9 landscape & visual impact 9.1 introduction · landscape impact assessment (lia) as stated...
TRANSCRIPT
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-1
9 LANDSCAPE & VISUAL IMPACT
9.1 Introduction
9.1.1.1 This chapter presents the potential landscape and visual impacts due to the construction
and operation of Trunk Road T2 (hereinafter referred to as “the Project”) in accordance
with the Environmental Impact Assessment Ordinance (EIAO). The focus of the
Landscape Impact Assessment (LIA) as stated within the April 2009 EIA Study Brief
ESB-203/2009 shall include areas within 100 metres from the boundary of the project
and proposed off-site work sites. The focus of the Visual Impact Assessment (VIA) is
defined by the three visual envelopes of the project.
9.1.1.2 Since the 31 July 2009 date for commencement, the original proposals and locations for
the project, and the location of the Trunk Road T2 Eastern Ventilation Building have
been relocated to the Lam Tin Interchange. The Trunk Road T2 Eastern Ventilation
Building is outside the scope of this study and has been addressed by a separate
consultancy. For information regarding the Trunk Road T2 Eastern Ventilation
Building within Lam Tin Interchange, please refer to Section 9 Appendix A for the
relevant extracted text and supporting figures from AECOM’s October 2012,
Agreement No. CE 42/2008 Tseung Kwan O - Lam Tin Tunnel and Associated Works
– Investigation Report (TKO-LTT), which includes an in-depth section within their
LVIA and supporting photomontages for the Trunk Road T2 Eastern Ventilation
Building, located within the Lam Tin Interchange. Please note the TKO-LTT EIA is
awaiting approval.
9.1.1.3 Trunk Road T2 and associated buildings will be commissioned by the end of 2020 in
coordination with both the CKR and TKO-LTT Route 6 projects. According to the
approved March 2009 KTD EIA Report and the KTD Recommended Outline
Development Plan, the Kai Tak development is proposed to be commissioned by the
end of 2020.
9.1.1.4 This LVIA will focus on both the Cha Kwo Ling Eastern Works Area and the KTD
South Apron Western Works Area in the construction phase and the Trunk Road T2
Western Ventilation and Tunnel Portal Buildings in the operation phase. All future
developments planned within the Kai Tak Development (or any planned developments
as appropriate) do not form part of the Project and are not intended for approval under
this EIA Submission but are discussed in the section on Cumulative Landscape &
Visual Impacts.
9.1.1.5 The scale of the Project will inevitably cause landscape and visual impacts, on both
existing and future landscape resources and characteristics as well as visually sensitive
receivers (VSRs). Key issues on landscape and visual impacts during construction and
operation stages are identified and assessed. The scale and extent of the Project site is
likely to alter the visual context of some VSRs in Kowloon Bay, Kowloon City and
Kwun Tong.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-2
9.1.1.6 Given that all underground activities and facilities will unlikely cause landscape and
visual impacts, this report assesses potential landscape and visual impacts associated
with surface construction activities, excavation, storage and above-ground structures
(Tunnel Portal Building & Ventilation Building).
9.1.1.7 The LVIA follows the criteria and guidelines in Annexes 10 and 18 of the EIAO TM.
Photographs showing baseline conditions, and photomontages and illustrative materials
supporting conclusions are provided and the locations of key viewpoints are mapped.
Photomontages provide comparisons between existing views, proposals on day 1 after
completion without mitigation measures, on day 1 after completion with mitigation
measures, and in year 10 after completion with mitigation measures in accordance with
EIAO Guidance Note No. 8/2010.
9.2 Environmental Legislation, Standards and Guidelines
9.2.1.1 The following legislation, standards and guidelines are applicable to landscape and
visual impact assessment associated with the construction and operation of the Project:
EIAO (Cap.499.S.16) and the TM on EIA Process, particularly Annexes 10 and
18;
EIAO Guidance Note 8/2010;
Protection of Endangered Species of Animals And Plants Ordinance (Cap 586);
Town Planning Ordinance (Cap 131);
Protection of the Harbour Ordinance (Cap 531);
Hong Kong Planning Standards and Guidelines (HKPSG);
Study on Landscape Value Mapping of Hong Kong;
Land Administration Office Instruction (LAOI) Section D-12 - Tree Preservation;
WBTC No. 25/92 - Allocation of Space for Urban Street Trees;
WBTC No. 7/2002 - Tree Planting in Public Works;
ETWB TC(W) No. 13/2003 - Guidelines and Procedures for Environmental
Impact Assessment of Government Projects and Proposals;
ETWB TC(W) No. 13/2003A - Guidelines and Procedures for Environmental
Impact Assessment of Government Projects and Proposals; Planning for
Provision of Noise Barriers;
ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape
Features;
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-3
ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees (OVTs), and
Guidelines for their Preservation;
ETWB TCW No. 8/2005 - Aesthetics Design of Ancillary Buildings in
Engineering Projects;
ETWB No. 36/2004 - Advisory Committee on the Appearance of Bridges and
Associated Structures (ACABAS);
ETWB TCW No. 3/2006 - Tree Preservation;
DEVB TCW No. 2/2012 - Allocation of Space for Quality Greening on Roads;
DEVB TCW No. 2/2013 - Greening on Footbridges And Flyovers;
DEVB TCW No. 3/2012- Site Coverage of Greenery for Government Building
Projects
Highways Department - Structures Design Guidelines for Highways & Railways,
Third Edition. Section 17.
9.2.1.2 As requested in the EIA Study Brief, relevant Outline Development Plans, Outline
Zoning Plans, Layout Plans, Recommended Outline Development Plan for the Kai Tak
Development, other planning briefs and studies, guidelines and reports on landscape
strategies and landscape/urban frameworks will be reviewed to understand the future
outlook of the area affected and to assess whether the project is compatible with its
surroundings.
9.2.1.3 The following Statutory and Administrative Plans are relevant to this Study:
Draft Ngau Tau Kok and Kowloon Bay Outline Zoning Plan No. S/K13/27
gazetted on 14/10/2011;
Approved Kwun Tong (South) Outline Zoning Plan No. S/K14S/18 gazetted on
14/6/2013;
Approved Cha Kwo Ling, Yau Tong, Lei Yue Mun Outline Zoning Plan No.
S/K15/19 gazetted on 17/06/2011;
Approved Kai Tak Outline Zoning Plan No. S/K22/4 gazetted on 14/09/2012; and
Recommended Outline Development Plan (RODP) for Kai Tak Development.
9.2.1.4 The following approved EIA Reports are referred to in this Study:
Kai Tak Airport North Apron Decommissioning EIA Report (EIAO Register No.
AEIAR- 002/1998);
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-4
Comprehensive Feasibility Study for the Refined Scheme of South East Kowloon
Development (EIAO Register No. AEIAR-044/2001);
Further Development of Tseung Kwun O Feasibility Study (EIAO Register No.
AEIAR-092/2005);
Dredging Works for Proposed Cruise Terminal at Kai Tak (EIAO Register No.
AEIAR-115/2007);
Decommissioning of the Former Kai Tak Airport Other than the North Apron
(EIAO Register No. AEIAR-114/2007);
Kai Tak Development EIA (EIAO Register No. AEIAR-130/2009); and
Installation of Submarine Gas Pipelines and Associated Facilities from To Kwa
Wan to North Point for Former Kai Tak Airport Development (EIAO Register
No. AEIAR-153/2010).
9.2.1.5 The following previous Kai Tak Development studies and con-current works reports are
considered for this LVIA:
CE 35/2006 (CE) – Kai Tak Development Engineering Study cum Design and
Construction of Advance Works – Preliminary Design Report and Design
Memorandum of Trunk Road T2 (Final);
CE 35/2006 (CE) – Final Report on Planning, Landscape and Urban Design
Study;
CE 35/2006 (CE) – Final Preliminary Design Report for Advance Works;
CE 35/2006 (CE) – Review Report;
CE 35/2006 (CE) – Kai Tak Development Environmental Impact Assessment
Report;
CE 35/2006 (CE) – ACABAS Submission for Preliminary Design of Highway
Structures in KTD; (Revision A)(6-7-09);
CE 58/2006 (HY) – Central Kowloon Route and Gascoigne Road Flyover
Landscape and Visual Impact Assessment Report;
CE 42/2008 (CE) Tseung Kwan O - Lam Tin Tunnel and Associated Works –
Investigation Report;
CE 43/2010 (HY) Central Kowloon Route - Design & Construction: Draft
Landscape and Visual Impact Assessment – Baseline Study;
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-5
SCL-NEX/2206 EIA Study for Tai Wai to Hung Hom Station (MTR Corporation
LTD);
CV/2009/06 - Greening Master Plan (GMP) for Kwun Tong District by CEDD;
and
Recommended Outline Development Plan (RODP) for Kai Tak Development.
9.3 Assessment Methodology
9.3.1 General Methodology
9.3.1.1 Landscape and visual impacts have been assessed separately for the construction and
operation phases.
9.3.1.2 The methodology will comply with the requirements of Annexes 10 and 18 of the EIAO
TM, the EIA Study Brief ESB-203/2009 (issued in April 2009) and the EIAO Guidance
Note No. 8/2010. The methodology consists of the following procedures:
Review of the planning and development control framework;
Landscape impact assessment;
Visual impact assessment;
Recommendation on landscape and visual mitigation measures;
Identification of residual impacts; and
Predication of acceptability of impacts.
9.3.2 Review of the Planning and Development Control Framework
9.3.2.1 A review of the existing planning studies and documents for the Project is carried out to
understand the planned role of the site and help determine if the Project fits into the
wider landscape context.
9.3.2.2 The review will consider all areas zoned on the Outline Development Plans, Outline
Zoning Plans, Layout Plans, and Recommended Outline Development Plan for Kai Tak
Development which are physically affected by the Project including the area within the
project boundary and temporary construction or works areas. The review considers the
following aspects of planning designations:
Loss of zoning areas due to the implementation of the Project;
Degradation zoning areas which might affect the viability of its landscape
planning designation;
The visual amenity enjoyed by future residents or users; and
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-6
The compatibility of the Project with this future landscape.
9.3.3 Landscape Impact Assessment
9.3.3.1 The assessment of landscape impacts involves:
Baseline landscape review;
Assessment of the degree of sensitivity of the landscape resources and landscape
character areas;
Identification of potential sources of landscape impacts;
Assessment of the magnitude of landscape impacts before and after mitigation
measures: and
Prediction of significance of landscape impacts.
9.3.4 Baseline Landscape Review
9.3.4.1 A baseline landscape review is achieved by site visits and desktop study of
topographical maps, information databases and photographs to identify the baseline
landscape resources (LRs) and landscape character areas (LCAs) within the study area.
Landscape resources include vegetation, patterns of settlement, land use and water
bodies.
9.3.5 Assessment of the Degree of Sensitivity of the Landscape Resources and Landscape
Character area
9.3.5.1 Sensitivity of LCAs and LRs identified in the baseline landscape review is assessed by
the following factors:
Quality and maturity;
Importance or rarity;
Ability to accommodate change;
Significance of the change in local and regional context;
Overall size within the study area; and
Whether there are any statutory or regulatory limitations / requirements relating to
the LCAs and LRs.
9.3.5.2 Sensitivity of each LCA and LR is classified as follows:
High: Important landscape resources or landscape with particularly distinctive
character or high importance, sensitive to small changes.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-7
Medium: Moderately important landscape resources or landscape with moderately
valued landscape characteristics reasonably tolerant to changes.
Low: Landscape resources of low value or relatively unimportant landscape
characteristics highly tolerant to changes.
9.3.6 Identification of Potential Sources of Landscape Impacts
9.3.6.1 These are various elements of construction and operational works which generate
landscape impacts. Such impacts are described, measured and illustrated in this report.
9.3.7 Assessment of the Magnitude of Landscape Impacts
9.3.7.1 The magnitude of the impact or magnitude of change depends on a number of factors
including:
Scale of Project;
Location of Project;
Compatibility of Project with the surrounding landscape;
Duration of impacts under construction and operation phases;
The relative size of the change in comparison to the size of the LCAs and LRs;
and
Reversibility of change (changes are residual or not residual after mitigation).
9.3.7.2 The magnitude of landscape impacts is classified as follows:
Large: The LCA or LR would experience major change.
Intermediate: The LCA or LR would experience moderate change.
Small: The LCA or LR would experience slight or barely perceptible
changes.
Negligible: The LCA or LR would experience no discernible change.
9.3.8 Prediction of Significance of Landscape Impacts
9.3.8.1 The degree of significance of landscape impact is derived from the magnitude of change
which the Project will cause to the existing LRs & LCAs and ability to tolerate the
change, i.e. their sensitivity. The landscape impacts during construction and operation
are assessed by combining the sensitivity and the magnitude of change for LRs and
LCAs according to Table 9.1. Any such impacts are further defined as beneficial or
adverse.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-8
Table 9.1 Matrix for Impact Significance Threshold
Ma
gn
itu
de
of
Ch
an
ge
cau
sed
by
th
e P
roje
ct Large Moderate
Moderate /
Substantial Substantial
Intermediate Slight / Moderate Moderate Moderate /
Substantial
Small Slight Slight / Moderate Moderate
Negligible Insubstantial Insubstantial Insubstantial
Low Medium High
Sensitivity (LCAs, LRs or VSRs)
9.3.8.2 The Degree of Impact Significance Threshold is divided into four thresholds:
Substantial: Adverse / beneficial impact where the proposal would cause significant
deterioration or improvement in existing landscape.
Moderate: Adverse / beneficial impact where the proposal would cause noticeable
deterioration or improvement in existing landscape.
Slight: Adverse / beneficial impact where the proposal would cause slight or
barely perceptible deterioration or improvement in existing landscape.
Insubstantial: No discernible change in the existing landscape.
9.3.9 Visual Impact Assessment
9.3.9.1 The assessment of visual impacts has involved the followings procedures:
Identification of Zone of Visual Influence (ZVIs);
Identification of Visually Sensitive Receivers (VSRs) within the ZVIs;
Identification of relative numbers of VSRs;
Assessments of the degree of sensitivity of the VSRs;
Identification of potential sources of visual impacts;
Assessment of the magnitude of visual impacts; and
Predication of significance of visual impacts.
9.3.10 Identification of Zone of Visual Influence (ZVI)
9.3.10.1 This is achieved by site visits and desktop study of topographic maps and photographs,
and preparation of cross-section to determine visibility of the Project from various
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-9
locations. The ZVI for both construction and operational phases of the Project are
identified.
9.3.11 Identification of Visually Sensitive Receivers (VSRs) within the ZVI
9.3.11.1 These are the people who would reside within, work within, play within, or travel
through, the ZVI.
9.3.12 Identification of relative numbers of VSRs
9.3.12.1 The relative number of VSRs is expressed in terms of whether there are few, medium or
many.
9.3.13 Assessments of the Degree of Sensitivity of the VSRs
9.3.13.1 The individual VSRs identified are assessed by the following factors that influence
sensitivity:
The type of VSRs, which is classified as Residential User, Occupational User,
Recreational User or Travelling User according to whether the person is at home,
at work, at school, at play, or travelling;
Estimated number of receiver population;
Value and quality of existing views;
Availability and amenity of alternative views;
Duration or frequency of view; and
Degree of visibility.
9.3.13.2 The ratings for sensitivity of the VSRs are classified below:
High: The VSR is highly sensitive to any change in their viewing experience.
Medium: The VSR is moderately sensitive to any change in their viewing
experience.
Low: The VSR is slightly sensitive to any change in their viewing experience.
9.3.14 Identification of Potential Sources of Visual Impacts
9.3.14.1 These are the various elements of the construction works and physical aboveground
structures of the Project that would generate visual impacts.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-10
9.3.15 Assessment of Magnitude of Visual Impacts
9.3.15.1 Factors for considering the Potential Magnitude of Visual Impacts include:
Compatibility with the landscape and character of the surroundings;
Duration of impacts;
Scale of the project;
Reversibility of the change (changes are residual or not residual after mitigation);
Viewing distance; and
Potential blockage of views.
9.3.15.2 The rating for Magnitude of Change of the view of VSRs is classified as below:
Large: The VSR would suffer major change in their viewing experience.
Intermediate: The VSR would suffer moderate change in their viewing experience.
Small: The VSR would suffer slight or barely perceptible changes.
Negligible: The VSR would suffer no discernible change.
9.3.16 Predication of Significance of Visual Impacts
9.3.16.1 The significance threshold for visual impacts is rated in a similar fashion to the
landscape impact, i.e. significant, moderate, slight and negligible. The visual impact
during construction and operation is assessed by combining the sensitivity of change
and the magnitude of change of various VSRs according to Table 9.1. The impacts may
be beneficial or adverse.
9.3.16.2 The Degree of the Impact Significance is divided into four thresholds:
Substantial: Adverse / beneficial impact where the proposal would cause significant
deterioration or improvement in existing visual quality.
Moderate: Adverse / beneficial impact where the proposal would cause noticeable
deterioration or improvement in existing visual quality.
Slight: Adverse / beneficial impact where the proposal would cause slight or
barely perceptible deterioration or improvement in existing visual
quality.
Insubstantial: No discernible change in the existing visual quality.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-11
9.3.17 Recommendation on Landscape and Visual Mitigation Measures
9.3.17.1 The identification of the landscape and visual impacts will highlight those sources of
conflict requiring design solutions or modifications to reduce the impacts, and, if
possible, blend the development and associated activities with the surrounding
landscape. Mitigation measures have considered factors including:
Adopting alternative design or revisions to the basic engineering or architectural
design to prevent and / or minimize adverse impacts;
Mitigation measures such as colour, architectural and landscape treatment of
physical, engineering and building features;
Compensatory measures such as the implementation of landscape design
measures such as creation of new amenity area to compensate for unavoidable
adverse impacts and to attempt to generate potentially beneficial long-term
impacts;
Compensatory tree planting to compensate for felled trees; and
Additional tree planting to screen the Trunk Road T2 and associated structures.
9.3.17.2 The mitigation measures will be included in the detail design, construction and
operation phases of the Project and associated works to reduce impacts to acceptable
levels. Responsible parties will be identified for the on-going management and
maintenance of the proposed mitigation measures to ensure their effectiveness
throughout the operation phase of the Project and associated works. The Funding
Agency and Implementation Agency for the implementation of the recommended
mitigation measures are presented in Tables 9.20 and 9.21. This will follow ETWB
TCW No.2/2004 Maintenance of Vegetation and Hard Landscape Features, and ETWB
TCW No.3/2006 - Tree Preservation.
9.3.18 Identification of Residual Impacts
9.3.18.1 Residual impacts are those which remain after the proposed mitigation measures have
been implemented. These are assessed both during the construction and operation
periods, which are taken to be day 1 and 10 years after the Project has been operational.
9.3.18.2 During the operational period the soft landscape mitigation measures will reach a level
of maturity that allows them to perform their original design objectives. The residual
impacts in this instance will reduce over time as the vegetation becomes established and
mature.
9.3.18.3 The significance threshold of residual impacts is derived from the matrices described
separately above for the landscape and visual impacts. Both landscape and visual
residual impacts are products of magnitude of change and sensitivity of the receiver.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-12
9.3.19 Predication of Acceptability of Impacts
9.3.19.1 The acceptability of the Project is dependent upon the significance of the residual
impacts in accordance with the five criteria set out in Annex 10 of the Technical
Memorandum of the Environmental Impact Assessment Process (EIAO-TM). The
criteria are summarized below:
Beneficial. The project will complement the landscape and visual character of its
setting, will follow the relevant planning objectives and will improve the
landscape and visual quality of the study area;
Acceptable. The assessment indicates that there will be no significant effects on
the landscape, no significant visual effects caused by the appearance of the
project, or no interference with key views;
Acceptable With Mitigation Measures. There will be some adverse effects;
these can be eliminated, reduced or offset to a large extent by specific measures;
Unacceptable. The adverse effects are considered too excessive and are unable to
be mitigated practically; and
Undetermined. Significant adverse effects are likely, but the extent to which they
may occur or may be mitigated cannot be determined from the study. Further
detailed study will be required for the specific effects in question.
9.4 Scope and Content of the Study
9.4.1 Description of the Project
9.4.1.1 The nature, scope and implementation programme of the Project is described in Section
2 & 3 of this Report. In accordance with the Study Brief, this study will assess the
landscape and visual impacts during the construction and operation phases of the
Project.
9.4.1.2 Background: The Kai Tak (North) Outline Zoning Plan (OZP) and Kai Tak (South)
OZP were gazetted in 1998 providing the statutory planning framework for the area.
Following subsequent reviews and consultation processes, the OZP for the entire Kai
Tak area was gazetted and subsequently amended under the Town Planning Ordinance
between 2006 and 2012. It is noted that the land use proposals for Kai Tak would be
refined in later stages. This report also reflects the best available information from the
latest Kai Tak OZP and CEDD’s draft Recommended Outline Development Plan
(RODP) for Kai Tak Development at the time of preparing the report.
9.4.1.3 As a part of the strategic road network within the South East Kowloon Development,
Route 6 forms an east west express link between West Kowloon and Tseung Kwan O.
Route 6 comprises the Central Kowloon Route (CKR), Trunk Road T2 and Tseung
Kwan O – Lam Tin Tunnel (TKO-LTT).
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-13
9.4.2 Consideration of Alternatives and Development of a Preferred Option
9.4.2.1 Details of the comparison of various development options and how the preferred option
is formulated and translated are summarized in Section 2 of this report.
9.4.3 Scope and Content of the Study
9.4.3.1 The Project boundary covers the Kowloon Bay, Former Kai Tak South Apron, Kwun
Tong and Cha Kwo Ling as shown in Figures 9.1 and 9.2.
9.4.3.2 According to EIA Study Brief No. ESB-203/2009, the study area for the landscape
impact assessment shall include all areas within 100m extended from the Project
boundary and the proposed off-site work sites. The assessment area for the visual
impact assessment shall be defined by the visual envelope of the Project (ZVI). The
study area for the landscape impact assessment and ZVI are indicated in Figures 9.1
and 9.2.
9.5 Review of Planning and Development Control Framework
9.5.1 Review of Outline Development Plan and Outline Zoning Plans
9.5.1.1 The proposed Trunk Road T2 has been planned within limited land take and where
possible is in tunnel. A review of the existing and planned development framework for
the proposed works and for the surroundings is undertaken. It identifies issues for
neighbouring planned land uses, identifying potential resources and sensitive receivers,
and ensuring a high compatibility between the Project and the surroundings.
9.5.1.2 The study area is covered by:
Draft Ngau Tau Kok and Kowloon Bay Outline Zoning Plan No. S/K13/27
gazetted on 14/10/2011;
Approved Kwun Tong (South) Outline Zoning Plan No. S/K14S/18 gazetted on
14/6/2013;
Approved Cha Kwo Ling, Yau Tong, Lei Yue Mun Outline Zoning Plan No.
S/K15/19 gazetted on 17/06/2011;
Approved Kai Tak Outline Zoning Plan No. S/K22/4 gazetted on 14/09/2012; and
Recommended Outline Development Plan (RODP) for Kai Tak Development
(KTD).
9.5.1.3 The review of ODPs and OZPs has not only included a review of the plans, but also the
“Notes” and “Explanatory Statements” which accompany, and form part of these plans.
9.5.1.4 The proposed alignment of the at-grade section of Trunk Road T2 at the south apron is
located within the planned road corridor of the approved Kai Tak OZP as shown in
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-14
Figures 9.5 and 9.5.1 to 9.5.8. However, some of the proposed works will cause a
minor change of current land use in the area. The change comprises:
9.5.1.5 The proposed Ventilation Building at Kai Fuk Road located within areas zoned “Other
Specific Uses (Tunnel Ventilation Shaft)” (“OU”) as shown in Figure 9.1. Since this
zone is already reserved for tunnel ventilation shaft use, it is not considered to have
potential conflicts with the planning intention of this OZP.
9.5.1.6 On completion of the approved design of the Trunk Road T2 and associated buildings,
it is recommended that the OZP shall be amended to incorporate the changes arising
from the Project.
9.5.1.7 Apart from the change in land use mentioned above, there will not be any impacts on
guidelines on landscape strategies, landscape frameworks, urban design concept,
building height profiles, special design areas, landmarks, designated view corridors,
open space networks and landscape links of the area except for the RODP for KTD.
Ongoing liaison between the proponent of this Project and KTD regarding the proposed
zoning and road alignment will be carried out throughout the design development
process to ensure the Project is compatible with the future context of the area.
9.5.1.8 As a whole, it is considered that the Project would be in accordance with the planning
intentions for the study areas, as set out in the OZPs and other planned development
framework.
9.6 Baseline Study
9.6.1 Baseline Study
9.6.1.1 The study areas cover the South Apron of the former Kai Tak Airport, Kwun Tong, Cha
Kwo Ling, and adjacent water bodies. The extent of works are illustrated in Figures 9.1
and 9.2.
9.6.1.2 The landscape baseline review comprises the identification of all existing Landscape
Resources (LRs) and Landscape Character Areas (LCAs) within 100m from the works
limit of the Project.
9.6.1.3 The visual baseline review comprises the identification of all Visually Sensitive
Receivers (VSRs) within the Zones of Visual Influence (ZVIs) of the Project.
9.6.1.4 For ease of reference each LR, LCA and VSR is given an identity number, which is
used in all relevant tables and figures in this report.
9.6.2 Landscape Resources
9.6.2.1 The baseline landscape resources that will be affected during the Construction and
Operation Phases, together with their sensitivity, are described in Table 9.2. The
locations of LRs are mapped in Figures 9.6.1 and 9.6.2. Photo views illustrating the
LRs within the study area are illustrated in Figures 9.7.1 to 9.7.4.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-15
9.6.2.2 In surveying and reviewing the Trunk Road T2 Works Area, no Old and Valuable
Trees, important trees or wall trees are found within the site boundary or within the
proximity of the works area. For all tree locations, refer to Figures 9.10.1 and 9.10.2.
