8 vedlegg b
TRANSCRIPT
-
DET NORSKE VERITASTM
REPORT NO./DNV REG NO.: 2013-4091 / 17TLT29-5
REV 1, 11.06.2013
APPENDIX B
HAZID
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 1 of 12
Table of Contents Page
1 BACKGROUND AND SCOPE OF WORK ...................................................................................... 2
2 METHODOLOGY .............................................................................................................................. 4
3 PARTICIPANTS ................................................................................................................................. 6
4 SUMMARY OF HAZARDS IDENTIFIED ....................................................................................... 6
5 HAZID LOG ....................................................................................................................................... 7
6 REFERENCES .................................................................................................................................. 11
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 2 of 11
Conclusion of the review on the 17.05.2013:
After review of the HAZID inputs and conclusion delivered on the 18.05.2012, DNV assessed that no
update is required as the concept design used as basis for the HAZID has not changed in the detail
engineering phase.
1 BACKGROUND AND SCOPE OF WORK
A one day HAZID workshop was carried out in June 2011 for the design at that stage of LNG
bunkering station in Risavika, ref. /1/. As the design has changed considerably since then, an update of
the HAZID was carried out on February 16 2012.
The objective was to identify and assess potential hazards for the LNG bunkering station, with focus
on safety. Risks reducing measures were identified and assessed where possible.
Like the HAZID in 2011, this update focuses only on hazards associated with bunkering of LNG to
ferries on jetty 38. This includes equipment and operations both inside and outside the LNG Base Load
Plant, ref. Figure B - 1 and Figure B - 2, respectively.
For remaining hazards associated with the LNG Base Load Plant, reference is made to the QRA from
2009, ref. /2/.
The HAZID does not take into account the risks due to ship or truck LNG loading to the ferry.
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 3 of 11
Figure B - 1 Equipment associated with the bunkering system located inside the plant
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 4 of 11
Figure B - 2 Route of the underground pipe and bunkering station on jetty 38
2 METHODOLOGY
HAZID (Hazard Identification) is a systematic review of installations and/or operations in order to
screen potential hazards. The HAZID review on February 16 2012 was run in a workshop with
participants from Skangass, Fjordline and DNV. Each hazard was assigned a likelihood and
consequence category, so that each hazard could be ranked in accordance with a predefined risk
matrix, see Table B - 1. This risk matrix is the same as the one used in HAZID in June 2011.
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 5 of 11
Table B - 1 Risk matrix
Severi
ty
Consequence Categories Likelihood
Peo
ple
En
viro
n-
men
t
Del
ay /
Do
wn
tim
e
Rep
uta
tio
n
1 2 3 4 5 6
Failure is not
expected
< 10-5
Never heard of in
Industry
10-4 - 10-5
An incident
has occurred
in Industry
10-3 - 10-4
Has been experienced
by most Operators 10-2 - 10-3
Occurs several times
per year per
Operator 10-1 - 10-
2
Occurs several times
per year per
facility >10-1
1 No or superficial injuries
Slight effect on environment, < 1 BBL
< 2 hours
Slight impact; local public awareness but no public concern
L L L M M M
2
Slight injury, a few lost work days
Minor effect Non-compliance. < 5 BBL
< 1 day
Limited impact; local public concern may include media
L L M M M H
3
Major injury, long term absence
Localized effect Spill response required. < 50 BBL
1 - 10 days
Considerable impact; regional public/slight national media attention
L M M M H H
4
Single fatality or permanent disability
Major Effect Significant spill response, 100 BBL
> 60 days
Extensive negative attention in international media
M M H H H H
Risk Definition:
High Actions must be taken to reduce risk to at least the medium level
Medium
Risk reduction measures must be taken if their respective costs are not disproportionately high as compared to their
attained benefits (ALARP principal); actions need to be taken to manage and measure risk.
Low Monitoring actions required to identify whether the risk rises to medium level
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 6 of 11
3 PARTICIPANTS
Table B - 2 Participants at the HAZID workshop March 16 2012
Name Company Position / role in HAZID
Camilla Gautestad Skangass Process Manager, Gas & LNG projects
Gunnar Helmen Skangass Key Account Manager, LNG Industry & Marine
sbjrn Folvik Skangass Process engineer, LNG Industry & Regulations
Morten Larsen Fjordline Technical & Nautical Director
Erik Skramstad DNV HAZID facilitator
Jon Magne Ofte DNV QRA Project Manager
Jean-Baptiste Berthomieu DNV Scribe
4 SUMMARY OF HAZARDS IDENTIFIED
The new design of Skangass bunkering system is considered an improvement in terms of safety, as it mitigates or eliminates some of the hazards identified in the HAZID from June 2011: The likelihood of
a leak is reduced by introducing underground, double wall pipeline and by eliminating buffer tanks and
flare.
