6.the risk managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by qs-is-2345 2 5 4...

29
CLAMDA-IM Giuseppe Gherardi Project Management 6. The Risk Management Clip 982 Titanic and 983 Challenger

Upload: others

Post on 21-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Project Management

6. The Risk Management

Clip 982 Titanic and 983 Challenger

Page 2: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Risk Management

• Managing projects means taking risks• Every decision, every estimate, every plan is a potential risk driver• The most common way to manage risks is reaction…. When some

unexpected event happens, we react taking corrective actions• But very often, when risks happen, it is too late and we suffer a lack

of effectiveness/efficiency• Setting aside some money for risks management does not mean

we are managing the risks, it means we are hoping that whatever might happen will be covered by the fund we have stored

• We can also have a pro-active approach: we visualize every risk and we decide every possible corrective action we have to take. Then we define corrective action costs.

• At this point we decide what cost we can afford and want to afford: now we are managing risks

Page 3: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

ppe

Ghe

rard

i

Risk Management

• Is it possible to overcome the reactive approach?

• Is it possible to increase the pro-active approach?

• …..

• A Standish Group research tells that on 9.000 IT projects developed in the USA, only the 19% was on time….

• We need a method to manage all the risks we might have

Page 4: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Risk Management

• What is the meaning of “Risk”?

• Risk is a event that has a defined probability to happen and can be a damage for the project…

• “Can” not “will be”…• Risk is, in fact, related to uncertainty. Uncertainty though,

could also be an opportunity if its results are good• “Both threats and opportunities are ‘uncertainties that

matter’, so both are type of risks”

Page 5: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Risk Management

Example:

• I went out with my new suede shoes but the weather forecast says it could rain….

• I am not sure about the rain, so there is a risk…• If it does not rain, I will have a light pair of shoes to walk

easier..• If rains, I will destroy my shoes…• If I see dark clouds, I’ll have to run for shelter because it will

rain!

We have all the elements to identify and manage the risk!

Page 6: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e G

hera

rdi Risk Management

Ex:

TARGET WEARING MY NEW SHOES

RISK

ADVANTAGE

DAMAGE

TRIGGER (sentinel)

PROBABILITY OF RAIN

WALKING EASIER

RUINING MY SHOES

NOTICE BLACK CLOUDS

IF I SEE DARK CLOUDS, I START SEEKING SHELTERSTRATEGY

Page 7: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

ppe

Ghe

rard

i

Risk Management

• Risks can mean threats or opportunities…. We have two kind of risks:

– PURE RISK – if it happens, we only have the probability to suffer a loss• Managing strategy: avoiding, transferring, mitigating

– SPECULATIVE RISK – if it happens, we can suffer a loss or we can have an advantage• Managing strategy: taking advantage, sharing, improving

• Ex: a decrease of a bond in stock exchange could be a threat or an opportunity. It depends on whether we need to sell or we want to buy!

Page 8: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

pp

e G

he

rard

i

Risk Management

• If I have a planned risk managing system, I am able to know what to do in case of a negative event!!

• The Project Team, led by the Project Manager, has to define

risks, triggers, threats/opportunities, strategies…

• Risk strategies cost…

• Who defines the cost level vs risks?....

…. The Sponsor, by setting risk priority and a budget to manage it!

Page 9: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Risk Management

Risk ManagementThe risk management method is a four steps process:

1. Risk identification – we define the risks that could have an impact on the project. We must define the risk characteristics:

1. Risk impacts (damages/advantages), 2. Risk probability3. Risk trigger/sentinel

The project team must start this analysis after the project planning and before the economic phase

Page 10: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

ppe

Ghe

rard

i

Risk Management

2. Qualitative and quantitative analysis – we must define a risk priority list based on the probability to happen and the possible impact (see FMEA analysis). This is the phase when we define the risk management costs and the border between risks (and costs) we want to consider and risks (and costs) we decide to ignore

3. Defensive action plan against risks – we must define actions to minimize threats and maximize opportunities. In this phase we will add new activities (and costs) to the project plan, not directly related to the project target

