57352002 earthing calculation

Upload: mourad-benderradji

Post on 04-Apr-2018

259 views

Category:

Documents


3 download

TRANSCRIPT

  • 7/30/2019 57352002 Earthing Calculation

    1/20

    Earthing Calculation

    ROW1 Ohm meter 39.29

    1.1 Soil resistivity(taken for calculation) ROW Ohm meter

    1.2 Soil resistivity due to concrete ROWS Ohm meter 500

    1.3 Fault current(for conductor size design) I KA 50.00

    1.4 Fault duration for sizing TF1 sec 1.00

    1.5 Fault duration for step and touch potentials TF2 sec 0.70

    1.6 Depth of burial of grid conductors h metres 0.80

    1.7 Thickness of concrete hs metres 0.20

    1.8 N umber of ground rod/pipe electrodes,3m long N nos 150

    1.9 Area of the earth mat AG sq.metres 640,000

    1.10 Effective earth fault current I kA 22.245

    (Refer enclosed annexure for this calculation)

    2.1 Factor K0 (1/ALPHAR)-TR

    216.412.2 TCAP is defined by

    TCAP = 4.184*SW*SH

    3.75

    2.3 Minimum area of cross section A = I*(SQRT(X1/X2))

    where

    2.4 X1 = (TF1*ALPHAR*ROWE*10000)/TCAP

    169.24

    2.5 X2 = LN(1+(TM-TA)/(K0-TA))

    1.31

    2.6 Minimum area of cross section A sq.mm 568.432.7 Diameter of conductor mm 26.91

    2.8 Temperature co-efficient of material ALPHAR 0.00423

    2.9 R esistivity of earthing material ROWE micro-ohm/ 15.00

    2.10 Specific heat of material SH cal/gram/C 0.114

    2.11 Density of material SW gram/cc 7.86

    2.12 Reference temperature of material constant TR C 20

    2.13 Max.allowable temperature for welded joints TM C 500

    2.14 Ambient temperature TA C 50

    2.15

    Average rate of corrosion is 0.12 mm per annum is considered for a period of 40 years.

    Total Corrosion expected =0.12*40 4.8 mm

    Calculations are based on IEEE Vol 80,1986 version.

    North Chennai Thermal Power ProjectStage II(2x525 MW)

  • 7/30/2019 57352002 Earthing Calculation

    2/20

    Earthing Calculation

    Calculations are based on IEEE Vol 80,1986 version.

    North Chennai Thermal Power ProjectStage II(2x525 MW)

    CS = 1-a*((1-s)/u) where

    a=0.106 metre;s=(ROW/ROW S);U=(2hs+a)

    s = 0.1000

    u = 0.506

    a = 0.11

    CS = 0.811

    3.5 Permissible Estep volts

    3.6 Permissible Etouch volts

    4

    4.1 Length of the earth mat L metres 800.00

    4.2 Breadth of the earth mat B metres 800.00

    4.3 Assumed spacing for the conductors D metres

    4.4 Total no of conductors parallel to length N1 nos (B/D)+1

    17

    4.5 Total no of conductors arallel to breadth N2 nos L/D)+117

    4.6 Total quantity of conductors laid LC metres (N1*L)+(N2*B)

    27,200

    4.7

    Interconnections to the grid(30% of calculated

    quantity) LINT metres 8,160

    4.7 Total ground rods length LR metres 450

    4.8 Effective grid conductor length L metres

    5.1 Emesh = (ROW*KM*KI*I *1000)/L5.2 E step = (ROW*KS*KI*I *1000)/L

    5.3 KM = (1/(2*3.14))*(LN(A+B-C)+D*LN(E))

    5.4 where A = D^2/(16*h*d)

    4,882.813

    5.5 B = (D+2*h)^2/(8*D*d)

    166.4100

    5.6 C = (h/4*d)

    5.000

    5.7 D = (Kii/Kh)

    0.745

    5.8 E = 8/(3.14*(2n-1))

    = 0.077

  • 7/30/2019 57352002 Earthing Calculation

    3/20

    Earthing Calculation

    Calculations are based on IEEE Vol 80,1986 version.

