROW. b) Compliance to the conditions of earlier EC in juxta position.

Page 47: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

47

 

c) Yield of the bore wells estimated through actual measurement. d) Details on present average per capita supply of water from the panchayath. e) Alternate source of water in case of shortage of supply from the panchayath. f) Clearance from the Central Ground Water Authority/competent Authority to abstract

ground water. g) Revised specific social commitment plan with activity, budget and time frame.

18. "Marian Park", Residential Apartment at Sy.no.58/3A, 3A1 (P1, P2, P3, P4, P5, P6),

58/3A, 3B, 58/3A, 3A2, 58/3A2, 90/5, 90/6P, 91/1P, 276/1, P1 and P2, Kadri village, Mangalore Taluk, Dakshina Kannada District by M/s Marian Projects Pvt. Ltd. (SEIAA 139 CON 2012)

It is a proposal for construction of of Residential Apartments of 195 units with 5 Basement +Stilt+Ground +14 Upper Floor on an area of 10,481.21 Sq.m and with the total built up area of 44,714 Sq.m. The total water requirement is 169.6 KLD. The total parking provided is for 242 cars and 120 Two wheelers.

M/s. Marian Projects (P) Ltd., have applied for Environmental Clearance (EC) from SEIAA for their new proposed residential project "Marian Park" project at Survey Nos: 58/3A, 3A1 (P1, P2, P3, P4, P5, P6), 58/3A, 3B, 58/3A, 3A2, 58/3A2, 90/5, 90/6P, 91/1P, 276/1P1 and P2, Kadri Village, Mangalore Taluk, Dakshina Kannada District, under 8(a) of Schedule of EIA Notification, 2006 under category-B. Land conversion obtained from DC. The project is located in moderately populated zone as per Master Plan of MCC (CDP).

Project Details: Land: Total plot area: 10,481.21 Sqm; Total built up area: 30,500 Sqm.

Project consists of 195 flats with 5B+Stilt+G+14UF. Landscape area: 3410 Sqm (32.53 % of plot area). The geology of the site area is hard laterite. Water Requirement: Total water requirement is 169.6 KLD; Fresh water requirement: 107.6 KLD, sourced from MCC & 2 open wells. Sewage: Total quantity generated: 126.4 KLD out of which 90.4 KLD will be treated in proposed STP of design capacity 120 KLD and 36 KLD will be discharged to UGD; Sludge generated: 1.8 kg/day used as manure. Municipal Solid Waste: Total generated: 390 kg/day; Organic waste: 195 kg/day treated in organic convertor and product used as manure. Inorganic waste: 156 kg/day will be sent for recycling. Power: Total Requirement: 1500 KVA from MESCOM; Backup Power: DG sets of 2 X 250 KVA; Parking: 242 Cars + 120 two wheelers.

Project surrounding details: Bajpe International Airport: 8.6 kms; Other details: Rain Water Harvesting is proposed. The site is located on Kanyakumari –Panavel Road (NH-17).

The subject was discussed in the SEAC meeting held on 25.08.2012. The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 44.7 m and the RoW of the existing road in front of the project site is 27 m (Kadri Park road). The fire station is 1.5 km away from the project site. The level difference in the project site is 35.99 m. The UGD facility is available. The proponent informed that the project site is located on Kadri Park road, off Kanyakumari Panavel road (NH-66) within the limits of MCC. Widening of NH-66 into 6 lanes is in progress. The existing, projected and modified LoS of Kanyakumari Panavel road is B-B-B (road towards Panavel) and B-A-B (road towards Kanyakumari). The proponent submitted the copy of the NOC dated 24.08.2012 from MCC for

Page 48: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

48

 

supply of water to the project. The proponent also informed that the trees existing on the periphery of the project would be retained.

The proponent informed that he has committed to spend Rs. 6 Lakhs for laying the pipeline for supply of excess treated water from the project to the Kadri Park and also Rs. 4 Lakhs for constructing houses for the underprivileged near Talapadi, Dakshina Kannada which was agreed by the Committee.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the details of excavated earth and its disposal from the proponent.

The proponent has furnished the information vide letter dated 13.09.2012. The Authority perused the proposal and took note of the recommendation of the SEAC. The Authority after discussion, decided to issue Environmental Clearance subject to

submission of the following information:

a) Authentic document with regard to ROW. b) Status of UGD and plan for disposal of excess treated water in the absence of UGD. c) Location of STP and facility for handling MSW duly marking on the lay out plan. d) Revised specific social commitment plan with activity, budget and time frame.

Industry Projects:

1. Establishment of Active Pharmaceutical Ingredients (APIs), Nutraceuticals manufacturing Industry, Plot No. 57, Sompura Industrial Area, Dobaspet, Nelamangala, Bangalore Rural District by M/s Bio-Gen Extracts Pvt. Ltd (SEIAA 29 IND 2011)

It is a project proposal for Establishment of Active Pharmaceutical Ingredients (APIs), Nutraceuticals manufacturing Industry. The total plot area is 4,035.26. The total water requirement is 11,805 LPD . The investment is of Rs. 5.04 Crores.

M/s. Biogen Extracts (P) Ltd., have applied for EC for their new proposed for establishment of Active Pharmaceutical Ingredients (APIs) and Nutraceutical manufacturing industry at Plot No. 57, Sompura Industrial Area (KIADB Notified), Dobaspet, Nelamangala Taluk, Bangalore Rural District under Sl. No. 5 (f) of schedule of EIA Notification, 2006. Total project cost: Rs. 5.04 Crores. This is medium scale industrial unit.

Product manufacture details: Ritodrine Hydrochloride: 300 Kg/annum (API); Pyrimethamine: 6000 Kg/annum (API); Natural Beta Carotene: 6000 Kg/annum (Nutraceuticals) and Lycopene: 3600 Kg/annum (Nutraceuticals).

Project Details: Land: Total plot area: 4,035.26 Sqm; Total built up area: 2,110.02 Sqm (Admin Block (G+2); Production Block (G+1), stores, utility and drum storage); green belt area: 1,350 Sqm (33.45 % of plot area); Water Requirement: Total water requirement is 12.6 KLD sourced from KIADB. Waste water: 6.99 KLD proposed to be sent to authorized CETP; Power Requirement: Total Requirement: 315 KVA from KIADB; Power Backup: 320 KVA DG sets; Solid waste: 15 Kg/day; organic: 9 KG/day; inorganic: 6 Kg/day; Hazardous waste: (a) Process:

Page 49: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

49

 

Pyrimethamine 1st stage: 2370 Kg/annum 2nd Stage: 3159 Kg/annum; Lycopene 1st stage: 3036 Kg/annum; Beta Carotene 1st Stage: 2680.2 Kg/annum. (b) Catalyst: Ritodrine Hydrochloride 1st Step: 25.2; (c) Other: Waste Oil generation from DG sets: 100 L; Residue from solvent recovery: 410.5 Kg.

Project surroundings: Water Bodies: Nidvanda Kere: 1.3 km; Hire Kere: 4.25 Km; Sondilvadi Kere: 3.75 Km; Maldala Kere: 12.5 Km; Billanakote Lake: 1.5 Km; Sabarapolya Lake: 1.6 KM; Hosahalli Kere: 2.5 km; Manne Kere: 3.3 km; Kodihalli Kere: 5.4 km; Chikkannayyane Kere: 7.5 km; Kalalaghatta Kere: 7.2 km; Forests: Mavinakommanahalli Forest: 6.5 Km; Nijagal State Forest: 5 Km; Jakkasandra State Forest: 7 Km; Krishnarajpura Forest: 7.5 Km. Other details: MSDS, Project report, soil investigation report, risk assessment report, KIADB allotment letter, MoU with Pai & Pai Chemical for disposal of liquid hazardous waste and letter of acceptance for disposal of hazardous waste and liquid waste by M/s. Shalini Enterprises submitted.

The subject was placed in the 77th SEAC meeting held on 2/3.12.2011 and the proponent was present explained the project. The proponent informed construction activity is already started and they have applied for CFE. KIADB lease cum sale deed is in possession of the proponent.

After deliberation, the Committee decided to issue the following ToRs along with model ToRs to the proponent for preparation of EIA by an accreditated consultant.

1. Project proponent to ensure that the project site is in Zone-III and IV of T.G Halli Reservoir catchment area.

2. Distance from Kumudvathi River. 3. Chemical products to be verified for hazardous /banned chemical. 4. Ground water variations to be measured. 5. HAZOP and risk assessment study. 6. Layout and monitoring parameter as per fire hydrant and other norms.

The proponent has submitted the EIA on 12.04.2012 in response to the ToRs issued on 21.12.2011.

The subject was placed in the 84th SEAC meeting held on 22/23.06.2012 and the proponent and the consultant were present in the meeting explained the EIA. The Committee observed the following:

The material balance is not matching in respect of various products and VOC is not measured.

Hydrogen explosion due to leakage is not considered. EIA under worst case scenario is not done. Input data in respect of wind direction and dust distribution is not correct. Some of the technologies adopted are old. The proponent was requested to adopt green

technology with latest method.

The proponent informed that the project site is located at the upstream of the T. G Halli reservoir and is at a distance of 27 km approximately. The project site is at a distance of 4.4 km from Kumudvathi River and 26 km from Arkavathi River.

After deliberation, the Committee decided to recall the proponent for presentation after obtaining the following information from him:

1. Revised material balance for all products. 2. Alternative for use of 4 Chloro benzyl cyanide for synthesis of Pyrimethamine.

Page 50: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

50

 

3. Proponent to ensure that the survey numbers of the project area not coming in the Thippagondanahalli Reservoir catchment area as per the notification.

4. Prediction based on the wind rose diagram for all the 3 stacks. 5. VOC base line data. 6. In view of small area of 1 acre, location and layout plan of the reactors, onsite

emergency plans and solvent storage. 7. Commitment for adopting green technology. 8. Social commitment plan for Rs. 2 Lakhs on letterhead, as committed.

The proponent has submitted the above information on 01.08.2012 in response to this office letter dated 03.07.2012.

The proponent and environmental consultant present explained queries raised by the SEAC during the meeting held on 22nd & 23rd June 2012. The proponent informed the Committee that the project site is located at the upstream of the Thippagondanahalli Reservoir and is at a distance of 27 km approximately. The project site is at a distance of 4.4 km and 26 km approximately from Kumdvati River and Arkavathi River respectively. The project site is located 2.2 km away from NH-4 (Bangalore –Pune). The proponent also present model input data for the air emissions with isotherms.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance with a condition that 4-chloro benzyl cyanide should not be used in pyrimethamine synthesis.

The Authority perused the proposal and took note of recommendation of the SEAC.

The Authority noted that the trade effluents are proposed to be sent to authorized CETP.

The Authority observed that reports on the treatment and disposal of trade effluents by the CETP’s is not encouraging. There is no proper Energy Audits, checks and balances to treat effluents by these units. According to the State of Environment Report water sources have been polluted. Traces of these industrial effluents are observed both in the surface water and ground water samples. Therefore serious thinking is necessary as to ensure complete treatment of trade effluents. The Authority also sought to know whether the proposed site attracts the T.G.Halli notification. The Authority felt that in situ treatment of trade effluent is required to be attended.

The Authority therefore decided to get the following information for further consideration

of the proposal: a) Authentic document to establish that the proposed site does not fall within the

restricted area of T.G.Halli Notification. b) Plan for in situ treatment and disposal of trade effluents. c) Commitment to adopt suggestion made by SEAC with regard to avoid use of

4-chloro benzyl cyanide for synthesis of Pyrimethamine and its alternative.

The Authority also decided to invite the proponent to the meeting after submission of the above information.

Page 51: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

51

 

2. Production of Specialty Surfactants, Plot No.61&62, Malur KIADB Industrial Area, Koorandahally Village, Malur, Kolar District by M/s ECOF Industries Private Limited(SEIAA 10 IND 2012)

It is a project proposal for expansion of existing industry. The total plot area is 8036 Sqm. The total water requirement is 75 KLD. The investment is of Rs. 910 Lakhs.

M/s. ECOF Industries Pvt. Ltd., have applied for Environmental Clearance (EC) from SEIAA for their proposed expansion of existing industry at Plot No. 61 & 62, KIADB Industrial Area, Koorandahally Village, Malur Taluk, Kolar District for production of specialty surfactants of capacity 5000 TPA under Sl. No. 5(f) of schedule of EIA Notification, 2006. Total project cost is Rs. 910 Lakhs.

Project Details: Land: overall Land Area: 8036 Sqm (Existing: 4046 Sqm+ Proposed: 3990 Sqm (vacant land) inclusive of green belt – 2812 Sqm); Total built up area: 2,374 Sqm. Water: Total water requirement: 75 KLD sourced from KIADB; Sewage: Total quantity generated: 4 KLD sent to septic tank/soak pit. Liquid effluent will be sent to CETP after pre-treatment. Municipal Solid Waste: Total generated: 100 kg/day; Power: Total Requirement: 436 KVA from BESCOM/KPTCL; Backup Power: DG sets of 1 X 500 KVA. Solid wastes: Ash from boiler- 15 MT/month given to farmers. Other details: Rain Water Harvesting is proposed.

Presently the existing capacity of the industry is manufacturing of Detergent Powder/ Surfactant Powder at 3000MTPA and Scouring Powder at 2000MTPA.

The proposed expansion capacity is as under:

Product Details Proposed expansion Capacity per

Month (in MT) 1. Sugar Esters 360 2. CAPB 50 3. CDEA 25

The raw materials requirement is listed as below:

Raw Material MT/ day Fatty Acid 10 Diethanolamine 10 Dimethylamino propyl amine 5 D M Water 20 Caustic Lye 10 Mono Chloro Acetic Acid 10 Dextrose 30 Fatty Alcohol 50 Catalyst 10

The subject was placed in the 84th SEAC meeting held on 22/23.06.2012 and the proponent

and environmental consultant were present explained the proposed ToRs. The consultant informed that there are 2 existing borewell in the project site. After deliberation, the Committee decided to issue the following ToRs along with model ToRs for preparation of EIA by the proponent:

Page 52: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

52

 

1. Scientific assessment of quantity & quality of borewell water along with impact on the competitive users.

2. Risk assessment associated with chemicals. 3. One month data in addition to two months data already collected by the

proponent. The proponent has submitted the EIA on 01.08.2012 with response to the ToRs issued on

25.07.2012.

The proponent and environmental consultant present explained the EIA before the SEAC meeting held on 24th & 25th August 2012. The Committee suggested the proponent to look into improvements in the manufacture of surfactants in view of the recent R&D. The proponent informed that the ash collected from biomass boiler will be given to farmers. The solid waste collected from MEE operation will be stored and send to dump site at Dabaspet. The hazardous waste oil of 200 Kg/year generated from the industry will be sold to re-processors as per KSPCB guidelines. The proponent committed and submitted an undertaking to spend Rs. 2 Lakhs as a part of his social commitment plan toward environmental cause.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance.

