971375 environmental impact assessment of typical road project
TRANSCRIPT
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
1/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 1
Environmental Impact Assessment ofTypical Road Project
CHAPTER ONE
1.0 INTRODUCTION
The Project area state plays a very important role in the development of state.
The significance of good roads in the countrys quest for infrastructure and
industrial development is well recognized. However, wide range of environmental
problems resulting from uncontrolled industrial growth, urbanization and resource
exploitation today seriously threatens the natural environment. The consciousness
and concern about this is now worldwide and has necessitated a number of
international conventions and summits. Environment was described as the global
issue of the year in 1970.
This concern culminated in the 1972 Stockholm Conference on the environment.
Environmental issues have since gained prominence in national and international
statutes and conventions, amongst the latest of which arose from the Rio Global
Environmental Summit of 1992. All sectors of the global society now acknowledge
the centrality of environment to human existence. The promotion of human dignity
is linked to the right to a healthy environment, this right highlights the dynamics of
relationship between the individual and society, the danger of serious damage to
land and sea and to the climate, flora and fauna, calls for profound change in way
we manage the environment, particularly in the richer countries.
1.1 Background
Prior to embarking on any major project, activity or development in Nigeria it is
mandatory that the proponent carries out a study to ascertain the likely impacts,
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
2/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 2
adverse and/or beneficial and the extent of these impacts on the physical,
biological and human socio-economic environment. Throughout all stages of the
project from its planning phase to operational and decommissioning phases the
proponent shall ensure that all identified adverse impacts addressed in different
stages of the project. One of the most important aspects of the E.I.A process is
consultation with the communities, stakeholders and the regulatory agencies.
1.1.1 Country Location.
Nigeria, lying between latitudes 40and 14
0North of the equator and longitudes 30
and 140 East of the Greenwich Meridian on the West coast of Africa, covers an
area of 923,768km2. Chad and Niger Republics to the North, Cameroon to the
East, Republics of Benin and Togo to the West and the Atlantic Ocean to the
South border it. With a population of about 130million, it is the most populous
black African nation in the world. Socio-economic activities include commerce,
agriculture (farming/fishing),
1.1.2 Project Location
The project traverses Local Government Areas viz: Askira/Project area Local
Government, Borno State (Fig. 1.1), and lies between latitudes 302220E and
268001E and between longitudes 1157159N and 1191258N. The route is on a dry
savanna terrain of light mangroves, bush and especially but gradually yielding to
encroachment by human activity. Agriculture is mainly subsistence farming, and
driving forms the main occupation of the people. The topography of the area is
relatively flat, and it is characterized by sandy clayey topsoil, and savanna
vegetation.
1.1.3 Vegetation
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
3/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 3
Vegetation of the study areas are characterised by Sub sudan zone and the
Northern Guinea Savanna. The sub sudan zone marked by short grasses and
interspersed by short tree.The grassland along the bank depends to a large extent
on the floodplain boundaries during the rainy season.
1.1.4 Area Geology
The geology of the study area falls within the Bima Sandston of the lau basin. The
adjoining area is predominantly savanna ecosystem. The scattered trees along the
project area are mature and fully developed, with a height of over 25 m and a girth of
about 2 m. The entire zone is rich in species and therefore very highly fragile and
sensitive to development activities.
The proposed project lies within the Lau basin early Tertiary sediment build-up.
Geologically, Extensive deposits of sandstone occur north and south of the basin
underlie the study area and environs. This formation, which comprises chiefly soilsandy, clay stone shaley, and granite, weathered and fractured.
Subsurface in the area is made up of a few metres thickness of sandstone fairly
cemented, clay stone shaley of the first 23 to 72 m. Between depths of 72 to 107m,
the lithology may include Mudstone, dark grey, granite, weathered and fractured.
Thin beds of fine sands may alternate with sandy clay beds.
Good aquifers may be encountered at depth below 60. In most cases, however, clean gravel
sand alternate with confining black greyish clays between depths of 55 to 70m. In fact, most
boreholes have gone as deep as 90 to 100 m tapping sand and gravel beds as aquifers.
1.1.5 Climate
The study area experiences a dry/hot tropical climate. The region experiences two distinct
weather seasons the dry season from November to March and the wet season from April
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
4/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 4
to October although rain falls throughout the year. The rainfall pattern exhibits maxima with
peak in August. Average annual rainfall is about 750-1000mm distributed over every month
with 80% received during the rainy season. Wind speed is generally high with annual mean
of 6.7 m/second and is mostly in the south-westerly, southerly to westerly direction. Higher
wind speed tends to occur during the dry season months and at the beginning of the wet
season.
1.2 The Proponent
The proponent is the Federal Ministry of Works and Housing Abuja. The ministry is
involved in the infrastructure and logistic aids development and maintenance. These
infrastructures such as roads and bridges are distributed throughout the Federation. More
than 32000 km of roads have been constructed or rehabili tated by the present
administration.
1.3 The Project
The Federal Ministry of Works proposes to embark on the development of new road
project within the Borno State. This is part of Federal Governments efforts at opening up
the area given its place as one of the main contributor to the economy of the country.
Borno is home to companies involved in the exploration and exploitation of minera
resources for domestic and commercial purposes.
It is now proposed by the FMW to construct a road that would cover Project area road
with paved s houlders and strengthening the exis ting one by
overlays/rehabilitation/reconstruction.
Existing cross-drainage structures on the route are proposed to be repaired/rehabilitated.
New cross-drainage structures would be provided on the new ne carriageway. In addition
to strengthening the existing carriageway, the project would improve the geometric
deficiencies including the improvement of any intersection encountered. The proposed
improvement aims at enhancing the riding quality, improving journey speed and reducing
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
5/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 5
congestion of traffic on the highway. It is proposed to provide service roads, proper
drainage, grade-separation, road furniture, utilities and amenities wherever required. The
project highway pass es through 5 major towns and 15 village settlements.
1.4 Legal And Administrative Framework
Some statutory regulations exists, which, require that a Development Permit for any new
project and those that require the proponent of a major/mandatory project to submit an
EIA, study report prior to the execution and before an approval for project execution. The
Project area is subject to many other specific statutes, guidelines and standards that
ensure compliance with environmental pollution abatement in facilities that generate
wastes, groundwater protection and surface impoundment, health and safety, and
hazardous substances. These statutory regulations are summarized or tabulated below:
1.4.1 Landuse Act 1978
The Landuse Act was promulgated in 1978 with commencement date of March 29, 1978.
It vests all land in each State of the Federation (except land already vested in the Federal
Government of Nigeria or its agencies) in the Governor of the State. It makes the State
Government the authority for allocating land in all urban areas for residential, agricultural,
commercial and other purposes, while it confers similar powers regarding non-urban
areas on the local governments in such cases. The governor of a State can revoke a
right of occupancy for overriding public interest (e.g. new road development purposes)
The following surface rights are permitted under Section 51 of the Landuse Act:
fishing rights
buildings and other structures, juju shrines, objects of worship
farms, cultivated crops, economic trees, roads
loss of use of the land.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
6/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 6
1.4.2 Federal Ministry of Environment, FMEnv
The Federal Ministry of Environment is now the apex institution in Nigeria charged with
the overall responsibility for the protection and development of the environment,
biodiversity conservation and sustainable development of Nigerias natural resources.
The Ministry grants permits for environmental and laboratory consultancies and must
approve an EIA study of a major development activity such as this one before the
proponent can implement execution.
1.4.3 Federal Environmental Protection Agenc y, FEPA, Act No. 58, 1988
The decree which was issued in 1991, provides National Interim Guidelines and
Standards for industrial effluents, gaseous emissions, noise, air quality and hazardous
wastes management for Nigeria
1.4.4 Environmental Impact Assessment Act No. 86, 1992EIA Act No. 86 decree, became operational on 10
thDecember 1992, provides guidelines
for activities, in which EIA is mandatory in Nigeria. Such developments include the
following:
Coastal reclamation involving an area of 50 hectares or more;
Conversion of mangrove swamps for industrial use covering an area
of 50 hectares or more
New road development.
This process involves the undertaking of mandatory study/meditation or
assessment by a review panel and the preparation of a mandatory EIA
report.
1.4.5 Former FEPA Regulations
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
7/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 7
The Federal Ministry of Environment through former FEPA has the following
other regulations, policies and guidelines:
(a) The National Policy on Environment, FGN 1989
(b) National Guidelines and Standards for Environmental Pollution Control
in Nigeria.
