9. just in time

Upload: apeksha-gupta

Post on 07-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/4/2019 9. Just in Time

    1/28

    The McGraw-Hill Companies, Inc.,

    1

    Chapter 11

    Just-in-Time and

    Lean Systems

    LEANPRODUCTION

  • 8/4/2019 9. Just in Time

    2/28

    The McGraw-Hill Companies, Inc.,

    2

    Leanproduction

    can be defined as an integratedset of activities designed toachieve high-volume productionusing minimal inventories of rawmaterials, work in process, andfinished goods.

    It also involves the elimination ofwaste in production effort

    Lean is also based on the logic

    that nothing will be produced

  • 8/4/2019 9. Just in Time

    3/28

    The McGraw-Hill Companies, Inc.,

    3

    FEATURES OF LEANPRODUCTION

    WHAT IT IS?Management philosophyPull System through the plant

    WHAT IT DOES?Attacks waste (time, inventory, scrap)Exposes problems and bottlenecksAchieves streamlined production

    WHAT IT REQUIRES?Employee participationIndustrial Engineering

    Total Quality ControlSmall Lot SizesContinuous Improvement

    WHAT IT ASSUMES?Stable environment

  • 8/4/2019 9. Just in Time

    4/28

    The McGraw-Hill Companies, Inc.,

    4

    JIT and Lean Management

    JIT can be divided into two terms:Big JIT and Little JIT

    Big JIT (also called Lean Management)

    is a philosophy of operationsmanagement that seeks to eliminatewaste in all aspects of a firmsproduction activities: human

    relations, vendor relations, and themanagement of materials andinventory

    Little JIT focuses more narrowly onscheduling goods inventory and

  • 8/4/2019 9. Just in Time

    5/28

    The McGraw-Hill Companies, Inc.,

    5

    Pull Logic

    Customers

    Sub

    Sub

    Fab

    Fab

    Fab

    Fab

    Vendor

    Vendor

    Vendor

    Vendor

    Final

    Assembly

    Here the customer starts

    the process, pulling an

    inventory item from Final

    Assembly

    Here the customer starts

    the process, pulling an

    inventory item from Final

    Assembly

    Then sub-assembly

    work is pulled

    forward by that

    demand

    Then sub-assembly

    work is pulled

    forward by that

    demand

    The process continues

    throughout the entire

    production process

    The process continues

    throughout the entire

    production process

  • 8/4/2019 9. Just in Time

    6/28

    The McGraw-Hill Companies, Inc.,

    6

    Waste in Operations

    1. Waste from overproduction

    2. Waste of waiting time

    3. Transportation waste4. Inventory waste

    5. Processing waste

    6. Waste of motion

    7. Waste from product defects

  • 8/4/2019 9. Just in Time

    7/28

    The McGraw-Hill Companies, Inc.,

    7eliminationof waste

    1. Focused factory Networks

    2. Group Technology

    3. Quality at source

    4. Uniform Plant loading (Heijunka)

    5. JIT production

    6. Kanban Production control

    7. Minimized set up times

    N t k

  • 8/4/2019 9. Just in Time

    8/28

    The McGraw-Hill Companies, Inc.,

    8Networks:Plant designed for onepurpose can be constructedand operated moreeconomically

    CoordinationSystem

    Integration

    These are smallspecialized plantsthat limit the rangeof products produced(sometimes only onetype of product for anentire facility).

    These are smallspecialized plantsthat limit the range

    of products produced(sometimes only onetype of product for anentire facility).