    North Chennai Thermal Power ProjectStage II(2x525 MW)

    5.15 KI,the irregularity factor = 0.656+0.172*n

    3.580

    5.16 KS = (1/3.14)*(A+B+C(1-E))

    WHERE

    5.17 A = 1/ 2*h)

    0.625

    5.18 B = (1/(D+h))

    0.0205.19 C = 1/D

    0.020

    5.20 E = 0.5^(n-2)

    0.0000305

    5.21 KS = 0.2117

    5.22 Hence E step KS*KI*ROW*I *1000/L

    Volts

    Volts

    To achieve the above conditions,the following condition has to be satisfied.

    6.1 L = (KM*KI*ROW*I *1000)/Permissible Emesh

    metres

    7.1 RG ohm ROW*(F+G*(1+(1/J)))

    where

    7.2 F = (1/L)

    0.00003

    7.3 G = 1/(SQRT (20*A))

    0.000287.4 J = 1+(h*(SQRT (20/A)))

    1.004

    7.5 Hence RG = ohm

    8

    Total grid potential rise IR Volts I*RG

    volts

    Hence from the above calculation the conductors

    provided meet the Step and touch potential criter ia

    and also the other re uirement.

    The mat will be made to suit the above requirement.

    As shown in the enclosed diagram.

  • 7/30/2019 57352002 Earthing Calculation

    4/20

    Calculations are based on IEEE Vol 80,1986 version.

    1 Parameters for design purposes:1.1 Soil resistivity ROW Ohm meter 45.0

    1.2 Soil resistivity due to concrete ROWS Ohm meter 500

    1.3 Fault current I KA 50.00

    1.4 Fault duration for sizing TF1 sec 1.00

    1.5 Fault duration for step and touch potentials TF2 sec 0.70

    1.6 Depth of burial of grid conductors h metres 0.80

    1.7 Thickness of concrete hs metres 0.20

    1.8 Number of ground rod/pipe electrodes,3m long N nos 10

    1.9 Area of the earth mat AG sq.metres 10,0001.10 Effective earth fault current Ia kA 23.40

    2 Evaluation of conductor sizing

    2.1 Factor K0 (1/ALPHAR)-TR

    216.41

    2.2 TCAP is defined by

    TCAP = 4.184*SW*SH

    3.75

    2.3 Minimum area of cross section A = I*(SQRT(X1/X2))

    where

    2.4 X1 = (TF1*ALPHAR*ROWE*100

    169.24

    2.5 X2 = LN(1+(TM-TA)/(K0-TA))

    1.31

    2.6 Minimum area of cross section A sq.mm 568.43

    2.7 Diameter of conductor mm 26.91

    2.8 Temperature co-efficient of material ALPHAR 0.00423

    2.9 Resistivity of earthing material ROWE micro-ohm/ 15.00

    2.10 Specific heat of material SH cal/gram/C 0.114

    2.11 Density of material SW gram/cc 7.86

    2.12 Reference temperature of material constant TR C 20

    2.13 Max.allowable temperature for welded joints TM C 500

    2.14 Ambient temperature TA C 50

    2.15 Corrosion allowanceAverage rate of corrosion of steel is 61 mils for the f irst 12 years and 50% of that value

    30.5 mils for the next 12 years.After this period,it is assumed that no corrosion takes place.

    (Reference IEEE Transactions of PAS-Volume 98.

  • 7/30/2019 57352002 Earthing Calculation

    5/20

    -0.835

    CS =1 for no gravel/ concrete.