The Authority perused the proposal and took note of the recommendation of the SEAC. The Authority after discussion, decided to issue Environmental Clearance subject to

submission of the following information: a) Compliance to the existing EC and CFO in juxtaposition. b) Quantification of hazardous material and plan for its safe disposal including in situ

incineration with permission from the competent Authority. c) Plan for in situ treatment of trade effluent. d) Permission from the competent Authority for drawal of ground water as Malur being

the grey area. e) Details and extent of green belt developed along with latest Photograph.

Mining Projects:

1. Hirekasanakandi Quartz Mine (M.L.No2349) at Sy No. 13, Hirekasanakandi Village, Koppal Taluk and District by M/s. Sarana Basaveshwara Mining Co. (SEIAA 2 MIN 2012)

It is a project proposal for increase the production from 44,000 tonnes to 1,80,000 tonnes.. Total land area 8.09 Ha. in Private Patta land. The investment of Rs. 131 lakhs.

M/s. Sarana Basaveshwara Mining Company have applied for EC from SEIAA for their proposed expansion of Quartz of production from 44,000 to 1,80,000 TPA at Quarry Lease No 2349 over an extent of 8.09 Ha (20.00 Acres) of Government (Revenue) Land at Sy. No. 13 of Hirekasanakandu Village, Koppal Taluk, Koppal District under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. The total project cost is Rs. 131.00 Lakhs. Man Power: 30 persons. Proposed Method of Quarrying: Open Cast semi mechanized mining by using drilling and blasting.

Page 53: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

53

 

Project Details: (a) Land: The Quarry/ Mining Lease area is 8.09 Ha (20.00 Acres) Land. Land Use pattern: Quarry– 1.70 Ha; Waste Dumps- 1.04 Ha; Roads – 0.10 Ha; Green Belt 0.30 Ha; Unexplored Area: 4.09 Ha. (b) Water: Total Requirement: 30 KLD is sourced from borewells for domestic, sprinkling for dust suppression and afforestation. (c) Over Burden: total Quantity: 44,000 TPA. (d) Power: total requirement325 KVA DG set. (e) Green Belt Details: it is proposed to plant 1000 saplings/year.

Project Surrounding Details: Back water of Tungabhadra Dam – 2.50 km; Tungabhadra Dam – 12km, Hirekasankandi Village – 2.10 km, Koppal Taluk – 10.00 km, Forest area – 7.50 km. Other details: Mining Lease is granted by DMG on 07.05.2002 and is valid for 20 years.

Documents submitted:

o Application in prescribed Form-1 o Pre-feasibility report in prescribed format o Mining Plan from Mines & Geology Dept o Mining Lease granted by DMG on 07.05.2002 valid for 20 years. o Geological plan, Key plan , surface plan and ultimate Land Use plan

The subject was discussed in the SEAC meeting held on 7th July 2012. The proponent and environmental consultant present explained the project. The environmental consultant informed that this is a lone quarry and there are no sanctuaries, monuments, national parks, temples and interstate boundary within or nearby the project area. The proponent informed that there is no nallah or ground water source within the lease area. There are no human settlements or villages situated within the area. The proponent informed that the scheme of mining is approved by IBM on 09.11.2011. The modified mining scheme for expansion in production is under process. The CFE is obtained from KSPCB. NOC from Deputy Commissioner is obtained.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent:

1. Survey of India Toposheet duly marking the project site covering 15 km radius. 2. Health status of the workers with medical report. 3. Modified IBM approved mining plan for expansion in production. 4. Details of aerial distance (in km) from the project site to Tungabhadra Dam, National

Parks, Wild life sanctuary, Industrial area and interstate boundary (if any) marked on toposheet also.

5. Present traffic density connecting to the nearest SH/NH along with route map. 6. Intensity of the blasting and its effect on the TB dam. 7. Social commitment plan for Rs. 2 Lakhs with special emphasis on providing toilets

particularly for girl students (with borewell & overhead tank) in Government schools/Anganwadi.

The proponent has submitted information vide letter dated 30.07.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority noted that it is proposed to expand production from the present 44000 TPA to 180,000 TPA of quartz. The Authority while perusing the modified scheme of mining noted that the total reserve including proved and probable is 531406 Tons. The lease is reported to have been granted on 7.8.2002 which means the remaining period is 10 years. Considering the sustainable

Page 54: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

54

 

mining for the extraction shall be less than 53000 Tons per Annum. The Authority therefore could not find any justification for the proposed 180000 TPA.

The Authority therefore decided to get the following information for further consideration

of the proposal: a) Compliance on the earlier EC/CFO obtained in juxtaposition. b) Year wise production and despatch as per the report submitted to the department of

Mines and Geology. c) Details of available resource with method of estimation. d) Technical Justification for the proposed expansion. e) Quantity of waste generated since inception to be generated in remaining lease

period, and plan for its disposal/utilization. f) Rehabilitation and Reclamation plan including progressive and final mine closure

plan. g) Health status of the 30 workers engaged with chest X-Ray and lung Function Test. h) Details and extent of development of greenery with latest dated photograph.

The Authority also decided to invite the proponent to the meeting after submission of the information.

2. Grey Granite Quarry at, Sy.no.74/2, Gowral Village, Yelburga Tehsil, Koppel District by

M/s Himalaya Impex (SEIAA 14 MIN 2012)

It is a project proposal for Grey Granite Quarrying with the production capacity of 500 cubic mtrs / annum. Total land area 2.50 Acres (1.01 Ha.)in Private Patta land. The investment of Rs. 20 lakhs.

M/s Himalaya Impex have applied for EC from SEIAA for their proposed New Quarry with production of Grey Granite Quarry at 300 cum/year at Sy. No. 74/2 of Gowral. Village, Yelburga Taluk, Koppal District over an area of 2.20 Acres of Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Man Power: 9; Proposed Method of Quarrying: Open Cast Manuel with semi-mechanization. Total saleable reserves: 60,500 cum. The proponent has submitted the land documents (RTC) and Government Notification dated 19.01.2012 granting quarry lease for a period of 10 years by Commerce & Industry Department, Government of Karnataka.

The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent present explained the project. The proponent submitted a copy of the approved mining plan from DMG and informed that land conversion from DC for patta land is obtained. The Committee after deliberation, decided to defer the subject and to take up the project for appraisal after obtaining the following details/documents from the project proponent:

1. Environmental Management Plan (EMP). 2. Details of the distance in kilometres from the project site to sanctuaries, national

parks, monuments, interstate boundaries, reserve forests and water bodies (if any). 3. Duly filled up format (check list) of details of the project.

In view of the above facts the Committee after deliberation decided to reiterate its earlier decision of classifying the project under B2 category and recommend the proposal to SEIAA for environmental clearance.

Page 55: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

55

 

The proponent has submitted the above information on 23.08.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after taking the proved resource into consideration and keeping principles of sustainable quarrying in mind decided to issue Environment Clearance for extraction of 300 Cubic meter of Gray Granite per Annum subject to submission of the following information.

a) Lay out plan of the lease area duly marking various land use such as quarrying pit, storage of mineral blocks, waste dump, office/workers accommodation, green belt and other infrastructures.

b) Photograph of the lease area with proposed quarry area. c) Copy of the land conversion order. d) Land use of area abutting to the proposed quarry with photographs. e) Details of quarries in operation within a radius of one Kilo meter. f) Rehabilitation and Reclamation plan including progressive and final mine closure plan. g) Original topo sheet of Survey Of India in 1:50000 scale duly marking the lease area and a

circle of 10Km radius keeping the midpoint of the lease area as its centre. h) Commitment that there are no ecological sensitive areas, Areas notified under the Wildlife

Protection Act, critically polluted areas declared by MOEF, international/interstate boundaries within 10 Kms from the project site.

3. Pink Granite Quarry at R.S.No.4/2, Purathgeri village, Yerigonal Post, Kushtagi

Taluk, Koppal District by M/s Bharat Timber & Construction Co. (SEIAA 37 MIN 2012)

It is a project proposal for pink Granite Quarrying with the production of 9,150 cum per Annum. Total land area 6.677 Ha. in Private Patta land. The investment of Rs. 5.38 Crores.

M/s Bharat Timber & Construction Co., have applied for EC from SEIAA for their renewal of Quarrying of Pink Granite of 9150 Cum/year at Quarry Lease No 014 (granted on 15.2.96 valid for 10 years) at Sy. No. RS No. 4/2 of Purthagere Village, Kushtagi Taluk, Koppal District over an area of 16-02 Acres of Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying: Open Cast, Manual. Man Power: 59 Nos; Total project cost: Rs. 5.38 Crores.

Project Surrounding Details: Railway station Bagalkot- 60 kms. Town, Ilkal Town– 15 kms Near NH-4 Bypass cross road, Karwar Road, Hubli-24 Hubli, Taluk, Dharwad District.

The Project Proponent has submitted approved quarrying Plan from Mines & Geology Dept dated 09.07.2012, NA from Revenue Department dated 26.08.2010, NOC from DCF dated 01.12.2011 for grant of lease in private lands. Land documents (RTC), Notification for renewal of lease dated 24.08.2011 issued by Department of Commerce and Industries, and Survey of India Topo-sheet duly marking the project site and Pre-feasibility Report in prescribed format and also Environmental Management Plan (EMP).

The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent and environmental consultant present explained the project. The proponent committed and submitted an undertaking to spend Rs. 5 Lakhs as a part of his Social commitment plan toward environmental cause.

Page 56: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

56

 

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the baseline data on health status of workers employed from the proponent.

The proponent has submitted the above information on 23.08.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after taking the proved resource in to consideration and keeping principles of sustainable quarrying in mind decided to issue Environment Clearance for extraction of 8000 Cubic meter of pink Granite Per Annum subject to submission of the following information.

a) Lay out plan of the lease area duly marking various land use such as quarrying, storage of mineral blocks, waste dump, office/workers accommodation, green belt and other infrastructures.

b) Photograph of the lease area with quarry. c) Details of quarries in operation within a radius of 1Km. d) Health status of the 59 workers engaged with chest X-Ray and lung Function Test e) Rehabilitation and Reclamation plan including progressive and final mine closure plan. f) Original topo sheet of Survey Of India in 1:50000 scale duly marking the lease area and a

cirle of 10Km radius keeping the midpoint of the lease area as its centre. g) Commitment that there are no ecological sensitive areas, Areas notified under the Wildlife

Protection Act, critically polluted areas declared by MOEF, international/interstate boundaries within 10 Kms from the project site.

4. Pink Granite Quarry at Sy.no. 41/2, Makapura Village, Lingasgur Taluk, Raichur District by Sri Ashok Gowda Patil (SEIAA 53 MIN 2012)

It is a project proposal for Pink Granite Quarrying with the production of 2300 cubic mtrs / annum. Total land area 2.43 Ha.in Private Patta land. The investment of Rs. 100 lakhs.

M/s. Ashok Gowda Patil has applied for EC from SEIAA for their proposed renewal of quarry lease for pink granite quarry of 2,300 Cum/annum production at Quarry Lease No. 177 (valid for 10 years w.e.f 7.4.98 from DMG) at Sy.No. 41/2, Makapura Village, Lingasugur Taluk, Raichur District over an area of 2.43 Ha (6 Acres) of Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying/ Mining: Open Cast Semi-mechanized; Drilling by jack-hammer and cutting by wire optima saw. Man Power: 45; Total project cost: Rs. 100 Lakhs.

The Project Proponent has submitted approved quarrying Plan from Mines & Geology Dept dated 03.07.2012, NA conversion dated 23.12.2008, NOC from Revenue Department for grant of renewal of quarry lease dated 29.12.2008, NOC from DCF dated 28.02.2012 for grant of lease in private lands. Land documents (RTC), Notification for renewal of lease dated 17.02.2012 issue d by Department of Commerce and Industries for a period of 10 years and, Survey of India Topo-sheet duly marking the project site and Pre-feasibility Report in prescribed format and also Environmental Management Plan (EMP). Geological resources: 85134 Cum; Total Mineable reserve: 41430 Cum.

Project Details: Nature of land: Patta Land; Land-use pattern: Quarry – 1.40 Ha; Infrastructure: 0.04 HA; Road: 0.20 Ha; Green belt: 0.40 Ha; unexplored area (with exposures of granite): 0.36 Ha; Water: Total Requirement: 5 KLD sourced from Borewell; Over Burden (OB):

Page 57: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

57

 

Total Quantity: 4350 Tonnes & Waste generated is 26,747 tonnes during the life of the mine. Project Surroundings Details: nearest village Adapur Village: 31 km;

The subject was discussed in the SEAC meeting held on 27.04.2012. The proponent and environmental consultant present explained the project. The proponent informed that there are no national park, wildlife sanctuary, archaeological sites and interstate boundaries within 10 km radius of the project site. The proponent informed that there are 3 quarries each within 3 & 5 km radius of the project site. The proponent committed and submitted an undertaking to spend Rs. 2 Lakhs as a part of his Social commitment plan toward environmental cause.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the baseline data on health status of workers employed from the proponent.

The proponent has submitted the inf. vide letter dated 23.08.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after taking the proved resource in to consideration and keeping principles of sustainable quarrying in mind decided to issue Environment Clearance for extraction of 2250 Cubic meter of Pink Granite Per Annum subject to submission of the following information.

a) Lay out plan of the lease area duly marking various land use such as quarrying, storage of mineral blocks, waste dump, office/workers accommodation, green belt and other infrastructures.

b) Photograph of the lease area with quarry. c) Copy of land conversion order. d) Details of quarries in operation within a radius of 1Km. e) Rehabilitation and Reclamation plan including progressive and final mine closure plan. f) Original topo sheet of Survey Of India in 1:50000 scale duly marking the lease area and a

cirle of 10Km radius keeping the midpoint of the lease area as its centre. g) Commitment that there are no ecological sensitive areas, Areas notified under the Wildlife

Protection Act, critically polluted areas declared by MOEF, international/interstate boundaries within 10 Kms from the project site.

5. Pink Porphery Ornamental Granite Quarry at Sy.No. 44, Kengal village, Nelamangala

Taluk, Bangalore Rural District by M/s. Vijay Enterprises (SEIAA 54 MIN 2012)

It is a project proposal for Pink Porphery Ornamental Granite Quarrying with the production of 3600 Cum / annum. Total land area 1.6 Ha. in Private Patta land. The investment of Rs. 40 lakhs.

M/s. Vijaya Enterprises, have applied for EC from SEIAA for their proposed renewal of Quarrying of pink porphery ornamental granite quarry of 3600 cum/year production at Quarry Lease No. applied at Sy.No.44, Kengal Village, Nelamangala Taluk, Bangalore District over an area of 1.62 ha (4-00 Acres) of Government Gomala Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying/ Mining: Open Cast and drilling with compressor operated jack hammer. Man Power: 32; Total project cost: Rs. 40 Lakhs.