(c) National Effluent Limitations Regulations S.1.8, 1991, lists the
parameters in industrial effluents and gaseous emissions and their
limitations and standards for discharges into the environment.
(d) National Pollution Abatement in Industries and Facilities Generally
Wastes Regulations S.1.9 1991 requires every industry to install anti
pollution abatement equipment to treat effluent discharges and gaseous
emissions to the s tandards and limits prescribed in Regulations S.1.8
(e) Was te Management and Hazardous Wastes Regulations S.1.15
1.4.6 World Bank Guidelines and Requirements on Environmental Assessment
World Bank requires the execution of an EIA on a proposed industrial activity by a
borrower as a pre-requisite before granting any financial assistance in form of loans.
Details of World Banks EIA procedures and guidelines are published in the Banks EA
Source Book vols. I-III of 1991. Potential issues considered for EA include the following:
Biological Diversity
Coastal and Marine Resources Management
Cultural Properties
Hazardous and Toxic Materials and
International Waterways.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
8/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 8
This project is a Category A project, because of its cumulative magnitude of
environmental and social impacts, and therefore requires full environmental analysis and
assessment. The emphasis of the World Bank is an integration of the mitigation measures
into the project design and mainstreaming environment in all stages of planning,
implementation and operation.
It may also be pertinent to note that while the World Bank requirements now have been
modified and new projects must conform to the OD 4.01, this project was identified and
the individual environmental assessments were prepared within the framework of OD
4.01 only.
1.4.7 Forestry Law CAP 52, 1994
Forestry Law CAP 51 OF Lagos is the only substantive legislation applicable to all parts
of the federation. The law prohibits any act that may lead to the destruction of or causeinjuries to any forest produce, forest growth or forest property. The law prescribes the
administrative framework for the management, utilization and protection of forestry
resources in Nigeria. This law is applicable to the mangrove forest of the Niger Delta.
A list of Nigerian laws and regulations enacted at various times since 1963, that are
concerned with environmental protection are tabulated hereunder.
1.4.8 Federal Ministry of Works Regulations
It is in compliance with the above national and International regulations and the newly
established Ministry of Works HSE policy and guidelines that this EIA studies on the
proposed action is being undertaken.
FMW is committed to its environmental management policy by complying with relevant
legislation covering various environmental effects arising from the construction and
operation of the proposed road project, including noise, gaseous emission, particulate,
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
9/168
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
10/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 10
Manage HSE matters as any other activity
Promote a culture in which all FMW em ployees share this commitment.
Pursue the goal of no harm to people while executing its projects and
other activities.
Protect the environment
Use material efficiently to provide quality products and services.
Develop infrastructures, products and services consistent with these aims
Consult with our stakeholders and publicly report on our performance
Play a leading role in promoting best practice in our in the Ministry.
Some specific Nigerian Government Laws and regulation related to environmental,
conservation and safety in Nigeria includes but not limited to include the following:
S/No
Document Title And Description Date
1 Mineral Oils (Safety) Regulations 1963
2 Petroleum Regulations 1967
3 Petroleum Act. 1969
4 Trade Dispute Act. 1973
5 Earthing Code of Practice 1976
6 Electricity Supply Regulations (Including Electrical Supply
Act.1929)
1979
7 Wiring Regulations 1979
8 Labour Act 1987
9 Workmens Compensation Act 1987
10 Factories Act 1987
11 Harmful Waste (Special Criminal Provisions, Etc.) Act 1988
12 Federal Environmental Protection Agency Decree No 58 1988
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
11/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 11
13 Gas Industry in Nigeria, Draft Regulations 1989
14 Director of Petroleum and Mineral Resources
Environmental Guidelines and Standards for the Petroleum
Industry in Nigeria
1991
15 S.1.8: National Environmental Protection (Effluent
Limitation) Regulations
1991
16 S.1.9: national Environmental Protection (Pollution
Abatement in Industries and Facilities Generating Waste)
Regulations
1991
17 Federal Environmental Protection Agency Interim
Guidelines and Standards for Environmental Pollution
Control in Nigeria
1991
18 Environmental Impact Assessment Decree No. 86 1992
19 S.1.14 Oil and Gas Pipelines Regulations 1995
20 Endangered Species Act No. 11 1985
1.5.9 Borno State Environmental Protection Agency, (BSEPA)
The Edict setting up the Borno State Environmental Protection Agency (BSEPA)
outlines the primary responsibilities of the agency, which is to protect and develop
the general environment of Borno State.
The EIA Act No 86 of 1992 is the substantive law that regulates the
siting of projects that impinge on environmental elements in Nigeria, the state in
which each project is located has a major role to play in the overall EIA process as
a matter of law.
Es tablishment and implementation of the numerous strategies of the
National Policy on Environment towards achieving sustainable
development;
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
12/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 12
Implementation of applicable existing edicts on activities related to
the environment.
Monitoring the implementation of EIA and Environmental audit (EAR)
guidelines and procedure on all developed policies and project within
the state.
Responsibility for general environmental matters in the state
including the negative effects of soil degradation due to oil and
mineral exploitation and exploration.
1.6 Environmental Impact Assessment Process in The Project
The environmental impact assessment for the project employed a reiterative approach in
which environmental issues have been identified in successive levels of detail and
specificity at each step in the process. Incorporation of feedback from the variousstakeholders as well as 'public hearings' and analyzing were essential features of this
methodology.
The following were the stages of environmental impact assessment of the project
Initial Environmental and Social Screening (IESS): An IESS s tudy of the project
had been carried out as part of the feasibility study, to categorise the corridor into
sections based on environmental and social sensitivity, and to screen significant
environmental and social issues that needed to be addressed.
Documentation of Baseline Conditions: The potentially affected area (PAA) was
defined and the baseline conditions were documented.
Assessment of Potential Impacts: Potential s ignificant impacts were identified on
the basis of an analytical review of baseline data.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
13/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 13
Integration of Environmental Assessments in the Design Process: The design and
decision-making process integrated environmental and resettlement and
rehabili tation issues and prompted the early identification of appropriate actions, as
shifts in alignments based on awareness of the locations of cultural resources.
Assessment of Alternatives : Alternatives were continuously assessed throughout
the process. A more formal assessment was also undertaken as a part of the
environmental assessment process, including the assessment of the 'No Action'
Alternative.
Mitigation & Enhancement Measures: Positive actions to not only avoid advers e
impacts, but to capitalize on opportunities to correct environmental degradation or
improve environmental conditions were determined. The mitigation measures
would be directed towards the restoration of the dynam ic balance of nature.
Community Consultation: Consultations with concerned officials, agencies and
potentially affected persons continued through out the process and will continue as
the project proceeds. The issues raised by the communities and the various
stakeholders were incorporated, as far as possible, in the design andconstruction/operation plan of the project.
Environmental Management Plans (EMP): An EMP for the road section detailing
the measures to be taken for the implementation of the various measures
proposed. This includes the monitoring plan and gives details of the resources
budgeted and the implementation arrangements.
In addition to the EA process as adopted, a further in-depth study of the following issues
has been carried out as part of the OBSG:
Address ing of direct and induced impacts on the various environmental
components;
Specific designs for the mitigation measures provided;
Site specific enhancement designs for elements along the corridor, including
cultural properties, water bodies, bus stops etc;
Redevelopment of borrow areas;
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
14/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 14
Prediction of impacts due to the project on air quality, noise, and provision of
mitigation measures;
Traffic management plans during construction; and
Monitoring mechanisms and indicators during construction and operation periods.
This Environmental Impact Assessment of the proposed road project is part of the
environmental management strategy FMW adopts to ensure preservation of the Nigeria
environment and its resources through sound environmental practices.
The process encourages interacting with the public, government, leaseholders the
contractor and other planning group so that any identified unacceptable environmental
effects of the project are mitigated. Consultation among all stakeholders, especially
among EIA team will ensure that all relevant information regarding design, construction
and maintenance are jointly acceptable.
Acquisition of the baseline data for the assessment was through field surveys,questionnaire administration/interviews supplemented with published data (literature). To
enable the establishment of the existing state of the environment using the criteria set out
in FMEn vs Sectoral EIA Guidelines.
