a. hervé - 17 oct. 2007 clic-workshop-0710-43531 clic workshop: 17 oct. 07 interaction region...

42
A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710- 4353 1 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

Upload: alaina-goodman

Post on 17-Jan-2016

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 1

CLIC Workshop: 17 Oct. 07

Interaction Region

Engineering at ILC

Push-Pull Option

A. Hervé/CERN

Page 2: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 2

Contents

• Hypotheses for ILC Workshop in September– Deep site, push-pull, surface assembly…

• Various dispositions of Experimental Area– Two Large Shafts directly over UX– Two Large Shafts offset wrt. UX

• Possible Underground-Hall Parameters• Conclusions for ILC (and CLIC…)

Page 3: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 3

Hypotheses for ILC workshop in September

• Difficult to equip ILC with two independent IRs, but need two indpendent experiments

• Choice of Push-Pull scheme to exchange experiments frequently, say every month or so

• Exchange must be done quickly, say in small week.

Page 4: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 4

Hypotheses for ILC workshop in September

• These goals are ambitious. It was concluded that they can be met, but this cannot be for free.

• Part of the saving from doing away with a second IR will have to be invested to provide a well-engineered, efficient and safe push-pull system.

Page 5: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 5

Hypotheses for ILC workshop in September

• Chosen site is a ‘Deep Site’, say 100 m deep or so.• ‘Surface Assembly’ scheme followed by

‘Heavy-Lifting’ à la CMS is used.• The ‘Larger Detector’ will drive the requirements

(GLDc is used as example here).• If the other one is a ‘Smaller Detector’, it will

benefit from improved facilitities.

Page 6: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 6

Moving platform is a safe solution…

• To move quickly and safely a 12’000-ton (or so) large composite object is not easy and a dedicated platform would do the trick.

• It provides a well-defined interface from which all parties can design with different time scales (Civil Engineering needs to go in construction earlier than experiments).

• The platform would allow the detector to be commissioned in the garage position and moved in a nearly working state towards IP.

.

Page 7: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 7

.. And a clear interface for organization

• Collaboration could be responsible for opening, maintening, closing, and operating its experiment above the platform

• ILC machine could be responsible for moving the platform carrying a detector to the beam position, and from it to the garage positions.

• Mainly beam line protruding inside the detector would need to be re-connected (and re-aligned), in a common effort.

Page 8: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 8

A concrete platform will be stiff enough….

Example:A 2’500-ton load on the CMS cover : 20 m between supports and only 3 mm sag…

Page 9: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 9

ILC Sliding Platform Design Concept

Concept developed by J. Amann, A. Hervé and H. Gerwig

Platform details:

• 20x15x2m• 5m wide trenches for cable chain and roller access. • Steel reinforced concrete

Page 10: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 10

ILC Sliding Platform Design Concept

Uses 1.5kT roller module with1kT hydraulic jacks. Designmust be optimized to distributeload evenly over roller module.

Feet support platform when stationary.Could provide isolation from vibration

Space for access to rollers/jacks.

Page 11: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 11

SX520m shaftto expt cavern

12m shaft to service cavern

Oct 2000

Pressure from Civil Engineering Schedule will be as important for ILC than for CMS, (maybe also for CLIC… )

Choice of Full Surface Assembly for schedule reasons

Page 12: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

Elements are fully cabled to local racks.All services, gas and water cooling pipes are there.Subdetectors are fully commissioned.Once below they can be connected to the umbilical cables going to the counting rooms through the cable chains.

Another advantage of Surface Assembly ‘à la CMS’ is that Elements fully are fully commissioned

before being lowered

Page 13: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 13

IRENG07 Workshop: 17 Sept. 07

Experimental Area

Two Large Shafts

RDR Design

Page 14: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

Side pressurized Egress tunnels

connected to stairs/liftsCommon to all designs

Started design with twolarge shafts directly above UX-Hall

Strong interference in Logistics and Safetybetween Shafts and Detector Areas

This design has been put asidelooking for better solutions

Safety and logistics problems duringALL handling operationsDifficult to position lifts

and stairs

Page 15: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 15

IRENG07 Workshop: 17 Sept. 07

Experimental Area

Two Large Offset Shafts

Page 16: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 16

Shafts are moved outside the main cavern

• The two shafts are positioned outside the footprint of the main underground hall to do away with interferences (in safety logistic and schedule) between loading/unloading areas and working areas.

• This solution has been used for 3 of the 4 LEP experiments, Aleph, Delphi, Opal.

