Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm to Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
A CITIZEN PARTICIPATORY AUDIT REPORT
CPA Report No. 2015-01A
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm to Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
ABBREVIATIONS AND ACRONYMS……………………………………………… i
LETTER……………………………………………………………………………….. 1
1.0 BACKGROUND…………………………………………………………... 3
2.0 AUDIT FOCUS……………………………………………………………. 4
3.0 AUDIT OBJECTIVES…………………………………………………….. 6
4.0 AUDIT CRITERIA………………………………………………………... 7
5.0 AUDIT METHODOLOGY………………………………………………... 8
6.0 AUDIT PERIOD…………………………………………………………... 9
7.0 AUDIT RESULTS………………………………………………………… 10
7.1 PLANNING AND PROGRAMMING……………………………… 10
7.2 PROJECT IMPLEMENTATION…………………………………… 11
7.2.1 BARANGAY MALAG-IT………………………………….. 12
7.2.2 BARANGAY SAN PEDRO………………………………… 14
7.2.3 BARANGAY TABUC………………………………………. 17
7.3 RESULTS OF SURVEY RENDERED BY CSO…………………… 20
7.3.1 REPORT FINDING…………………………………………. 21
8.0 AUDIT CONCLUSIONS………………………………………………….. 27
9.0 RECOMMENDATIONS FOR EXECUTIVE ACTION…………………... 28
10.0 AUDITEE’S COMMENTS………………………………………………… 29
11.0 AUDITOR’S EVALUATION/REJOINDER………………………………. 30
12.0 ACKNOWLEDGEMENT………………………………………………….. 31
APPENDICES……………………………………………………………………………
APPENDIX A – MAP OF THE MUNICIPALITY OF PONTEVEDRA…………
APPENDIX B – BARANGAY SAN PEDRO, FMR (1ST AND 2ND SECTIONS)..
APPENDIX C – BARANGAY TABUC, FMR……………………………………
APPENDIX D – BARANGAY MALAG-IT, FMR……………………………….
APPENDIX E – SATELLITE VIEW OF BARANGAYS SAN PEDRO, TABUC
AND MALAG-IT, FMRs FROM THE NATIONAL
HIGHWAY
APPENDIX F – SURVEY QUESTIONNAIRE
APPENDIX G – CONSOLIDATED RESULT OF SURVEY CONDUCTED BY
CSO PARTNERS IN BARANGAYS SAN PEDRO, TABUC
AND MALAG-IT
TABLE OF CONTENTS
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
i
ABC Approved Budget of the Contract
AIP Annual Investment Plan
APP Annual Procurement Plan
COA Commission on Audit
CPA Citizen Participatory Audit
CSOs Civil Society Organizations
DILG Department of Interior and Local Government
DO Department Order
CY Calendar Year
DPWH Department of Public Works and Highways
FMRs Farm to Market Roads
GPPB Government Procurement Policy Board
HLH Hercor Lumber and Hardware
JASAC Jaro Archdiocesan Social Action Center
LGU Local Government Unit
NTP Notice to Proceed
PAPs Programs, Activities and Projects
PCCP Portland Cement Concrete Pavement
PERT/CPM Program Evaluation and Review Technique/Critical Path
Method
PICPA Philippine Institute of Certified Public Accountant
PO Purchase Order
POW Program of Work
RA Republic Act
SGH Seal of Good Housekeeping
TS Technical Services
VFM Value for Money
ABBREVIATIONS AND ACRONYMS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
1
Republic of the Philippines
COMMISSION ON AUDIT
Regional Office No. VI
Ungka I, Pavia, Iloilo
__________________________________________________________________________
June 30, 2015
Honorable ESTEBAN JOSE B. CONTRERAS, M.D.
Municipal Mayor
Municipality of Pontevedra
Province of Capiz
Dear Mayor Contreras,
Pursuant to Commission on Audit (COA) Resolution No. 2006-002 dated January 31, 2006,
directing Auditors to conduct compliance as well as performance or value-for-money (VFM)
audits, complementary to their financial audit, and to prepare separate reports for the
compliance/VFM audit, while including the gist of the significant findings, observations and
recommendations from the said audit in the Annual Audit Report, the Audit Team of the
Municipality of Pontevedra, Capiz conducted a performance audit of Farm-to-Market Road
(FMR) implemented by administration and completed in CY 2014.
For the purpose, we adopted the audit technique of citizen participatory audit in line with the
COA’s response to the call of the President of the Philippines for increased transparency and
citizen participation in governance, and, invoking COA’s authority granted by the 1987
Constitution “to define the scope of its audit and examination” and “establish the techniques
and methods required therefore”. As audit tools, we used “geo-tagging” during project
inspection and administered Survey Questionnaires on the implementation of FMR projects.
The survey jointly conducted by the Audit Team and Members of the Civil Society
Organizations, namely, Jaro Archdiocesan Social Action Center (JASAC) and Philippine
Institute of Certified Public Accountants (PICPA) aimed to determine whether the FMR
contributed to the attainment of the objectives and intent of Republic Act No. 8435 and its
Implementing Rules and Regulations.
LETTER
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
2
In addition the survey was conducted to determine whether the purpose of the FMR Project is
achieved by the Local Government Unit (LGU) through proper identification of priority
locations of FMRs that takes into account the number of farmers and fisher folk and their
families who shall benefit therefrom and the amount, kind and importance of agriculture and
fisheries products produced in the area.
The details of the audits are embodied in this letter.
LETTER
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
3
Republic Act (RA) No. 8435, otherwise known as the Agriculture Modernization Act of the
Philippines, prescribes urgent related measures to modernize the agriculture and fisheries
sectors of the country in order to enhance their profitability, and prepare said sectors for the
challenges of globalization through an adequate, focused and rational delivery of necessary
support services, appropriating funds therefor and for other purposes.
Pertinent portion of the said RA states that it is the declared policy of the State to enable those
who belong to the agriculture and fisheries sectors to participate and share in the fruits of
development and growth in a manner that utilizes the nation’s resources in the most efficient
and sustainable way possible by establishing more access to assets, income, basic and support
services and infrastructure.
Section 46 of the said RA provides for Agriculture and Fisheries Infrastructure Support
Services. – The Department of Public Works and Highways, the Department of Transportation
and Communications, the Department of Trade and Industry and the LGUs shall coordinate
with the Department of Agriculture (referred to as the “Department” in the Act) to address the
infrastructure requirements in accordance with this Act. Provided, that the Department and the
LGU shall also strengthen its agricultural engineering support in carrying out the smooth and
expeditious implementation of agricultural infrastructure projects.
As such, Section 52 of the RA provides that the Department of Agriculture shall coordinate
with the LGUs and the resident-farmers and fisher folk in order to identify priority locations of
farm-to-market roads (FMRs) that take into account the number of farmer and fisher folk and
their families who shall benefit therefrom and the amount, kind and importance of agriculture
and fisheries products produced in the area.
The importance of implementation of FMR road projects in country-side development that will
help uplift the lives of farmers and fisherfolks in the rural areas and the role of LGUs in this
regard, led to the selection of FMR projects for the next pilot on Citizen Participatory Audit
(CPA) by the Commission. FMRs were subjected to CPA considering, among others, the value
and extent of implementation, the degree of improvement the project will have in the quality of
life of the project beneficiaries, the importance of addressing the need to provide infrastructure
access, and vulnerability to corruption. In Region VI, among the six (6) Provinces, the Province
of Capiz had the most number of FMR projects involving large amount of money implemented
in CY 2014, hence, selected FMRs were subjected to CPA.
1.0 BACKGROUND
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
4
The audit focused on FMR projects completed during CY 2014 adopting the “Citizen
Participatory Audit” (CPA) approach. For this purpose, the criteria for high value in terms of
project cost and the presence of resident or advocate Civil Society Organizations (CSOs),
among others, were considered in the selection criteria of projects for evaluation.
The focus of Audit Team 4 was the FMRs located in Barangays Malag-it, Tabuc and San Pedro,
Municipality of Pontevedra, Province of Capiz. The projects covered by the audit have a total
length of 249 meters with a total population of 6,075 that accounted for 14% of the total
population of 43,525.
Barangay San Pedro
Project Cost: P389,420
Length: 75 meters
Width : 4 meters
Mode of Implementation:
By Administration
No. of Population:
1,142
Barangay Tabuc
Project Cost: P430,610
Length: 84 meters
Width : 4 meters
Mode of Implementation:
By Administration
No. of Population:
3,254
Barangay Malag-it
Project Cost: P489,771
Length: 90 meters
Width : 4 meters
Mode of Implementation:
By Administration
No. of Population:
1,679
Station 2 Station 1
Brgy San Pedro FMR
Brgy Tabuc FMR
Brgy Malag-it FMR
2.0 AUDIT FOCUS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
5
The entrance conference was conducted on May 22, 2015 by the Members of the CPA Team
composed of COA Auditors and CSO partners, namely, Jaro Archdiocesan Social Action
Center (JASAC) and Philippine Institute of Certified Public Accountant (PICPA), with
Honorable Mayor Esteban Jose B. Contreras and his staff mainly to inform about the Citizen
Participatory Audit (CPA), a priority program of the COA founded on the premise that public
accountability can prosper only with vigilant and involved citizenry.
Entrance conference May 22, 2015 with
COA Audit Team, CSO partners and
LGU Officials
ATL discussed the FMRs covered
by CPA with the Municipal Mayor
ATL discussed the purpose of CPA
using geotagging as a tool with the
assistance of TAS and CSO partners
2.0 AUDIT FOCUS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
6
The citizen participatory audit was conducted to determine whether:
1. Estimates of the work, items, quantities and costs in the approved Program of Works
(POW) were accurate and project costs were reasonable;
2. FMR projects were implemented in accordance with approved POW, plans and
specification and DPWH Department Orders;
3. FMR projects achieved the intended purpose
Specifically,
3.1 To validate the public awareness on the FMR projects implemented by
LGUs;
3.2 To verify access of farmers/fisher folk to market as well as arterial roads
and highways through FMR projects; and
3.3 To assess the level of satisfaction of beneficiaries on the FMR projects
implemented by LGUs in their respective barangays.
3.0 AUDIT OBJECTIVES
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
7
To achieve the audit objectives, the team adopted the following audit criteria:
Accuracy of estimates and reasonableness of project cost
RA 9184 and its Implementing Rules and Regulations;
DPWH Department Order (DO) No. 11 Series of 2014 dated February 3, 2014
and DO No. 72, s. of 2012;
COA Circular Nos. 2012-003 and 2009-001 dated October 29, 2012 and
February 12, 2009, respectively; and
GPPB Resolution Nos. 018-2006, 07-2009 and 03-2011.
Compliance with POW, plans and specifications
DPWH Department Order No. 11 regarding provision on standard measurement
for road width, length and shoulder.
Effective utilization of FMR projects
Farmers’/fisher folk access/link to market through FMR projects;
Road links to the agricultures and fisheries production sites, coastal landing
points and post-harvest facilities to the market and arterial roads and highways;
Located within key production areas under convergence initiatives which link
these areas to higher road class system.
4.0 AUDIT CRITERIA
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
8
The Audit Team performed the following techniques and procedures:
Gathered and reviewed approved Annual Investment Plan (AIP), Annual
Procurement Program (APP) and project documents such as POW and detailed cost
estimates, approved plans and specifications, Approved Budget of the Contract
(ABC), bid and contract documents;
Analyzed disbursement vouchers and supporting documents;
Reviewed financial and project accomplishment reports;
Conducted ocular inspection using Geo-tagging and documentation of the project
with the assistance of Technical Audit Specialist and CSO Partners;
Evaluated contract cost and validated reported accomplishment together with the
Technical Audit Specialist and CSO Partners;
Interviewed LGU officials and employees involved in project implementation;
Administered survey questionnaire to end-users/project beneficiaries with the
assistance of CSO Partners to evaluate project utilization. For this purpose, the
Team adopted the format used in the previous FMR-CPA;
The consolidation, analysis and preparation of survey results were mainly done by
CSO Partners; and
Issued Audit Observation Memorandum.
5.0 AUDIT METHODOLOGY
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
9
The CPA planning was slated April 27-30, 2015 with COA Auditors and CSOs representatives
in attendance. The data gathering and processing, actual fieldwork, inspection, data analysis,
preparation and submission of CPA report were undertaken from June 1 to 30, 2015.