Page 58: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

58

 

The Project Proponent has submitted Quarrying Plan from Mines and Geology Department dated 17.07.2012, Land documents (RTC mentioning Gomala Land), Notification for renewal grant of lease dated 26.06.2012 issued by C&I dept, NOC from DCF dated 10.08.2011, joint inspection report dated 25.01.2011 and letter of Tahsildar Nelamangal Taluk dated 01.06.2011, Survey of India Topo-sheet duly marking the project site and Pre-feasibility Report in prescribed format and EMP. Project Surrounding Details: Nijigal SF: 1.4 km; nearest village Kengal: 0.93 km. Water requirement: 3 KLD. Over Burden: 1500 Cum for 5 years.

The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent

present explained the project. The proponent informed that there are no national park, wildlife sanctuary, archaeological sites and interstate boundaries within 10 km radius of the project site. The proponent committed and submitted an undertaking to spend Rs. 2 Lakhs as a part of his Social commitment plan toward environmental cause.

After deliberation, the Committee decided to recommend the proposal after obtaining

baseline data on environmental parameters and health status of workers employed from the proponent.

The proponent has submitted the information vide letter dated 23.08.2012 and reclamation & rehabilitation plan vide letter dated 25.09.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority while going through the proposal noted that the Tahsildar, Nelamangala taluk have reported that penalty amount was collected from the proponent for having stored waste outside the lease area. Whether the area is cleared now, is not forthcoming from the appraisal. The Authority further observed that justification for the proposed extraction of 3600Cm per annum is also not forthcoming.

The Authority therefore decided to get the following information for further consideration of the proposal:

a) Lay out plan of the lease area duly marking various land use such as quarrying, storage of mineral blocks, waste dump, office/workers accommodation, green belt and other infrastructures.

b) Reason for the penalty imposed with copy of the order of competent Authority. c) Present status of the land unauthorisedely used for dumping of waste. d) Year wise production and despatch as per the report submitted to the department of

Mines and Geology. e) Details of available resource with method of estimation. f) Whether safety margin of minimum of 7.5 Metre is maintained along the lease

boundary. g) Technical Justification for the proposed extraction. h) Quantity of waste expected and mode of disposal. i) Rehabilitation and Reclamation plan including progressive and final mine closure

plan. j) Copy of recommendation made by the Deputy Commissioner for allotting Gomala

land for quarrying purpose k) Details and extent of development of greenery with latest dated photograph of

quarry and greenbelt developed.

Page 59: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

59

 

6. Grey Granite Quarry at Sy. No.1, Madapalli village, Chintamani Taluk, Chikkaballapura District by M/s Saddharma Minerals (SEIAA 40 MIN 2012)

It is a project proposal for Grey Granite Quarrying with the production of 2500 cum/Annum. Total land area 5.66 Ha (14.20 Acres) in Gomala land. The investment of Rs. 20 lakhs.  

M/s. Saddharma Minerals., have applied for EC from SEIAA for their proposed Quarrying of “Grey Granite of production capacity of 2500 cum/Annum at Quarry Lease No 107at Sy.No. 1 of Madaballi Village, Chintamani Taluk, Chikkaballapura District over an area of 14-20 Acres of Government Gomal Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying: Open Cast other than fully mechanized. Drilling by jackhammer and cutting by wire saw. Man Power: 20 Nos; Total project cost: Rs. 20 Lakhs. Geological resources: grey granite: 27,000 Cum; Mineable reserve: grey granite: 67,500 Cum. Land-use pattern: Waste dump yard: 024 ha; Infrastructure: 0.01 Ha; Roads – 0.06 Ha; Mineral Storage: 0.03 Ha. Water requirement: 10 KLD sourced from borewell. The Project Proponent has submitted Mining plan approved by DMG on 22.06.2012, Land documents (RTC),Notification for grant of lease dated 17.02.2012 issued by C&I Dept, Survey of India Topo-sheet duly marking the project site and Pre-feasibility Report and EMP. Project Surrounding Details: Thalagavara Lake: 2.5 km; Kadahalli Lake: 4.5 km; Bedarahalli Lake: 4 km; Kadavipura SF: 5.5 km; Handikere SF: 7 km; Chintamani Railway Station – 15 km; Bangalore International Airport- 50 km; Chintamani – 15 km. Kolar- 26 km. The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent present explained the project. The Committee observed that the proponent has not submitted baseline data on environmental parameters in the EMP submitted. The proponent committed and submitted an undertaking to spend Rs. 1 Lakh as a part of his Social commitment plan toward environmental cause. After deliberation, the Committee decided to recommend the proposal to SEIAA for environmental clearance after obtaining the baseline data on environmental parameters and health status of workers employed from the proponent. The proponent has submitted the information vide letter dated 09.09.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after taking the proved resource into consideration and keeping principles of sustainable quarrying in mind decided to issue Environment Clearance for extraction of 1700 Cubic meter of Gray Granite Per Annum subject to submission of the following information.

a) Lay out plan of the lease area duly marking various land use such as quarrying, storage of mineral blocks, waste dump, office/workers accommodation, green belt and other infrastructures.

b) Photograph of the lease area with quarry. c) Land use of abutting area to the quarry with photographs. d) Copy of recommendation made by the Deputy Commissioner for allotting Gomala land for

quarrying purpose. e) Details of quarries in operation within a radius of One Kilometer.

Page 60: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

60

 

f) Rehabilitation and Reclamation plan including progressive and final mine closure plan. g) Original topo sheet of Survey Of India in 1:50000 scale duly marking the lease area and a

circle of 10Km radius keeping the midpoint of the lease area as its centre. h) Commitment that there are no ecological sensitive areas, Areas notified under the Wildlife

Protection Act, critically polluted areas declared by MOEF, international/interstate boundaries within 10 Kms from the project site.

7. Green quartz Mining, Sy.No.214, Kanchugarahalli vilalge, Channagiri Taluk, Davanagere District by Sri Marakatha Mining Industries. (SEIAA 56 MIN 2012)

It is a project proposal for Green quartz Quarrying with the production of 650 Tons/Year. Total land area 2.023 Ha in Private Patta land. The investment of Rs. 5 lakhs.  

M/s. Sri. Marakatha Mining Industries have applied for EC from SEIAA for their proposed new of mining of green quartz mining of capacity 650 TPA at AML No. 159/2009, Sy. No. 214, Kanchugarahalli Village, Channagiri Taluk, Davanagerre District over an area of 2.023 Ha (5 Acres) of Private Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Mining: Open Cast with Manual. Man Power: 13; Total project cost: Rs. 45.00 Lakhs.

The Project Proponent has submitted approved Quarrying Plan from Mines and Geology Department dated 09.03.2012, Land documents (RTC), Survey of India Topo-sheet duly marking the project site and Pre-feasibility Report in prescribed format. Land conversion letter from agricultural to non-agricultural (green quartz mining) from DC, Davanagere on 28.03.2011 and EMP.

Project Details: Nature of land: Private Patta Land. Land-use pattern: Mining: 0.082 Ha; Overburden Dumps: 0.140 ha; Mineral Storage: 0.050 ha; Infrastructure: 0.030 ha; Road: 0.061 ha; Green Belt: 0.800; Others (Parapet walls, settling tank): 0.035 ha; Undisturbed area: 0.825 ha. Water: Total Requirement: 7.5 KLD sourced from nearby borewell. Over Burden (OB): Total Quantity: 375 TPA and sub grade of 130 TPA of green quartz. Project Surrounding details: nearest village Ujjinipur: 2.5 km; nearest water body: Tugabadra River: 4 km; Daginakatte Kere: 6 km; Sulekere RF: 6 km;

The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent present explained the project. The proponent informed that there are no national park, wildlife sanctuary, archaeological sites and interstate boundaries within 10 km radius of the project site.

After deliberation, the Committee decided to recommend the proposal after obtaining baseline data on environmental parameters and health status of workers employed along with social commitment plan for Rs. 1 Lakh towards the environmental cause from the proponent.

The proponent has submitted the information vide letter dated 06.09.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after taking the proved resource into consideration and keeping principles of sustainable quarrying in mind decided to issue Environment Clearance for extraction of 450 TPA of Green Granite subject to submission of the following information.

Page 61: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

61

 

a) Lay out plan of the lease area duly marking various land use such as quarrying, storage of mineral blocks, waste dump, office/workers accommodation, green belt and other infrastructures.

b) Photograph of the lease area with quarry. c) Details of mineral resource with method of estimation. d) Details of waste to be generated and plan for utilization of the same. e) Land use of area abutting to proposed quarry with photographs. f) Notification issued by the Mines and Geology Department for grant of lease. g) Details of quarries in operation within a radius of one Kilometer. h) Rehabilitation and Reclamation plan including progressive and final mine closure plan. i) Original topo sheet of Survey Of India in 1:50000 scale duly marking the lease area and a

cirle of 10Km radius keeping the midpoint of the lease area as its centre. j) Commitment that there are no ecological sensitive areas, Areas notified under the Wildlife

Protection Act, critically polluted areas declared by MOEF, international/interstate boundaries within 10 Kms from the project site and distance from the Ranebennur Black buck Sanctuary.

k) Plan to ensure that the nearby water bodies are not affected and silted up due to the project activity.

8. Green Granite Quarry, Sy.no.59, Gandalu village, Chikkamagalur Taluk & District by

M/s. Maina and Co. (SEIAA 63 MIN 2012)

It is a project proposal for Green Granite Quarrying with the production of 250 CBM. Total land area 1.29 ha (3.20 Acres) in Gomala land. The investment of Rs. 20 lakhs.

M/s. Maina & Company has applied for EC from SEIAA for their proposed New of Quarry of green granite 250 Cum production at Quarry Lease No. applied at Sy.No. 59 of Gandalu Village, Chikkamagalur Taluk & District over an area of 1.29 Ha (3.20 Acres) of Gomala Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying/ Mining: Open Cast OTFM. Total project cost: Rs. 20 Lakhs. Land-use pattern: Waste dump yard: 0.04 ha; Infrastructure: 0.0056 Ha; Roads – 0.08 Ha; Mineral Storage: 0.03 Ha.

The Project Proponent has submitted quarrying Plan from Mines & Geology Dept dated 25.07.2012, Land documents (RTC), Notification for grant of lease dated 11.06.2012 issued by Commerce & Industries Department, Survey of India Topo-sheet duly marking the project site and Pre-feasibility Report in prescribed format. The proponent has submitted joint inspection report dated 21.06.2010; Project Surrounding Details: Chikkamagaluru: 15 km; nearest Village (Lakya): 1.5 km; nearest water body Sadarahalli Lake: 2 km; Magadi Lake: 8.5 km;

The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent present explained the project. The proponent informed that there are no national park, wildlife sanctuary, archaeological sites and interstate boundaries within 10 km radius of the project site. The proponent committed and submitted an undertaking to spend Rs. 0.5 Lakhs as a part of his Social commitment plan toward environmental cause.

After deliberation, the Committee decided to recommend the proposal after obtaining baseline data on environmental parameters and health status of workers employed from the proponent.

The proponent has submitted the information vide letter dated 06.09.2012.

Page 62: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

62

 

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after taking the proved resource in to consideration and keeping principles of sustainable quarrying in mind decided to issue Environment Clearance for extraction of 250 cum of Green Granite subject to submission of the following information.

a) Lay out plan of the lease area duly marking various land use such as quarrying, storage of mineral blocks, waste dump, office/workers accommodation, green belt and other infrastructures.

b) Photograph of the lease area with quarry. c) Details of mineral resource with method of estimation. d) Details of waste to be generated and plan for utilization of the same. e) Land use of the areas abutting to proposed quarry with photographs. f) Copy of land conversion order. g) Details of quarries in operation within a radius of 1Km. h) Rehabilitation and Reclamation plan including progressive and final mine closure plan. i) Original topo sheet of Survey Of India in 1:50000 scale duly marking the lease area and a

cirle of 10Km radius keeping the midpoint of the lease area as its centre. j) Commitment that there are no ecological sensitive areas, Areas notified under the Wildlife

Protection Act, critically polluted areas declared by MOEF, international/interstate boundaries within 10 Kms from the project site.

k) Plan to ensure that the nearby water bodies are not affected and silted up due to the project activity.

9. Ornamental Stone quarry, Sy.No.49, Gattipura village, Magadi Taluk, Ramanagar District by M/s Shrishyla Granites (SEIAA 22 MIN 2012)

M/s. Shrishyla Granites have applied for EC from SEIAA for their proposed Expansion of Quarry of Ornamental granite Stone of 6500 Cum/annum production at Quarry Lease No 6059 at Sy.No. 49 of Gattipura Village, Magadi Taluk, Ramanagara District over an area of (10-00 Acres) of Government Gomala Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying/ Mining: Open Cast/ Manual / Semi-mechanized. Man Power: 20; Total project cost: Rs. 25 Lakhs. The Project Proponent has submitted Mining Plan approved on 02.08.2012, Survey of India Topo-sheet, RTC mentioning Gomala Land, Environmental Management Plan (EMP) and Pre-feasibility Report. The PP was granted QL for a period of 10 years w.e.f. 26.05.1990. Renewal application is filed before DMG. Project Surrounding Details: Magadi Town – 10km.

Land-use pattern: Excavated: 0.08 Ha; Infrastructure: 0.0056 Ha; Roads: 0.10 Ha; Mineral Storage: 0.08 Ha.

The subject was discussed in the SEAC meeting held on 4th August 2012. The proponent present explained the project. The proponent submitted his letter dated 04.08.2012 addressed to the Secretary; DFEE enclosing the joint site inspection report dated 28.03.2009 by Subdivision Officer, Ramanagar Subdivision, Ramanagar and informed that the Gomala land does not come under the purview of the Deputy Commissioner as per the Department of Mines and Geology. The entire area of Gomala land covers 132 acres. However, it is ascertained from Deputy Commissioner, Bangalore Rural District that based on the joint inspection report the DC will issue the NOC for quarrying in Gomala land. The proponent committed and submitted an undertaking to spend Rs. 1 Lakh as a part of his Social commitment plan toward environmental cause.

Page 63: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

63

 

After deliberation, the Committee decided to recommend the proposal to SEIAA for environmental clearance after obtaining the following information from the proponent:

1. Baseline & cumulative data on environmental parameters and health status of workers employed.

2. NOC from Deputy Commissioner, Ramanagara for quarrying in Gomala land.

The proponent has submitted the information vide letter dated 03.09.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority while perusing the joint inspection report observed that the proposed project site is a gomal land. There is a lake adjacent to the proposed quarry in the North East direction. The Authority further observed that some of the gomal lands in the Bangalore Rural/ Ramanagaram districts are overlapping with forest lands. The Authority also noted that the report of Dr.U.V.Singh have revealed many irregularities in these districts.

