Eskom Holdings, Inc. - Project Kusile
146838.70.0501
Vendor Document Submittal Schedule
Event Due Date
01100 Technical Scope and System Performance .
0001 01100 Preliminary Spare Parts List 150 After Commencement Date
0002 01100 Final Spare Parts List With Installation Manual05500 Miscellaneous Metals .
0003 05500 Structural Steel Material Certification Upon request
0004 05500 High Strength Bolts Material Certification Upon request
0005 05500 Structural Steel Fabrication and Erection Drawings 30 After Receipt of IFC
Drawings0006 05500 Grating Fabrication and Erection Drawings 45 After Receipt of IFC
Drawin s11700 Safety Showers and Eye Wash Stations
0007 11700 Certified drawings of combination safety shower/eye wash
equipment.
90 After Commencement Date
0008 11700 Wiring and schematic diagrams showing all external
power/control/instrumentation connections, indicating who furnishes
cable, who installs cable, and who terminates each cable. Wiring
installed b others to beshown as dashed line.
90 After Commencement Date
13203 Field Erected Bolted Tanks .
0009 13203 Pressure and leak test reports 15 After Test
0010 13203 As-built drawings Upon completion of
erection0011 13203 Site safety manual 20 Before Site Mobilization
Shop Fabricated Tanks .
0012 Pressure and leak test reports 15 After Test
0013 Final As-Buil t Drawings and Documentat ion (Only i f d ifferent from
design drawings)
30 After Final Acceptance
15061 Pipe Supports Designed by Employer .
0014 15061 Shop drawing submittal 21 After Receipt of hanger
list(s)0015 15061 Revised shop drawing submittals 14 After Receipt of reviewed
drawings0016 15061 Coating system information as specified herein for all coatings 60 After Commencement Date
0017 15061 Final As-Built Drawings and Documentation (Only if different from
previously submitted drawings)
30 After Final Acceptance
15062 Pipe Supports Designed by Contractor .
0018 15062 Shop drawing submittal 28 After Receipt of hanger list (if
applicable)0019 15062 Support design data, including equipment loads broken out by load
case (dead, operating, etc), anchor bolt sizes and locations, and
e ui mentbases izes
28 After Receipt of hanger list (if
applicable)
Calendar Days
Schedule of Submittals
WWTP Construction
Item No.Reference
DocumentSubmittal Item
Submittal Dates
i i .15221 Fabricated Steel Pipe .
0020 15221 Copies of Certified Test and Inspection Reports including material testreports
7 After Test/Inspection
0021 15221 Factory Acceptance Test Procedure Including Acceptance Criteria 90 Before Test
0022 15221 Reader sheets of radiographs of weld buildups for satisfactory fit-up in
circumferential butt welds in rolled and welded plate pipe to permit
complete analysis of the joint after field radiography
7 After Completion of Weld
0023 15221 Manufacturer's data for piping material and piping accessories 30 After Receipt of "Released
For Fabrication" Piping
Isometrics0024 15221 Calculations and descriptive information documenting compliance
with area replacement requirements for branch welds
30 After Receipt of "Released
For Fabrication" Piping
Isometrics0025 15221 Documentation that integrally reinforced forged branch outlet fittings
have been designed in accordance with the applicable code
30 After Receipt of "Released
For Fabrication" Piping
Isometrics0026 15221 Testing and inspection procedures for base metals including the
extent of each examination, stage of manufacture at time of
examination, detailed nondestructive testing procedures, and
acce tance criteria/reection standards
30 After Receipt of "Released
For Fabrication" Piping
Isometrics
0027 15221 Bending equipment and procedures used for all pipe bends, including
calculations to document compliance with Code required minimum
wall thickness resulting from bending and post bending heat
treatment rocedures
30 After Receipt of "Released
For Fabrication" Piping
Isometrics
0028 15221 Bending results documentation showing records of actual wall
thicknesses
15 After Completion of Bend
0029 15221 Erection lug sizing calculations in accordance with the applicable
codes.
30 After Receipt of "Released
For Fabrication" Piping
Isometrics0030 15221 Pipe fabrication spool sheet drawings 14 After Receipt of "Released
For Fabrication" Piping
Isometrics0031 15221 Special piping details including butt weld end preparations, special
connections such as performance test connections, and other details
14 After Receipt of "Released
For Fabrication" Piping
Isometrics
Page 1 of 4
7/21/2019 8 -- Vendor Doc Submittal Schedule
http://slidepdf.com/reader/full/8-vendor-doc-submittal-schedule 2/4
VENDOR
DOCUMENT
SUBMITTAL
SCHEDULE
Event Due DateCalendar DaysItem No.