Table 9.2 List of Landscape Resources and their Sensitivity
ID.
No. Landscape Resources
Sensitivity
(Low, Medium,
High)
LR1
Roadside Planting (Kai Fuk Road)
There are approximately 40 trees of semi-mature size planted
along the roadside. The area is approximately 6,430 square
metres. No area will be required by the Project for either
Construction or Operation phases. Trees in this area are 5-12
meters in height with low to medium amenity value. The species
mainly include Acacia confusa, Albizia lebbeck, Aleurites
moluccana, Caryota mitis and Melaleuca cajuputi subsp.
cumingiana. Some tall shrubs such as Schefflera arboricola and
Schefflera actinophylla are planted underneath. The sensitivity
of this landscape resource is considered medium.
Medium
LR2
Derelict / Disturbed Land Proposed as Open Space (Kai Fuk
Road)
There are approximately 78 trees of young to mature size
planted along the road side and periphery of the amenity area.
The size of the area is approximately 3,120 square metres. This
area is currently used for storage of construction materials. No
area will be required by the Project for either Construction or
Operation phases. Trees in this area are 3-9 meters in height
with low to medium amenity value. The species mainly include
Macaranga tanarius var. tomentosa, Leucaena leucocephala,
Morus alba, Thevetia peruviana and Aleurites moluccana. The
sensitivity of this landscape resource is considered medium.
Medium
LR3
Roadside Planting (Sheung Yee Road)
Small shrubs in columnar form such as Garcinia subelliptica
and Podocarpus macrophyllus are planted along Sheung Tee
Road. Some colourful and flowering shrubs such as Cordyline
fruticosa, Duranta erecta, Osmanthus fragrans, Loropetalum
chinensis f. rubrum and Ixora chinensis are planted underneath.
The size of the area is approximately 2,560 square metres. No
area will be required by the Project for either Construction or
Operation phases.The sensitivity of this landscape resource is
considered medium.
Medium
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-16
ID.
No. Landscape Resources
Sensitivity
(Low, Medium,
High)
LR4
Car Park (GW Parking Lot at Sheung Yee Road)
There are approximately 28 trees of young to semi-mature size
planted within Sheung Yee Road Parking Lot. The size of the
area is approximately 4,710 square metres. Trees in this area
are 3-8 metres in height with low to medium amenity value. The
dominant species include Albizia lebbeck, Aleurites moluccana,
and Macaranga tanarius var. tomentosa. No area will be
required by the Project for either Construction or Operation
phases. The sensitivity of this landscape resource is considered
low.
Low
LR5
Occupational Land (Kai Fuk Road Shell Garage)
There are approximate 11 trees of young to semi-mature size
planted within amenity planters at Kai Fuk Road Shell Garage.
The size of the area is approximately 1,590 square metres. Trees
in this area are 5-8 metres in height with medium amenity value.
The dominant species include Aleurites moluccana, Bombax
ceiba and Delonix regia. No area will be required by the Project
for either Construction or Operation phases. The sensitivity of
this landscape resource is considered medium.
Medium
LR6
Amenity Area (Kai Fuk Road / Kwun Tong By-pass)
This amenity area comprises a series of small sitting out areas
and a footpath, in addition to planting under and next to the
elevated Kuwn Tong Bypass. The size of the area is
approximately 11,010 square metres. Within the site there are
approximately 81 trees of young to semi-mature size planted
along the amenity area next to Kwun Tong By-pass in the T2
area. Trees in this area are 5-12 mxeters in height with low to
medium amenity value. The dominant species include Albizia
lebbeck, Aleurites moluccana, Bauhinia variegata and
Spathodea campanulata. The overall form and health of trees
surveyed are fair to poor. A majority of them have broken
and/or dead branches and are damaged. Some colourful and
flowering shrubs such as Cordyline fruticosa, Duranta erecta,
Excoecaria cochinchinensis and Ixora chinensis are planted
underneath. The sensitivity of this landscape resource is
considered medium.
Medium
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-17
ID.
No. Landscape Resources
Sensitivity
(Low, Medium,
High)
LR7
Amenity Area (under Kwun Tong By-pass)
This is a small amenity area connecting the Kowloon Bay
Industrial Area and the former Kai Tak South Apron. Parts of
the area are under the Kai Fuk Road Flyover and Kwun Tong
By-pass. The size of the area is Approximately 19,720 square
metres. There are approximately 100 semi-mature trees of 6 -
10 metres height with low to medium amenity value. Dominant
species include Acacia confusa, Lagerstroemia speciosa,
Caryota mitis, Schima superba and Delonix regia. Some shrubs
such as Cordyline fruticosa, Duranta erecta, Allamanda schottii
and Spathiphyllum floribundum are planted around the planting
area. No area will be required by the Project for either
Construction or Operation phases. Given the relative small size
of this open area and less prominent location, the sensitivity of
this landscape resource is considered medium.
Medium
LR8
Derelict / Disturbed Land (KTD South Apron)
There are 46 trees recorded within the Project. The dominant
species include Melia azedarach and Archontophoenix
alexandrae. An exotic species of invasive weed tree is also
abundant in the area near Cheung Yip Street, namely Leucaena
leucocephala. There are two planters which combine to measure
159 square metres.
The size of the area is approximately 208,440 square metres.
The temporary Western Works construction area will require
approximately 75,300 square metres of LR8. The sensitivity of
this landscape resource is considered low.
Low
LR9
Water Body (Kai Tak Approach Channel)
It is an artificial water body connecting the Kai Tak Nullah and
Kwun Tong Typhoon Shelter. The size of the area is
approximately 32,910 square metres. Both sides of the channel
are linear man-made intertidal hard shore with some weeds
scattered along it. It serves as a transition between a nullah and
open water which is sensitive to reclamation. The sensitivity of
this landscape resource is considered medium.
Medium
LR10
Artificial Shoreline (KTD South Apron)
The straight artificial shoreline along former Kai Tak South
Apron comprises armour stone and concrete pavement. The size
of the area is approximately 1,100 square metres. Some self-
seeded trees, including the invasive weed tree Leucaena
leucocephala, grow between the gaps along the artificial
shoreline which are of low amenity value. It is currently
bounded by the construction site which is not accessible to the
public. The sensitivity of this landscape resource is considered
low.
Low
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-18
ID.
No. Landscape Resources
Sensitivity
(Low, Medium,
High)
LR11
Amenity Area (Public Works Central Laboratory)
There are approximately 25 trees of young to semi-mature size
planted within the amenity areas in Public Works Central
Laboratory. The size of the area is approximately 870 square
metres. Trees in this area are 4-15 meters in height with low to
medium amenity value. The dominant species include Aleurites
moluccana, Bombax ceiba, Callistemon viminalis,
Chrysalidocarpus lutescens and Spathodea campanulata. Some
colourful and flowering shrubs such as Duranta erecta and
Ixora chinensis are planted underneath. No area will be
required by the Project for either Construction or Operation
phases. The sensitivity of this landscape resource is considered
medium.
Medium
LR12 Water Body (Kwun Tong Typhoon Shelter)
It is a semi-enclosed water body bounded by the runway of
former Kai Tak Airport, the man-made hard shore of Kwun
Tong Public Cargo Working Area and the breakwater at
southern end. The size of the area is approximately 315,320
square metres. The sensitivity of this landscape resource is
considered medium.
Medium
LR13 Water Body (Victoria Harbour)
It is a recognised and distinctive feature of Hong Kong
worldwide, both as a tourist attraction and working port. The
size of the area is approximately 206,790 square metres. The
area will be used for barging construction and demolition waste
from the Western Works Area. No area will be required by the
Project throughout the Operation phase. The Harbour forms an
iconic centrepiece for Hong Kong, with the airport runway
forming a unique coastline edge. The sensitivity of this
landscape resource is considered high.
High
LR14 Roadside Planting (Cha Kwo Ling Road)
There are approximately 43 trees of young to semi-mature size
planted along the Cha Kwo Ling Road. The size of the area is
approximately 1,570 square metres. No area will be required by
the Project for either Construction or Operation phases. Trees in
this area are 5-12 meter in height with low to medium amenity
value. The dominant species include Bischofia javanica,
Melaleuca cajuputi subsp. cumingiana and Spathodea
campanulata. The sensitivity of this landscape resource is
considered medium.
Medium
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-19
ID.
No. Landscape Resources
Sensitivity
(Low, Medium,
High)
LR15 Residential Landscape (Cha Kwo Ling Residential Area)
There are approximately 80 trees within the low rise area of Cha
Kwo Ling Village. The size of the area is approximately 21,660
square metres. No area will be required by the Project for either
Construction or Operation phases. Trees in this area are 5-14
meter in height with low to medium amenity value. The
dominant species include Acacia spp., Eucalyptus spp., Ficus
spp., Litsea glutinosa, Mallotus paniculatus, Sterculia
lanceolata. The existing trees and shrubs occupy an area of 1ha.
The sensitivity of this landscape resource is considered
medium.
Medium
LR16 Derelict / Disturbed Land Proposed as Cha Kwo Ling
Promenade Park by Others (Cha Kwo Ling Former Public
Cargo Working Area)
It is currently a fenced-off area inaccessible to the public of
approximately 27,020 square metres. Some self-seeded weeds
and one tree, Macaranga tanarius var. tomentosa, with low
amenity value grow between the gaps in the concrete pavement.
The sensitivity of this landscape resource is considered low.
Low
LR17 Derelict / Disturbed Land (Wai Lok Street Reclaimed
Industrial Area)
The size of the area is approximately 7,370 square metres. No
area will be required by the Project for either Construction or
Operation phases. The area has some self-seeded weeds with
low amenity value. There are no trees within the promenade
area. It is currently fenced-off and inaccessible to the public. A
temporary holding nursery is beside Wai Lok Street Reclaimed
Industrial Area. There are approximately 15 trees of young to
semi-mature size within the area. Trees are 3-7 meters in height
with low to medium amenity value. The dominant species
include Delonix regia, Hibiscus tiliaceus and Senna siamea. The
sensitivity of this landscape resource is considered low.
Low
LR18 Occupational Land (Wai Lok Street Garage)
There are approximately 30 trees of young to semi-mature size
planted within Wai Lok Street Garage area. The size of the area
is approximately 7,040 square metres. No area will be required
by the Project for either Construction or Operation phases. The
trees in this area are 4-11 metres in height with low to medium
amenity value. The dominant species include Ficus elastica,
Callistemon viminalis, Hibiscus tiliaceus and Macaranga
tanarius var. tomentosa. An exotic species of invasive weed tree
is abundant within the area, namely Leucaena leucocephala.
The sensitivity of this landscape resource is considered low.
Low
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-20
ID.
No. Landscape Resources
Sensitivity
(Low, Medium,
High)
LR19 Amenity Area and Access Road (Adjacent to Wai Lok Street
Temporary Soccer Pitch)
There are approximately 18 trees of young to semi-mature size
along the southern boundary of the area adjacent to the soccer
pitch. The size of the area is approximately 900 square metres.
No area will be required by the Project for either Construction
or Operation phases. The trees in this area are 3-6 metres in
height with medium amenity value. The dominant species
includes Delonix regia. Some colourful and flowering shrubs
such as Duranta erecta ‘Variegata’, Allamanda cathartica and
Wedelia trilobata are planted around the study area. A grass
soccer pitch is adjacent to the southern boundary of the area.
The sensitivity of this landscape resource is considered
medium.
Medium
LR20 Derelict / Disturbed Land Proposed as Cha Kwo Ling
Promenade Park by Others (Wai Yip Street / Cha Kwo Ling
Road Reclaimed Industrial Area)
This derelict/disturbed land is approximately 11,240 square
metres. No area will be required by the Project for either
Construction or Operation phases. There are approximately 5
trees of young to semi-mature size within the area. Trees in this
area are 5-11 metres in height with low to medium amenity
value. The dominant species includes Casuarina equisetifolia
and Ficus microcarpa. The sensitivity of this landscape resource
is considered low.
Low
LR21 Occupational Land (Wai Yip Street Car Park)
This is a hard standing area with approximately 4 trees of young
to semi-mature size. The size of the area is approximately 1,840
square metres. No area will be required by the Project for either
Construction or Operation phases. Trees in this area are 3-5
metres in height with low amenity value. The dominant species
include Macaranga tanarius var. tomentosa and the invasive
exotic weed tree Leucaena leucocephala. The sensitivity of this
landscape resource is considered low.
Low
9.6.3 Landscape Character Areas
9.6.3.1 Landscape Character Areas have been identified within the Study Area in accordance
with the Study on Landscape Value Mapping of Hong Kong. These are described in
Table 9.3 and mapped in Figures 9.8.1 to 9.8.2. Photo views illustrating the LCAs
within the study area are illustrated in Figures 9.9.1 and 9.9.2.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-21
Table 9.3 List of Landscape Character Areas and their Sensitivity
ID.
No. Landscape Character Area
Sensitivity
(Low, Medium,
High)
LCA1 Major On-Going Development Landscape
This area comprises the former Kai Tak Airport which can be
further sub-divided to the North Apron area, the South Apron
corner and the Runway Precinct. The area is generally flat, open,
primarily hard standing. Currently the area is undergoing
various demolition/site clearance, infrastructure and
construction projects within both the South Apron and Runway
Precinct areas. The area is comprised of the following
Landscape Resources: LR8, LR10 & LR11. In total the
landscape resources is approximately 210,410 square metres.
As previously discussed, in the landscape resources section the
temporary Western Works construction area is approximately
75,300 square metres. Given the area is already disturbed by
ongoing construction work but includes 159 square metres of
planting and 71 trees, the sensitivity of this area is considered
low.
Low
LCA2 Kowloon Bay Industrial Urban Landscape
This is an area of industrial and commercial use. This
comprises medium to high -rise industrial buildings. The
streetscape is a mix of utilitarian with very little soft landscape
treatment within the older Kowloon Bay industrial areas and
upgraded streetscape of a mix of trees and planter beds around
the new developments. The area is comprised of the following
Landscape Resources: LR2, LR3 & LR4. In total the landscape
resources is approximately 10,390 square metres which includes
106 trees. Given the urbanized nature of the area the sensitivity
of this area is considered medium.
Medium
LCA3 Transport Corridor
This area are comprises the Kwun Tong Bypass (elevated
bypass expressway), Kai Fuk Road, Wai Yip Street and Cha
Kwo Ling Road. The area is comprised of the following
Landscape Resources: LR1, LR5, LR6, LR7 & LR14. In total
the landscape resources is approximately 40,320 square metres.
Within the area a few amenity plantings of low to medium
amenity value are found in the central medians on both sides of
the corridors which include 275 trees. It is slightly sensitive to
highway development. Given the urbanized nature of the area
and the few amenity plantings, the sensitivity of this area is
considered medium.
Medium
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-22
ID.
No. Landscape Character Area
Sensitivity
(Low, Medium,
High)
LCA4 Kwun Tong Typhoon Shelter Landscape
This is an area for typhoon shelter use in Kwun Tong. It is
substantially enclosed by coast and offshore breakwater. Though
they consist primarily of water, other features in these
landscapes include jetties, pontoons and navigational features
resulting in a landscape that is a transitional one between land
and sea. The area is comprised of the following Landscape
Resources: LR12. In total the landscape resources is
approximately 315,320 square metres. Given this area is
comprised by mainly water body, the sensitivity of this area is
considered medium.
Medium
LCA5 Kai Tak Typhoon Shelter Landscape
This is an area for typhoon shelter use in Kai Tak and Kowloon
bay. It is enclosed by an artificial coastline and offshore
breakwater. The area is an unused large standing body of water.
It is comprised of the following Landscape Resource: LR9 and
LR10. In total the landscape resources is approximately 34,010
square metres. Given this area is comprised by mainly man
made artificial features the sensitivity of this area is considered
medium.
Medium
LCA6 Cha Kwo Ling Miscellaneous Urban Fringe Landscape
This area is dominated by low rise residential development
scattered along the hillside. There are patches of roadside tree
planting of low to medium amenity value along the Cha Kwo
Ling Road. Fruit trees have been planted by the villagers, in
front of their homes. The area is sensitive to tunnel and highway
development. The area is comprised of the following Landscape
Resources: part of LR15. In total the landscape resources is
approximately 21,660 square metres with approximately 80
trees. Given the urbanized nature of the area and the low to
medium amenity value of tree planting, the sensitivity of this
area is considered medium.
Medium
LCA7 Cha Kwo Ling Reclaimed Industrial Urban Landscape
This is a fenced-off area of mixed of reclaimed industrial areas,
sewage treatment works, reclaimed open storage, cargo and
dock. The study area is utilitarian and lack of amenity plantings.
Most of the study area is hard standing or vacant with self-
seeded weeds that are with low amenity value. The area is
slightly sensitive to the highway development. The area is
comprised of the following Landscape Resources: LR14, LR16
and LR17. In total the landscape resources is approximately
34,390 square metres with approximately 16 trees. Though
LR14 is within the boundary of LCA7, the area coverage is
included in LCA3. Given the urbanized nature of the area and
lack of amenity plantings, the sensitivity of this area is
considered low.
Low
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-23
ID.
No. Landscape Character Area
Sensitivity
(Low, Medium,
High)
LCA8 Wai Yip Street/Cha Kwo Miscellaneous Urban Fringe
Landscape This is an area of mixed of a petrol station, car park,
temporary soccer pitch and temporary tree nursery. Some
amenity plantings with trees and shrubs of low to medium
amenity value are found within the petrol station and temporary
soccer pitch. The area is comprised of the following Landscape
Resources: LR18, LR19, LR20, LR21 and a small portion of
LR17. In total the landscape resources is approximately 21,020
square metres which include 57 trees. Given the urbanized
nature of the area and the low to medium amenity value of the
planting, the sensitivity of this area is considered medium.
Medium
LCA9 Victoria Harbour Inshore Water Landscape
This area refers to costal water off Kowloon Bay and Kwun
Tong. The extent of seascape is part of the open seascape
locally. The area is comprised of the following Landscape
Resources: LR13. In total the landscape resources is
approximately 206,790 square metres. As the area is very
sensitive to reclamation, the sensitivity of this area is considered
high.
High
9.6.4 Zones of Visual Influence
9.6.4.1 The Zones of Visual Influence for the Project vary between the Construction and
Operation Phases. Both ZVIs for Construction and Operation Phases are mapped in
Figures 9.14 to 9.14.7 and 9.15 to 9.15.6 respectively. VSRs within the study area are
illustrated in Figures 9.16.1 to 9.16.13.
9.6.4.2 For the Construction Phase the ZVI has been divided into Western and Eastern Works
Areas. The Western Works Area ZVI is quite extensive through the Construction Phase
as there are potentially clear views on to the works area whilst the Kai Tak
Development Runway Precinct and South Apron are under construction. The Eastern
Works Area ZVI is not as extensive, though there are still open views onto the works
area from the surrounding developments and across Kowloon Bay from Hung Hom.
9.6.4.3 In the Operation Phase only the Western Works Area ZVI is affected. The ZVI will be
limited to the above-ground permanent structures including the road corridor, tunnel
portal and ventilation buildings. Due to proposed developments, as per the
Recommended Outline Development Plan (RODP) for Kai Tak, these buildings will be
potentially screened by the adjacent buildings and elevated Kwun Tong By Pass.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-24
9.6.5 Visually Sensitive Receivers
9.6.5.1 Key VSRs found within the ZVI are described in Table 9.4. The assessments of the
degree of sensitivity are listed in Tables 9.5, 9.6 and 9.7. VSRs are divided into
Residential, Occupational, Recreational and Travelling.
Table 9.4 List of the Visually Sensitive Receivers – Construction Phase
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O1
General
Description
Newport Centre
The building is low rise, with eastern views
across Kowloon Bay and KTD: The Runway
Precinct on to the Western Works Area.
Currently the site is undergoing various
clearance, and infrastructure construction work
with no major aesthetic appeal for the area.
The building is planned for redevelopment.
The value and quality of the existing view is
fair.
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
have open eastern views of approximately
1150m min, onto the Western Works Area.
Depending on the detailed design and
construction of RE5, there could be glimpsed
views of the site. The sensitivity of this VSR is
considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Refer to R1 For
description.
O2
General
Description
Kai Tak 1M: Comprehensive Development
Area
A planned high rise building, on a reclaimed
site within the KTD: North Apron Area. The
Area is currently undergoing various
regeneration and construction projects.
Occupational Planned
(2016)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: Development is planned
to be operational by 2016. VSRs in this
location will have a glimpse south eastern
view of approximately 1350m min towards the
Western Works Area. The sensitivity of this
VSR is considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-25
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O2
Operational
Phase
Eastern Works Area: N/A Occupational Planned
(2016) Western Works Area: Depending on the detail
design of GIC6, GIC7, GIC9 & GIC10, future
VSRs in this location will have a glimpse
southern view of approximately 1450m min
towards the Trunk Road T2 Western Tunnel
Portal & Ventilation Building. The sensitivity
of this VSR is considered low.
O3
General
Description
Skyline Tower, Kowloon Bay
This VSR is one of the tallest commercial
buildings in Kowloon Industrial Area. Viewers
at medium to high levels in these buildings
have open and panoramic south eastern views
over the area and onto Victoria Harbour.
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a partial south eastern view of
approximately 700m min towards the Trunk
Road T2 Works Area. The sensitivity of this
VSR is considered low.
Operational
Phase Eastern Works Area: N/A
Western Works Area: Due to South Apron
Development being completed by 2021, the
view will be screened by GIC9 and GIC10
depending on the detailed design and
construction of the above buildings. VSRs in
this location will have a partial southern view
of approximately 650m min onto the Western
Tunnel Portal & Ventilation Building. The
sensitivity of this VSR is considered low.
O4
General
Description
Hong Kong International Trade and
Exhibition Centre
Existing medium rise building. VSRs in this
location will have partial views to the project
area. Views are blocked by the elevated Kwun
Tong By-pass, roadside trees and the Jordan
Valley Box Culvert; desilting & pumping
station house buildings, which are currently
under construction. South eastern facing users
will be affected.
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a partial south eastern view of
approximately 400m min towards the Western
Works Area. As the VSR is currently looking
onto the derelict South Apron site, the
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-26
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O4
Operational
Phase
Eastern Works Area: N/A Occupational Existing
Western Works Area: Due to South Apron
Development being completed by 2021, the
view will be screened by GIC6, GIC9 &
GIC10, depending on the detailed design and
construction of the buildings. VSRs will have a
partial southern view of approximately 500m
min onto the Western Tunnel Portal &
Ventilation Building. The sensitivity of this
VSR is considered low.
O5
General
Description
Enterprise Square & Enterprise Square II,
Industrial/Office development Kowloon Bay
Existing medium to high rise buildings with
partial south and south-eastern views from the
upper building levels onto the Trunk Road T2,
area. The view to the project site is partially
blocked by elevated Kwun Tong By-pass,
roadside trees and the Jordan Valley Box
Culvert; desilting & pumping station house
buildings. South eastern facing users will be
affected.
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a partial south eastern view of
approximately 200m min towards the Western
Works Area. As the VSR is currently looking
onto the derelict South Apron site, the
sensitivity of this VSR is considered medium.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Due to South Apron
Development being completed by 2021, the
view will be screened by GIC9 & GIC10,
depending on the detailed design and
construction of the buildings. VSRs will have a
partial southern view of approximately 250m
min towards upon the Western Tunnel Portal
& Ventilation Building. The sensitivity of this
VSR is considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-27
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O6
General
Description
Kai Fuk Industrial Center, Hong Leong
Industrial Complex & Billion Centre
Existing medium to high rise buildings. The
view to the project site is partially blocked by
elevated Kwun Tong By-pass, roadside trees
and the Jordan Valley Box Culvert; desilting &
pumping station house buildings.
Occupational
Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs will have a full
south eastern view of approximately 120m min
towards the Western Works Area. As the VSR
is currently looking onto the derelict South
Apron site, the sensitivity of this VSR is
considered medium.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Due to South Apron
Development being completed by 2021, the
area will be screened by the proposed
buildings. VSRs will have a partial southern
view of approximately 140m min towards
upon the Western Tunnel Portal & Ventilation
Building. The sensitivity of this VSR is
considered medium.
O7
General
Description
Mega Box/Enterprise Square V, Enterprise
Square III, Exchange Tower, Manhattan
Place & One Kowloon
VSRs in these locations are some of
Kowloon’s industrial and commercial areas
tallest buildings. The users in mid to upper
levels will have panoramic views of the
Victoria Harbour area, depending on the detail
design of the completed Runway Precinct and
South Apron Area.
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a full south eastern to south western
view of approximately 70m min towards the
Western Works Area. As the VSR is currently
looking onto the derelict South Apron site, the
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-28
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O7
Operational
Phase
Eastern Works Area: N/A Occupational Existing
Western Works Area: Due to South Apron
Development being completed by 2021, VSRs
will have a partial western to southern view of
approximately 70m min towards upon the
Western Tunnel Portal & Ventilation Building.
The sensitivity of this VSR is considered
medium.
O8
General
Description
Petrol Stations along Kai Fuk Road
VSRs in these locations are on separate sides
of the Kai Fuk Road. The existing view is a
typical road corridor comprised by elevated
Kwun Tong By-pass, Kai Fuk Road and
roadside amenity planting.
Occupational
Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a southern view of approximately
80m min to the Western Works Area has a
glimpse view due to screening of the roadside
amenity planting, the road corridor and the
Jordan Valley Box Culvert; desilting &
pumping station house buildings. The
sensitivity of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a southern view of approximately
80m min to the Western Tunnel Portal &
Ventilation Buildings are glimpsed due to the
screening of roadside amenity planting, the
road corridor, GIC9 & GIC10. The sensitivity
of this VSR is considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-29
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O9
General
Description
Kai Tak Runway Precinct Hotel Belt
A row of medium-rise buildings are planned
on the southern fringe for hotel development.