The Authority therefore decided to get the following information for further consideration of the proposal:

a) Compliance on the earlier EC/CFO obtained. b) Lay out plan of the lease area duly marking various land use such as quarrying,

storage of mineral blocks, waste dump, office/workers accommodation, green belt, other infrastructures with Photograph of the lease area with quarry

c) Year wise production and despatch as per the report submitted to the department of Mines and Geology.

d) Details of available mineral resource with method of estimation. e) Technical Justification for the proposed expansion. f) Quantity of waste expected and mode of disposal. g) Health status of the workers engaged with chest X-Ray and lung Function Test. h) Details and extent of development of greenery with latest dated photograph. i) Land use of the areas abutting to proposed quarry with photographs. j) Copies of land conversion order and NOC from the Deputy Commissioner for

undertaking quarry in Gomala land. k) NOC from the Forest department. l) Details of quarries in operation within a radius of one Kilometer. m) Rehabilitation and Reclamation plan including progressive and final mine closure

plan. n) Original topo sheet of Survey Of India in 1:50000 scale duly marking the lease

area and a cirle of 10Km radius keeping the midpoint of the lease area as its centre. o) Commitment that there are no ecological sensitive areas, Areas notified under the

Wildlife Protection Act, critically polluted areas declared by MOEF, international/interstate boundaries within 10 Kms from the project site.

p) Plan to ensure that the adjacent lake is not affected and silted up due to the project activity.

10. Grey Granite Quarry, Sy.No. 83/2 and 83/3, Kukkanur village, Yelburga Taluk, Koppal District by Sri Gangadhara B. Hiremath (SEIAA 27 MIN 2012)

Page 64: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

64

 

It is a project proposal for Grey Granite Quarrying with the production of 2000 608 CMT.. Total land area 1.01 Ha. in Private Patta land. The investment of Rs. 15 lakhs.

Sri. Gangadhar B. Hiremath, Proprietor has applied for EC from SEIAA for their proposed New of Quarry of Grey Granite at 180 cum production at Quarry Lease No. applied at Sy.No. 83/2 and 83/3 of Kukkanur Village, Yelburga Taluk, Koppal District over an area of 2-20 Acres Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying: Open Cast other than fully mechanized with wire saw method. Total project cost: Rs.15 Lakhs. Man Power: 20; Geological resources: grey granite: 24,750 Cum; Mineable reserve: 11,385 Cum

The Project Proponent has submitted, Land documents (RTC), project site and Pre-feasibility Report in prescribed format. Land conversion obtained from DC. Land-use pattern: Waste dump yard: 0.03 Ha; Infrastructure: 0.0056 Ha; Roads – 0.06 Ha; Mineral Storage: 0.02 Ha. Water requirement: 0.5 KLD sourced from borewell and tankers.

Project Surrounding Details: Benakal Lake: 5 km; Hirehall Nallah: 6.5 kml HireNadi: 9 km;

The subject was discussed in the SEAC meeting held on 4th August 2012The proponent

present explained the project. The proponent has submitted quarrying plan from Department of Mines & Geology approved on 31.07.2012, environmental management plan, grant of lease Notification dated 11.06.2012 and toposheet. The proponent informed that there are no reserve forest, wildlife and sanctuary within 10 km radius of the project. The nearest village is Kukkanur Village. The proponent committed and submitted an undertaking to spend Rs. 1 Lakh as a part of his Social commitment plan toward environmental cause.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent:

1. Baseline data on health status of workers employed. 2. Commitment on upgradation of the approach mud road.

The proponent has submitted the information vide letter dated 28.08.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after taking the proved resource in to consideration and keeping principles of sustainable quarrying in mind decided to issue Environment Clearance for extraction of 600 cum of Gray Granite subject to submission of the following information.

a) Lay out plan of the lease area duly marking various land use such as quarrying, storage of mineral blocks, waste dump, office/workers accommodation, green belt, other infrastructures.

b) Photograph of the lease area with quarry. c) Details of mineral resource with method of estimation. d) Details of waste and plan for utilization the same. e) Land use of the adjoining plot with photographs. f) Copy of land conversion order. g) Details of quarries in operation within a radius of one Kilometer. h) Rehabilitation and Reclamation plan including progressive and final mine closure plan.

Page 65: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

65

 

i) Original topo sheet of Survey Of India in 1:50000 scale duly marking the lease area and a circle of 10Km radius keeping the midpoint of the lease area as its centre.

j) Commitment that there are no ecological sensitive areas, Areas notified under the Wildlife Protection Act, critically polluted areas declared by MOEF, international/interstate boundaries within 10 Kms from the project site.

k) Plan to ensure that the nearby water bodies are not affected and silted up due to the project activity.

Recommended for Closure:

The following proposals have been recommended by SEAC during the meeting held on 24th August 2012 for closure. Abstract of the proceedings of the said SEAC meeting is given under each of the proposals for consideration of the Authority.

Construction Projects:

1. Construction of Residential Apartment & Villas, Adarsh Palm Retreat, Sy.Nos.88, 89, 90, 91/1, 91/2, 92/1, 92/2, 93, 94/1, 94/2, 94/3, 95, 107, 108, 109, 110, 111 & 112, Bhoganahalli Village, and Sy. Nos. 73, 74, 92, 93, 94, 96, 97, 98, 99 & 100, Doddakanahalli Village, Vartur Hobli, Bangalore East Taluk, Bangalore by M/s. Adarsh Developers (SEIAA 49 CON 2009)

The proposal is for construction of ‘Adarsh Palm Retreat’ a apartments & villas project at Sy.Nos.89, 90, 91/1, 91/2, 92/1, 92/2, 92/3, 93, 94/1, 94/2, 94/3, 95, 107, 108, 109, 110, 111, 112 of Bhoganahalli Village and Sy.No. 73, 74, 92, 93, 94, 96, 97, 98, 99 & 100 of Doddakanahalli Village, Varthur Hobli, Bangalore with site area 4,23,088.07 M2, built up area 4,87,258.62 M2 (for Apartments is 2,82,603.78 M2, Villas is 1,88,344.84 M2, Club House is 16,310 M2) Water consumption 1074 KLD, source of water from BWSSB, car parking is 4,220 Nos, power requirement (for apartment 13,990 kVA, villas 9417 kVA, Club House 815 kVA), DG set is 4 Nos x 1200 kVA, 2 Nos 1500 kVA & 1 No. 500 kVA and investment of Rs.586 Crores. The proposed project consists of Residential Apartments (1424 Nos flats) & Villas (526 Nos.). Apartments consists 30 Blocks with 2 Basements + Ground Floor + 12 Upper Floors. Villas consists of Ground Floor + 1 Upper floor.

The proponent presented and explained ToR. The Committee discussed and deliberated on the solid waste scheme, source of water, traffic management plan and mitigative measures, baseline datas, EMP etc., The Committee suggested that an In-house scheme for Disposal of Biodegradable waste needs to be developed, against the suggestion of the proponent to arrange for 50% of the waste to be lifted by the BWSSW, which was felt not feasible.

Regarding water supply the Proponent categorically stated that apart from the NOC issued by the BWSSB, he has paid the water connection charges to prove that there is a commitment on part of the BWSSB for assuring the supply of water to the project.

The Committee therefore, decided to issue the following additional ToRs along with the model ToRs for the incorporation of the same in the preparation of EIA report.

Page 66: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

66

 

1. Scheme for disposal for in house biodegradable waste and clear disposal for non-degradable waste.

2. Recent sanctioned letter from BWSSB as stated by the proponent for having paid the water connection charge for assured supply of water.

3. Specific Social commitment plan as committed by the proponent with specific letter of requirement of the components of SCR / MOU between the proponent and the local recipient.

Accordingly ToRs were issued vide letter dated 3.6.2010 for preparation of EIA report. Subsequently reminder was issued on 24.01.2011. Since no reply was received the subject was placed before SEAC during the meeting held on 24th /25th August 2012. The Committee have recommended the file for closure as the 2-year time limit for submission of EIA expires on 14.06.2012 as stipulated in EIA notification.

In the mean time the proponent have submitted a letter dated 28th September 2012 to the Authority requesting the Authority to send the file back to SEAC for required appraisal as the EIA report has been prepared and is being submitted to SEAC.

The Authority perused the proposal and took note of the recommendation of the SEAC and as well as the submission made by the proponent.

The Authority noted that as per OM NO.J-11013/41/2006-IA.II(I) dated 22nd March 2010, a

validity of 2 years which can be extendable to 3years has been fixed for the TOR's issued from 1.4.2010.

The Authority after discussion opined that considering the explanation/justification

furnished by the Proponent, the SEAC may extend the validity of TOR issued to 3 years and appraise the proposal based on its merit if the EIA Report is submitted in time.

The Authority with the above observation decided to send the proposal back to SEAC for

appraisal in accordance with the EIA Notification, 2006 and to send recommendation as deemed fit on its merit.

2. Residential Apartments, Sy.Nos. 52/1A, 53, 57 and 56/2, Kadirenahalli Village,

Uttarahalli Hobli, Bangalore South Taluk by M/s. Adarsh Developers (SEIAA 51 CON 2010)

M/s. Adarsh Developers have applied for EC from SEIAA for their new proposed residential project at Sy. No. 52/1A, 53, 57 & 56/2 of Kadirenahalli Village, Uttarahalli Hobli, Bangalore South Taluk, Bangalore under Schedule No 8(a) of EIA Notification, 2006. Total project cost: Rs. 80 Crores. Project comes under BBMP.

Project Details: Land: Total plot area: 15,884 Sqm; Total built up area: 49,481.35 Sqm; The project consists of 246 residential flats in 4 blocks each consisting of B + G+ 17 UF. Landscape area: 8,358.56 Sqm (52.62%). Water Requirement: Total fresh water requirement is 130 KLD. Sourced from BWSSB (NOC obtained). Sewage: Total quantity generated: 141 KLD treated in proposed STP of design capacity of 145 KLD based on MBR technology; sludge- 10 Kg/day used as manure. Solid waste: Total generated: 738 Kg/day; organic waste of 443 Kg/day treated in

Page 67: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

67

 

organic converter and product used as manure. Inorganic waste of 295 Kg/day will be sent for recycling. Power Requirement: Total Requirement: 1469.1 KVA from BESCOM; Power Backup 1X380 KVA and 1X250 KVA DG sets. Parking proposed for 440 Numbers.

The subject was again placed in the 70th SEAC meeting held on 17-18.06.2011 and the Committee noted that in spite of letter dated: 04/06/2010 followed by reminder dated: 05/04/2011 requesting the proponent to submit the required information within 15 days failing which his file would be recommended for closure at his risk, the proponent has failed to submit the information. Hence, the Committee decided to recommend the proposal to SEIAA for closure as sufficient information was not available in the file.

The subject was placed in the 42nd SEIAA meeting held on 22.07.2011 and the Authority having considered the representation submitted by the proponent seeking some time and decided to refer back to SEAC to provide one more opportunity and appraise based on available records.

The subject was placed in the 74th SEAC meeting held on 16/17.09.2011 and It was informed that the proponent vide letter dated 21.07.2011 had informed that he will submit the required information sought by SEAC. But, vide his letter dated: 15.09.2011 has expressed his inability to attend the SEAC meeting. After deliberation, The Committee decided to give final one more opportunity to the proponent to attend SEAC meeting.

The subject was placed in the 75th SEAC meeting held on 14-15.10.2011 and the project proponent was present explained the project. The proponent informed that the proposed project is a residential apartment comprising 330 units in 4 blocks with a configuration of 2B + G + 24 UF and a club house. The plot area is 15,884 Sqm and built up area is 94,633 Sqm. The landscape area is 6,108.3 (38.4 % of plot area). The Committee observed certain discrepancies in the proposal as compared to the Form 1 & 1A submitted earlier and hence, requested the proponent to submit revised Form 1 & 1A as above. The proponent informed that the project site is surrounded by a fully developed area and Kadirenahalli Lake is located far away. The level difference in the project site is 11 m.

The proponent informed that the project is located along ORR which connects to Mysore Road on one side and Kanakapura Road on other side. The existing LoS of the ORR road towards Mysore road is C and that towards Kanakapura road is D. The same for projected and modified traffic scenario of these two roads is D-D and >F- >F. The Committee suggested the proponent that the bio-degradable waste should be composted and used for gardening within the premises instead of giving the same to BBMP for disposal. The Committee also advised to plant alternative species to Gulmohar trees proposed for landscaping as they are shallow rooted and likely to fall down. The Committee also advised the proponent to use tertiary treated water from BWSSB for construction purpose instead of fresh water.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance after obtaining the following information from the proponent with a condition that the proponent should install bio-convertor for treating biodegradable waste produced in the project.

1. Revised Form 1 & 1A. 2. Dated peak hour traffic density photographs. 3. Social commitment plan for Rs. 6 Lakhs, as committed by the proponent.

Page 68: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

68

 

The subject was again placed in the 81st SEAC meeting held on 07.04.2012 for closure as the proponent have not submitted the information sought vide letter dated 29.10.2011 by SEAC and the Committee discussed on the status of the proposal placed before the Committee in detail and decided that a final reminder with a time limit of 30 days can be given to the proponent to obtain the required details/documents failing which the proposal may be brought before SEAC for closure.

The proponent has submitted the information on 18.05.2012 with response to this office letter dated 29.10.2011 and reminder dated: 18.04.2012.

The Committee during the meeting held on 22nd & 23rd June 2012, observed that in the revised Form 1&1A submitted by the proponent, there is no mention of the height of the building and also the configuration of 2B+G+24 UF as recorded in the earlier proceedings dated 14/15.10.2011. The approximate height of the building works out to 75 m. The proponent has informed that the RoW in front of the project site is 20 m (Outer Ring Road). The proponent has submitted the revised proposal on 18.05.2012 after the issuance of O.M. on high rise buildings by MoEF, GoI on 07.02.2012. The revised proposal doesn’t comply with the guidelines of the O.M.

The Committee also noted that the appraisal of the project was done on 14/15.10.2011 in the 75th SEAC meeting and recommended to SEIAA for environmental clearance after obtaining the revised proposal. Now, that the revised proposal submitted by the project proponent doesn’t comply with the guidelines on high rise buildings, the Committee decided to forward the file to SEIAA to take suitable decision with respect to application of O. M. on high rise buildings and consider issue of environmental clearance to the project.

The subject was placed in the 54th SEIAA meeting held on 06.08.2012 and the Authority perused proposal and took note of the recommendation of the SEAC.

