6 project management realistic scheduling and accurate estimating
DESCRIPTION
RLabs Project Management Presentation 5TRANSCRIPT
![Page 1: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/1.jpg)
Realistic Scheduling and
accurate estimating
Copyright © RLabs 2013
![Page 2: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/2.jpg)
Scheduling is the fundamental
element of any project.
Copyright © RLabs 2013
![Page 3: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/3.jpg)
Realistic Scheduling
Copyright © RLabs 2013
![Page 4: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/4.jpg)
Gantt Chart
Technique: Focuses on Schedule
Management
Representing the phases and activities of a
project work breakdown structure (WBS)
Great tool for managing smaller projects
Does not give you a holistic view of a project
magnitude.
Copyright © RLabs 2013
![Page 5: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/5.jpg)
• A realistic schedule takes into consideration
all the objectives of the project .
• Each planning step relies on the one
preceding it, and each adds a new element
to the plan .
Copyright © RLabs 2013
![Page 6: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/6.jpg)
Recap of the steps involved in
planning a project
1. Create the project definition
2. Develop a risk management strategy.
3. Build a work breakdown structure .
4. Identify tasks relationships .
5. Estimate work packages.
6. Calculate initial schedule.
7. Assign and level resources.
Copyright © RLabs 2013
![Page 7: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/7.jpg)
These steps generate all the information
required to understand how a project will be
executed. The steps are systematic, but they
don't necessarily come up with the 'right
answer'.
Copyright © RLabs 2013
![Page 8: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/8.jpg)
Copyright © RLabs 2013
![Page 9: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/9.jpg)
Milestones
Milestones have zero duration, so adding them
to a project doesn't affect the schedule at all.
1. Project start and finish milestones are useful
anchor for the network.
2. Milestones can be used to mark input from one
party to one another.
3. A milestone can represent significant events that
aren't already represented by a work package or
summary.
Copyright © RLabs 2013
![Page 10: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/10.jpg)
1. Idea evaluation or "ball park estimate"
2. Project selection or order of magnitude
3. Detailed estimate
3 Levels of Accuracy
Copyright © RLabs 2013
![Page 11: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/11.jpg)
Copyright © RLabs 2013
![Page 12: 6 project management realistic scheduling and accurate estimating](https://reader033.vdocuments.net/reader033/viewer/2022051323/5482e0b5b47959d30c8b48f3/html5/thumbnails/12.jpg)
Estimating techniques
1. Phased estimating
2. Apportioning
3. Parametric estimates
4. Bottom- up estimating
Copyright © RLabs 2013