1.6.1 Objectives Of EIA
Specifically, the objectives of conducting the EIA are to:
(i) Identify the exis ting biophysical, chemical and socio-economic setting
of the environment within the context of the road route;
(ii ) Quantitatively and qualitatively evaluate the impacts of the proposed
road construction and operations on the environment;
(iii) Recommend modifications and mitigations plans with change and
control measures to eliminate or decrease identified impacts; and
(iv) Identify means to or rehabil itate damaged environment, including
monitoring programmes.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
15/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 15
Generally the objective of the EIA is aimed at providing a sound basis for
decision making about the design of the project components that takes
environmental considerations into account, ensuring that the project is
implemented with awareness of environmental factors, and that potential
environmental impacts are recognized and addressed.
The work/studies for the full E.I.A consist of field and laboratory
assessments in the following headings:
Biodiversity and Wildlife
Health Risk
Community and Socio-Economic
Air Quality and Noise Level
Water and Soil
Aquatic Biology
Vegetation Waste and Environmental Management
1.7 Terms of Reference, TOR
The objectives of the TOR are to:
collate baseline information available to bekebor and Siama and its
environs
highlight the main environmental concerns to guide execution project.
serve as a liaison product in which the FMW contractors identify the
existing and proposed road
serve as an advance notification to the Regulatory Agencies
especially the Federal Ministry of Environment.
1.8 EIA Premises
The key EIA premises were established to provide general guidance, framework and a
commitment to standards, which are acceptable nationally and internationally. In line with
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
16/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 16
this, the premises will be retained in this study and variations allowed only in
circumstances where there is absolute necessity to do so with supported facts and
evidences. Additional procedures, commitments and understandings necessary to resolve
environmental impact, were developed and adopted through the EIA process. The
premises are as follows:
Federal Ministry of Works recognises the Federal Ministry of
Environment (FMEnv) and the Department of Petroleum
Resources (DPR) National Environmental Guidelines and
Standards for the Petroleum Industry in Nigeria, 1991, and other
laws operating both nationally and internationally. Furthermore,
the project has adopted the best option relevant to the local
circumstances and situations.
The road has been designed to comply with these local and
national laws, together with all the international protocols,
agreements and conventions.
The understandings reached with environmental regulators,
during the course of the EIA process, will be respected and
honoured.
Consultations have and will continue to be held with all
stakeholders at various levels (Federal, State and Local
Governments) together with all communities that will be affected
by the proposed project. Consultation meetings shall be
maintained on a mutually agreed basis.
An Environmental Management programme (EMP) has been
developed as part of the EIA process. The implementation of the
plan will be the responsibility of FMW.
1.9 Implementation Arrangements
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
17/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 17
The OBSG Road Project has been initiated and is being carried out by the FMW,
established as an authority, as a part of the Government of Nigeria. The FMW, through
the Director of Roads in the Ministry will be responsible for the effective implementation of
the project activities. Project
Project Implementation Unit (PIU) with a Project Director as its head have been
es tablished. The PlU would p lay a key role in im plementation including the overall control
of construction activities and implementation of contracts. Consultants have been
appointed for carrying out the feasibility study and preparation of the Detailed Project
Reports and designs for the project packages. To ensure the effective implementation of
the project, Construction Supervision Consultants procured under Competitive Bidding
will support the FMW.
To assess, advise and monitor the environmental performance of the various projects
being planned, designed and implemented by the FMW, an Environmental Unit has been
es tablished at the Corporate Headquarter of the Minis try in Abuja. The EnvironmentalUnit is responsible for the co-ordination of the environmental and social issues of the
various project packages and PlU, and work in close interaction with the environmental
manager.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
18/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 18
CHAPTER TWO
2.0 DESCRIPTION OF THE PROJECT
2.1 Declaration
The Federal Ministry of Works (FMW) on behalf of the Federal Government of
Nigeria hereby declares its intention to embark on a road construction project from
Project area traversing one local government area of Askira/Project area in Borno
State.
Planning, construction and operational stages of this project shall involve the
Federal Ministry of Works:
complying with environmental regulations, laws, statues and edicts.
adopt appropriate measures to mitigate identified and predicted adverse
environmental impacts arising from or associated with the project.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
19/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 19
2.2 Project Execution Strategy/Plan
The execution of the road project will be integrated into the overall plan of the
Federal Government to construct more roads in the country. Engineering Design
Report for the project has been prepared. The approved Design will be tendered
and executed in a promptly manner. Field surveys for the conceptual design have
been concluded.
To achieve timely project completion the contracting strategy to be adopted will be
such that the selected contractor executes the detailed engineering, procurement,
construction and commissioning phases of the project.
2.2.1 Implementation Arrangements
The Project area Road Project has been initiated and is being carried out by theFMW, which will be responsible for the effective implementation of the project
activities. Project Directors of the various project units, Project Implementation
Unit (PIU) with a Project Director as its head have been established for the project.
The PlUs would play a key role in implementation including the overall control of
construction activities and implementation of contracts. Consultants have been
appointed to carry out the feasibility study and preparation of the Detailed Project
Reports and designs for the project packages. To ensure the effective
implementation of the project, Construction Supervision Consultants will be
selected to support the FMW supervisors.
To assess, advise and monitor the environmental performance of the various
projects being planned, designed and implemented by the Ministry, an
Environmental Unit has been established at the Corporate Headquarters of the
FMW Abuja. The Environmental Unit is headed by an Assistant Director
(Environment), and is assisted by a manager responsible for Environment and
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
20/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 20
Resettlement. The Environmental Unit is responsible for the co-ordination of the
environmental and social issues of the various project and work in close interaction
with the environmental managers of i ts contractors.
2.3 Operations and Maintenance
(a) Operations Philosophy
The road will be operated as an integral part of the existing Federal Road network
in Nigeria. The designs wi ll incorporate features that will guarantee a desired level
of durability.
(b) Maintenance Philosophy
Maintenance philosophy shall be to minimize road failure and safeguard theintegrity of all Federal facilities. The asset management philosophy of
implementation of condition monitoring, preventive maintenance, corrective
maintenance and frontline inspection and maintenance plans will be adopted.
Construction process shall be greatly influenced by the drive to reduce their impact
on the environment and enable compliance with environmental regulations. The
road shall be constructed to a standard that ensures proper management and
canalization of storm water.
2.4 Road Design
The road is designed in accordance with the all relevant engineering standards
and specification enumerated in the document Engineering Design of the Project
area Road Project belonging to the Federal Ministry of Works. It is proposed to be
a two-lane (2 x 3.5m) bituminous carriageway, with paved/unpaved shoulders and
strengthening the existing road by overlays/rehabilitation/reconstruction (including,
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
21/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 21
in places replacing the existing bituminous pavement by cement concrete rigid
pavement). Existing cross-drainage structures on the Project area to Mbalala
road are proposed to be repaired/rehabili tated. New cross-drainage structures
would be provided on the new 2-lane carriageway.
In addition to strengthening the existing carriageway, the project would improve the
geometric deficiencies including the improvement of any intersection encountered.
The proposed improvement aims at improving the riding quality, improving journey
speed and reducing traffic on the waterways. It is proposed to provide service
roads, proper drainage, grade-separation, road furniture, utilities and amenities
wherever required. To minimize the adverse impacts on the various settlements
and to minimize the land and structure acquisition, realignments have been
proposed.
2.5 Project Cost Estimates
The unit rates of existing contracts have been used to derive cost estimates based
on a 50/50 time estimate current inflation trends.
2.6 Construction Waste Management
Vegetation cuttings generated from surface bush clearing can be systematically
utilized and disposed as allowed by governmental regulatory agencies. It could be
useful in the construction of dykes and temporal embankments. Local residents
will be allowed to collect any useful material such as firewood.
2.7 Project Justification
The project is needed to enable FMW
increase employment and create new jobs
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
22/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 22
Generate additional revenue for the Federal Government of Nigeria through
possible evacuation of agricultural produce
meet its projected future road development plan
expand its existing road network in the country
facilitate linking the areas covered by the road to the national grid
2.8 Envisaged Sustainability
The project is expected to be sustained through proper inspection and routine
maintenance. The funding shall be through Federal Government allocation and
the proposed road tax when implemented.
2.9 Decommissioning/Abandonment
2.9.1 General
When the performance of the road usage scales to diminishing returns, a
decommissioning team is set up to plan and implement the laid down guidelines on
decommissioning by FMW. The following activities are involved in
decommissioning / abandonment:
Demolition and site clean-up;
Disposal of Was tes;
Rehabilitation of Sites.