The Authority observed that, the proceedings of the SEAC does not reveal any decision of the Committee in the spirit of the EIA Notification, 2006. The Authority observed that as per para 7 (i) Stage (4) para (i), the Expert Appraisal Committee is to make a categorical recommendations either for grant of Environmental Clearance with stipulated conditions or for rejection of the application with reasons for the same. The relevant para is reiterated below:

"On conclusion of this proceeding, the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned shall make categorical recommendations to the regulatory authority concerned either for grant of prior environmental clearance on stipulated terms and conditions, or rejection of the application for prior environmental clearance, together with reasons for the same."

The Authority after discussion, decided to send the proposal back to SEAC for making categorical recommendation in accordance with the provisions of EIA Notification, 2006.

The Authority also decided to send a note to Secretary, SEAC with a copy to the Chairman, SEAC, briefly covering the statutory requirement with regard to recommendation to be made by SEAC to the Authority with a request to read out the relevant provision in the ensuing Committee meeting.

The Committee after deliberations decided to strictly adhere to the above provision of the EIA Notification, 2006 while making recommendations to the SEIAA for environmental clearance. The Committee reiterated the decision taken in the 80th SEAC proceedings held on 17.03.2012 wherein it was decided to (i) strictly adhere to the guidelines stipulated in the O.M. (ii)

Page 69: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

69

 

obtain the details with respect to the O.M. from the proponent and (iii) recommend to SEIAA such proposals which are not complying with the O.M. for closure with a request to proponent to apply afresh with revised proposal before SEIAA.

The Committee noted that the revised proposal submitted by the proponent after the 75th

SEAC meeting held on 14/15.10.2011 does not comply with the provisions of the O.M dated 07.02.2012 and therefore decided to recommend the proposal to SEIAA for closure with a request to the proponent to apply afresh before SEIAA in compliance to the O.M if he is willing.

The proponent have submitted a letter dated 29th September 2012 to the Authority. The

proponent have submitted that the proposed building will have a height of 91.35 meter and the width of the road abutting the project site is 45 meters as per the Revised Master Plan (RMP) 2015 of BDA. A copy of the concerned RMP is also enclosed.

The Authority perused the proposal and took note of the recommendation of the SEAC and as well as the submission made by the proponent.

The Authority after discussion opined that as per the letter dated 29th September 2012 of the proponent, the project apparently meets the ROW criteria laid down by the MOEF vide OM dated 7.02.2012. The Authority therefore decided to send the proposal back to SEAC for appraisal in accordance with the EIA Notification, 2006 and to send recommendation as deemed fit on its merit.

3. Residential Apartment at new consolidated BBMP Khata Nos.46/1, 46/2, 47/2-8 (old

municipal nos. 46/1 &2, 47/2, 8/1-1 to 8/1-6), 17th Main Road, Marenahalli Village, JP Nagar 2nd Phase, Bangalore South Taluk, Bangalore by M/s Good Home Realty Pvt. Ltd. (SEIAA 1 CON 2012)

It is a proposal for construction of Residential Apartment of 147 Units with two wings North & South. North wing consists of 117 flats with 2 Basement + Stilt + Ground Floor + 25 Upper Floors and South Wing consists of 30 flats with 2 Basement Floors + Ground Floor & 11 Upper Floors and a Club house on an area of 14,739.89 Sq.m and with the total built up area of 81,362.59 Sq.m. The total water requirement is 150 KLD and the investment is of Rs. 211.27 crores.

M/s. Good Home Realty Private Limited have applied for EC from SEIAA for their new proposed residential project at new consolidated BBMP Khata Nos.46/1, 46/2, 47/2-8/1 (Old Municipal Nos. 46/1 &2, 47/2, 8/1-1 to 8/1-6), 17th Main Road, Marenahalli Village, JP Nagar 2nd Phase, Bangalore South Taluk, Bangalore under 8(a) of schedule of EIA Notification, 2006 under category-B requiring EC from SEIAA. Total project cost: Rs.211.27 Crores. Project comes under BBMP. The project site is located in Residential Zone of CDP.

Project Details: (a) Land: Total plot area: 14,739.89 Sqm; Total built up area: 81,362.59 Sqm. The project consists of 147 flats in two wings North & South. North wing consists of 117 flats with 2 Basement Floors + Stilt + Ground Floor + 25 Upper Floors and South Wing consists of 30 flats with2 Basement Floors + Ground Floor & 11 Upper Floors. Club house is also proposed. (b) Greenery: Landscape area: 7014.89 Sqm (47.6% of plot area). (c) Water Requirement: Total water requirement is 150 KLD; Source of water: BWSSB. (d) Soil: Total excavated soil: 54,000 Cum; Backfilling Quantity: 27,000 Cum, landscaping quantity: 6,000 Cum within the project site and the excess will be disposed off to an identified site. (e) Sewage: Total quantity generated: 120 KLD, treated in proposed STP of design capacity 125 KLD; Sludge

Page 70: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

70

 

generated: - 45 Kg/day used as manure. (f) Solid Waste: Total generated: 437 Kg/day; Organic waste: 262Kg/day treated in organic waste converter and product used as manure. Inorganic waste: 175Kg/day will be sent for recycling. (g) Power Requirement: Total Requirement: 2749KVA from BESCOM; Power Backup: 2X1010 KVA DG sets (h) Parking: 484 Numbers.

Project Surrounding Details: Water Bodies: Byrasandra Lake: 2.8 km; Puttenahalli Lake – 2 km, Lalbagh Lake – 3.6 km, Madivala Lake – 2.5 km, Bannerughatta National Park- 12Kms; Other Details: Rain Water Harvesting is proposed. Eco Technical Report, Risk Assessment & Management Plan submitted. Applied for NoC from BWSSB.

The subject was placed in the 79th SEAC meeting held on 9/10.02.2012 and the proponent present explained the project. The project site is located along J.P. Nagar 17th main road which connects Marenahalli road on one side and J.P. Nagar 2nd Phase on the other side. Marenahalli road connects BTM Layout on one side and Banashenkari on the other side. The existing, projected and modified LoS for Marenahalli road is C-E-E (BTM Layout) and C-F-F (Banashenkari). The same for J.P. Nagar 17th main road is B-C-C.

After deliberation, the Committee decided to reconsider the proposal after obtaining the following information from the proponent.

1. Rework on landscape plan along with number and species of fruit bearing trees. 2. Enhanced power saving. 3. Drainage pattern details with contour plan. 4. MoU for disposal of excavated earth. 5. Plan for adopting MBR Technology for STP. 6. Toposheet with survey numbers of the project site for 500 m radius. 7. NOC from the BWS&SB. 8. Social commitment plan for Rs. 20 Lakhs, as committed by the proponent.

The proponent has submitted the above information on 12.03.2012 in response to this office letter dated: 23.02.2012.

The subject was placed in the 81st SEAC meeting held on 07.04.2012 and the Committee discussed in detail the information submitted by the proponent. The Committee after deliberation decided to obtain the following from the project proponent for reconsideration:

1. Road width (RoW) in front of the project site, height of the building, distance to the nearest fire station and NOC from Disaster Management Authority.

2. NOC from BWS&SB for water supply.

The proponent has submitted the above information on 21.05.2012 with response to this office letter dated: 18.04.2012.

The subject was placed before SEAC in the meeting held on 07.07.2012. The Committee noted that as per the above letter:

a) The approach road (i.e. 7th Main Road) width to the project site is 12.75 m and height of the proposed building is 95 m.

b) The Main Road (i.e. JP Nagar Inner Ring Road) width is 18 m which is at a distance of 100 m only from the project site. The proponent has requested to consider this RoW as approach road to the project site and consider the project for issue of environmental clearance.

Page 71: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

71

 

The Committee also noted that the proponent has obtained NOC from BWS&SB on 18.04.2012 itself and has submitted it now. The Committee felt that the road width is not complying with the O.M. dated 07.02.2012 issued by MoEF, GoI on high rise buildings. The Committee after deliberation decided to send the proposal to SEIAA with this remark for suitable action since all other requirements are complying.

The subject was placed in the 54th SEIAA meeting held on 06.08.2012 and the Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority observed that, the proceedings of the SEAC does not reveal any decision of the Committee in the spirit of the EIA Notification, 2006. The Authority observed that as per para 7 (i) Stage (4) para (i), the Expert Appraisal Committee is to make a categorical recommendations either for grant of Environmental Clearance with stipulated conditions or for rejection of the application with reasons for the same. The relevant para is reiterated below:

"On conclusion of this proceeding, the Expert Appraisal Committee or State Level Expert Appraisal Committee concerned shall make categorical recommendations to the regulatory authority concerned either for grant of prior environmental clearance on stipulated terms and conditions, or rejection of the application for prior environmental clearance, together with reasons for the same."

The Authority after discussion, decided to send the proposal back to SEAC for making categorical recommendation in accordance with the provisions of EIA Notification, 2006.

The Authority also decided to send a note to Secretary, SEAC with a copy to the Chairman, SEAC, briefly covering the statutory requirement with regard to recommendation to be made by SEAC to the Authority with a request to read out the relevant provision in the ensuing Committee meeting.

The Committee after deliberations decided to strictly adhere to the above provision of the EIA Notification, 2006 while making recommendations to the SEIAA for environmental clearance. The Committee reiterated the decision taken in the 80th SEAC proceedings held on 17.03.2012 wherein it was decided to (i) strictly adhere to the guidelines stipulated in the O.M. (ii) obtain the details with respect to the O.M. from the proponent and (iii) recommend to SEIAA such proposals which are not complying with the O.M. for closure with a request to proponent to apply afresh with revised proposal before SEIAA.

The Committee after deliberations noted once again that the proposal submitted by the proponent does not comply with the provisions of the O.M dated 07.02.2012 and therefore decided to recommend the proposal to SEIAA for closure with a request to the proponent to apply afresh before SEIAA in compliance to the O.M if he is willing.

The proponent have submitted a letter dated 3.10.2012 to the Authority requesting for

granting time for submission of the revised proposal.

The Authority perused the proposal and took note of the recommendation of the SEAC and as well as the submission made by the proponent.

The Authority after discussion decided to provide time up to 31.10.2012 for submission of

the revised proposal. The Authority also decided to send the file to SEAC along with the revised proposal if submitted, in accordance with EIA Notification, 2006. In case the revised proposal is not submitted till 31.10.2012, the file shall be closed.

Page 72: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

72

 

4. Bagmane Peridot & Garnet (WTC 6 & 7), SEZ Development, Sy. No. 103, 104, 105/2, 37/2, Mahadevpura village, K.R.Puram Hobli, Bangalore East Taluk (SEIAA 9 CON 2012)

M/s. Bagmane Constructions Pvt. Ltd., have applied for EC from SEIAA for their New proposed residential project “Bagmane Peridot & Garnet (WTC 6 & 7)” at Survey Nos,103, 104, 105/2, 37/2, Mahadevpura Village, K.R.Puram Hobli, Bangalore East Taluk, Bangalore under 8(a) of schedule of EIA Notification, 2006 under category-B requiring EC from SEIAA. Total project cost: Rs. 190.35 Crores. Project comes under BBMP. Land converted from DC office. The project comes under SEZ area vide MoCI notification dated 11.07.2008.

Project Details: (a) Land: Total plot area: 24,865.27 Sqm; Total built up area: 1, 29,642.04 Sqm. The project consists of SEZ Development in two Blocks having 2 Basements + Ground Floor + 13 Upper Floors. (b) Greenery: Landscape area: 7,918.32 Sqm (32% of plot area). (c) Water Requirement: Total water requirement is 500 KLD of which fresh water requirement is 242 KLD; Source of water: BWSSB. (d) Soil: Total excavated soil: 69,527 Cum; Backfilling Quantity: 2500 Cum and landscaping quantity: 12010 Cum within the project site. (e) Sewage: Total quantity generated: 36 KLD, treated in proposed STP of design capacity 400 KLD with EAS; Sludge generated: 20 Kg/day used as manure. (f) Solid Waste: Total generated: 1500 Kg/day; Organic waste: 600 Kg/day used as manure. Inorganic waste: 900 Kg/day will be sent for recycling. (g) Power Requirement: Total Requirement: 7499 KVA from BESCOM; Power Backup: 1500 KVA DG sets 6 Nos. (h) Parking: 1019 Numbers.

Project Surrounding Details: K.R. Puram Railway Station – 5 Kms. Bangalore International Airport - 40 Kms. Bangalore City- 55 Km; Doddanekkundi lake-1km; Other Details: Rain Water Harvesting is proposed.

The subject was placed in the 79th SEAC meeting held on 9/10.02.2012 and the proponent present explained the project. The proponent informed that the Mahadevapur Lake is 50 m on the downstream side of the project site. The 30 m distance is left from the project building to the boundary of the lake. The project comes under mutation corridor. The project site is connected by ORR which connects KR Puram on one site and Marathahalli on the other side. The project is also connected to Goshala road which is connected to ORR. The existing, projected and modified LoS for ORR is C-E->F (road towards KR Puram) and D->F->F (road towards Marathahalli). The same for road towards Goshala road is A-B-D.

The Committee also decided that a condition in environmental clearance is to be stipulated that BDA norms are to be followed in respect of water body located near to the project site and the buffer should be maintained as NDZ and greenery without any paved area.

After deliberation, the Committee decided to reconsider the proposal after obtaining the following information from the proponent.

1. Revised land use pattern showing percentage of greenery on natural ground. 2. Enlarged version of the CDP with project site survey number marked. 3. Drainage pattern details along with contour plan. 4. Dated peak hour traffic density photographs. 5. Social commitment plan for Rs. 19 Lakhs, as committed by the proponent.

Page 73: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

73

 

The proponent has submitted the above information on 07.03.2012 in response to this office letter dated: 23.02.2012.

The subject was again placed in the 81st SEAC meeting held on 07.04.2012 and the Committee discussed in detail the information submitted by the proponent. The Committee after deliberation decided to obtain the following details from the project proponent for reconsideration:

a) Road width (RoW) in front of the project site, b) height of the building, c) distance to the nearest fire station and d) NOC from Disaster Management Authority considering the entire boundary shown on the

total overall plan of all the Bagmane projects.

The above information sought from PP on 18/04/2012 and the subject was placed in the 83rd SEAC meeting held on 25.05.2012 for closure. The Committee was discussed the status of the file placed before the Committee in detail and decided to recommend to SEIAA for closure since the proponents have not responded with replies even after issue of final notice.

The subject was placed in the 53rd SEIAA meeting held on 06.07.2012 and the Authority noted that the required information have been submitted and therefore decided to send the file back to SEAC for appraisal and sending suitable recommendation as deemed fit.

