2G KPI BASIC TARGET a. KPI Site Level target for 2G is as follow: OSS KPI Site Cell Level : KPI Basic (New Site) KPI Decongestion KPI Rehoming N o OSS KPI NAME TRAFFIC TYPE WEIGHT TARGET WEIGHT TARGET WEIGHT TARGET 1 CSSR Voice 40.00% 97.00% 25% Baseline **) 40.00% Baseline **) 2 CDR Voice 40.00% 1.25% 25% Baseline **) 40.00% Baseline **) 3 HOSR Voice 20.00% 97.00% 10% Baseline **) 20.00% Baseline **) 4 TBF Establishment Success Rate *) Data na Info only na Info only na Info only 5 TBF Drop Rate *) Data na Info only na Info only na Info only 6 SDCCH Drop Rate Voice na na 10% Baseline na na 7 TCH Assignment Failure Rate Voice na na 10% baseline na na 8 Traffic CS Voice na na 20% baseline na Info only 9 Traffic PS Data na na na Info only na Info only Remarks : *) Total GPRS and EDGE; UL and DL **) If in cell level baseline of CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, degradation delta 5% (counted from Failure rate) on achievement can be considered to be PASSED (example if baseline CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, so achievement CSSR>=98.95%, HOSR>=98.95% & CDR<=0.55%, can be considered to be PASSED)

Upload: thats-myname

Post on 12-Nov-2014

54 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: 72519459 2g 3g Kpi Basic Target

2G KPI BASIC TARGET

a. KPI Site Level target for 2G is as follow:

OSS KPI Site Cell Level :

KPI Basic (New Site) KPI Decongestion KPI Rehoming No OSS KPI NAME TRAFFIC

TYPE WEIGHT TARGET WEIGHT TARGET WEIGHT TARGET

1 CSSR Voice 40.00% 97.00% 25% Baseline **) 40.00% Baseline **)

2 CDR Voice 40.00% 1.25% 25% Baseline **) 40.00% Baseline **)

3 HOSR Voice 20.00% 97.00% 10% Baseline **) 20.00% Baseline **)

4 TBF Establishment Success Rate *)

Data na Info only na Info only na Info only

5 TBF Drop Rate *) Data na Info only na Info only na Info only

6 SDCCH Drop Rate Voice na na 10% Baseline na na

7 TCH Assignment Failure Rate Voice na na 10% baseline na na

8 Traffic CS Voice na na 20% baseline na Info only

9 Traffic PS Data na na na Info only na Info only

Remarks : *) Total GPRS and EDGE; UL and DL **) If in cell level baseline of CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, degradation delta 5% (counted from Failure rate) on achievement can be considered to be PASSED (example if baseline CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, so achievement CSSR>=98.95%, HOSR>=98.95% & CDR<=0.55%, can be considered to be PASSED)

Page 2: 72519459 2g 3g Kpi Basic Target

Drive Test KPI Site Cell Level :

KPI Basic (New Site)

KPI Decongestion KPI Rehoming

No OSS KPI NAME

DT Mode WEIG

HT TARGET

WEIGHT TARGET WEIG

HT TARGET

1 CSSR QoS 20.00% 98.00% na na na na

2 CDR QoS 20.00% 1.00% na na na na

3 HOSR QoS 15.00% 98.00% na na na na

4 SQI (Speech Quality Index) > 20 QoS

15.00% 92.00%

na na na na

5 Rx Quality (0 – 5) QoS 15.00% 92.00% na na na na

6 Rx Level >= -85 dBm Idle

15.00%

95.00% *) na na na na

Remarks : *) Based on coverage comparation with Prediction Plot

b. KPI Cluster Level target for 2G is as follow:

OSS KPI Cluster Level :

KPI Swap (Modernisasi) *) KPI Reparenting *) KPI LAC Splitting *)

No OSS KPI NAME TRAFFI

C TYPE WEIGHT TARGET WEIGHT TARGET WEIGHT TARGET

1 CSSR Voice na Baseline ***) na Baseline

***) na Baseline ***)

2 CDR Voice na Baseline ***) na Baseline

***) na Baseline ***)

3 HOSR Voice na Baseline ***) na Baseline

***) na Baseline ***)

4 TBF Establishment Success Rate **) Data na baseline na baseline na baseline

5 TBF Drop Rate **) Data na baseline na baseline na baseline

6 SDCCH Drop Rate Voice na Baseline

****) na na na na

7 TCH Assignment Failure Rate Voice na Baseline

****) na na na na

8 Traffic CS Voice na baseline na baseline na baseline 9 Traffic PS Data na baseline na baseline na baseline Remarks : *) All OSS KPI items target must be achieved . In case Modernization Swap, Reparenting & LAC