2.9.2 Demolition and Site Clean-up
The demolition exercise is carried out with skill and diligence to avoid further
damage to the environment. At the end of demolition, various solid wastes are
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
23/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 23
sorted according to their types and they are disposed of according to approved
waste disposal methods.
2.9.3 Rehabilitation of Site
After all manners of wastes have been satisfactorily disposed of, the topsoil may
be stripped and replaced with top-soil from un-impacted neighborhood. Seedlings
from the original vegetation are obtained from neighbouring vegetation and planted
as advised by landscaping experts.
CHAPTER THREE
3.0 CONSULTATION PROGRAMME
3.1 Introduction
The Public Consultation has been carried out at various stages of project preparation,
including at the Environmental Screening stage, Feasibility stage and the Environmental
Assessment Preparation stage. Public Consultation was conducted along the various
project major towns including Project area , Wondio, Rumirgo,Yimirali,Askira and Mbalala
Consultation is the process of asking for information about the environmental implications
of projects subject to EIA process, from designated bodies, organizations or persons with
environmental responsibilities or interests, Lee and Wood, (1995). Provisions and
practices relating to consultation, and particularly to e course of public participation, must
be strongly influenced by the culture, the educational level and the political consciousness
in the jurisdiction concerned.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
24/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 24
The project proponent, the Federal Ministry of Works (FMW) consulted wildly with all
stakeholders before embarking on the project
3.2 Objectives of Consultation
The objectives are:
to avoid conflicts by addressing issues promptly,
to ensure that any fears or apprehensions about the project are fully
addressed,
to avoid misunderstanding about full project implementation
to identify and mitigate impacts emanating from the existing project
3.3 Consultation Processes
3.3.1 Stake Holders
Stakeholders are those who are to be affected to varying degrees by the impact of the
proposed project. There are two classes of stake holders- Primary and Secondary. The
primary impact stakeholders range from those communities dotted along the proposed
Project area road.
Secondary impact stakeholders are the Local Government areas responsible for the
welfare of the affected communities, the naturalists, conservationists and theenvironmental NGO groups all over the country.
3.3.2 Institutional Consultation
These are mainly regulatory bodies and are classified into primary regulatory and
secondary regulatory authorities are. FMEn v and DPR are examples of primary
regulatory authorities, while the secondary regulatory authorities are the BornoState EPA
and Relevant Local Government Environmental Authority.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
25/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 25
3.3.3 Public Involvement
The road route and their surrounding environment belong to the communities, hence
consultations were held with them During the meeting, the community was informed that
the purpose of conducting EiA was to comply with statutory requirement.
The Public Consultation has been carried out at various stages of project preparation,
including at the Environmental Screening stage, Feasibility stage and the Environmental
Assessment Preparation stage. Public Consultation was conducted along the various
project major towns including Project area , Wondio, Rumirgo,Yimirali,Askira and Mbalala
respectively).
These included Door-to-Door Personal Interviews, Focus Group Discussions,
Stakeholders and Consultation Sessions. Consultation with the communities resulted in
arriving at design solutions, appropriate and conducive to the felt needs of the people.
Comprehensive documentation about ecosystem components, hotspots and community
networks enabled minimizing the possible impacts.
To redress the environmental issues likely to surface during construction and operational
phases, constant communication needs to be continued. This will be ensured by regular
progress monitoring of the construction and inviting suggestions/ complaints through
grievance redressal.
Meetings will be organized with the project affected people and the various stakeholders
at regular intervals at the potential hotspot/sensitive locations before and during project
implementation.
During the consultations, the communities complained that as a result of lack of good
access road in their area over the years,
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
26/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 26
they had lost a lot of their agricultural produce due to lack of adequate
market
they los t some of productive youths to other cities due to emigration,
their farmers have abandoned their farmlands and have become less
productive because everybody want to be seen as government worker.
No evidence of significantly improved quality of life in their community
because of lack of good road liking them with other parts of the country.
3.3.4 Community Consultations
Engineers carried out community consultations in the area. Various community
executives represented their individual communities.
Prior to the consultation process, the team had made arrangements to ensure that
all the relevant parties to the consultation process were well informed in advance
of our purpose of vis it and the nature of project to be executed the following groupswere represented at the consultation sessions:
Community executive council
Youth groups and associations
The women groups and
Community members
Highlights from the consultation process in the study communities include the following:
The objectives of the consultation exercise was explained to all, and
these were: to explain the nature of the project to the communities,
enlighten them on environmental conservation as stakeholders,
solicit for social permit from them to execute the project as it will
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
27/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 27
benefit them and thus ensure peaceful and harmonious relationship
between the project team and the benefiting communities.
Attendance at all the consultation were appreciable and cut across
the different strata of the communities
The team was well received at most of the study communities and
On the part of the communities, emphasis was placed on the need
for government to ensure that a competent company of repute is
considered for the project to ensure timely completion and avoid
abandonment of the project midway.
They also want the government to compel the company to consider
some of their youths for employment during project execution.
3.3.5 Future Consultations
Consultation is a continuous process and as such the Federal Ministry of
Works will continue to consult with all the relevant parties concerned, with
all stakeholders or those likely to be affected by its projects at all stages of
the project implementation.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
28/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 28
CHAPTER FOUR
4.0 DESCRIPTION OF THE PROJECT ENVIRONMENT
4.1 GENERAL
This chapter describes the baseline environmental conditions of the entire road
project route. The description of the field study methods and the key findings of the
survey (biophysical, social and health) are presented. It includes data gathered
from literature survey, field study and laboratory analysis. The purpose of this
environmental description is to provide qualitative and quantitative baseline
information on the existing status of the project area against which future
departures as a result of the emplacement of the proposed project will be weighed.
4.2 BASE LINE DATA ACQUISITION METHODS/STUDY APPROACH
4.2.1 Quality Assurance/Quality Control
The quality assurance/quality Control programme covers all aspects of the study,
including sample collection, handling, laboratory analysis, data coding and
manipulation, s tatistical analysis, presenting and communicating results.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
29/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 29
4.2.2 Sampling Strategy
Sampling and data collection for the various environmental components and
parameters were in accordance with recommended procedures and practices for
environmental data collection in Nigeria (FMENV 1992 and DPR, 2002 Part vii D
sampling and handling of samples).
4.2.2.1 Air Quality and Noise Studies.Air pollution is becoming a major factor in the quality of life of urban and
rural dwellers, and it posses risk to both human health and the environment.
Therefore, it is necessary to study the background quality of the air prior to
any project and also to predict the impact such a project would have on the
air quality.
Thus, the following air quality parameters were sampled during the field
work viz: Suspended Particulate Matter (SPM), Sulphur Oxides (SOX),
Nitrogen Oxides (NOx), Carbon Monoxide (CO), Hydrogen Sulphides (H2S),
and Hydrocarbon gases using highly sensitive digital in-situ Gas Monitors.
Similaraly, the background noise levels were taken using a portable digital
sound level meter.
4.2.2.2 Meteorological and Climatic Characteristics
The climatic and meteorological characteristics of the area were acquiredfrom exis ting literature.
4.2.2.3 Geological, Geophysical and Hydro-geological Studies
Long spread Schlumberger vertical electrical sounding (VES) were used for
both near surface soil resistivity determination and subsurface stratigraphic
sequence delineation. The test points varied depending on the ease of
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
30/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 30
accessibility. Available literature on the geology and hydrogeology of the
road project routes were also reviewed.
4.2.2.4 Aquatic Studies
The hydrology of the project area consists of rivers, creeks and creeklets.
The major water body is the Forcados River. A total of twelve (12) stations
were sampled for water. A water sampler was used to collect water samples
at designated locations. Samples for BOD measurement were collected
Winklers bottles while samples for heavy metals analyses were collected in
glass containers and acidified with concentrated nitric acid to avoid
precipitation. Water samples for microbiology were collected in sterile
MacCartney bottles while water samples for benthos were collected in
plastic containers and preserved in 10% v/v formalin. All samples were
preserved in ice chest (coolers) prior to transportation to the laboratory for
analysis.
Unstable physicochemical parameters of the water such as pH, DO,
temperature, salinity, turbidity and conductivity, were measured in-situ,
using pre-calibrated portable digital meters.
Sediment samples were also collected at the water sampling points using a
grab sampler. Sediment samples for physico-chemical analysis were
collected in Polythene bags while those for microbiological analysis were
collected in Aluminium foil.
Similarly, all the sediment samples were temporarily stored in ice packed
coolers prior to transfer to the laboratory.
