7311 STEVENS CROFT
WOOD BURNING POWER
PLANT
THE UK’s LARGEST BIOMASS
PLANT
UHN
The
Stack
85M HIGH
45M HIGH
KEY ROLES
• CLIENT - E-on
• JOINT VENTURE: • CIVILS DELIVERY COMPANY – SIEMENS
• M&E DELIVERY COMPANY – METSO
• DELIVERY OF THE CIVILS WORKS: • 95% ALFRED McALPINE
• 5% Re-Bau (UK division ceased trading)
SOME FACTS AND FIGURES
• OVERALL PROJECT VALUE – £90m
• AMPS ELEMENT – £5.6m
• AT PEAK LOAD THE PLANT WILL PRODUCE –
50MW OF POWER OF WHICH 5MW WILL BE
RETAINED ON SITE
• ENOUGH POWER FOR 70,000 HOMES
• THE PLANT WILL BURN 220,000T OF OVEN DRIED
WOOD EACH YEAR (OR 235m3/hr) TO MEET ITS
RENEWABLE FUEL TARGET
PRINCIPLE QUANTITIES
• TOTAL CONCRETE PLACED – 7,000M3
• TOTAL REINFORCEMENT FIXED – 900T
• TOTAL FORMWORK INSTALLED – 11,500M2
KEY PROGRAMME DATES
• CONTRACT AWARD DATE: 06 April 06
• START ON SITE: 24 April 06
MILESTONE DATES
STRUCTURE MILESTONE MILESTONE
DATE
COMPLETION
DATE
UMA Turbine foundation finalised:
LD – £25k/wk 23 June 06 23 June 06
UHA/UGD Ready for erection of steelwork on
finalised foundation: LD – £20k/wk 26 July 06 26 July 06
UBA Ready for erection of walls and
columns on finalised foundation:
LD – £10k/wk
04 Aug 06 04 Aug 06
UMA Ready for erection of steelwork
and turbine on finalised
foundation: LD – £35k/wk
15 Sept 06 26 July 06
UBA Ready for erection of electrical
installation: LD – £15k/wk 13 Nov 06 13 Nov 06
UEA Ready for erection of mechanical
parts: LD – £10k/wk 08 Dec 06 22 Dec 06
ARRIVAL ON SITE
UMA
TURBINE BUILDING
UHA/UGD
BOILER HOUSE/ WATER DEMIN
BUILDING
UHN
THE STACK
UEA
FUEL STORAGE BUILDING
ADDITIONAL WORKS
THE FIRE AND DOMESTIC MAIN
THE TEAM Project Director – Stuart Cameron
Commercial Manager – Chris Notman
Project Manager – Mark Johnston
Site Support – Steve Murray
Site Support – Bob Meadows
GF – Dave Pickering
QS – Colin Irving
Senior Engineer – Brian Baguley
Site Engineer – Robert Conn
Office Manager – Jannette Young
Assistant Office Manager – Lorette Anderson
Formwork And Concrete – Tom Osprey Joiners
Reinforcement – Henderson Rebar
Structural Steel And Cladding - Polimex