The Committee observed that the proponent was given 30 days time for submission of the required information on or before 18.05.2012 as per the SEAC letter dated 18.04.2012. The proponent has not submitted the information even on 25.05.2012 being the date of 83rd SEAC meeting. Hence the Committee had recommended to SEIAA the proposal for closure. The Committee noted that the proponent has submitted the information on 29.05.2012 after the decision of the SEAC for closure. Hence the Committee decided to recommend the proposal to SEIAA for closure with a request to the proponent to make fresh application before SEIAA.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project is taken up without prior Environmental Clearance.

5. Bagmane Amber (WTC 9), SEZ Development, Sy. No. 34/1, 35/1, 36/1 & 2, 37/2, Mahadevpura village, K.R.Puram Hobli, Bangalore East Taluk by M/s Bagmane Constructions Pvt. Ltd. (SEIAA 68 CON 2012)

The proposal has been considered in the SEAC meeting held on 25th /26th May 2012. Abstract of the minutes is given below.

"M/s. Bagmane Constructions Pvt. Ltd., have applied for Environmental Clearance (EC) from SEIAA for their new proposed SEZ development project called "Bagmane Amber (WTC 9)" at Survey Nos: 34/1, 35/1, 36/1, 2, 37/2, Mahadevpura Village, K. R. Puram Hobli, Bangalore East Taluk, Bangalore under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 50.55 Crores. Project comes under BBMP; Land conversion obtained from DC vide letter dated 04.10.2008, 16.04.2009, 11.06.2009 & 26.04.2005.

Page 74: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

74

 

Project Details: Land: Total plot area: 8,903.02 Sqm; Total built up area: 21,809.06 Sqm. Project consists of one blocks with B+G+11 UF. Landscape area: 2,729.44 Sqm (30.65% of plot area). Water Requirement: Total water requirement is 90 KLD; Fresh water requirement: 50 KLD, sourced from BWS&SB. Excavated Earth: Total Quantity of excavated earth: 27,500 Cum; Sewage: Total quantity generated: 80 KLD, treated in proposed STP of design capacity 80 KLD adopting extended aeration activated sludge process; Sludge generated: 4 kg/day used as manure. Municipal Solid Waste: Total generated: 495 kg/day; Organic waste: 200 kg/day treated in organic convertor and product used as manure. Inorganic waste: 295 kg/day will be sent for recycling. Power: Total Requirement: 2022.82 KVA from BESCOM; Backup Power: DG sets of 3 X 1250 KVA.

Project surrounding details: Mahadevapura Lake 3 to 5 m and Doddanekundi lake is 1 --. Other details: Rain Water Harvesting is proposed. NOC from BWS&SB not submitted.

The proponent and the consultant present in the meeting explained the project. The proponent informed that the height of the proposed building is 49.35 m; the RoW of the existing road in front of the building is 45 m., The nearest Fire Station is at a distance of 3.5 km. the level difference in the project site is 2.5 m with the lowest ground level located adjacent to Mahadevapura Lake.

The Committee observed that raja kaluve might be there in between the two lakes namely Mahadevapura and Doddanekundi. The proponent informed that they are taking up 9 WTC towers and another 4 WTC towers are proposed and the combined impact of all these towers will be presented before the Committee with Master Plan. The proponent informed that the excess treated water from WTC 2 project of Bagmane constructions will be utilized for construction purpose in this project. The project site is located along Goshala road which connects ORR on one site and Garudacharplaya on the other side. The ORR connects Marathalli on one side and K. R. Puram on the other side. The existing, projected and modified LoS of ORR road is C-E-E (road towards K. R. Puram), D->F->F (road towards Marathalli) and the same for Goshala road is A-B-C.

The Committee after deliberation decided for a site inspection by a sub committee consisting of SEAC members namely Dr. Bela Zutshi, Dr. Manoj Kumar and Sri. M. B. Girish to find out the course of flow from upper lake to lower lake as well as the arrangements proposed by the project proponent for protection of lake and the raja kaluve.

The Committee also decided to obtain the following information from the project proponent:

1. Dated site photographs. 2. STP flow chart. 3. Parking details. 4. Excess earth work quantity and disposal details. 5. Protective measure for lake and raj kaluve. 6. Lowest ground level of the project site adjacent to lake and maximum water level in

lake. 7. Quantity of the treated wastewater generated inWTC2 and its disposal. 8. Changes in WTC 2 water balance since the STP treated water from WTC 2 project

will be utilized for construction purpose in this project 9. Social commitment plan for Rs. 5 Lakhs, as committed by the proponent during

meeting (letter not given)

Page 75: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

75

 

Action to be taken: Secretary, SEAC to obtain the above information, the site inspection report from the subcommittee and recall the proponent for the presentation before the SEAC."

Accordingly the information was sought vide letter dated 11.6.2012. Since no information was received the subject was again placed in the SEAC meeting held on 24th /25th August 2012. The committee have decided to recommend the proposal for closure as the information has not been submitted by the proponent in time.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project is taken up without prior Environmental Clearance.

6. Residential Apartments, Sy No’s 11/2, 130/5, Kammasandra Village,Attibele Hobli, Anekal taluk,Bangalore Urban District by M/s Nandhini Hotels Pvt. Ltd. (SEIAA 88 CON 2012)

The proposal has been considered in the 84th SEAC meeting held on 22-23/06/2012. Abstract of the minutes is given below.

"M/s Nandhini Hotels Private Limited have applied for Environmental Clearance (EC) from SEIAA for their new proposed Residential Apartment project at Sy No’s 11/2, 130/5, Kammasandra Village, Attibele Hobli, Anekal Taluk, Bangalore Urban District under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 32 Crores. Project comes under Hebbagodi Grama Panchayth.

Project Details: Land: Total plot area: 9611.21 Sqm; Total built up area: 30,022.25 Sqm. Project consists of 170 units with Basement Floor + Ground Floor and 7 Upper Floors. Landscape area: 2979.47 Sqm (31% of plot area). Water Requirement: Total water requirement is 125 KLD sourced from Hebbagodi Grama Panchayth. Excavated Earth: Total Quantity of excavated earth: 16788.75 Cum; backfilling quantity: 5036.62 Cum; landscaping quantity: 1903.01 Cum; Mound Creation in land scaped area: 1678.87; balance soil carted out to neighboring Agricultural lands/brick kilns – 8170.25 cum; Sewage: Total quantity generated: 100 KLD, treated in proposed STP of design capacity 102 KLD; Sludge generated: 15.30 kg/day used as manure. Municipal Solid Waste: Total generated: 383 kg/day; Organic waste: 230 kg/day treated in organic convertor and product used as manure. Inorganic waste: 153 kg/day will be sent for recycling. Power: Total Requirement: 500 KVA from BESCOM; Backup Power: DG sets of 2X250 KVA; Parking: 194 Numbers. Other details: Rain Water Harvesting is proposed.

The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 21.6 m and the RoW of the existing road in front of the project site is 18 m. The fire station is 3.5 km away from the project site. The proponent informed that the Kammasandra Lake is 3 km away from the project site. A kharab land of 2 Gunta extent is situated within the project site. The Committee advised the proponent to enhance the landscape by

Page 76: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

76

 

growing trees in the kharab land. The level difference in the project site is 4.5m. The proponent informed that the project site is located near to Singena Agraha to Chandapura road and the LoS remains at A. There is no UGD at present in the project site.

After deliberation, the Committee decided to reconsider the proposal after obtaining the following information from the proponent:

1. MoU for disposal of balance excavated earth. 2. Details of landscape area occupying 33 % of the plot area. 3. Scientific assessment of the Panchayath borewells with quality and quality and its

impact on the competitive users. 4. Rework on the water balance chart with realistic assessment of treated water usage. 5. Revised STP flow chart. 6. Social Commitment Plan for Rs. 3 Lakhs on letterhead as committed.

Action to be taken: Secretary, SEAC to obtain the above information and place it before the SEAC. "

Accordingly the information was sought vide letter dated 3.7.2012. Since no information was received the subject was again placed in the SEAC meeting held on 24th /25th August 2012. The committee have decided to recommend the proposal for closure as the information has not been submitted by the proponent in time.

The proponent in the mean time have submitted the information vide letter dated

1.10.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC and as well as the information submitted by the proponent.

The Authority after discussion, decided to send the file back to SEAC for appraisal in

accordance with the EIA Notification, 2006 to send recommendation as deemed fit on its merit.

7. Residential Apartment by at Sy. No: 37, Vasanthapura Village, Uttharahalli Hobali Bangalore South Taluk, Bangalore by M/s. Comfort Builders & Developers (SEIAA 92 CON 2012)

The proposal has been considered in the 84th SEAC meeting held on 22-23/06/2012. Abstract of the minutes is given below.

"M/s. Comfort Builders & Developers have applied for Environmental Clearance (EC) from SEIAA for their new proposed residential apartment project at Survey Nos: 37, Vasanthapura Village, Uttharahalli Hobli, Bangalore South Taluk, Bangalore under 8(a) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 40 Crores. Project comes under BBMP. Land conversion obtained from DC.

Project Details: Land: Total plot area: 13,258.27 Sqm; Kharab area: 202.41 Sqm; Net plot area: 13055.86; Total built up area: 41,893.97 Sqm. Project consists of 216 flats with B+G+11 UF. Landscape area: 6064.44 Sqm (46.45 % of plot area). Water Requirement: Total water requirement is 145.8 KLD; Fresh water requirement: 112.8 KLD, sourced from BWS&SB.

Page 77: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

77

 

Excavated Earth: Total Quantity of excavated earth: 23,000 Cum will be used within the project site for landscaping of gardens and road making etc. Sewage: Total quantity generated: 116.6 KLD, treated in proposed STP of design capacity 120 KLD; Sludge generated: 5 kg/day used as manure. Municipal Solid Waste: Total generated: 324 kg/day; Organic waste: 194.4 kg/day treated in organic convertor and product used as manure. Inorganic waste: 129.6 kg/day will be sent for recycling. Power: Total Requirement: 1.5 MW from BESCOM; Backup Power: DG sets of 2 X 500 KVA; Parking: 240 Numbers.

Project surrounding details: Konanakunte Lake: 1.5 km; Puttenarahalli Lake: 3.4 km; Jayachamarajkendra Industrial Estate: 2.4 km; Other details: Rain Water Harvesting is proposed. Land records submitted.

The proponent and environmental consultant present explained the project. The proponent informed that the height of the building is 36 m and the RoW of the existing road in front of the project site is 18 m. The fire station is 6 km away from the project site. The level difference in the project site is 2.706 m sloping towards the road. There is no UGD at present. The project proponent informed that the project site is located along Dodda Kallasandra Village road which connects Kannakapur Main road which in turn connects Kannakapura on one side and Bangalore City other side. The existing, projected and modified LoS of Kannakapura Main road is C-E-E (Road towards Kannakapura) and D->F->F (Road towards Bangalore City) and the same for Dodda Kallasandra Village road is B-B-C.

After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of

environmental clearance after obtaining the following information from the proponent. 1. NOC from BWS&SB for water supply. 2. Enhanced energy savings. 3. Social Commitment Plan for Rs. 4 Lakhs on letterhead as committed.

Action to be taken: Secretary, SEAC to recommend the proposal to SEIAA after obtaining the above information from the proponent. "

Accordingly the Secretary, SEAC has addressed a letter dated 3.7.2012 to the proponent for submitting the above information.

The proposal was again placed before the SEAC during the meeting held on 24th /25th

August 2012 for having not received the information sought. The committee have decided to recommend to close the file.

In the mean time the proponent have submitted the information sought by the SEAC vide letter dated 7.09.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC and as well as the information submitted by the proponent.

The Authority noted that as per para 7(IV)(iii) of the EIA Notification, 2006,

"recommendation of the State Expert Appraisal Committee Shall be placed before the competent Authority for a final decision within the next fifteen days."

Page 78: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

78

 

The Authority also noted the EIA Notification, 2006 does not provide for revision of decision by SEAC unless the proposal is referred back by the Regulatory Authority to do so.

The Authority opined that, in view of the above provision, the proposal needs to be considered in accordance with the recommendation made by SEAC during the meeting held on 22-23/06/2012 along with the information submitted by the proponent on 25.09.2012 for issue of EC.

The Authority after discussion decided to issue Environmental Clearance subject to submission of the following information.

a) Authentic document with regard to ROW. b) Status of UGD and plan for disposal of excess treated water in the absence of UGD c) Revised specific social commitment plan with activity, budget and time frame.

8. "Falnir Terraces", Residential Apartment, Sy.no.686/1 (Part) No.86, Attavar Village, Mangalore Taluk, Dakshina Kannada District by Rosedale Associates (SEIAA 141 CON 2012)

M/s. Rosedale Associates., have applied for Environmental Clearance (EC) from SEIAA for their new proposed residential Apartment “Falnir Terraces” project at Survey Nos: 686/1 (Part) No.86 Attavar Village, Mangalore Taluk, Dakshina Kannada District under 8(a) of Schedule of EIA Notification, 2006 under category-B. RTC submitted.

Project Details: Land: Total plot area: 5060.00 Sqm; Total built up area: 22059.12 Sqm. Project consists of 102 flats with residential units + Multipurpose hall with associated amenities. With consists of 2 basements + Ground + 18 Upper Floors Landscape area: 1952 Sqm (38.57% of plot area). Water Requirement: Total water requirement is 52.8 KLD of Freshwater + Recycled water 33.2 KLD, sourced from Mangalore City Corporation and open well in case of scarcity. Sewage: Total quantity generated: 47.2 KLD, treated in proposed STP of design capacity 65 KLD; Sludge generated is used as manure. Municipal Solid Waste: Total generated: 200 kg/day; Organic waste: 100 kg/day treated in organic convertor and product used as manure. Inorganic waste: 80 kg/day will be sent for recycling. Power: Total Requirement: 600 KVA from MESCOM; Parking: 124 Numbers.

Other details: Rain Water Harvesting is proposed.

The proposal was considered in the SEAC meeting held on 24/25.08.2012. The proponent present in the meeting and informed that the road in front of the project site is 12 m wide and the height of the building is 59.95 m. The fire station is 1.5 km away from the project site. The Committee observed that as per the O.M dated 07.02.2012 issued by MoEF, GoI regarding guidelines for high rise building, the minimum RoW stipulated for the height of the building varying from 45 to 60 m is 24 m and as such the project does not comply with the stipulated guidelines of the O.M. The Committee after deliberation decided to recommend the proposal to SEIAA for closure.

The Authority perused the proposal and took note of the recommendation of the SEAC

The Authority after discussion, decided to close the file as the proposal is not meeting the criteria laid down in the O.M dated 07.02.2012 issued by the MOEF, GOI, with regard to ROW with a liberty to the proponent to submit fresh proposal if need be following the due procedure of law.