Occupational/
Recreational Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have glimpse of approximately 500m min
north and north-western views onto the project
site. Though buildings close to the D4 road
bridge will have direct northern views onto the
Western Tunnel Portal Building, depending on
the detail design and construction of GIC11A
which is planned to be completed by 2016, and
R5, RE8 & GIC11C, which are planned for
completion in 2021. The sensitivity of this
VSR is considered low.
O10
General
Description
Kai Tak Cruise Terminal & Tourism
Related Commercial Development
A mixed use commercial development of low
to high rise buildings is currently under
construction and is planned for completion by
2014 and 2015.
Occupational/
Recreational
Planned
(2014-
2015)
Construction
Phase
Eastern Works Area: VSR’s in this location
will have a partial south eastern view of
approximately 1100m min onto the Eastern
Works Area. Additional marine traffic for
moving construction and demolition material
between the Eastern and Western Works Areas
will have an indirect impact onto this VSR. As
the view onto the eastern site waterfront area is
in context with adjacent redevelopment, the
sensitivity of this VSR is considered low.
Western Works Area: VSRs in this location
will have a partial north western view of
approximately 500m min towards the Western
Works Area. However this will be viewed
within the context of adjacent major KTD
redevelopment. The sensitivity of this VSR is
considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-30
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O10
Operational
Phase
Eastern Works Area: N/A Occupational/
Recreational Planned
(2014-
2015) Western Works Area: Due to South Apron
Development being completed by 2021, the
area will be screened by O12 and GIC11A,
which are planned to be completed by 2016,
and R5, RE9 which are planned for completion
in 2021. Depending on the detail design and
construction of these developments, the future
users within the upper floors will have glimpse
north and north-western views of
approximately 1200m min onto the project site
onto the Western Tunnel Portal Building. The
sensitivity of this VSR is considered medium.
O11
General
Description
Vacant Lot at southern end of former Kai
Tak South Apron/3E1 Commercial
Development
The Site is currently a bus parking area.
Within the construction phase the site is
planned to be used as a site works area. As per
the RODP, the Site is designated as a medium
to high rise commercial development. At
present, there is no re-development schedule
available for review. (Exact details for
demolition or redevelopment are not currently
known).
Occupational
Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: As this area is
designated as a site works area within the
Construction phase, it is not designated as a
VSR.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a partial north western to northern
view of approximately 320m min to the
Western Tunnel Portal & Ventilation
Buildings. As the completion of the buildings
is proposed for completion in 2021, the
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-31
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O12
General
Description
Kai Tak South Apron: Gas Pigging Station
Within Appendix A – Development Schedule
for Draft RODP [Ref: WP019-02] (August
2012) A Gas Pigging Station is proposed for a
2012 completion. There is a caveat, that the
area could be rezoned for residential
development.
Occupational Planned
(2012-
2015)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a view of approximately 5m min
onto the Western Works Area. The sensitivity
of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: On completion of the
2021, South Apron Development the future
users will have partial north-western views of
approximately 350m min onto the project site
onto the Western Tunnel Portal Building. The
sensitivity of this VSR is considered low.
O13
General Description
Pacific Trade Centre/ Proposed 3D2
Commercial Development
The site is currently the Pacific Trade Centre.
As per the RODP the site is planned to be
redeveloped into a medium to high rise
commercial development. At present, there is
no re-development schedule available for
review (exact details for demolition or
redevelopment are not currently known).
Occupational Existing/Planned
(2021)
Construction Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have south eastern partial views,
obstructed by 014, R3 and R4, of approx 200m
min onto the project area. The sensitivity of
this VSR is considered low.
Operational Phase
Eastern Works Area: N/A
Western Works Area: Future viewers in this
VSR will have a partial north western to
northern view of approximately 380m min to
the Western Tunnel Portal & Ventilation
Buildings. As the completion of the buildings
is proposed for completion in 2021, the
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-32
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O14
General Description
Octa Tower
Existing high-rise office development with 360
degree views on the Kowloon Bay/Kwun Tong
Commercial Areas and of Victoria Harbour.
Occupational Existing
Construction Phase
Eastern Works Area: VSRs in this location
will have glimpse south eastern views of
approximately 1800m min onto the Eastern
Works Area. As the view is onto the
waterfront area and Victoria Harbour, the
sensitivity of this VSR is considered low.
Western Works Area: VSRs in this location
will have full south western to north western
views onto the Western Works Area of
approximately 20m. The sensitivity of this
VSR is considered medium.
Operational Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have a partial north western to northern
view of approximately 320m min to the
Western Tunnel Portal & Ventilation
Buildings. As the buildings are proposed to be
operational in 2021, the sensitivity of this VSR
is considered medium.
O15
General
Description
Not Used
Construction
Phase
Eastern Works Area: Not Used.
Western Works Area: Not Used.
Operational
Phase Eastern Works Area: Not Used.
Western Works Area: Not Used.
O16
General
Description
Proposed Industrial/Office development at
Kwun Tong Commercial Area
Planned high rise building. The view to the
project site is partially blocked by elevated
Kwun Tong By-pass.
Occupational\ Planned
(2015
Construction
Phase
Eastern Works Area: There are glimpse views
onto the Eastern Works Area, though
additional marine traffic between the eastern
and Western sites will have an indirect impact
onto this VSR. As the view onto the waterfront
area is dominated by additional marine traffic
for construction and demolition material, the
sensitivity of this VSR is considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-33
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O16
Construction
Phase
Western Works Area: South west and north
west facing VSRs are affected whilst the
Trunk Road T2 Western Works Area is under
construction. VSRs in this location will have a
partial south western to north western view of
approximately 300m min to the Western
Works Area. The sensitivity of this VSR is
considered medium.
Occupational\ Planned
(2015
Operational Eastern Works Area: N/A
Phase Western Works Area: VSRs in this location
will have a glimpse western view of
approximately 650m min to the Western
Tunnel Portal & Ventilation Buildings,
depending on the detailed design and
construction of R3, R4, O11, O13 and
GIC11B. The sensitivity of these VSRs is
considered low.
O17
General
Description
Industrial/Office development at Kwun
Tong Western commercial area
The existing view is of Kwun Tong Typhoon
Shelter to the south west and a typical
industrial area with medium to high-rise
buildings within Kwun Tong’s commercial
district.
Occupational Existing
Construction
Phase
Eastern Works Area: At the north western end,
there are no direct views onto the Eastern
Works Area, though views of approximately
200m min to additional marine traffic for
construction and demolition material between
the eastern and western sites will have a partial
indirect impact onto this VSR. The sensitivity
of this VSR is considered low.
Western Works Area: The view to the project
site is partially blocked by elevated Kwun
Tong By-pass and cargo working areas. Only
south west facing users are affected whilst the
Western Works Area is under construction.
Viewers in these VSR’s will have a partial
south western – north western view of
approximately 320m min to the Trunk Road
T2 Western Works Area. The sensitivity of
this VSR is considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-34
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O17
Operational
Phase
Eastern Works Area: N/A Occupational Existing
Western Works Area: Viewers in these VSR’s
will have a glimpse western view of
approximately 650m min to the Western
Tunnel Portal & Ventilation Buildings,
depending on the detailed design and
construction of R3, R4, O11 and O13 the
completion of the buildings which are
proposed for completion in 2021, the
sensitivity of this VSR is considered low.
O18
General
Description
Industrial/Office development at Kwun
Tong Eastern commercial area
The existing view is of Kwun Tong Typhoon
Shelter & Kai Tak Cruise terminal to the south
west. The area is a mix of medium-to- high-
rise, new commercial and industrial buildings
within Kwun Tong’s commercial district.
Occupational Existing
Construction
Phase
Eastern Works Area: At the south eastern end,
the VSRs have glimpse south eastern views of
approximately 360m min onto the project site.
As the site is currently a decommissioned
cargo works area the sensitivity of this VSR is
considered low.
Western Works Area: The view to the project
site is partially blocked by elevated Kwun
Tong By-pass and a decommissioned cargo
Works Area. Only south west facing users are
affected whilst the Western Works Area is
under construction. VSRs in this location will
have a partial south western – north western
view of approximately 750m min to the Trunk
Road T2 Western Works Area. The sensitivity
of this VSR is considered low.
Operational
Phase
Eastern Works Area: Not Used.
Western Works Area: Not Used.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-35
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O19
General
Description
Kwun Tong Sewage Treatment
Works/Kwun Tong Pumping Station
/Planned Landscape Decked: Enclosed
Sewage Works
The development is divided into two sites,
separated by the Kwun Tong By-pass and
Kwun Tong Nullah. The existing view is an
open view of Victoria Harbour to the south
west, typical industrial area with medium rise
industrial buildings to the north and partially
blocked views of Laguna City by elevated
Kwun Tong By-pass to the north east. The area
is proposed to be redeveloped and enclosed
with landscaped deck.
Occupational Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area. Additional marine traffic
between the eastern and western sites will have
an indirect impact onto this VSR. VSRs in this
location will have partial south western views
of approximately 160m min to the Eastern
Works Area The sensitivity of this VSR is
considered low.
Western Works Area: VSRs in this location
will glimpse western views of approximately
1400m min to the Western Works Area. The
views are blocked by the existing ferry piers
and Kwun Tong Typhoon Shelter. Additional
marine traffic between the eastern and western
sites will have an indirect impact onto this
VSR. As the views onto the waterfront area
will be dominated by additional marine traffic
for construction and demolition material, the
sensitivity of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
O20
General
Description
Soccer Pitch, Car Park, Petrol Filling
Station & Vacant Sites (Proposed Cha Kwo
Ling Promenade Park)
This area comprises a soccer pitch, car park,
petrol filling station & vacant sites. The area is
planned to be redeveloped as part of the
proposed Cha Kwo Ling Promenade Park.
Occupational/
Recreational
Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area: The VSR will have full
south eastern views of approximately 5m min
to the Eastern Works Area whilst the project is
under construction. The sensitivity of this VSR
is considered medium.
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-36
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
O20
Operational
Phase
Eastern Works Area: N/A Occupational/
Recreational
Existing/
Planned
(2021)
Western Works Area: Refer to RE17: Cha
Kwo Ling Park, N/A
O21
General
Description
Proposed Cha Kwo Ling Promenade
The site is a decommissioned commercial
cargo working area. The area is planned to be
redeveloped as part of the proposed Cha Kwo
Ling Promenade/Park.
Occupational/
Recreational
Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area: As this area is designated
as a site works area within the construction
phase, it is not designated as a VSR.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
O22
General
Description
Tin Hau Temple
This is a Tin Hau Temple with a vegetated
hillside backdrop to the north.
Occupational Existing
Construction
Phase
Eastern Works Area: The view to the project
site is partially screened by the roadside
planting along the Cha Kwo Ling Road.
The VSR will have partial south western views
of approximately 900m min to the Eastern
Works Area. The sensitivity of this VSR is
considered low.
Western Works Area: N/A
Operational Eastern Works Area: N/A
Phase Western Works Area: N/A
GIC1
General
Description
EMSD Workshops, Sewage Pumping
Station & Electricity Substation.
Existing government workshops are proposed
to be redeveloped into a sewage pumping
station and electricity substation by 2016. The
buildings are low rise, with eastern views
across Kowloon Bay and KTD: The Runway
Precinct on to the Western Works Area.
Currently the KTD site is undergoing various
clearance, and infrastructure construction work
with no major aesthetic appeal for the area.
Government
/Institutional/
Community
Existing/
Proposed
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-37
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
GIC1
Construction
Phase
Eastern Works Area: N/A Government
/Institutional/
Community
Existing/
Proposed Western Works Area: Buildings are planned to
be redeveloped by 2016. Depending on detail
design of RE4 & RE5. VSRs in this location
will have partial eastern views of
approximately 1000m min, onto the Western
Works Area. The value and quality of the
existing view is fair and the sensitivity of this
VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on detail
design of RE8, GIC7, GIC8 & GIC11C, VSRs
in this location will glimpse eastern views of
approximately 1200m min onto the Western
Works Area The sensitivity of this VSR is
considered low.
GIC2
General
Description
Electricity Substation
Planned low rise building on open land
adjacent to Kai Tak Tunnel and Kai Tak
Nullah. Views into the site are screened due to
existing and proposed CKR elevated roads,
and proposed South Apron pedestrian bridge
extensions.
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on detail
design of GIC6, GIC7 & GIC11C. VSRs in
this location will glimpse south eastern views
of approximately 900m min, onto the Western
Works Area. The sensitivity of this VSR is
considered low.
GIC3
General
Description
Tunnel Ventilation Shaft & Administration
Building
Planned low rise to medium rise building, on
open land adjacent to Kai Tak Tunnel and Kai
Tak Nullah.
Government
/Institutional/
Community
Planned
(2016)
Construction Eastern Works Area: N/A
Phase Western Works Area: VSRs in this location
will glimpse south eastern views of
approximately 600m min, onto the Western
Works Area. The sensitivity of this VSR is
considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-38
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
GIC3
Operational
Phase
Eastern Works Area: N/A Government
/Institutional/
Community
Planned
(2016)
Western Works Area: Depending on detail
design of GIC6, GIC7 & GIC11C, VSRs in
this location will glimpse south eastern views
of approximately 640m min, onto the onto the
Western Tunnel Portal Building. The
sensitivity of this VSR is considered low.
GIC4
General
Description
Tunnel Ventilation Shaft & Administration
Building (Kai Tak Tunnel Entrance)
Existing low rise to medium rise buildings
adjacent to the Kai Tak Nullah. Views into the
site are screened by existing and proposed
CKR elevated road, and proposed South Apron
pedestrian bridge extensions.
Government
/Institutional/
Community
Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will glimpse south eastern views of
approximately 690m min, onto the Western
Works Area. The sensitivity of this VSR is
considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on detail
design of GIC6, GIC7 & GIC11C, VSRs in
this location will glimpse south eastern views
of approximately 800m min, onto the onto the
Western Tunnel Portal Building. The
sensitivity of this VSR is considered low.
GIC5
General
Description
DSD Desilting Compound
Planned low rise to medium rise building, on
open land adjacent to Kai Tak Tunnel and Kai
Tak Nullah. Views into the site are screened
due to existing and proposed CKR elevated
roads, and proposed South Apron pedestrian
bridge extensions.
Government
/Institutional/
Community
Planned
(2016)
GIC5
Construction
Phase
Eastern Works Area: N/A Government
/Institutional/
Community
Planned
(2016)
Western Works Area: VSRs in this location
will glimpse south eastern views of
approximately 760m min, onto the Western
Works Area. The sensitivity of this VSR is
considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-39
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
GIC5
Operational
Phase
Eastern Works Area: N/A Government
/Institutional/
Community
Planned
(2016)
Western Works Area: Depending on detail
design of GIC6, GIC7 & GIC11C, viewers
within this VSR will have glimpse south
eastern views of approximately 760m min,
onto the onto the Western Tunnel Portal
Building. The sensitivity of this VSR is
considered low.
GIC6
General
Description
Northern Undesignated Government Site at
former Kai Tak South Apron
Planned low rise to medium rise building.
Depending on detail design of buildings.
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Viewers within this
VSR will have partial south eastern views of
approximately 400m min, onto the Western
Tunnel Portal Building. The sensitivity of this
VSR is considered medium.
GIC7
General
Description
Southern Undesignated Government Site at
former Kai Tak South Apron
Planned low rise to medium rise building.
Depending on detail design of buildings.
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have partial south eastern to eastern views
of approximately 150m min, onto the Western
Tunnel Portal & Ventilation Buildings. The
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-40
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
GIC8
General
Description
Social Welfare Facilities
Planned low rise to medium rise building.
Depending on detail design of building.
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have full south eastern to eastern views of
approximately 140m min, onto the Western
Tunnel Portal & Ventilation Buildings. The
sensitivity of this VSR is considered medium.
GIC9
General
Description
Animal Management Centre
Planned low rise building. Depending on detail
design of buildings.
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have partial south eastern views of
approximately 130m min, onto the Western
Tunnel Portal Building. The sensitivity of this
VSR is considered low.
GIC10
General
Description
Jordan Valley Box Culvert: DSD Desilting
Building & Pumping Station
Existing low rise to medium rise building.
Depending on detail design of building.
Government
/Institutional/
Community
Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
will have full south eastern – eastern views of
approximately 5m min onto the Western
Tunnel Portal & Ventilation Buildings The
sensitivity of this VSR is considered medium.
Operational
Phase
As defined for the Construction Phase
Eastern Works Area: N/A
Western Works Area: medium
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-41
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
GIC11A
General
Description
Hospital at Former Kai Tak South Apron
This planned VSR is proposed as one of three
planned medium-rise hospital buildings.
Government
/Institutional/
Community
Planned
(2018)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The future users have an
open view at varying levels of approximately
10m min. The Trunk Road T2 and associated
work areas are located to the northwest and
south east of the hospital site, with full views
directly upon the construction of the T2
Ventilation, Tunnel Portal Building. As no
existing buildings were previously within this
part of the South Apron area, the sensitivity of
this VSR is considered medium.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The future users have a
full northern view onto the project site at
varying levels of approximately 10m min, but
only those directly facing the project will be
affected. However, they will have an
alternative high amenity view to south of the
future metro park. The sensitivity of this VSR
is considered medium.
GIC11B
General
Description
Electrical & Mechanical Services
Department, Kowloon Bay Vehicle
Servicing Station/ Proposed Hospital at
former Kai Tak South Apron
At present the site is an Electrical &
Mechanical Services Department, Kowloon
Bay Vehicle Servicing Station. The current
building is planned for demolition, as the
future area is planned to house a medium-rise
hospital building.
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: Building is planned for
demolition. Date of Demolition unknown.
VSRs in this location will have full southern –
north western views of 10m min from the
Project in the construction phase. The
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-42
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
GIC11B
Operational
Phase
Eastern Works Area: N/A Government
/Institutional/
Community
Planned
(2021)
Western Works Area: The future users have a
full view at varying levels of approximately
10m min onto the onto the Western Tunnel
Portal & Ventilation Buildings, which are
located to the northwest of the Hospital site,
with full views directly upon the Ventilation,
Tunnel Portal Buildings but only those directly
facing the project will be affected. The
sensitivity of this VSR is considered medium.
GIC11C
General
Description
Derelict land and Proposed Hospital at
former Kai Tak South Apron
Currently the site is being used as a waste
holding area. The area has been designated as
a T2 works area until 2019 as per the
submitted CE38/2008 (HY) Land Requirement
Plan. On release of the land, this visually
sensitive receiver is proposed as one of three
planned medium-rise hospital buildings, with
direct northern and north-eastern views onto
the project site.
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: As this area is
designated as a site works area within the
Construction phase, it is not designated as a
VSR.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The future users have a
full view at varying levels of approximately
10m min onto the Western Tunnel Portal &
Ventilation Buildings. Which are located to the
northwest of the Hospital site, with full views
directly upon the T2 Ventilation & Tunnel
Portal Buildings but only those directly facing
the project will be affected. However, they will
have an alternative high amenity view to south
of the future metro park. The sensitivity of this
VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-43
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
GIC12
General
Description
Kwun Tong Public Transport Interchange
and Kwun Tong Ferry Pier
The area is an existing transportation hub for
buses, taxis and public ferries. The main
transportation hub is set back from the water’s
edge, and is partially blocked by existing
mature trees and the elevated Kwun Tong By-
pass. The ferry pier has open views onto
Victoria Harbour and the surrounding area.
Government
/Institutional/
Community
Existing
Construction
Phase
Eastern Works Area: There are full views of
approximately 450m min from the ferry pier
onto the Eastern Works Area. The sensitivity
of this VSR is considered low.
Western Works Area: Viewers within the
Ferry Pier will glimpse views of approximately
1250m min to the Western Works Area due to
obstruction by the existing breakwaters. The
VRS’s will have full southern views views of
approximately 80m min onto additional marine
traffic for construction and demolition material
within Victoria Harbour. The sensitivity of this
VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
R1
General
Description
Comprehensive Development Area, Ma Tau
Kok.
A planned medium to high rise building with
eastern views across Kowloon Bay and KTD:
The Runway Precinct on to the Western Works
Area. The value and quality of the existing
view is good.
Residential Planned
(2021)
Construction Eastern Works Area: N/A
Phase Western Works Area: Refer to O1 for
description.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: After the completion of
Kai Tak Development, the view will be
screened by the South Apron Development
Government. The VSR would glimpse eastern
views of approximately 1350m min, onto the
Trunk Road T2 Western Ventilation Building,
depending of detailed design and construction
of RE5, RE8, GIC7, GIC8, & GIC11C. The
sensitivity of this VSR is considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-44
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R2
General
Description
Kai Tak 2B: Comprehensive Development
Area
A planned medium to high rise building, on a
reclaimed site within the KTD: North Apron
Area. The Area is currently undergoing
various regeneration and construction projects.
On completion South eastern facing users will
be affected.
Residential Planned
(2021)
Construction
Phase Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of GIC6, GIC7, GIC9 & GIC10, VSRs
in this location will have a glimpse southern
view of approximately 1600m min towards the
Trunk Road T2 Western Tunnel Portal &
Ventilation Building. The sensitivity of this
VSR is considered low.
R3
General
Description
S/K22/13 Commercial Development
Planned VSR on the western edge of the South
Apron.
Residential
Planned
(2016)
Construction
Phase
Eastern Works Area: The users within the
upper floors will have partial south eastern
views of approximately 1740m min onto the
Eastern Works Area. The sensitivity of these
VSR’s is considered medium.
Western Works Area: VSRs in this location
will have partial north western – south eastern
view of approximately 10m min to the
Western Works Area. The sensitivity of this
VSR is considered high.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of O11 & GIC11B, VSRs in this
location will have a partial north western -
northern view of approximately 500m min to
the Western Tunnel Portal & Ventilation
Buildings. As the completion of the buildings
is proposed for completion in 2021. The
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-45
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R4
General
Description
S/K22/11 Comprehensive Development
Area
Planned VSR on the western edge of the South
Apron.
Residential
Planned
(2016)
Construction
Phase
Eastern Works Area: The users within the
upper floors will have partial south eastern
views of approximately 1740m min onto the
Eastern Works Area. The sensitivity of these
VSR’s is considered medium.
Western Works Area: Future viewers in this
VSR will have full western – eastern view of
approximately 10m min to the Western Works
Area. The sensitivity of this VSR is considered
high.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Future viewers in this
VSR will have a partial north western -
northern view of approximately 500m min to
the Western Tunnel Portal & Ventilation
Buildings, depending on the detail design and
construction of O11 & GIC11B. As the
completion of the buildings is proposed for
2021, the sensitivity of this VSR is considered
medium.
R5
General
Description
Kai Tak Runway Precinct Housing
Development
A row of medium rise residential
developments are planned on the northern
fringe of the KTD Runway Precinct.
Residential
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: depending on the detail
design and construction of GIC11A which is
planned to be completed by 2016, and R5,
RE8, GIC11C and the D4 Road Bridge, which
are planned for completion in 2021, the future
VSRs will glimpse north and north-western
views of approximately 400m min onto the
Western Tunnel Portal Building. The
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-46
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R6
General
Description
Laguna City
The existing view is an open view of Victoria
Harbour to the south west, typical industrial
area with medium rise industrial buildings to
the north west and typical urban residential
area to the north east. Only south and south
west facing users are affected.
Residential Existing
Construction
Phase
Eastern Works Area: The residents at mid to
upper level of this visual sensitive receiver
have a full south eastern sea view to the
Eastern Works Area of approximately 160m
min. The sensitivity of this VSR is considered
high.
Western Works Area: The residents at mid to
upper levels of this residential development
have an glimpse western to north western s sea
view to the Western Works Area of
approximately 1600m min. The sensitivity of
this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
R7
General
Description
Residential development at Cha Kwo Ling
Road
The existing view is of the decommissioned
open storage and cargo working area with a
backdrop of Victoria Harbour to the west and
vegetated hillsides to the east. Only west
facing users are affected.
Residential Existing
Construction
Phase
Eastern Works Area: VSR’s will have a full
view to the Eastern Works Area of
approximately 50m min. Only east facing
users are affected within the construction stage
of the project. The sensitivity of this VSR is
considered high.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-47
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R8
General
Description
Cha Kwo Ling Tsuen
This visual sensitive receiver shares similar
existing views with R3 but Victoria Harbour is
highly blocked by the decommissioned cargo
working area and roadside planting in front as
the residential complex is close to the ground
level.
Residential Existing
Construction
Phase
Eastern Works Area: The VSRs have a full
view of approximately 20m min to the Eastern
Works Area The sensitivity of this VSR is
considered high.
Western Works Area: N/A
Operational Eastern Works Area: N/A
Phase Western Works Area: N/A
R9
General
Description
Grand Waterfront, To Kwa Wan
Existing high rise building. The existing view
is a panorama view across Kowloon Bay and
over the Kai Tak development, which is
currently undergoing various demolition/site
clearance, infrastructure and construction
projects throughout the KTD. The residents of
this visual sensitive receiver have a full view
to the Western Works area, but only those
facing east to north east are affected. However,
they have views south to south east of Victoria
Harbour and the planned Metro Park.
Residential Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs will have a
glimpse view of approximately 1150m min to
the Western Works Area, depending on the
detailed design of RE4 & RE5. The sensitivity
of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE4, RE5, RE8, GIC7, GIC8 &
GIC11C, the VSRs would have a glimpse
eastern view of approximately 1400m min,
onto the Trunk Road T2 Western Ventilation
Building. The sensitivity of this VSR is
considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-48
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R10
General
Description
Wyler Gardens, To Kwa Wan
Existing medium to high rise building. The
existing view is a panorama view across
Kowloon Bay and over the Kai Tak
development, which is currently undergoing
various demolition/site clearance,
infrastructure and construction projects
throughout the KTD.
