6.33 topographical survey specification

23
KCP-GNS-CVL-SPC-0001 Rev.: 03 Project Title: Kingsnorth Carbon Capture & Storage Project Page 1 of 23 Document Title: Topographical Survey Specification Kingsnorth CCS Demonstration Project The information contained in this document (the Information) is provided in good faith. E.ON UK plc, its subcontractors, subsidiaries, affiliates, employees, advisers, and the Department of Energy and Climate Chan ge (DECC) make no representation or warranty as to the accuracy, reliability or completeness of the Information and neither E.ON UK plc nor any of its subcontractors, subsidiaries, affiliates, employees, advisers or DECC shall have any liability whatsoever for any direct or i ndirect loss howsoever arising from the use of the Information by any party. Topographical Survey Specification Table of Contents 1 INTRODUCTION ............................................................................................................. 4 1.1 DOCUMENT SCOPE..................................................................................................... 4 1.2 DEFINITIONS ............................................................................................................... 4 1.3 A BBREVIATIONS ......................................................................................................... 5 2 QUALITY ASSURANCE / QUALITY CONTROL .......................................................... 6 3 SAFETY, WORK RULES AND REGULATIONS........................................................... 7 4 SCOPE OF WORK.......................................................................................................... 8 4.1 GENERAL ................................................................................................................... 8 4.2 PERSONNEL ............................................................................................................... 8 4.3 EQUIPMENT ................................................................................................................ 8 4.4 M ETHOD STATEMENT ................................................................................................. 9 4.5 THIRD PARTIES .......................................................................................................... 9 5 PIPELINE ROUTE......................................................................................................... 10 5.1 CENTRELINE SETTING OUT....................................................................................... 10 5.2 ROUTE SURVEY........................................................................................................ 10 5.3 SPECIAL CROSSINGS ................................................................................................ 11 5.4 FOREIGN SERVICES AND E XISTING UTILITIES ............................................................ 11 5.5 PIPELINE VAL VE STATION SITE SURVEY ................................................................... 11 6 SURVEY FRAMEWORK, ACCURACY AND CONTROL ........................................... 13 6.1 GENERAL ................................................................................................................. 13 6.2 CO-ORDINATE SYSTEM P ARAMETERS ...................................................................... 13 6.3 SURVEY CONTROL A CCURACY ................................................................................. 13 6.4 GEODETIC HORIZONTAL AND V ERTICAL D ATU MS ...................................................... 13 6.5 SURVEY CONTROL ................................................................................................... 13 6.6 SURVEY CONTROL MEASUREMENTS ......................................................................... 14 6.7 PRIMARY CONTROL .................................................................................................. 14 6.8 SECONDARY CONTROL ............................................................................................. 14 6.9 CALIBRATION AND CHECK SURVEY ........................................................................... 15 6.10 LEVEL CONTROL ...................................................................................................... 15 7 PRESENTATION OF DATA ......................................................................................... 16 7.1 GENERAL ................................................................................................................. 16 7.2 GENERAL DATA FOR MAT .......................................................................................... 16 7.3 FILE I DENTIFICATION................................................................................................. 17 7.4 SPECIAL CROSSINGS AND PIPELINE VALVE STATION SITES ....................................... 17 7.4.1 Surveyed Mapping Data ................................................................................... 17 7.4.2 Special Crossing Drawings ............................................................................... 18 7.4.3 Pipeline Valve Station Drawing ........................................................................ 18 7.5 PIPELINE ROUTE ...................................................................................................... 18

Upload: babloosingh215

Post on 22-Oct-2014

141 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 1 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

Topographical Survey Specification Table of Contents 1 INTRODUCTION ............................................................................................................. 4

1.1 DOCUMENT SCOPE..................................................................................................... 4 1.2 DEFINITIONS............................................................................................................... 4 1.3 ABBREVIATIONS ......................................................................................................... 5

2 QUALITY ASSURANCE / QUALITY CONTROL .......................................................... 6

3 SAFETY, WORK RULES AND REGULATIONS ........................................................... 7

4 SCOPE OF WORK.......................................................................................................... 8

4.1 GENERAL ................................................................................................................... 8 4.2 PERSONNEL ............................................................................................................... 8 4.3 EQUIPMENT ................................................................................................................ 8 4.4 METHOD STATEMENT ................................................................................................. 9 4.5 THIRD PARTIES .......................................................................................................... 9

5 PIPELINE ROUTE......................................................................................................... 10

5.1 CENTRELINE SETTING OUT....................................................................................... 10 5.2 ROUTE SURVEY........................................................................................................ 10 5.3 SPECIAL CROSSINGS................................................................................................ 11 5.4 FOREIGN SERVICES AND EXISTING UTILITIES ............................................................ 11 5.5 PIPELINE VALVE STATION SITE SURVEY ................................................................... 11

