A-CDM – Integration of Airport into the Network Implementation Steps & Status. Hans Koolen NMOC/CFMU Network Operations Services. Edition June 2012. Introduction. Purpose of presentation - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: A-CDM – Integration of Airport into the Network Implementation Steps & Status

© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

A-CDM – Integration of Airport into the NetworkImplementation Steps & Status

A-CDM – Integration of Airport into the NetworkImplementation Steps & Status

Hans KoolenNMOC/CFMUNetwork Operations Services

Hans KoolenNMOC/CFMUNetwork Operations Services

Edition June 2012Edition June 2012

Page 2: A-CDM – Integration of Airport into the Network Implementation Steps & Status

2© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

Introduction Introduction Introduction Introduction

Purpose of presentation To describe which implementation steps are applicable for

Integrating a CDM airport into the Network via DPI and FUM messages.

To provide the latest available planning information

Target Audience Management Airport CDM Project Team All others who would like to have a global overview of the

planning

Page 3: A-CDM – Integration of Airport into the Network Implementation Steps & Status

3© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

AGENDA AGENDA AGENDA AGENDA

1)Introduction2)DPI/FUM Implementation Steps3)Last available planning info

Page 4: A-CDM – Integration of Airport into the Network Implementation Steps & Status

4© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● A-CDM is implemented in phases

● It is a Cooperation between:

At the airport: AO, handler, Airport, ATC/TWR

EUROCONTROL: Airport CDM-team, NMOC/CFMU

● The process requires:

Clear roles & responsibilities of EUROCONTROL

Identification of clear & transparent criteria

● The process has been defined together by APT and NMOC/CFMU

Airport CDM Integration PlanAirport CDM Integration Plan

Page 5: A-CDM – Integration of Airport into the Network Implementation Steps & Status

5© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

DPI/FUM Implementation ProcedureDPI/FUM Implementation Procedure

Implementation

Decision

Gap

Analysis

Completeness

Assessment

Implementation

Elements (1 - 5)

CBA

DPI Message

Go - No - Go

Decision NMOC/CFMU

Operational

Evaluation

Not Ready Advice

Airport Interest

in Airport CDMInformation

More Analysis

Decision

Operational DPI

Transmission to

NMOC/CFMU

Information

Phase

Analysis

Phase

Implementation

Phase

DPI Operational

Evaluation Phase

Implementation

DPI Element *

* The technical support for the DPI element can be implemented e ither in parallel with elements

1 - 5 or after their completion

Local Airport

CDM Operating

Status CDM

Airport

Page 6: A-CDM – Integration of Airport into the Network Implementation Steps & Status

6© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● Information Phase

NMOC/CFMU provides general info about DPI/FUM and NMOC/CFMU’s role in the A-CDM project

● Analysis Phase

NMOC/CFMU does not actively participate but is ready to answer to questions if necessary.

● Implementation Phase

NMOC/CFMU provides DPI implementation details

NMOC/CFMU and Airport CDM Project team draft DPI-ICD

Airport CDM platform software is updated with DPI/FUM processing

NMOC/CFMU and Airport CDM Project team agree planning of the DPI Operational Evaluation Phase

● DPI Operational Evaluation Phase

Before start: Evaluate CDM Completeness Criteria

Evaluate DPI messages

● Put DPIs into operations

Five A-CDM Implementation PhasesFive A-CDM Implementation Phases

Page 7: A-CDM – Integration of Airport into the Network Implementation Steps & Status

7© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

CDM Implementation Phases (1/3)CDM Implementation Phases (1/3)

Information Collection

Airport is interested in A-CDM

Decision to analyse the options

CBADecision to

Implement A-CDMGap Analysis

Information Phase

Analysis Phase

Mainly Airport CDM Activities – NMOC/CFMU provides information

Page 8: A-CDM – Integration of Airport into the Network Implementation Steps & Status

8© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

CDM Implementation Phases (2/3)CDM Implementation Phases (2/3)

CDM Completeness Assessment

Decision to start DPI transmission to

NMOC/CFMU

Decision to implement Airport CDM

Implement CDM Elements 1 to 5 Implement FUM

(local) CDM in Operations

Ready

Not yetReady

Implement DPI

Implementation Phase

Activity managed by Airport CDM with support from NMOC/CFMU

Page 9: A-CDM – Integration of Airport into the Network Implementation Steps & Status

9© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● First Information Exchange

● Development of the DPI-ICD

● FUM used by A-CDM

● Validation of Local Data accuracy and Timelines

● DPI Operational Evaluation

1. Communication and Message Syntax

2. Evaluation of Live Data

3. ATFCM Impact Assessment

4. Operational Trial

● DPIs Fully operational

DPI Implementation StepsDPI Implementation Steps

Page 10: A-CDM – Integration of Airport into the Network Implementation Steps & Status

10© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

DPI Implementation StepsDPI Implementation Steps

FUM used by A-CDM

First InformationExchange

Development ofDPI-ICD

Validation of Local Data Accuracy

and Timelines

DPI OperationalEvaluation

DPIs Operationalat NMOC/CFMU

Page 11: A-CDM – Integration of Airport into the Network Implementation Steps & Status

11© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

First Information Exchange First Information Exchange First Information Exchange First Information Exchange

● Purpose NMOC/CFMU provides Global Overview of DPI/FUM messages. Airport provides overview of the A-CDM project. First contact between the A-CDM project team and the NMOC/CFMU team.

● When After the A-CDM project has been approved The A-CDM project wants to include DPI/FUM into the project planning

● Duration 1 day meeting

● Required participants A-CDM project team (preferably a representative of each stakeholder such as

Airport, ATC-TWR ATC-FMP, AO,…) NMOC/CFMU staff

Page 12: A-CDM – Integration of Airport into the Network Implementation Steps & Status

12© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

Development of the DPI-ICD Development of the DPI-ICD Development of the DPI-ICD Development of the DPI-ICD

● Purpose NMOC/CFMU provides DPI messages implementation details. NMOC/CFMU provides detailed presentation on the DPI Operational

Evaluation process. NMOC/CFMU and A-CDM project team start drafting the DPI-ICD.

● When When the A-CDM project is approaching the implementation phase. Before the A-CDM software requirements for the DPI messages are

written.

● Duration Start with a 1-2 day meeting Finalisation of the DPI-ICD is estimated to take 1-2 months

● Required participants A-CDM project team, especially TWR OPS staff, FMP representative,

Software Requirements Specialist. NMOC/CFMU staff

Page 13: A-CDM – Integration of Airport into the Network Implementation Steps & Status

13© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

FUM used by A-CDM FUM used by A-CDM FUM used by A-CDM FUM used by A-CDM

● Purpose NMOC/CFMU will provide FUM on request. The A-CDM team can send request to NMOC/CFMU.

● When After the A-CDM info sharing platform is ready to receive

the FUM.

● Duration Provision of FUM can be arranged on short notice.

● Required participants A-CDM project Mgr. ODSG representative of ANSP concerned.

Page 14: A-CDM – Integration of Airport into the Network Implementation Steps & Status

14© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

Validation of Local Data Accuracy and Timelines Validation of Local Data Accuracy and Timelines Validation of Local Data Accuracy and Timelines Validation of Local Data Accuracy and Timelines

● Purpose To assess accuracy of CDM Data Provision To prevent unnecessary long DPI Operational Evaluation See “CDM Completeness Criteria” in Airport CDM Manual.

● When After A-CDM has been put into operations. Before DPI Operational Evaluation is started.

● Duration Estimated duration: 1 week – 1 month.

● Required participants A-CDM project team to asses the Criteria. EUROCONTROL CND Airport team to discuss the Criteria.