Residential Existing
Construction Eastern Works Area: N/A
Phase Western Works Area: VSRs in this location
will have a glimpse view of approximately
1250m min to the Western Works Area,
depending on detailed design of RE4 & RE5.
The sensitivity of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE4, RE5, RE8, GIC7, GIC8 &
GIC11, the VSRs would glimpse eastern views
of approximately 1500m min, onto the Trunk
Road T2 Western Ventilation Building. The
sensitivity of this VSR is considered low.
R11
General
Description
Sky Tower, Kowloon City
This is one of the tallest residential building
blocks in Ma Tau Kok and residents in mid
and upper levels currently enjoy a high quality
panoramic view of the surroundings. The
existing view is a panorama view across To
Kwa Wan, Kowloon Bay and over the Kai Tak
development, which is currently undergoing
various demolition/site clearance,
infrastructure and construction projects
throughout the KTD.
These VSRs are medium to high rise buildings
and residents in the mid to upper levels will
have a direct view to the Project Site.
Residential Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
have a glimpse eastern to south eastern view of
approximately 1550m min to the Western
Works Area, depending of detailed design of
RE4 & RE5. The sensitivity of this VSR is
considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-49
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R11
Operational
Phase
Eastern Works Area: N/A Residential Existing
Western Works Area: Depending on the detail
design of RE4, RE5, RE8, GIC7 & GIC11C,
the VSR would glimpse eastern to south
eastern views of approximately 1900m min,
onto the Trunk Road T2 Western Ventilation
Building. The sensitivity of this VSR is
considered low.
R12
General
Description
Sunrise Villas, To Kwa Wan
Existing medium to high rise building. The
existing view is a panorama view across
Kowloon Bay and over the Kai Tak
development, which is currently undergoing
various demolition/site clearance,
infrastructure and construction projects
throughout the KTD.
These VSRs are medium to high rise buildings
and residents in the mid to upper levels will
have a direct view to the Project Site.
Residential Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: VSRs in this location
have an eastern glimpse view of approximately
1600m min to the Western Works Area,
depending on detailed design of RE4 & RE5.
The sensitivity of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE5, RE8, GIC7, GIC8 & GIC11C
VSRs would glimpse eastern views of
approximately 2000m min onto the Trunk
Road T2 Western Ventilation Building. The
sensitivity of this VSR is considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-50
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R13
General
Description
Laguna Verde Complex, Hung Hom
Existing medium to high rise building. The
existing view is a panorama view across
Kowloon Bay and over the Kai Tak
development, which is currently undergoing
various demolition/site clearance,
infrastructure and construction projects
throughout the KTD.
Residential Existing
Construction
Phase
Eastern Works Area: There are glimpse views
of approximately 3800m min onto the Eastern
Works Area, though these views will be
obstructed by operation of the Kai Tak Cruise
Terminal. Although additional marine traffic
between the Eastern and Western sites will
have an indirect impact onto this VSR. As the
view onto the waterfront is currently
dominated by the cruise terminal and
associated marine traffic, the sensitivity of this
VSR is considered low.
Western Works Area: VSRs in this location
have glimpse eastern views of approximately
1620m min to the Western Works Area,
depending on the detail design and
construction of RE5 and GIC11A. The
sensitivity of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: depending on the detail
design and construction of O9, R5, RE6, RE8
& GIC11C, which are planned for completion
in 2021, this VSR, would have a glimpse
eastern view of approximately 1840m min,
onto the Trunk Road T2 Western Ventilation
Building. The sensitivity of this VSR is
considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-51
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R14
General
Description
Harbourfront Landmark & Harbour
Grand, Kowloon, Hung Hom
These buildings are the furthest away from the
Project. The developments house a high
number of residents. This existing VSR’s view
is a panorama across Victoria Harbour,
Kowloon Bay and over the Kai Tak
development and a direct view of the Kai Tak
Cruise Terminal.
Residential Existing
Construction
Phase
Eastern Works Area:
The VSR’s will have a glimpse eastern view of
approximately 3200m min view via the Kai
Tak Cruise Terminal onto the Eastern Works
Area. Though additional marine traffic
between the Eastern and Western sites will
have an indirect impact onto this VSR. As the
view is currently dominated by the cruise
terminal and associated marine traffic, the
sensitivity of this VSR is considered low.
Western Works Area: Depending on the detail
design of RE5, & GIC11A the VSR would
glimpse a north eastern view of approximately
2110m min, onto the Trunk Road T2 Western
Ventilation Building. The sensitivity of this
VSR is considered low.
Operational Eastern Works Area: N/A
Phase Western Works Area: Depending on the detail
design of O9, R5, RE6, RE8, GIC7 & GIC11C
the VSR would glimpse north eastern views of
approximately 2000m min onto the Trunk
Road T2 Western Ventilation Building. The
sensitivity of this VSR is considered low.
R15
General
Description
Kai Tak 2B Housing Development
A planned medium to high rise building, on a
reclaimed site within the KTD: North Apron
Area. The Area is currently undergoing
various regeneration and construction projects.
On completion South eastern facing users will
be affected.
Residential Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-52
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R15
Operational
Phase
Eastern Works Area: N/A Residential Planned
(2021) Western Works Area: Depending on the detail
design of GIC6, GIC7, GIC9 & GIC10, future
viewers in this VSR will have a glimpse
southern view of approximately 1550mm min
towards the Trunk Road T2 Western Tunnel
Portal & Ventilation Building. The sensitivity
of this VSR is considered low.
R16
General
Description
Kai Tak 1L & 1K Housing Development
Planned medium to high rise building. South
eastern facing users will be affected.
Residential Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of GIC6, GIC9 & GIC10, VSRs in this
location will have a partial southern view of
approximately 1060m min towards the Trunk
Road T2 Western Tunnel Portal & Ventilation
Building. The sensitivity of this VSR is
considered low.
R17
General
Description
Kai Tak 1H & 1I Housing Development
Planned medium to high rise building. South
eastern facing users will be affected. Views of
Western Works Area are obscured by the
Kowloon Bay commercial area.
Residential Planned
(2016)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The Development is
planned to be operational by 2016. VSRs in
this location will have a partial south eastern
view of approximately 1050m min towards the
Western Works Area. The sensitivity of this
VSR is considered low.
Operational
Phase Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of GIC6, GIC9 & GIC10, VSRs in this
location will glimpse south eastern views of
approximately 1100m min towards the Trunk
Road T2 Western Tunnel Portal & Ventilation
Building. The sensitivity of this VSR is
considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-53
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
R18
General
Description
Hing Yan Street Residential Block
Existing medium rise building. South eastern
facing VSRs will be affected. Views of the
Western Works Area are obscured by the
Kowloon Bay commercial area.
Residential Existing
Construction Eastern Works Area: N/A
Phase Western Works Area: VSRs in this location
will have an east to north east glimpse view of
approximately 1200m min to the Western
Works Area, depending of detailed design of
RE5. The sensitivity of this VSR is considered
low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Refer to R1 For details
R19
General
Description
Yau Tong Bay Development
Planned medium to high rise building mixed
use waterfront development.
Residential/
Occupational
Planned
(2018)
Construction
Phase
Eastern Works Area: VSRs in this location
will have a partial view of approximately
300m min to the Eastern Works area The
sensitivity of this VSR is considered high.
Western Works Area: N/A
Operational Eastern Works Area: N/A
Phase Western Works Area: N/A
E1
General
Description
Ma Tau Kok: Regional Open Space
At present, proposed development is being
used as a Wilson Car park. The existing view
is a panorama at pedestrian level across
Kowloon Bay and over the Kai Tak
development, which is currently undergoing
various demolition/site clearance,
infrastructure and construction projects
throughout the KTD.
Recreational Planned
(2014)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE4 & RE5, Pedestrians at ground
level within this VSR will glimpse eastern to
north eastern views of approximately 1800m
min, onto the Western Works Area The
sensitivity of this VSR is considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-54
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
E1
Operational
Phase
Eastern Works Area: N/A Recreational Planned
(2014) Western Works Area: Depending on the detail
design of RE8, & GIC11C, pedestrians at
ground level within this VSR will glimpse
eastern to north eastern views of
approximately 1650m min onto the Western
Works Area. The sensitivity of this VSR is
considered low.
RE2
General Description
Hoi Sham Park, Ma Tau Kok
Existing public waterfront park. At pedestrian
level there are good panoramic views across
Kowloon Bay and over the Kai Tak
development, which is currently undergoing
various demolition/site clearance,
infrastructure and construction projects
throughout the KTD.
Recreational Existing
Construction Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE4 & RE5, pedestrians at ground
level within this VSR will glimpse eastern to
north eastern views of approximately 1500m
min, onto the Western Works Area The
sensitivity of this VSR is considered low.
Operational Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE8 & GIC11C Pedestrians at
ground level within this VSR will have a
glimpse eastern to north eastern view of
approximately 1600m min, onto the Trunk
Road T2 Western Ventilation Building. The
sensitivity of this VSR is considered low.
RE3
General Description
Current & Future Waterfront Promenade,
Ma Tau Kok
Existing waterfront park with good open south
eastern to north western views onto Victoria
Harbour and KTD. Promenade will later be
extended and connected to the Kia Tak
Development.
Recreational Existing/ Planned
(2021)
Construction Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE4 & RE5, Pedestrians at ground
level within this VSR will glimpse south
eastern to north western views of
approximately 1200m min onto the Western
Works Area. The sensitivity of this VSR is
considered low.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-55
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
RE3
Operational
Phase
Eastern Works Area: N/A Recreational Existing/ Planned
(2021) Western Works Area: Depending on the detail
design of RE8, GIC7, GIC8 & GIC11C
Pedestrians at ground level within this VSR
will glimpse south eastern to north western
views of approximately 1300m min, onto the
Trunk Road T2 Western Ventilation Building.
The sensitivity of this VSR is considered low.
RE4
General
Description
Planned Multi-Purpose Stadium Complex –
Park
Viewers in this future VSRs will mainly be
focused inside the stadium complex and their
views to the proposed Trunk Road T2 Site
could be potentially screened by landscaping
or other structures.
Recreational Planned
(2016-
2020)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: Pedestrians at ground
level within this VSR will have partial south
eastern views of approximately 1000m min
onto the Western Works Area. The sensitivity
of this VSR is considered low.
Operational
Phase Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE8, GIC7, GIC8 & GIC11C.
Pedestrian VSRs will glimpse eastern to south
eastern views of approximately 1000m min
onto the Trunk Road T2 Western Ventilation
Building. The sensitivity of this VSR is
considered low.
RE5
General
Description
Kai Tak Runway Precinct: Metro Park
Proposed waterfront public park. This visual
sensitive receiver has north eastern and eastern
views into the site via the L18 Road. As per
the RODP the date of completion is under
review.
Recreational Planned
(2017)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: Pedestrians at ground
level within this VSR will have partial eastern
to south eastern views of approximately 300m
min to the Western Works Area. The
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-56
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
RE5
Operational
Phase
Eastern Works Area: N/A Recreational Planned
(2017) Western Works Area: Depending on the detail
design of RE8, GIC7, GIC8 & GIC11C
Pedestrians at ground level within this VSR
will have a glimpse of eastern to south eastern
views of approximately 400m min, onto the
Trunk Road T2 Western Ventilation Building.
The sensitivity of this VSR is considered
medium.
RE6
General
Description
Kai Tak Runway Precinct Northern
Promenade
Proposed waterfront public promenade.
Recreational Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE8, GIC7, GIC8 & GIC11C and
the D4 road bridge, pedestrian VSRs at ground
level will have partial south eastern, north and
north-western views of approximately 330m
min onto the Western Tunnel Portal Building.
The sensitivity of this VSR is considered
medium.
RE7
General
Description
Kai Tak Runway Park
Proposed waterfront public park. The park is
built in 2 phases:
1st phase, planned 2013
2nd
phase is under review. Details unknown.
Recreational Planned
(2013)
Construction
Phase
Eastern Works Area: Pedestrians VSRs at
ground level will have full south eastern views
of approximately 700m min. Additional
marine traffic for construction and demolition
material will have an indirect impact onto this
VSR. The sensitivity of this VSR is considered
medium.
Western Works Area: Pedestrian VSRs will
have a full northern view of approximately
350m min to the Trunk Road T2 Works Area.
The sensitivity of this VSR is considered
medium.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-57
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
RE8
General
Description
Kai Tak South Apron: Southern
Promenade
Proposed waterfront public promenade.
Recreational Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of RE8, GIC7, GIC11A & GIC11C and
the D4 road bridge, pedestrian VSRs will have
partial north and north eastern views of
approximately 100m min onto the Western
Ventilation Building and the Tunnel Portal
Building. The sensitivity of this VSR is
considered medium.
RE9
General
Description
Kai Tak South Apron: Kowloon Bay Square
Planned Public Waterfront Park with proposed
MTR/Light Rail Station (station details to be
finalised). As per the RODP of KTD, the
planned park is currently under review, details
unknown.
Recreational Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of O11, O12, GIC11A & GIC11C,
future VSRs will have partial northern and
north western of approximately 450m min to
the Western Tunnel Portal & Ventilation
Buildings. The sensitivity of this VSR is
considered medium.
RE10
General
Description
Kai Tak South Apron: Amenity Area
Undesignated Amenity Area, adjacent to the
Western Tunnel Portal & Ventilation
Buildings.
Recreational Planned
(2021)
Construction Eastern Works Area: N/A
Phase Western Works Area: Area is designated to be
within site boundary area - N/A.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Pedestrian VSRs would
have full north western views of approximately
5m min, onto the Trunk Road T2 Western
Tunnel Portal & Ventilation Buildings. The
sensitivity of this VSR is considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-58
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
RE11
General
Description
Enterprise Square: CIC Zero Carbon
Building
Existing Public Park. This VSR has slight
south western views towards the project site.
Views are screened mostly by the elevated
Kwun Tong By-pass, Kai Fuk Road and
roadside amenity planting.
Recreational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of GIC10, pedestrian VSRs would
glimpse southern views of approximately
150m min onto the Trunk Road T2 Western
Tunnel Portal & Ventilation Buildings. The
sensitivity of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Depending on the detail
design of GIC10, pedestrian VSRs would
glimpse southern views of approximately
150m min onto the Trunk Road T2 Western
Tunnel Portal & Ventilation Buildings. The
sensitivity of this VSR is considered low.
RE12
General
Description
Hoi Bun Road Park
Existing Public Park. Views of the Project to
this VSR will be partially blocked by the
elevated Kwun Tong By-pass and existing
trees inside the park.
Recreational Existing
Construction
Phase
Eastern Works Area: There are no views onto
the Eastern Works Area, though VSRs may
glimpse views of approximately 300m min to
additional marine traffic for construction and
demolition material between the eastern and
western sites. This may have an indirect
impact. The sensitivity of this VSR is
considered low.
Western Works Area: The view to the Project
is partially blocked by the elevated Kwun
Tong By-pass. Only south west facing VSRs
are affected. VSRs will glimpse south western
to north western views of approximately 350m
min to the Western Works Area. The
sensitivity of this VSR is considered low.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-59
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
RE13
General
Description
Kwun Tong Promenade (Existing )
Existing Public Waterfront Promenade Park
with north western views onto the project site.
Recreational Existing
Construction
Phase
Eastern Works Area: There are no views onto
the Eastern Works Area, though VSRs will
have full views of approximately 200m to
additional marine traffic for construction and
demolition material between the eastern and
western sites. This will have an indirect
impact. The sensitivity of this VSR is
considered low.
Western Works Area: Pedestrian VSRs would
have full north western to western views of
approximately 750m min onto the Western
Works Area. VSRs will have full views of
approximately 200m to additional marine
traffic for construction and demolition material
between the eastern and western sites. This
will have an indirect impact. The sensitivity of
this VSR is considered medium.
Operational Eastern Works Area: N/A
Phase Western Works Area: N/A
RE14
General
Description
Kwun Tong Promenade (Planned)
This is a linear strip of decommissioned land
on the Kwun Tong Waterfront awaiting
redevelopment. This area will shortly become
a construction site for the new promenade,
hence VSRs are considered to be occupational
but will become recreational in 2021.
Occupational/
Recreational Planned
(2021)
Construction
Phase
Eastern Works Area: There are no views onto
the Eastern Works Area, VSRs will have full
views of approximately 200m min to
additional marine traffic for construction and
demolition material between the eastern and
western site. This is considered an indirect
impact. The sensitivity of this VSR is
considered low.
Western Works Area: Viewers within this
VSR will have full south western to north
western views of approximately 200m min to
the Western Works Area. The sensitivity of
this VSR is considered low.
Operational
Phase Eastern Works Area: N/A
Western Works Area: N/A.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-60
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
RE15
General
Description
Laguna Park
Existing Public Park. Views of the Project in
this location are partially blocked by the
elevated Kwun Tong By-pass, Kwun Tong
Nullah and existing trees inside the park.
Recreational Existing
Construction
Phase
Eastern Works Area: Pedestrian VSRs would
glimpse south eastern views of approximately
300m min onto the Eastern Works Area. The
sensitivity of this VSR is considered low.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A.
T1
General
Description
Kwun Tong By-pass and Kai Fuk Road
These are elevated and at-grade roads. The
existing views are of the former Kai Tak South
Apron, Kwun Tong Typhoon Shelter, Victoria
Harbour to the west and typical industrial area
to the east. VSRs travelling on these roads will
have direct sea views to the Project which in
part are blocked by roadside trees, shrub
planting and noise barriers.
Travelling Existing
Construction
Phase
Eastern Works Area: VSRs travelling on these
roads will have a glimpse south eastern and
eastern view of the Eastern Works Area. The
sensitivity of this VSR is considered medium.
Western Works Area: VSRs travelling on these
roads will have a full open view of
approximately 5m min to the Western Works
Area. The sensitivity of this VSR is considered
medium.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The travellers of this
visual sensitive receiver have a full view of
approximately 5m onto the Trunk Road T2
Western Tunnel Portal & Ventilation
Buildings. The sensitivity of this VSR is
considered medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-61
VSR
ID. No. Visually Sensitive Receivers
Type of
VSRs Status
T2
General
Description
Cha Kwo Ling Road
This is a road with existing views of the
former open storage and cargo working area to
the west and low rise residential buildings with
a vegetated hillside backdrop to the east.
Travelling Existing
Construction
Phase
Eastern Works Area: VSRs on this road will
have full views of the Project which in parts
will be blocked by roadside planting, fences,
walls, and the former cargo working area. The
sensitivity of this VSR is considered medium.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
T3
General
Description
Harbour Traffic at Victoria Harbour
VSRs in harbour traffic include cruise liners,
ferries and commercial boats, and will have
open sea views of the Project. The existing
view is of a water body with development as a
back drop.
Travelling Existing
Construction
Phase
Eastern Works Area: VSRs will have full open
views to the Eastern Works Area. The
sensitivity of this VSR is considered medium.
Western Works Area: VSRs will have full
open views of approximately 5m min to the
Western Works Area. The sensitivity of this
VSR is considered medium.
Operational Eastern Works Area: N/A
Phase Western Works Area: VSRs will have glimpse
views of approximately 100m onto the Project
due to the proposed O11, O12, GIC11A
GIC11C, R3, R4, RE8 & RE9 developments.
The sensitivity of this VSR is considered
medium.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-62
Table 9.5 Assessments of the Degree of Sensitivity: Construction Phase (Eastern Works
Area)
VSR
ID. No.
Number
of VSRs
(Many/
Medium/
Few)
Quality
of
Existing
View
(Good/
Fair/
Poor)
Availability
and
Amenity
Value of
Alternative
View
(High/
Medium/
Low)
Minimum
Distance
between
VSRs and
Impact
Sources
(m)
Duration
or
Frequency
of View
(Long/
Medium/
Short)
Degree
of
Visibility
(Full/
Partial/
Glimpse/
(M))*
Sensitivity
(Low,
Medium,
High)
O10 Many Fair Medium 1100 Medium Partial Low
O14 Medium Fair Medium 1800 Medium Glimpse Low
O16 Medium Fair Medium 1800 Medium Glimpse Low
O17 Medium Fair Medium 200 Medium Partial
(M) Low
O18 Many Fair Medium 360 Medium Glimpse Low
O19 Few Fair Medium 160 Medium Partial Low
O20 Medium Fair Medium 5 Medium Full Medium
O22 Few Fair Low 900 Medium Partial Low
GIC12 Medium Fair Medium 450 Medium Full (M) Low
R3 Many Fair Medium 1740 Long Partial Medium
R4 Many Fair Medium 1740 Long Partial Medium
R6 Many Fair Medium 160 Long Full High
R7 Many Fair Medium 50 Long Full High
R8 Many Fair Medium 20 Long Full High
R13 Many Fair High 3800 Long Glimpse Low
R14 Many Fair High 3200 Long Glimpse Low
R19 Many Fair Medium 300 Long Partial High
RE7 Medium Fair High 700 Medium Full Medium
RE12 Medium Poor Medium 300 Medium Glimpse
(M) Low
RE13 Medium Poor High 200 Medium Full
(M)
Low
RE14 Medium Poor High 200 Medium Full (M) Low
RE15 Medium Fair Medium 300 Medium Glimpse Low
T1 Many Fair Medium 5 Short Glimpse Medium
T2 Many Fair Medium 5 Short Full Medium
T3 Many Fair Medium 5 Short Full Medium
Note: *Degree of Visibility (M) denotes:- No direct views onto Works Area; views are onto additional marine traffic
for construction and demolition materials
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-63
Table 9.6 Assessments of the Degree of Sensitivity: Construction Phase (Western Works
Area)
VSR
ID. No.
Number
of VSRs
(Many/
Medium/
Few)
Quality
of
Existing
View
(Good/
Fair/
Poor)
Availability
and
Amenity
Value of
Alternative
View
(High/
Medium/
Low)
Minimum
Distance
between
VSRs and
Impact
Sources
(m)
Duration
or
Frequency
of View
(Long/
Medium/
Short)
Degree
of
Visibility
(Full/
Partial/
Glimpse/
(M))*
Sensitivity
(Low,
Medium,
High)
O1 Medium Fair High 1150 Medium Glimpse Low
O2 Medium Fair High 1350 Medium Glimpse Low
O3 Medium Fair Medium 700 Medium Partial Low
O4 Medium Fair Medium 400 Medium Partial Medium
O5 Many Fair Medium 200 Medium Partial Medium
O6 Medium Fair Medium 120 Medium Full Medium
O7 Many Fair Medium 70 Medium Full Medium
O8 Few Fair Low 80 Medium Glimpse Low
O10 Many Fair High 500 Medium Partial Medium
O12 Few Fair Low 5 Medium Full Low
O13 Medium Fair Medium 200 Medium Partial Low
O14 Medium Fair Medium 20 Medium Full Medium
O16 Medium Fair Medium 300 Medium Partial Medium
O17 Many Fair Medium 320 Medium Partial Low
O18 Many Fair Medium 750 Medium Partial Low
O19 Few Fair Medium 1400 Medium Glimpse Low
GIC1 Few Fair High 1000 Medium Partial Low
GIC3 Few Poor Medium 600 Medium Glimpse Low
GIC4 Few Poor Medium 690 Medium Glimpse Low
GIC5 Few Poor Medium 760 Medium Glimpse Low
GIC10 Few Fair Low 5 Medium Full Medium
GIC11A Medium Fair Low 10 Medium Full Medium
GIC11B Few Fair Low 10 Medium Full Medium
GIC12 Medium Fair Medium 1250 Medium Glimpse Low
R3 Medium Fair Medium 10 Long Partial High
R4 Medium Fair Medium 10 Long Full High
R6 Medium Fair Medium 1600 Long Glimpse Low
R9 Medium Fair High 1150 Long Glimpse Low
R10 Medium Fair High 1250 Long Glimpse Low
R11 Medium Fair Medium 1550 Long Glimpse Low
R12 Medium Fair High 1600 Long Glimpse Low
R13 Many Fair High 1620 Long Glimpse Low
R14 Many Fair High 2110 Long Glimpse Low
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-64
VSR
ID. No.
Number
of VSRs
(Many/
Medium/
Few)
Quality
of
Existing
View
(Good/
Fair/
Poor)
Availability
and
Amenity
Value of
Alternative
View
(High/
Medium/
Low)
Minimum
Distance
between
VSRs and
Impact
Sources
(m)
Duration
or
Frequency
of View
(Long/
Medium/
Short)
Degree
of
Visibility
(Full/
Partial/
Glimpse/
(M))*
Sensitivity
(Low,
Medium,
High)
R17 Many Fair Medium 1050 Long Partial Low
R18 Medium Fair Medium 1200 Long Glimpse Low
RE1 Medium Fair High 1800 Medium Glimpse Low
RE2 Medium Fair High 1500 Medium Glimpse Low
RE3 Medium Fair High 1200 Medium Glimpse Low
RE4 Medium Fair High 1000 Medium Partial Low
RE5 Medium Fair High 300 Medium Partial Medium
RE7 Medium Fair High 350 Medium Full Medium
RE11 Medium Fair Low 150 Medium Glimpse Low
RE12 Medium Fair Medium 350 Medium Glimpse
(M) Low
RE13 Medium Fair High 750 Medium Full Medium
RE14 Medium Fair Medium 200 Medium Full Low
T1 Many Fair Medium 5 Short Full Medium
T3 Many Fair Medium 5 Short Full Medium
Note: *Degree of Visibility (M) denotes:- No direct views onto Works Area; views are onto additional marine traffic
for construction and demolition materials
Table 9.7 Assessments of the Degree of Sensitivity: Operation Phase (Western Works
Area)
VSR
ID. No.