6 SURVEY FRAMEWORK, ACCURACY AND CONTROL ........................................... 13

6.1 GENERAL ................................................................................................................. 13 6.2 CO-ORDINATE SYSTEM PARAMETERS ...................................................................... 13 6.3 SURVEY CONTROL ACCURACY ................................................................................. 13 6.4 GEODETIC HORIZONTAL AND VERTICAL DATUMS ...................................................... 13 6.5 SURVEY CONTROL ................................................................................................... 13 6.6 SURVEY CONTROL MEASUREMENTS......................................................................... 14 6.7 PRIMARY CONTROL .................................................................................................. 14 6.8 SECONDARY CONTROL ............................................................................................. 14 6.9 CALIBRATION AND CHECK SURVEY ........................................................................... 15 6.10 LEVEL CONTROL ...................................................................................................... 15

7 PRESENTATION OF DATA ......................................................................................... 16

7.1 GENERAL ................................................................................................................. 16 7.2 GENERAL DATA FORMAT .......................................................................................... 16 7.3 FILE IDENTIFICATION................................................................................................. 17 7.4 SPECIAL CROSSINGS AND PIPELINE VALVE STATION SITES....................................... 17

7.4.1 Surveyed Mapping Data ................................................................................... 17 7.4.2 Special Crossing Drawings ............................................................................... 18 7.4.3 Pipeline Valve Station Drawing ........................................................................ 18

7.5 PIPELINE ROUTE ...................................................................................................... 18

Page 2: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 2 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

8 REPORTING AND MEETINGS .................................................................................... 19

8.1 DOCUMENTATION REQUIREMENTS............................................................................ 19 8.2 SCHEDULE ............................................................................................................... 19 8.3 DAILY REPORTS ....................................................................................................... 19 8.4 WEEKLY REPORT ..................................................................................................... 20 8.5 FINAL REPORTING .................................................................................................... 20 8.6 INDUCTION MEETING ................................................................................................ 20

9 FACILITIES AND UTILITIES FURNISHED BY CONTRACTOR ................................ 21

10 COMPANY SUPPLIED INFORMATION ...................................................................... 22

11 REFERENCE DOCUMENTS ........................................................................................ 23

Page 3: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 3 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

Table of Holds

HOLD Description Section 1 CLEARED

2 Onshore route map drawing number(s) 1.1, 10.0, 11.0 3 Preliminary crossing schedule document number 5.3, 10.0, 11.0

4 E.ON Project Environmental Management Plan document number

3.0, 10.0, 11.0

Page 4: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 4 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

1 Introduction

1.1 Document Scope The Specification covers the minimum requirements for the topographical survey of the onshore pipeline route which forms part of Kingsnorth Carbon Capture and Storage Project, Transport Pipeline and Injection Facilities Project.

The limits of this specification shall be as shown on the onshore pipeline route map(s), (HOLD2) [S1] and as defined below:

from the pipeline landfall;

to the Kingsnorth pipeline ESD valve.

1.2 Definitions For the purpose of this document the following definitions shall apply:

COMPANY E.ON UK or its nominated representative.

CONTRACTOR The companies designated on the purchase order form as

being the selected Contractor of materials and services.

SUB-CONTRACTOR The companies selected / designated by the CONTRACTOR

as suppliers of materials and services.

WORK The task, process or operation being conducted by the

CONTRACTOR or SUBCONTRACTOR on any tier on behalf of COMPANY.

DEVIATION Departure by CONTRACTOR or SUB-CONTRACTOR, without the APPROVAL of the COMPANY, from the requirements of

this document.

APPROVE / APPROVAL Act of granting permission or act accepting as suitable, fit for

purpose, etc., a document, process, procedure, etc. Used to indicate that the COMPANY or CONTRACTOR does not wish WORK to proceed unless certain features have been agreed in

writing. Such APPROVAL shall not relieve the CONTRACTOR of its contractual or statutory responsibilities.

NON-CONFORMANCE REPORT

A report to be raised upon discovery by any party of a DEVIATION from this document.

Shall Indicates mandatory requirement

Should Indicates preferred course of action

May Indicates optional course of action

In the context of this document, the titles and definitions shall be specific when shown in upper case and non-specific when shown in lower case

Page 5: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 5 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

1.3 Abbreviations Within this document, the following abbreviations are used:

AGI Above Ground Installation CCS Carbon Capture and Storage CM Central Meridian

DPR Daily Progress Report DTM Digital Terrain Map ESD Emergency Shutdown

FEED Front End Engineering Design GOGC Genesis Oil and Gas Consultants GPS Global Positioning System

IP Intersection Point MSL Mean Sea Level NUI Normally Unattended Installation

RTK Real Time Kinematic UTM Universal Transverse Mercator

Page 6: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 6 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

2 QUALITY ASSURANCE / QUALITY CONTROL

The COMPANY requires that all surveys, regardless of the method by which they are carried out, shall be performed by, or under the direct supervis ion of a professional land surveyor or a professional engineer.

In addition, activities which require the application of engineering principles and the interpretation of engineering data shall be performed by, or under the direct supervision of a professional engineer.

The CONTRACTOR shall provide the professional expertise and trained personnel necessary to

achieve the required results. During surveying operations, the CONTRACTOR shall ensure that CONTRACTORS employees and SUB-CONTRACTORS comply with all conditions, restrictions and terms of the agreements made with COMPANY or any third parties including any conditions,

restrictions and terms of the agreements made through leases, rights -of-way, easements. The CONTRACTOR shall coordinate all surveying operations, including any contact with third parties, with the appropriate COMPANY representatives.