    ALTERNATIVELY,

    CS = 1-a*((1-s)/u) where

    a=0.106 metre;s=(ROW/ROWS);U=(2hs+a)

    s = 0.0900

    u = 0.506

    a = 0.11

    CS = 0.809

    Choose a lower value of CS from the above.Hence CS=0.82

    3.5 Permissible Estep volts 479.723.6 Permissible Etouch volts 223.91

    4 Preliminary layout

    4.1 Length of the earth mat L metres 100.00

    4.2 Breadth of the earth mat B metres 100.00

    4.3 Assumed spacing for the conductors D metres 10.00

    4.4 Total no of conductors parallel to length N1 nos (B/D)+1

    11

    4.5 Total no of conductors parallel to breadth N2 nos (L/D)+1

    11

    4.6 Total quantity of conductors laid LC metres (N1*L)+(N2*B)

    2,200

    4.7 Interconnections to the grid LINT metres 660

    4.7 Total ground rods length LR metres 30.00

    4.8 Effective grid conductor length L metres 2,895

    5 Estimation of actual mesh and step voltages

    5.1 Emesh = (ROW*KM*KI*I*1000)/L

    5.2 E step = (ROW*KS*KI*I*1000)/L

    5.3 KM = (1/(2*3.14))*(LN(A+B-C)+D*

    5.4 where A = D^2/(16*h*d)

    195.313

    5.5 B = (D+2*h)^2/(8*D*d)

    42.05005.6 C = (h/4*d)

    5.000

    5.7 D = (Kii/Kh)

  • 7/30/2019 57352002 Earthing Calculation

    6/20

    5.12 Number of parallel conductors n = SQRT(N1*N2)

    11

    5.13 KI,the irregularity factor = 0.656+0.172*n2.548

    5.14 Hence E mesh = KM*KI*ROW*I*1000/L

    1,222.491 volts

    PERMISSIBLE VALUE 223.91

    5.15 KI,the irregularity factor = 0.656+0.172*n

    2.548

    5.16 KS = (1/3.14)*(A+B+C(1-E))

    WHERE

    5.17 A = 1/(2*h)0.625

    5.18 B = (1/(D+h))

    0.093

    5.19 C = 1/D

    0.100

    5.20 E = 0.5^(n-2)

    0.0019531

    5.21 KS = 0.2603

    5.22 Hence E step KS*KI*ROW*I*1000/L

    515.599

    PERMISSIBLE VALUE 479.72

    6 Minimum conductor length requirement

    To achieve the above conditions,the following condition has to be satisfied.

    6.1 L = (KM*KI*ROW*I*1000)/Permi

    7,395.77 metres

    7 Evaluation of grid resistance

    7.1 RG ohm ROW*(F+G*(1+(1/J)))

    where

    7.2 F = (1/L)

    0.00035

    7.3 G = 1/(SQRT (20*A))

    0.00224

    7.4 J = 1+(h*(SQRT (20/A)))

    1.0367.5 Hence RG = 0.213 ohm

    8 Grid potential rise

  • 7/30/2019 57352002 Earthing Calculation

    7/20

    0)/TCAP

  • 7/30/2019 57352002 Earthing Calculation

    8/20

    LN(E))

  • 7/30/2019 57352002 Earthing Calculation

    9/20

    issible Emesh

  • 7/30/2019 57352002 Earthing Calculation

    10/20

    Calculations are based on IEEE Vol 80,1986 version.