Actual inspection with CSO partners and COA Audit
Team stopped momentarily due to the outpour of heavy
rain
Capability Building April 27-30, 2015 Entrance Conference May 22, 2015
Start of Actual Fieldwork June 1-3, 2015 Processing/analysis of data with
ATL, Senior TAS June 9-10, 2015
Exit Conference June 25, 2015
6.0 AUDIT PERIOD
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
10
Cognizant of the objectives and rationale on the enactment of RA 8435, the Municipal
Government of Pontevedra committed to provide FMRs linking the agriculture production sites
to the market and arterial roads and highways. For this purpose, the Municipal Government
included in their CY 2014 APP and AIP the construction of FMRs amounting to P1.750 million
under the 20% Development Fund. Of the said amount, three (3) FMR projects costing P1.340
million were subjected to Citizen Participatory Audit. The Local Government Unit has the
capability to undertake projects by administration with one (1) Municipal Engineer assigned to
supervise the projects and available heavy equipment to be utilized, hence, the projects were
implemented by that Municipality by administration for a total amount of P1.310 million as
follow:
Project Location
Project Cost/POW
Actual Project Expenditures
Materials *Fuel Labor Total
Brgy. Malag-it 499,988.70 369,315.00 21,000.00 99,456.00 489,771.00
Brgy. San Pedro 399,998.10 289,580.00 21,000.00 78,840.00 389,420.00
Brgy. Tabuc 439,997.40 322,060.00 21,000.00 *87,550.00 430,610.00
Total 1,339,984.20 980,955.00 63,000.00 265,846.00 1,309,801.00 * Fuel consumption based on POW (supported with vale slip);
** Based on POW in the absence of Pakyaw Contract
During the audit the following deficiencies were noted:
1. Accuracy of estimates and reasonableness of project cost
1.1 The preparation of ABC and POW are detailed engineering activities required in
the implementation of infrastructure projects. The POW shall include, among other
things, estimates of the work, items, quantities and costs and a PERT/CPM network
of the project activities. In the preparation of POW, Detailed Cost Estimates and
ABC, the implementing agencies are guided by Department Orders (DO) issued by
the DPWH.
1.2 Audit, however, disclosed that estimates for 3 FMR projects as reflected in the
LGUs POW were not compliant with DPWH DOs. Only the18 man-days project
duration for labor was indicated in the POW instead of period of project completion
from procurement of materials. Also, provision of a minimum of 1.5 meters
shoulder gravel surfacing was not indicated in the POW.
The approved POW and cost estimates for the implementation of Malag-it, Tabuc
and San Pedro were found to be 19.07%, 7.09% and 10.62%, respectively, above
COA evaluated cost, hence, considered excessive.
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
11
1.3 The deficiencies in the project POW which was the basis for the subsequent bidding
and award of procurement contracts for materials and labor resulted to
uneconomical and inefficient project implementation.
1.4 Notices to Proceed issued pertain to delivery of materials only. The projects were
reported completed from May 19, 2014 to November 28, 2014 or 73 to 210 days
from receipt of materials with labor component of the project completed beyond the
period stipulated in the Pakyaw Labor Contracts as follow:
2. Project implementation in conformity with POW, Plans and Specifications
2.1 Inspection conducted on June 1 to 3, 2014 revealed that the 3 FMR projects
costing P1.340 million per POW implemented by the Municipality for a total
amount of P1.309 million were not in accordance with the approved POW,
plans and specification, thus, resulted to project deficiency amounting to
P122,883.57.
Particulars
Name of Barangay
San Pedro Tabuc Malag-it
Length 75 mts 84 mtrs 90 mtrs
Width 4 meters 4 meters 4 meters
Date of NTP/PO (materials) 10/16/13 5/5/2014 9/16/14
Date of Acceptance (materials) 10/18/13 5/8/2014 -
Labor period per POW 18 MDs 18 MDs 18 MDs
Date started (Labor) 4/30/14 7/14/14 10/8/14
Pakyaw Labor Contract period 15 CD 15CD 20 CD
Date completed (Labor) 5/16/14 8/7/2014 11/28/14
Period of completion - Labor 16 24 51
Period of completion from receipt of
materials
210 91 *73
Date of Certification as 100% completed by
Project Engineer
5/19/14
8/8/2014
11/13/14
Legend: * Based on NTP issued in the absence of Acceptance Report while DR and CI were
undated
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
12
Payee/
Contractor Project Cost
Per COA
Evaluation Difference Remarks
BARANGAY MALAG-IT Concreting of 360 sq.m. Barangay Road, with 0.80m Shoulders at both sides and a carriageway of 4.00 meters x 0.15
meters thick
HLH/
Erwin
Buño
P 489,771.00 P443,726.70 P 46,044.30 Based on POW, the project has a total length of 90 meters
and width of 4 meters. Result of project validation and
evaluation disclosed that the work accomplished was only
90.60% equivalent to P443,726.70 with project deficiency
amounting to P46,044.30, computed as follow:
Item No.
Per Pakyaw Contract Per COA-TAS Evaluation
U. Cost Qty Amt. Qty Amt. Diff.
Labor 105 4 565 2,260 504.00 2,016.00 244.00
210 13 170 2,210 144.90 1,883.70 326.30
311 1,759 54 94,986 54 94,986.00 0.00
Sub-total 99,456 98,885.70 570.30
Fuel 105 210 50 10,500 92 4,600.00 5,900.00
210 210 50 10,500 115 5,750.00 4,750.00
311 - 50 - - - 0.00
Sub-total 21,000 10,350.00 10,650.00
Materials
Item 105 – item 104 used as shoulder
104 340 85 32,300 85 32,300.00 -
210 400 170 68,000 144.90 57,960.00 10,040.00
311
Cement 270 596 160,920 567 153,090.00 7,830
H.Blade 65 6 390 6 390.00 0.00
RSB,
16mm
420 32 13,440 32 13,440.00 0.00
RSB
10mm
160 7 1,120 7 1,120.00 0.00
CWN 65 5 325 5 325.00 0.00
W.gravel 918 68 62,424 58 53,244.00 9,180.00
W.sand 598 42 25,116 29 17,342.00 7,774.00
spade 980 1 975 1 975.00 0.00
Flat bar 1,260 1 1,255 1 1,255.00 0.00
R.lumber 612 5 3,050 5 3,050.00 0.00
Sub-total 369,315 334,491.00 34,824
Total 489,771 443,726.70 46,044.30
Ocular inspection of concrete pavement - Length – 90
meters, Width – 4 meters
Total Area – 504 sq. m.
Length of 90 meters and width of 4 meters or a total of
360 sq. meters in accordance with Plans and specs
7.0 AUDIT RESULTS
Barangay Malag-it FMR
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
13
Payee/
Contractor Project Cost Per COA
Evaluation Difference Remarks
Start of concrete pavement measured at 360 sq. meters per
Pakyaw Contract
The deficiencies are discussed as follow:
Item 105 – Subgrade Preparation
At the time of inspection, the road was already paved, hence,
the quality of work could no longer be validated. The
accomplished area as measured was 504 sq.m. out of 565.00
sq.m per POW/Pakway Contract equivalent to 89.20% or a
variance of 61.00 sq.m amounting to P6,144.00.
Per Pakyaw Contract Sq.m. 565
Actual Accomplishment per Inspection 504
Accomplishment under/(over) 61
Labor (61 sq.m. x P4/sq.m.) P 244.00
Fuel and oil
Per POW 210 lts. @ 50/liter 10,500
Per Eval. 92 ltrs @ P50/liter 4,600 5,900.00
Deficiency P6,144.00
Item 104 was used as road shouldering materials. Actual
subgrade preparation was measured 504 sq.m. out of 565
per Pakyaw Contract.
Measurement of actual width of road shoulders at both
sides was .80 meters in accordance with Plans & Specs but
below the DPWH standard of 1.50 meters
In addition, the following observations were noted: As indicated in the road cross section detail 85.00 cu.m.
of Item 104 – Backfilling materials which were included
were under this work item and utilized as road
shouldering materials. This scope of work should have
been treated as a separate pay item. Per DPWH standard
specifications Item 104 is not suited for road shoulders;
and
Width of road shoulders at both sides per approved plan
was only 0.80 meters which was below 1.50 meters as
required under DPWH Department Order No. 11, dated
February 3, 2014.
Noted pavement cracks
during actual inspection.
Total actual
accomplishment was only
85.24% or 144.9 cu.m. of
the 170 cu.m.
Item 201 – Aggregate Base Course
The volume accomplished was only 144.9 cu.m. or 85.24% of
the required volume of 170 cu.m. per POW or a variance of
25.10 cu.m amounting to P15,116.30 computed below:
Per Pakyaw Contract cu.m. 170.00
Actual Accomplishment ( including shrinkage factor) 144.90
Accomplishment under/(over) cu.m. 25.10
Materials (25.10 x 400/cu.m.) P10,040.00
Labor (25.10 x 13/cu.m) 326.30
Fuel and oil
Per POW 210 lts. @ 50/liter 10,500
Per Evaluation 115 ltrs @ P50/liter
5,750 4,750.00
Deficiency P15,116.30
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
14
Payee/ Contractor Project Cost
Per COA Evaluation Difference Remarks
\
End of concrete pavement
measured at 90 linear
meters
Measuring actual thickness
of concrete pavement in
accordance with POW
Item 311 – Portland Cement Concrete Pavement (PCCP)
The total length of concrete paved road measured was 90.00
linear meters which was in accordance with the approved
plans and POW, however, provisions for materials were
excessive by P24,784 as follow:
Material
Unit
Quantity
Diff.
Unit
Cost
Amt. PO/
PO
W
COA
Est.
Portland Cement bag 596 567 29 270 7,830
Washed Gravel cu.m. 68 58 10 918 9,180
Washed Sand cu.m. 42 29 13 598 7,774
Total cost of deficiency 24,784
Other deficiencies noted:
Standard thickness of 0.15m and width of 6.10m were not
observed; and
Scaling in concrete pavement
BARANGAY SAN PEDRO
Concreting of 300sq.m. Barangay Road, with 0.80m. Shoulders at both sides and a carriageway of 4.00 meters X 0.15
meters thick BY & Sons
Trading/E. Buno P389,420.00 P346,815.96 P42,604.04
Based on POW, the project has a total length of 75 meters
and width of 4 meters. Result of project validation and
evaluation disclosed that the work accomplished was only
89.06% equivalent to P346,815.96 with project deficiency
amounting to P42,604.04 computed below:
Station 1 with 34.31 and Station 2 with 39.35 linear meters
and width of 4 meters or a total of 294.64 sq. meters of the
300 sq. meters per Plans & Specs
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
15
Payee/ Contractor
Project Cost
Per COA Evaluation
Difference Remarks
Barangay San Pedro - Station 1
Length – 34.31 linear meters Width – 4 meters
Total Area – 137.24 sq. mtrs.
Barangay San Pedro - Station 2
Length – 39.35 linear meters
Width – 4 meters Total Area -157.40 sq. mtrs.
Item No.
Per Pakyaw Contract Per COA-TAS Evaluation
U. Cost Qty Amt. Qty Amt. Diff.
Labor 105 5.10 450 2,295 355.42 1,812.62 482.38
210 17 135 2,295 102.18 1,737.10 557.90
311 1,650 45 74,250 44.20 72,923.40 1,326.60
Sub-total 78,840 76,473.12 2,366.88
Fuel
105 210 50 10,500 92 4,600.00 5,900.00
210 210 50 10,500 115 5,750.00 4,750.00
311 - 50 - - - 0.00
Sub-total 21,000 10,350.00 10,650.00
Materials
Item 105 – item 104 used as shoulder 104 380 68 25,840 68 25,840.00 -
210 400 135 54,000 102.18 40,872.84 13,127.16
311
Cement 255 495 126,225 473 120,615.00 5,610
H.Blade 71 5 355 5 355.00 0.00
RSB,
16mm 420 24 10,080 24 10,080.00 0.00
Item No. Per Pakyaw Contract Per COA-TAS Evaluation
U. Cost Qty Amt. Qty Amt. Diff.
RSB 10mm 160 4 640 4 640.00 0.00
CWN 60 4 240 4 240.00 0.00
W.gravel 900 57 51,300 48 43,200.00 8,100.00
W.sand 550 30 16,500 25 13,750.00 2,750.00
spade 800 1 800 1 800.00 0.00
Flat bar 1,200 1 1,200 1 1,200.00 0.00
R.lumber 600 4 2,400 4 2,400.00 0.00
Sub-total 289,580 259,992.84 29,587.16
Total 389,420 346,815.96 42,604.04
Actual inspection of FMR Project was measured at 73.66
linear meters out of 75 linear meters per Plans and Specs
Actual area accomplished for
subgrade preparation was
measured @ 355.42 sq.m.or 78.98% of the 450 sq.m.