Page 3: 72519459 2g 3g Kpi Basic Target

Splitting, beside all KPI item target in the cluster must be achieve, each site level achievement in this cluster also shall PASS the OSS KPI Basic Cell Site Level Target (refer to OSS KPI Basic New Site Table) as minimum performance **) Total GPRS and EDGE; UL and DL ***) If in cluster level baseline of CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, degradation delta 5% (counted from Failure rate) on achievement can be considered to be PASSED (example if baseline CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, so achievement CSSR>=98.95%, HOSR>=98.95% & CDR<=0.55%, can be considered to be PASSED) ****) This KPI Item (SDCCH Drop rate & TCH Assignment Failure Rate) will be applied if there is additional capacity on Swap (Modernization) Project

Drive Test KPI Cluster Level :

KPI Swap (Modernisasi) *) KPI Reparenting *) KPI LAC Splitting *)

No OSS KPI NAME DT Mode WEIGHT TARGET WEIGHT TARGET WEIGHT TARGET

1 CSSR QoS na baseline na baseline na baseline

2 CDR QoS na baseline na baseline na baseline

3 HOSR QoS na baseline na baseline na baseline 4 SQI > 20 QoS na baseline na baseline na baseline 5 Rx Quality (0 – 5) QoS na baseline na baseline na baseline

6 Rx Level >= -80 dBm Idle na baseline na baseline na baseline

Remarks : *) All DT KPI items target must be achieved

Page 4: 72519459 2g 3g Kpi Basic Target

Remarks for 2G KPI Target (OSS & DT):

General :

• Passing Criteria for Project Activity is if the achievement score is >= 90 (for all OSS & DT), and can be achieved at defined time frame

• KPI Successfulness calculation weighting for each activity is as follow:

KPI Type New Sites

Decongestion Rehoming Modernization

(Swap) Reparenting LAC Splitting

OSS 50% 100% 100% No weighting (All KPI Target must be achieved)

No weighting (All KPI Target must be achieved)

No weighting (All KPI Target must be achieved)

DT 50% na na No weighting (All KPI Target must be achieved)

No weighting (All KPI Target must be achieved)

No weighting (All KPI Target must be achieved)

Minimum score to be achieved

90% 90% 90% 100% 100% 100%

• KPI Successfulness calculation timeline for each activity is as follow:

KPI Type New Sites

Decongestion Rehoming

Modernization (Swap)

Reparenting

LAC Splitting

OSS 4 weeks 4 weeks 4 weeks 4 weeks 4 weeks 4 weeks DT 4 weeks na na 4 weeks 4 weeks 4 weeks

• After project activity implementation vendor shall perform :

Measurement Lock Value (CSSR>= 88.00% & CDR<=6.00%) as long as 3 hours after implementation (hourly). If can not achieve this threshold, cell should be locked on related NE which cause bad performance. Vendor should provide fall back scenario and shall perform trouble shooting for solve the problem immediately

Quality Performance Monitoring for checking stability of performance as long as 3 days before & after implementation. Quality Statement Report on 4th day after implementation shall be submitted to all related party (the result of 3 days quality monitoring before & after implementation)

Page 5: 72519459 2g 3g Kpi Basic Target

KPI Site Cell Level :

• KPI Site Cell Level will be implemented to New Site, Decongestion & Rehoming activity. • KPI Site Cell Level means that KPI will be measured based on cell achievement, but for

acceptance will be based on Site Level • KPI Site Cell Level acceptance will be based on site cell level achievement for OSS & DTOSS

Data will be checked based on each cell achievement for the related site • OSS Site Achievement score based on average of each cell achievement score • OSS measurement data for baseline & achievement based on 1 week measurement data

(7x24 hours), starting from Monday to Sunday • If in cell level baseline of CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, degradation delta 5%

(counted from Failure rate) on achievement can be considered to be PASSED (example if baseline CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, so achievement CSSR>=98.95%, HOSR>=98.95% & CDR<=0.55%, can be considered to be PASSED)

• Certificate of KPI Basic for New Site, Decongestion & Rehoming activity will be issued per Site Level if the achievement score is >= 90 (for all OSS & DT), and can be achieved at defined time frame

KPI Cluster Level :

• KPI Cluster Level will be implemented to Modernization (Swap), Reparenting & LAC Splitting Activity