Number
of VSRs
(Many/
Medium/
Few)
Quality
of
Existing
View
(Good/
Fair/
Poor)
Availability
and
Amenity
Value of
Alternative
View
(High/
Medium/
Low)
Minimum
Distance
between
VSRs and
Impact
Sources
(m)
Duration
or
Frequency
of View
(Long/
Medium/
Short)
Degree
of
Visibility
(Full/
Partial/
Glimpse/
M=V)
Sensitivity
(Low,
Medium,
High)
O2 Many Fair Medium 1450 Medium Glimpse Low
O3 Medium Fair Medium 650 Medium Partial Low
O4 Medium Fair High 500 Medium Partial Low
O5 Medium Fair High 250 Medium Partial Low
O6 Medium Fair High 140 Medium Partial Medium
O7 Many Fair High 70 Medium Partial Medium
O8 Few Fair Low 80 Medium Glimpse Low
O9 Medium Fair High 500 Medium Glimpse Low
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-65
VSR
ID. No.
Number
of VSRs
(Many/
Medium/
Few)
Quality
of
Existing
View
(Good/
Fair/
Poor)
Availability
and
Amenity
Value of
Alternative
View
(High/
Medium/
Low)
Minimum
Distance
between
VSRs and
Impact
Sources
(m)
Duration
or
Frequency
of View
(Long/
Medium/
Short)
Degree
of
Visibility
(Full/
Partial/
Glimpse/
M=V)
Sensitivity
(Low,
Medium,
High)
O10 Many Fair High 1200 Medium Glimpse Medium
O11 Medium Fair Medium 320 Medium Partial Medium
O12 Few Fair Medium 350 Medium Partial Low
O13 Medium Fair High 380 Medium Partial Medium
O14 Medium Fair High 320 Medium Partial Medium
O16 Medium Fair Medium 650 Medium Glimpse Low
O17 Medium Fair Medium 650 Medium Glimpse Low
GIC1 Few Fair Medium 1200 Medium Glimpse Low
GIC2 Few Fair Medium 900 Medium Glimpse Low
GIC3 Few Fair Medium 640 Medium Glimpse Low
GIC4 Few Fair Medium 800 Medium Glimpse Low
GIC5 Few Fair Medium 760 Medium Glimpse Low
GIC6 Medium Fair Medium 400 Medium Partial Medium
GIC7 Medium Fair Medium 150 Medium Partial Medium
GIC8 Medium Fair Medium 140 Medium Full Medium
GIC9 Few Fair Medium 130 Medium Partial Low
GIC10 Few Good Medium 5 Medium Full Medium
GIC11A Medium Good Medium 10 Medium Full Medium
GIC11B Medium Good Medium 10 Medium Full Medium
GIC11C Medium Good Medium 10 Medium Full Medium
R1 Medium Good High 1350 Long Glimpse Low
R2 Medium Fair Medium 1600 Long Glimpse Low
R3 Medium Fair High 500 Long Partial Medium
R4 Medium Fair High 500 Long Partial Medium
R5 Many Fair Medium 400 Long Glimpse Medium
R9 Medium Fair High 1400 Long Glimpse Low
R10 Medium Fair High 1500 Long Glimpse Low
R11 Medium Fair Medium 1900 Long Glimpse Low
R12 Medium Fair Medium 2000 Long Glimpse Low
R13 Many Fair High 1840 Long Glimpse Low
R14 Many Fair High 2000 Long Glimpse Low
R15 Many Fair Medium 1550 Long Glimpse Low
R16 Many Fair Medium 1060 Long Partial Low
R17 Many Fair Medium 1100 Long Glimpse Low
RE1 Medium Fair High 1650 Medium Glimpse Low
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-66
VSR
ID. No.
Number
of VSRs
(Many/
Medium/
Few)
Quality
of
Existing
View
(Good/
Fair/
Poor)
Availability
and
Amenity
Value of
Alternative
View
(High/
Medium/
Low)
Minimum
Distance
between
VSRs and
Impact
Sources
(m)
Duration
or
Frequency
of View
(Long/
Medium/
Short)
Degree
of
Visibility
(Full/
Partial/
Glimpse/
M=V)
Sensitivity
(Low,
Medium,
High)
RE2 Medium Fair High 1600 Medium Glimpse Low
RE3 Medium Fair High 1300 Medium Glimpse Low
RE4 Medium Fair High 1000 Medium Glimpse Low
RE5 Medium Fair High 400 Medium Glimpse Medium
RE6 Medium Fair High 330 Medium Partial Medium
RE8 Medium Fair High 100 Medium Partial Medium
RE9 Medium Fair High 450 Medium Partial Medium
RE10 Medium Fair Medium 5 Medium Full Medium
RE11 Medium Fair Low 150 Medium Glimpse Low
T1 Many Fair Medium 5 Short Full Medium
T3 Many Fair Medium 100 Short Glimpse Medium
9.7 Landscape Impact Assessment
9.7.1 Potential Sources of Impacts
9.7.1.1 The nature and scope of works are described in detail in Section 3. Sources of impacts
of Trunk Road T2 during the construction phase would include:
9.7.2 Construction Works (Direct Impacts)
Construction of a dual two-lane trunk road approximately 0.3km long at grade
section and about 2.7 km in the form of a tunnel and Tunnel Portal building;
Construction of Ventilation building, administration buildings and a traffic control
and surveillance system; and
Construction of associated civil, electrical, mechanical, landscape and
environmental protection and mitigation works.
9.7.3 Construction Site Operation (Indirect Impacts)
Stockpiling of excavated and building materials and storage of construction
equipment;
Minor demolition of existing facilities;
Temporary noise mitigation measures (e.g. barriers and enclosures);
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-67
Contractor’s temporary works areas, including site offices temporary barging
point, haulage between T2 sites, and parking areas.
9.7.4 Sources of Impacts in the Operation Phase
Dual two-lane trunk road of approximately 0.3km long at grade and 2.7km in the
form of a tunnel;
The completed ventilation and administration buildings; and
The completed associated civil, electrical, mechanical, landscape and
environmental protection and mitigation works.
9.7.5 Impact on Existing Trees
9.7.5.1 Within the 100m works boundary area, there are an approximately 605 trees.
9.7.5.2 128 trees are recorded within Trunk Road T2 area and 10m offset buffer zone from the
works limit. No registered Old and Valuable Tree, protected or endangered species are
recorded. 30 trees will be protected from the impact of the proposed T2 development,
31 trees are recommended for transplantation, and 67 trees unsuitable for transplanting
are recommended for felling. In total 152 new trees of minimum 75mm DBH are
proposed to compensate the loss of trees in T2 area. Refer to Figures 9.10.1 and 9.10.2.
9.7.5.3 Compensatory tree planting will be incorporated along all roadside amenity areas
affected by the construction works. The required numbers and locations of
compensatory trees shall be determined and agreed with the Government during the
Tree Removal Application under ETWB TCW No. 3/2006.
Table 9.8 Summary of Proposed Treatment of Trees (Trunk Road T2 Works
Area)
Proposed Treatment Quantity
Total tree quantity 128
Retain 30
Transplant 31
Fell 67
Accumulated loss of DBH (m) 114.00
9.7.5.4 Table 9.8 summarise the number of trees affected by the whole Trunk road T2 works
and Table 9.9 summaries the affected trees with respect to the Western and Eastern
Works Areas.
Table 9.9 Summary of Proposed Treatment of Trees (Individual Works Areas)
Proposed Treatment Western Works Area Eastern Works Area Total
Total tree quantity 127 1 128
Retain 30 0 30
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-68
Proposed Treatment Western Works Area Eastern Works Area Total
Transplant 31 0 31
Fell 66 1 67
Accumulated loss of
DBH(m) 113.865 0.135 114
9.7.6 Impact on Existing Passive Amenity Areas
9.7.6.1 The only area affected by construction of the Trunk Road T2 and associated buildings is
the amenity area next to Kwun Tong By-pass.
9.7.7 Degree of Compatibility of the Project and Associated Works
9.7.7.1 The Trunk Road T2, ventilation and tunnel portal buildings are scheduled to be
commissioned in 2020 and operational by 2021 within the Kai Tak South Apron
Development. Currently the land is mainly derelict with areas allocated for temporary
storage and on-going infrastructure projects. The proposed construction within the Kai
Tak Development covers 3 main areas: The North Apron, South Apron and Runway
Precinct. As per the KTD RODP, Trunk Road T2 will be operational at approximately
the same time as the surrounding South Apron. The KTD agency has provided a
landscape masterplan document for future Kai Tak Development to adhere to. As the
area is intended to have a cohesive design approach, Trunk Road T2 and associated
works will be designed in harmony with the surrounding context.
9.7.7.2 With the completion of Trunk Road T2 and associated works, the area of T2 will be
reinstated into a Kai Tak South: Amenity Area, with provision of street trees, shrubs
and ground cover planting. A green design approach is provided for the ventilation
building, tunnel portal and refuge collection buildings, including green walls and
stepped planted berms, which will minimise the visual impact and blend the
development into the design of the proposed surrounding landscape.
9.7.7.3 Tables 9.10 and 9.11 present the impacts on landscape resources and character areas
respectively. Magnitude of change is considered to be small to negligible at the
operation phase.
9.7.8 Nature and Magnitude of Unmitigated Landscape Impacts in Construction and
Operation Phases
9.7.8.1 The magnitude of impacts, before mitigation measures, on LRs and LCA’s in the
construction and operation phases are described below and tabulated in Tables 9.10 to
9.11.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-69
Table 9.10 Impacts on Landscape Resources of the Proposed Works and their Magnitude of Change
LR
ID No.
Landscape
Resources
Size of LR
(m2)
Description of Impacts Sources of impact Reversibility Scale of
Development
Compatibility
with
Surrounding
Landscape
Duration of impact (Low,
Medium, High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Construction Operation Construction Operation
LR6 Amenity
Area (Kai
Fuk Road /
Kwun Tong
By-pass)
11,010 Within the portion of LR6 where impact
is expected, of the 81 nos. trees, 18 trees
will be retained and protected, 21 trees
will be transplanted and 42 trees will be
felled. Approximately 3,620 square
metres of planting area would be lost by
construction of building and temporary
works and associated impacts.
Approximately 1,250 square metres of
planting area will be permanently lost by
the construction of the Ventilation
Building.
Construction of
ventilation building,
Temporary storage and
stockpiling area.
No
Large
Low
Medium
High
Large
Large
LR8 Derelict /
Disturbed
Land (KTD
South
Apron)
208,440 The T2 Western Works Area is currently
an area of approximately 75,300 square
metres of hard standing which will be
temporarily lost in the construction
phase.
8,500 square metres of hard standing will
be lost by the construction of the Tunnel
Portal & Ventilation Buildings.
Approximately 46 nos. trees are recorded.
10 nos. of trees will be transplanted and
24 nos. trees unsuitable for transplanting
are recommended to be felled. The
remaining 12 nos. trees will be protected
on site. In addition, two planting areas
containing 159 square meters will be lost.
Impacts due to the construction of cut and
cover tunnel, underwater tunnel, minor
demolition works of existing facilities,
temporary traffic arrangement, temporary
Storage and stock piling, temporary
barging point and associated impacts.
Temporary Storage
area and site office,
work site for proposed
temporary traffic
arrangement,
temporary storage and
stock piling area,
temporary barging
point.
Construction of
Ventilation Building,
Tunnel Portal
Buildings,
construction of
depressed road,
construction of cut and
cover tunnel,
construction of
underwater tunnel,
minor demolition
works of existing
facilities.
No
Large
Medium
Medium
High
Large
Large
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-70
LR
ID No.
Landscape
Resources
Size of LR
(m2)
Description of Impacts Sources of impact Reversibility Scale of
Development
Compatibility
with
Surrounding
Landscape
Duration of impact (Low,
Medium, High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Construction Operation Construction Operation
LR12 Water Body
(Kwun Tong
Typhoon
Shelter)
315,320 Barges operating between 07.00 and
19.00.
Impacts due to the
construction of
underwater tunnel and,
temporary barging
point.
The temporary barging
point has a vertical
seawall face and no
temporary facilities
would be needed to be
constructed above the
sea. It will be consist
of a one vehicle
unloading ramp and a
fully enclosed
conveyor belt
unloading chute from
LR8
Yes Large Low Medium
N/A Small Negligible
LR16 Derelict /
Disturbed
Land
Proposed as
Cha Kwo
Ling
Promenade
Park by
Others (Cha
Kwo Ling
Former
Public Cargo
Working
Area)
27,020 1 tree to be felled.
Impacts due to the additional construction
works traffic in area and views onto
Trunk Road T2 Western Works Area.
An approximate area of 21,500 square
metres of hard standing will be temporary
lost for the Eastern Works Area site
offices.
Temporary Storage
area and site office,
Temporary vehicular
haulage from Trunk
Road T2 Eastern
Works Area to T2
Western Works Area.
Yes
Large
High
Medium
N/A
Intermediate
Negligible
Notes: The duration of impacts will be from 2016 to 2020 for both Construction Stages of the Eastern and Western areas.
Only Landscape Resources that are impacted are discussed.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-71
Table 9.11 Impacts on Landscape Character Areas of the Proposed Works and their Magnitude of Change
LCA
ID No.
Landscape
Resources
within the
LCA
Size of LR
(m2)
Description of Impacts Sources of Impact Reversibility Scale of
development
Compatibility
with
Surrounding
Landscape
Duration of impact Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Construction Operation Construction Operation
LCA1 LR8, LR10
& LR11
210,410 The Western Works Area site boundary is
approximately 75,300 square metres of
hard standing. This area will be
temporarily lost throughout the
construction phase. 8,500 square metres of hard will be lost
by the construction of the Tunnel Portal &
Ventilation Buildings.
Within LR8 and LR11, approximately 71
nos. trees are recorded.
Within the portion of LR8 where impact
is expected, approximately 46 nos. trees
are recorded. 10 nos. of trees will be
transplanted and 24 nos. trees unsuitable
for transplanting are recommended to be
felled. The remaining 12 nos. trees will be
protected on site. In addition, two planting
areas containing 159 square meters will be
lost. Impacts due to the construction of cut and
cover tunnel, underwater tunnel, minor
demolition works of existing facilities,
temporary traffic arrangement, temporary
Storage and stock piling, temporary
barging point and associated impacts.
Temporary storage
area and site office,
work site for proposed
temporary traffic
arrangement,
temporary storage and
stock piling area,
temporary barging
point.
Construction of
Ventilation and Tunnel
Portal Buildings,
construction of
depressed road,
construction of cut and
cover tunnel,
construction of
underwater tunnel,
minor demolition
works of existing
facilities.
No
Large
Medium
Medium
High
Large
Large
LCA3 LR1, LR5,
LR6, LR7 &
LR14
40,320 Within LR1, LR5, LR6, LR7 & LR14,
approximately 275 nos. trees are recorded.
Within the portion of LR6 where impact
is expected, 18 trees will be retained and
protected, 21 trees will be transplanted
and 42 trees will be felled.
Approximately 3,620 square metres of
planting area would be lost by
construction of building and temporary
works and associated impacts. Approximately 1,250 square metres of
planting area will be permanently lost by
the construction of Ventilation Building.
Construction of
ventilation building,
temporary storage and
stockpiling area.
Temporary vehicular
haulage from Trunk
Road T2 Eastern
Works Area to
Western Works Area.
No Large Low Medium
High
Large
Large
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013
l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Page 9-72
ID No. Landscape
Resources
Size of LR
(m2)
Description of Impacts Sources of Impact Reversibility Scale of
Development
Compatibility
with
Surrounding
Landscape
Duration of impact Magnitude of Change (Negligible,
Small, Intermediate, Large)
Construction Operation Construction Operation
LCA4 LR12 315,320 Impacts due to the construction of
underwater tunnel and temporary barging
point.
Impacts due to the
construction of
underwater tunnel and,
temporary barging
point. The temporary
barging point has a
vertical seawall face
and no temporary
facilities would be
needed to be
constructed above the
sea. It will be consist
of a one vehicle
unloading ramp and a
fully enclosed
conveyor belt
unloading chute from
LCA1 (LR8).
Yes Large Low Medium
N/A Small Negligible
LCA7 LR14&
LR16
34,390 Impacts due to the additional construction
works traffic in the area, temporary
excavation works, site offices, structures
and heavy machinery and 1 tree to be
felled.
An approximate area of 21,500 square
metres of hard standing will be temporary
lost for the Eastern Works Area site
offices.
Temporary storage
area and site office,
temporary vehicular
haulage from Trunk
Road T2 Eastern
Works Area to Trunk
Road T2 Western
Works Area.
Temporary vehicular
haulage from Trunk
Road T2 Eastern
Works Area to Trunk
Road T2 Western
Works Area.
1 tree to be felled.
Yes
Large
High
Medium
N/A
Intermediate
Negligible
Notes: The duration of impacts will be from 2016 to 2020 for both Construction Stages of the Eastern and Western areas.
Only Landscape Resources that are impacted are discussed.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-73 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
9.7.9 Assessment of Significance of Landscape Impacts
9.7.9.1 The significance threshold of landscape impacts are tabulated in Tables 9.12 and 9.13.
All impacts are adverse unless otherwise stated.
Table 9.12 Significance Threshold of Landscape Resources before Mitigation
ID.
No.
Sensitivity
(Low,
Medium,
High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Significance Threshold Before
Mitigation
(Insubstantial, Slight,
Moderate, Substantial)
Construction Operation Construction Operation
LR6 Medium Large Large
Moderate Moderate
LR8 Low Large Large Moderate Moderate
LR12 Medium Small
Negligible Slight
Insubstantial
LR16 Low Intermediate Negligible
Slight
Insubstantial
Note: Only Landscape Resources that are impacted are discussed.
Table 9.13 Significance Threshold of Landscape Character Areas before
Mitigation
ID.
No.
Sensitivity
(Low,
Medium,
High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Significance Threshold Before
Mitigation
(Insubstantial, Slight,
Moderate, Substantial)
Construction Operation Construction Operation
LCA1 Low Large Large Moderate Moderate
LCA3 Medium Large Large
Moderate
Moderate
LCA4 Medium Small
Negligible Slight
Insubstantial
LCA7 Low Intermediate Negligible
Slight
Insubstantial
Note: Only Landscape Resources that are impacted are discussed.
LR6 – Amenity Area (Kai Fuk Road / Kwun Tong By-pass)
9.7.9.2 The significance threshold before mitigation for LR6 within the construction phase of
the Ventilation Building and Western Works Area is considered as moderate, due to the
loss of an amenity area, which includes sitting out areas, a footpath and a planting area
of 3,620 square metres. 18 of the trees at this location will be retained and protected, 21
trees will be transplanted and 42 trees unsuitable for transplanting will be felled. The
significance threshold before mitigation for LR6 within the operation phase is
considered as moderate as, on completion of the Project a planting area of 1,250 square
metres will be lost due to Trunk Road T2 and Ventilation Building.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-74 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
LR8 - Derelict / Disturbed Land (KTD South Apron)
9.7.9.3 Since this is an area of derelict / disturbed land measuring 75,300 square metres and a
planting area of 159 square metres, where 12 trees will be protected, 10 trees are
recommended for transplanting, and 24 trees which are not suitable for transplanting
will be felled. The significance threshold before mitigation for LR8 within the
construction phase of the Ventilation and Tunnel Portal Buildings and Western Works
Area is considered as moderate. On completion of the Project, an area of 8,500 square
meters will be permanently lost to the Trunk Road T2, Ventilation and Tunnel Portal
Buildings.
LCA1 – Major On-Going Development Landscape
9.7.9.4 Since this is an area of derelict / disturbed land measuring 75,300 square metres and a
planting area of 159 square metres, where 12 trees will be protected, 10 trees are
recommended for transplanting, and 24 trees which are not suitable for transplanting
will be felled. The significance threshold before mitigation for LCA1 within the
construction phase of the Ventilation and Tunnel Portal Buildings and Western Works
Area is considered as moderate. On completion of the Project, an area of 8,500 square
meters will be permanently lost to the Trunk Road T2, Ventilation and Tunnel Portal
Buildings.
LCA3 – Transport Corridor
9.7.9.5 The significance threshold before mitigation for LCA3 within the construction phase of
the Ventilation Building and Western Works Area is considered as moderate, due to the
loss of an amenity area, which includes sitting out areas, a footpath and a planting area
of 3,620 square metres. 18 of the trees at this location will be retained and protected, 21
trees will be transplanted and 42 trees unsuitable for transplanting will be felled. The
significance threshold before mitigation for LCA3 within the operation phase is
considered as moderate as, on completion of the Project a planting area of 1,250 square
metres will be lost due to Trunk Road T2 and Ventilation Building.
9.8 Visual Impact Assessment
9.8.1 Potential Sources of Visual Impacts
9.8.1.1 The sources of impacts due to the Project would create varying levels of visual impact
during the construction and operation phases. Potential visual impacts would result
from the elements stated in Sections 9.7.1 to 9.7.4. Compatibility of the Project within
its visual context is described in Section 9.7.7.
9.8.2 Assessment of Magnitude to Change and Significance of Visual Impacts before
Mitigation
9.8.2.1 The sensitivity and magnitude of change to VSRs is presented in Table 9.14 and the
magnitude of change to VSRs before mitigation in the construction and operation
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-75 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
phases is then summarised in Tables 9.15 to 9.17 below. The significance of visual
impacts before mitigation is presented in Tables 9.18 and 9.19.
Table 9.14 Sensitivity and Magnitude of Change for Visual Sensitive Receivers
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O1
General
Description
Newport Centre
This low rise commercial building is planned
for redevelopment. Please refer to R1 for
description.
The description and evaluation of impacts on
the workers are discussed below:
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1150 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered negligible during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Refer to R1 For
description.
O2
General
Description
Kai Tak 1M: Comprehensive Development
Area
The description and evaluation of impacts on
the both the residents and workers are
discussed below:
Occupational Planned
(2016)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1350 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered negligible during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-76 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O2
Operational
Phase
Eastern Works Area: N/A Occupational Planned
(2016) Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1450 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC7, GIC9 &
GIC10 within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
O3
General
Description
Skyline Tower, Kowloon Bay
The description and evaluation of impacts on
the workers are discussed below:
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 700 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-77 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O3
Operational
Phase
Eastern Works Area: N/A Occupational Existing
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 650 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC9 & GIC10 within
the operation phase, the magnitude of impact
for this VSR is considered small.
O4
General
Description
Hong Kong International Trade and
Exhibition Centre
The description and evaluation of impacts on
the both the visitors and workers are discussed
below:
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 400 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-78 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O4
Operational
Phase
Eastern Works Area: N/A Occupational Existing
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 500 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC9 & GIC10
within the operation phase, the magnitude of
impact for this VSR is considered small.
O5
General
Description
Enterprise Square & Enterprise Square II,
Industrial/Office development Kowloon Bay
The description and evaluation of impacts on
the workers are discussed below:
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-79 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O5
Operational
Phase
Eastern Works Area: N/A Occupational Existing
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 250 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC9 & GIC10 within
the operation phase, the magnitude of impact
for this VSR is considered small.
O6
General
Description
Kai Fuk Industrial Center, Hong Leong
Industrial Complex & Billion Centre
The description and evaluation of impacts on
the workers are discussed below:
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 120 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 140 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the operation phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-80 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O7
General
Description
Mega Box/Enterprise Square V, Enterprise
Square III, Exchange Tower, Manhattan
Place & One Kowloon
The description and evaluation of impacts on
both the visitors and workers are discussed
below.
Occupational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 70 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Operational
Phase
Eastern Works Area: N/A.
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 70 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the operation phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-81 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O8
General
Description
Petrol Stations along Kai Fuk Road
The description and evaluation of impacts on
the both the visitors and workers are discussed
below:
Occupational
Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 80 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 80 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC9 & GIC10 within
the operation phase, the magnitude of impact
for this VSR is considered small.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-82 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O9
General
Description
Kai Tak Runway Precinct Hotel Belt
The description and evaluation of impacts on
both the visitors and workers are discussed
below:
Occupational/
Recreational
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 500 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by R5, RE8, GIC11A &
GIC11C within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
O10
General
Description
Kai Tak Cruise Terminal & Tourism
Related Commercial Development
The description and evaluation of impacts on
both the visitors and workers are discussed
below:
Occupational/
Recreational
Planned
(2014-
2015)
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be partial
and the distance of the view is approximately
1100 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-83 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O10
Construciton
Phase
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 500 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Occupational/
Recreational
Planned
(2014-
2015)
Operational
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by O12, GIC11A, R5 &
RE9 GIC6 within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
O11
General
Description
Vacant Lot at southern end of former Kai
Tak South Apron/3E1 Commercial
Development
The description and evaluation of impacts on
workers are discussed below:
Occupational
Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The site is designated as
a construction works area.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-84 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O11
Operational
Phase
Eastern Works Area: N/A Occupational
Existing/
Planned
(2021) Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 320 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the operation phase.
O12
General
Description
Kai Tak South Apron: Gas Pigging Station
The description and evaluation of impacts on
the visitors and workers are discussed below:
Occupational Planned
(2012-
2015)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be full,
and the distance of the view is approximately 5
meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 350 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the operation phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-85 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O13
General
Description
Pacific Trade Centre/ Proposed 3D2
Commercial Development
The description and evaluation of impacts on
the workers are discussed below:
Occupational Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 200 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 380 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the operation phase.
O14
General
Description
Octa Tower
The description and evaluation of impacts on
the workers are discussed below:
Occupational Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be a
glimpse, and the distance of the view is
approximately 1800 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-86 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O14
Construction
Phase
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 20 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the construction phase.
Occupational Existing
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 320 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the operation phase.
O15
General
Description
Not Used
Construction
Phase
Eastern Works Area: Not Used.