Actual thickness was
measured at 0.15 meters
The deficiencies are discussed as follow:
Item 105 – Subgrade Preparation
At the time of inspection, the road was already paved,
hence, the quality of work could no longer be validated.
The accomplished area as measured was 355.42 sq.m. out
of 450.00 sq.m per POW/Pakway Contract equivalent
only to 78.98% or a variance of 95.48 sq.m amounting to
P6,382.38.
Per Pakyaw Contract Sq.m. 450.00
Actual Accomplishment (Sections 1 and 2) 355.42
Accomplishment under/(over) 94.58
Labor (94.58 sq.m @ P.10/sq.m.) P482.38
Fuel and oil
Per POW 210 lts. @ 50/liter 10,500
Per Eval. 92 ltrs @ P50/liter 4,600 5,900.00
Deficiency P6,382.38
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
16
Payee/
Contractor
Project Cost Per COA
Evaluation
Difference
Remarks
Side of the concrete
pavement without shoulder
due to limited carriageway
Side of the concrete
pavement with
inadequate/limited width
In addition, the following observations were noted:
Some portion of the right and left side of the road
showed no shouldering materials applied due to limited
carriageway;
Some portion of the right and left side of roadway have
loose shouldering materials which would tend to erode
at the outpour of heavy rain;
Due to observed inadequate/limited width, some
sections within the project limits were not provided with
road shoulders specifically section 2 left side, hence, the
actual area of subgrade preparation was reduced; and
As indicated in the road cross section detail 68.00 cu.m.
of Item 104 – Backfilling materials were included were
under this work item and utilized as road shouldering
materials. This scope of work should have been treated
as a separate pay item. Per DPWH standard
specifications Item 104 is not suited for road shoulders.
Side of the concrete
pavement with loose
shoulder
Measurement of actual
volume of aggregate base
course was only 75.69% or
102.18 cu.m.of the 135
cu.m.
Actual PCCP was
measured at 73.66 linear
meters of the 75 linear
meters per Plans and
Specs
Item 201 – Aggregate Base Course
The volume accomplished was only 102.18 cu.m. or 75.69% of
the required volume of 135 cu.m. per POW or a variance of
32.82 cu.m amounting to P18,435.06 computed below.
Per Pakyaw Contract cu.m. 135.00
Actual Accomplishment (including shrinkage factor) 102.18
Accomplishment under/(over) P 32.82
Materials (32.82 x 400/cu.m.) 13,127.16
Labor (32.82 cu.m. @ P17/cu.m.) 557.90
Fuel and oil 0
Per POW 210 lts. @ 50/liter 10,500 0
Per Eval. 115 ltrs @ P50/liter 5,750 4,750.00
Deficiency P18,435.06
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
17
Payee/
Contractor
Project
Cost
Per COA
Evaluation
Difference
Remarks
Item 311 – Portland Cement Concrete Pavement (PCCP)
The total length of concrete paved road was measured at 73.66 linear meters of the 75.00 linear meters as programmed which is equivalent
to 98.21%. The deficiency amounting toP17,786.60 was computed, as
follow:
Per Pakyaw Contract - (75 l.m) Cu.m. 45.00
Actual Accomplishment (73.66 l.m.) 44.20
Accomplishment under/(over) 0.80
Labor cost per cu.m. P1,650.00
Deficiency - Labor P1,326.60
Material
Unit Quantity
Diff.
U. Cost
Amt. PO/
POW COA Eval.
P.Cement bag 495 473 22 255 5,610
W.Gravel cu.m. 57 48 9 900 8,100
W. Sand cu.m. 30 25 5 550 2,750
Deficiency-material P16,460
End of Brgy San Pedro FMR, from Stn 1 with 34.31 to
Stn 2 with 39.35 linear meters or a total of 73.66 liner
meters.
Barangay Tabuc Concreting of 300 sq.m. Barangay Road, with 0.80m Shoulders at both sides and a carriageway of 4.00 meters x 0.15
meters thick HLH/Erwin
Buno
P430,610.00 P396,374.77 P34,235.23
Based on POW, the project has a total length of 84 meters
and width of 4 meters. Result of project validation and
evaluation disclosed that the work accomplished was only
92.05% equivalent to P396,374.77 with project deficiency
amounting to P34,235.23, as summarized below.
Item
No.
Per Pakyaw Contract Per COA-TAS Evaluation
U. Cost Qty Amt. Qty Amt. (Over)
/Under
Labor
105 4.56 504 2,300 477.01 2,175.16 124.84
210 15.33 150 2,300 137.14 2,102.36 197.64
311(.15m) 246.88 336 82,950 340.72 84,116.95 -1166.95
Sub-total 87,550 88,394.47 -844.47
Fuel
105 210 50 10,500 92 4,600.00 5,900.00
210 210 50 10,500 115 5,750.00 4,750.00
311 - 50 - - - 0.00
Sub-total 21,000 10,350.00 10,650.00
Length of 84 meters and width of 4 meters or a total area of
336 sq. meters
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
18
Payee/
Contractor
Project
Cost
Per COA
Evaluation
Difference
Remarks
Materials
Item 105 – item 104 used as shoulder
104 380 69 26,220 69 26,220 -
210 395 150 59,250 137.1
4
54,170.30 5,079.70
311 0
Cement 260 555 144,300 530 137,800 6,500.00
H.Blade 70 5 350 5 350 0.00
RSB,
16mm
420 26 10,920 26 10,920 0.00
RSB 10mm 160 5 800 5 800 0.00
CWN 60 4 240 4 240 0.00
W.gravel 900 63 56,700 53 47,700 9,000.00
W.sand 550 34 18,700 27 14,850 3,850.00
spade 800 1 800 1 800 0.00
Flat bar 1,240 1 1,240 1 1,240 0.00
R.lumber 635 4 2,540 4 2,540 0.00
Sub-total 322,060 297,630.30 24,429.70
Total 430,610 396,374.77 34,235.23
Actual inspection of FMR Project was measured at 85.18 meters
and width of 4.00 meters
The deficiencies are discussed as follow:
Item 105 – Subgrade Preparation
At the time of inspection, the road was already paved, hence,
the quality of work could no longer be validated.The length of
the road as measured was 85.18 l.m. which is over by .18 l.m.
as compared with the length per POW of 85 l.m. It was also
noted that the width of the project ranged from 4.00 to 5.60m.
In view of this, some sections within the project limits were
provided with road shoulders, the actual area of subgrade
preparation accomplished was 477.01 sq.m. representing
94.64% of the area of 504.00 sq.m. per POW. Per attached
detailed unit price analysis, the fuel consumption required to
undertake the sub-grade preparation of 477.01 sq.m. is only 92
liters instead of 210.00 liters per POW with prevailing market
price of fuel @ P50, the computed cost of project discrepancy
amounted to P5,900.
Actual subgrade
preparation was measured @ 477.01 sq.m.or 94.64%
of the 504 sq.m.
Actual thickness was measured at
0.15 meters
In addition, the following observations were noted: 69.00 cu.m. of Item 104 – Backfill materials included this
pay item were utilized as road shouldering materials as
indicated in the road cross section detail. This scope of
work should have been treated as a separate pay item,
however, per DPWH standard specifications, Item 104 is
not suited for road shoulders.
Width of road shoulders at both sides as per approved
plan was only 0.80 meters which was not in accordance
with DPWH DO No. 11 dated 2/3/14 relative to the
design standrads for FMRs which requires width of 1.50
meters for road shoulder.
Actual width was measured 4 meters while road shoulders at both
sides was .80 meters which is below the DPWH standard of 1.50
meters
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
19
Payee/
Contractor
Project Cost Per COA
Evaluation
Difference
Remarks
Measurement of actual volume of aggregate base course
was only 91.43% or 137.14 cu.m.of the 150 cu.m.
Item 201 – Aggregate Base Course
The volume accomplished was only 137.14 cu.m. or 91.43%
of the required volume of 150 cu.m. per POW or a variance of
12.86 cu.m, thus the computed deficiency amounted to
P10,112.46, as tabulated below.
Materials (12.86 x 400/cu.m.) P5,143.85
Labor 218.61
Fuel and oil
Per POW 210 lts. @ 50/liter 10,500
Per Eval. 115 ltrs @ P50/liter 5,750 4,750.00
Deficiency P10,112.46
End of Brgy Tabuc FMR, with an actual length of
concrete pave road measured @ 85.18 linear meters instead
of 84.00 linear meters as per POW
Item 311 – Portland Cement Concrete Pavement (PCCP)
The total length of concrete paved road as measured was 85.18
linear meters instead of 84.00 linear meters as programmed,
having an excess accomplishment of 1.18 l.m. equivalent to
1.40%. Although, the total length of road paved is longer by
1.18 l.m., compared to the length in the plan and POW, it was
noted that the quantities of materials were found to be
overestimated thus, the materials used in the project were
purportedly less than the quantity procured by a total amount
P19,350.00 computed as follow:
Material
Unit Quantity
Diff.
Unit Cost
Amt. PO/
POW COA Est.
Portland Cement bag 555 530 25 260 6,500
Washed Gravel
cu.m. 63 53 10 900 9,000
Washed Sand cu.m. 34 27 7 550 3,850
Total cost of deficiency 19,350
Total
P1,309,801.00
P1,186,917.43
P122,883.57
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
20
EFFECTIVENESS OF PROJECT
7.1 RESULTS OF THE CITIZEN SURVEY
In connection with the on-going CPA of selected
FMR projects in the Municipality of Pontevedra,
the Audit Team administered survey
questionnaires on some of the residents of the
Barangays of Tabuc, San Pedro and Malag-it
where sampled FMRs were located. The survey
aimed to determine whether the primary objective
of FMR of enabling the Barangay residents to
transport farm produce, among others, to the
market efficiently, was achieved.
7.1.1 SOCIO ECONOMIC FACTOR
The survey was administered to at
least 30 respondents on each
Barangay or a total of 90
respondents with ages ranging from
20 to over 60 years on June 1, 2015, as shown on the following table:
Age
Barangay TOTAL % to Total
Malag-it
San Pedro
Tabuc
20-29 3 3 2 8 9.00
30-39 9 9 2 20 22.00
40-49 10 6 7 23 26.00
50-59 4 8 5 17 19.00
60 & above 4 4 14 22 24.00
TOTAL 30 30 30 90 100.00
Of the 90 respondents, 68 or 76 % were female and 22 or 24% were males. As such
majority were elementary and high school graduate, 76 or 84% and the remaining
percentage are college graduate. At least 18 % of the respondents are self-employed, 28
% are fisherman, 42 % are farmers, 7 % are employed either as manager or executive
Respondents from Brgy. Tabuc
filled-up the Survey questionnaire
Respondent from Brgy.
San Pedro filled-up the Survey
questionnaire
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
21
and that 80% or 72 of the respondents are earning P10,000.00 or less, which means
majority belongs to the lower echelon of the society.
7.1.2 UTILIZATION OF THE FARM TO MARKET ROAD BY THE COMMUNITY
7.1.2.1 Existing Condition before the construction of FMR
The survey revealed among others that before the construction of the FMR, farm
and other agricultural produce in the area are being transported to the market
generally thru carrying and by other means as shown in the table on the
following tabulation:
Particulars/Means
Respondents TOTAL (90)
Malag-it (30) San Pedro (30) Tabuc (30)
Number %age Number %age Number %age Numbe
r %age
Handcarry 11 37 15 50 12 40 38 42
Carabao (Paragos) 4 13 1 3 3 10 8 9
Truck/Jeep 3 10 0 0 4 13 7 8
Tricycle 12 40 9 30 6 20 27 30
Motorcycle/Bicycle 0 0 5 17 1 3 6 7
Tractor/Kuliglig 0 0 0 0 4 14 4 4
TOTAL 30 100 30 100 30 100 90 100
It can be noted from the above tabulation that majority of the respondents walk
and hand carry their farm produce and other agricultural products to be able to
sell them at the market. With the above means of transportation, it usually took
the respondents maximum of 8 hours to bring their agricultural products/farm
produce to the market. This condition, however, changed with the construction
of the FMR in said Barangays. Survey showed that at least 32% of the
respondents now use tricycle and only a meager 4% resorted to walking as
shown in the following table.