Page 79: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

79

 

9. "Nitesh Plaza", Residential Apartment, Sy.no.16, Ali Askar Road, Bangalore District by M/s Nitesh Estates Limited (SEIAA 147 CON 2012)

M/s. Nitesh Estates Limited have applied for Environmental Clearance (EC) from SEIAA for their new proposed “Nitesh Plaza” Mixed Development project at Sy.No. 16, Ali Askar Road, Bangalore under 8(b) of Schedule of EIA Notification, 2006 under category-B. Total project cost is Rs. 172.6 Crores. Project comes under BBMP limits.

Project Details: Land: Total plot area: 9878.639 Sqm; Total built up area: -49756.57 Sqm. Project consists of 2.5 Basement Floors + Ground Floor + Upper Ground Floor+ 26 Upper Floors. Landscape area: 2104.726 Sqm. Water Requirement: Total water requirement is 191.472 KLD; Fresh water requirement: 140.662KLD, sourced from BWSSB. Excavated Earth: Total Quantity of excavated earth: 68797Cum; backfilling quantity: 5450 Cum; landscaping quantity: 526 Cum and balance shall be disposed of scientifically. Sewage: Total quantity generated: 175 KLD, treated in proposed STP of design capacity 175KLD; Sludge generated: - 9 kg/day used as manure. Municipal Solid Waste: Total generated: 760kg/day; Organic waste: 300 kg/day treated in organic convertor and product used as manure. Inorganic waste: 460 kg/day will be sent for recycling. Power: Total Requirement: 2641 KVA from BESCOM; Backup Power: DG sets of 3X1500 KVA; Parking: 522 Numbers.

Project surrounding details: Ulsoor Lake – 6km. Other details: Rain Water Harvesting is proposed.

The proposal was considered in the SEAC meeting held on 24/25.08.2012. The proponent present in the meeting and informed that the road in front of the project site is 16.83 m (average) wide and the height of the building is 146 m. The Committee observed that as per the O.M dated 07.02.2012 issued by MoEF, GoI regarding guidelines for high rise building, the minimum RoW stipulated for the height of the building varying above 60 m is 24 m and as such the project does not comply with the stipulated guidelines of the O.M. The Committee after deliberation decided to recommend the proposal to SEIAA for closure.

The Authority perused the proposal and took note of the recommendation of the SEAC.

The Authority after discussion, decided to close the file as the proposal is not meeting the criteria laid down in the O.M dated 07.02.2012 issued by the MOEF, GOI, with regard to ROW with liberty to the proponent to submit fresh proposal if need be following the due procedure of law.

Mining Projects:

1. "Bellary Bandi Granite Quarry" at Sy.No. 492/bp1, Harapahalli village, Harappanahalli Taluk, Davanagere District by Sri D.Narayanappa (SEIAA 7 MIN 2012)

The proposal has been considered in the 85th SEAC meeting held on 7/07/2012. Abstract of the minutes is given below.

"M/s. Bellary Bandi Granite Quarry have applied for EC from SEIAA for their proposed New Quarry with production of Granite at 100 TPD (Building stones) at Sy. No. 492/bp1 of Harapanahalli Village and Taluk, Davanagere District over an area of 1.21 Ha (3.00Acres) of Government (Revenue) Land / Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying/: Open

Page 80: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

80

 

Cast manual. Project Surrounding Details: 1) The project site is connected to State Highway-26 (Harappanahalli – Harihara). 2) Reserve Forest – Jattian Katti Reserve Forest is 4 km away. The proponent has submitted the Notification dated 08.03.2009 for Quarry Lease issued by DMG.

The proponent present explained the project. The members informed that circulation material has not been received. The Committee after deliberation, decided to defer the subject and to take up the project for appraisal after obtaining the following details/documents from the project proponent:

1. Approved mining plan from IBM/Department of Mines and Geology as the case may be.

2. Environmental Management Plan (EMP) 3. Details of the distance in kilo meters from the project site to sanctuaries, national

parks, monuments, interstate boundaries, reserve forests and water bodies (if any). 4. Duly filled up format (check list) of details of the project.

Action to be taken: Secretary, SEAC to obtain the above information and place it

before SEAC for appraisal."

Accordingly a letter was addressed to the proponent on 17.7.2012. Since there was no response from the proponent, the proposal was again placed before SEAC during the meeting held on 24th/25th August, 2012. The Committee have decided to recommend for closure.

The Authority perused the proposal and took note of the recommendation of the SEAC. The Authority decided to close the file for non submission of required information.

2. Building Stone quarrying, Sy.No.93, Kallanakere village, K.R.Pete Taluk, Mandya

District by Sri Manjunath (SEIAA 11 MIN 2012)

The proposal has been considered in the 85th SEAC meeting held on 7/07/2012. Abstract of the minutes is given below. "Sri. Manjunath have applied for EC from SEIAA for their proposed New Building Stone (Grey Granite) over an extent of 10 Acres of Government (Revenue) Land at Sy. No. 93 of Kallanakere Village, K.R.Pet Taluk, Mandya District under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. The total project cost is Rs. 8.00 Lakhs. Proposed Method of Quarrying: Open Cast Manual. Total Geological Reserve: 33,00,000 cum; Total Estimated Reserve: 10.76 Tonnes.

Project Details: (a) Land: The Quarry Lease area is Non- Agricultural Revenue (Government Gomal Land) Land. Total Over Burden waste: 15,000 in first 5 years. Project Surrounding Details: Mandagere – 20 km, National High way – 47 km, Kikkeri Town – 2.5 km, Melkote Wildlife Zone – 8.00 km ( As per DCF report dated 29.02.2012), Kundur Forest Area – 2.00 km.

The proponent present explained the project. The Committee after deliberation, decided to defer the subject and to take up the project for appraisal after obtaining the following details/documents from the project proponent:

Page 81: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

81

 

1. Approved mining plan from IBM/Department of Mines and Geology as the case may be.

2. Environmental Management Plan (EMP). 3. DC letter permitting the activity in Government Gomal land. 4. Details of aerial distance in kilo meters from the project site to Melukote wildlife zone,

sanctuaries, national parks, monuments, interstate boundaries, reserve forests and water bodies (if any).

5. Duly filled up format (check list) of details of the project.

Action to be taken: Secretary, SEAC to obtain the above information and place it before SEAC for appraisal. "

Accordingly a letter was addressed to the proponent on 17.7.2012. Since there was no response from the proponent, the proposal was again placed before SEAC during the meeting held on 24th/25th August, 2012. The Committee have decided to recommend for closure.

In the mean time the proponent have submitted the information vide letter dated 15.9.2012

and 17.9.2012.

The Authority perused the proposal and took note of the recommendation of the SEAC. The Authority after discussion decided to send the proposal back to SEAC for further necessary action in accordance with law as the information sought by the SEAC stand submitted.

3. Multicolour Granite, Sy.No. 30, Parvathapura Village, Magadi Taluk, Ramanagar District by Sri G. Srinivasan Spectro and Co. (SEIAA 20 MIN 2012)

The proposal has been considered in the 85th SEAC meeting held on 7/07/2012. Abstract of the minutes is given below.

"Sri. G. Srinivasan (M/s. Spectro & Co.) has applied for EC from SEIAA for their proposed

New Quarry with production of Multi color Granite at 500 cum/year at Sy. No. 30 of Parvathapura Village, Magadi Taluk, Ramanagara District over an area of 0.51Ha (0.30 Acres) of Patta Land under Schedule 1 (a) of EIA Notification, 2006 read with O.M. dated 18.05.2012 of MoEF under Category- B. Proposed Method of Quarrying: Open Cast Manual. Mineable reserves – 22,230 cum.

Project Details: (a) Land Use pattern: Quarry– 0.25 Ha; Waste Dumps- 0.09 Ha; Roads – 0.05 Ha; Infrastructure – 0.01 Ha; Green Belt 0.02 Ha; Project Surrounding Details: Magadi Town – 2.5km.

The proponent submitted the land documents (RTC), NoC issued by DC, Ramanagar dated 31.03.2009, N.A conversion issued by DC, Ramanagar dated 10.06.2010 and Government Notification dated 20.12.2011 by Commerce and Industry Department, Government of Karnataka.

The proponent present explained the project. The proponent informed that the land as per RTC belongs to Sri. Rangaswamiah S/o Gangaiah and the proponent he has obtained consent letter from Sri. Rangaswamiah for the purpose of sanction of quarry lease from DMG. The Committee after deliberation, decided to defer the subject and to take up the project for appraisal after obtaining the following details/documents from the project proponent:

Page 82: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

82

 

1. Letter of consent from Sri. Rangaswamiah S/o Gangaiah. 2. Approved mining plan from IBM/Department of Mines and Geology as the case may

be. 3. Environmental Management Plan (EMP) 4. Details of the distance in kilometres from the project site to sanctuaries, national parks,

monuments, interstate boundaries, reserve forests and water bodies (if any). 5. Duly filled up format (check list) of details of the project.

Action to be taken: Secretary, SEAC to obtain the above information and place it before SEAC for appraisal."

Accordingly a letter was addressed to the proponent on 17.7.2012. Since there was no response from the proponent, the proposal was again placed before SEAC during the meeting held on 24th/25th August, 2012. The Committee have decided to recommend for closure.

The Authority perused the proposal and took note of the recommendation of the SEAC. The Authority decided to close the file for non submission of required information.

Miscellaneous Projects:

Construction projects:

1. Expansion of "Ivory Towers", Residential Apartment at R.S.No.762, 784, 788, 782, 780/1B, 781, 766, 768/2, T.S.No.726(P), 704(P), 700, 706 (P), 708/1B (P), 707 (P), 722/2(P), 720/2 (P), Corporation Khatha No.5183, Attavar Village, Mangalore Taluk, Dakshina Kannada District by M/s Mohtisham Complexes Pvt. Ltd. (SEIAA 115 CON 2011)

It is a proposal for expansion of Residential Apartment and club house with addition of 15 flats. The total project consists of 197 flats with 2 Basement + Ground floor & 17 Upper floors (Additional 3 floors) and Club house & Commercial shops with Basement+ Ground Floor+ First Floor on an area of 12951.61 Sq.m and with the total built up area of 52,563.07 Sq.m. The total water requirement is 147 KLD and the expansion cost is Rs. 4.39 crores. Total parking provided is for 252 cars.

The Authority have issued Environmental Clearance vide letter dated SEIAA 115 CON 2011 dated 21st June 2012.

The proponent have submitted a representation dated 01.08.2012, seeking corrigendum for the Environmental Clearance issued vide letter dated 21st June 2012 with regard to reduction of STP capacity to 60 KLD instead of 150 KLD as only 60 KLD water is required to be treated for flushing and other non potable purposes. The proponent have further submitted that to save the operation and maintenance cost and to save energy they proposed to install STP of 60 KLD.

The proponent has further submitted a letter dated 28.09.2012 informing that the request made vide letter dated 1.8.2012, pursuant to the discussion he had with the Member Secretary of the Authority, stands withdrawn.

Page 83: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

83

 

  The Authority observed that the capacity of STP as determined during detailed appraisal is fixed and requires no revision. The entire sewage is to be treated as to avoid additional load on the existing infrastructure of sewer line and excess treated waste water only to be discharged to the existing sewer network.

The Authority after discussion, decided that the letters may be filed as no action is needed.

2. "Micasa", Proposed Residential Apartment, Sy.No. 39, Bellahalli Village, Bangalore North Taluk, Bangalore by M/s Canter B & B Infrastructure (SEIAA 38 CON 2010)

It is a proposal for construction of "Micasa", Residential Apartment of 198 units & 139 Row Houses, comprising 12 towers in ground + 10 floors, and a club house on a site area of 7116.05 Sqm and total built up area of 27,979.05 Sqm. The water requirement is 150 KLD and investment is ` 42 crores. The parking provided is for 284 cars.

The proposal was discussed in the Authority meeting held on 10.02.2011. The Authority noted that an application has been submitted to BWS&SB for NoC with regard to supply of water. After discussion, the Authority decided to clear the proposal for issue of Environmental Clearance after the receipt of the NoC from BWS&SB. Accordingly, a letter was addressed to the proponent on 18.02.2011. The proponent vide letter dated 22.02.2011 have submitted a copy of the recommendation made by the Executive Engineer for issue of NOC.

The letter was placed before the Authority during the meeting held on 17.06.2011. The Authority decided to provide a last opportunity with a minimum of 30 days time.

Accordingly a letter has been addressed to the proponent vide letter dated 30.06.2011.

In response the proponent letter dated 14.07.2011 requesting not to initiate any action as the NOC would be submitted shortly. Subsequently the proponent vide letter dated 21.09.2011 submitted a Demand Note issued by the BWS&SB to make payment for the NOC.

As the NOC was not received so far, a last reminder was issued on 18.08.2012 directing the proponent to submit the NOC latest by 30th August 2012 and the proponent have been informed that the file will be closed if the NOC is received within the stipulated time.

The NOC has not so far been submitted.

The letter addressed to the proponent has been returned by the Post and Telegraph Department with a remark that the company has left.

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project has been taken up without prior Environmental Clearance.

Page 84: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

84

 

3. Shopping Mall and Multiplex, Sy.No.27/66, (Old No.17), Kempegowda Road, BBMP Ward No. 27, Bangalore by M/s C.B. Infrastructure & Developers Pvt. Ltd. (SEIAA 59 CON 2010)

It is a proposal for construction of Shopping Mall and Multiplex with 5 basements + ground floor + 5 upper floors on an area of 5032.67 Sqm and with a total built up area is 30,529.13 Sq.m. The total water requirement is 60 KLD and the investment is of Rs.55 crores. The total parking provided is for 379 cars.

The proposal was discussed in the Authority meeting held on 15.04.2011.

The Authority after discussion decided to get the following information for further consideration of the proposal.

1. Possible effect of excavation on the structures located within 100 meters from the boundary of the project site and plan to mitigate it.

2. Measures proposed to ensure normal air circulation and cross ventilation in 5 basements proposed.

3. Possibility of seepage and flooding of the basements especially during the monsoon season and measures proposed to prevent it.

4. Possible temperature variation and other indoor pollution aspects in the lower basement area and proposed measures for prevention of the same.

5. Safety measures proposed for the people who will be in the basements. 6. Commitment with regard to compensating the greenery in the surrounding area at least

to the level of 33 % of the project site area if there is no scope to increase green belt within the project site.

7. Safety measures proposed during construction and during the operation. 8. Possible impact on the traffic in the surrounding area mainly on parking and traffic

jams. 9. Revised specific Social Commitment Plan with activity, budget and the time frame.

The Authority also decided to invite the proponent with all the relevant information.

Accordingly, a letter was addressed to the proponent on 20.04.2011.

The information sought was not received so far even after a lapse of 16 months.

A letter was sent to the proponent vide letter dated 18.08.2012 requesting to submit the above information latest by 30th August 2012, failing which the project proposal will stand closed.

The information has not been received so far.

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project has been taken up without prior Environmental Clearance.

