5s check sheet
DESCRIPTION
5S Check sheetTRANSCRIPT
Page 1 of 4
5S AUDIT (SHOP FLOOR)
Audit Date Area
Next Audit Date Auditor
Element Checking ItemEvaluation RankA B C D E
Disposal of waste / Burr / Scrap Parts
Disposal of Scrap Parts
Rework Not pending more than 3 Days
Disposal of unwanted Records / Documents
Disposal of Unwanted / Used materials
Disposal of Excess WIP / Non-moving WIP
Disposal of unwanted tools / jigs / equipment
Proper identification of WIP / Gauges / Trollys
Marking of Trolly keeping area(input&output)
Gauges are Properly organised
Two tray systems used where necessary
AM Check points are properly identified
Identification of Rejection & Rework
F/M/L pieces identification fixure available
Scrap box avaialble to keep scraped pieces
Wires & Hoses are routed properly
SEIRI(CLEARING UP)
SEITON(ORGANISING)
Material / Tools / Gauges kept on the identified places(not on machines)
Page 2 of 4
5S AUDIT (SHOP FLOOR)
Audit Date Area
Next Audit Date Auditor
Condition of Trollys & trays
Condition of Fans & Light fittings
Condition of gauges & Masters(free from rust)
AM Check sheet available in all machines
Adequecy of Lighting
Display of SOP
Follow of First 3 Steps
Adherence to PSC & SOP
Gauges used are under calibration status
Total Score
% Score
A Excellent (No abnormalities) - "10" Points D Very Low adherence - "3" PointsB Good ( one or two Problem) - "7" Points E Very Poor - "0" PointsC 75% Adherence only - "5" Points
SEISO(CLEANING)
Condition of Floor (free from dents,projections, uneven Oil spillage / Dirt)
Condition of Machines (No rusting & Oil leakage, No dirt inside panels)
SEIKETSU(STANDARDISING)
SHITSUKE(TRAINING & DISCIPLINE)
All Personnel wearing Uniform & Shoes / Safety equipments as required
Updating PMC / SPC and Process monitoring check sheets
Machines are manned with only trained Manpower