    1 Parameters for design purposes:

    1.1 Soil resistivity ROW Ohm meter 73.0

    1.2 Soil resistivity due to concrete ROWS Ohm meter 500

    1.3 Fault current I KA 50.00

    1.4 Fault duration for sizing TF1 sec 1.00

    1.5 Fault duration for step and touch potentials TF2 sec 0.70

    1.6 Depth of burial of grid conductors h metres 0.80

    1.7 Thickness of concrete hs metres 0.20

    1.8 Number of ground rod/pipe electrodes,3m long N nos 10

    1.9 Area of the earth mat AG sq.metres 200,0001.10 Effective earth fault current Ia kA 23.40

    2 Evaluation of conductor sizing

    2.1 Factor K0 (1/ALPHAR)-TR

    216.41

    2.2 TCAP is defined by

    TCAP = 4.184*SW*SH

    3.75

    2.3 Minimum area of cross section A = I*(SQRT(X1/X2))where

    2.4 X1 = (TF1*ALPHAR*ROWE*100

    169.24

    2.5 X2 = LN(1+(TM-TA)/(K0-TA))

    1.31

    2.6 Minimum area of cross section A sq.mm 568.43

    2.7 Diameter of conductor mm 26.91

    2.8 Temperature co-efficient of material ALPHAR 0.00423

    2.9 Resistivity of earthing material ROWE micro-ohm/ 15.00

    2.10 Specific heat of material SH cal/gram/C 0.114

    2.11 Density of material SW gram/cc 7.86

    2.12 Reference temperature of material constant TR C 20

    2.13 Max.allowable temperature for welded joints TM C 500

    2.14 Ambient temperature TA C 50

    2.15 Corrosion allowanceAverage rate of corrosion of steel is 61 mils for the f irst 12 years and 50% of that value

    30.5 mils for the next 12 years.After this period,it is assumed that no corrosion takes place.

    (Reference IEEE Transactions of PAS-Volume 98.

  • 7/30/2019 57352002 Earthing Calculation

    11/20

    -0.745

    CS =1 for no gravel/ concrete.

    ALTERNATIVELY,

    CS = 1-a*((1-s)/u) where

    a=0.106 metre;s=(ROW/ROWS);U=(2hs+a)

    s = 0.1460

    u = 0.506

    a = 0.11

    CS = 0.821

    Choose a lower value of CS from the above.Hence CS=0.82

    3.5 Permissible Estep volts 479.723.6 Permissible Etouch volts 223.91

    4 Preliminary layout

    4.1 Length of the earth mat L metres 500.00

    4.2 Breadth of the earth mat B metres 400.00

    4.3 Assumed spacing for the conductors D metres 21.00

    4.4 Total no of conductors parallel to length N1 nos (B/D)+1

    20

    4.5 Total no of conductors parallel to breadth N2 nos (L/D)+125

    4.6 Total quantity of conductors laid LC metres (N1*L)+(N2*B)

    19,948

    4.7 Interconnections to the grid LINT metres 5,984

    4.7 Total ground rods length LR metres 30.00

    4.8 Effective grid conductor length L metres 25,966

    5 Estimation of actual mesh and step voltages

    5.1 Emesh = (ROW*KM*KI*I*1000)/L

    5.2 E step = (ROW*KS*KI*I*1000)/L

    5.3 KM = (1/(2*3.14))*(LN(A+B-C)+D*

    5.4 where A = D^2/(16*h*d)

    861.328

    5.5 B = (D+2*h)^2/(8*D*d)

    76.00605.6 C = (h/4*d)

    5.000

    5.7 D = (Kii/Kh)

  • 7/30/2019 57352002 Earthing Calculation

    12/20

    5.12 Number of parallel conductors n = SQRT(N1*N2)

    22

    5.13 KI,the irregularity factor = 0.656+0.172*n

    4.492

    5.14 Hence E mesh = KM*KI*ROW*I*1000/L

    474.659 volts

    PERMISSIBLE VALUE 223.91

    5.15 KI,the irregularity factor = 0.656+0.172*n

    4.492

    5.16 KS = (1/3.14)*(A+B+C(1-E))

    WHERE

    5.17 A = 1/(2*h)0.625

    5.18 B = (1/(D+h))

    0.046

    5.19 C = 1/D

    0.048

    5.20 E = 0.5^(n-2)

    0.0000008

    5.21 KS = 0.2288

    5.22 Hence E step KS*KI*ROW*I*1000/L144.479

    PERMISSIBLE VALUE 479.72

    6 Minimum conductor length requirement

    To achieve the above conditions,the following condition has to be satisfied.