Sampling was also carried out for phytoplankton and zooplankton
composition and diversity, in each of 12 (twelve) water-sampling stations.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
31/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 31
Planktons were collected using plankton net. The catches were removed
into a bottle and preserved in 5% formalin.
Benthic samples were collected using an Eckman grab. The bottom
samples were sieved using a set of Tyler s ieves (between 500 650mm).
Data on fisheries and other aquatic resources were collected mostly through
oral interviews with local fishermen. These were complemented with
information from literature studies.
4.2.2.5 Soil Studies
Soil samples were collected from each of the stations with the aid of a Dutch
Hand auger, hand gloves, a spool and hammer at depths of 0 15cm and15 30cm, representing top and bottom samples. These are the soil depths
at which most (>80%) of the plants feeder roots and soil micro-organisms
are concentrated. Thus, most of the soil nutrients useful to plants and soil
micro-organisms are concentrated at these depths.
The samples for microbiological analysis were collected in McCartney
bottles and stored in an ice chest, while samples for hydrocarbon analysis
were collected in glass jars. Samples for physicochemical analysis were
collected in polythene bags.
4.2.2.6 Vegetation.
Visual observations were used to assess the vegetation along the proposed
road routes. Inventory of plants species on either sides of the routes were
taken at about 1km intervals. The characterization, identification and
classification of the plant species and communities were undertaken both at
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
32/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 32
the field and with reference to some taxonomic texts. Furthermore, analysis
of plant species within a 10m 2area at each 1km interval was carried out to
determine the density and relative distribution of plant species.
4.2.2.7 Wildlife
This involved a survey/census of mammals, birds, reptiles and amphibians
along the study areas. Direct count method, using a pair of binoculars, was
employed for the census of the reptiles, birds and other animals which
readily offered themselves for observation. The presence of some of the
animals were ascertained by probing such humid habitat like logs, heaps of
dead decaying leaves, forest undergrowths, ponds and burrows. Thus, all
s ighted, captured or dislodged animals were identified, often on the spot, to
possible taxonomic levels using field guides and keys. (Walkey et al 1968;
Elgood 1960; Happold 1987; Brach 1988). The indirect method which
makes use of evidence of animals presence (Dasmann, 1963) was used for
species which do not offer themselves readily for observation. Such signs ofanimal presence such as burrows, faecal pellets (droppings), hairs, foot
prints or tracks, sloughed skin, devoured food (cassava, yam, oil palm nuts,
etc) as well as vocalization, skeleton/carcass and trampled grass were of
immense use in the course of the investigation. Interviews with hunters also
provided further information on the wildlife diversity, abundance and use in
the areas.
4.2.2.8 Socio-economics
The socioeconomic data gathered comprises historical information,
cultural norms, land tenure and land use pattern, population and
demographic characteristics; health, morbidity, mortality, and fertility,
occupations and income distribution, health social and other
infrastructure. This involved meetings with the communities,
quest ionnaires and oral interviews with local inhabitants.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
33/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 33
4.2.3 Laboratory Analysis
The methods of analysis used were those specified in DPR Guidelines and
Standards and other International Analytical Standards such as APHA for water
quality. Trace metal analysis was carried out using Atomic Absorption
Spectrophotometer duly calibrated with authentic standards. Physicochemical
parameters were determined using the DREL 2000 HACH Spectrophotometer,
duly calibrated with standards, as well as Flame Photometer.
4.2.4 Statistical Analysis
Errors in field data include those resulting from the instrument and those
introduced by the observer. With sustained calibration of the instrument and the
use of standardised observational procedures, equipment errors were brought to
acceptable minimum. However, other errors arise from the m ethod of sampling.
Errors often arise from two-stage sampling or sub sampling, or even from the fact
that the samples collected are not representative samples of the medium. There
are also spatial variations of the same medium, e.g., soil and water. Thus, it is
necessary to determine the true mean and the estimated variance among the
number of samples taken, so as to establish a reasonable level of confidence in
the results obtained. A good result is obtained when the variance is within 5% of
the mean.
4.2.5 Data Coding and Manipulation
To ensure preservation of the integrity of data collected, data coding forms for use
in the field, were designed in such a way that field data could be directly entered
into computer data sheets.
Since their analysis may be required in legal proceedings, it is essential to
es tablish sample authenticity. Samples must be properly sealed and labeled. All
data collected were labeled and the following information provided among others:
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
34/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 34
Identification code or sample number,
Date and time of sampling,
Description of sample,
Methods of sampling,
Particulars of any photographs taken.
Where samples were sent to another laboratory for examination, a duplicate copy
of this information was sent along with the sample to the laboratory, independent of
the sample. All movements of the samples were included on the samples record.
Basic information was recorded together with results of analysis, in a register.
4.3 BASELINE RESULTS AND DISCUSSION
4.3.1 Air Quality and NoiseThe results of air quality measurements for the study areas are presented in the table
below. The monitored pollutant gases include Nitrogen Oxide (NO and NO2), Sulphur
dioxide (SO2), Carbon Monoxide (CO), hydrogen sulphide (H2S) and hydrocarbon gases
(HC) and suspended particulate matter (SPM). Generally, the concentrations of the
measured air pollutants in the ambient atmosphere suggest that the area is a relatively
pristine environment. More so, the values recorded were not significantly different and
were within acceptable regulatory limits, where detected. Result of air quality studies and
regulatory limits are presented in tables 4.3.1.1 4.3.1.4 below.
4.3.1.1 Nitrogen Oxide
Nitrogen oxides are products of high temperature combustion like vehicle engines,
domestic fires and industrial combustions. The Nitrogen Oxides of interest are nitric oxide
(NO2) and nitrons oxide (NO). Studies have shown that man or animal exposure to NO2
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
35/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 35
concentration above 0.563ppm may cause pulmonary diseases and increased
susceptibility to bacterial infection (ACGIH, 1995). Concentrations of NO2measured in
the area ranged from below detectable limit to 0.05 ppm and averaged 0.028 + 0.02 ppm.
Similarly, the concentrations of NO ranged from below detectable limit to 0.06 ppm.
Generally, the concentrations of the nitrogen oxides were below the maximum
permissible FMEnv. Limits of 0.075 to 0.113 ppm for daily average of 1-hour values. This
shows that no significant high temperature combustion of Nitrogen oxides was going on
along the project routes during the study.
4.3.1.2 Sulphur Dioxide (SO2)
SO2is a more important oxide of sulphur as a primary pollutant, and is formed from the
oxidation of sulphur containing fuels.
Exposure to SO2at concentrations above 13.0 ppm could stimulate broncho-constriction
(as in asthma), mucus secretion, and eye irritation in man and other animals (ACGIH,
1995). Long-term exposure to lower concentrations may result in death from cardiac
and/or respiratory diseases and increased prevalence of related symptoms. Also,
atmospheric Sulphur dioxide is oxidized forming sulphuric acid. Sulphuric acid may be
incorporated into rain or dry-deposited as fine droplets and in doing so, causes
acidification of soils and surface waters. This is termed acid rain.
SO2 were generally not detected in the area i.e. below the equipment detection limit,
during s tudy.
4.3.1.3 Carbon Monoxide.
Carbon Monoxide is a product of incomplete combustion (oxidation) of fossil fuels or
hydrocarbons. Ambient accumulation of CO of values greater than 228ppm could lead to
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
36/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 36
suffocation and death as a result of the prevention of blood oxygenation and the formation
of carboxy-haemoglobin (OSHA 1989).
The measured CO values at the field range from 0.06ppm to 0.13 ppm, with an average
of 0.088 + 0.025 ppm. The values were within FMEnv. lim it of 11.40 ppm for daily
average of hourly values in Nigeria.
4.3.1.4 Hydrogen Sulphide (H2S)
Hydrogen Sulphide gas is extrem ely toxic, odorous and corrosive and m ay be formed
during the oxidation or combustion of Sulphur containing fuels, mainly coal containing
Sulphur in the presence of air (oxygen). Exposure to concentrations above 0.15 ppm
could result in death (SIEP, 1995). H2S were generally not detected (below detection
limits) at the field during the study.
4.3.1.5 Hydrocarbons (HC)
The sources of atmospheric hydrocarbon gases include incomplete combustion of fuels,
fugitive emissions and vents. The primary hydrocarbon contaminants include aromatics,
olefins, and paraffins, while the secondary contaminants include aldehydes, ketones,
and organic acids. The permissible limit is 0.160 ppm for daily average of 3 hourly
values. Mos t of the incomplete combustion products are very toxic, and exposure to
hydrocarbon gases above permissible limits could cause certain types of cancer and
leukemia (SIEP, 1995).