The CONTRACTOR shall operate an effective Corporate Quality System matching the requirements of ISO 9001:2000.

The CONTRACTOR shall submit a project specific Quality Plan to COMPANY for review, comment

and approval within one (1) week of Contract award.

The project specific Quality Plan shall comply with the requirements of ISO 9001:2000 or equivalent and shall detail the controls and verifications to be implemented to assure quality during execution of

the WORK. The Quality Plan may be in the form of a reference to the appropriate documented procedures that form an integral part of the CONTRACTORS Quality System.

CONTRACTOR shall submit a copy of each procedure, certificate, and report applicable to the field

survey work, data processing and document production to COMPANY for review / approve.

CONTRACTOR shall be responsible for ensuring that all documentation requiring permit approval is submitted in a timely manner and in a format acceptable to COMPANY.

Page 7: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 7 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

3 SAFETY, WORK RULES AND REGULATIONS

Survey operations will be carried out in accordance with COMPANY Approved Quality Plan.

Personnel carrying out site work will adhere to the Site Safety policies at all times with emphasis on wearing the correct safety clothing and equipment relative to the type of operation being performed.

All personnel, including Third Parties will be safety inducted prior to the commencement of the WORK.

Safety precautions are of paramount importance to prevent any possible danger to the Survey Team

or public. Any operations carried out adjacent to public access or thoroughfare will be closely monitored by the Project Safety Advisor.

CONTRACTOR shall follow the guidelines in the E.ON Project Environmental Management Plan,

(HOLD4) [S3] to minimise disturbance to the area along the proposed onshore pipeline route.

As a guide, CONTRACTOR shall take into account the following issues and measures as part of their scope of work:

Community awareness Environmental protection Security

Waste management Access during wet weather Access routes - keep to existing tracks and roads

Livestock protection Permissions from landowners

COMPANY shall have the right to review, for acceptance, any work being per formed by

CONTRACTOR. This review by COMPANY shall not relieve CONTRACTOR of his responsibility to provide complete and accurate data.

Page 8: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 8 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

4 Scope of Work

4.1 General The Scope of Work shall include mobilisation, route survey, data processing, drawing production and reporting.

The CONTRACTOR shall mobilise the necessary personnel and equipment (including spare parts

and consumables) to carry out the work.

The CONTRACTOR shall provide all resources and equipment necessary to perform the WORK in a timely efficient manner to the satisfaction of COMPANY and in accordance with the Project Schedule.

Resources shall include, but not be limited to: office and field personnel, equipment, material supplies and labour necessary to complete the WORK.

COMPANY shall have the right to review, for acceptance, any WORK being performed by the

CONTRACTOR. This review by COMPANY shall not relieve the CONTRACTOR of its responsibility to provide complete and accurate data.

The CONTRACTOR shall at all times be aware of and address the ne eds concerning the

environmental nature of the site. This consideration shall be made with respect to access, survey methods, and any other activity likely to impact on the environmental integrity of the various areas of the site.

4.2 Personnel The CONTRACTOR shall appoint an experienced Senior Survey Engineer to manage and co -

ordinate the field survey activities, data processing and drawing production. Simultaneously a qualified and experienced Survey Engineer shall be assigned to site full time to supervise field survey activities and liaise with COMPANY. He shall be responsible for all surveying activities and shall

confirm the accuracy of all information transmitted to COMPANY in whatever form. The above personnel should be suitably educated to HND level, or local equivalent, and have at least 5 years appropriate surveying experience.

The number of personnel shall be sufficient to carry out the surveys, other associated work, data processing, and drawing production in a timely and efficient manner in accordance with COMPANY approved programme.

COMPANY reserves the right to review and approve or reject the credentials and performance of all personnel provided by CONTRACTOR to perform the WORK.

4.3 Equipment The CONTRACTOR shall supply, maintain and operate all the equipment necessary to carry out the

WORK in accordance with this specification and the COMPANY approved programme.

An equipment itinerary for each survey unit shall be submitted for approval to the COMPANY prior to commencement of any fieldwork.

The CONTRACTOR shall ensure that all equipment necessary to carry out the WORK has been calibrated within 6-months prior to commencing fieldwork. Copies of relevant calibration certi ficates shall be made available to COMPANY for review, as requested, prior to commencement of WORK.

Copies of the calibration certi ficates shall be included in the Field Survey report. The CONTRACTOR shall carry out daily and weekly field checks on equipment to ensure the continuing validity of calibrations. The results of these field checks and any subsequent adjustments shall be documented

and all such documentation shall be part of the regular reporting.

COMPANY is not expected to be site-based and the CONTRACTOR will be required to communicate as necessary with COMPANY or its representative. CONTRACTOR shall have computer capabilities

with high-speed modem and appropriate communication software for t ransfer of survey information

Page 9: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 9 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

via standard communication links to COMPANY. All technical information shall be sent to

COMPANY in native format - e.g. drawings in AutoCAD, tabulations in a data base format or Excel or equivalent etc. Signature certi fied data can be sent in pdf format together with an unsigned native format copy.