Reference
DocumentSubmittal Item
Submittal Dates
0032 15221 Descriptive information on spectacle flanges and special fittings 30 After Receipt of "Released
For Fabrication" Piping
Isometrics0033 15221 Final As-Built Drawings and Documentation (Only if different from
previously submitted drawings)
30 After Final Acceptance
0034 15221 Coating and surface preparation specification 60 After Commencement Date
0035 15221 Hydrostatic Testing Procedure 60 After Commencement Date
0036 15221 Pipe root side purging procedure 60 After Commencement Date
0037 15221 Description of abrasive blast cleaning process including manufacturerand trade name of blast media and detailed procedure along with an
ultimate anal sis of blastin media.
30 Before Blasting
15225 General Service Pipe .
0038 15225 Details of pipe fittings, attachments, joints, and specials, including
dimensions and weights
30 After Commencement Date
0039 15225 Details of closure sections where indicated on the drawings 30 After Commencement Date
0040 15225 Provisions for piping attachment (if furnished by Supplier) or
recommendations for Employer-furnished system
30 After Commencement Date
0041 15225 Final As-Built Drawings and Documentation (Only if different from
previously submitted drawings)
30 After Final Acceptance
0042 15225 Coating and surface preparation specification 60 After Commencement Date
15243 Piping Expansion Joints - Rubber .
0043 15243 Certified drawings showing dimensions, weights, and materials of
construction
60 After Issue of Release for
Purchase Mechanical
Device List0044 15243 Calculations documenting the size and quantity of control units N/A N/A N/A
15245 Flexible Hoses .
0045 15245 Certified drawings showing dimensions, weights, and materials of
construction
60 After Issue of Release for
Purchase Mechanical
Device List15251 Strainers and Filters .
0046 15251 Certified drawings indicating type, size, mesh/filter size, arrangement,
weights of each component, and breakdown for shipment
60 After Issue of Release for
Purchase Mechanical
Device List15253 Tr ap s .
0047 15253 Certified drawings indicating type, size, arrangement, weights of each
component, and breakdown for shipment
60 After Issue of Release for
Purchase Mechanical
Device List15262 Misc Valves .
0048 15262 Drawings showing overall dimensions and valve tag numbers, weld
end details, direction of flow, manufacture specification and sizing
sheets, and weights of valves, actuators, and all accessories
60 After Issue of Release for
Purchase Valve List
0049 15262 Cv curves showing percent open versus Cv 90 After Issue of Release for
Purchase Valve List0050 15262 Final As-Built Drawings and Documentation (Only if different from
reviousl submitted drawin s
30 After Final Acceptance
0051 15262 Coating and surface preparation specification 90 After Issue of Release for
Purchase Valve List0052 15262 Typical data for locking devices 90 After Issue of Release for
Purchase Valve List0053 15262 Typical standard drawing for each valve type, size, pressure class,
and material
60 After Issue of Release for
Purchase Valve List0054 15262 Hydrostatic shell and seat leakage test reports for tests required by
a licable standards and tests re uired herein
5 After Test
0055 15262 Records of hydrostatic shell and seat leakage tests and radiographic
tests, if re uired
14 After Tests
15264 Miscellaneous Valves .
0056 15264 Typical standard drawing for each valve type, size, pressure class,
material, and accessories
60 After Issue of Release for
Purchase Valve List0057 15264 Typical data for locking devices and other special features 90 After Issue of Release for
Purchase Valve List0058 15264 Hydrostatic shell and seat leakage test reports for tests required by
applicable standards and tests required herein
7 After Test
0059 15264 Installation instructions 30 Before Delivery
15265 Rubber Seated Butterfly Valves .
0060 15265 Certified Material Test Report (CMTR) indicating aluminum content
not exceeding 0.08 percent, or documentation demonstrating
compliance with ASTM A703 S23 requirements, for each castingfurnished as a pressure-retaining component and with a design
tem era
Upon Shipment of Equipment
0061 15265 Documentation of body casting repairs, including postweld heat
treatment records and re-examination records
Upon Shipment of Equipment
0062 15265 Radiograph reports in accordance with applicable standards Upon Shipment of Equipment
0063 15265 Shell pressure test and seat leakage test reports (for tests required by
applicable standards)
7 After Test
0064 15265 Pressure Class Ratings for all Valves in accordance with applicable
standards
30 After Issue of Release for
Purchase Valve List0065 15265 Dimensional drawings including overall dimensions and valve tag
numbers
60 After Issue of Release for
Purchase Valve List
Page 2 of 4
7/21/2019 8 -- Vendor Doc Submittal Schedule
http://slidepdf.com/reader/full/8-vendor-doc-submittal-schedule 3/4
VENDOR
DOCUMENT
SUBMITTAL
SCHEDULE
Event Due DateCalendar DaysItem No.
Reference
DocumentSubmittal Item
Submittal Dates
0066 15265 Valve and accessory outline with overall dimensions and valve tag
numbers, weights (including operators and accessories), direction of
flow, orientation of disks and shafts, direction of rotation, location of
o erator and o erator removal clearances
60 After Issue of Release for
Purchase Valve List
0067 15265 Final As-Built Drawings and Documentation (Only if different from
previously submitted drawings)
30 After Final Acceptance
0068 15265 Coating and surface preparation specification 90 After Issue of Release for
Purchase Valve List
0069 15265 Factory Valve and Accessory Outline Drawings With all AccessoryEquipment Shown. Drawings should include overall dimensions and
valve tag numbers, operator removal clearance, end-to-end
dimensions, and direction of flow.