Page 15: A-CDM – Integration of Airport into the Network Implementation Steps & Status

15© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● Implement 5 Airport CDM Concept Elements

Airport CDM Information Sharing

Airport CDM Turn-around process – Miles Stones Approach

Variable Taxi-Time (VTT) Calculation

Collaborative Pre-Departure Sequence (TSAT)

CDM in Adverse conditions

● Inclusion of the following major events in the CDM process

Verification of the flight plan with the airport slot

Establishment of the TOBT

Issue of the TSAT

Actual Off-Block

● Adherence to Operational Procedures

CDM procedures documented in AIP and Airport Operating Instructions

● See Airport CDM Implementation Manual – Attachment 6

CDM Completeness Criteria (1/2)CDM Completeness Criteria (1/2)

Page 16: A-CDM – Integration of Airport into the Network Implementation Steps & Status

16© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● Accuracy & Coverage of the provided data

DPIs received for at least 97% of the flights

Accuracy of TTOT based upon TOBT <= 12min

Accuracy of TTOT based upon TSAT <= 10min

Accuracy of TTOT based upon AOBT <= 5min

The accuracy of the provided TOTs must be for 95% of the flights during normal circumstances

● Adherence to ATFM Slots

Must be 80% or better during the last month before the CDM Completeness Assessment

● Agreements

MoU signed by all partners at the airport

DPI-ICD with NMOC/CFMU agreed

LoA with NMOC/CFMU ready

CDM Completeness Criteria (2/2)CDM Completeness Criteria (2/2)

Page 17: A-CDM – Integration of Airport into the Network Implementation Steps & Status

17© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

DPI Operational Evaluation DPI Operational Evaluation DPI Operational Evaluation DPI Operational Evaluation

● Purpose To evaluate completeness and accuracy of DPI messages. See “DPI & FUM Implementation Roadmap” for details.

● When After local A-CDM has been put into operations. Before DPI messages are put into operations in

NMOC/CFMU.

● Duration Estimated duration: 3-6 months.

● Required participants A-CDM project (OPS and ENG expertise). NMOC/CFMU (URB and OPS expertise).

Page 18: A-CDM – Integration of Airport into the Network Implementation Steps & Status

18© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

CDM Implementation Phases (3/3)CDM Implementation Phases (3/3)

DPI Operational Evaluation

Decision to start DPI transmission to

NMOC/CFMU

System & Operations Improvements

Ready

Not yetReady

Operations

DPI Operational Evaluation

Phase

Activity managed by NMOC/CFMU

Page 19: A-CDM – Integration of Airport into the Network Implementation Steps & Status

19© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

DPI in Operations DPI in Operations DPI in Operations DPI in Operations

● Purpose To do the last preparations (admin). To put DPIs into operations (at NMOC/CFMU).

● When After successful DPI Operational Evaluation

● Duration Estimated duration: 1 month.

● Required participants A-CDM project team. NMOC/CFMU.

Page 20: A-CDM – Integration of Airport into the Network Implementation Steps & Status

20© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

DPI Implementation StepsDPI Implementation Steps

FUM used by A-CDM

First InformationExchange

Development ofDPI-ICD

Validation of Local Data Accuracy

and Timelines

DPI OperationalEvaluation

DPIs Operationalat NMOC/CFMU

Page 21: A-CDM – Integration of Airport into the Network Implementation Steps & Status

21© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

1. Communication and Message Syntax

2. Evaluation of Live Data

3. ATFCM Impact Assessment

4. Operational Trial

5. Operations

6. Post Operations Support

DPI Operational Evaluation – Major StepsDPI Operational Evaluation – Major Steps

Page 22: A-CDM – Integration of Airport into the Network Implementation Steps & Status

22© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

1. Communication and Message Syntax

Purpose: Initial and quick verification of message syntax and connections in order to save time during testing with live data.

How: transmission of copies of several DPI message types via e-mail and via AFTN.