CONTRACTOR shall provide gas detection equipment for use in the proximity of existing hydrocarbon plant or pipelines. CONTRACTOR shall adopt a No Smoking Policy in such areas.

4.4 Method Statement CONTRACTOR shall submit a technical method statement for COMPANY review and approval within

(2) weeks following Contract award and prior to commencement of field activities.

The method statement shall include a schedule and detailed description, including responsibilities, of all personnel, the number of survey teams, the methodology and equipment necessary to carry out

the WORK in accordance with this Specification.

The contractor shall also submit a health, safety and emergency plan.

4.5 Third Parties The CONTRACTOR shall provide permits and all authorisations necessary to carry out the WORK. Any regulatory bottlenecks, such as hold-up of permits, shall be reported to the COMPANY as soon

as possible.

The CONTRACTOR shall liaise with COMPANY prior to making contact with any third parties.

CONTRACTOR shall be responsible for compliance with any specific conditions and requi rements

imposed by third party authorities who are associated with or affected by the WORK.

Page 10: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 10 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

5 Pipeline Route

5.1 Centreline Setting Out Initial setting out will be done from the information provided and the centreline pegged out at 200 metre intervals, at crossing points, at field boundaries and intersection points. As a minimum, stakes shall be visible from the adjacent stakes.

Marker pegs, at least 50 cm square and 750 cm long, will be painted red with pipeline route intersection points (IP’s) clearly identified by red and white pegs.

IP’s shall be sequentially numbered and the following information recorded in field Survey Books:

Identification number. X, Y, Z co-ordinates, and offset pegging data. Intersection Angle Value.

Location sketch with north sign. Survey date, surveyor’s name and signature.

This information will be passed onto the COMPANY for review, including any details of proposed re -

routes.

5.2 Route Survey CONTRACTOR shall survey a 60m strip located along the centre line of the pipeline route (30m either side). CONTRACTOR shall verify information supplied by COMPANY on site.

Survey shall be carried out in order to establish elevations and coordinates of all natural and

manmade features within the pipeline corridor. All buildings and structures in any condition, within the corridor, shall be surveyed. Buried services shall be identified using a suitable pipeline / cable locator and its bearing relative to the pipeline corridor shall be defined.

CONTRACTOR shall survey the new pipeline centreline after setting out.

The pipeline route shall be surveyed in order to produce the following data, in addition to that mentioned above.

A sequential list of centreline co-ordinates (AutoCAD 3D polyline) that represents the original ground profile and horizontal alignment.

1:2500 preliminary alignment sheets (the format shall be provided by COMPANY).

Feature codes as follows: AM Aerial Marker RDX Road Crossing

RLX Railway Crossing RVX Named River Crossing CLX Manmade Canal

STX Stream Crossing DTX Ditch Crossing TRX Track Crossing

SVX Service Crossing PLX Pipeline Crossing STN Station Site

VLV Valve Site

The frequency or density of the survey will be determined by the ground profile, nature of topography and anticipated scale of presentation of data.

Page 11: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 11 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

5.3 Special Crossings CONTRACTOR shall perform a detailed topographic survey at all special crossings, these shall

include road, river, railway and foreign service / utility crossings to enable additional surface / subsurface features to be surveyed for inclusion in the detailed crossing design.

The topographic survey shall be completed to provide sufficient information for the production of

crossing drawings at a scale of 1:500.

CONTRACTOR shall allow for the production of crossing drawings at scales appropriate to the length of each crossing. An original ground level profile will be positioned beneath each plan on every

crossing drawing.

CONTRACTOR shall ensure sufficient points are surveyed to enable an accurate crossing drawing to be produced, in plan and profile.

A preliminary crossing schedule, (HOLD3) [S2] shall be provided by COMPANY which the CONTRACTOR shall update during the course of the survey works .

5.4 Foreign Services and Existing Utilities CONTRACTOR shall obtain co-ordinates and crossing angle of all existing overhead, surface and buried foreign services / utilities, including parallel pipelines. This shall include, but not be limited to,

power lines / cables, buried pipelines, telephone cables, berms, roads and tracks etc.

During execution of the WORK, CONTRACTOR shall produce and maintain an accurate crossing schedule detailing the position, size, location, height and depth, where applicable, of all foreign

services / utilities encroaching or crossing the pipeline corridor and pipeline station sites.

In addition, where pipeline alignment runs parallel to or crosses a power line, the following information shall be collected by CONTRACTOR and included in the Report. Applicable information

shall also be shown on the relevant drawings:

Power line voltage Current carried in the power line

Distance of power line from the pipeline Height of tower or depth of cable (as applicable) Length of parallel run (where pipeline alignment runs parallel to power line)

CONTRACTOR shall submit the crossing schedule for review as the survey progresses. Following completion of all field survey work, the crossing schedule shall be updated to include the entire pipeline route.

5.5 Pipeline Valve Station Site Survey COMPANY will identify the location of the proposed valve station site on the route drawings issued. After the location has been confirmed, CONTRACTOR shall establish the site limits during survey preparation for review on site by COMPANY.

CONTRACTOR shall carry out a full topographic survey of the site mapping all features (above and below ground) within the proposed site extending for a distance of 30m outside the proposed boundaries. If the site is located on sloping ground, COMPANY may extend the survey area subject

to site conditions.