Particulars/Means
Respondents TOTAL (90)
Malag-it (30) San Pedro (30) Tabuc (30)
Number %age Number %age Number %age Number %age
Handcarry 0 0 1 3 3 10 4 4
Carabao (Paragos) 0 0 0 0 1 3 1 1
Truck/Jeep 8 27 9 30 10 33 27 30
Tricycle 16 53 13 43 0 0 29 32
Motorcycle/Bicycle 6 20 6 20 12 40 24 27
Tractor/Kuliglig 0 0 1 4 4 14 5 6
TOTAL 30 100 30 100 30 100 90 100
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
22
Likewise, at least 94% of the respondents informed that after the construction of
the FMRs, it took them only one to two (1-2) hours to travel from their
Barangays to the market to sell their farm produce/agricultural products, as can
be seen on the table below:
Particulars/
Travel Time
(No. of Hrs.)
Respondents TOTAL (90)
Malag-it (30) San Pedro (30) Tabuc (30)
Number %age Number %age Number %age Number %age
1-2 30 100 25 83 30 100 85 94
3-4 0 0 3 10 0 0 3 3
5-6 0 0 1 3 0 0 1 1
7-8 0 0 1 3 0 0 1 1
TOTAL 30 100 30 100 30 100 90 100
This manifests that, the construction of the FMR projects in the said Barangays
have favorably affected the lives of the respondents-residents economically or
otherwise. Result of survey disclosed that 99% were satisfied with the project/s.
However, their level of satisfaction vary from somewhat satisfied (4%) to very
satisfied (50%) as shown on the following:
Particulars/Level of
Satisfaction
Respondents
TOTAL (90)
Malag-it (30)
San Pedro (30) Tabuc (30)
Number %age Number %age Number %age
Numb
er %age
Very Satisfied 15 50 15 50 15 50 45 50
Satisfied 12 40 15 50 13 43 40 44
Somewhat Satisfied 2 7 0 0 2 7 4 4
Not Satisfied 1 3 0 0 0 0 1 2
TOTAL 30 100 30 100 30 100 90 100
Further, as to the respondents’ assessment of the FMR projects, generally, they
are satisfied, but again, the degree of satisfaction vary from somewhat to very
satisfied summarized as follows:
Particulars/ Level
of Satisfaction
Respondents TOTAL (90)
Malag-it (30) San Pedro (30) Tabuc (30)
Number %age Number %age Number %age Number %age
Very Satisfied 14 47 7 23 11 37 32 35
Satisfied 10 33 17 57 15 50 42 47
Somewhat Satisfied 6 20 6 20 4 13 16 18
Not Satisfied 0 0 0 0 0 0 0 0
TOTAL 30 100 30 100 30 100 90 100
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
23
In general, the FMR projects in the barangays provide access from the farms and
fish ponds/fishing areas to the market/business center of the Municipality where
the farmers/fisher folks can trade/sell their produce. It also provides access
from one point to another, open passage for agri-tourism, livelihood opportunity,
among others, which helped uplift the living condition of the barangay residents
as shown in the tabulation below:
Benefits Derived
Respondents TOTAL (90)
Malag-it (30) San Pedro (30) Tabuc (30)
Number %age Number %age Number %age Number %age
Passage in
transporting goods
to the market 12 40 9 30 18 60 39 43
Good access from
place devoid of
livelihood 8 27 4 13 10 33 22 24
Access from areas affected by calamity 6 20 9 30 2 7 17 19
Passage from Agri-
tourism 1 3 4 13 0 0 5 6
Passage for economic progress 2 7 3 10 0 0 5 6
No benefit for
barangay livelihood 1 3 1 4 0 0 2 2
TOTAL 30 100 30 100 30 100 90 100
Moreover, majority of the respondents, about 72%, responded that the
constructed FMR which apparently is now being used, is contributory to the
increase in their family income. As a result, at least 98% informed that said
project was beneficial to them and their family. As mentioned earlier, benefits
derived from the project, among others were, better access road which brought
comfort and convenience not only in transporting goods to the market, but also,
in commuting to and from their works. As such, respondents informed that they
are satisfied with the project and assessed the benefits therefrom as excellent
(36%), good (53%), slightly good (10%) and a very low 1% says the project has
no effect in their lives, as shown in the table that follow:
Particulars/
Level of
Satisfaction
Respondents TOTAL (90)
Malag-it (30) San Pedro (30) Tabuc (30)
Number %age Number %age Number %age Number %age
Excellent 12 40 8 27 12 40 32 36
Good 16 53 16 53 16 53 48 53
Slightly Good 2 7 5 17 2 7 9 10
No Effect 0 0 1 3 0 0 1 1
Bad 0 0 0 0 0 0 0 0
TOTAL 30 100 30 100 30 100 90 100
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
24
Details of the results of survey administered by the team are shown in Appendix G.
While the FMRs provide the barangay residents engaged in farming and fishery
access to transport their produce, linkage of the projects to the main road was not
achieved. Prioritization and proper sectioning was not done as one section is not
linked to the other section. As such, the residents still have to traverse undeveloped
pathways/sections in order to reach the continuation of the road sections until the
national highway is reached. Thus, efficiency in transporting products to the
market was not maximized as envisioned
under RA 8435.
As contained in pertinent portion of RA 8435,
otherwise known as the Agriculture
Modernization Act of the Philippines, it is the
declared policy of the State to enable those
who belong to the agriculture and fisheries
sectors to participate and share in the fruits of
development and growth in a manner that
utilizes the nations resources in the most
efficient and sustainable way possible by
establishing a more equitable access to assets,
income, basic and support services and infrastructure.
As such, Section 52 of the above RA provides that the Department of Public Works and
Highways (DPWH) shall coordinate with the LGUs and the resident-farmers and fisher
folk in order to identify priority locations of farm-to -market roads that take into account
the number of farmer and fisher folk and their families who shall benefit therefrom and
the amount, kind and importance of agricultural and fisheries products produced in the
area.
Further, Section 46 of the RA provides for Agriculture and Fisheries Infrastructure
Support Services. - The Department of Public Works and Highways, the Department of
Transportation and Communications, the Department of Trade and Industry and the
LGUs shall coordinate with the Department (referring to Departmentof Agriculture) to
address the infrastructure requirements in accordance with this Act, Provided, that The
Department and the LGU shall also strengthen its agricultural engineering support in
carrying out the smooth and expeditious implementation of agricultural infrastructure
projects.
National Highway
Brgy Malag-it FMR
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
25
Ocular Inspection of the FMR
project in Barangays San Pedro
disclosed that the project is divided
into two road sections. The first
section with a length of 34.31 (sta.
0+ 000 to sta 0+ 034.31), begins one
(1) kilometer from the National
Highway. It is located 20 meters
away from the Barangay Hall where
motorcycle/bicycle is the usual mode
of transportation. The 2nd section
continues 150 meters from the first
section, passing through a few small
houses, until it reached and ends at
the coastal area where the Capiz State University fishponds connect other two (2)
coastal barangays surrounded by farms and aqua farms, namely, Guba and Manapao.
The FMR has a total length of 300 sq. m., with 0.80 shoulders on both sides, roadway
of 4.00 x 0.15 meters and at least one (1) kilometer from the main road leading to the
market where small retail stores and a number of construction and service industries
centered. As discussed earlier, majority of
the residents manifested satisfaction with
the FMR project, however, they emphasized that the road be interconnected/linked and
concreted from the farm to the market access to enhance and/or improve even more the
manner/way of transporting the produce of farmers and fishermen.
Tabuc - Pontevedra
FMR
2nd Road Section
1st Road Section
Barangay San Pedro, FMR
Barangay Tabuc, FMR
National Highway
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
26
This would even more help them to improve/uplift their lives economically or otherwise.
COAns and CSO partners dialogue with respondents of Barangay Tabuc
7.0 AUDIT RESULTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
27
In terms of the implementation of the FMR projects selected for CPA, they were in
consonance with the AIP of the Municipality sourced from the 20% Development Fund
amounting to P1.750 million. The bidding process was undertaken for the procurement of
materials only in compliance with the Revised Implementing rules and Regulations of RA No.
9184 and other pertinent laws, rules and regulations. Further, the selected projects costing a
total of P1.340 million were implemented. Actual project expenditure was P1,309,801.
However, evaluation and ocular inspection of the said FMRs disclosed that actual
accomplishments were not in accordance with plans, specifications and POW as manifested in
the deficiencies noted costing P122,883.57, due to quantity and/or volume of work
accomplished for PCCP was less than the quantity/volume as implemented by LGU. The width
constructed was not in accordance with the standard set by DPWH Department Order for
FMRs and some work items were not done. During inspection, major scaling, cracks and some
portion of the right and left side of the road showed no shouldering materials applied due to
inadequate/limited width. These conditions will unfavorably affect the life span of the FMRs.
Despite the above deficiencies, survey conducted on the respondents-beneficiaries/barangay
residents disclosed that, generally, they were satisfied with the FMRs constructed as these
considerably reduced their travel time in bringing their products to the market. Likewise, they
are pleased that their transportation problem due to poor road access was solved and reportedly
have increased their income. However, they are requesting for more FMR projects to be
implemented in their barangays for the benefit of other residents, specifically those who have
to bring their fishery and agriculture produce to the market. Also, information about the
project should be made through the use of project billboards so as not to deprive the people of
information about the project and possible participation in its implementation.
8.0 AUDIT CONCLUSIONS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
28
In the preparation of ABC, POW and detailed cost estimates, we recommend that
Management:
1. Direct the concerned Municipal Official to prepare the POW, plans and detailed
estimates in accordance with DPWH standards/requirements and ensure that FMR
projects are implemented in accordance with the approved plans and specifications,
cost estimates and DPWH standards. Require the refund of the cost of project
deficiencies amounting to P122,883.57;
2. Indicate the project completion from the procurement of materials instead of project
duration of labor. Likewise, provide a minimum of 1.5 meters shoulder gravel
surfacing in the preparation of POW;
In the implementation of FMR projects, we recommend that Management:
3. Consider the importance of planning in all aspects of execution of construction
works that would ensure timely procurement of needed materials for the construction
of FMRs so that the quality of construction works, especially with regard to the
smoothness of the concrete finish be retained;
4. Provide readily available construction equipment to continuously supply the needed
requirement in carrying out simultaneous construction of FMRs; and
On the level of satisfaction with the use of FMRs, we recommend that Management consider
the construction of FMR in priority sites linking farm/fishpond areas to the main road as
envisioned in RA 8435, thus, increasing job opportunities and maximizing the efficient and
most convenient way of transporting farm/fish products to the market, thus, improving the
people’s lives in the countryside (barangay folks).
9.0 RECOMMENDATIONS FOR EXECUTIVE ACTION
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
29
The Audit Team discussed the findings/observation and recommendations with the Municipal
Mayor and concerned staff in an exit conference conducted on June 25, 2015. Their comments
are summarized as follows:
1. The Municipal Government informed the team that they have corrected the noted
deficiencies of P122,883.57 by increasing the length of 4.5 meters in the three
concrete projects as contained in the “As Built POW and Plans”;
2. Henceforth, preparation of POW, plans and specifications, and cost estimates shall
be strictly observed in accordance with DPWH standards including the provision of
1.5 meters shoulder gravel surfacing of all FMRs;
3. Timely procurement of labor and materials shall be considered in the
implementation of FMRs to ensure effective and efficient use of government
resources;
4. Proper scheduling of personnel and construction equipment to carry out
simultaneous construction operations shall be strictly observed in the future FMR
projects; and
5. With respect to the construction of FMR in priority sites linking farm/fishpond areas
to the main road, the management informed the team that it is the DILG through its
Performance Challenge Fund that identified areas to be prioritized as an incentive in
valuing the fundamentals of good governance having passed the Seal of Good
Housekeeping (SGH) assessment, and in some, garnered the Gawad Pamana ng Lahi
award.