Western Works Area: Not Used.
Operational
Phase Eastern Works Area: Not Used.
Western Works Area: Not Used.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-87 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O16
General
Description
Proposed Industrial/Office development at
Kwun Tong Commercial Area
The description and evaluation of impacts on
the workers are discussed below:
Occupational Planned
(2015)
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be a
glimpse, and the distance of the view is
approximately 1800 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered negligible during the construction
phase.
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 300 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational Eastern Works Area: N/A
Phase Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 650 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by R3, R4, O11, O13 and
GIC11B within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-88 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O17
General
Description
Industrial/Office development at Kwun
Tong Western commercial area
The description and evaluation of impacts on
the workers are discussed below:
Occupational Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be partial
and the distance of the view is approximately
320 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational Eastern Works Area: N/A
Phase Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 650 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by R3, R4, O11 and O13
within the operation phase, the magnitude of
impact for this VSR is considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-89 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O18
General
Description
Industrial/Office development at Kwun
Tong Eastern commercial area
The description and evaluation of impacts on
the workers are discussed below
Occupational Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be a
glimpse, and the distance of the view is
approximately 360 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 750 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Operational
Phase
Eastern Works Area: Not Used.
Western Works Area: Not Used.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-90 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O19
General
Description
Kwun Tong Sewage Treatment
Works/Kwun Tong Pumping Station
/Planned Landscape Decked: Enclosed
Sewage Works
The description and evaluation of impacts on
the workers are discussed below
Occupational Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 160 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1400 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered negligible during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-91 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O20
General
Description
Soccer Pitch, Car Park, Petrol Filling
Station & Vacant Sites (Proposed Cha Kwo
Ling Promenade Park)
The description and evaluation of impacts on
the users and workers are discussed below.
Occupational/
Recreational
Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 5 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the construction phase.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Refer to RE17: Cha
Kwo Ling Park, N/A
O21
General
Description
Proposed Cha Kwo Ling Promenade
The description and evaluation of impacts on
the workers are discussed below
Occupational/
Recreational
Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area: The site is designated as
a construction works area.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
O22
General
Description
Tin Hau Temple
The description and evaluation of impacts on
the users are discussed below
Occupational Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 900 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-92 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
O22
Operational
Phase
Eastern Works Area: N/A Occupational Existing
Western Works Area: N/A
GIC1
General
Description
EMSD Workshops, Sewage Pumping
Station & Electricity Substation.
The description and evaluation of impacts on
the workers are discussed below
Government
/Institutional/
Community
Existing/
Proposed
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 1000 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE4 & RE5 within the
construction phase, the magnitude of impact
for this VSR is considered small.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE8, GIC7, GIC8 &
GIC11C, within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-93 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC2
General
Description
Electricity Substation
The description and evaluation of impacts on
the workers are discussed below
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 900 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC7 & GIC11C.
within the operation phase, the magnitude of
impact for this VSR is considered negligible.
GIC3
General
Description
Tunnel Ventilation Shaft & Administration
Building
The description and evaluation of impacts on
the workers are discussed below
Government
/Institutional/
Community
Planned
(2016)
Construction Eastern Works Area: N/A
Phase Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 600 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-94 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC3
Operational
Phase
Eastern Works Area: N/A Government
/Institutional/
Community
Planned
(2016)
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 640 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC7, & GIC10
within the operation phase, the magnitude of
impact for this VSR is considered small.
GIC4
General
Description
Tunnel Ventilation Shaft & Administration
Building (Kia Tak Tunnel Entrance)
The description and evaluation of impacts on
the workers are discussed below
Government
/Institutional/
Community
Existing
Construction
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 690 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 800 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC7 & GIC11C,
within the operation phase, the magnitude of
impact for this VSR is considered small.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-95 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC5
General
Description
DSD Desilting Compound
The description and evaluation of impacts on
the workers are discussed below
Government
/Institutional/
Community
Planned
(2016)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 760 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 760 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC7 & GIC11C,
within the operation phase, the magnitude of
impact for this VSR is considered small.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-96 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC6
General
Description
Northern Undesignated Government Site at
former Kai Tak South Apron
The description and evaluation of impacts on
the workers are discussed below
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 400 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the operation phase.
GIC7
General
Description
Southern Undesignated Government Site at
former Kai Tak South Apron
The description and evaluation of impacts on
the workers are discussed below
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 150 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the operation
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-97 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC8
General
Description
Social Welfare Facilities
The description and evaluation of impacts on
the workers are discussed below.
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 140 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the operation
phase.
GIC9
General
Description
Animal Management Centre
The description and evaluation of impacts on
the workers are discussed below
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 130 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the operation
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-98 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC10
General
Description
Jordan Valley Box Culvert: DSD Desilting
Building & Pumping Station
The description and evaluation of impacts on
the workers are discussed below.
Government
/Institutional/
Community
Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 5 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the construction phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Same as Construction
Phase
GIC11A
General
Description
Hospital at Former Kai Tak South Apron
The description and evaluation of impacts on
the visitors and workers are discussed below
Government
/Institutional/
Community
Planned
(2018)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 10 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the construction phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-99 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC11A
Operational
Phase
Eastern Works Area: N/A Government
/Institutional/
Community
Planned
(2018)
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 10 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the operation phase.
GIC11B
General
Description
Electrical & Mechanical Services
Department, Kowloon Bay Vehicle
Servicing Station/ Proposed Hospital at
former Kai Tak South Apron
The description and evaluation of impacts on
the visitors and workers are discussed below
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 10 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the construction phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 10 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the operation phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-100 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC11C
General
Description
Derelict land and Proposed Hospital at
former Kai Tak South Apron
The description and evaluation of impacts on
the visitors and workers are discussed below
Government
/Institutional/
Community
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The site is designated as
a construction works area.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 10 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the operation phase.
GIC12
General
Description
Kwun Tong Public Transport Interchange
and Kwun Tong Ferry Pier
The description and evaluation of impacts on
the users and workers are discussed below
Government
/Institutional/
Community
Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be full,
and the distance of the view is approximately
450 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered negligible during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-101 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
GIC12
Construction
Phase
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1250 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered negligible during the construction
phase.
Government
/Institutional/
Community
Existing
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
R1
General
Description
Comprehensive Development Area, Ma Tau
Kok.
The description and evaluation of impacts on
the residents are discussed below
Residential
Planned
(2021)
Construction Eastern Works Area: N/A
Phase Western Works Area: Refer to O1 for
description.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1350
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE5, RE8, GIC7, GIC8,
& GIC11C within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-102 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R2
General
Description
Kai Tak 2B: Comprehensive Development
Area
The description and evaluation of impacts on
the residents and workers are discussed below
Residential Planned
(2021)
Construction
Phase Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1600
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC7, GIC9 &
GIC10 within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
R3
General
Description
S/K22/13 Commercial Development
The description and evaluation of impacts on
the residents and workers are discussed below
Residential
Planned
(2016)
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 1740 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-103 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R3
Construction
Phase
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered high. The degree of
visibility to the Project will be partial, and the
distance of the view is approximately 10
meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered large during the construction phase.
Residential
Planned
(2016)
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 500 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by O11 & GIC11B within
the operation phase, the magnitude of impact
for this VSR is considered small.
R4
General
Description
S/K22/11 Comprehensive Development
Area
The description and evaluation of impacts on
the residents and workers are discussed below
Residential
Planned
(2016)
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 1740 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-104 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R4
Construction
Phase
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered high. The degree of
visibility to the Project will be full, and the
distance of the view is approximately 10
meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered large during the construction phase.
Residential
Planned
(2016)
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 500 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by O11 & GIC11B. within
the operation phase, the magnitude of impact
for this VSR is considered small.
R5
General
Description
Kai Tak Runway Precinct Housing
Development
The description and evaluation of impacts on
the residents are discussed below
Residential
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-105 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R5
Operational
Phase
Eastern Works Area: N/A Residential
Planned
(2021)
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 400 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE8, GIC11A, GIC 11C
within the operation phase, the magnitude of
impact for this VSR is considered negligible.
R6
General
Description
Laguna City
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered high. The degree of
visibility to the Project will be full, and the
distance of the view is approximately 160
meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered large during the construction phase.
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1600
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-106 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R7
General
Description
Residential development at Cha Kwo Ling
Road
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered high. The degree of
visibility to the Project will be full, and the
distance of the view is approximately 50
meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered large during the construction phase.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
R8
General
Description
Cha Kwo Ling Tsuen
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered high. The degree of
visibility to the Project will be full, and the
distance of the view is approximately 20
meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered large during the construction phase.
Western Works Area: N/A
Operational Eastern Works Area: N/A
Phase Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-107 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R9
General
Description
Grand Waterfront, To Kwa Wan
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1150
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1400
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE4, RE5, RE8, GIC7,
GIC8 & GIC11C within the operation phase,
the magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-108 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R10
General
Description
Wyler Gardens, To Kwa Wan
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction Eastern Works Area: N/A
Phase Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1250
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE4 & RE5 within the
construction phase, the magnitude of impact
for this VSR is considered small.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1500
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE4, RE5, RE8, GIC7,
GIC8 & GIC11 within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-109 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R11
General
Description
Sky Tower, Kowloon City
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1550
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE4 & RE5, within the
construction phase, the magnitude of impact
for this VSR is considered small.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1900
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE4, RE5, RE8, GIC7,
& GIC11 within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-110 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R12
General
Description
Sunrise Villas, To Kwa Wan
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1600
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE4 and, RE5, within
the construction phase, the magnitude of
impact for this VSR is considered small.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 2000
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE5, RE8, GIC7, GIC8
& GIC11C within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-111 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R13
General
Description
Laguna Verde Complex, Hung Hom
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be a glimpse, and
the distance of the view is approximately 3800
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Overall the magnitude of impact for this VSR
is considered negligible during the
construction phase.
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1620
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE5, & GIC11A within
the construction phase, the magnitude of
impact for this VSR is considered small.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1840
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by O9, R5, RE6, RE8 &
GIC11C within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-112 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R14
General
Description
Harbourfront Landmark & Harbour
Grand, Kowloon, Hung Hom
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction
Phase
Eastern Works Area:
The frequency and duration of views would be
long. Sensitivity for this VSR is considered
low. The degree of visibility to the Project will
be a glimpse, and the distance of the view is
approximately 3200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered negligible during the construction
phase.
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 2110
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE5, & GIC11A within
the operation phase, the magnitude of impact
for this VSR is considered small.
Operational Eastern Works Area: N/A
Phase Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 2000
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by O9, R5, RE6, RE8,
GIC7 & GIC11C within the operation phase,
the magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-113 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R15
General
Description
Kai Tak 2B Housing Development
The description and evaluation of impacts on
the residents are discussed below
Residential Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1550
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC7, GIC9 &
GIC10 within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
R16
General
Description
Kai Tak 1L & 1K Housing Development
The description and evaluation of impacts on
the residents are discussed below
Residential Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be partial, and the
distance of the view is approximately 1060
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC9 & GIC10,
within the operation phase, the magnitude of
impact for this VSR is considered small.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-114 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R17
General
Description
Kai Tak 1H & 1I Housing Development
The description and evaluation of impacts on
the residents are discussed below
Residential Planned
(2016)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be partial, and the
distance of the view is approximately 1050
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1100
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC6, GIC9 & GIC10
within the operation phase, the magnitude of
impact for this VSR is considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-115 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R18
General
Description
Hing Yan Street Residential Block
The description and evaluation of impacts on
the residents are discussed below
Residential Existing
Construction Eastern Works Area: N/A
Phase Western Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered low. The degree of
visibility to the Project will be glimpse, and
the distance of the view is approximately 1200
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: Refer to R1 for details
R19
General
Description
Yau Tong Bay Development
The description and evaluation of impacts on
the residents are discussed below
Residential/
Occupational
Planned
(2018)
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be long. Sensitivity
for this VSR is considered high. The degree of
visibility to the Project will be partial, and the
distance of the view is approximately 300
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Western Works Area: N/A
Operational Eastern Works Area: N/A
Phase Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-116 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE1
General
Description
Ma Tau Kok: Regional Open Space
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Planned
(2014)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1800 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction of RE4 & RE5 within the
operation phase, the magnitude of impact for
this VSR is considered small
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1650 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE8, & GIC11C within
the operation phase, the magnitude of impact
for this VSR is considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-117 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE2
General
Description
Hoi Sham Park, Ma Tau Kok
Existing public waterfront park. At pedestrian
level there are good panoramic views across
Kowloon Bay and over the Kai Tak
development, which is currently undergoing
various demolition/site clearance,
infrastructure and construction projects
throughout the KTD.
Recreational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1500 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction of RE4 & RE5 within the
operation phase, the magnitude of impact for
this VSR is considered small
Operational
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1600 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE8 & GIC11C within
the operation phase, the magnitude of impact
for this VSR is considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-118 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE3
General
Description
Current & Future Waterfront Promenade,
Ma Tau Kok
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Existing/
Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE4 & RE5 within the
construction phase, the magnitude of impact
for this VSR is considered small during the
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1300 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE8, GIC7, GIC8 &
GIC11C within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-119 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE4
General
Description
Planned Multi-Purpose Stadium Complex –
Park
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Planned
(2016-
2020)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
partial, and the distance of the view is
approximately 1000 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 1000 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE8, GIC7, GIC8 &
GIC11C, within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-120 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE5
General
Description
Kai Tak Runway Precinct: Metro Park
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Planned
(2017)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 300 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 400 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered high.
Due to obstruction by RE8, GIC7, GIC8 &
GIC11C within the operation phase, the
magnitude of impact for this VSR is
considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-121 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE6
General
Description
Kai Tak Runway Precinct Northern
Promenade
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 330 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE8, GIC7, GIC8 &
GIC11C, within the operation phase, the
magnitude of impact for this VSR is
considered intermediate.
RE7
General
Description
Kai Tak Runway Park
The description and evaluation of impacts on
the recreational users are discussed below:.
Recreational Planned
(2013)
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 700 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-122 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE7
Construction
Phase
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 350 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Recreational Planned
(2013)
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
RE8
General
Description
Kai Tak South Apron: Southern
Promenade
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 100 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by RE8, GIC7, GIC11A &
GIC11C within the operation phase, the
magnitude of impact for this VSR is
considered intermediate.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-123 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE9
General
Description
Kai Tak South Apron: Kowloon Bay Square
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Planned
(2021)
Construction
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
partial, and the distance of the view is
approximately 450 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by O11, O12, GIC11A &
GIC11C, within the operation phase, the
magnitude of impact for this VSR is
considered intermediate.
RE10
General
Description
Kai Tak South Apron: Amenity Area
The description and evaluation of impacts on
the recreational users are discussed below:.
Recreational Planned
(2021)
Construction Eastern Works Area: N/A
Phase Western Works Area: Area is designated to be
within site boundary area - N/A.
Operational
Phase Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 5 meters min.
The scale of the development is considered
large. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered large during the operation phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-124 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE11
General
Description
Enterprise Square: CIC Zero Carbon
Building
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Existing
Construction
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 150 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 150 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by GIC10, within the
operation phase, the magnitude of impact for
this VSR is considered negligible.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-125 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE12
General
Description
Hoi Bun Road Park
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be a
glimpse, and the distance of the view is
approximately 300 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered negligible during the construction
phase.
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be
glimpse (M), and the distance of the view is
approximately 350 meters min.
The scale of the development is considered
medium. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the operation phase.
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
RE13
General
Description
Kwun Tong Promenade (Existing )
The description and evaluation of impacts on
the recreational users are discussed below:.
Recreational Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be full,
and the distance of the view is approximately
200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-126 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
R13
Construction
Phase
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered medium.
The degree of visibility to the Project will be
full, and the distance of the view is
approximately 750 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Recreational Existing
Operational Eastern Works Area: N/A
Phase Western Works Area: N/A
RE14
General
Description
Kwun Tong Promenade (Planned)
The description and evaluation of impacts on
the recreational users are discussed below:
Occupational/
Recreational
Planned
(2021)
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be full,
and the distance of the view is approximately
200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered high. Overall the
magnitude of impact for this VSR is
considered negligible during the construction
phase.
Western Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be full,
and the distance of the view is approximately
200 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Operational
Phase Eastern Works Area: N/A
Western Works Area: N/A.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-127 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
RE15
General
Description
Laguna Park
The description and evaluation of impacts on
the recreational users are discussed below:
Recreational Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be medium.
Sensitivity for this VSR is considered low. The
degree of visibility to the Project will be a
glimpse, and the distance of the view is
approximately 300 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered low. Overall the
magnitude of impact for this VSR is
considered negligible during the construction
phase.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A.
T1
General
Description
Kwun Tong By-pass and Kai Fuk Road
The description and evaluation of impacts on
the travellers are discussed below:
Travelling Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be short. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be a
glimpse, and the distance of the view is
approximately 5 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered small during the construction
phase.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-128 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
T1
Construction
Phase
Western Works Area: The frequency and
duration of views would be short. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be full,
and the distance of the view is approximately 5
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Travelling Existing
Operational
Phase
Eastern Works Area: N/A
Western Works Area: The frequency and
duration of views would be short. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be full,
and the distance of the view is approximately 5
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the operation
phase.
T2
General
Description
Cha Kwo Ling Road
The description and evaluation of impacts on
the travellers are discussed below:
Travelling Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be short. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be full,
and the distance of the view is approximately 5
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Western Works Area: N/A
Operational
Phase
Eastern Works Area: N/A
Western Works Area: N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-129 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity and Magnitude of Change for
VSRs
Type of
VSRs Status
T3
General
Description
Harbour Traffic at Victoria Harbour
The description and evaluation of impacts on
the travellers are discussed below:
Travelling
Existing
Construction
Phase
Eastern Works Area: The frequency and
duration of views would be short. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be full,
and the distance of the view is approximately 5
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Western Works Area: The frequency and
duration of views would be short. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be full,
and the distance of the view is approximately 5
meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium. Overall
the magnitude of impact for this VSR is
considered intermediate during the
construction phase.
Operational Eastern Works Area: N/A
Phase Western Works Area: The frequency and
duration of views would be short. Sensitivity
for this VSR is considered medium. The
degree of visibility to the Project will be
glimpse, and the distance of the view is
approximately 100 meters min.
The scale of the development is considered
small. Compatibility within the surrounding
visual context is considered medium.
Due to obstruction by O11, O12, GIC11A
GIC11C, R3, R4, RE8 & RE9 within the
operation phase, the magnitude of impact for
this VSR is considered negligible.
Note:- “N/A” denotes – No views of Project or construction traffic
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-130 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Table 9.15 Magnitude of Change to Visually Sensitive Receivers: Eastern Works Area - Construction Phase
VSR
ID. No.
Compatibility
with surrounding
(High/ Medium/
Low)
Duration of Impacts
under Construction
Phase
(Long/ Medium/
Short)
Scale of the
Construction
Project
(Large/ Medium/
Small)
Reversibility
(Yes/No)
Degree of Visibility under
Construction
(Full/Partial/
Glimpse/None)
(M)*
Magnitude of Change
under Construction
(Negligible, Small,
Intermediate, Large)
O10 Medium Medium Small No Partial Small
O14 Medium Medium Small No Glimpse Small
O16 Medium Medium Small No Glimpse Negligible
O17 Medium Medium Small No Partial (M) Small
O18 Medium Medium Medium No Glimpse Small
O19 Medium Medium Large No Partial Intermediate
O20 Medium Medium Large No Full Large
O22 Medium Medium Medium No Partial Small
GIC12 Medium Medium Medium No Full (M) Negligible
R3 Medium Medium Small No Partial Small
R4 Medium Medium Small No Partial Small
R6 Low Medium Large No Full Large
R7 Low Medium Large No Full Large
R8 Low Medium Large No Full Large
R13 Medium Medium Small No Glimpse Negligible
R14 Medium Medium Small No Glimpse Negligible
R19 Low Medium Small No Partial Intermediate
RE7 Low Medium Small No Full Intermediate
RE12 Medium Medium Small No Glimpse (M) Negligible
RE13 Medium Medium Small No Full (M) Small
RE14 High Medium Small No Full (M) Negligible
RE15 Low Medium Small No Glimpse Negligible
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-131 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Compatibility
with surrounding
(High/ Medium/
Low)
Duration of Impacts
under Construction
Phase
(Long/ Medium/
Short)
Scale of the
Construction
Project
(Large/ Medium/
Small)
Reversibility
(Yes/No)
Degree of Visibility under
Construction
(Full/Partial/
Glimpse/None)
(M)*
Magnitude of Change
under Construction
(Negligible, Small,
Intermediate, Large)
T1 Medium Short Small No Glimpse Small
T2 Medium Short Small No Full Intermediate
T3 Medium Short Small No Full Intermediate
Notes: Compatibility: The visual context within which the Project is located.
Scale of Construction: Based on distance from Project and compatibility with surrounding redevelopment
* Degree of Visibility (M): No direct views onto Works Area; views are onto additional marine traffic for construction and demolition materials
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-132 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Table 9.16 Magnitude of Change to Visually Sensitive Receivers: Western Works Area - Construction Phase
VSR
ID. No.
Compatibility
with surrounding
(High/ Medium/
Low)
Duration of Impacts
under Construction
Phase
(Long/ Medium/
Short)
Scale of the
Construction
Project
(Large/ Medium/
Small)
Reversibility
(Yes/No)
Degree of Visibility under
Construction
(Full/Partial/
Glimpse/None) (M)*
Magnitude of Change
under Construction
(Negligible, Small,
Intermediate, Large)
O1 Medium Medium Small No Glimpse Negligible
O2 Medium Medium Small No Glimpse Negligible
O3 Medium Medium Small No Partial Small
O4 Medium Medium Small No Partial Small
O5 Medium Medium Small No Partial Intermediate
O6 Medium Medium Large No Full Intermediate
O7 Medium Medium Large No Full Intermediate
O8 Medium Medium Large No Glimpse Small
O10 Low Medium Small No Partial Intermediate
O12 Medium Medium Large No Full Intermediate
O13 Medium Medium Medium No Partial Small
O14 Medium Medium Large No Full Large
O16 Medium Medium Medium No Partial Small
O17 Medium Medium Small No Partial Small
O18 Medium Medium Small No Partial Intermediate
O19 Medium Medium Small No Glimpse Negligible
GIC1 Medium Medium Small No Partial Small
GIC3 Medium Medium Small No Glimpse Small
GIC4 Medium Medium Small No Glimpse Small
GIC5 Medium Medium Small No Glimpse Small
GIC10 Medium Medium Large No Full Large
GIC11A Medium Medium Large No Full Large
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-133 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Compatibility
with surrounding
(High/ Medium/
Low)
Duration of Impacts
under Construction
Phase
(Long/ Medium/
Short)
Scale of the
Construction
Project
(Large/ Medium/
Small)
Reversibility
(Yes/No)
Degree of Visibility under
Construction
(Full/Partial/
Glimpse/None) (M)*
Magnitude of Change
under Construction
(Negligible, Small,
Intermediate, Large)
GIC11B Medium Medium Large No Full Large
GIC12 Medium Medium Small No Glimpse Negligible
R3 Low Long Large No Partial Large
R4 Low Long Large No Full Large
R6 Medium Long Small No Glimpse Small
R9 Medium Long Small No Glimpse Small
R10 Medium Long Small No Glimpse Small
R11 Medium Long Small No Glimpse Small
R12 Medium Long Small No Glimpse Small
R13 Medium Long Small No Glimpse Small
R14 Medium Long Small No Glimpse Small
R17 Medium Long Small No Partial Small
R18 Medium Long Small No Glimpse Small
RE1 Medium Medium Small No Glimpse Small
RE2 Medium Medium Small No Glimpse Small
RE3 Medium Medium Small No Glimpse Small
RE4 Medium Medium Medium No Partial Small
RE5 Medium Medium Medium No Partial Small
RE7 Medium Medium Medium No Full Intermediate
RE11 Medium Medium Small No Glimpse Small
RE12 Medium Medium Medium No Glimpse (M) Small
RE13 Medium Medium Small No Full Intermediate
RE14 Medium Medium Small No Full Small
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-134 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Compatibility
with surrounding
(High/ Medium/
Low)
Duration of Impacts
under Construction
Phase
(Long/ Medium/
Short)
Scale of the
Construction
Project
(Large/ Medium/
Small)
Reversibility
(Yes/No)
Degree of Visibility under
Construction
(Full/Partial/
Glimpse/None) (M)*
Magnitude of Change
under Construction
(Negligible, Small,
Intermediate, Large)
T1 Medium Short Small No Full Intermediate
T3 Medium Short Small No Full Intermediate
Notes: Compatibility: The visual context within which the Project is located.
Scale of Construction: Based on distance from Project and compatibility with surrounding redevelopment
* Degree of Visibility (M): No direct views onto Works Area; views are onto additional marine traffic for construction and demolition materials
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-135 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Table 9.17 Magnitude of Change to Visually Sensitive Receivers: Western Works Area - Operation Phase
VSR
ID. No.