The topographic survey shall take positions and elevations, as a minimum, on a 5m grid in addition to specific points, existing boundaries etc. Contour intervals of 0.2m minor and 1m major shall be

generated for the site drawings.

Page 12: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 12 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

CONTRACTOR shall map the following existing features during the s ite survey:

Road culverts and tracks; Structures such as buildings, wells, etc; Water courses such as streams and drainage ditches;

Fences and walls; Overhead power lines, poles and pylons; Buried pipelines, cables and other foreign services and features;

New and existing survey monuments; Spot elevation points measured on site;

A minimum of 4 survey monuments are required to enable accurate definition of elevation, plan

location and orientation. These bench marks shall be located a minimum distance of 50m outside of the selected area, and shall have a life span of 3 years.

The topographic survey shall be completed to provide sufficient information for the production of

drawings at a scale of 1:250.

Page 13: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 13 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

6 SURVEY FRAMEWORK, ACCURACY AND CONTROL

6.1 General Survey co-ordinates and maps shall use standard UK horizontal and vertical datums as origin with survey observations tied into Government survey control stations and benchmarks as necessary.

The scale of capture of survey data shall be suitable to support mapping at 1:2500 scale or better

where larger scale mapping is used for crossings and other specialist areas.

6.2 Co-Ordinate System Parameters Contractor shall perform the topographic surveys using the following co-ordinate system parameters:

Spheroid Airy 1830

Semi-Major axis (a) 6377563.396m

Semi-Minor axis (b) 6356256.910m

First Eccentricity Sq (e2) 0.0066705397616

Inverse Flattening (1/f) 299.3249646

Datum OSGB36 National Grid

Central Meridian (CM) 2°W (UTM Zone 30N, 0°W - 6°W)

Latitude of Origin 49°

False Easting 400000m

False Northing -100000m

Scale Factor on CM 0.9996012717

6.3 Survey Control Accuracy Survey of control monuments shall be conducted to achieve accuracy as follows:

Primary 1/10,000 Secondary 1/5,000

Surveying of the pipeline alignment from secondary control, using RTK GPS or Total Station techniques shall be conducted to achieve:

Horizontal accuracy ± 0.05m

Vertical accuracy ± 0.05m Surveying of stations and valve sites shall be conducted to achieve an accuracy of ± 0.01m

relative to the site survey monuments.

To ensure these accuracies are maintained, the CONTRACTOR shall make regular (not longer than manufacturer’s recommended frequency) verifications to demonstrate that the initial bench calibration by the manufacturer is still valid and within specified requirements.

6.4 Geodetic Horizontal and Vertical Datums All survey work shall be based on OSGB36 datum, Airy 1830 Ellipsoid and Transverse Mercator co -

ordinates or otherwise as directed by the COMPANY.

Topographical heights shall be in metres and based on Ordnance Datum Newlyn mean sea level (MSL) as defined by UK maps.

6.5 Survey Control Horizontal and vertical control of the work shall be undertaken utilising dual frequency geodetic receivers or Total Station equipment with levels derived using precise automatic survey levels.

Page 14: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 14 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

The control shall be referenced to a minimum of 3 geodetic reference stations co-ordinated with

respect to the Ordnance Survey national grid at 1st or 2nd order level. Levels shall be derived from bench marks of a similar accuracy.

Markers, reference points and monuments for the survey may vary in composition from Hilti or road

nails in concrete, to steel pins to concrete monuments. Material for monumentation shall be chosen in regard to the terrain and situation that exists at the site of the survey and be approved by COMPANY. The primary network of survey monuments shall be constructed using markers that will

remain in serviceable condition for up to 3 years.

The location of the monuments shall be chosen to offer both convenience to the project and protection for the monument. Base line monuments will be used to establish the location of the

centre-line of the entire project. Benchmarks for elevation control shall be located on the most permanent and stable base convenient to the site. Horizontal and vertical control monuments shall be placed at intervals of not more than 500m or as directed by the COMPANY.

6.6 Survey Control Measurements The CONTRACTOR shall carry out the WORK using modern GPS systems combined, where necessary (e.g. where GPS signal masking occurs), with Total Station and precise level technology.

GPS control survey shall be carried out using a minimum of two dual frequency receivers. Final

locations shall be computed using post-processed static techniques with a minimum of two vectors being used to co-ordinate any new survey station. Equipment, data collection process, compilation and reporting format shall be subject to the approval of COMPANY prior to implementation. Each

surveyor shall be responsible for locating the designated data and collecting data for subsequent RTK post-processing.

6.7 Primary Control A primary control network of survey stations is required that extends to the geographic limits of this project.

The CONTRACTOR shall tie-in to a sufficient number of primary geodetic control points required to meet positioning tolerances and ensure consistency within the geodetic network. The CONTRACTOR shall devise the appropriate network plan, and shall utilise existing national survey

stations. Values for existing national control stations shall be obtained by the CONTRACTOR. At least three horizontal and three vertical geodetic control point ties shall be made to first or second order national survey stations from primary control stations.

Sufficient baselines shall be independently measured to ensure that all new control stations are established as an over-determined solution.