However, the field hydrocarbon gases concentration were very low and below the
maximum permissible limit. The values ranged from 0.001 to 0.002ppm (mean = 0.0016
+ 0.0007 ppm). This implies that no significant activity leading to hydrocarbon emission
was taking place in the vicinity of the project routes.
4.3.1.6 Suspended Particulate Matter (SPM)
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
37/168
Environmental Impact Assessment of Typical Road Project
Draft Report. Version: 01 37
This comprises of light materials, solid and liquid matter of organic or inorganic
composition (usually dust and other particles) found suspended in the atmosphere, and
carried around by wind. The FMEnv regulatory limit for SPM is 0.250 ppm for daily
average of 1-hour values. Ambient concentrations of SPM above this in Nigeria may
cause or aggravate respiratory problems such as cough and asthma. However, the
measured SPM values were very low, probably because activity/vehicular movement
goes on in the area was minimal. The values ranged from 0.062 ppm to 0.089 ppm
(mean = 0.075 + 006 ppm).
4.3.1.7 Noise
Prolonged exposure to noise of frequencies higher than regulatory limits can result in
temporary loss of hearing (temporary threshold shift), which disappears in a few hours or
days, or permanent loss (permanent threshold shift). The FMEnv permissible noise limitfor an 8-hour working period is 90dB. The measured noise levels at the proposed project
routes were low and mostly within natural background status of 20 to 50dB. The
contributing sources of the recorded noise levels include singing birds, other wild animals
within the vicinity of the project site, passing motor vehicles and community inhabitants
activities. The levels however were also within FMEnv permissible limits and ranged from
41.7 dB(A) to 67.7 dB(A), averaging 48.04 + 7.45 dB(A).
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
38/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Project
Draft Report. Version: 01 39
Table 4.3.1.1 : Results of Air Quality and Noise Studies for the EIA of the Areas.
PARAMETER (ppm)
NO2 NO SO2 CO H2S HC SPM
NOISE
dB(A)
0.03 0.05 BDL 0.17 BDL 0.001 0.021 51.7
BDL BDL BDL 0.11 BDL 0.002 0.024 67.7
0.03 0.06 BDL 0.08 BDL 0.001 0.012 46.7
0.01 BDL BDL 0.07 BDL 0.002 0.021 77.5
0.02 0.03 BDL 0.05 BDL 0.002 0.020 50.8
0.02 0.04 BDL 0.10 BDL 0.001 0.018 46.8
0.05 0.05 BDL 0.06 BDL 0.003 0.029 53.9
0.03 0.05 BDL 0.08 BDL 0.001 0.016 51.2
0.02 0.04 BDL 0.07 BDL 0.001 0.016 48.5
0.04 0.05 BDL 0.10 BDL 0.001 0.025 41.7
0.02 0.04 BDL 0.08 BDL 0.001 0.018 44.6
0.02 0.05 BDL 0.07 BDL 0.001 0.018 44.6
0.028+
0.02
0.035+
0.22BDL
0.088 +0.025
BDL
0.0016 +
0.0007
0.022+
0.006
58.04 +7.45
0.075-
0.113
0.075
0.113
BDL 11.4 - 0.160 0.250 90.0
BDL = Below Detectable Limited (Not Detected)
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
39/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Project
Draft Report. Version: 01 40
Table 4.3.1.2: Nigerian Ambient Air Quality Standards (FMEnv, 1991)
Pollutant Time of Average Limit
Particulates Daily average of 1hr values 250 g/m3- *600 g/m3
Sulphur oxides(Sulphur dioxide)
Daily average of 1hr values 0.01 ppm (26 g/m3) -
ppm (260 g/m3)
Non-methane hydrocarbon Daily average of 3hr values 160 g/m3
Carbon monoxide Daily average of hourly valu
8hr average
10 ppm (11.4 g/m3)
20 ppm (22.8
g/m
3
)
Nitrogen oxides (Nitrogen dioxide) Daily average of hourly valu(range)
0.4 ppm - 0.06 ppm(75.0g/m
3- 113 g/m
3)
Photochemical oxidant Hourly values 0.06 ppm
*Concentrations not to be exceeded for more than once a year.
Table 4.3.1.3 Noise Exposure Limits For Nigeria.
Duration per Day, Hour Permissible Exposure Limit
(dBA)
8 906 92
4 953 97
2 1001.5 102
1 1050.5 110
0.25 or less 115
Source: FEPA National Standards and Guide lines (1991).
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
40/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Project
Draft Report. Version: 01 41
Table 4.3.1.4: Ambient Concentrations of Heavy metal Pollutants in Air at
Some Locations In The Study Area (mg/m3)
Air Sampling PointFe Mn Cd Cr Ni V Zn Hg
0.056
0.004
0.006
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
41/168
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
42/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Project
Draft Report. Version: 01 43
Table 4.3.2 below gives a summary of the extreme weather conditions in the area.
Parameter Mean
Temperature 34.5oC
Relative Humidity 30%
Wind
Speed
Direction
2.7m/s
Northeast
Rainfall 890mm
4.3.3 Soil
4.3.3.1 Soil Fertility Evaluation
The samples picked from the field were subjected to physical and chemical analysis
for fertility evaluation. This evaluation is based on the classification of ISRIC (1995)
and other earlier investigations (Enwezor et al, 1981). Table 4.3.3.1 and 4.3.3.2
show the mean values of the soil physical and chemical parameters respectively.
4.3.3.2 Soil Physical Properties
The soil physical properties are mostly optimum for arable crop production except
for their sandy nature in some areas. The bulk densities of the soils are generally
very low (0.48-0.57 g/cm3). Also, the hydraulic conductivity values range from 43.0-
51.2 S/cm and 42.0-51.1S/cm at the top and bottom soil respectively. There is
relatively easy passage of water through the soils. The characteristic almost flat to
very gentle slope (0-1.3%) of most of the landscape and the sandy nature of the
soils enhance their susceptibility to erosion and further loss of fertility. The major
factors responsible for the low nutrient status of the soil include poor fertility
maintenance practices (e.g. burning of farm residues and over cropping) and the
high pressure on the available little land.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
43/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Project
Draft Report. Version: 01 44
i.) Particle Size Analysis
The results of the particle size analysis of soil samples are presented in table
4.3.3.1. Evaluation of the field and laboratory analytical results of the soils shows
that the texture of soils in the field was mainly Loamy Sand and Sandy loam with
the Sand particles dominating the aggregates. The percent sand ranged from
56.9% to 76.1%, averaging about 67.57% and the top samples (0-15cm depths)
have more sand particles than the bottom or lower (15-30cm depths). Clay
particle had the least composition of between 2.4% to 18.6%. It had a mean
percent composition of 9.54%, which increased down the profile (Table4.3.3.1).
The highest percent clay was recorded at Bomadi. The higher values of clay at
the lower horizons could be attributed to the loss of these particles by the water
in filtration down the soil profile (Opara Nadi and Juo, 1986).
ii.) Porosity
In general, the porosity of the soils in the area was moderately high with a range
of 47-75% for the 0-15cm depth and 40-66% for the 15-30cm depths. Unlike the
bulk density, the porosity is higher on the surface. There was no area in the field
where the total porosity was within 9-10% that would have resulted in inadequate
supply of oxygen for good root development at field capacity.
iii.) Water Holding Capacity (WHC)
The WHC of the soils in the fields ranged from 10 - 70% in the top soil and 20-
45% in the lower 15-30cm depths. The upper depths recorded higher values as
a result of higher organic carbon, which increased the ability of the soils to hold
more water. Organic Carbon increases the ability of the soils to hold water.
