8 vedlegg b

Upload: gilang-romadhon

Post on 12-Oct-2015

16 views

Category:

Documents


1 download

TRANSCRIPT

  • DET NORSKE VERITASTM

    REPORT NO./DNV REG NO.: 2013-4091 / 17TLT29-5

    REV 1, 11.06.2013

    APPENDIX B

    HAZID

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 1 of 12

    Table of Contents Page

    1 BACKGROUND AND SCOPE OF WORK ...................................................................................... 2

    2 METHODOLOGY .............................................................................................................................. 4

    3 PARTICIPANTS ................................................................................................................................. 6

    4 SUMMARY OF HAZARDS IDENTIFIED ....................................................................................... 6

    5 HAZID LOG ....................................................................................................................................... 7

    6 REFERENCES .................................................................................................................................. 11

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 2 of 11

    Conclusion of the review on the 17.05.2013:

    After review of the HAZID inputs and conclusion delivered on the 18.05.2012, DNV assessed that no

    update is required as the concept design used as basis for the HAZID has not changed in the detail

    engineering phase.

    1 BACKGROUND AND SCOPE OF WORK

    A one day HAZID workshop was carried out in June 2011 for the design at that stage of LNG

    bunkering station in Risavika, ref. /1/. As the design has changed considerably since then, an update of

    the HAZID was carried out on February 16 2012.

    The objective was to identify and assess potential hazards for the LNG bunkering station, with focus

    on safety. Risks reducing measures were identified and assessed where possible.

    Like the HAZID in 2011, this update focuses only on hazards associated with bunkering of LNG to

    ferries on jetty 38. This includes equipment and operations both inside and outside the LNG Base Load

    Plant, ref. Figure B - 1 and Figure B - 2, respectively.

    For remaining hazards associated with the LNG Base Load Plant, reference is made to the QRA from

    2009, ref. /2/.

    The HAZID does not take into account the risks due to ship or truck LNG loading to the ferry.

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 3 of 11

    Figure B - 1 Equipment associated with the bunkering system located inside the plant

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 4 of 11

    Figure B - 2 Route of the underground pipe and bunkering station on jetty 38

    2 METHODOLOGY

    HAZID (Hazard Identification) is a systematic review of installations and/or operations in order to

    screen potential hazards. The HAZID review on February 16 2012 was run in a workshop with

    participants from Skangass, Fjordline and DNV. Each hazard was assigned a likelihood and

    consequence category, so that each hazard could be ranked in accordance with a predefined risk

    matrix, see Table B - 1. This risk matrix is the same as the one used in HAZID in June 2011.

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 5 of 11

    Table B - 1 Risk matrix

    Severi

    ty

    Consequence Categories Likelihood

    Peo

    ple

    En

    viro

    n-

    men

    t

    Del

    ay /

    Do

    wn

    tim

    e

    Rep

    uta

    tio

    n

    1 2 3 4 5 6

    Failure is not

    expected

    < 10-5

    Never heard of in

    Industry

    10-4 - 10-5

    An incident

    has occurred

    in Industry

    10-3 - 10-4

    Has been experienced

    by most Operators 10-2 - 10-3

    Occurs several times

    per year per

    Operator 10-1 - 10-

    2

    Occurs several times

    per year per

    facility >10-1

    1 No or superficial injuries

    Slight effect on environment, < 1 BBL

    < 2 hours

    Slight impact; local public awareness but no public concern

    L L L M M M

    2

    Slight injury, a few lost work days

    Minor effect Non-compliance. < 5 BBL

    < 1 day

    Limited impact; local public concern may include media

    L L M M M H

    3

    Major injury, long term absence

    Localized effect Spill response required. < 50 BBL

    1 - 10 days

    Considerable impact; regional public/slight national media attention

    L M M M H H

    4

    Single fatality or permanent disability

    Major Effect Significant spill response, 100 BBL

    > 60 days

    Extensive negative attention in international media

    M M H H H H

    Risk Definition:

    High Actions must be taken to reduce risk to at least the medium level

    Medium

    Risk reduction measures must be taken if their respective costs are not disproportionately high as compared to their

    attained benefits (ALARP principal); actions need to be taken to manage and measure risk.