Since the HAZID in 2011, the number of hazards with criticality High is reduced to one:
1-4 Leaks from the loading arm during bunkering operations, caused by fabrication or material defects; weld defects, leaking seals and swivels. Possible consequences are fires if ignition
sources on and around bunkering ferry (under ro-ro operation) are present; risks to ship
passengers.
The main changes include the lower criticality of the following hazards, due to reduction of likelihood
and/or consequence:
Criticality changed from Medium to Low:
o 1-1 Release of N2 and HC from vents on the ship (ship-side)
o 1-2 Inability of purging N2 from the loading arms
o 1-12 Damage to loading arms with possible release of LNG (New: No crane operations during bunkering operations.)
o 3-1 Loss of LNG supply capacity
o 3-2 Damage to piping system inside the LNG plant
Criticality changed from High to Medium:
o 1-10 Loss of control during filling of ship (New: ESD has been provided; the system will fail in a safe position.)
Other changes since the HAZID in 2011 do not move hazards from one criticality level to the next.
All changes are marked with text in red in the HAZID log in the next chapter.
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 7 of 11
5 HAZID LOG
(Text in red has been revised since HAZID June 2011)
ID HAZARD CAUSE POSSIBLE CONSEQUENCES
DETECTION SAFEGUARDS / CONTROL MEASURES
Cat
ego
ry
Co
nse
qu
ence
Lik
elih
oo
d
Cri
tica
lity COMMENTS
1-0 Loading area loading arm from LNG Base Load Pant to ship 1-1 Release of N2 and HC
from vents on the ship (ship-side)
N2 purging of loading arms into the ship's main header vent system
Fire hazard if ignition sources on and around bunkering ferry (under ro-ro operation) are present
Design of cold vent; minimise purging through better control of the process; design of fire fighting system (foam etc.)
1 3 L This could be a problem when simultaneous passenger and cargo "offloading" are being carried out
1-2 Inability of purging N2 from the loading arms
Pollution of fuel in the ship's fuel tank
Control of the purging process
1 2 L
1-3 Release of N2 and HC from the loading arms (shore-side)
Unintended releases during connection and preparation for the LNG transfer
Minor fire with HC release Demonstration to authorities on this (safe?) design
1 3 L Neighbouring pressure relief valves can be connected to this onshore header vent system. With the current procedure, the release is small, then the consequences will be small as well.
1-4 Leaks from the loading arm during bunkering operations
Fabrication or material defects; weld defects; leaking seals and swivels
Gas dispersion Manual detection possible but not reliable (due to surrounding noise pollution during work)
Gas detectors and immediate / automatic shut-down
2 3 M Consider visual indication of closed connections; hydraulic backup system of the loading arms should be considered
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 8 of 11
ID HAZARD CAUSE POSSIBLE CONSEQUENCES
DETECTION SAFEGUARDS / CONTROL MEASURES
Cat
ego
ry
Co
nse
qu
ence
Lik
elih
oo
d
Cri
tica
lity COMMENTS
1-5 Fires if ignition sources on and around bunkering ferry (under ro-ro operation) are present; risks to ship passengers
Visual detection (continuously operated during ship loading)
Immediate / automatic shut-down; elimination of ignition sources in classified areas; fire-fighting
4 4 H Address radiation level and fire effects on personnel and passengers on the open-bridge and open decks during the bunkering; Consider access control to the open-deck and fire protection on the bridge.
1-6 Embrittlement Spill protection (for the steel on the deck)
3 3 M
1-7 Frost burns PPE mandatory 3 3 M
1-8 Unplanned disconnection of the loading arms, with possible damage to equipment and release of LNG
Excessive ship motions due to failure in engine control system on the ship; failure in mooring; passing ships; weather
Refer to consequences in ID 1.04,1.05,1.06,1.07
Manual detection Berthing control of the ship; weak link/quick release coupling will minimise damages to the loading arm
3 3 M Emergency procedures to be addressed in the overall operation procedures as well as during training etc.
1-9 Overfilling of fuel tank (ship)
Control failure (instrument; operational etc.)
Release of LNG through tank relief valves, and NG through pressure relief valves. Refer to consequences in ID 1.04,1.05,1.06,1.07
Level alarm controls
Operational procedures and tank protection system (level indicators)
4 3 M This is linked to the ship design, it will be designed according to the IMO guidelines (ESD link will be provided)
1-10 Loss of control during filling of ship
Loss of power Abortion of the filling process in an unsafe state
Loss of power / black-out should be easily detected
This has to be addressed in the ESD philosophy (including the back-up of power supply)
2 3 M ESD has been provided; the system will fail in a safe position.