    Some plantsin Japanhave as fewas 30 andas many as1000employees

    Some plantsin Japanhave as fewas 30 and

    as many as1000employees

    Mi i i i W t G T h l (P t

  • 8/4/2019 9. Just in Time

    9/28

    The McGraw-Hill Companies, Inc.,

    9Minimizing Waste: Group Technology (Part1)

    Using Departmental Specialization for plant layout can cause

    a lot of unnecessary material movement

    Using Departmental Specialization for plant layout can cause

    a lot of unnecessary material movement

    Saw Saw

    Lathe PressPress

    Grinder

    LatheLathe

    Saw

    Press

    Heat Treat

    Grinder

    Note how the flow lines are going back and forthNote how the flow lines are going back and forth

  • 8/4/2019 9. Just in Time

    10/28

    The McGraw-Hill Companies, Inc.,

    10

    Minimizing Waste:Group Technology (Part 2) Revising by using Group Technology Cells can reduce

    movement and improve product flow

    Revising by using Group Technology Cells can reducemovement and improve product flow

    Press

    Lathe

    Grinder

    Grinder

    A

    2

    BSaw

    Heat Treat

    LatheSaw Lathe

    PressLathe

    1

  • 8/4/2019 9. Just in Time

    11/28

    The McGraw-Hill Companies, Inc.,

    11

    Suppose we operate a production plant thatproduces a single product. The schedule ofproduction for this product could be

    accomplished using either of the two plantloading schedules below.

    Heijunka is the levelling of production byboth volume and product mix. This system

    does not build products according to theactual flow of customerorders. Heijunka takes the total volume oforders in a period and levels them out so the

    same amount and mix are being made each

    Suppose we operate a production plant thatproduces a single product. The schedule ofproduction for this product could be

    accomplished using either of the two plantloading schedules below.

    Heijunka is the levelling of production byboth volume and product mix. This system

    does not build products according to theactual flow of customerorders. Heijunka takes the total volume oforders in a period and levels them out so the

    same amount and mix are being made each

    Uniform Plant Loading(heijunka)

  • 8/4/2019 9. Just in Time

    12/28

    The McGraw-Hill Companies, Inc.,

    12

    Monday Production

    Tuesday Production

    Wednesday Production

    Chan eover

    UNLEVELEDPRODUCTION

    13

  • 8/4/2019 9. Just in Time

    13/28

    The McGraw-Hill Companies, Inc.,

    13

    UNLEVELEDPRODUCTION

    Figure 1 gives an example of traditionalunlevelled production, for Company X thatmanufactures tractors. The line makes small,medium, and large tractors. The medium are thebig sellers and are made early in the week,

    Monday through part of Wednesday. There is achangeover and the small tractors are madeWednesday through Friday morning. Afteranother changeover the largest tractors, which arein smallest demand, are made Friday afternoon.

    This typical unlevelled method creates fourproblems:

    Customers usually do not buy productspredictably. If the customer decides to buy the

    large tractors early in the week the plant is introuble.

    14

  • 8/4/2019 9. Just in Time

    14/28

    The McGraw-Hill Companies, Inc.,

    14

    LEVELED PRODUCTION

    Figure 2 represents an example of mixedmodel levelled production. By reducing thechangeover time and employing other Leanmethods, the plant is able to build thetractors in any order they want to on theirmixed model assembly line. The four benefitsof levelling the schedule is:

    Flexibility to make what the customer wantswhen they want it.

    Reduced risk of unsold goods.

    Balanced use of labour and machines.

    Smoothed demand on the upstream

    15

  • 8/4/2019 9. Just in Time

    15/28

    The McGraw-Hill Companies, Inc.,

    15Monday Production

    Tuesday Production

    Wednesday Production

    16

  • 8/4/2019 9. Just in Time

    16/28

    The McGraw-Hill Companies, Inc.,

    16

    Quality at source

    Quality at the source means do it right thefirst time and when something goes wrong,stop the process or assembly line

    immediately. Factory workers becometheir own inspectors, personallyresponsible for the quality of their output.