Compatibility
with surrounding
(High/ Medium/
Low)
Duration of Impacts
Operation Phase
(Long/ Medium/
Short)
Scale of the
Operation
Project
(Large/ Medium/
Small)
Reversibility
(Yes/No)
Degree of Visibility in
Operation Phase
(Full/Partial/
Glimpse/None)
(M)*
Magnitude of Change
Operation Phase
(Negligible, Small,
Intermediate, Large)
O2 Medium Medium Small No Glimpse Negligible
O3 Medium Medium Small No Partial Small
O4 Medium Medium Small No Partial Small
O5 Medium Medium Small No Partial Small
O6 Medium Medium Medium No Partial Small
O7 Medium Medium Medium No Partial Small
O8 Medium Medium Medium No Glimpse Small
O9 Medium Medium Small No Glimpse Negligible
O10 Medium Medium Small No Glimpse Negligible
O11 Medium Medium Medium No Partial Small
O12 Medium Medium Medium No Partial Small
O13 Medium Medium Medium No Partial Small
O14 Medium Medium Medium No Partial Small
O16 Medium Medium Small No Glimpse Negligible
O17 Medium Medium Small No Glimpse Negligible
GIC1 Medium Medium Small No Glimpse Negligible
GIC2 Medium Medium Small No Glimpse Negligible
GIC3 Medium Medium Small No Glimpse Small
GIC4 Medium Medium Small No Glimpse Small
GIC5 Medium Medium Small No Glimpse Small
GIC6 Medium Medium Small No Partial Small
GIC7 Medium Medium Large No Partial Intermediate
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-136 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Compatibility
with surrounding
(High/ Medium/
Low)
Duration of Impacts
Operation Phase
(Long/ Medium/
Short)
Scale of the
Operation
Project
(Large/ Medium/
Small)
Reversibility
(Yes/No)
Degree of Visibility in
Operation Phase
(Full/Partial/
Glimpse/None)
(M)*
Magnitude of Change
Operation Phase
(Negligible, Small,
Intermediate, Large)
GIC8 Medium Medium Large No Full Intermediate
GIC9 Medium Medium Large No Partial Intermediate
GIC10 Medium Medium Large No Full Large
GIC11A Medium Medium Large No Full Large
GIC11B Medium Medium Large No Full Large
GIC11C Medium Medium Large No Full Large
R1 Medium Long Small No Glimpse Negligible
R2 Medium Long Small No Glimpse Negligible
R3 Medium Long Medium No Partial Small
R4 Medium Long Medium No Partial Small
R5 Medium Long Medium No Glimpse Negligible
R9 Medium Long Small No Glimpse Negligible
R10 Medium Long Small No Glimpse Negligible
R11 Medium Long Small No Glimpse Negligible
R12 Medium Long Small No Glimpse Negligible
R13 Medium Long Small No Glimpse Negligible
R14 Medium Long Small No Glimpse Negligible
R15 Medium Long Small No Glimpse Negligible
R16 Medium Long Small No Partial Small
R17 Medium Long Small No Glimpse Negligible
RE1 Medium Medium Small No Glimpse Negligible
RE2 Medium Medium Small No Glimpse Negligible
RE3 Medium Medium Small No Glimpse Negligible
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-137 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Compatibility
with surrounding
(High/ Medium/
Low)
Duration of Impacts
Operation Phase
(Long/ Medium/
Short)
Scale of the
Operation
Project
(Large/ Medium/
Small)
Reversibility
(Yes/No)
Degree of Visibility in
Operation Phase
(Full/Partial/
Glimpse/None)
(M)*
Magnitude of Change
Operation Phase
(Negligible, Small,
Intermediate, Large)
RE4 Medium Medium Medium No Glimpse Negligible
RE5 High Medium Medium No Glimpse Negligible
RE6 Medium Medium Medium No Partial Intermediate
RE8 Medium Medium Medium No Partial Intermediate
RE9 Medium Medium Medium No Partial Intermediate
RE10 Medium Medium Large No Full Large
RE11 Medium Medium Small No Glimpse Negligible
T1 Medium Short Small No Full Intermediate
T3 Medium Short Small No Glimpse Negligible
Notes: Compatibility: The visual context within which the Project is located.
Scale of Construction: Based on distance from Project and compatibility with surrounding redevelopment
* Degree of Visibility (M): No direct views onto Works Area; views are onto additional marine traffic for construction and demolition materials
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-138 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Table 9.18 Significance of Visual Impacts before Mitigation (Eastern Works Area)
VSR
ID. No.
Sensitivity
(Low, Medium, High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Significance Threshold
Before Mitigation (Insubstantial, Slight, Moderate,
Substantial)
Construction Operation Construction Operation Construction Operation
O10 Low N/A Small N/A Slight N/A
O14 Low N/A Small N/A Slight N/A
O16 Low N/A Negligible N/A Insubstantial N/A
O17 Low N/A Small N/A Slight N/A
O18 Low N/A Small N/A Slight N/A
O19 Low N/A Intermediate N/A Slight/Moderate N/A
O20 Medium N/A Large N/A Moderate/Substantial N/A
O22 Low N/A Small N/A Slight N/A
GIC12 Low N/A Negligible N/A Insubstantial N/A
R3 Medium N/A Small N/A Slight/Moderate N/A
R4 Medium N/A Small N/A Slight/Moderate N/A
R6 High N/A Large N/A Substantial N/A
R7 High N/A Large N/A Substantial N/A
R8 High N/A Large N/A Substantial N/A
R13 Low N/A Negligible N/A Insubstantial N/A
R14 Low N/A Negligible N/A Insubstantial N/A
R19 High N/A Intermediate N/A Moderate/Substantial N/A
RE7 Medium N/A Intermediate N/A Moderate N/A
RE12 Low N/A Negligible N/A Insubstantial N/A
RE13 Low N/A Small N/A Slight N/A
RE14 Low N/A Small N/A Slight N/A
RE15 Low N/A Negligible N/A Insubstantial N/A
T1 Medium N/A Small N/A Slight/Moderate N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-139 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity
(Low, Medium, High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Significance Threshold
Before Mitigation (Insubstantial, Slight, Moderate,
Substantial)
Construction Operation Construction Operation Construction Operation
T2 Medium N/A Intermediate N/A Moderate N/A
T3 Medium N/A Intermediate N/A Moderate N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-140 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Table 9.19 Significance of Visual Impacts before Mitigation (Western Works Area)
VSR
ID. No.
Sensitivity
(Low, Medium, High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Significance Threshold
Before Mitigation (Insubstantial, Slight, Moderate,
Substantial)
Construction Operation Construction Operation Construction Operation
O1 Low N/A Negligible Negligible Insubstantial N/A
O2 Low Low Negligible Negligible Insubstantial Insubstantial
O3 Low Low Small Small Slight Slight
O4 Medium Low Small Small Slight/Moderate Slight
O5 Medium Low Intermediate Small Moderate Slight
O6 Medium Medium Intermediate Small Moderate Slight/Moderate
O7 Medium Medium Intermediate Small Moderate Slight/Moderate
O8 Low Low Small Small Slight Slight
O9 N/A Low N/A Negligible N/A Insubstantial
O10 Medium Medium Intermediate Negligible Moderate Insubstantial
O11 N/A Medium N/A Small N/A Slight/Moderate
O12 Low Low Intermediate Small Slight/Moderate Slight
O13 Low Medium Small Small Slight Slight/Moderate
O14 Medium Medium Large Small Moderate/Substantial Slight/Moderate
O16 Medium Low Small Negligible Slight/Moderate Insubstantial
O17 Low Low Small Negligible Slight Insubstantial
O18 Low N/A Intermediate N/A Slight/Moderate N/A
O19 Low N/A Negligible N/A Insubstantial N/A
GIC1 Low Low Small Negligible Slight Insubstantial
GIC2 N/A Low N/A Negligible N/A Insubstantial
GIC3 Low Low Small Small Slight Slight
GIC4 Low Low Small Small Slight Slight
GIC5 Low Low Small Small Slight Slight
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-141 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity
(Low, Medium, High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Significance Threshold
Before Mitigation (Insubstantial, Slight, Moderate,
Substantial)
Construction Operation Construction Operation Construction Operation
GIC6 N/A Medium N/A Small N/A Slight/Moderate
GIC7 N/A Medium N/A Intermediate N/A Moderate
GIC8 N/A Medium N/A Intermediate N/A Moderate
GIC9 N/A Low N/A Intermediate N/A Slight/ Moderate
GIC10 Medium Medium Large Large Moderate/Substantial Moderate/Substantial
GIC11A Medium Medium Large Large Moderate/Substantial Moderate/Substantial
GIC11B Medium Medium Large Large Moderate/Substantial Moderate/Substantial
GIC11C N/A Medium N/A Large N/A Moderate/Substantial
GIC12 Low N/A Negligible N/A Insubstantial N/A
R1 N/A Low N/A Negligible N/A Insubstantial
R2 N/A Low N/A Negligible N/A Insubstantial
R3 High Medium Large Small Substantial Slight/ Moderate
R4 High Medium Large Small Substantial Slight/ Moderate
R5 N/A Medium N/A Negligible N/A Insubstantial
R6 Low N/A Small N/A Slight N/A
R9 Low Low Small Negligible Slight Insubstantial
R10 Low Low Small Negligible Slight Insubstantial
R11 Low Low Small Negligible Slight Insubstantial
R12 Low Low Small Negligible Slight Insubstantial
R13 Low Low Small Negligible Slight Insubstantial
R14 Low Low Small Negligible Slight Insubstantial
R15 N/A Low N/A Negligible N/A Insubstantial
R16 N/A Low N/A Small N/A Slight
R17 Low Low Small Negligible Slight Insubstantial
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-142 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Sensitivity
(Low, Medium, High)
Magnitude of Change
(Negligible, Small,
Intermediate, Large)
Significance Threshold
Before Mitigation (Insubstantial, Slight, Moderate,
Substantial)
Construction Operation Construction Operation Construction Operation
R18 Low N/A Small N/A Slight N/A
RE1 Low Low Small Negligible Slight Insubstantial
RE2 Low Low Small Negligible Slight Insubstantial
RE3 Low Low Small Negligible Slight Insubstantial
RE4 Low Low Small Negligible Slight Insubstantial
RE5 Medium Medium Small Negligible Slight/Moderate Insubstantial
RE6 N/A Medium N/A Intermediate N/A Moderate
RE7 Medium N/A Intermediate N/A Moderate N/A
RE8 N/A Medium N/A Intermediate N/A Moderate
RE9 N/A Medium N/A Intermediate N/A Moderate
RE10 N/A Medium N/A Large N/A Moderate/Substantial
RE11 Low Low Small Negligible Slight Insubstantial
RE12 Low N/A Small N/A Slight N/A
RE13 Medium N/A Intermediate N/A Moderate N/A
RE14 Low N/A Small N/A Slight N/A
T1 Medium Medium Intermediate Intermediate Moderate Moderate
T3 Medium Medium Intermediate Negligible Moderate Insubstantial
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-143 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
9.9 Mitigation Measures
9.9.1 Tables 9.20 and 9.21 describe a series of mitigation measures to be used within the
construction and operational phases to potentially reduce any landscape or visual
impacts that have previously been identified within other sections of this report. The
landscape and visual mitigation measures are illustrated in Figure 9.11.2.
Table 9.20 Construction Phase Mitigation Measures
ID No. Landscape and Visual Mitigation Measure Funding
Agency
Implementation
Agency
CM1 All works shall be carefully designed to
minimize impacts on existing landscape
resources and visually sensitive receivers.
Existing trees within works area shall be
retained and protected.
CEDD CEDD’s
Contractor
CM2 Existing trees of good quality and condition
that are unavoidably affected by the works
should be transplanted.
CEDD CEDD’s
Contractor
CM3 Not used Not used Not used
CM4 Not used. Not used. Not used.
CM5 Large temporary stockpiles of excavated
material shall be covered with unobtrusive
sheeting to prevent dust and dirt spreading to
adjacent landscape areas and vegetation, and
to create a neat and tidy visual appearance.
CEDD CEDD’s
Contractor
CM6 Construction plant and building material shall
be orderly and carefully stored in order to
create a neat and tidy visual appearance.
CEDD CEDD’s
Contractor
CM7 Erection of decorative screen hoarding should
be designed to be compatible with the existing
urban context.
CEDD CEDD’s
Contractor
CM8 All lighting in construction site shall be
carefully controlled to minimize light pollution
and night-time glare to nearby residences and
GIC user. The contractor shall consider other
security measures, which shall minimize the
visual impacts.
CEDD CEDD’s
Contractor
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-144 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Table 9.21 Operation Phase Mitigation Measures
ID
No.
Landscape and Visual
Mitigation Measure
Funding
Agency
Implementation
Agency
Maintenance/
Management
Agency
OM1 Compensatory tree planting shall
be incorporated along roadside
amenity areas affected by the
construction works. The required
numbers of compensatory trees
shall follow the requirements of
ETWB TCW No. 3/2006.
CEDD CEDD’s
Contractor
LCSD
OM2 Compensatory tree planting shall
be incorporated by the Project.
The required numbers of
compensatory trees shall follow
the requirements of ETWB TCW
No. 3/2006. Loss of amenity area
adjacent to the Kwun Tong By-
pass and planting areas in KTD
South Apron will be mitigated by
the creation of the Kai Tak South
Apron: Amenity Area, which will
be equal to or larger than the
current provision.
CEDD CEDD’s
Contractor
LCSD
OM3 Trees, shrubs and climbers shall
be planted to soften and screen
proposed roads, central medians
and associated structures, and to
enhance streetscape greening.
CEDD CEDD’s
Contractor
LCSD
OM4 All works areas, excavated areas
and disturbed areas for tunnel
construction and temporary road
diversion or any other proposed
works shall be reinstated to
former conditions or better, with
landscape treatment and to the
satisfaction of the relevant
Government departments.
CEDD CEDD’s
Contractor
Relevant
Government
Departments
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-145 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
ID
No.
Landscape and Visual
Mitigation Measure
Funding
Agency
Implementation
Agency
Maintenance/
Management
Agency
OM5 Tunnel portals and all above
ground structures shall be
sensitively designed to ensure the
element with colour, texture and
tonal quality being compatible to
the existing urban context. Trees
and shrub planting to minimize
the potential adverse landscape
and visual impacts shall be
included where space permits.
Roof top greening and vertical
greening shall also be provided.
CEDD CEDD’s
Contractor
LCSD/ HyD
9.10 Environmental Monitoring & Audit Requirement
9.10.1 Construction Phase
9.10.1.1 It is recommended that professionally qualified (i.e. LARB) Resident Site Landscape
Staff (SRLA/RLA) supervise and monitor the construction phase landscape and visual
mitigation measures. This is necessary, to ensure that topsoil is saved, to ensure that
existing trees earmarked for retention on site or transplanting are protected and to
monitor advance screen planting works, including procurement of plants, and the
effectiveness of temporary screen hoardings. Regular site inspections should be
undertaken to closely monitor all these aspects of the work.
9.10.2 Operation Phase
9.10.2.1 During the operation phase, landscape and visual mitigation measures should be monitored by the Environmental Team and Independent Environmental Checker –
during the first 10 years to check that the intended mitigation effects are realised.
Regular monitoring should be undertaken to ensure that the landscape and visual
mitigation measures have been implemented, are effective and are being managed and
maintained. The compensatory tree planting required to offset the loss of existing trees
should be checked, and the additional planting works for screening and amenity
purposes. Planting must be established and sustainable and provide long term landscape
and visual mitigation. Hardworks elements that have been provided as part of the new
works or as the reinstatement of impacted works should also be monitored and checked
that they are being maintained and are achieving their mitigation function.
9.11 Residual Impacts
9.11.1 Illustrations of Residual Impacts
9.11.1.1 Figures 9.17.1 to 9.17.4 provide photomontages of Trunk Road T2 and associated
buildings and adjacent developments, showing the outline massing of the proposed
developments, as per the KTD Recommended Outline Development Plan.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-146 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
9.11.1.2 Landscape and visual impacts, at both construction and operation phases, which remain
after all mitigation measures have been assessed, are provided in Tables 9.22 to 9.25.
9.11.2 Illustrations of Residual Visual Impacts (Refer to Figures 9.17 and 9.17.1 to 9.17.4)
9.11.2.1 In reviewing the location and context of the T2 Project in both the construction and
operation phases, it is considered that on completion the only above ground structures
that may impact the immediate and surrounding areas are within the Western Works
Area. The views from Hung Hum, To Kwa Wan, Kwun Tong and Cha Kwo Ling would
be significantly screened by the proposed KTD Runway Precinct and South Apron
Development. As the maximum proposed height of the Ventilation and Tunnel Portal
building is +17m PD, the following views were proposed to show context and detail of
the T2 Works Area and associated buildings:
9.11.2.2 Figure 9.17.1: Viewpoint No 1. - 16th Floor of Mega Box. Mega Box is part of the
Enterprise Square V complex. Upper floors of these buildings have a direct view onto
the site from the Kowloon Bay Commercial Area. The views looking onto the Western
Works Area and the proposed T2 Buildings are partially screened by Kowloon
Bay/Kwun Tong By-Pass on lower floors of the buildings. The photomontages show the
existing and proposed operational phase in scale and context, both with and without
mitigation measures as per the latest Recommended Outline Development Plan (RODP)
for Kai Tak Development. With the proposed mitigation measures and greening
initiatives, the T2 Ventilation and Tunnel Portal Buildings complement the proposed
KTD considering the current existing conditions.
9.11.2.3 Figure 9.17.2: Viewpoint No 2. – Trunk Road T2 & Road 18. The photomontages are
based upon a pedestrian view at ground level and show the Tunnel Portal and the
descending T2 Road. On Day 1, the view shows the Tunnel Portal and Ventilation
Buildings with vertical greening and planting. The trees are planted at semi mature size
to help screen the buildings on Day 1. Within 10 years, the trees will soften and mask
the top and sides of the tunnel portal from views at both pedestrian level and from the
surrounding buildings.
9.11.2.4 Figure 9.17.3: Viewpoint No 3. – Trunk Road T2, refuse collection building & Road
D4. The photomontages are based on a pedestrian view at ground level to provide a
scale perspective of the Refuse Collection & Ventilation Building, both in size and
context with the existing Kwun Tong By-pass, Kowloon Bay Commercial Area and the
proposed KTD: South Apron Developments. It is anticipated that the refuse collection
building will have vertical greening and planting. The greening measures will soften the
hard concrete structure, and blend into the context of the regenerated surrounding area.
Trees are planted on either side of the building so that their canopies, within 10 years,
will help to screen the structures from surrounding roads and buildings.
9.11.2.5 Figure 9.17.4: Viewpoint No 4. – Top Floor Proposed Residential Block at R3 Runway
Precinct Housing Development. The photomontages are based on a resident’s view
within the Runway Precinct Housing Development. The photomontages illustrate the
size and scale of the Tunnel Portal and refuse collection buildings against the back drop
of the Kwun Tong By-pass with proposed mitigation measures. The refuse collection
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-147 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
building on Day 1 fits in with the proposed soft landscape. In 10 years the building is
screened by trees along the D6 bridge, and merges into the back drop of the trees along
the edge of the Kwun Tong By-pass.
9.11.3 Concurrent Projects
9.11.3.1 Trunk Road T2 is to be constructed in conjunction with two other Route 6 Projects; the
CKR in the western South Apron area and the Tseung Kwan O - Lam Tin Tunnel
Interchange at the eastern end, forming a major transportation route within the Kowloon
Peninsula. The Kai Tak South Apron Development has a series of residential,
commercial and government buildings proposed adjacent to the Trunk Road T2,
Ventilation & Tunnel Portal Buildings. The various developments are scheduled to be
completed and operational by 2021.
9.11.3.2 As per the KTD Recommended Outline Development Plan the North Apron and
Runway precinct areas will also be constructed and operational by 2021.
9.11.4 Assessment of the Significance of Residual Landscape Impacts
9.11.4.1 On completion of the Project, at the eastern end of Trunk Road T2 and associated
works, within Cha Kwo Ling Road area, the residual landscape impacts are considered
to be insubstantial.
9.11.4.2 On Day 1 of completion of the Project, at the western end of Trunk Road T2 and
associated buildings, the residual landscape impacts are considered slight to
insubstantial as the project will adhere to the mitigation measures shown in Tables 9.22
and 9.23, and illustrated in Figure 9.11.2 and Figures 9.12.1 to 9.12.4. At Year 10 the
impacts are slight to insubstantial, though are considered beneficial to the Project.
9.11.4.3 Residual landscape impacts on Landscape Resources & Landscape Character Areas at
Day 1 and Year10 are summarised in Tables 9.22 and 9.23 respectively. Impacts on
Landscape Resources by the Project are described as follows:
LR6 – Amenity Area (Kai Fuk Road / Kwun Tong By-pass): An amenity area
including sitting out areas along a footpath and a planting area of 3,620 square
metres will be lost by the construction of the Ventilation Building and Western
Works Area. On completion of the Project a planting area of 1,250 square metres
will be lost due to Trunk Road T2 and Ventilation Building. This will be
compensated by a planting area to the immediate east of approximately 4,900
square metres (refer to Figure 9.11.2). Within the Western Works Area, 18 trees
will be retained and protected, 21 trees will be transplanted and 42 trees
unsuitable for transplanting will be felled. 63 trees will be provided as
compensation in accordance with ETWB TCW No. 3/2006 (refer to Figure
9.11.2).
LR8 – Derelict / Disturbed Land (KTD South Apron): An area of derelict /
disturbed land measuring 75,300 square metres and a planting area of 159 square
metres will be lost due to the Western Works Area. On completion of the Project,
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-148 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
an area of 8,500 square meters will be permanently lost to the Trunk Road T2,
Ventilation and Tunnel Portal Buildings. This will be compensated by a planting
area of approximately 15,740 square metres. 12 trees will be protected from
impact by the Project, 10 trees are recommended for transplanting, and 24 trees
which are not suitable for transplanting will be felled. 89 trees will be provided as
compensation in accordance with ETWB TCW No. 3/2006 (refer to Figure
9.11.2).
LR12 – Water Body (Kwun Tong Typhoon Shelter): A temporary barging
point will be located at the south eastern corner of the South Apron LR8 during
the construction phase only. The barging point will not damage any parts of the
seabed and is situated on the existing seawall. Residual impacts will be the
operation of barges between 07.00 & 19.00 in the construction phase only. The
sea wall will be reinstated following completion of the Project.
LR16 – Derelict / Disturbed Land Proposed as Cha Kwo Ling Promenade
Park by Others (Cha Kwo Ling Former Public Cargo Working Area): An
approximate area of 21,500 square metres of hard standing will be lost for the
Eastern Works Area site offices. One tree, Macaranga tanarius, which is not
considered suitable for transplanting is recommended to be felled. Mitigation for
the felled tree has been included within the compensatory trees for the Western
Works Area in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2).
The site will be reinstated and handed over for future development of Cha Kwo
Ling Promenade Park under a separate project.
9.11.4.4 Impacts on Landscape Character Areas affected by the Project are described as follows:
LCA1 – Major On-Going Development Landscape: An area of derelict /
disturbed land measuring an area of 75,300 square metres and a planting area of
159 square metres will be lost to the Western Works Area. On completion of the
Project an area of 8,500 square meters will be lost to the Trunk Road T2,
Ventilation and Tunnel Portal Buildings. A planting area of 15,740 square metres
will be provided to compensate the loss of this area. 12 trees will be protected
from the impact of the proposed T2 development, 10 trees are recommended for
transplanting, and 24 trees which are not suitable for transplanting will be felled.
89 trees will be provided as compensation in accordance with ETWB TCW No.
3/2006 (refer to Figure 9.11.2).
LCA3 – Transport Corridor: An approximate planting area of 3,620 square
metres will be lost as a result of the Western Works Area. On completion of the
Project a planting area of 1,250 square metres will be lost by the Western
Ventilation Building. This will be compensated by approximately 4,900 square
metres of amenity area as referred to in the report as RE10 Kai Tak South Apron:
Amenity Area. Within the works area, 18 trees will be retained and protected, 21
trees are recommended for transplanting and 42 trees which are not suitable for
transplanting will be felled. 63 trees will be provided as compensation in
accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2).
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-149 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
LCA4 – Kwun Tong Typhoon Shelter Landscape: A temporary barging will be
located at the south eastern corner of the South Apron (LCA1) within the
construction phase. For mitigation measures please refer to LR12 above.
LCA7 – Cha Kwo Ling Reclaimed Industrial Urban Landscape: Within the
Eastern Works Area, no planting areas will be lost as the site is currently hard
standing. An approximate area of 21,500 square metres of hard standing will be
lost for the Eastern Works Area site offices. One tree, a Macaranga tanarius
which is not considered suitable for transplanting is recommended to be felled.
Mitigation for the felled tree has been included within the compensatory trees for
the Western Works Area in accordance with ETWB TCW No. 3/2006 (refer to
Figure 9.11.2). The site will be reinstated and handed over for future
development of Cha Kwo Ling Promenade Park under a separate project.
9.11.4.5 The following Table 9.22 refers to the Landscape Resources impacted by the Project
and Table 9.23 refers to the Landscape Character Areas impacted by the Project.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-150 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Table 9.22 Residual Impacts on Landscape Resources after Mitigation
ID.
No.
Landscape resources Significance Threshold Before Mitigation
(Insubstantial, Slight, Moderate, Substantial) Recommended Mitigation Measures
Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Adverse or Beneficial
Construction Operation Construction Operation Construction Operation Day1 Operation Year 10
LR6 Amenity Area (Kai Fuk Road
/ Kwun Tong By-pass)
Moderate
Moderate CM1 to CM2 OM1 to OM5 Moderate
Adverse
Slight
Beneficial
Slight
Beneficial
LR8 Derelict / Disturbed Land
(KTD South Apron)
Moderate Moderate CM1 to CM2 OM1 to OM5 Moderate
Adverse
Slight
Beneficial
Slight
Beneficial
LR12 Water Body (Kwun Tong
Typhoon Shelter)
Slight Insubstantial CM1 OM4 Slight
Adverse
Insubstantial Insubstantial
LR16 Derelict / Disturbed Land
Proposed as Cha Kwo Ling
Promenade Park by Others
(Cha Kwo Ling Former Public
Cargo Working Area)
Slight
Insubstantial CM1 to CM2 OM4 Slight
Adverse
Insubstantial Insubstantial
Table 9.23 Residual Impacts on Landscape Character Areas after Mitigation
ID.