• It needs horizontal transfer of loads but this is well adapted to the full surface assembly scheme when the number and weight of elements to transfer in UX is limited.

Page 17: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 17

Two shaftswith lift/stairs

services80-t crane access

from surface

9m shaftfor machine

service

Two Large Shafts outside the Footprint

Page 18: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 18

Stairs & Lift +services

Stairs & Lift+ services

Potential risk of structuralweakness

on this side

Page 19: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 19

IRENG07 Workshop: 17 Sept. 07

Experimental Area

Two Large Shafts Offset Diagonally wrt IP

Page 20: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

Two Large Shafts in Diagonal to reduce structural weakness on the side of the two shafts

Page 21: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 21

Page 22: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 22

For the Experiments in the Underground Hall there is no difference

Page 23: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 23

Platform

Page 24: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

Elements could be lowered at an angle and rotated in the Transfer Tunnel

Page 25: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 25

For two experiments, it is too crowded with only one SX hallBecause during Phase I, shaft areas have to be reserved for CE

Civil Engineeringturf during phase I

Civil Engineeringturf during phase I

Page 26: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 26

One solution is to separate the two Surface HallsIf needed gantry can be shared

Page 27: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 27

However, the simplest solution for logistics is to have two parallel halls The gantry can still be shared if needed

Page 28: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 28

This is a view of phase I, when civil engineering uses the shafts

Page 29: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 29

And a view of phase II

Page 30: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 30

And a view of phase II during Heavy Lifting operations

Page 31: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 31

IRENG07 Workshop: 17 Sept. 07

Experimental Area

Underground Hall Parametersfor Two Large Shaft Solution

Page 32: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

Possible Hall Parameters - Length around 90 m

Space reserved for shielding wall

8 m working corridor, could be from 0 to 100% on any one side of experimentin 2-m increments, using ‘working platforms’ to fill the gaps

Space for ancillaries recovered from curved end-wall

Maximum stroke 28m

Page 33: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 33

Transfertunnel

31 m

5.6m9m

Possible Hall Parameter - WidthTransfer Tunnel allows easy extraction of ‘Tracking Device’

Page 34: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

1

31 m

11 m 9 m

Possible Hall Parameter - WidthDepends of Crane Reach and Pacman Region

2

28 mGLDc

Two 40-tcranes with asymmetric

crabs

This bottomspaceis ‘free’

becauseof the invert

Top used byventilation

ducts

Page 35: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

The interface between the experiment, the last part of the machine and the movable shielding (pacman) is a complex region that needs an integrated effort

Example of GLDc at ILC

Page 36: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

Example of GLDc at ILC, Opening Scenarios govern the choice of hall parameters

Page 37: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 37

IRENG07 Workshop: 17 Sept. 07

Conclusions

Page 38: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 38

Conclusions-I

Various experimental area dispositions have been looked at for ILC, assuming that:

- A deep site is used- Assembly on the surface and heavy lifting ‘à la

CMS’ are used- At least one large detector is installed on a

platform and push-pull scheme is used

Page 39: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 39

Conclusions-II

- The platform can move on heavy-duty rollers as it has to go in one direction only

- The preferred solution for moving the detector elements is to use air-pads as complex paths are likely to be required

- These air pads can be used in the ‘sublifting’ mode for maintenance operations guaranteeing no relative vertical movements (H. Gerwig)

Page 40: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 40

Conclusions-III

• If surfaced assembly is used, two large shafts positioned directly above the underground hall are not the preferred solution

- If two large shafts are used it seems better to position them diagonally wrt IP, outside the footprint of the underground hall

- Stairs, lift and services can be installed in these large offset shafts

Page 41: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 41

Conclusions-IV

• The length of the underground hall could be around 90 m for the two-large-offset-shaft solution

- The width depends of the way the pacman region is designed and which crane coverage is acceptable

- These parameters, like the best disposition of the experimental area, are ‘detector dependent’.

Page 42: A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-43531 CLIC Workshop: 17 Oct. 07 Interaction Region Engineering at ILC Push-Pull Option A. Hervé/CERN

 A. Hervé - 17 Oct. 2007 CLIC-Workshop-0710-4353 42

Conclusions-V

• Most of this reasoning is certainly applicable to CLIC IR, however there will be differences, for example the amount of services and the radiation environment outside the detectors.

• It would be useful to form early enough a study group, working closely with a proto-collaboration and a typical CLIC detector, to orient correctly the civil engineering studies for the CLIC IR and experimental hall(s), (and also other studies for CLIC detectors…)