    17

  • 8/4/2019 9. Just in Time

    17/28

    The McGraw-Hill Companies, Inc.,

    17

    Minimizing Waste: Just-In-TimeProduction

    Management philosophy Pull system though the plant

    Hydraulic Push Systems

    WHAT IT IS

    Employee participation Continuing improvement

    Small lot sizes

    WHAT IT REQUIRES

    Attacks waste

    WHAT IT DOES

    Stable environment

    WHAT IT ASSUMES

    18

  • 8/4/2019 9. Just in Time

    18/28

    The McGraw-Hill Companies, Inc.,

    18

    Inventory Hides Problems Justas Water in a Lake Hides Rocks

    Scrap

    Setuptime

    Latedeliverie

    s

    Qualityproble

    ms

    Process

    downtime

    Scrap

    Setuptime

    Latedeliverie

    s

    Qualityproble

    ms

    Process

    downtime

    Inventorylevel

    Inventorylevel

    19

  • 8/4/2019 9. Just in Time

    19/28

    The McGraw-Hill Companies, Inc.,

    19

    Scrap

    Work in process inventory level(hides problems)

    UnreliableVendors

    CapacityImbalances

    Lowering InventoryReduces Waste

    20

  • 8/4/2019 9. Just in Time

    20/28

    The McGraw-Hill Companies, Inc.,

    20

    Scrap

    Reducing inventory revealsproblems so they can be solved.

    UnreliableVendors

    CapacityImbalances

    WIP

    Lowering InventoryReduces Waste

    21

  • 8/4/2019 9. Just in Time

    21/28

    The McGraw-Hill Companies, Inc.,

    21

    Scrap

    Reducing inventory revealsproblems so they can be solved.

    UnreliableVendors

    CapacityImbalances

    WIP

    Lowering InventoryReduces Waste

    22

    T L I

  • 8/4/2019 9. Just in Time

    22/28

    The McGraw-Hill Companies, Inc.,

    22

    To Lower Inventory,Reduce Lot Sizes

    Time

    Inventory Level

    Lot Size200

    Lot Size80

    Average

    inventory =100

    Averageinventory =

    40

    Average inventory = (Lotsize)/2

    23e uc ng o zes

  • 8/4/2019 9. Just in Time

    23/28

    The McGraw-Hill Companies, Inc.,

    23

    Customerorders 10

    Lot size = 5

    Lot 1 Lot 2

    Lot size = 2

    Lot 1 Lot 2 Lot 3 Lot 4 Lot 5

    e uc ng o zesIncreases the Number ofLots

    24

    Whi h I

  • 8/4/2019 9. Just in Time

    24/28

    The McGraw-Hill Companies, Inc.,

    24

    Which IncreasesInventory Costs

    Lot Size

    Cost

    Holdin

    gCost

    TotalC

    ost

    Setup Cost

    OptimalLot Size

    SmallerLot Size

    25

    U l S t C t

  • 8/4/2019 9. Just in Time

    25/28

    The McGraw-Hill Companies, Inc.,

    25

    Unless Setup Costsare Reduced

    Lot Size

    Cost

    Holdin

    gCostTot

    alCost

    Setup Cost

    Originaloptimallot size

    Newoptimallot size

    26Lower Total Cost Requires

  • 8/4/2019 9. Just in Time

    26/28

    The McGraw-Hill Companies, Inc.,

    26Lower Total Cost RequiresSmall Lot Sizes and LowerSetup Costs

    Lotsize

    Sum of

    orderingand holdingcost

    T1

    T2

    S2

    S1

    Cost

    27

  • 8/4/2019 9. Just in Time

    27/28

    The McGraw-Hill Companies, Inc.,

    Minimizing Waste: KanbanProduction Control Systems

    Storage PartA

    Storage PartA

    MachineCenter

    AssemblyLine

    Material Flow

    Card (signal)Flow

    Withdrawalkanban

    Once the Production kanban isreceived, the Machine Center

    produces a unit to replace the

    one taken by the Assembly Line

    people in the first place

    This puts thesystem back

    were it was

    before the item

    was pulled

    The process begins by the Assembly Line

    people pulling Part A from Storage

    Productionkanban

    28

  • 8/4/2019 9. Just in Time

    28/28

    Respect for People

    Level payrolls

    Cooperative employee unions

    Reliable Subcontractor networks