The CONTRACTOR shall liaise with COMPANY as to existing monuments that may be available.

All existing local horizontal and vertical control station descriptions shall be included in the final report. Station markers shall be made clearly visible and able to be located by any third party using the station description sheet.

6.8 Secondary Control Secondary network stations shall be established as required to complete the field survey work.

Such stations shall be tied into the primary network and full station descriptions (including witness marks) provided to the COMPANY.

Page 15: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 15 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

6.9 Calibration and Check Survey The accuracy of primary and secondary control shall be determined by the CONTRACTOR to meet

the requirements of the topographic survey.

The CONTRACTOR shall:

Keep GPS, electronic and optical surveying instruments in close adjustment according to

manufacturer’s specifications or in compliance to textbook standards. Ensure that electronic distance measuring devices are compared to a base line, measured by

static GPS or a standardized or calibrated tape, at least every six months. Field

measurements of angles and distance shall be done in such fashion as to satisfy the closures and tolerances expressed above.

6.10 Level Control Local vertical control shall be undertaken using double measurement techniques (forward and reverse) using control data obtained from the national mapping authority. A minimum of 2 vertical

control points shall be used at the terminations of the routes and two further points along the route section.

Page 16: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 16 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

7 PRESENTATION OF DATA

7.1 General Surveys will include, but are not limited to, the proper location, monumentation, description of roadways, highways, and railways; transmission lines for communications, fuel, oil, gas, chemical, water and electrical needs; canals, waterways, drainage ditches and sewers.

The survey map shall represent the information gathered during the survey and shall be generated using automated CAD technology compatible with those utilised by COMPANY.

7.2 General Data Format Unless stated otherwise, all text, dimensions, test data, results and all other information relating to the WORK shall be expressed in English and referenced to SI units.

COMPANY will supply blocks of numbers for the production of drawings.

The final deliverable of the data collected from the topographical survey shall be delivered as one complete model file.

CONTRACTOR shall provide the first 2km of the survey as soon as possible after commencement and this data will be used for checking and QC purposes. COMPANY reserves the right to alter size type and representation of data provided by the CONTRACTOR.

All linear features shall be presented as a 3D polyline and all non-linear features shall be presented as 3D points. All features defining closed boundaries of data shall be represented as 3D polygons.

All data shall be supplied in AutoCAD R2004 format (i.e. dwg files);

All drawing objects are to be drawn in model space at a scale of 1:1 (i.e. AutoCAD units = 1m). INSUNITS (AutoCAD setting) to be set to the value of 6, which defines the drawing as metres;

All entities are to be in colour BY LAYER and line type BY LAYER; All entity groups i.e. trees are to be on separate layers; All point data i.e. trees are to be defined as a block and have attributes assigned;

All polyline data i.e. field boundaries are to be one continuous polyline with no slope line shown. i.e. tracks and roads are to be defined by a continuous polylines. All polylines are to have text on the line describing the entity in the field;

All polygon data i.e. owner boundaries are to be a closed polygon with all text pertaining to the polygon within the boundary;

Page 17: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 17 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

CONTRACTOR shall adopt the layering convention as detailed in the following table:

Layer Name Enti ty Type Description P_Route 3D Polyline Centreline of pipeline route

F_River_Bank 3D Polyline Top of river bank

F_River_WL 3D Polyline River water level

F_Road 3D Polyline Edge of Road

F_Track 3D Polyline Edge of Track

F_Ditch 3D Polyline Centreline of ditch

F_Railway_Easement 3D Polyline Railway boundary

F_Railway_Track 3D Polyline Centreline of railway lines

F_Tree Point Trees

F_Field 3D Polyline Field boundaries

F_Building 3D Polyline Buildings

F_Fence 2D Polyline Fence lines

F_Wall 3D Polyline Walls

F_Well Point Wells

F_River_HW 2D Polyline High Water Level

F_SpotHeight Point Spot Height (Point co-ordinate = elevation)

F_Feature Point / 2D Polyline Other Significant Features

F_Bench_Mark Point Bench Marks

S_Water_AG 3D Polyline Above ground water pipelines

S_Water_UG 3D Polyline Underground water pipelines

S_Oil_AG 3D Polyline Above ground oil pipelines

S_Oil_UG 3D Polyline Underground oil pipelines

S_Gas_AG 3D Polyline Above ground gas pipelines

S_Gas_UG 3D Polyline Underground gas pipelines

S_Elec_OH 3D Polyline Overhead electricity lines

S_Elec_Pole Point Electrical Poles

S_Elec_UG 3D Polyline Underground electricity lines

S_Tele_OH 3D Polyline Overhead telecom lines

S_Tele_Pole Point Telegraph poles

S_Tele_UG 3D Polyline Underground telecom lines

7.3 File Identification All documents / drawings shall be numbered in accordance with the following COMPANY procedure:

KCP-ARP-PMG-PRO-0010 Project Document Numbering Guidelines and Procedure [S5]

7.4 Special Crossings and Pipeline Valve Station Sites

7.4.1 Surveyed Mapping Data

The surveyed mapping data shall illustrate the following:

Natural features, including but not limited to, water gullies, river crossings etc including

water level and bed level; Existing man-made features, including but not limited to; houses, schools, plantations,

vegetation, electric lines (including the cable height for overhead lines), water pipes,

roads and future roads, bridges etc. An attribute shall be shown which provides a brief description;

New and existing survey monuments;

Page 18: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 18 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

Transverse profiles location (for roads);

Special Crossings; Other significant features (i.e. archaeology, religious sites); Co-ordinates of all bench marks shown next to the symbol. (The referenced elevations

shall be rounded to and shown to the nearest 1cm). Spot elevations shown to the nearest 1cm. Contour lines shall be at 0.20m (minor), 1m (major) vertical intervals and shall be

labelled with the correct elevation above a specified reference datum.