How Long: one or several e-mails and a few messages via AFTN.

Report: feedback is given by NMOC/CFMU via e-mail.

Operational Evaluation PhasesOperational Evaluation Phases

Page 23: A-CDM – Integration of Airport into the Network Implementation Steps & Status

23© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

2. Evaluation of Live Data

Purpose: Determine accuracy and consistency of Live Data and suitability for ATFCM purposes.

How: transmission of DPIs for operational traffic to the ETFMS OPS evaluation (test) system.

How Long: initially 1 hour, later 24hours to several days.

Report: initial feedback is given by NMOC/CFMU via e-mail. Later statistics reports will be produced and discussed with the airport concerned.

Note that this phase may take several months dependent on the results of the first evaluations. It is required to have at least one long duration test of 7-14 days.

Operational Evaluation PhasesOperational Evaluation Phases

Page 24: A-CDM – Integration of Airport into the Network Implementation Steps & Status

24© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

3. ATFCM Impact Assessment

Purpose: Determine the impact of the provided DPIs on the ATCFM process managed by ETFMS.

How: transmission of DPIs for operational traffic to the ETFMS OPS evaluation (test) system.

How Long: at least 24 hours without interruption.

Report: Analysis and reports will be done via the ETFMS standard HMI (count graphs, oplog query,..).

Operational Evaluation PhasesOperational Evaluation Phases

Page 25: A-CDM – Integration of Airport into the Network Implementation Steps & Status

25© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

4. Operational Trial

Purpose: to verify the correct working of DPI/FUM messages in a fully operational environment.

How: transmission of DPIs for operational traffic to the ETFMS OPS system and FUMs to the airport OPS system.

How Long: several hours on 2 different days.

Report: Analysis and reports will be done via the ETFMS standard HMI (count graphs, oplog query,..) and via the airport CDM system.

Operational Evaluation PhasesOperational Evaluation Phases

Page 26: A-CDM – Integration of Airport into the Network Implementation Steps & Status

26© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

5. Operations (prepare for…)

Purpose: to organise a GoNoGo meeting and take the last actions for final operations

How: Organise the meeting, do last actions.

How Long: takes approximately 1 week.

Report: Go or NoGo decision and completed action-list.

Operational Evaluation PhasesOperational Evaluation Phases

Page 27: A-CDM – Integration of Airport into the Network Implementation Steps & Status

27© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

6. Post Operations Support

Purpose: to learn from operations and to iron-out last problems

How: Closely monitor operations and ensure the availability of Operations Support.

How Long: approximately 2 weeks close monitoring and after that normal operations support.

Report: Incident reports and others.

Operational Evaluation PhasesOperational Evaluation Phases

Page 28: A-CDM – Integration of Airport into the Network Implementation Steps & Status

28© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

Summary - Evolutionary ApproachSummary - Evolutionary ApproachA-CDM CFMU

DevelopmentsCommunication and

syntax tests

CDM operations in place

CDM Maturity Evaluation

CDM Operations and

System Improvement Processes

Evaluation of live data

Evaluation with external OPS users

Operational Trial

Operational

Y

Report

Technical and CDM Readyness

Improvements Required

Data quality readyness

Ready

ATFCM Impact Assesment

Network Integration readyness

N

External users approval

Y

N

Operational readyness

Y

N

Page 29: A-CDM – Integration of Airport into the Network Implementation Steps & Status

29© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● DPI Quality Indicators

DPI Completeness; i.e. DPIs for almost all flights

DPI Update rate; i.e. sufficient nr of updates per flight

DPI to Flight plan correlation; no DPIs for VFR/OAT flights

Rejected/ignored DPIs; must be below 3%

Filing time behaviour; must be as agreed in the ICD

● DPI performance Indicators

TOT predictability; must be better than flight plan predictability

DPI Operational Evaluation Criteria DPI Operational Evaluation Criteria

Page 30: A-CDM – Integration of Airport into the Network Implementation Steps & Status

30© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

AGENDA AGENDA AGENDA AGENDA

1) Implementation Phases

2) CDM Completeness Criteria

3) DPI Operational Evaluation Process

4) Summary

5) Documentation & Contacts

Page 31: A-CDM – Integration of Airport into the Network Implementation Steps & Status

31© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● Four main A-CDM Implementation Phases

Phases 1,2 : Information & Analysis Phases (NMOC/CFMU provides info)

Phase 3: (local) Implementation Phase (NMOC/CFMU provides support)

Phase 4: DPI Operational Evaluation Phase (managed by NMOC/CFMU)

● Phase 3 ends with: CDM Completeness Assessment

Determines if Airport is ready be integrated in the ATM Network

● Phase 4: DPI Operational Evaluation

System integration testing & putting into Operations

Takes 3-6 months

Summary Summary

Page 32: A-CDM – Integration of Airport into the Network Implementation Steps & Status

32© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

AGENDA AGENDA AGENDA AGENDA

1) Implementation Phases

2) CDM Completeness Criteria

3) DPI Operational Evaluation Process

4) Summary

5) Documentation & Contacts

Page 33: A-CDM – Integration of Airport into the Network Implementation Steps & Status

33© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● Airport CDM Manual

Contains CDM Milestones approach and a general Description of DPI messages

Ref: Edition 3.1, July 2010.

http://www.euro-cdm.org/library/cdm_implementation_manual.pdf

● NM/CFMU Flight Progress Messages Document

Contains DPI and FUM message syntax and semantics, general trigger events

Ref: URB/USD/MSG_INTF, version 1.900, dated 01/02/2012

http://www.cfmu.eurocontrol.int/cfmu/gallery/content/public/library/handbook_supplements/user_guides/docu_flight_progress_msg_latest.pdf

● DPI Implementation Guide

Contains a details of DPI messages, including trigger events and processing by ETFMS

Ref: URB/USD/DPI_Impl_Guide, version 1.600, dated 01/02/2012

http://www.cfmu.eurocontrol.int/cfmu/gallery/content/public/userdocs/dpi/DPI_Impl_Guide.pdf

Documentation (1/2)Documentation (1/2)

Page 34: A-CDM – Integration of Airport into the Network Implementation Steps & Status

34© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● FUM Implementation Guide

Contains a details of FUM messages, including accuracy info and implementation guidelines

Ref: URB/USD/FUM_Impl_Guide, version 1.200, dated 01/02/2012

http://www.cfmu.eurocontrol.int/cfmu/gallery/content/public/userdocs/dpi/FUM_Impl_Guide.pdf

● DPI & FUM Implementation Road Map

Contains description of steps for the DPI & FUM evaluation and Evaluation Criteria

Ref: URB/USD/DPI_FUM_Impl_RM, version 1.400, dated 01/02/2012

http://www.cfmu.eurocontrol.int/cfmu/gallery/content/public/userdocs/dpi/DPI_FUM_Impl_RM.pdf

● DPI ICD

Contains the Airport specific DPI interface with the actual implementation of the DPI contents and trigger events

http://www.cfmu.eurocontrol.int/cfmu/gallery/content/public/userdocs/dpi/DPI_ICD_template_v1450.pdf

Documentation (2/2)Documentation (2/2)

Page 35: A-CDM – Integration of Airport into the Network Implementation Steps & Status

35© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

● Contacts:

Hans Koolen, tel +32 2 729 9876

e-mail: [email protected]

Ioana Coliban, tel +32 2 729 9826

e-mail: [email protected]

ContactsContacts

Page 36: A-CDM – Integration of Airport into the Network Implementation Steps & Status

© EUROCONTROL 2012 – Network Management Operations Centre (NMOC or CFMU)

Thank you for your attention

Thank you for your attention