Page 85: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

85

 

4. "Sattva RPG", Office Building, Sy Nos. 11, 12 and 13/5, Khata Nos, 303/284/242, 303/285, 243, Bengaluru Hosur Road, Bommanahalli Village, Begur Hobli, Bengaluru South Taluk, Bengaluru District by M/s Darshita Housing Private Ltd. (SEIAA 207 CON 2011)

It is a proposal for construction of Office Building with Basement + Ground + 18 Upper floors & Terrace floor on an area of 8294.166 Sq.m and the total built up area of 42,000 Sq.m. The total water requirement is 142.65 KLD and the investment is of Rs.81 crores. The total parking provided is for 537 cars.

The proposal was discussed in the Authority meeting held 05.04.2012.

    The Authority after discussion, decided to issue Environmental Clearance subject to submission of the following information:

(a) Plan to compensate greenery. (b) Commitment / undertaking to obtain NOC / fire clearance from the Fire and Emergency

Services Department before starting the project. (c) NOC from BWSSB for supply of water (d) Authentic document with regard to width of road(RoW) (e) Revised corporate social responsibility with time frame budget and activity.

Accordingly, a letter was addressed to the proponent on 13.04.2012. The information sought was not received so far even after a lapse of 4 months.

A letter was sent to the proponent vide letter dated 18.08.2012 requesting to submit the above information latest by 30th August 2012, failing which the project proposal will stand closed.

The information has not been received so far.

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project has been taken up without prior Environmental Clearance.

5. Residential Development, Sy. Nos.27, 28/2,3,4, Kogilu village, Yelahanka Hobli, Bangalore by Sri Suresh Jain (SEIAA 105 CON 2010)

It is a proposal for construction of Residential Apartment with 342 Units & 139 Row Houses on a site area of 40816.33 Sqm and total built up area of 89,323.42 Sqm. The water requirement is 370 KLD and investment is Rs. 96.5 crores. The parking provided is for 533 cars.

The proposal was discussed in the Authority meeting held on 15.04.2011.

The Authority after discussion decided to clear the proposal for issue of environmental clearance after submission of the following.

1. NOC from BWSSB for supply of water. 2. Commitment with regard to maintain the buffer zone with the details of set back from

the nalla and water body as per BDA/BBMP bylaw. 3. Plan to ensure that the lakes in the surrounding area are not affected due to the

proposed activity and to prevent entry of sewage to the lakes/water bodies.

Page 86: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

86

 

4. Commitment with regard to likely hood of laying sewer line and the expected time within which it will be laid.

5. Plan to ensure safety of open well including safety structures to prevent any accidents. 6. Revised specific Social Commitment Plan of Rs.15 lakhs with Rs.5 lakhs each to assist

construction of houses for flood victims of Uttara Karnataka, Akshaya Patra and the ASHA Charitable Trust (Academy for Severely Handicapped and Autistic children), Bangalore as committed during the discussion.

Accordingly, a letter was addressed to the proponent on 20.04.2011.

The information sought was not received so far even after a lapse of 18 months.

A letter was sent to the proponent requesting to submit the above information latest by 25th August 2012, failing which the project proposal will stand closed.

The information has not been received so far.

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project has been taken up without prior Environmental Clearance.

6. Proposed Residential Apartment, Sy.No. 61/2, 62 and 63/2, Kasavanahalli Village, Varthur Hobli, Bangalore East Taluk, Bangalore by M/s Microgate Trading Company Pvt. Ltd. (SEIAA 61 CON 2010)

It is a proposal for construction of Residential Apartment of 585 residential units in Block A, B & C (recreation Block). Block A consists of 360 flats with Basement + Ground floor and 14 upper floors; Block B consists of 225 flats with Basement +Ground floor and 14 floors; Block C (recreation Block) consists of Ground and First on an area of 50585 Sq.m and with total built up area is 1,24,623 Sq.m. The total water requirement is 435 KLD and the investment is of Rs.189 crores. The total parking provided is for 1079 cars.

The proposal was discussed in the Authority meeting held on 17.06.2011.

The Authority noted the observation made by the sub-committee during the visit with regard to the narrow approach road and with regard to the legal notice served for demolition of the private building which is adjacent and within the site boundary.

After discussion the Authority, decided to get the following information for further consideration of the proposal:

(a) Details of approach road which is stated to be narrow and plan for managing the easy traffic flow.

(b) Details of legal notice served for demolition of private building which is said to be within the site boundary.

(c) Details of nalah duly marking on the concerned village map and the project layout plan.

Page 87: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

87

 

(d) Revised social commitment plan like supporting / assisting construction of houses for the flood affected people in North Karnataka / J.S.S poor children free education fund for the school which is at Suttur, Nanjangud Taluk, Mysore district through JSS Mahavidyapeetha, Mysore and / or assisting Akshayapatra Yojana for the mid day meal programme of school going children or any such other programmes/activities .

Accordingly, a letter was addressed to the proponent on 24.06.2011. The information sought was not received so far even after a lapse of 14 months. A letter was sent to the proponent vide letter dated 14.08.2012 requesting to submit the above information latest by 25th August 2012, failing which the project proposal will stand closed.

The information has not been received so far.

The letter addressed to the proponent has been returned by the Post and Telegraph Department with a remarks "Door lock".

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project has been taken up without prior Environmental Clearance. 7. Group Housing Development Project, Sy.No. 20-1 Part and 39-2, Kavoor Village,

Mangalore by M/s CNC Mangalore-Kavoor Project Pvt. Ltd. (SEIAA 38 CON 2009) It is a proposal for construction of Residential Apartments at Sy. No. 20-1, Part and 39-2,

Kavoor Village, Mangalore with a site area of 75,513.76 M2; built up area is 1,92,487.00 M2; Water requirement is 500 KLD and car parking provided is for 1,006 Nos. The investment of the project is Rs. 244 Crores. The proposed project comprises of 4 wings of 2 towers with 3 basements, ground and twenty two upper floors, Villas & Estate bungalows. The project comprises of 399 flats and 26 nos. of Villas & 20 Estate bungalows.

The proposal was examined by the State Level Expert Appraisal Committee (SEAC) in the meeting held on 28th & 29th January 2011. The Committee after discussion have decided to recommend the proposal to SEIAA for issue of E.C. subject to submission of the following information:

1. Carrying capacity of the sewer line and STP to carry additional 100 KLD water along with correspondence done with MCC/KUDCEMP in this regard.

2. NOC from Mangalore City Corporation for water supply. 3. Alternative source of the water along with the calculation of yield of bore well and STP capacity.

4. Social commitment plan ` 15 Lakhs as committed.

Accordingly, a letter was sent by the Secretary, SEAC on 8.2.2011. The file has been transferred to SEIAA on 9.2.2011.

The information sought by SEAC has not been received so far.

Page 88: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

88

 

The issue was discussed in the 40th SEIAA meeting held on 13th May 2011. The Authority decided to give a final opportunity for submission of the required information already sought within 30 days from the date of the letter.

Accordingly, a letter was addressed to you on 14.06.2011 requesting to submit the required information within 30 days from the date of receipt of the said letter. The information was not received so far. Therefore the final notice has been issued vide letter dated 14.08.2012 to submit the information sought by 25th August 2012. The letter addressed to the proponent has been returned by the Post and Telegraph Department with a remark that no such firm is there in the address.

The Authority after discussion decided to close the file with an intimation to the proponent

that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project has been taken up without prior Environmental Clearance.

8. "Sattva Mulberry", Office Building at Khata .No.s 10/9/9, 10/9/9E, 16/3/19/10P, 15/12. 18/10P, 11/10/11, 14-11/ 1, 10/48, 11/10/12, 12/12/1/12P, 13/11/14/13, 13/11/14, 17/14, 20/15. 18/15, 21/15P, 19/16, 22/16, Beretena Agrahara village, Begur Hobli, Bengaluru b M/s Darshita Gruha Nirman Pvt. Ltd. (SEIAA 140 CON 2011)

It is a proposal for construction of Commercial Building with Basement + Ground + 9 upper floors+ Terrace floor on an area of 5,343 sqm and the total built up area of 22,000 Sqm. The total water requirement is 57.5 KLD and the investment is of Rs. 40 crores. The total parking provided is for 349 cars.

The proposal was discussed in the Authority meeting held on 06.01.2012.

The Authority after discussion, decided to clear the proposal for issue of Environmental Clearance subject to submission of the following information:

(a) NOC from the BWS&SB. (b) Plan for increasing the greenbelt to at least 33%. (c) Specific social commitment plan with budget, activity and time frame.

Accordingly, a letter was addressed to the proponent on 16.01.2012. The proponent while submitting the reply dated 24.01.2012, submitted a copy of the Demand Note of BWS&SB instead of NOC for supply of water. The NOC has not so far been submitted. The proponent has been directed to submit the NOC by 25th August 2012 vide letter dated 14.08.2012. The information has not been received so far.

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project has been taken up without prior Environmental Clearance.

Page 89: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

89

 

9. "Bhuvana Greens", Residential Development, Sy. Nos.15/3D, 29/4(P) and 29/5, Kasavanahalli Village, Varthur Hobli, Bangalore South by Golden Gate Projects (SEIAA 71 CON 2010)

It is a proposal for construction of Residential Apartment of 220 Units and 1 Club House in 4 Towers with Basement + Ground + 10 Upper floor on an area of 14062 Sq.m and the total built up area is 39,828.65 Sq.m. The total water requirement is 156.2 KLD and the investment is of Rs.37.07 crores. The total parking provided is for 320 vehicles.

The proposal was discussed in the Authority meeting held on 22.07.2011.

The Authority perused the information submitted by the proponent and took note of the recommendation of the SEAC. The Authority observed that the letter issued by the BWS&SB is not a NOC. The project proponent has to submit the NOC issued by the BWS&SB.

The Authority after discussion, decided to clear the project for issue of Environmental Clearance subject to submission of the following information:

(a) NOC from the BWS&SB.

(b) Plan to increase greenery to atleast 33% of the project site.

Accordingly, a letter was addressed to the proponent on 28.07.2011. So far no reply has been received from the proponent.

The proponent has been directed to submit the NOC by 25th August 2012 vide letter dated 14.08.2012. The information has not been received so far.

The Authority after discussion decided to close the file with an intimation to the proponent that suitable legal action will be initiated if the project is taken up without prior Environmental Clearance. The Authority also decided to mark a copy of such intimation to the KSPCB with a direction to initiate suitable action in accordance with E(P) Act, 1986 if the project has been taken up without prior Environmental Clearance.

Industry projects: 1. Expansion for Bulk Drug, Pharmaceutical Intermediates & Job work plant at Plot

No.11-D, KIADB Industrial Area, Doddaballapur, Bangalore by M/s Hexagon Bio-Pharma Pvt. Ltd. (SEIAA 44 IND 2010)

It is a project proposal for Expansion of bulk drug, pharmaceutical intermediate & job

work. The total plot area is 4046.86 Sqm. The investment is of Rs. 5.72 crores.

The Authority have issued Environmental Clearance vide letter dated SEIAA 44 IND 2010 dated 28th April 2012

The proponent have submitted a representation dated 01.08.2012 seeking corrigendum for the Environmental Clearance issued vide letter dated 28th April 2012 with a request for issue of corrigendum to the EC issued as " Gabapantine intermediate purification on job work basis", instead of Gabapantine intermediate manufacturing.

Page 90: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

90

 

The representation was placed before the Authority for perusal and suitable decision. The Authority opined that manufacture includes purification and therefore does not make any difference.

The Authority after discussion decided to issue the corrigendum as sought for.

2. Augmentation of storage capacity for 2 x 1000 MT capacity LPG mounded storage of HPCL, Hubli LPG bottling plant at Plot No. 165/166, KIADB, Belur Industrial Area, Dharwad by Hindustan Petroleum Corporation Limited (SEIAA 21 IND 2011)

M/s. HPCL had applied for EC for their expansion of the existing Hubli LPG bottling

plant at Sy. No. 165/166, KIADB, Belur Industrial Area, Dharwad from 6 X 140 MT to 2 X 1000 MT storage capacity under item 6(b) of EIA notification under category –B within the existing premises. Cost of the project is Rs. 35 Crores. Land: total plot area: 26 acres; total proposed area for activity: 8665.32 Sqm. No additional land required for expansion; 8.5 acres land developed for green belt. Water: 0.5 to 1 KLD from borewell during construction.

Environmental clearance has been issued vide letter No. SEIAA 21 IND 2011 dated 23.05.2012 for the above project.

The proponent have submitted a representation dated 10.07.2012 seeking amendment to the Environmental Clearance issued as 3 X 650 MT mounded storage instead of 2 X 1000 MT. The representation was forwarded to SEAC as per the decision taken in the Authority meeting held on 6th August 2012. The request has been considered by the SEAC during the meeting held on 24.08.2012. Abstract of the proceedings of the SEAC is as follows:

"The proponent has obtained environmental clearance for the earlier proposal vide letter No. SEIAA 21 IND 2011 dated 23.05.2012 for setting up of 2000 MT (2 X 1000 MT) mounded storage facility at the above project site. The proponent has submitted revised proposal on 10.07.2012 along with Form – 1 for setting up of 1950 MT (3 X 650 MT) mounded storage facility due to operational reasons at the same location. The existing 6 X 140 MT bullets at the plant are proposed to be phased out in later stage. The proponent has requested for issue of amended environmental clearance for setting up of 1950 MT (3 X 650 MT) mounded storage vessel in place of 2000 MT (2 X 1000) mounded storage.

The subject was deliberated in the 54th SEIAA meeting held on 06.08.2012 and it was decided to refer the request of the proponent to SEAC for appraisal and recommendation in view of change in the configuration.

The proponent present explained the project during the SEAC meeting held on 24.08.2012. The proponent informed that the 3 bullets of 650 MT capacities each are proposed for operational convenience for receipt, delivery & standby each and they are more secured due to mounded storage. This is in lieu of 2 bullets of 1000 MT each. After deliberation, the Committee decided to recommend the proposal to SEIAA for issue of environmental clearance."

The Authority perused the proposal and took note of the recommendation of the SEAC. The Authority noted that there is no increase in the storage capacity. However, since the number of bullets will be 3 instead of 2, the Authority decided to issue corrigendum subject to condition that clearance from the Site Clearance Committee of the Department of Factories and Boilers should be taken.

Page 91: 56 SEIAA Meeting (3.10.2012).pdf

56th SEIAA Meeting Proceedings Dated 3rd October 2012

 

91

 

Meeting concluded with thanks to the Chair.

(Dr. H.S.Ramesh)

Chairman, SEIAA, Karnataka

(Dr. H.R.Rajmohan) Member,

SEIAA, Karnataka.

(Kanwerpal) Member Secretary, SEIAA, Karnataka.