    Low Monitoring actions required to identify whether the risk rises to medium level

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 6 of 11

    3 PARTICIPANTS

    Table B - 2 Participants at the HAZID workshop March 16 2012

    Name Company Position / role in HAZID

    Camilla Gautestad Skangass Process Manager, Gas & LNG projects

    Gunnar Helmen Skangass Key Account Manager, LNG Industry & Marine

    sbjrn Folvik Skangass Process engineer, LNG Industry & Regulations

    Morten Larsen Fjordline Technical & Nautical Director

    Erik Skramstad DNV HAZID facilitator

    Jon Magne Ofte DNV QRA Project Manager

    Jean-Baptiste Berthomieu DNV Scribe

    4 SUMMARY OF HAZARDS IDENTIFIED

    The new design of Skangass bunkering system is considered an improvement in terms of safety, as it mitigates or eliminates some of the hazards identified in the HAZID from June 2011: The likelihood of

    a leak is reduced by introducing underground, double wall pipeline and by eliminating buffer tanks and

    flare.

    Since the HAZID in 2011, the number of hazards with criticality High is reduced to one:

    1-4 Leaks from the loading arm during bunkering operations, caused by fabrication or material defects; weld defects, leaking seals and swivels. Possible consequences are fires if ignition

    sources on and around bunkering ferry (under ro-ro operation) are present; risks to ship

    passengers.

    The main changes include the lower criticality of the following hazards, due to reduction of likelihood

    and/or consequence:

    Criticality changed from Medium to Low:

    o 1-1 Release of N2 and HC from vents on the ship (ship-side)

    o 1-2 Inability of purging N2 from the loading arms

    o 1-12 Damage to loading arms with possible release of LNG (New: No crane operations during bunkering operations.)

    o 3-1 Loss of LNG supply capacity

    o 3-2 Damage to piping system inside the LNG plant

    Criticality changed from High to Medium:

    o 1-10 Loss of control during filling of ship (New: ESD has been provided; the system will fail in a safe position.)

    Other changes since the HAZID in 2011 do not move hazards from one criticality level to the next.

    All changes are marked with text in red in the HAZID log in the next chapter.

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 7 of 11

    5 HAZID LOG

    (Text in red has been revised since HAZID June 2011)

    ID HAZARD CAUSE POSSIBLE CONSEQUENCES

    DETECTION SAFEGUARDS / CONTROL MEASURES

    Cat

    ego

    ry

    Co

    nse

    qu

    ence

    Lik

    elih

    oo

    d

    Cri

    tica

    lity COMMENTS

    1-0 Loading area loading arm from LNG Base Load Pant to ship 1-1 Release of N2 and HC

    from vents on the ship (ship-side)

    N2 purging of loading arms into the ship's main header vent system

    Fire hazard if ignition sources on and around bunkering ferry (under ro-ro operation) are present

    Design of cold vent; minimise purging through better control of the process; design of fire fighting system (foam etc.)

    1 3 L This could be a problem when simultaneous passenger and cargo "offloading" are being carried out

    1-2 Inability of purging N2 from the loading arms

    Pollution of fuel in the ship's fuel tank

    Control of the purging process

    1 2 L

    1-3 Release of N2 and HC from the loading arms (shore-side)

    Unintended releases during connection and preparation for the LNG transfer

    Minor fire with HC release Demonstration to authorities on this (safe?) design

    1 3 L Neighbouring pressure relief valves can be connected to this onshore header vent system. With the current procedure, the release is small, then the consequences will be small as well.