10.0 AUDITEE’S COMMENTS
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
30
The team appreciates the actions taken/to be taken by the Municipal Government. However,
validation of corrective actions on the project shall be made to ensure that the deficiencies are
corrected by the concerned LGU staff.
Likewise, compliance with the standards set/requirements for FMRs on the preparation of
POW, detailed estimates, among others, shall be checked by the team.
While it is true that the DILG is mandated to address the infrastructure requirements and to
identify the priority location of FMR as provided in Section 52 of Republic Act 8435, the
Comprehensive Development Plan should be formulated at the LGU level, which includes
among others, the Programs, Activities and Projects (PAPs) for the achievement of Medium
Term Development Goals (e.g. school buildings, rural health units/health centers, birthing or
lying-in facilities, water and sanitation, and housing and settlements), Maintenance of Core
Road Network to Boost Tourism and Local Economic Development (e.g. core local roads and
bridges, farm-to-market roads, drainage), Disaster Risk Reduction and Management (e.g. flood
control, reforestations, storm drainage, dikes, seawall and related flood protection measures and
slope protection, evacuation centers, rainwater collection facility, early warning system/devices
and rescue equipment) and Ecological Solid Waste Management (e.g. sanitary landfill, material
recovery facilities, sewerage system).
11.0 AUDITOR’S EVALUATION/REJOINDER
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
31
We acknowledge the cooperation and assistance extended to the CPA Team by the officials and
staff of the Municipal Government of Pontevedra, the Punong Barangays and their officials, and
the respondents/residents during the conduct of survey and validation.
We also thank the World Bank for the support and funds provided to the CPA. The Bank shall
be furnished copy of the report.
The report shall be made available at the COA website at http://www.coa.gov.ph and the COA
CPA website at http://www.i-kwenta.com.
12.0 ACKNOWLEDGEMENT
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
32
Submitted in compliance with COA Regional Office No. VI Office Order No. 2015-088
dated May 18, 2015.
DAVE D. ADRICULA PRISCILLA M. MUYUELA
Team Member – CSO (JASAC) Team Member – OIC-TS
RICHARD S. BIONA JUNMAR D. NATANAUAN
Team Member – CSO (JASAC) Team Member
DENMARK L. LLANERA HANNAH D. MARCELINO
Team Member – CSO (PICPA) Team Member
MARILOU P. SUMCAD
Team Leader
RIZALDE P. DIZON
Team Supervisor
Reviewed by: Approved by:
LINA R. MACARAIG EVELYN P. REYES
Director III Director IV
`
Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
0
APPENDIX A – MAP OF THE MUNICIPALITY OF PONTEVEDRA
APPENDIX B – BARANGAY SAN PEDRO, FMR (1st and 2nd SECTIONS)
APPENDIX C – BARANGAY TABUC, FMR
APPENDIX D – BARANGAY MALAG-IT, FMR
APPENDIX E – SATELLITE VIEW OF FMR AT BARANGAYS SAN PEDRO,
TABUC AND MALAG-IT FROM THE NATIONAL HIGHWAY
APPENDIX F – SURVEY QUESTIONNAIRE
APPENDIX G – CONSOLIDATED RESULT OF SURVEY CONDUCTED BY
CSO PARTNERS AT BARANGAYS SAN PEDRO, TABUC
AND MALAG-IT
APPENDICES
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
APPENDIX A: MAP of the Municipality of Pontevedra
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
APPENDIX B: Barangay San Pedro, FMR (1st and 2nd Sections)
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
APPENDIX C: Barangay Tabuc, FMR
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
APPENDIX D: Barangay Malag-it, FMR
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
1ST station
2nd station
APPENDIX E: Satellite View of FMRs from the National Highway
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
National Highway
APPENDIX E: Satellite View of FMRs from the National Highway
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
National Highway
APPENDIX E: Satellite View of FMRs from the National Highway
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
National Highway
APPENDIX E: Satellite View of FMRs from the National Highway
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
This survey is conducted with the following objectives:
1. To check if the Farm to Market Road Project is in accordance with the pertinent provisions of
Republic Act No. 8435 and its implementing Rules and Regulations
2. To check if the purpose of the FMR Project is achieved by the LGU through proper identification of
priority locations of FMRs that takes into account the number of farmers and fisherfolk and their
families who shall benefit therefrom and the amount, kind and importance of agricultural and fisheries
products in the area.
"Farm to Market Roads" refers to roads linking the agriculture and fisheries production sites, coastal
landing points and post-harvest facilities to the market and arterial roads and highways.
This activity is in line with the Commission on Audit's (COA) Citizen Participatory Audit (CPA)
project implemented with the Philippine Institute of Certifie Public Accountant (PICA) and Jaro
Archdiocesan Social Action Center (JASAC) , and support from the Land Bank.
TO BE ACCOMPLISHED BY THE ENUMERATOR:
Date of Interview: Start Time: End Time:
PART I - GENERAL INFORMATION
1. Pangalan(Name):
3. Kasarian(Gender): Check (/) one:
[ ] Male (lalaki)
[ ] Female (babae)
2. Tirahan(Address):
4. ___________________(refer to COA Cell list)
5. Distrito(District):
PART II - SOCIO-ECONOMIC FACTORS
6. Ano ang saklaw ng edad mo? (What is your age
range?)
Check (/) one:
[ ] 13-19
[ ] 20-29
[ ] 40-49
[ ] 30-39
[ ] 50-59
[ ] 60 and above
7. Anong antas ng edukasyon ang natapos mo? (What
is your highest educational attainment?
Check (/) one:
[ ] Elmentary
[ ] Highschool
[ ] College
[ ] Masters
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
8. Anong trabaho mo? (What is your occupation?) Check (/) one:
[ ] Self Employe
[ ] Professional
[ ] Manager (executive)
[ ] Administrative / clerical
[ ] Magsasaka
[ ]Housewife/Husband (maybahay)
[ ] Househelp (kasambahay)
[ ] Student
[ ] Retired (reterado)
[ ] Mangingisda
9. Ilang miyembro ng inyong sambahayan ang
may pinagkakakitaan? (How many member/s
of your household is/are earnings?)
Check (/) one:
[ ] 0
[ ] 1
[ ] 2
[ ] 3
[ ] 4
[ ] 5
[ ] 6 or more
10. Magkano ang total na kita ng sambahayan niyo
buwan-buwan? (What is your total monthly
household income?)
Check (/) one:
[ ] P10,000 or less
[ ] P10,0001 to P20,000
[ ] P20,001-P30,000
[ ] P30,001-P40,000
[ ] P40,001-P50,000
[ ] 50,001 and up
[ ] Don't Know
PART III: COMMUNITY AWARENESS OF THE FARM TO MARKET ROAD PROJECTS
11. Narinig mo na ba ang batas na RA No. 8435?
(Have you heard about RA 8435?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
12. Alam mo ba ang batas na RA No. 8435 na
naglalayon na magkaroon ng Farm to Market
Project? (Are you aware of RA No. 8435
providing for the construction of farm to market
project?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
13. Alam mo ba ang Pamahalaan ay nagpagawa ng
proyekto na farm to market road sa
_______________(lugar)? (Are you aware that
the Government is implementing a construction
project of farm to market road in
___________________? (location).
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
[ ] Don't Know (Hindi alam)
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
14. Alam mo ba kung ilan ang resindente na nakatira
o malapit sa barangay kung saan ipinagawa ang
FMR na proyekto? (Are you aware of the number
of residing near or living in the barangay where
FMR project was constructed?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
[ ] Don't Know (Hindi alam)
If Yes, how many? kung Oo ilan?
[ ] 50 to 100
[ ] 101 to 200
[ ] 201 to 300
[ ] 301-400
[ ] 401 to 500
[ ] Over 500
15. Alam mo ba kung saang lugar itinayo ang FMR
na ipinagawa ng Pamahalaan? (Are you aware of
the location where the FMR was constructed by
the Government?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
If Yes, Where? kung Oo, Saan?
16. Alam mo ba kung kailan ginawa ang FMR na
ipinagawa ng Pamahalaan? (Are you aware of the
date when the FMR was constructed by the
government? Kailan nasiimulan ang proyekto?
(When was the project started?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
If yes, when? Kung Oo, Kailan?
17. Natapos na ba ang pinapagawang FMR na
proyekto? (Had the FMR project been
completed?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
[ ] Don't Know (Hindi alam)
18. Kailan natapos ang pinapagawang FMR na
proyekto? (When was the estimated date of
completion? Kung o, kailan? (If when)?
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
Petsa (Date):
19. Ito bang FMR na proyektong ito ay ginagamit na?
(Is the FMR Project now being used?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
[ ] Don't Know (Hindi alam)
20. Sa paanong paraan mo nalaman ang ipinagawang
FMR na proyekto? (In what way were you able to
learn about FMR Project?)
Check (/) all answers that apply,.
[ ] Work nearby (malapit lang ang trabaho)
[ ] This is my usual path (Ito ay aking
dinadaanan madalas)
[ ] Good access to transit of goods (Ito ay
nagdudulot ngmagandang daan para sa
byahe ng aming kalakal)
[ ] Provincial assembly (Pagpupulong sa
Probinsya)
[ ] Municipal assembly (Pagpupulong sa
Munisipyo)
[ ] Barangay assembly (Pagpupulong sa
Barangay)
[ ] Distribution of flyers/leaflets by province
(Pamamahagi ng flyers/leaflets ng probinsya
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
21. Alam mo ba kung ang Pamahalaang local
ay may tamang anunsyo tungkol sa mga
ipinapagawang proyektong FMR sa iyong
komunidad? (Do you know if the LGU
provides adequate posting and publicity on
the construction of FMR Project?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
22. Alam mo ba kung anong ahensya ng
gobyerno ang nagpapagawa/nagpapatupad
ng FMR? (Do you know what agency of the
government implements the construction
and rehabilitation of FMR?) Kung Oo, Sino
ang gumawa ng/nagpapatupad ng proyekto?
(If yes, what agency implements the
project?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
Check one:
[ ] Provincial Govenrment (Pamahalaang Probinsya)
[ ] Municipal Government (Pamahalaang
Munisipyo)
[ ] Barangay
[ ] DPWH
[ ] Dept. of Agriculture
[ ] Others: (Mag iba pa)
23. Paano ninyo nalaman kung sino ang
nagpapagawa ng proyekto? (How did yo
you know the implementing agaency of the
project?)
Check (/) applicable answer:
[ ] Posting/Billboard
[ ] Balita ng kaibigan o kabrgy.
[ ] Others (Mag iba pa)
24. Alam mo ba kung sino ang kontratista ng
proyekto? (Do you know the contractor of
the project?) Kung OO, Sino ang
kontratista? (If Yes, Who is the contractor?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
Name of Contractor/Company: (Pangalan ng
Kontratista/Kompanya)
25. Paano mo nalaman kung sino ang
kontratista? (How did you know the
contarct of the project?)
Check (/) all answers that apply:
[ ] Posting/Billboard
[ ] Neighbor/resident of the brgy. (Kapitbahay/
barangay)
[ ] Others: (Mga iba)
26. May nakalagay bang panagalan ng opisyal
ng pamahalaan sa anunsyo? (Was there a
name of government official in the
billboard/posting?)
Kung Oo, Kaninong pangalan ng opisyal
ang nakalagay sa anunsyo? (If Ye, whose
name was indicated in the billboard?)
Check (/) one:
[ ] Yes (Oo)
[ ] None (Wala)
[ ] Don't Know (Hindi alam)
Name (Pangalan)
27. May litrato ba ng opisyal/mga opisyal ng
pamahalaan sa anunsyo? ( Was there a
picture of government official/s in the
billboard?)
Kung Oo, Knainong litrato ang nakalagay
sa anunsyo? (If Yes, whose picture
was printed in the billboard?)
Check (/) one:
[ ] Yes (Oo)
[ ] None (Wala)
[ ] Don't Know (Hindi alam)
Name (Pangalan)
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
28. Ano ang mga kagamitan na ginagamit
sa proyekto? (What are the equipment
used in the project?)