No.
Landscape
Character Areas Significance Threshold Before Mitigation
(Insubstantial, Slight, Moderate, Substantial) Recommended Mitigation Measures
Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Adverse or Beneficial
Construction Operation Construction Operation Construction Operation Day 1 Operation Year 10
LCA1 LR8, LR10 and LR11 Moderate Moderate CM1 to CM2 OM1 to OM5 Moderate
Adverse
Slight
Beneficial
Slight
Beneficial
LCA3 LR1, LR6 and LR14 Moderate
Moderate CM1 to CM2 OM1 to OM5 Moderate
Adverse
Slight
Beneficial
Slight
Beneficial
LCA4 LR12 Slight Insubstantial CM1 OM4 Slight
Adverse
Insubstantial Insubstantial
LCA7 LR14 and LR16 Slight
Insubstantial CM1 to CM2 OM4 Slight
Adverse
Insubstantial Insubstantial
Note: The impacts on Landscape Resources and Landscape Character Areas are considered to reduce after 10 years of operation due to the maturity of tree and plant growth.
The impacts are considered beneficial.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-151 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
9.11.5 Assessment of the Significance of Residual Impacts on Visually Sensitive Receivers
9.11.5.1 Residual landscape impacts on Visually Sensitive Receivers are summarised in Tables
9.24 and 9.25 respectively. Impacts on Visually Sensitive Receivers by the Project are
described as follows:
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-152 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
Table 9.24 Residual Impacts on Visually Sensitive Receivers after Mitigation (Eastern Works Area)
VSR
ID.
No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation
Day 1
Operation Year
10
O10 Slight N/A CM1, CM5 to
CM8 N/A Insubstantial N/A NA
O14 Slight N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
O16 Insubstantial N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
O17 Slight N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
O18 Slight N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
O19 Slight/ Moderate N/A CM1, CM5 to
CM8
N/A Slight
Adverse
N/A NA
O20 Moderate/
Substantial
N/A CM1, CM5 to
CM8
N/A Moderate
Adverse
N/A NA
O22 Slight N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
GIC12 Insubstantial N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
R3 Slight/ Moderate N/A CM1, CM5 to
CM8
N/A Slight
Adverse
N/A NA
R4 Slight/ Moderate N/A CM1, CM5 to
CM8
N/A Slight
Adverse
N/A NA
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-153 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID.
No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation
Day 1
Operation Year
10
R6 Substantial N/A CM1, CM5 to
CM8
N/A Moderate/
Substantial
Adverse
N/A NA
R7 Substantial N/A CM1, CM5 to
CM8
N/A Moderate/
Substantial
Adverse
N/A NA
R8 Substantial N/A CM1, CM5 to
CM8
N/A Moderate/
Substantial
Adverse
N/A NA
R13 Insubstantial N/A CM1, CM5 to
CM8 N/A Insubstantial N/A NA
R14 Insubstantial N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
R19 Moderate/
Substantial
N/A CM1, CM5 to
CM8
N/A Moderate
Adverse
N/A NA
RE7 Moderate N/A CM1, CM5 to
CM8
N/A Slight/ Moderate
Adverse
N/A NA
RE12 Insubstantial N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
RE13 Slight N/A CM1, CM5 to
CM8 N/A Insubstantial N/A NA
RE14 Slight N/A CM1, CM5 to
CM8
N/A Insubstantial N/A NA
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-154 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID.
No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation
Day 1
Operation Year
10
RE15 Insubstantial N/A CM1, CM5 to
CM8 N/A Insubstantial N/A NA
T1 Slight/
Moderate
N/A CM1, CM5 to
CM8
N/A Slight
Adverse
N/A NA
T2 Moderate N/A CM1, CM5 to
CM8
N/A Slight/
Moderate
Adverse
N/A NA
T3 Moderate N/A CM1, CM5 to
CM8
N/A Slight/
Moderate
Adverse
N/A NA
Table 9.25 Residual Impacts on Visually Sensitive Receivers after Mitigation:(Western Works Area)
VSR
ID. No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation Day 1 Operation Year
10
O1 Insubstantial N/A CM1, CM5 to
CM8
OM1 to OM5 Insubstantial N/A N/A
O2 Insubstantial Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-155 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation Day 1 Operation Year
10
O3 Slight Slight CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
O4 Slight/
Moderate
Slight CM1, CM5 to
CM8
OM1 to OM5 Slight
Adverse
Insubstantial Insubstantial
O5 Moderate Slight CM1, CM5 to
CM8
OM1 to OM5 Slight/
Moderate
Adverse
Insubstantial Insubstantial
O6 Moderate Slight/
Moderate
CM1, CM5 to
CM8 OM1 to OM5 Slight/
Moderate
Adverse
Slight
Beneficial
Insubstantial
O7 Moderate Slight/
Moderate
CM1, CM5 to
CM8
OM1 to OM5 Slight/
Moderate
Adverse
Slight
Beneficial
Insubstantial
O8 Slight Slight CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
O9 N/A Insubstantial CM1, CM5 to
CM8 OM1 to OM5 N/A Insubstantial Insubstantial
O10 Moderate Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Slight/
Moderate
Adverse
Insubstantial Insubstantial
O11 N/A Slight/
Moderate
CM1, CM5 to
CM8
OM1 to OM5 N/A Slight
Beneficial
Insubstantial
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-156 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation Day 1 Operation Year
10
O12 Slight/
Moderate
Slight CM1, CM5 to
CM8
OM1 to OM5 Slight
Adverse
Insubstantial Insubstantial
O13 Slight Slight/
Moderate
CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Slight
Beneficial
Insubstantial
O14 Moderate/
Substantial
Slight/ Moderate CM1, CM5 to
CM8
OM1 to OM5 Moderate
Adverse
Slight
Beneficial
Insubstantial
O16 Slight/
Moderate
Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Slight
Adverse
Insubstantial Insubstantial
O17 Slight
Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
O18 Slight/
Moderate
N/A CM1, CM5 to
CM8
N/A Slight
Adverse
N/A Insubstantial
O19 Insubstantial N/A CM1, CM5 to
CM8
N/A Insubstantial N/A Insubstantial
GIC1 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
GIC2 N/A Insubstantial CM1, CM5 to
CM8
OM1 to OM5 N/A Insubstantial Insubstantial
GIC3 Slight Slight CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
GIC4 Slight Slight CM1, CM5 to
CM8 OM1 to OM5 Insubstantial Insubstantial Insubstantial
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-157 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation Day 1 Operation Year
10
GIC5 Slight Slight CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
GIC6 N/A Slight/
Moderate
CM1, CM5 to
CM8
OM1 to OM5 N/A Slight
Beneficial
Insubstantial
GIC7 N/A Moderate CM1, CM5 to
CM8
OM1 to OM5 N/A Slight/
Moderate
Beneficial
Slight
Beneficial
GIC8 N/A Moderate CM1, CM5 to
CM8 OM1 to OM5 N/A Slight/
Moderate
Beneficial
Slight
Beneficial
GIC9 N/A Slight/
Moderate
CM1, CM5 to
CM8
OM1 to OM5 N/A Slight
Beneficial
Insubstantial
GIC10 Moderate/
Substantial
Moderate/
Substantial
CM1, CM5 to
CM8
OM1 to OM5 Moderate
Adverse
Moderate
Beneficial
Slight/Moderate
Beneficial
GIC11A Moderate/
Substantial
Moderate/
Substantial
CM1, CM5 to
CM8
OM1 to OM5 Moderate
Adverse
Moderate
Beneficial
Slight/Moderate
Beneficial
GIC11B Moderate/
Substantial
Moderate/
Substantial
CM1, CM5 to
CM8
OM1 to OM5 Moderate
Adverse
Moderate
Beneficial
Slight/Moderate
Beneficial
GIC11C N/A Moderate/
Substantial
CM1, CM5 to
CM8
OM1 to OM5 N/A Moderate
Beneficial
Slight/Moderate
Beneficial
GIC12 Insubstantial N/A CM1, CM5 to
CM8
OM1 to OM5 Insubstantial N/A N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-158 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation Day 1 Operation Year
10
R1 N/A Insubstantial CM1, CM5 to
CM8
OM1 to OM5 N/A Insubstantial Insubstantial
R2 N/A Insubstantial CM1, CM5 to
CM8
OM1 to OM5 N/A Insubstantial Insubstantial
R3 Substantial Slight/
Moderate
CM1, CM5 to
CM8 OM1 to OM5 Moderate/
Substantial
Adverse
Slight
Beneficial
Insubstantial
R4 Substantial Slight/
Moderate
CM1, CM5 to
CM8
OM1 to OM5 Moderate/
Substantial
Adverse
Slight
Beneficial
Insubstantial
R5 N/A Insubstantial CM1, CM5 to
CM8
OM1 to OM5 N/A Insubstantial Insubstantial
R6 Slight
N/A CM1, CM5 to
CM8
OM1 to OM5 Insubstantial N/A N/A
R9 Slight Insubstantial CM1, CM5 to
CM8 OM1 to OM5 Insubstantial Insubstantial Insubstantial
R10 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
R11 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
R12 Slight Insubstantial CM1, CM5 to
CM8 OM1 to OM5 Insubstantial Insubstantial Insubstantial
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-159 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation Day 1 Operation Year
10
R13 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
R14 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
R15 N/A Insubstantial CM1, CM5 to
CM8 OM1 to OM5 N/A Insubstantial Insubstantial
R16 N/A Slight CM1, CM5 to
CM8
OM1 to OM5 N/A Insubstantial Insubstantial
R17 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
R18 Slight N/A CM1, CM5 to
CM8
OM1 to OM5 Insubstantial N/A N/A
RE1 Slight Slight CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
RE2 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
RE3 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
RE4 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
RE5 Slight Insubstantial CM1, CM5 to
CM8 OM1 to OM5 Slight
Adverse
Insubstantial Insubstantial
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-160 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation Day 1 Operation Year
10
RE6 N/A Moderate CM1, CM5 to
CM8
OM1 to OM5 N/A Slight/
Moderate
Beneficial
Slight
Beneficial
RE7 Moderate N/A CM1, CM5 to
CM8
OM1 to OM5 Slight/
Moderate
Adverse
N/A N/A
RE8 N/A Moderate CM1, CM5 to
CM8 OM1 to OM5 N/A Slight/
Moderate
Beneficial
Slight
Beneficial
RE9 N/A Moderate CM1, CM5 to
CM8
OM1 to OM5 N/A Slight/
Moderate
Beneficial
Slight
Beneficial
RE10 N/A Moderate/
Substantial
CM1, CM5 to
CM8
OM1 to OM5 N/A Moderate
Beneficial
Slight/Moderate
Beneficial
RE11 Slight Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Insubstantial Insubstantial Insubstantial
RE12 Slight N/A CM1, CM5 to
CM8 N/A Insubstantial N/A N/A
RE13 Moderate N/A CM1, CM5 to
CM8
N/A Slight/
Moderate
Adverse
N/A N/A
RE14 Slight N/A CM1, CM5 to
CM8
N/A Insubstantial N/A N/A
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-161 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
VSR
ID. No.
Significance Threshold Before
Mitigation
(Insubstantial, Slight, Moderate,
Substantial)
Recommended Mitigation Measures Residual Impact After Mitigation
(Insubstantial, Slight, Moderate, Substantial)
Construction Operation Construction Operation Construction Operation Day 1 Operation Year
10
T1 Moderate Moderate CM1, CM5 to
CM8
OM1 to OM5 Slight/
Moderate
Adverse
Slight/
Moderate
Beneficial
Slight
Beneficial
T3 Moderate Insubstantial CM1, CM5 to
CM8
OM1 to OM5 Slight/
Moderate
Adverse
Insubstantial Insubstantial
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-162 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
9.11.6 Summary of Residual Impacts on Landscape Resources and Landscape Character Areas
9.11.6.1 Residual Impacts on Landscape Resources and Landscape Character Areas are
described in Tables 9.22 and 9.23 respectively.
9.11.6.2 LR6, amenity area, will experience moderate adverse residual impacts during the
construction phase, due to the felling of trees and loss of amenity area to accommodate
the Western Works Area and Ventilation Building. Within the operation phase, impacts
are slight and are considered beneficial, due to compensatory roadside tree and shrub
planting and construction of approximately 4,900 square metres of amenity area as
referred to in the report as RE10 Kai Tak South Apron: Amenity Area (refer to Figure
9.11.2). In addition, there will be comprehensive greening to roofs and associated
structures of the Tunnel Portal and Ventilation Buildings which help blend the Project
into the surrounding landscape (refer to Figures 9.12.1 to 9.12.4). By Year 10 of
operation, residual landscape impacts are considered slight and beneficial in nature.
9.11.6.3 LR8, derelict / disturbed land, will experience moderate adverse residual impacts during
the construction phase, due to the loss of hard standing to accommodate the Western
Works Area. Within the operation phase, impacts are slight and are considered
beneficial, due to compensation by approximately 4,900 square metres of amenity area
as referred to in the report as RE10 Kai Tak South Apron: Amenity Area (refer to
Figure 9.11.2). By Year 10 of operation, residual landscape impacts are considered
slight and beneficial in nature.
9.11.6.4 LR12, water body, will experience slight adverse residual impacts during the
construction phase, due to the barges carrying materials to and from a temporary
barging point located on the sea wall. Within the operation phase the barging point will
be removed and impacts on Day 1 and Year 10 are considered insubstantial.
9.11.6.5 LR16, derelict / disturbed land in the Eastern Works Area, will experience slight
adverse residual impacts during the construction phase, due to loss of one tree, a
Macaranga tanarius, and hard standing to accommodate the Eastern Works Area. The
tree will be mitigated by trees, shrubs and amenity space created in the Western Works
Area by the Project (refer to Figure 9.11.2). Within the operation phase the impacts on
Day 1 and Year 10 are considered insubstantial. The site will be reinstated and handed
over for future development of Cha Kwo Ling Promenade Park under a separate project.
9.11.7 Impacts on Landscape Character Areas
9.11.7.1 LCA1, derelict / disturbed land, will experience moderate adverse residual impacts
during the construction phase, due to the loss of hard standing to accommodate the
Western Works Area. Within the operation phase, impacts are slight and are considered
beneficial, due to compensatory roadside tree and shrub planting and compensation by
approximately 4,900 square metres of amenity area as referred to in the report as RE10
Kai Tak South Apron: Amenity Area (refer to Figure 9.11.2). By Year 10 of operation,
residual landscape impacts are considered slight and beneficial in nature.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-163 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
LCA3, amenity area, will experience moderate adverse residual impacts during the
construction phase, due to the felling of trees and loss of amenity area to accommodate
the Western Works Area and Ventilation Building. Within the operation phase, impacts
are slight and are considered beneficial, due to compensatory roadside tree and shrub
planting and construction of approximately 4,900 square metres of amenity area as
referred to in the report as RE10 Kai Tak South Apron: Amenity Area (refer to Figure
9.11.2). In addition, there will be comprehensive greening to roofs and associated
structures of the Tunnel Portal and Ventilation Building which help blend the Project
into the surrounding landscape (refer to Figures 9.12.1 to 9.12.4). By Year 10 of
operation, residual landscape impacts are considered slight and beneficial in nature.
9.11.7.2 LCA4, water body, will experience slight adverse residual impacts during the
construction phase, due to the barges carrying materials to and from a temporary
barging point located on the sea wall. Within the operation phase the barging point will
be removed and impacts on Day 1 and Year 10 are considered insubstantial.
9.11.7.3 LCA7, derelict / disturbed land in the Eastern Works Area, will experience slight
adverse residual impacts during the construction phase, due to loss of one tree, a
Macaranga tanarius, and hard standing to accommodate the Eastern Works Area. The
tree will be mitigated by trees, shrubs and amenity space created in the Western Works
Area by the Project (refer to Figure 9.11.2). Within the operation phase the impacts on
Day 1 and Year 10 are considered insubstantial. The site will be reinstated and handed
over for future development of Cha Kwo Ling Promenade Park under a separate project.
9.11.8 Impacts on Visually Sensitive Receivers
9.11.8.1 At the Eastern Works Area, upon implementation of mitigation measures, VSRs with
moderate to substantial residual impacts in the construction phase are R6, R7, R8, R19,
and O20. They have close and direct views onto the construction site and are also
impacted by additional barges within Victoria Harbour. There will be no impacts onto
the Eastern Works Area after completion of the construction phase, as after the
operational stage the site will be handed back to CEDD, where the site is planned to be
developed into the Cha Kwo Ling Promenade and Park. VSRs with slight to moderate
residual impacts in the construction phase are O19, R3, R4, RE7, T1, T2 and T3 and the
remaining VSRs will experience visual impacts of insubstantial significance.
9.11.8.2 Upon implementation of mitigation measures, within the Western Works Area in the
construction phase, VSRs O14, GIC10, GIC11A, GIC11B, R3 & R4 will experience
moderate to substantial residual impacts. This is due to the T2 works area being
adjacent to the VSRs in the construction phase. VSRs with slight to moderate residual
impacts in the construction phase is O4. O5, O6, O7, O10, O12, O16, O18, RE5, RE7,
RE13, T1 and T3 and the remaining VSRs will experience visual impacts of
insubstantial significance. As a large area of the KTD Runway Precinct and South
Apron will also be under construction at the same time, the residual impacts within the
western area are not viewed as adverse and cumulative impacts are not considered to be
unacceptable within such a context.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-164 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
9.11.8.3 Residual visual impacts to a majority of VSRs in the Western Works Area in the
operation phase will be of slight to insubstantial significance, except for the VSRs
GIC10, GIC11A, GIC11B, GIC11C, and RE10 which will experience moderate visual
impacts and VSRs O6, O7, O11, O13, O14, GIC6, GIC7, GIC8, GIC9, R3, R4, RE6,
RE8, RE9, and T1 that will experience visual impacts of slight to moderate significance.
Despite the presence of physical above ground structures the residual visual impacts
could be considered to be positive, since the structures are sensitively designed and
extensive greening and tree planting will be in place to improve the overall visual
experience of the structures and the surrounding area.
9.12 Cumulative Landscape & Visual Impacts
9.12.1 Concurrent Projects
9.12.1.1 The landscape and visual impacts generated by the Project are assessed in the context of
associated impacts of concurrent projects.
9.12.1.2 Previously the Kai Tak Development (KTD) was a disused airport runway. On
regenerating the area into a high-end mixed use development, the KTD will create a
multifunctional mixed use area, providing various government, occupational, residential
and recreational facilities for the Kowloon Bay and Hong Kong areas as a whole.
9.12.1.3 Trunk Road T2 is to be constructed in conjunction with two other Route 6 Projects; the
CKR Route (Western Kowloon – Kai Tak) in the western South Apron area and the
Tseung Kwan O - Lam Tin Tunnel Interchange at the eastern end, forming a major
transportation route within the Kowloon Peninsula. For the CKR & TKO-LTT Route 6
projects that interface with the Project, separate EIAs have been carried out. The CKR
and the Trunk Road T2 connect at the South Apron area running north west to south
east directly through the site, while the Trunk Road T2 & TKO LTT will join at the
Lam Tin Interchange.
9.12.1.4 The Project and associated buildings will be viewed from the north by the Kowloon Bay
commercial area, comprised of newly built high rise commercial developments. From
the south and south eastern areas, a cruise terminal, hotels, residential developments, a
government hospital, and other related medical centers would be either in construction
or are planned. Due to the increase in developments within the area, the Trunk Road T2
will play a vital role in providing public access for the growing urban population and
linking the Kai Tak Development to both the immediate local areas and Hong Kong as a
whole.
9.12.1.5 The Trunk Road T2 and associated buildings have insubstantial impacts to the area and
are in keeping with the contemporary character of the proposed KTD. Trunk Road T2
and associated buildings will be commissioned by the end of 2020, in coordination with
both the CKR and TKO-LTT Route 6 projects.
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-165 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
9.12.2 Impacts on Landscape Resources and Character Areas
9.12.2.1 Impacts on existing Landscape Resources and Character Areas will be mitigated in the
construction and operation phases.
9.12.2.2 The cumulative impacts of the Project on Landscape Resources and Character Areas in
the Western and Eastern Works Areas are listed below:
Western Works Area, temporary loss of 75,300 square metres and a permanent
loss of 8500 square meters of hard standing, 5029 square meters of planting areas
and loss of 66 trees. This will be mitigated by 15,740 square meters of planting
areas and 4,900 square meters of Amenity Area as referred to in the report as
RE10 Kai Tak South Apron: Amenity Area. Extensive compensatory planting will
include 152 trees in accordance with ETWB TCW No. 3/2006 (refer to Figure
9.11.2). Within the operation phase, impacts are slight and are considered
beneficial.
Eastern Works Area: no planting areas will be lost as the site is currently hard
standing. An approximate area of 21,500 square metres of hard standing will be
lost for the Eastern Works Area site offices. One tree, a Macaranga tanarius
which is not considered suitable for transplanting is recommended to be felled.
Mitigation for the felled tree has been included within the compensatory trees for
the Western Works Area in accordance with ETWB TCW No. 3/2006 (refer to
Figure 9.11.2). The site will be reinstated and handed over for future
development of Cha Kwo Ling Promenade Park under a separate project.
9.12.2.3 If the Trunk Road T2 and associated buildings were the only developments in the area,
the discussed landscape and visual impacts would appear more significant. As the
Project is scheduled to be constructed at the same time as many KTD proposed
developments, it would appear to blend into the South Apron Development with
landscape mitigation measures. As a large area of the KTD Runway Precinct and South
Apron will also be under construction at the same time, the residual impacts within the
western area are not viewed as adverse and cumulative impacts are not considered to be
unacceptable within such a context.
9.12.2.4 On assessing the Project within the context of the CKR & TKO LTT Route 6 Projects
and the KTD RODP plan for other proposed developments, and reviewing the
cumulative impacts generated by the Trunk Road T2 and associated buildings, it is
considered compatible with the surrounding proposed landscape. Mitigation measures
will include extensive compensatory tree and shrub planting, sensitive design and
architectural detailing, and finishing of built structures and provision of new public
amenity area.
9.13 Summary and Conclusions
9.13.1 For the construction phase of the Trunk Road T2 within the Eastern Works Area, there
are anticipated to be only very limited impacts, due to the relatively small amount of
construction works to be carried out in the Eastern Works Area. Upon implementation
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-166 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
of mitigation measures, VSRs R6, R7, R8 and R19 will be affected due to their being
adjacent to the works area throughout the construction phase. However, they will only
be affected by excavation of the receiving shaft early in the Project, and later the
extraction and removal off-site of the tunnel boring machine. There will be no visual
impacts by the Project in the Operation Phase.
9.13.2 For the construction phase of Trunk road T2 within the Western Works Area, upon
implementation of mitigation measures, VSRs O14, GIC10, GIC11A, GIC11B, R3 &
R4 will experience moderate to substantial residual impacts. This is due to the T2 works
area being adjacent to the VSR’s in the developments through the construction phase.
VSR’s with slight to moderate residual impacts in the construction phase are O4. O5,
O6, O7, O10, O12, O16, O18, RE5, RE7, RE13, T1 and T3 and the remaining VSR’s
experience visual impacts of insubstantial significance. As a large area of the KTD
Runway Precinct and South Apron will also be under construction at the same time, the
residual impacts within the western area are not viewed as adverse and cumulative
impacts are not considered to be unacceptable within such a context.
9.13.3 On completion of the Project, the majority of Trunk Road T2 is underground, except for
the low rise (+17mPD) Ventilation Building, Tunnel Portal Building and refuse
collection building. In the Western Works Area, there will be a temporary loss of
75,300 square metres and a permanent loss of 8500 square meters of hard standing and,
5029 square meters of planting areas will be permanently lost. This will be mitigated by
15,740 square meters of planting areas and 4,900 square meters of Amenity Area as
referred to in the report as RE10 Kai Tak South Apron: Amenity Area. 98 trees will be
impacted upon. 67 trees are recommended to be felled and 31 are proposed to be
transplanted to a location that will be identified at a later stage of the project. Extensive
compensatory planting will include 152 trees in accordance with ETWB TCW No.
3/2006 (refer to Figure 9.11.2). In the Eastern Works Area one tree and an approximate
area of 21,500 square metres of hard standing will be lost. Mitigation for the felled tree
has been included within the compensatory trees for the Western Works Area. The site
will be reinstated and handed over for future development of Cha Kwo Ling Promenade
Park under a separate project. Details of the landscape proposals for the Western Works
Area will be reviewed within the detail design stage. It is considered there will be no
substantial adverse landscape and visual impacts by the Project during the operation
phase.
9.13.4 For VSRs in the Kowloon Bay area having southern views towards the development,
Trunk Road T2 and associated buildings are considered to be in context with the future
developments in the South Apron and KTD.
9.13.5 The tunnel portal and refuse collection building would be sensitively designed and
proposed to be no higher than 17mPD (Figures 9.12.1 – 9.12.4). Mitigation measures
including vertical greening and tree planting are proposed to be provided. The overall
visual impacts on the surrounding VSRs would not be significant and could be
considered positive to a certain extent.
9.13.6 Due to the intended 2021 completion dates of the Kai Tak Development including the
Metro Park, Runway Residential and Hotel Precinct, the Cruise Terminal and Tourism
Final EIA Report – Section 9: LVIA (F0143-EB000560-MIEL-HKR-02)
July 2013 Page 9-167 l:\environ\91164e trunk road t2\reports\public inspection\final eia report\09 lvia.doc
and Leisure Hub, three hospital sites and other government buildings, views from the
Victoria Harbour and Southern Kowloon areas will be screened and covered.
Substantial adverse visual impacts are not expected.
9.13.7 Overall, it is considered that the residual landscape and visual impacts of the Project are
acceptable with mitigation measures during construction and operation phases.