    1-4 Leaks from the loading arm during bunkering operations

    Fabrication or material defects; weld defects; leaking seals and swivels

    Gas dispersion Manual detection possible but not reliable (due to surrounding noise pollution during work)

    Gas detectors and immediate / automatic shut-down

    2 3 M Consider visual indication of closed connections; hydraulic backup system of the loading arms should be considered

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 8 of 11

    ID HAZARD CAUSE POSSIBLE CONSEQUENCES

    DETECTION SAFEGUARDS / CONTROL MEASURES

    Cat

    ego

    ry

    Co

    nse

    qu

    ence

    Lik

    elih

    oo

    d

    Cri

    tica

    lity COMMENTS

    1-5 Fires if ignition sources on and around bunkering ferry (under ro-ro operation) are present; risks to ship passengers

    Visual detection (continuously operated during ship loading)

    Immediate / automatic shut-down; elimination of ignition sources in classified areas; fire-fighting

    4 4 H Address radiation level and fire effects on personnel and passengers on the open-bridge and open decks during the bunkering; Consider access control to the open-deck and fire protection on the bridge.

    1-6 Embrittlement Spill protection (for the steel on the deck)

    3 3 M

    1-7 Frost burns PPE mandatory 3 3 M

    1-8 Unplanned disconnection of the loading arms, with possible damage to equipment and release of LNG

    Excessive ship motions due to failure in engine control system on the ship; failure in mooring; passing ships; weather

    Refer to consequences in ID 1.04,1.05,1.06,1.07

    Manual detection Berthing control of the ship; weak link/quick release coupling will minimise damages to the loading arm

    3 3 M Emergency procedures to be addressed in the overall operation procedures as well as during training etc.

    1-9 Overfilling of fuel tank (ship)

    Control failure (instrument; operational etc.)

    Release of LNG through tank relief valves, and NG through pressure relief valves. Refer to consequences in ID 1.04,1.05,1.06,1.07

    Level alarm controls

    Operational procedures and tank protection system (level indicators)

    4 3 M This is linked to the ship design, it will be designed according to the IMO guidelines (ESD link will be provided)

    1-10 Loss of control during filling of ship

    Loss of power Abortion of the filling process in an unsafe state

    Loss of power / black-out should be easily detected

    This has to be addressed in the ESD philosophy (including the back-up of power supply)

    2 3 M ESD has been provided; the system will fail in a safe position.

    1-11 Damage to loading arms with possible release of LNG

    Impacts from trucks and crane arms

    Fire hazards (trucks acting as potential ignition sources). Injuries to facility operators and ferry

    Manual detection Concrete or other protective barriers and traffic rules (speed limits etc.); no traffic during bunkering operation

    4 1 M

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 9 of 11

    ID HAZARD CAUSE POSSIBLE CONSEQUENCES

    DETECTION SAFEGUARDS / CONTROL MEASURES

    Cat

    ego

    ry

    Co

    nse

    qu

    ence

    Lik

    elih

    oo

    d

    Cri

    tica

    lity COMMENTS

    1-12 Dropped objects on loading arms from cranes loading the ship

    passengers. Refer also to consequences in ID 1.04,1.05,1.06,1.07

    Manual detection No crane operations during bunkering operations

    3 1 L Crane activities should be carried out at a safe distance from loading manifold (or vice versa)

    1-13 Ship collision / impact from other passing vessels

    Human error and / or technical failures, leading to loss of navigational control

    Structural damage to the ship. Possible damage to the loading arms cannot be disregarded.