Check (/) applicable answer: (Piliin ang naayon na Sagot)
[ ] Dump truck
[ ] Water truck (Truck na pandilig)
[ ] Road Roller (Pison)
[ ] Cement/concrete mixer (Panghalo ng semento)
[ ] Transit Mixer
[ ] Vibrator (Pansiksik ng semento)
[ ] Others (Mga iba)
29. Ano ang mga ginagawa sa pagsasagawa
ng proyekto? (What are the items of
works done in the project? )
Check (/) applicable answer: Piliin ang naayon na sagot)
[ ] Piles of soil (Tambak ng lupa)
[ ] Piles of stone (Tambak ng bato)
[ ] Cement/concrete (Semento/konkreto)
30. May nagtratrapik ba sa ginagawang
proyekto? (Was there a flagman to
control the traffic in the
construction/project area?)
Check (/) one:
[ ] Yes (Oo)
[ ] None (Wala)
[ ] Don't Know (Hindi alam)
PART IV – LOCAL GOVERNMENT (BARANGAY) AWARENESS OF THE FARM TO MARKET
ROAD PROJECT
31. Alam mo ba kung may naganap na
general assembly sa lokal niyong
pamahalaan para sa annual
development projects? (Are you aware
of any general assembly held in your
LGU for annual development projects?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
[ ] Don't Know (Hindi alam)
32. Sa anong paraan mo nalaman na ang
FMR Project ay isa sa mga proyekto na
nakapaloob sa Annual Investment Plan
(AIP) ng lokal na pamahalaan? (How
did you know that FMR Projects is one
of the projects included in the AIP in
your locality?)
Note: Dito nalalaman din natin kung
may pagsasaliksik na ginawa ang LGU
para malaman kung saan ilalagay ang
FMR Project. (With this, we will be
able to know if the LGU conducted a
study where the FMR Project willbe
constructed.)
Check (/) all answers that apply:
[ ] City/Municipal assembly (pagpupulong sa
city/Municipal hall)
[ ] Baranagy assembly (Pagpupulong ng Barangay)
[ ] Distribution of fliers fliers/leaflets/Mun. Hall
(pamamahagi ng fliers/leaflets ang city/Municipal
Hall)
[ ] Distribution of fliers fliers/leaflets by the barangay
(pamamahagi ng fliers/leaflets ng barangay hall)
[ ] Home visit by city/mun. official (pagbisita ng mga
opisyal mula sa city/mun. hall)
[ ] Home visit by barangay officials (pagbisita ng mga
opisyal mula sa barangay)
[ ] Poster/tarpauline
[ ] Radio/television (radio/telebisyon)
[ ] Others (sa iba), specify: ___________
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
33. Alam mo ba o may kilala ka ba na opisyal ng
pamahalaan na nakatira o may pag-aari sa lugar na to?
(Are you aware of any government officials living or
has property within the areas?
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
34. Napapaligiran po ba ng mga taniman at sakahan ang
inyong lugar? (Is your place surrounded with
agricultural plants/farms?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
35. Marami po bang dumadaan na sasakyan dito tulad ng:
(Is this area accessible to transportation like:)
a. Truck
b. Jeep
c. Karitela
d. Bus
e. Tricycle
f. Motor/Bisikleta
g. Paragos
h. Traktora
i. Kuliglig
Yes No
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
36. Alam nyo ba na may pinagawang daan (FMR) sa inyong
lugar?(Are you aware that an FMR has been constructed
in your area/locality?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
37. Alam mo ba kung may opisina sa lokal na pamahalaan
na nagpapatupad ng tamang pamamahala ng contruction
ng FMR Project? (Are you aware if there's any in your
locality (LGU) Offices which implementing the
construction of FMR?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
[ ] Don't Know (Hindi alam)
38. Sa inyong pagkakaalam sino ang nagpapatupad ng
tamang pamamahala ng construction ng FMR
Project?(Who is implementing and managing the
construction of the FMR Project?)
Check (/) one:
[ ] City/Municipal Government
[ ] Barangay Officials (Opisyal ng
barangay)
[ ] Don't Know (Hindi alam)
[ ] Others, (Iba), pls.
specify_______________
PART V - UTILIZATION OF THE FARM TO MARKET ROAD BY THE COMMUNITY
39. Sa iyong obserbasyon, anu-ano ang mga kalakal na
dumadaan sa kalsada na ito?(Based on your observation,
what are the various agricultural products being
transported using the FMR?)
Check (/) all answers that apply:
[ ] Vegetable (Gulay)
[ ] Meat (Karne)
[ ] Fish (Isda)
[ ] Rice (Bigas)
[ ] Animals (Hayop)
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
40. Noon pong wala pang kalsada dito, paano niyo po
dinadala ang mga kalakal sa palengke o tindahan? (Prior
to the construction of the FMR, how did you transport
your agricultural produce to the market/store?)
Check (/) all answers that apply:
[ ] Handcarry (Lakad/Buhat)
[ ] Carabao (Kalabaw)
[ ] Horse (Kabayo)
[ ] Truck
[ ] Jeep
[ ] Karitela
[ ] Bus
[ ] Tricycle
[ ] Motor/Bisikleta
[ ] Paragos
[ ] Traktora
[ ] Kuliglig
41. Paano naman po ngayon na may kalsada na? (How about
after construction of the FMR?)
Check (/) all answers that apply:
[ ] Handcarry
[ ] Carabao
[ ] Horse
[ ] Truck
[ ] Jeep
[ ] Karitela
[ ] Bus
[ ] Tricycle
[ ] Motor/Bisikleta
[ ] Paragos
[ ] Traktora
[ ] Kuliglig
42. Noon pong wala pang kalsada dito, ilang araw/oras po
inaabot ang pagdadala ng mga kalakal sa palengke o
tindahan? (Prior to the construction of the FMR, how
many days/hours did it take for you to bring your
agricultural produce to the market/store?)
Check (/) all answers that apply:
[ ] 1-2 hrs
[ ] 3-4 hrs
[ ] 5-6 hrs
[ ] 7-8 hrs
43. Paano naman po ngayon na may kalsada na? (How about
after construction of the FMR?)
Check (/) all answers that apply:
[ ] Less than 1 hour
[ ] 1-2 hrs
[ ] 3-4 hrs
[ ] 5-6 hrs
[ ] 7-8 hrs
44. Nagagamit mo ba ang FMR sa pagbabyahe ng mga ani at
produkto mula sa sakahan/bagsakan papunta sa palengke
o pamilihang bayan?(Are you using the FMR in
transporting farm produces and fish ports to the market?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
45. Sa iyong palagay, nakatulong ba ang kalsada sa pagtaas
ng inyong kita?(In your opinion, did the FMR improve
your income?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
46. Kung Oo, Gaano ka nasisiyahan? (If yes, how satisfied
are you?)
Check (/) applicable answer:
[ ] Very Satisfied (tuwang-tuwa)
[ ] Satisfied (natutuwa)
[ ] Somewhat Satisfied (medyo natutuwa)
[ ] Not Satisfied at all (hindi natutuwa)
47. Kung Hindi, Bakit? (If No, why?)
PART VI - LEVEL OF COMMUNITY SATISFACTION WITH THE USE OF FARM TO MARKET
ROAD
48. Ikaw ba ay nasisiyahan sa proyekto? (Are you satisfied
with the project?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
49. Kung Oo, Gaano ka nasisiyahan?(If yes, how satisfied
are you?)
Check (/) applicable answer:
[ ] Very Satisfied (tuwang-tuwa)
[ ] Satisfied (natutuwa)
[ ] Somewhat Satisfied (medyo natutuwa)
[ ] Not Satisfied at all (hindi natutuwa)
50. Kung Hindi, Bakit? (If No, why?)
51. Kung bibigyan ng marka ang proyekto anong marka
ang ibibigay mo? (If you will asked to assess the
project, how will you rate it?
Check (/) applicable answer:
[ ] Very Satisfied (tuwang-tuwa)
[ ] Satisfied (natutuwa)
[ ] Somewhat Satisfied (medyo natutuwa)
[ ] Not Satisfied at all (hindi natutuwa)
52. Ano ang maimumungkahi mo para maipabuti pa ang
proyekto? (What are your recommendations to improve
the project?)
Specify here: (Isulat dito)
53. Alam mo ba kung nakatulong s ainyong
pangkabuhayan ang itinayong FMR na proyekto sa
inyong komunidad? (Do you know if potential
livelihood benefits were derived by your community
from the completed FMR Project?)
Check applicable answer:
[ ] resulted to good access road/passage in
the transit of goods to market. (Nagdulot
ng ugnayan mula sa mga
bukirin/palaisdaan papunta sa mga
pamilihan o merkado)
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
[ ] resulted to good access road/passage from the
areas void of livelihood and
experiencing poverty capaign to eliminate
poverty. (Nagdulot ng daanan mula sa mga lugar
na salat sa kabuhayan/karalitaan ayon sa
kampanya ng pamahalaan sugpuin ang kahirapan)
[ ] resulted to good access road/passage from the
areas affected by calamity. (Nagdulot ng daanan
mula mga lugar na napinsala ng kalamidad)
[ ] resulted to good access road/passage for
agricultural tourism. (Nagdulot ng daanan para sa
turismong pangsakahan)
[ ] resulted to good access road/passage for
economic progress. (Nagdulot ng daanan para sa
ikauunlad ng ekonomiya)
[ ] No potential benefit derived for the barangay
livelihood. (Walang idinulot na benepisyong
potensyal sa pangkabuhayanng barangay)
54. Nakatulong ba sa inyong kabuhayan/kita ang
ginawang FMR? (Did your income increase
with the help of completion of FMR?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
[ ] Don't Know (Hindi alam)
Comment/Remarks (Puna): _____________
55. Nagkaroon ba ng mabuting epekto sa iyong
sarili at sa iyong pamilya ang pagkagawa ng
FMR proyekto sa probinsya? (Had the FMR
Project constructed been beneficial to
yourself and to your family?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
[ ] Don't Know
Comment/Remarks:
56. Masasabi mo ba kung ano ang mga
pansariling epekto o benepisyo na nakuha mo
sa ipinagawang FMR Proyekto? (Can you
cite the effects of benefits that you have
personally derived from the FMR Project?)
Check (/) one:
[ ] resulted to better access road in going to work
everyday (Nagbigay ng mabilis na daanan sa
aming gawain/trabaho araw-araw)
[ ] accelerated&brought comfort/convenience in our
daily livelihood (Nagpabilis ng takbo at nagdulot
ng kaginhawaan sa aming pang araw-araw na
kabuhayan)
[ ] no benefit derived in our daily livelihood.
(Walang idinulot na benepisyo sa aming araw-araw na
pangkabuhayan)
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
57. Ikaw ba ay natutuwa sa ipinagawang FMR
Proyekto? (Are you satisfied with the FMR
Project?) If yes, how satisfied are you?) Kung
OO, gaano ka natuwa? Kung HINDI, bakit? (If
no, why?)
Check (/) applicable answer:
[ ] Very Satisfied (tuwang tuwa)
[ ] Satisfied (Natuwa)
[ ] Somewhat Satisfied (Medyo natuwa)
[ ] Not Satisfied at all(hindi natuwa)
Check applicable answer (piliin ang naaayon na
sagot)
[ ] Not beneficial (walang idinulot na maganda)
[ ] Wrong location (mali ang lugar ng FMR na
proyekto)
[ ] Poor quality and workmanship (mali ang
pagkakagawa)
[ ] others (mga iba)
58. Kung bibigyan mo ng marka ang kabutihang
idinulot ng FMR Proyekto, anong marka ang
ibibgay mo? (If you will assess the benefits of the
FMR Project to your community, how will you
rate it?)
Check (/) applicable answer (Piliin ang sagot)
[ ] Excellent (Napakabuti)
[ ] Good (Mabuti)
[ ] Slightly good (Medyo mabuti)
[ ] No effect (walang ibinuti)
[ ] Bad (masama)
Comments/Remarks (Puna)____________
59. Ano ang maimumungkahi mo para mapabuti ang
pagpapagawa ng mga sumusunod na FMR
Proyekto ng probinsya sa mga darating na
panahon? (What are your recommendation/s to
improve construction of future FMR Projects by
the Province?)