    6.1 L = (KM*KI*ROW*I*1000)/Permi

    25,760.69 metres

    7 Evaluation of grid resistance

    7.1 RG ohm ROW*(F+G*(1+(1/J)))

    where

    7.2 F = (1/L)

    0.00004

    7.3 G = 1/(SQRT (20*A))

    0.00050

    7.4 J = 1+(h*(SQRT (20/A)))

    1.0087.5 Hence RG = 0.076 ohm

    8 Grid potential rise

  • 7/30/2019 57352002 Earthing Calculation

    13/20

    0)/TCAP

  • 7/30/2019 57352002 Earthing Calculation

    14/20

    LN(E))

  • 7/30/2019 57352002 Earthing Calculation

    15/20

    issible Emesh

  • 7/30/2019 57352002 Earthing Calculation

    16/20

    ABB-PE EARTHING DESIGN FOR NEYVELI IN POWER BLOCK AREA 121757677.xls.ms_office

    Calculations are based on IEEE Vol 80,1986 version.

    1 Parameters for design purposes:

    1.1 Soil resistivity ROW Ohm meter 73

    1.2 Soil resistivity due to concrete ROWS Ohm meter 500

    1.3 Fault current I KA 50.00

    1.4 Fault duration for sizing TF1 sec 1.00

    1.5 Fault duration for step and touch potentials TF2 sec 0.70

    1.6 Depth of burial of grid conductors h metres 0.80

    1.7 Thickness of concrete hs metres 0.20

    1.8 Number of ground rod/pipe electrodes,3m long N nos 50

    1.9 Area of the earth mat AG sq.metres 120,0001.10 Effective earth fault current Ia kA 23.40

    2 Evaluation of conductor sizing

    2.1 Factor K0 (1/ALPHAR)-TR

    216.41

    2.2 TCAP is defined by

    TCAP = 4.184*SW*SH

    3.75

    2.3 Minimum area of cross section A = I*(SQRT(X1/X2))

    where2.4 X1 = (TF1*ALPHAR*ROWE*10000)/TCAP

    169.24

    2.5 X2 = LN(1+(TM-TA)/(K0-TA))

    1.31

    2.6 Minimum area of cross section A sq.mm 568.43

    2.7 Diameter of conductor mm 26.91

    2.8 Temperature co-efficient of material ALPHAR 0.00423

    2.9 Resistivity of earthing material ROWE micro-ohm/ 15.00

    2.10 Specific heat of material SH cal/gram/C 0.1142.11 Density of material SW gram/cc 7.86

    2.12 Reference temperature of material constant TR C 20

    2.13 Max.allowable temperature for welded joints TM C 500

    2.14 Ambient temperature TA C 50

    Page 16

  • 7/30/2019 57352002 Earthing Calculation

    17/20

    ABB-PE EARTHING DESIGN FOR NEYVELI IN POWER BLOCK AREA 121757677.xls.ms_office

    2.15 Corrosion allowanceAverage rate of corrosion of steel is 61 mils fo r the first 12 years and 50% of that value

    30.5 mils for the next 12 years.After this period,it is assumed that no corrosion takes place.

    (Reference IEEE Transactions of PAS-Volume 98.

    Total corrosion=(61+30.5)2 =183 mils ie 4.64mm.

    2.16 Diameter of the conductor after corrosion= 31.55 mm.

    2.17 Diameter of the conductor chosen d 0.04 M

    3 Permissible step and touch voltages

    3.1 E step = (1000+(6*CS(hs,K)*ROWS))*0.116/(SQRT TF2)3.2 E touch = (1000+(1.5*CS(hs,K)*ROWS))*0.116/(SQRT TF2)

    3.3 CS is a reduction factor depending upon the depth of gravel /concrete and reflection factor K.

    CS is obtained from Figure 8 of IEEE. = 0.82

    3.4 K = (ROW-ROWS)/(ROW+ROWS)

    -0.745

    CS =1 for no gravel/ concrete.