4.3.3.3 Chemical Properties
i.) pH- soil Reaction
The soils in the study areas are acidic (pH 5.53-5.9) both at the top and bottom
sapmles. This conforms to the findings of earlier workers (Ogunkunle, 1982; SSSN,
1981), who classified the soils of similar hydrogen ion concentrations as "acid
sands. The mean soil pH value for the upper (top Soil) 0-15cm depths washigher than the lower depths. (Table 4.3.3.2). This could be due to the higher
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
44/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Project
Draft Report. Version: 01 45
organic matter, which contain exchangeable bases in the upper layers. The
acidic nature of these soils could be ascribed to the low rainfall of this area.
ii.) Exchangeable Cations (Na, K, Ca & Mg)
Calcium and sodium are the most abundant cations in the soil exchange
complex. This finding is in agreement with the observation that calcium is the
predominant cation in the soil complex because of its strong adsorption by the
soil (Beckeh, 1965). Magnesium and potassium were also abundant in the soils
in varying quantities. The values for calcium range from 2.41-4.63 meq/100g soil
in the 0-15cm and 2.83-4.71 meq/100g soil for the lower 15-30cm depths
respectively thus Calcium was followed by Sodium with a value in the range of
2.01-4.11meq/100g soil at the surface and 2.0-4.45 meq/100g soil at the
subsurface. Potassium is the least abundant exchangeable bases ranging form
0.01 0.09 meq/100g soil at the subsurface.
The contents of these cations were higher in the sub- soils than in the surface
soils and showed a high positive correlation with organic carbon. Generally, theexchangeable bases, like the other nutrients, were high and above the 2.0
meq/100g soil of Ca and Mg required of a good soil in Nigeria and 0.2 meq/100g
soil for K and therefore will require straight Mg and K fertilization for optimum
crop production.
The mean values of the exchangeable cations were above the 2 meq/100g soil of
magnesium, calcium and 0.2 meq/100g of Potassium required for good crop
performance in most Nigerian soils (Odu et al, 1985).
Similarly, the anions SO4and NO3were detected in the ranges of 0.11-0.23 and2.24-4.31mg/kg.
iv.) Total Organic Carbon and Nitrogen
The Total Organic Carbon and total nitrogen are contained in Table 4.3.3.2.
While the values of organic matter could be said to be high considering the value
adjudged high (>1.45%) by Sobulo and Adepetu, (1987) the same can not be
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
45/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Project
Draft Report. Version: 01 46
said of total nitrogen. The organic carbon value ranged from 0.84 2.88% with
higher values recorded mostly on the surface (0-15cm) samples. This may be as
result of the dense mass of decayed mangrove roots about 60cm thick in the
soils. The range of total nitrogen values was 4.60 8.33mg/kg with a mean of
about 6.2mg/kg. These soils were taken from project area with good ground
cover, which reduced raindrop erosion and leaching of mobile nutrients like
nitrogen. Nitrogen is the most important nutrient of plants and like the organic
carbon, the values in the field are generally high. This could be due to high
organic carbon contents (Agboola and Curey, 1973). Overall, except at some few
points with TOC values below the 1.5% critical level of Adepetu (1986), the rest
values are above 1.5% and high enough to maintain optimum yield of continuous
cropping of the land.
However, the total nitrogen contents showed a very high positive correlation with
organic carbon indicating that the reserve of this element was mainly in organic
matter (Okusami, 1986).
V.) Heavy Metals and hydrocarbon contents
According to the international standard, (Nature Conservancy Council NCC,
1991) and FEPA (1991) guidelines, the heavy metals contents of the soils are
generally below the critical levels to constitute hazard. The heavy metal
concentrations of the fields are shown in Table 4.3.3.3. The values of these
metals are low which is an indication that industrial activities especially oil
activities are low along these routes. Despite the low acidity, the Iron and Mn
concentrations are low an indication that there are no pyrites in these soils (Dent,
1986). FAO (1972) reported that high value of Iron is peculiar to poorly drained
soils and a concentration of 20ppm has been reported to be toxic to rice plants
(Kyuma et al, 1986). Extremely high values, more than 1 x 104ppm will be very
toxic to crop plants.
The Iron concentration was the highest among the heavy metals and the values
ranged from 5.94mg/kg in Project area to 16.61mg/kg in Mbalala. Generally, the
values were below 20mg/kg, considered toxic for rice as reported by Kosaki and
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
46/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Project
Draft Report. Version: 01 47
Juo (1986). Next to Iron in abundance are Zinc (Zinc has been reported to be
involved in root-to-shoot translocation) and Manganese (Manganese is required
for sporulation in Aspergillus niger). Soils in the mangrove areas are known to
record high value of zinc. A 1.5 ppm critical level of Zn is reported by
Ponnamperuma (1974)and most values exceeded this limit. Toxicity of Mn can
be suspected if more than 100ppm. Mn is present in plant dry matter (Bear,
1965). The values ranged from 1.32 3.68mg/kg in the soil samples from the
study route. These values are within the accepted range for optimum crop
production. In a descending order of abundance, the heavy concentrations can
be written as follows: Fe>Zn>Mn>Cd> Cu > Ni >Cr>V>Pb.
Table 4.3.3.1: SUMMARY OF PARTICL E SIZE ANALYSIS OF SOILS FROM THE STUDY
AREAS
LOCATION DEPTH(Cm)
% CLAY % SILT % SAND TEXTURALCLASS
Project area -1 0-15 6.3 07.9 76.1 Loamy Sand
Pro ject area -2 15-30 10.2 14.8 62.2 Sandy LoamProject area -3 0-15 12.4 25.3 62.4 Sandy Loam
Project area -4 15-30 5.4 33.8 60.8 Sandy LoamWomdio-1 0-15 2.6 14.9 72.3 Loamy Sand
Womdio-2 15-30 5.5 23.9 60.7 Sandy LoamRumirgo 0-15 12.4 15.4 62.6 Sandy LoamYimir-Ali 15-30 12.4 15.2 62.4 Sandy Loam
Askira-1 0-15 2.6 14.9 72.3 Loamy SandAsskira-2 15-30 6.2 17.6 75.8 Loamy SandMbalala-1 15-30 5.5 23.9 60.7 Sandy Loam
Mbalala-2 0-15 6.4 17.9 75.9 Loamy Sand
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
47/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Projec
Draft Report. Version: 01
Table 4.3.3.2: Results of Chemical Properties of Soils in the Fields
Meq/100g
Location
identity
DEPTH(CM)
pH(H2O)
EC(s/cm)
T.Nitorgen
mg/kg
NO3
-
NO2
-
NH4N
SO4
2+
Organic
Carbon%
PO4
EA
K
0-15 4.80 50.6 5.04 2.39 2.81 0.15 0.12 2.84 3.82 0.02 2.00 0.06
15-30 4.80 50.4 5.04 2.38 2.81 0.14 0.14 2.28 3.82 0.03 2.03 0.06
0-15 4.53 44.0 6.03 3.22 3.10 0.08 0.23 1.36 2.44 0.02 2.05 0.06
15-30 4.88 46.4 7.56 4.11 3.29 0.07 0.20 0.85 2.29 0.04 2.17 0.08
0-15 4.62 44.2 8.35 4.31 3.80 0.03 0.12 2.03 2.13 0.03 2.25 0.09
15-30 4.66 44.2 8.35 4.31 3.80 0.03 0.13 2.02 2.13 0.02 2.27 0.08 0-15 4.80 50.6 5.04 2.39 2.81 0.15 0.11 2.84 3.82 0.04 3.11 0.05
15-30 4.53 44.0 6.03 3.22 3.10 0.08 0.12 1.36 2.44 0.04 3.41 0.08
0-15 4.88 46.40 7.56 4.11 3.29 0.07 0.20 0.85 2.29 0.04 2.50 0.09
15-30 4.62 44.24 8.35 4.31 3.80 0.03 0.21 2.03 2.13 0.03 2.11 0.06
0-15 4.66 44.20 8.35 4.31 3.80 0.03 0.22 2.02 2.13 0.03 4.11 0.06
15-30 4.57 50.2 5.01 2.24 2.41 0.08 0.22 2.42 2.80 0.03 4.43 0.08
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
48/168
Environmental Impact Assessment of Ojobo- Bomadi-Siama- Gbekebor Road Projec
Draft Report. Version: 01
Table 4.3.3.3: Results of Heavy Metal Analysis of Soils from the Fields
Sample LocationSoilSamplingDepth (Cm)
mg/kgFe Mn Cu Cr Pb
0-15 14.64 3.13 0.09 0.06 0.06 0.115-30 12.48 2.13 0.22 0.06 0.06 0.1
0-15 16.52 2.18 0.11 0.09 0.02 0.115-30 6.95 2.05 0.19 0.08 0.13 0.1
0-15 12.31 1.42 0.07 0.08 0.01 0.1
15-30 14.34 1.62 0.11 0.07 0.01 0.10-15 15.45 2.17 0.01 0.08 0.05 0.1
15-30 6.83 2.04 0.02 0.06 0.12 0.10-15 14.44 1.32 0.06 0.09 0.13 0.1
15-30 16.61 1.34 0.08 0.06 0.05 0.10-15 16.43 2.14 0.12 0.07 0.02 0.1
15-30 6.94 1.90 0.11 0.09 0.03 0.1
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
49/168
ENGINEERING CONSU LTANT
ENVIRONMENTAL IMPACT ASSESSMENT
4.3.3.4 Sediment StudiesThe summary (in mean and range) of the physico-chemical characteristics of thesediments in the study area is presented in table 4.3.3.4.1.