1-11 Damage to loading arms with possible release of LNG
Impacts from trucks and crane arms
Fire hazards (trucks acting as potential ignition sources). Injuries to facility operators and ferry
Manual detection Concrete or other protective barriers and traffic rules (speed limits etc.); no traffic during bunkering operation
4 1 M
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 9 of 11
ID HAZARD CAUSE POSSIBLE CONSEQUENCES
DETECTION SAFEGUARDS / CONTROL MEASURES
Cat
ego
ry
Co
nse
qu
ence
Lik
elih
oo
d
Cri
tica
lity COMMENTS
1-12 Dropped objects on loading arms from cranes loading the ship
passengers. Refer also to consequences in ID 1.04,1.05,1.06,1.07
Manual detection No crane operations during bunkering operations
3 1 L Crane activities should be carried out at a safe distance from loading manifold (or vice versa)
1-13 Ship collision / impact from other passing vessels
Human error and / or technical failures, leading to loss of navigational control
Structural damage to the ship. Possible damage to the loading arms cannot be disregarded.
Manual detection Port traffic controls 3 2 M Harbour traffic control (especially due to the increased sea traffic opposite to LNG bunkering facility) - Refer to DNV Risk Analysis on Risavika Harbour
1-14 Damage to loading arms when disconnected
Truck traffic; dropped containers; collision impact from other vessels
Material damage to the (normal stainless steel) arm and possible release of LNG (before LNG has evaporated)
Visual observation / inspection
Shut-down valves at both the ship-side and onshore tank-side of the filling line; consider possibility to empty loading arm after disconnection
2 3 M Low probability (and minimal spillage of LNG); Loading arm will contain LNG shortly after loading; safety zone around the loading arm; access is restricted to limited (trained) personnel; protection equipment by personnel present at that area
1-15 Unplanned abortion of fuelling operation
External fire (on ship, building and truck)
Damage to equipment (including escalation); delay
Visual observation Fire detection and fire-fighting; ESD and emergency plans
3 3 M To be addressed as part of the ESD procedures
1-16 Sabotage and terrorist attacks
Covered as part of meeting the international regulation requirements (ISPS)
1-17 Failure of the vacuum-insulated transfer line
Material fabrication defects Shut down and need for repairs
Loss of vacuum (detected in the control room)
Design of culvert, pipe support and draining system of the culvert, ventilation system if culvert is closed
3 3 M
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 10 of 11
ID HAZARD CAUSE POSSIBLE CONSEQUENCES
DETECTION SAFEGUARDS / CONTROL MEASURES
Cat
ego
ry
Co
nse
qu
ence
Lik
elih
oo
d
Cri
tica
lity COMMENTS
1-18 LNG releases in the culvert
Double barriers failure; digging activities; flooding; Fatigue; improper installation; excessive loads of traffic activities; vibrations; settlement.
Fire and explosion Gas detectors (if flanges are present inside the culvert); otherwise vacuum detectors / monitoring should be adequate
Minimise valves / flange connections inside the culvert
4 1 M Valves / flange connections should preferably be outside the culvert
2.0 LNG Buffer Tank(s) (top and bottom filling inlets) & its filling lines No longer part of the design
3-0 Main LNG plant - 42-TR-101 tank & truck loading bay
3-1 Loss of LNG supply capacity
Loss of fuelling capacity, i.e. breakdown of facility's reliability
Visual Revise the operational manual so as to consider the reliability of the truck and Buffer tank(s) filling
1 3 L
3-2 Damage to piping system inside the LNG plant
Release of LNG in Truck Loading Bay; fire and explosion (due to ignition sources from the trucks)
Process control and gas detectors at the Truck Loading Bay
Ensure that piping system is designed for situation with back-flow in the system
1 3 L Vapour return line to be considered?
3-3 Failure of liquid lines from pump 42-PS-101B
Increased frequency of use The increased use of this pump should be reflected in the QRA
-
DET NORSKE VERITAS
Report for Skangass AS
Appendix B HAZID
MANAGING RISK
DNV Reg. No.: 17TLT29-5
Revision No.: 1
Date : 11.06.2013 Page 11 of 11
6 REFERENCES
/1/ Risikovurdering av LNG bunkring av RoPax ferje i Risavika havn, DNV reg. no. 12PABXZ-
21, 26.08.2011
/2/ QRA for Skangass LNG plant, DNV report no. 2009-0068, rev 1, 08.05.2009
-
Det Norske Veritas:
DNV is a global provider of knowledge for managing risk. Today, safe and responsible business conduct is both a license to operate and a competitive advantage. Our core competence is to identify, assess, and advise on risk management, and so turn risks into rewards for our customers. From our leading position in certification, classification, verification, and training, we develop and apply standards and best practices. This helps our customers to safely and responsibly improve their business performance. Our technology expertise, industry knowledge, and risk management approach, has been used to successfully manage numerous high-profile projects around the world. DNV is an independent organisation with dedicated risk professionals in more than 100 countries. Our purpose is to safeguard life, property and the environment. DNV serves a range of industries, with a special focus on the maritime and energy sectors. Since 1864, DNV has balanced the needs of business and society based on our independence and integrity. Today, we have a global presence with a network of 300 offices in 100 countries, with headquarters in Oslo, Norway.
Global impact for a safe and sustainable future:
Learn more on www.dnv.com