Recommendation/s (Mungkahi/Mga
mungkahi)________________________
60. Alam mo ba na pwede mong ipaalam ang iyong
mga reklamo tungkol sa FMR proyekto sa
pamamagitan ng pagkuha ng litrato at
pagpapadala nito sa www.Ikwenta.com?(Do you
know that you can report complaints on poor and
inferior FMR Projects by submitting photographs
to www.Ikwenta.com?)
Check (/) one:
[ ] Yes (Oo)
[ ] No (Hindi)
IMPORTANT: To be filled up by the enumerator
Name of the Interviewee:
Signature of Interviewer:
Address:
Mobile Number:
Email (if applicable):
Signature of the Enumerator:
Interview Notes (If applicable):
APPENDIX F: SURVEY QUESTIONNAIRE
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
LOCATION : Concreting of
Brgy. Roads, Brgy.
Malag-it
Concreting of
Brgy. Roads,
Brgy. San Pedro
Concreting of
Brgy. Roads,
Brgy. Tabuc
GRAND TOTAL
Responses Total
Respon-
dents
% to
Total
Total Respon
-dents
% to
Total
Total Respon-
dents
% to
Total
Question No. 30 33.33 30 33.33 30 33.33 90 100.00
% Total % Total % Total Total Respondents
PART I GENERAL INFORMATION
3
Gender
Male 20 6 27 8 27 8 24.44 22
Female 80 24 73 22 73 22 75.56 68
100 30 100 30 100 30 100.00 90
PART II SOCIO ECONOMIC FACTORS
6
Age
20-29 10 3 10 3 7 2 8.89 8
30-39 30 9 30 9 7 2 22.22 20
40-49 33 10 20 6 23 7 25.56 23 50-59 13 4 27 8 17 5 18.89 17
60< 13 4 13 4 47 14 24.44 22 No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
Education
Elementary 43 13 37 11 53 16 44.44 40
7
High School 53 16 33 10 33 10 40.00 36
College 3 1 30 9 13 4 15.56 14
Masters 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
8
What is your occupation?
Self-Employed 10 3 10 3 33 10 17.78 16
Professional (Doctor, Engr) 0 0 0 0 0 0 0.00 0 Manager, Executive, etc. 10 3 0 0 10 3 6.67 6
Admin, Clerical,
Secretaray
0
0
3
1
0
0 1.11 1 Farmer 0 0 0 0 0 0 0.00 0
Housewife/Husband
Maybahay
57
17
37
11
33
10 42.22 38 Househelp/Kasambahay 3 1 0 0 0 0 1.11 1
Student 0 0 0 0 0 0 0.00 0
Retired 0 0 0 0 10 3 3.33 3 Fisherman 20 6 50 15 13 4 27.78 25
100 30 100 30 100 30 100.00 90
9
How many member of your household is earning?
0 37 11 3 1 10 3 16.67 15
1 30 9 77 23 57 17 54.44 49
2 7 2 20 6 33 10 20.00 18
3 3 1 0 0 0 0 1.11 1
4 7 2 0 0 0 0 2.22 2
5 3 1 0 0 0 0 1.11 1
6 or more 13 4 0 0 0 0 4.44 4
100
30
100
30
100 30 100.00
90
APPENDIX G: CONSOLIDATED RESULT OF SURVEY
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
LOCATION : Concreting of
Brgy. Roads, Brgy.
Malag-it
Concreting of
Brgy. Roads,
Brgy. San Pedro
Concreting of
Brgy. Roads,
Brgy. Tabuc
GRAND TOTAL
Responses
Total
Respon-
dents
% to Total
Total
Respon
-dents
% to
Total
Total
Respon-
dents
% to Total
Question No.
30 33.33 30 33.33 30 33.33 90 100.00
% Total % Total % Total Total Respondents
10
How much is your total monthly income?
10,000 or less 80 24 90 27 70 21 80.00 72
10,001-20,000 0 0 10 3 0 0 3.33 3 10,001-20,000 0 0 10 3 0 0 3.33 3
20,001-30,000 0 0 0 0 0 0 0.00 0
30,001-40,000 0 0 0 0 0 0 0.00 0 DONT KNOW 20 6 0 0 30 9 16.67 15
100 30 100 30 100 30 100.00 90
PART 111
COMMUNITY AWARENESS OF THE FARM TO MARKET ROAD PROJECT
11
Have you heard about RA 8435?
YES 10 3 7 2 7 2 7.78 7
NO 90 27 93 28 93 28 92.22 83
100 30 100 30 100 30 100.00 90
12
Are you aware of RA No. 8435 providing for the construction of FMRs?
YES 37 11 37 11 30 9 34.44 31
NO 63 19 63 19 70 21 65.56 59 No Answer 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
13
Are you aware that the government is implementing a construction project of FMRs? YES 80 24 77 23 77 23 77.78 70
NO 17 5 20 6 7 2 14.44 13
DN 3 1 3 1 17 5 7.78 7
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
14
Number of residentsresiding near or living in the barangay where the FMR project was constructed.
50-100 27 8 40 12 3 1 23.33 21
101-200 3 1 17 5 3 1 7.78 7
201-300 30 9 0 0 3 1 11.11 10
301-400 0 0 0 0 3 1 1.11 1
401-500 3 1 0 0 7 2 3.33 3
Over 500 27 8 3 1 3 1 11.11 10
DN 7 2 40 12 20 6 22.22 20
No Answer 3 1 0 0 57 17 20.00 18
15
Are you aware of the location where the FMR was constructed?
YES 87 26 83 25 63 19 77.78 70
NO 13 4 17 5 37 11 22.22 20 IF YES, WHERE?
100 30 100 30 100 30 100.00 90
16
Are you aware of the date when the FMR was constructed? YES 43 13 37 11 23 7 34.44 31 NO 57 17 63 19 77 23 65.56 59
If yes, when?
100 30 100 30 100 30 100.00 90
17
Had the FMR Project been completed?
YES 43 13 67 20 63 19 57.78 52
NO 50 15 20 6 30 9 33.33 30 DN 7 2 13 4 7 2 8.89 8
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
APPENDIX G: CONSOLIDATED RESULT OF SURVEY
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
LOCATION : Concreting of
Brgy. Roads, Brgy.
Malag-it
Concreting of
Brgy. Roads,
Brgy. San Pedro
Concreting of
Brgy. Roads,
Brgy. Tabuc
GRAND TOTAL Responses
Total Respon-
dents
% to
Total
Total Respon
-dents
% to
Total
Total Respon-
dents
% to
Total
Question No.
30 33.33 30 33.33 30 33.33 90 100.00
% Total % Total % Total Total Respondents
18
Do you know when was the estimated date of completion?
YES 3 1 17 5 7 2 8.89 8
NO 97 29 83 25 93 28 91.11 82
No Answer 0 0 0 0 0 0 0.00 0 If yes, when?
100 30 100 30 100 30 100.00 90
19
Is theFMR project now being used?
YES 93 28 17 5 100 30 70.00 63 NO 7 2 83 25 0 0 30.00 27
DN 0 0 0 0 0 0 0.00 0
No Answer 0 0 0 0 0 0 0.00 0 100 30 100 30 100 30 100.00 90
20
In what way were you able to learn about the FMR project?
I work nearby 23 7 23 7 7 2 17.78 16
Usual Path 23 7 60 18 67 20 50.00 45 Good Access to Transit 23 7 7 2 0 0 10.00 9
Provincial Assembly 3 1 0 0 0 0 1.11 1 MunicipalAssembly 3 1 3 1 13 4 6.67 6
Barangay Assembly 23 7 7 2 13 4 14.44 13
100 30 100 30 100 30 100.00 90
21
Do you know if the LGU provides adequate posting and publicity on the construction of FMR project? YES 47 14 60 18 57 17 54.44 49
NO 53 16 40 12 43 13 45.56 41
100 30 100 30 100 30 100.00 90
22
Do you know what agency of the government implements the construction and rehab of FMR?
YES 30 9 23 7 23 7 25.56 23 NO 70 21 77 23 77 23 74.44 67
100 30 100 30 100 30 100.00 90
If yes, what agency? Municipal Government 27 8 7 2 5 2 52.17 12
Provincial Government 0 0 7 2 5 2 17.39 4
Barangay 3 1 3 1 3 1 13.04 3
DPWH 0 0 7 2 5 2 3.45 4
100 30 100 30 100 30 100.00 90
23
How did you know the implementing agency of the project? Posting / Billboard 43 13 10 3 33 10 28.89 26
Kabarangay 20 6 63 19 20 6 34.44 31
Others 37 11 27 8 47 14 36.67 33
100 30 100 30 100 30 100.00 90
24
Do you know the contractor of the project? YES 0 0 93 28 0 0 31.11 28
NO 100 30 7 2 100 30 68.89 62
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
25
How did you know the contractor of the project? Neighbor 17 5 40 12 37 11 31.11 28
Billboard 0 0 13 4 10 3 7.78 7
Others 83 25 47 14 53 16 61.11 55
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
26
Was there a name of government official in the bilboard/posting? YES 37 11 17 5 23 7 25.56 23
NO 57 17 47 14 20 6 41.11 37
DN 7 2 37 11 57 17 33.33 30
100 30 100 30 100 30 100.00 90
APPENDIX G: CONSOLIDATED RESULT OF SURVEY
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
LOCATION : Concreting of
Brgy. Roads, Brgy.
Malag-it
Concreting of
Brgy. Roads,
Brgy. San Pedro
Concreting of
Brgy. Roads,
Brgy. Tabuc
GRAND TOTAL
Responses
Total
Respon-dents
% to
Total
Total
Respon-dents
Total
Respon-dents
% to
Total
Question No.
30 33.33 30 33.33 30 33.33 90 100.00
% Total % Total % Total Total Respondents
27
Was there a pictureof government official in the billboard?
YES 53 16 17 5 20 6 30.00 27 NO 47 14 43 13 33 10 41.11 37
DN 0 0 40 12 47 14 28.89 26 Who's on the picture? 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
28
What are the equipments used in the project?
Dump Truck 17 5 27 8 20 6 21.11 19 Water Truck 13 4 7 2 17 5 12.22 11
Road Roller 20 6 7 2 10 3 12.22 11
Cement/Concrete Mixer 20 6 17 5 20 6 18.89 17 Transit Mixer 7 2 7 2 7 2 6.67 6
Vibrator 3 1 3 1 7 2 4.44 4
Others 20 6 33 10 20 6 24.44 22 100 30 100 30 100 30 100.00 90
29
What are the items of works done in the project?
Piles of soil 40 12 27 8 40 12 35.56 32
Piles of stone 23 7 27 8 20 6 23.33 21 Cement/concrete 37 11 47 14 40 12 41.11 37
100 30 100 30 100 30 100.00 90
30
Was there a flagman to control the traffic in the construction/project area?
YES 47 14 60 18 67 20 57.78 52 NO 37 11 40 12 27 8 34.44 31
DN 17 5 0 0 7 2 7.78 7
100 30 100 30 100 30 100.00 90
PART IV
LOCAL GOVERNMENT AWARENESS OF THE FARM TO MARKET ROAD PROJECTS
31
Are you aware of any general assembly held in your LGU for annual dev't. Projects?
YES 23 7 73 22 57 17 51.11 46
NO 67 20 13 4 10 3 30.00 27 DN 10 3 13 4 33 10 18.89 17
100 30 100 30 100 30 100.00 90
32
How did you know that FMR projet is one of the projcts included in the AIP in your locality (LGU)?
City/Municipal 0 0 7 2 50 15 18.89 17 Barangay 30 9 47 14 0 0 25.56 23
Distribution of fliers by the
city/municipality 0 0 0 0 0 0
0.00 0 Distribution of fliers by the
barangay 0 0 0 0 0 0
0.00 0
Home visit by city/mun 0 0 3 1 3 1 2.22 2 Home visit bt brgy 3 1 23 7 7 2 11.11 10
Poster/tarpaulin 20 6 0 0 3 1 7.78 7
radio/television 0 0 0 0 37 11 12.22 11 Others 47 14 20 6 0 0 22.22 20
100 30 100 30 100 30 100.00 90
33
Are you aware of any government officials living or has property within the area?