    Manual detection Port traffic controls 3 2 M Harbour traffic control (especially due to the increased sea traffic opposite to LNG bunkering facility) - Refer to DNV Risk Analysis on Risavika Harbour

    1-14 Damage to loading arms when disconnected

    Truck traffic; dropped containers; collision impact from other vessels

    Material damage to the (normal stainless steel) arm and possible release of LNG (before LNG has evaporated)

    Visual observation / inspection

    Shut-down valves at both the ship-side and onshore tank-side of the filling line; consider possibility to empty loading arm after disconnection

    2 3 M Low probability (and minimal spillage of LNG); Loading arm will contain LNG shortly after loading; safety zone around the loading arm; access is restricted to limited (trained) personnel; protection equipment by personnel present at that area

    1-15 Unplanned abortion of fuelling operation

    External fire (on ship, building and truck)

    Damage to equipment (including escalation); delay

    Visual observation Fire detection and fire-fighting; ESD and emergency plans

    3 3 M To be addressed as part of the ESD procedures

    1-16 Sabotage and terrorist attacks

    Covered as part of meeting the international regulation requirements (ISPS)

    1-17 Failure of the vacuum-insulated transfer line

    Material fabrication defects Shut down and need for repairs

    Loss of vacuum (detected in the control room)

    Design of culvert, pipe support and draining system of the culvert, ventilation system if culvert is closed

    3 3 M

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 10 of 11

    ID HAZARD CAUSE POSSIBLE CONSEQUENCES

    DETECTION SAFEGUARDS / CONTROL MEASURES

    Cat

    ego

    ry

    Co

    nse

    qu

    ence

    Lik

    elih

    oo

    d

    Cri

    tica

    lity COMMENTS

    1-18 LNG releases in the culvert

    Double barriers failure; digging activities; flooding; Fatigue; improper installation; excessive loads of traffic activities; vibrations; settlement.

    Fire and explosion Gas detectors (if flanges are present inside the culvert); otherwise vacuum detectors / monitoring should be adequate

    Minimise valves / flange connections inside the culvert

    4 1 M Valves / flange connections should preferably be outside the culvert

    2.0 LNG Buffer Tank(s) (top and bottom filling inlets) & its filling lines No longer part of the design

    3-0 Main LNG plant - 42-TR-101 tank & truck loading bay

    3-1 Loss of LNG supply capacity

    Loss of fuelling capacity, i.e. breakdown of facility's reliability

    Visual Revise the operational manual so as to consider the reliability of the truck and Buffer tank(s) filling

    1 3 L

    3-2 Damage to piping system inside the LNG plant

    Release of LNG in Truck Loading Bay; fire and explosion (due to ignition sources from the trucks)

    Process control and gas detectors at the Truck Loading Bay

    Ensure that piping system is designed for situation with back-flow in the system

    1 3 L Vapour return line to be considered?

    3-3 Failure of liquid lines from pump 42-PS-101B

    Increased frequency of use The increased use of this pump should be reflected in the QRA

  • DET NORSKE VERITAS

    Report for Skangass AS

    Appendix B HAZID

    MANAGING RISK

    DNV Reg. No.: 17TLT29-5

    Revision No.: 1

    Date : 11.06.2013 Page 11 of 11

    6 REFERENCES

    /1/ Risikovurdering av LNG bunkring av RoPax ferje i Risavika havn, DNV reg. no. 12PABXZ-

    21, 26.08.2011

    /2/ QRA for Skangass LNG plant, DNV report no. 2009-0068, rev 1, 08.05.2009

  • Det Norske Veritas:

    DNV is a global provider of knowledge for managing risk. Today, safe and responsible business conduct is both a license to operate and a competitive advantage. Our core competence is to identify, assess, and advise on risk management, and so turn risks into rewards for our customers. From our leading position in certification, classification, verification, and training, we develop and apply standards and best practices. This helps our customers to safely and responsibly improve their business performance. Our technology expertise, industry knowledge, and risk management approach, has been used to successfully manage numerous high-profile projects around the world. DNV is an independent organisation with dedicated risk professionals in more than 100 countries. Our purpose is to safeguard life, property and the environment. DNV serves a range of industries, with a special focus on the maritime and energy sectors. Since 1864, DNV has balanced the needs of business and society based on our independence and integrity. Today, we have a global presence with a network of 300 offices in 100 countries, with headquarters in Oslo, Norway.

    Global impact for a safe and sustainable future:

    Learn more on www.dnv.com