    ALTERNATIVELY,

    CS = 1-a*((1-s)/u) where

    a=0.106 metre;s=(ROW/ROWS);U=(2hs+a)s = 0.1460

    u = 0.506

    a = 0.11

    CS = 0.821

    Choose a lower value of CS from the above.Hence CS=0.82

    3.5 Permissible Estep volts 479.72

    3.6 Permissible Etouch volts 223.91

    Page 17

  • 7/30/2019 57352002 Earthing Calculation

    18/20

    ABB-PE EARTHING DESIGN FOR NEYVELI IN POWER BLOCK AREA 121757677.xls.ms_office

    4 Preliminary layout4.1 Length of the earth mat L metres 400.00

    4.2 Breadth of the earth mat B metres 300.00

    4.3 Assumed spacing for the conductors D metres 13.00

    4.4 Total no of conductors parallel to length N1 nos (B/D)+1

    24

    4.5 Total no of conductors parallel to breadth N2 nos (L/D)+1

    32

    4.6 Total quantity of conductors laid LC metres (N1*L)+(N2*B)

    19,162

    4.7 Interconnections to the grid LINT metres 5,7484.7 Total ground rods length LR metres 150.00

    4.8 Effective grid conductor length L metres 25,083

    5 Estimation of actual mesh and step voltages

    5.1 Emesh = (ROW*KM*KI*I*1000)/L

    5.2 E step = (ROW*KS*KI*I*1000)/L

    5.3 KM = (1/(2*3.14))*(LN(A+B-C)+D*LN(E))

    5.4 where A = D^2/(16*h*d)330.078

    5.5 B = (D+2*h)^2/(8*D*d)

    51.2404

    5.6 C = (h/4*d)

    5.000

    5.7 D = (Kii/Kh)

    0.745

    5.8 E = 8/(3.14*(2n-1))

    = 0.047

    5.9 KM = (1/(2*3.14))*(LN(A+B-C)+D*LN(E))

    Page 18

  • 7/30/2019 57352002 Earthing Calculation

    19/20

    ABB-PE EARTHING DESIGN FOR NEYVELI IN POWER BLOCK AREA 121757677.xls.ms_office

    = 0.581

    5.10 Kii=1 for grids with ground rods along the perimeterKii=1 for grids with ground rods at the grid corners

    Kii=1 for grids with ground rods along the perimeter and throughout the grid area

    5.11 Kh = SQRT(1+h/ha) where ha=1 metre.

    = 1.342

    5.12 Number of parallel conductors n = SQRT(N1*N2)

    28

    5.13 KI,the irregularity factor = 0.656+0.172*n

    5.413

    5.14 Hence E mesh = KM*KI*ROW *I*1000/L457.814 volts

    PERMISSIBLE VALUE 223.91

    5.15 KI,the irregularity factor = 0.656+0.172*n

    5.413

    5.16 KS = (1/3.14)*(A+B+C(1-E))

    WHERE

    5.17 A = 1/(2*h)

    0.625

    5.18 B = (1/(D+h))

    0.0725.19 C = 1/D

    0.077

    5.20 E = 0.5^(n-2)

    0.0000000

    5.21 KS = 0.2466

    5.22 Hence E step KS*KI*ROW*I*1000/L

    194.262

    PERMISSIBLE VALUE 479.72

    Page 19

  • 7/30/2019 57352002 Earthing Calculation

    20/20

    ABB-PE EARTHING DESIGN FOR NEYVELI IN POWER BLOCK AREA 121757677.xls.ms_office

    6 Minimum conductor length requirement

    To achieve the above conditions,the following condition has to be satisfied.

    6.1 L = (KM*KI*ROW*Ia*1000)/Permissible Emesh

    24,000.74 metres

    7 Evaluation of grid resistance

    7.1 RG ohm ROW*(F+G*(1+(1/J)))

    where

    7.2 F = (1/L)

    0.00004

    7.3 G = 1/(SQRT (20*A))0.00065

    7.4 J = 1+(h*(SQRT (20/A)))

    1.010

    7.5 Hence RG = 0.097 ohm

    8 Grid potential rise

    Total grid potential rise IR Volts I*RG

    4,833.56 volts

    Page 20