7.4.2 Special Crossing Drawings

CONTRACTOR shall prepare detailed surveys and drawings for specific pipeline crossings

and will include all road, rail and river crossings plus any additional locations as required by COMPANY. Drawings shall be made for crossing existing roads and new roads that will be constructed as part of this Project.

The area to be surveyed shall extend 50m both sides of the pipeline axis and 50m from road, railroad, river, watercourses, pipeline or cable boundaries. In case of two or more parallel lines the 50m widths are taken from the centre lines of the extreme pipeline.

Details of these special crossings will be incorporated into 1:500 Plan and Profile drawings (1:500 Horizontal and 1:200 Vertical). Drawings will be produced to show all data and topographical information gathered during the survey of crossings. COMPANY will supply the

format for these drawings.

7.4.3 Pipeline Valve Station Drawing

CONTRACTOR shall prepare detailed surveys and drawings for the pipeline valve station

identified by COMPANY.

The area to be surveyed shall extend 30m beyond the site boundary area identified by COMPANY or as otherwise directed.

Details of the pipeline valve station area will be incorporated in 1:250 drawin gs which show all data and topographical information gathered during the survey.

7.5 Pipeline Route Services and utility information supplied by COMPANY is for information only and shall be checked

on site and where necessary updated accordingly. CONTRACTOR shall produce preliminary alignment sheets at a scale of 1:2500. Scale for the ground elevation profile in cross section along the pipe axis shall be:

1:2500 horizontal 1:250 vertical

COMPANY will supply the format for these drawings.

In addition to the mapping data referenced in Section 7.4, the surveyed pipeline route maps shall

include the following:

Recorded points at every change in horizontal alignment (IP). Incorporation of match lines between each alignment drawing.

The pipeline mapping data shall be transmitted by E-mail and submitted in electronic format to COMPANY each week as the WORK progresses. If it transpires that files are too large to be transmitted by E-Mail then a back up solution using CD ROM shall be implemented. The break

between mapping sections shall be clearly identified using match lines allowing a continuous pipeline corridor to be produced without the loss of data.

Page 19: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 19 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

8 REPORTING AND MEETINGS

8.1 Documentation Requirements CONTRACTOR shall provide the Contract Deliverables as defined in this Section.

1) Within one (1) week of contract award:

Project Specific Quality Plan

Health, Safety and Emergency Plan Technical Method Statement Primary Survey Control Plan

Equipment Itinerary Survey Progress Report Proforma

2) Each week following commencement of field survey work:

One (1) electronic copy of pipeline mapping data of completed surveyed route One (1) hard copy of current crossing schedule One (1) hard copy of current survey monument schedule

3) Within five (5) weeks following completion of field survey work:

Two (2) CD ROM disc sets (sent separately). CD ROM to contain the pipeline route preliminary alignment sheets, special crossing

data, station site data, field survey data and text files of the complete centre line survey (x, y, z co-ordinates), held in separate directories which are to be suitably titled.

Three (3) hard copies of the survey control schedule

Two (2) hard copies of the final survey report

8.2 Schedule CONTRACTOR shall provide a bar chart schedule showing the manpower required by time interval for each activity and shall reflect percent of schedule completion by time interval.

8.3 Daily Reports The CONTRACTOR shall fully document all phases of the WORK, in a responsible and diligent

manner. The CONTRACTORS field survey personnel shall establish daily contact with COMPANY for progress reporting and quality control feedback. The CONTRACTOR shall prepare a Daily Survey Log for COMPANY. The Daily Survey Log shall be available for inspection at all times.

The Daily Survey Logs shall form the basis of the Activity Log of the Daily Progress Report.

The CONTRACTOR shall be responsible for safe custody of the field events log, a copy of which shall be submitted to COMPANY on completion of the Survey.

A Daily Progress Report (DPR) shall be compiled by the CONTRACTOR on a daily basis and presented to COMPANY for review and comment. The DPR shall include, as a minimum:

Activity Log;

Breakdown of hours reported by activity; Significant events; Intentions for next days work;

Weather conditions for past 24 hours and forecast for next 24 hour period; Any revision to the original survey team listing (issued at mobilisation); Safety comments;

Survey Co-ordinator comments; COMPANY comments; Disputed items;

Photos of calibration points and points of interest such as crossing points.

Page 20: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 20 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

The jointly signed DPR shall be deemed a contractual document and agreed factual statements may

therefore not be disputed afterwards.

8.4 Weekly Report The CONTRACTOR shall prepare a weekly report for COMPANY to review, which shall highlight progress and problems envisaged. This report may be of a brief nature.