YES 10 3 20 6 50 15 26.67 24 NO 90 27 80 24 50 15 73.33 66
100 30 100 30 100 30 100.00 90
APPENDIX G: CONSOLIDATED RESULT OF SURVEY
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
LOCATION : Concreting of
Brgy. Roads, Brgy.
Malag-it
Concreting of
Brgy. Roads,
Brgy. San Pedro
Concreting of
Brgy. Roads,
Brgy. Tabuc
GRAND TOTAL Responses
Total
Respon-dents
% to
Total
Total
Respon-dents
% to
Total
Total
Respon-dents
% to
Total
Question No.
30 33.33 30 33.33 30 33.33 90 100.00
% Total % Total % Total Total Respondents
34
Is your place surrounded with agricultural plants/farms/aquafarms? YES 83 25 100 30 83 25 88.89 80
NO 17 5 0 0 17 5 11.11 10
100 30 100 30 100 30 100.00 90
35
Is this area accessible to transportation like: Truck 7 2 7 2 13 4 8.89 8
Jeep 7 2 7 2 17 5 10.00 9
Karitela 7 2 27 8 3 1 12.22 11
Bus 3 1 10 3 3 1 5.56 5
Tricycle 27 8 13 4 13 4 17.78 16
Motor/bisikleta 23 7 10 3 13 4 15.56 14
Paragos 10 3 10 3 7 2 8.89 8
Traktora 7 2 7 2 0 0 4.44 4
Kuliglig 10 3 10 3 30 9 16.67 15
100 30 100 30 100 30 100.00 90
36
Are you aware that an FMR has been constructed in your locality?
YES 83 25 93 28 87 26 87.78 79
NO 17 5 7 2 13 4 12.22 11
100 30 100 30 100 30 100.00 90
37
Are you aware if there's any in your locality (PGU) offices which is implementing the construction of an FMR?
YES 47 14 63 19 57 17 55.56 50
NO 23 7 27 8 20 6 23.33 21
DN 30 9 10 3 23 7 21.11 19
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
38
As far as you're concerned, wh is implementing and managing the construction of the FMR project?
Brgy. Officials 87 26 0 0 0 0 28.89 26
Barangay Officials 3 1 63 19 47 14 37.78 34
Don't know 10 3 37 11 50 15 32.22 29
Others 0 0 3 1 1.11 1
100 30 100 30 100 30 100.00 90
PART V
UTILIZATION OF THE FARM TO MARKET ROAD BY THE COMMUNITY
39
Based on your observation, what are the various agricultural products being transported using this FMR?
Vegetable 27 8 30 9 33 10 30.00 27
Meat 7 2 13 4 10 3 10.00 9 Fish 17 5 13 4 17 5 15.56 14
Rice 30 9 30 9 23 7 27.78 25
Animals 20 6 13 4 17 5 16.67 15 100 30 100 30 100 30 100.00 90
40
Prior to the construction of the FMR, how did you transport your agricultural produce to the market/store? Handcarry 37 11 50 15 40 12 42.22 38
Carabao 13 4 3 1 10 3 8.89 8
Horse 0 0 0 0 0 0 0.00 0
Truck 7 2 0 0 10 3 5.56 5
Jeep 3 1 0 0 3 1 2.22 2
Karitela 0 0 0 0 0 0 0.00 0
Bus 0 0 0 0 0 0 0.00 0
Tricycle 40 12 30 9 20 6 30.00 27
Motor/bisikleta 0 0 17 5 3 1 6.67 6
Paragos 0 0 0 0 0 0 0.00 0
Traktora 0 0 0 0 3 1 1.11 1
Kuliglig 0 0 0 0 10 3 3.33 3
100 30 100 30 100 30 100.00 90
APPENDIX G: CONSOLIDATED RESULT OF SURVEY
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
LOCATION : Concreting of
Brgy. Roads, Brgy.
Malag-it
Concreting of
Brgy. Roads,
Brgy. San Pedro
Concreting of
Brgy. Roads,
Brgy. Tabuc
GRAND TOTAL
Responses Total
Respon-
dents
% to
Total
Total Respon
-dents
% to
Total
Total Respon-
dents
% to
Total
Question No.
30 33.33 30 33.33 30 33.33 90 100.00
% Total % Total % Total Total Respondents
41
How about after the construction of the FMR?
Handcarry 0 0 3 1 10 3 4.44 4
Carabao 0 0 0 0 0 0 0.00 0
Horse 0 0 0 0 0 0 0.00 0 Truck 3 1 13 4 20 6 12.22 11
Jeep 20 6 13 4 13 4 15.56 14
Karitela 0 0 0 0 0 0 0.00 0 Bus 3 1 3 1 0 0 2.22 2
Tricycle 53 16 43 13 40 12 45.56 41
Motor/bisikleta 20 6 20 6 13 4 17.78 16
Paragos 0 0 0 0 3 1 1.11 1
Traktora 0 0 3 1 0 0 1.11 1
Kuliglig 0 0 0 0 0 0 0.00 0 100 30 100 30 100 30 100.00 90
42
Prior to the construction of the FMR, how many days/hours did it take for you to bring your produce to the
market/store? 1-2 HOURS 100 30 83 25 100 30 94.44 85
3-4 HOURS 0 0 10 3 0 0 3.33 3
5-6 HOURS 0 0 3 1 0 0 1.11 1
7-8 HOURS 0 0 3 1 0 0 1.11 1
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
43
How about after the FMR has been constructed?
15-30 MINUTES 0 0 0 0 0 0 0.00 0
1-2 HOURS 100 30 93 28 100 30 97.78 88 3-4 HOURS 0 0 7 2 0 0 2.22 2
5-6 HOURS 0 0 0 0 0 0 0.00 0
7-8 HOURS 0 0 0 0 0 0 0.00 0
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
44
Are you using the FMR in trasporting farm produce and fish to market?
YES 73 22 100 30 87 26 86.67 78 NO 27 8 0 0 13 4 13.33 12
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
45
In your, opinion, did the FMR improve your income?
YES 100 30 67 20 67 20 77.78 70
NO 0 0 33 10 33 10 22.22 20
100 30 100 30 100 30 100.00 90
46
If yes, how satisfied are you?
Very Satisfied 50 15 50 15 50 15 50.00 45
Satisfied 40 12 50 15 43 13 44.44 40
Somewhat Satisfied 7 2 0 0 7 2 4.44 4 Not Satisfied 3 1 0 0 0 0 1.11 1
100 30 100 30 100 30 100.00 90
47 If Not, Why? 0 0 0 0 0 0 0.00 0
PART VI
LEVEL OF COMMUNITY SATISFACTION WITH THE USE OF FMR
48
Are you satisfied with the project?
YES 100 30 100 30 100 30 100.00 90
NO 0 0 0 0 0 0 0.00 0 100 30 100 30 100 30 100.00 90
APPENDIX G: CONSOLIDATED RESULT OF SURVEY
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
LOCATION : Concreting of
Brgy. Roads, Brgy.
Malag-it
Concreting of
Brgy. Roads,
Brgy. San Pedro
Concreting of
Brgy. Roads,
Brgy. Tabuc
GRAND TOTAL Responses Total
Respon-
dents
% to Total
Total
Respon
-dents
% to Total
Total
Respon-
dents
% to Total
Question No.
30 33.33 30 33.33 30 33.33 90 100.00
% Total % Total % Total Total Respondents
49
If yes, how satisfied are you?
Very Satisfied 50 15 30 9 57 17 45.56 41
Satisfied 50 15 57 17 40 12 48.89 44 Somewhat Satisfied 0 0 13 4 3 1 5.56 5
Not Satisfied 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
50
If not, Why?
Not Finished 0 0 0 0 0 0 0.00 0
51
If you will be asked to assess the project, how will you rate it?
Very Satisfied 47 14 23 7 37 11 35.56 32 Satisfied 33 10 57 17 50 15 46.67 42
Somewhat Satisfied 20 6 20 6 13 4 17.78 16
Not Satisfied 0 0 0 0 0 0 0.00 0 If Not, Why? 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
52
What are your recommendations to improve the project?
Finish the Project 30 9 33 10 17 5 26.67 24 More Improvement 20 6 17 5 17 5 17.78 16
More FMR Project 17 5 27 8 33 10 25.56 23
Do the Project Properly 20 6 10 3 20 6 16.67 15 Do Maintenance 7 2 7 2 7 2 6.67 6
Continue the Project 7 2 7 2 7 2 6.67 6
100 30 100 30 100 30 100.00 90
53
Do you know if potential livelihood benefits were derived by your community from the completed FMR project?
Resulted to good access
road/passage in the transit
of goods to market
40
12
30
9
60
18 43.33 39 Resulted to good access
road/passage from the areas
void of livelihood and experiencing poverty
campaign to eliminate
poverty
27
8
13
4
33
10 24.44 22 Resulted to good access
road/passage from areas
affected by calamity
20
6
30
9
7
2 18.89
17 Resulted to good access
road/passage for
agricultural tourism
3
1
13
4
0
0 5.56
5 Resulted good access
road/passage for economic
progress
7
2
10
3
0
0 5.56
5
No potencial benefit
derived for the barangay
livelihood
3
1
3
1
0
0 2.22
2 100 30 100 30 100 30 100.00 90
54
Did you income increase with the completion of FMR?
YES 72 21 42 21 62 23 72.22 65
NO 24 7 58 9 38 7 25.56 23 DN 4 2 0 0 0 0 2.22 2
100 30 100 30 100 30 100.00 90
APPENDIX G: CONSOLIDATED RESULT OF SURVEY
` Republic of the Philippines
COMMISSION ON AUDIT
Citizen Participatory Audit (CPA) Report No. 2015-01A
Pilot Audit 4: Farm-to-Market Road (FMR) Project in the
Municipality of Pontevedra, Province of Capiz
Prepared by:
DAVE D. ADRICULA RICHARD S. BIONA DENMARK L. LLANERA
CSO (JASAC) CSO (JASAC) CSO (PICPA)
Reviewed by:
MARILOU P. SUMCAD
Team Leader
LOCATION : Concreting of
Brgy. Roads, Brgy.
Malag-it
Concreting of
Brgy. Roads,
Brgy. San Pedro
Concreting of
Brgy. Roads,
Brgy. Tabuc
GRAND TOTAL Responses
Total
Respon-
dents
% to Total
Total
Respon
-dents
% to Total
Total
Respon-
dents
% to Total
Question No.
30 33.33 30 33.33 30 33.33 90 100.00
% Total % Total % Total Total Respondents
56
Can you cite the effects or benefits that you have personnaly derived fron the FMR project?
Resulted to better access
road in going to work everyday
48
14
30
15
35
13 46.67 42
Accelerated and bought
comfort/convenience in our daily livelihood
55
16
28
14
41
15 50.00 45
No benefit derived in our
daily livelihood
0
0
2
1
5
2 3.33 3
100 30 100 30 100 30 100.00 90
57
Are you satisfied with the FMR project?
YES 100 30 97 29 83 25 93.33 84
NO 0 0 3 1 17 5 6.67 6 DN 0 0 0 0 0 0 0.00 0
No Answer 0 0 0 0 0 0 0.00 0
100 30 100 30 100 30 100.00 90
58
If you will assess the benefits of the FMR project to your community, how will you rate it?
Excellent 40 12 27 8 40 12 35.56 32
Good 53 16 53 16 53 16 53.33 48
Slightly Satisfied 7 2 17 5 7 2 10.00 9 No Effect 0 0 3 1 0 0 1.11 1
100 30 100 30 100 30 100.00 90
59
What are your recommendationsto improve consruction of future FMR projects?
More FMR 40 12 50 15 33 10 41.11 37 Concrete All Roads 27 8 20 6 17 5 21.11 19
Do the Project Correctly 17 5 10 3 27 8 17.78 16
Get A Good Engineer 17 5 7 2 20 6 14.44 13 Continue the Project 0 0 13 4 3 1 5.56 5
100 30 100 30 100 30 100.00 90
60
Do you know that you can report complaints on poor and inferior FMR projects by submitting photographs to
www.ikwenta.com?
Yes 33 10 33 10 30 9 32.22 29
No 67 20 67 20 70 21 67.78 61
100 30 100 30 100 30 100.00 90
APPENDIX G: CONSOLIDATED RESULT OF SURVEY