4. Risk monitoring and controlling –

Page 11: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Risk Management

1 - Risk identification: the Standard Risk Model (SRM)• We define three variables:

1. RISK EVENT – the event that causes a loss/gaina. RISK EVENT DRIVER – is the sentinel, who says that the risk could happenb. RISK EVENT PROBABILITY – is the risk event probability (of occurring)

2. IMPACT – potential loss/gain if the risk happensa. IMPACT EVENT DRIVER – it is the sentinel, who says that the impact could happenb. IMPACT EVENT PROBABILITY – is the impact event probability (of occurring)

3. TOTAL LOSS – total loss (or gain) if the risk happens

Page 12: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e G

hera

rdi Risk Management

SRM - The three variables are related as following:

IMPACT

RISK EVENT

TOTAL

LOSS

RISK EVENT PROBABILITY

RISK EVENT DRIVERS

IMPACT EVENT DRIVERS

IMPACT EVENT PROBABILITY

Page 13: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Risk Management

SRM• The Standard Risk Model (SRM) is important because it

separates risks from impacts

• We have two levels of probabilities: risk probability and impact probability

• That means we can operate on two variables…. If I am not able to decrease the probability of a risk occurring, I can operate to decrease any negative effect (impact) on our project!

Page 14: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-IM

Giu

se

pp

e G

he

ra

rd

i

Risk Management

SRM example:

DESIGN

CONTROL + APPROVAL

WK1 WK2 WK3 WK4

Freddy is

UNAVAILABLE

Marco+Joel

Freddy

1st of April 21st of April7st of April 14st of April

WK5

Let’s imagine a short part of a project, formed by 2 activities: 1-

mechanical sub-assembly drawning; 2-drawing check and approval

by a technical controller

Watching the project’s calendar, we can see that Freddy will be unavailable on week 4

(Freddie will be on holyday or busy in othe activity).

The activity sequence shows a risk: if the drawing activity or the control activity will

have a delay, the activities block will suffer a delay amplified due to Freddy

unvailability on week 4

Page 15: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

pp

e G

he

rard

i

Risk Management

SRM example:

“Human resources working on the project are not enough…. We could delay the finish date”

• This sentence is completely inefficient because it doesn’t separate the time when I have the risk and time when I have the impact

• But, I can understand which activity I haven’t enough resources for…

• …Risk event 1 – the company HR write a mail to the project manager: “…from the 1st of April all the technicians will attend a course.”

Page 16: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

ppe

Ghe

rard

i

Risk Management

SRM example:

• Risk event driver – HR wrote: “Starting from the 1st of April, the two technicians will attend a course”

• Impact – the “Design” activity, scheduled for 3wks (2wks design and 1wk approval) will delay of 2wks

• Impact driver – the person in charge of the design approval will be unavailable starting from the 21st of April for 1wk

The Risk driver gives a three weeks loss, but the impact driver defines the delay length

Page 17: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

pp

e G

he

rard

i

Risk Management

SRM example:

Adopting the SRM, our target is working separately on the two

drivers to minimize the total impact

Risk driver action: I can negotiate with HR a new course date, so I can eliminate

the risk!

Impact driver action: if I cannot eliminate the risk, I can ask for a substitute

who will be in charge of design approval. In this way I can reduce the

impact of only 1wk

Thinking about different drivers with SRM allows us to define:

– Precautionary plans working on risks! – Reaction plans working on impacts!

Page 18: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di

1 - Risk identification: the Standard Risk Model (SRM)

Risk Management

The Risk Breakdown Structure (RBS) is a list of standard risk cathegories

Page 19: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

ppe

Ghe

rard

i

Risk Management

To identify risks, for each of them we have to define :• Risk (Risk event)• Risk event driver• Risk probability• Impact (impact event)• Impact event driver• Impact probability• Loss/gain • Total risk probability• Expected loss/gain• Priority

Page 20: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Risk Management2- Qualitative and quantitative analysis: the Failure Mode & Effect

Analysis (FMEA)

RISK (Failure mode)Is the risk mode, or the event.