• KPI Cluster Level acceptance will be based on cluster level achievement for OSS & DT • Each site in a cluster level should achieve OSS KPI Basic for New Site Target as minimum

performance • KPI Score for each site in a cluster is same, refer to KPI Cluster Score itself • OSS measurement data for baseline & achievement based on 1 week measurement data

(7x24 hours), starting from Monday to Sunday • If in cluster level baseline of CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, degradation delta

5% (counted from Failure rate) on achievement can be considered to be PASSED (example if baseline CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, so achievement CSSR>=98.95%, HOSR>=98.95% & CDR<=0.55%, can be considered to be PASSED)

• Certificate of KPI Basic for Modernization (Swap), Reparenting & LAC Splitting Activity will be issued per Site Level if the achievement score is >= 90 (for all OSS & DT), and can be achieved at defined time frame

Others :

• Related to parameter setting, vendor shall ensure that the parameters are set properly, including for handover relationship in order to avoid performance degradation

• Related to KPI Basic Drive Test scope, vendor shall ensure that these items performed:

a. To ensure no antenna feeder cross connect

b. To minimize overshooting signal to/from other cells

c. To ensure no bad frequency assignment such as co-BCCH

d. To define drive test route and get an approval from Indosat before performing drive test

e. To perform drive test after get an approval from Indosat

Page 6: 72519459 2g 3g Kpi Basic Target

3G KPI TARGET

KPI Basic Site Cell Level target for 3G is as follow:

OSS KPI Basic :

KPI Basic (New Site) KPI Rehoming *) No OSS KPI NAME

TRAFFIC TYPE WEIGHT TARGET WEIGHT TARGET

1 CSSR CS Voice 20.00% 97.00% na baseline

2 CDR CS Voice 20.00% 1.25% na baseline

3 HOSR Voice 30.00% 97.00% na baseline 4 CSSR PS Data 15.00% 97.00% na baseline 5 CDR PS Data 15.00% 1.25% na baseline Remarks : *) All KPI items target must be achieved

Drive Test KPI Basic :

KPI Basic (New Site) KPI Rehoming *) No OSS KPI NAME TRAFFIC TYPE

WEIGHT TARGET WEIGHT TARGET

1 CSSR Voice QoS 7.50% 98.00% na baseline

2 CSSR Video QoS 5.00% 98.00% na baseline

3 CSSR R99 QoS 7.50% 98.00% na baseline 4 CSSR HSDPA QoS 7.50% 98.00% na baseline 5 CDR Voice QoS 7.50% 1.00% na baseline 6 CDR Video QoS 5.00% 1.00% na baseline 7 CDR R99 QoS 7.50% 1.00% na baseline 8 CDR HSDPA QoS 7.50% 1.00% na baseline 9 HOSR **) QoS 10.00% 98.00% na baseline 10 CQI QoS 10.00% >=22 na baseline

11 Ec/No >= -10dB QoS 12.50% 92.00% na baseline

12 CPICH RSCP >= -86 dBm ***) Idle 12.50% 95.00% na baseline

Remarks :

*) All KPI items target must be achieved

**) include Softer, Soft and 3G-2G handover

***) on agreed route

Page 7: 72519459 2g 3g Kpi Basic Target

Remarks for 3G KPI Target (OSS & DT):

• KPI Successfulness calculation weighting for each activity is as follow:

KPI Type New Sites Rehoming

OSS 50% No weighting (All KPI Target must be achieved) DT 50% No weighting (All KPI Target must be achieved) Minimum score to be achieved 90% 100%

• KPI Successfulness calculation timeline for each activity is as follow:

KPI Type New Sites Rehoming

OSS 4 weeks 4 weeks DT 4 weeks na

• KPI Site Cell Level will be implemented to New Site & Rehoming activity.

• KPI Site Cell Level means that KPI will be measured based on cell achievement, but for acceptance will be based on Site Level

• KPI Site Cell Level acceptance will be based on site cell level achievement for OSS & DT

• OSS Data will be checked based on each cell achievement for the related site

• OSS Site Achievement score based on average of each cell achievement score

• OSS measurement data for baseline & achievement based on weekly data (7x24 hours)

• If in cell level baseline of CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, degradation delta 5% (counted from Failure rate) on achievement can be considered to be PASSED (example if baseline CSSR>=99.00% HOSR>=99.00% & CDR <=0.5%, so achievement CSSR>=98.95%, HOSR>=98.95% & CDR<=0.55%, can be considered to be PASSED)

• Certificate of KPI Basic for New Site & Rehoming activity will be issued per Site Level if the achievement score is >= 90 (for all OSS & DT), and can be achieved at defined time frame