With Instruction Manual
0070 15265 Sectional drawing showing materials and internal construction With Instruction Manual
0071 Final As-Buil t Drawings and Documentation (Only if di fferent from
previously submitted drawings)
30 After Final Acceptance
0072 Coating and surface preparation specification 90 After Issue of Release for
Purchase Control Valve
Data Sheets15271 Safety and Relief Valves .
0073 Final As-Buil t Drawings and Documentation (Only if di fferent from
previously submitted drawings)
30 After Final Acceptance
15901 Mechanical Equipment Erection .
0074 15901 Drawings showing how cranes will be utilized in construction including
location, swing radius, and estimated timing of use
90 After Commencement Date
0075 15901 Erection Schedule 90 After Commencement Date
and then Updated
Monthl15921 Piping Erect ion .
0076 15921 Erection procedure. 45 Before Erection of the system
0077 15921 Routing drawings for Contractor routed piping 15 Before Erection of the piping
covered by the drawing
15941 Insulation and Lagging .
0078 15941 Drawings detailing types and thicknesses of insulation for pipelines,
auxiliary equipment items, and flatwork areas
30 After Commencement Date
0079 15941 Installation details for insulation and lagging supports for each
flatwork area or equipment
30 After Commencement Date
0080 15941 Installation details including fastening of insulation and lagging to
supports, flashing methods, convection barriers, lagging closures,
and rovisions for ex ansion and contraction
30 After Commencement Date
0081 15941 Fabrication details for field fabricated pipe elbow jacketing, and
access door and manhole insulated covers
15 After Commencement Date
0082 15941 Storage and handling requirements for insulation and lagging
materials to be erected by others
30 Before Delivery of Materials
17320 Sight Flow Indicators .
i i i i i i i i li i i i i i , i , , i
component, connection size/type/material, and breakdown for
shipment
l
Purchase Mechanical
Device List17372 Orif ice Plates .
0084 17372 Orifice plate detail drawing including dimensions 60 After Issue of Release for
Purchase Mechanical
Device List18110 Mechanical Startup .
0085 18110 Verification in writing that all work and checkouts have been
completed, including verification by equipment manufacturers' field
service re resentatives, when a licable
Before Trial operation of
equipment
0086 18110 Trial operation summary as defined in Article 18110.3.2 Before Main systems checkout
Q002 General Quality System Requirements .
0087 Q002 Quality Manual, controlled copy 30 After Commencement Date
0088 Q002 Certification Letter or Certificate of Authorization (copy), if certified by
a registered agency, e.g., ASME Certificate of Authorization, ISO
Certificate
30 After Commencement Date
0089 Q002 Subsupplier listing 5 Before Issue of Subsupplier
Purchase Order 0090 Q002 Inspection and test plan 30 After Commencement Date
0091 Q002 Notification of inspection/test (for hold/witness points) 14 Before Test/Inspection
Q100 General Welding Requirements .0092 Q100 Welding Procedure Specifications (WPS) with applicable Procedure
Qualification Records (PQR)
30 Before Start of Fabrication
0093 Q100 Procedures for storing, issuing, and reconditioning of electrodes,
wires, and fluxes
30 Before Start of Fabrication
0094 Q100 Repair procedures associated with a nonconformance report 5 After Discovery of Repair
0095 Q100 Post-weld heat treatment procedures 30 Before Start of Fabrication
0096 Q100 Visual inspectors' qualifications and certificates 30 Before Start of Fabrication
0097 Q100 Nondestructive examination procedures 30 Before Start of Fabrication
0098 Q100 Root side purging procedures 30 Before Start of Fabrication
0099 Q100 Nonconformance reports 5 After Discovery of Nonconf.
0100 Q100 ASME Data Reports or equivalent 30 After Fabrication Completion
Page 3 of 4
7/21/2019 8 -- Vendor Doc Submittal Schedule
http://slidepdf.com/reader/full/8-vendor-doc-submittal-schedule 4/4
VENDOR
DOCUMENT
SUBMITTAL
SCHEDULE
Event Due DateCalendar DaysItem No.
Reference
DocumentSubmittal Item
Submittal Dates
0101 Q100 Radiographs 14 After Fabrication Completion
0102 Q100 Final Data Report 30 After Fabrication Completion
Q500 Shop Drawings and Instruction Manuals .
0103 Q500 Instruction Manuals - Draft Version 180 After Issue of Release for
Purchase Instrument
List and/or Mechanical
Device List
0104 Q500 Instruction Manuals - Final Manuals 30 Before Initial Operation
Page 4 of 4