8.5 Final Reporting No later than two (2) weeks after completion of data collection, the CONTRACTOR shall provide draft

final reports and map sheets for COMPANY approval.

The format of the Final Report shall be proposed by CONTRACTOR for COMPANY acceptance during pre-survey submissions. The format may be modified during post-survey discussions, taking

into consideration the extent of the actual survey.

The Final Report shall address the following:

1) Introduction and Summary;

2) Scope of Work (specified and achieved); 3) Deviations and Concessions. 4) Description of the Work including:

Survey overview; Horizontal and Vertical positioning systems; Equipment layouts /configurations;

Description of survey instrumentation, including scales, sensitivity settings, calibrations and operating parameters;

Survey procedures, including a quality statement covering sufficiency and accuracy

of data gathered; a comparison of data from survey line crossings, and a discussion of any problems affecting data acquisition or interpretation.

5) Survey Results: topographic, level and detail survey data;

6) Detailed survey charts meeting the requirements; 7) Chart Descriptions; 8) Three-dimensional DTM data, presented in ASCII format;

9) Log of events covering all relevant information in chronological order; 10) Personnel; 11) Equipment calibration certificates;

12) Photos of calibration points and points of interest.

A draft issue of the final report shall be issued to COMPANY in electronic format, on separate CD or DVD media. This will include draft issue copies of all drawings.

COMPANY will issue comments on the draft issue report to CONTRACTOR. The CONTRACTOR shall incorporate these comments into the issue of the Final Report.

Following the comment cycle on the draft Final Report submission, the CONTRACTOR shall issue 2

copies of the Final Report in electronic form (CD) and two hard copy versions.

8.6 Induction Meeting CONTRACTOR participation in certain non-productive activities shall be required. These activities shall include, but not be limited to indoctrination and orientation of all CONTRACTOR employees

prior to commencing work within the Kingsnorth Power Station site. This shall include the entire labour force and all new hires.

Page 21: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 21 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

9 FACILITIES AND UTILITIES FURNISHED BY CONTRACTOR

CONTRACTOR shall supply, install, properly maintain and remove all temporary facilities and utilities as and when necessary for full and complete performance of the Work. Such items shall include, but not be limited to those items listed below. The type of facilities, move-in and move-out dates, and

locations on jobsite shall be subject to approval by COMPANY.

Adequate weather tight storage for of materials, tools and equipment that may be subject to damage by weather;

All temporary buildings, including changing rooms (if required); Fuels and lubricants; All necessary heating and any heating fuels;

Transportation facilities; Communication facilities; Survey equipment;

Snow removal and frost protection, i f necessary; Water supply including potable water; All necessary permits;

All safety items necessary to perform the WORK; First aid facilities and services.

Page 22: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 22 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

10 COMPANY SUPPLIED INFORMATION

COMPANY shall provide CONTRA CTOR with the following information and services during execution of the WORK:

Onshore pipeline route map(s), (HOLD2) [S1] defining the pipeline route centreline and the

corridor to be surveyed; Preliminary special crossing schedule, (HOLD3) [S2]; Preliminary coordinates illustrating the location of the proposed tie-ins and pipeline valve

station site(s); Drawing templates for the production of alignment sheets and special crossing drawings; COMPANY organisation charts and details of personnel who will interface with

CONTRACTOR; E.ON Project Environmental Management Plan, (HOLD4) [S3].

The pipeline route as indicated on the drawings is provided for information and may be subject to

local re-routing during execution of the WORK as directed by COMPANY.

Page 23: 6.33 Topographical Survey Specification

KCP-GNS-CVL-SPC-0001 Rev.: 03

Project Title: Kingsnorth Carbon Capture & Storage Project Page 23 of 23

Document Title: Topographical Survey Specification

Ki ngsnor th C C S D emons tr ati on Pr oj ec t The i nfor mati on contai ned i n thi s document ( the Infor mati on ) i s pr ovi ded i n g ood fai th.

E.ON U K pl c , i ts subcontr ac tors , subsi di ari es , af fi li ates , empl oyees , advi sers , and the D epar tment of Ener g y and Cl i mate C han g e ( D EC C) make no r epr esentat i on or warr anty as to the accur acy, r eli abil ity or compl eteness of the In for mati on and nei ther E.ON U K pl c nor any of i ts subcontr ac tor s , subs i di ari es , af fil i ates , empl oyees , advi ser s or D EC C shall have any l i abi li ty whatsoever for any di r ec t or i ndi r ec t l oss howsoever ar i s i ng fr om the use of the Infor mati on by any par ty.

11 Reference Documents

[S1] KCP-HOLD2 Onshore Pipeline Route Maps

[S2] KCP-HOLD3 Preliminary Special Crossing Schedule

[S3] KCP-HOLD4 E.ON Project Environmental Management Plan

[S4] “Geometric Geodetic Accuracy Standards and Specifications for Using GPS Relative Positioning Techniques”, Federal Geodetic Control Committee; Version 5.0: May 11, 1988, or latest edition.

[S5] KCP-ARP-PMG-PRO-0010 Project Document Numbering Guidelines and Procedure