The sediments are slightly acidic to almost neutral with pH range of 5.23 6.97. the fertilitylevel of the sediments had ranges of 0.01 0.070, 0.46 20.47, 0.63 7.21, 0.18 2.22,0.09 1.02, 0.02 0.40meg/100g, 5.30 41.0, 18.10 72.0ppm. The oil and greasecontent of the sediment samples are Not Detected.
The heavy metals have a wide range of concentrations ranging as follows: Fe; 0.0412 32.31, Mn; 1.60 269.31, Zn; 1.10 09.86, Ni; 0.10 4.62, Pb; 1.90 4.02, and Cu; 0.70 5.03. These results were almost similar to those for soil.
Table 4.3.3.4.1: Summary of the Physico-chemical/Heavy Metals Characteristics of
the Sediments in the Study area.
S/N Parameter Range
1. pH 5.23 6.972 Sand % 31 963 Silt % 2 38
4. Clay % 2 425 % Organic Matter 0.80 5.166. % Total Nitrogen 0.01 0.07
7. Phosphorus (ppm) 0.46 20.478. Exch. Ca (meg/100g) 0.63 7.219. Mg (meg/100g) 0.18 2.2210 K (meg/100g) 0.09 1.02
11. Na (meg/100g) 0.02 0.4012. Exch. Acidity (meg/100g) 0.40 0.7013 Al uminium (ppm) 5.30 41.0
14 Sulphate (ppm) 18.10 -72.0015. Chloride 6.0 21.0016. ECEC 4.60 9.47
17. Oil & grease (ug/g) ND 720.9518. Fe (ug/g) 0.0412 32.313
19. Mn (ug/g) 1.60 269.3120 Zn (ug/g) 1.10 9.86
21. Ni (ug/g) 0.10 4.6222. Pb (ug/g) 1.90 4.0223. Cd (ug/g) 0.27 0.45
24. Cu (ug/g) 0.70 5.03
4.3.4 Land UseOver the millennia, land use had been determined by tenurial systems evolved over timeand determined by the perceived demand as well as the potential and actual socialpressure associated with its supply and use (Powel, 1995; Swallow and Kamara, 2000).
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
50/168
ENGINEERING CONSU LTANT
ENVIRONMENTAL IMPACT ASSESSMENT
As in the case of most communities in the Borno State, land ownership is vested infamilies and communities, rather than on individuals (Alagoa and Tamuno, 1989).
4.3.4.1: Land Use and Agricultural Systems:The land use types in Project area is for agriculture during the raining season. The
settlement is large (about 450 1000 houses) although some are provided with modern
facili ties such as schools, electricity and dispensaries. The main source of water for
domestic use is through wells and borehole. A group number of wells are dug at the
same location to provide suitable drinkable water for the community. There are little or no
much economic trees.
Agriculture is practiced on a small scale at the out sketch of the villages or on the opposite
bank. Crops grown are mainly arables. Small parts of the available land at the areas are
cultivated to food crops mainly guinea corn and millet. About 20-45% of the land is made up
of homesteads and the surrounding compound farms. Livestock is kept at the homestead
level except Fulani cattle rearers who moves around as usual with their cattle.
i.) Farming Systems
The traditional farming system in the study area is made up of land rotation with multiple
cropping systems. These crop production techniques have been developed by the peasant
farmers as conservation farming techniques under the minimum tillage practices
commonly adopted by the farmers in the study area. The major farm implements are hoes
and cutlasses, which can provide food for the farmers at subsistence level. The household
farm size is small (5-7.0ha) and fragmented.
ii.) Livestock
Most households keep some poultry birds on a free-range basis. Less than 65% of the
farmers keep sheep and goats because of the nearness of the farms to the housesteads.
Those farmers that can provide fence keep 2-3 goats or sheep and the children and
women provide browse plants for the animals. The animals are sometimes led to graze the
patches of grass, mainly Panicummaximum. The Fulani communities within the area
moves around with their cattle.
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
51/168
ENGINEERING CONSU LTANT
ENVIRONMENTAL IMPACT ASSESSMENT
iii.) Land Clearing, Land Preparation and Crop Establishment
Land clearing and land preparation are usually done by men while planting, weeding andharvesting operations are left to mainly women and children with men occasionally in
attendance. Period of cultivation depends mainly on rain establishment but usually Crops
are planted from March to September.
iv.) Cropping Patterns/Systems
The cropping pattern in the study area consists, mainly of mixed cropping with varying
number of crops in the mixtures.
The cropping systems involve compound farms, guinea corn-based, groundnut-based and
millet-based cropping systems.
v.) Compound Farms
The homesteads are surrounded with crops that are of immediate importance to the
household members. Such crops include: mango (Mangifera indica), oranges (Citrusspp.)
and cashew, vegetable crops.
The component crops in the compound farm are not planted in any definite pattern or
sequence. Manure is supplied to the crops from the household wastes.
vi.) Grain Based Systems
Farmers in the study area generally practice grain-based cropping system. The practice of
growing several crops on the same piece of land is an ancient strategy for crop production
among farmers in the tropics. Ruthenberg (1971) noted that mixed cropping is an
expression of African farmers desire to minimize risk. The system offers farmers insurance
against total crop failure. It brings about even distribution of farm labour. It also helps to
control soil erosion and weeds (Ikeorguet al, 1989).
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
52/168
ENGINEERING CONSU LTANT
ENVIRONMENTAL IMPACT ASSESSMENT
4.3.4 Vegetation (Aquatic and Terrestrial)
The vegetation pattern of the region is closely related to the soil distribution. This
derived from the fact that both, overtime, have been largely influenced by the nature
of the sediments, drainage characteristics as well as the prevailing climatic
conditions of the region.
4.3.4.1 Plant Species Composition
The study area lies within the lowland savanna zone ecosystem. Natural vegetation covers
less than 5% of the land area and even then it is largely degraded.(Tables 4.3.4.1 4.3.4.4).
The commonest plants within the zone consist of trees such as Adansonia digitata
(kuka),vitex domiana (dinya), which provide edible fruits and leaves, diospyros
mespiliformis (kanya), tamarindusindica (tsamiya), moringaoleifera (zogale).
Others species found in the area are parkia clappertoniana (dorawa) Anogeissus
Leicarpus (Marke) khaya segalensis (madaci) it is a good timber, fuel wood, medicinal and
provides fodder in the dry season.
Ziziphusspina-chrili (kurna), hyphaene the baica (goriba), Borrasusaethiopum (Giginya)
balanites aegyptiaca (Aduwa), acacia Senegal (dakwara) acacia nilotica (bagaruwa),
acavia seyal (dushe), acaciaalbida (gawo), guierasenegalensis (sabara), hyphaenethe
bacia (kaba) and piliostigmathonningii (kalgo). Stable crops such as millet, guinea corn,
groundnut dominate the farms. Some farmers however go into the high bushto make new
farms because of better state of soil fertility.
4.3.4.2 Vegetation Structure
-
8/13/2019 971375 Environmental Impact Assessment of Typical Road Project
53/168
ENGINEERING CONSU LTANT
ENVIRONMENTAL IMPACT ASSESSMENT
The vegetation of the project area traversed by theoosed route consist of shrubs and grass
layer with minor tree components. The distribution of trees, shrubs grasses vary depending
on location and soil/ bedrock (e.g trees are more prominent on sand soils whereas in areasof shallow soils over bedrock, grasses and shrubs are the more dominant vegetation).
Thorny shrubs such as Xeromphis nilotica and woody climbers (or spreading shrubs)
comreum micrathum and capparis corymbosa are abundant in this zone. The woody
climbers are also abundant often suppressing the herb layer on rock hills, which are not
grazed. The grasses are short (1.0 to 1.5m tall) and feathery in constrast to the Guinea
savannna grasses. Two distinct tree types occur in this zone
1.Large trees (8m to 15 tall) with wide spreading crowns (Anogeissus Leicarpus,
Sclerocaraya spp., Bal