9 March 2005 OT Meeting - LHCb week - Production and QA , Nie ls Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules Production Progress Quality Assurance

Upload: priscilla-wells

Post on 20-Jan-2016

222 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

1/19

Outer Tracker Module Production at NIKHEF

• Produced 60 modules Production Progress Quality Assurance

Page 2: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

2/19

Module Production at NIKHEF

Courtesy of Jan Spelt

Page 3: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

3/19

50% Milestone met

15/05/2003: EDR (Engineering Design Review)

02/2004: 10% prod.

04/2004: EDR(Electronics Design Review)

05/2004: PRR(Production Readiness Review)

03/2005: 50% prod.

12/2005: 100% prod

Page 4: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

4/19

Module Production at NIKHEF (1)

Module Date Logbook0 April Gas Tightness

1 May Curved panels discovered

2-3 June Self-sustained currents

4 July Changed to Ar/CO2 70/30

5 July Discovered bad wire quality

6-8 August OK

9 August Changed threshold HV in air 20100 nA

10-15 September OK

16 October Second team of (Russian) technicians started

17-18 October OK

19 October Observed loose soldering connections

20 October OK

21 November Double glue on side walls

22-25 November OK

26-30 November Low response on 1side

29 November Bad wire quality in HV in air, and tripping Sr scan

30 December Bad wire quality in HV in air, and tripping HV in gas

31 December Being build today

32 November Panel glueing with ropes

Poor man’s logbook

Page 5: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

5/19

Module Production at NIKHEF (2)

Module Date Logbook32-38 December OK

39 January Use 90Sr point source

40-48 January OK

49-57 February OK

58 March 4 broken wires

59-60 March OK

Poor man’s logbook

Page 6: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

6/19

Module Production at NIKHEF (3)

• Production process: some minor problems:

Watch glue on connectors Module 58: 4 broken wires Module 59: peculiar wire response

Page 7: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

7/19

Glue on Connector (1)

Traces of glue.Affects leakage currentfor wires 1 and 64 (~20-100nA)

Page 8: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

8/19

Glue on Connector (2)

Traces of glue.Affects leakage currentfor wires 1 and 64 (~20-100nA)

• Discovered on Heidelberg modules 21 and 22• 8 channels with high currents (10 – 270 nA)

• Checked at NIKHEF: found 6 wires• 64L: M16A M19A M26A• 1L: M20A M26A M41B

• Investigated influence of humidity on M16 and M19:1) measure current after production;2) measure current after drying;3) put module in cold, wet environment (= outside);4) measure current;5) scratch of glue;6) measure current.

After production

Drying Cooling Humidity Scratching

Date 26/10/2004 16/02/2005 16/02/2005 17/02/2005 17/02/2005

Time 10:00 16:00 10:00 17:00

M16A, ch 64L 7 nA 0.5 nA 5 nA 15 nA 0.2 nA

M19A, ch 64L 8 nA 0.3 nA 23 nA 1.9 nA 0.1 nA

Page 9: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

9/19

Broken wires in Mod 58

• Discovered 4 broken wires in Mod 58• History:

23 Feb Wired full panel

24 Feb 50U broken

01 Mar 60U broken, just before gluing module

04 Mar 56U short circuit

07 Mar 55U short circuit after shaking the module

• Hypothesis: Middle print tilted ?

?

Page 10: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

10/19

Selection of 10% spares

• We foresee 10% spares• Which ones would we select as spares?• How many bad channels are we left with?

Page 11: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

11/19

Quality Criteria

• Not used in quality criteria now: HV in air : correlated to the 90Sr numbers HV training : correlated to the 90Sr numbers Wire Tension: OK.

• Ignore modules 5012 and 0… Consider only modules 1-60

Number of bad wires from 90Sr scan.

Define bad: Low response: <15% on average

• Typically disconnected due to tripping HV supply High response: >15% on average

• Typically noisy High response: >100% at any place on the wire

• Spikes• Self-sustained currents• Missing wire locators

Page 12: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

12/19

Module Data (1)

Page 13: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

13/19

Module Data (2)

Page 14: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

14/19

Module Data (3)

• Module 60 about to be scanned…• Just found peculiar wire in Mod 59:

Low current, then self-sustained current

Being investigated

90Sr source Position

C

urre

ntWire locator

position

Page 15: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

15/19

Module Selection

N Mod <15% >15% >100% Total Comment“Disconnected”

“Noisy” “Suspicious”

1 1 2 0 9 11 Self-sustained currents

2 2 0 0 3 3 Self-sustained currents

3 3 0 0 2 2 Self-sustained currents

4 5 0 1 4 5 Bad wire

5 29 1 4 0 5 Bad wire

6 58 2 0 0 4 Broken wires

The rest 7 7 3 17 Out of 55*256 channels = 1.2‰

Selection of 6 worst modules:

Page 16: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

16/19

The worst modules from the rest…

• Probably module 16, 26 or 30:

N Mod <15% >15% >100% Total Comment

1 16 0 2 0 2

2 26 0 0 1 1

3 30 2 1 0 3

Rest 5 4 2 11 Out of 55*256 channels = 0.8‰

Page 17: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

17/19

Special Tests

• Weighing all panel and module components Calculate X/X0

• Survey of module flatness Requirement: dZ < +/- 500 um Result: dZ < +/- 400 um

• Humidity of modules Compare in-leak between leaky and gas-tight

module Confirm gas-tightness requirements

see Peter

LHCb 2004-114

in preparationLHCb 2005-009

Page 18: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

18/19

Summary

• Production: Only minor changes in production

process Satisfactory production speed

• Wire quality very good now• Gas tightness OK, with occasional leaky exceptions• 17 bad channels in best 90% of the modules = 1.2 ‰

• 11 bad channels in best 85% of the modules = 0.8 ‰

Page 19: 9 March 2005OT Meeting - LHCb week - Production and QA, Niels Tuning 1/19 Outer Tracker Module Production at NIKHEF Produced 60 modules  Production Progress

9 March 2005 OT Meeting - LHCb week - Production and QA , Niels Tuning

19/19

References

• LHCb week September 2004, Chia Scan of 4 Warsaw modules NIKHEF – Results Mod 0-10

• LHCb week December 2004, CERN NIKHEF - Module glueing, Connector

soldering

• OT meeting February 2005, Warsaw NIKHEF - Module selection 1-50

All quality plots for each module can be found here:http://www.nikhef.nl/pub/experiments/bfys/lhcb/outerTracker/QualityPlots/