It could be the way a component or a process fails

IMPACT (Effect)It is the impact we will have if the risk was not correctly

estimated

REASON (Cause)Is the actual cause of the risk

Page 21: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e G

hera

rdi Project Risk Management

•After the FMEA analysis, we have to define responsibilities and time for corrective/precautionary actions

• We have to verify the action’s effectiveness after being issued, evaluating the real risk priority index

•We have to update the FMEA according to project changes

2- Qualitative and quantitative analysis: the Failure Mode & Effect Analysis (FMEA)

Page 22: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Risk Management

The failure mode is how the risk appears in the process/project, the impact is the consequence of the risk

For each risk (mode), the project team has to define: •all the possible related impacts (effects), •all the possible related causes, • risk probability (p)• impacts (effects) importance (g)•risk driver “difficult to see” grade (r)

For each risk/impact/cause, we can calculate the

RISK PRIORITY INDEX = p x g x r

2- Qualitative and quantitative analysis: the Failure Mode & Effect Analysis (FMEA)

Page 23: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Project Risk Management2- Qualitative and quantitative analysis: the Failure Mode & Effect

Analysis (FMEA)

Page 24: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-IM

Giu

sepp

e G

hera

rdi

Company FMEA FMEA N°

Date:Group: Last rev

date:

Component Failure mode As Is Situation Corrective actions Final Situation

PN Description Mode Cause Effects ControlsP

(1-5)G

(1-5)R

(1-5)RPI

Actions planned

Resp. TimeActions

doneP

(1-5)G

(1-5)R

(1-5)RPI

100.34555.3Filter for ABS brake system

Net detaching

Net not well attached to support

Filter doesn’t run, brake system block, fatal acc

Statistic control by QS-IS-2345

2 5 4 40 0

100.34555.3Filter for ABS brake system

Filter is not complete

Wrong injection pressure

Filter doesn’t run, brake system block, fatal acc

Statistic control by QS-IS-2345

2 5 3 30 0

100.34555.3Filter for ABS brake system

Mode…. Cause… Effect…

Statistic control by QS-IS-2345

3 1 5 15 0

i

Project Risk Management

2- Qualitative and quantitative analysis: the Failure Mode & Effect Analysis (FMEA)

Page 25: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di

i

Project Risk Management2- Qualitative and quantitative analysis: the RISK ASSESSMENT

MATRIX

Page 26: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e G

hera

rdi

i

Project Risk Management3- Risk Contingency Plan

EVENT

DAMAGE

LOSS

ELUSION

PROTECTION

ASSURANCE

PREVENTION

RISK TRANSFER

RISK RETENTION

Risk Structure Risk Tools

PHYS

ICAL

CO

NTR

OL

FIN

ANCI

NG

CO

NTR

OL

Page 27: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

ppe

Ghe

rard

i

Project Risk Management

3- Risk Contingency Plan

Elusion – has the objective to exclude the possibility of risk occurrence by renouncing to carry out the project activities connected with this riskPrevention – set of measures aimed at reducing the probability of occurrence of risky events, while not renouncing to carry out the activities connected to themProtection – set of security measures aimed at limiting the economic impact of the damage connected to the risk, intervening only to verified damage. It intervenes that is when the prevention failsAssurance – insurance policy to transfer the risk to a specialized company

Page 28: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLA

MD

A-I

M G

iuse

ppe

Ghe

rard

i

Project Risk Management

3- Risk Contingency Plan

Transfer (non insurance) – consists of the transfer of risk to other subjects other than an insurance company (eg subcontracting)Retention – consists of another form of non-risk-based transfer, where the same organization that manages the project takes on the risk, providing for its financing with its own resources. In this regard it is necessary that the Project Manager reaches the complete knowledge of all the risks that could threaten the project, so that does not remain an unconscious area of retention. This prudence does not only apply to the identification of a risk, but also to the correct evaluation of its effect

Page 29: 6.The Risk Managementgiuseppegherardi.weebly.com/uploads/7/8/3/0/7830719/apm...by QS-IS-2345 2 5 4 40 0 100.34555.3 Filter for ABS brake system Filter is not complet e Wrong injection

CLAM

DA-IM

Giu

sepp

e Gh

erar

di Project Risk Management4- Risk control